Asphalt concrete production stirring mechanism and stirring method

By designing an asphalt concrete production mixing mechanism including heating barrels and rotating mechanisms, the problem of uneven components and uneven temperature in the traditional mixing method of traditional stirring method is solved. Essence

CN119352358APending Publication Date: 2025-01-24SHANGHAI SHISHEN IND & TRADE CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411655530.X
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-11-19
Publication Date
2025-01-24

AI Technical Summary

Technical Problem

Traditional asphalt concrete production and mixing methods are difficult to achieve full mixing of asphalt, stone and ore powder, resulting in inconsistent component ratios, affecting product quality and performance. In addition, the asphalt temperature during the mixing process is uneven, which can easily lead to equipment wear and low production efficiency.

Method used

An asphalt concrete production mixing mechanism including a heating barrel and a rotating mechanism is designed. The first motor drives the first spiral body to rotate, driving the fan blades to blow hot air to the asphalt and mineral aggregates, and the second motor drives the third spiral body to rotate. , transport asphalt and mineral aggregate into the heating barrel to prevent clogging and uneven temperature.

Benefits of technology

The uniform mixing of asphalt and stone and mineral powder ensures product quality and performance, reduce the mixing time and energy consumption, improve production efficiency, and extend the service life of the equipment.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119352358A_ABST
    Figure CN119352358A_ABST
Patent Text Reader

Abstract

The invention provides an asphalt concrete production stirring mechanism and a stirring method, and relates to the technical field of asphalt concrete mixture production. Stirring blades are fixedly mounted on the side wall of a first spiral body, a second spiral body is fixedly mounted at the bottom of the first spiral body, a discharging pipe is fixedly mounted at the bottom of the discharging pipe, and the second spiral body is arranged in the discharging pipe; when discharging is needed, a first motor is controlled to rotate anticlockwise, the first motor drives the first spiral body to rotate anticlockwise, and the first spiral body drives the second spiral body to rotate anticlockwise. When the first spiral body rotates anticlockwise, mixed asphalt concrete in the heating barrel is turned over from top to bottom, the asphalt concrete is stirred while being conveyed out of the heating barrel in an accelerated mode, and the second spiral body rotates anticlockwise so that the asphalt concrete can be conveyed out of the heating barrel in an accelerated mode.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention belongs to the technical field of asphalt concrete mixture production, and more specifically, particularly relates to an asphalt concrete production stirring mechanism and stirring method. Background Art

[0002] Asphalt concrete mixture is known for its good performance. When used as road paving, it can reduce the noise generated when cars are driving and ensure better grip when vehicles are driving on such roads. However, its production is relatively complicated and the asphalt and other mixtures used in it need to be heated.

[0003] 1. The traditional asphalt concrete production mixing method is to simply put the asphalt into the mixing barrel and stir it. This mixing method makes it difficult to fully mix the asphalt with stones, mineral powder, etc., resulting in inconsistent proportions of the components, affecting the quality and performance of the asphalt concrete, and may reduce the strength and durability of the asphalt concrete. Simple mixing may not ensure uniform temperature of the asphalt during the mixing process, and it is easy for local temperatures to be too high or too low, affecting the performance of the asphalt and the combination effect with other materials, and failing to achieve the ideal mixing effect. It may take a longer mixing time, reducing production efficiency.

[0004] 2. When the added asphalt concrete and other materials enter from a pipeline, there may be uneven feeding, which makes it difficult to achieve uniform distribution and affects the subsequent mixing effect and quality. It is easy to get clogged. If the asphalt concrete or other materials are sticky or have large particles, it will cause pipeline blockage and affect production continuity. The local impact force is large, which will cause a large impact on the local area of ​​the mixing device, causing equipment wear or even damage. It is difficult to accurately control the feed amount, which is not conducive to the precise control of the feed amount of different asphalt concretes, resulting in inaccurate proportions and affecting product performance. The mixing difficulty is increased. The uneven feeding method increases the difficulty of achieving uniform mixing of asphalt concrete during the mixing process, requiring longer mixing time and higher energy consumption.

[0005] 3. The traditional way of discharging is to remove the sleeve on the outside of the discharge pipe to allow the asphalt concrete to flow out from the inside of the discharge pipe. However, if it is not taken out in time, some of the asphalt concrete will spill out and cause waste. Moreover, when there is too much asphalt concrete inside, due to the gravity of the asphalt concrete, the asphalt concrete will be tightly pressed on the sleeve, causing the sleeve to be under greater pressure and making it difficult to remove the sleeve.

[0006] In view of this, the existing structure and defects are studied and improved, and an asphalt concrete production mixing mechanism and mixing method are provided. Summary of the invention

[0007] In order to solve the above technical problems, the present invention provides an asphalt concrete production mixing mechanism and a mixing method to solve the above problems.

[0008] An asphalt concrete production mixing mechanism includes a heating barrel, a rotating mechanism is arranged inside the heating barrel, the rotating mechanism includes a first motor, a first spiral, a fan blade, a stirring blade, a second spiral and a discharge pipe, the first motor is fixedly mounted on the top of the heating barrel, the first spiral is fixedly mounted on the output end of the first motor, the fan blade is fixedly mounted on the side wall of the first spiral, the stirring blade is fixedly mounted on the side wall of the first spiral, the second spiral is fixedly mounted on the bottom of the first spiral, the discharge pipe is fixedly mounted on the bottom of the discharge pipe, and the second spiral is arranged inside the discharge pipe.

[0009] Preferably, a second motor is fixedly mounted on the side wall of the heating barrel, a third spiral is fixedly mounted on the output end of the second motor, a first feed pipe is rotatably mounted on the side wall of the third spiral, and the first feed pipe is fixedly mounted on the side wall of the heating barrel.

[0010] Preferably, the side wall of the third spiral is transmission-installed with a first synchronous belt transmission assembly, the interior of the first synchronous belt transmission assembly is transmission-installed with a fourth spiral, and the side wall of the fourth spiral is rotationally installed with a second feed pipe.

[0011] Preferably, the second feed pipe is fixedly mounted on the side wall of the heating barrel, and the third spiral and the fourth spiral are rotatably mounted inside the heating barrel.

[0012] Preferably, a base is fixedly mounted on the side wall of the heating barrel, and a first sliding plate is slidably mounted inside the base.

[0013] Preferably, a first rack is fixedly mounted on the top of the first sliding plate, and a spring rod is fixedly mounted on the side wall of the first rack.

[0014] Preferably, a clamping block is fixedly mounted on one end of the spring rod away from the first rack, and a gear is meshed on the top of the first rack.

[0015] Preferably, a connecting rod is fixedly mounted on one end of the gear close to the heating barrel, and the connecting rod is rotatably mounted inside the heating barrel.

[0016] Preferably, the connecting rod side wall is driven and installed with a second synchronous belt drive assembly, the top of the gear is meshed with a second rack plate, the second rack plate is slidably installed inside the heating barrel, and the second rack plate is slidably installed on the discharge pipe.

[0017] A method for using an asphalt concrete production mixing mechanism comprises the following steps:

[0018] S1, start the second motor, the second motor drives the third spiral to rotate clockwise, put the asphalt into the first feed pipe, the third spiral rotates clockwise to transfer the asphalt from the second motor direction to the heating barrel, when the third spiral transfers the asphalt to the end of the first feed pipe, the asphalt will fall into the heating barrel, at this time the third spiral drives the first synchronous belt transmission assembly to drive clockwise, the first synchronous belt transmission assembly drives the fourth spiral to drive counterclockwise, put the mineral aggregate into the second feed pipe, the fourth spiral rotates clockwise to bring the mineral aggregate into the heating barrel, to prevent the asphalt and the mineral aggregate from clogging the feed pipe;

[0019] S2, start the first motor, the first motor drives the first spiral to rotate clockwise, the first spiral drives the fan blades to rotate clockwise, the fan blades blow the hot air generated by the heating barrel to the asphalt and mineral aggregates, and the fan blades will scrape the top of the heating barrel to clean the top of the heating barrel, and the first spiral drives the second spiral to rotate clockwise, the second spiral will re-transmit the asphalt and mineral aggregates that flow into the discharge pipe back to the heating barrel to prevent the asphalt and mineral aggregates from leaking out of the heating barrel. When discharging is required, control the first motor to rotate counterclockwise, the first motor drives the first spiral to rotate counterclockwise, the first spiral drives the second spiral to rotate counterclockwise, when the first spiral rotates counterclockwise, the mixed asphalt concrete in the heating barrel is swollen from top to bottom, speeding up the asphalt concrete from the heating barrel and stirring the asphalt concrete, so that the asphalt concrete is mixed more evenly, and the counterclockwise rotation of the second spiral will also speed up the asphalt concrete from the heating barrel.

[0020] S3, the first spiral body continues to rotate, the side wall of the first spiral body will be wrapped by asphalt and mineral aggregate, the first spiral body will drive the asphalt and mineral aggregate to be transported from bottom to top, the asphalt and mineral aggregate will surge from bottom to top inside the heating barrel, at this time the third spiral body and the fourth spiral body continue to rotate clockwise, the third spiral body and the fourth spiral body are also wrapped by asphalt and mineral aggregate, the third spiral body and the fourth spiral body transport the asphalt and mineral aggregate inside the heating barrel from the direction of the second motor to the direction of the heating barrel, at this time the asphalt and mineral aggregate will surge horizontally;

[0021] S4, push the clamping block from the middle to the left and right sides, then the spring rod will be forced to shrink, then put the collection bucket on the top of the first sliding plate, and when the collection bucket is placed approximately at the center of the first sliding plate, release the clamping block, then the spring rod will stretch, and the spring rod will drive the clamping block to move from both sides to the middle, clamping the collection bucket, and the clamping block will also correct the position of the collection bucket so that the collection bucket is at the center of the first sliding plate;

[0022] S5, at this time, the first sliding plate is pushed toward the base, and the first sliding plate drives the first rack, spring rod, clamping block and collecting bucket to move from front to back, and the first rack is meshed with the gear, and the first rack will drive the gear to rotate counterclockwise, and the gear will drive the connecting rod to rotate counterclockwise, and the connecting rod will drive the second synchronous belt drive assembly to transmit counterclockwise, and the gear will drive the second rack plate to move from front to back, and the second rack plate will be separated from the bottom of the discharge pipe, and the asphalt concrete inside the discharge pipe will fall into the collecting bucket.

[0023] Compared with the prior art, the present invention has the following beneficial effects:

[0024] In the present invention, a first spiral is provided, and a first motor drives the first spiral to rotate clockwise, and the first spiral drives the fan blades to rotate clockwise, and the fan blades blow the hot air generated by the heating barrel to the asphalt and mineral aggregates, and the fan blades will scrape the top of the heating barrel to clean the top of the heating barrel, and the first spiral drives the second spiral to rotate clockwise, and the second spiral will re-transmit the asphalt and mineral aggregates that flow into the discharge pipe back to the heating barrel to prevent the asphalt and mineral aggregates from leaking out of the heating barrel. When discharging is required, the first motor is controlled to rotate counterclockwise, and the first motor drives the first spiral to rotate counterclockwise, and the first spiral drives the second spiral to rotate counterclockwise. When the first spiral rotates counterclockwise, the mixed asphalt concrete in the heating barrel is caused to surge from top to bottom, and the asphalt concrete is transported out of the heating barrel at the same time, so that the asphalt concrete is mixed more evenly, and the counterclockwise rotation of the second spiral will also accelerate the transport of the asphalt concrete out of the heating barrel.

[0025] In the present invention, a second motor is provided, and the second motor drives the third spiral body to rotate clockwise to place asphalt into the first feed pipe. The third spiral body rotates clockwise to transfer the asphalt from the direction of the second motor to the direction of the heating barrel. When the third spiral body transports the asphalt to the end of the first feed pipe, the asphalt will fall into the heating barrel. At this time, the third spiral body drives the first synchronous belt transmission assembly to drive clockwise, and the first synchronous belt transmission assembly drives the fourth spiral body to drive counterclockwise to place the mineral aggregate into the second feed pipe. The fourth spiral body rotates clockwise to bring the mineral aggregate into the heating barrel to prevent the asphalt and the mineral aggregate from clogging the feed pipe.

[0026] In the present invention, by providing a third spiral, the first spiral continuously rotates, the side wall of the first spiral will be wrapped by asphalt and mineral aggregate, the first spiral will drive the asphalt and mineral aggregate to be transported from bottom to top, the asphalt and mineral aggregate will surge from bottom to top inside the heating barrel, at this time the third spiral and the fourth spiral continue to rotate clockwise, the third spiral and the fourth spiral are also wrapped by asphalt and mineral aggregate, the third spiral and the fourth spiral transport the asphalt and mineral aggregate inside the heating barrel from the direction of the second motor to the direction of the heating barrel, at this time the asphalt and mineral aggregate will surge horizontally, due to the transmission of the third spiral and the fourth spiral, the asphalt and mineral aggregate will not flow back from the first feed pipe and the second feed pipe, the vertical and horizontal surges will make the asphalt and mineral aggregate mixed more evenly, reduce the mixing time, and improve the production efficiency.

[0027] In the present invention, a clamping block is provided and pushed from the middle to the left and right sides. At this time, the spring rod will be forced to shrink. At this time, the collection bucket is placed above the first sliding plate. When the collection bucket is placed approximately at the center of the first sliding plate, the clamping block is released. At this time, the spring rod will extend and the spring rod drives the clamping block to move from both sides to the middle, clamping the collection bucket with the clamping block. The clamping block will also correct the position of the collection bucket so that the collection bucket is at the center of the first sliding plate.

[0028] In the present invention, a first sliding plate is provided, and the first sliding plate is pushed toward the base. The first sliding plate drives the first rack, the spring rod, the clamping block and the collecting bucket to move from front to back. The first rack is meshed with the gear. The first rack will drive the gear to rotate counterclockwise. The gear drives the connecting rod to rotate counterclockwise. The connecting rod drives the second synchronous belt drive assembly to rotate counterclockwise. The gear drives the second rack plate to move from front to back. The second rack plate will detach from the bottom of the discharge pipe. At this time, the asphalt concrete inside the discharge pipe falls into the collecting bucket. BRIEF DESCRIPTION OF THE DRAWINGS

[0029] Figure 1 It is a schematic diagram of the overall structure of the present invention;

[0030] Figure 2 It is a structural schematic diagram of the base of the present invention;

[0031] Figure 3 is a schematic structural diagram of a first synchronous belt transmission assembly of the present invention;

[0032] Figure 4 is a schematic structural diagram of the second feeding pipe of the present invention;

[0033] Figure 5 is a schematic structural diagram of the first helicoid of the present invention;

[0034] Figure 6 is a schematic diagram of the structure of the third helix of the present invention;

[0035] Figure 7 It is a structural schematic diagram of the spring rod of the present invention;

[0036] Figure 8 is a schematic structural diagram of a second synchronous belt transmission assembly of the present invention;

[0037] Fig. 9 is a schematic structural diagram of the first rack of the present invention;

[0038] Fig.10 It is a structural schematic diagram of the clamping block of the present invention;

[0039] Fig.11 It is a structural schematic diagram of the second rack plate of the present invention.

[0040] In the figure, the correspondence between the component names and the figure numbers is: 11, heating barrel; 12, first motor; 13, first spiral; 14, fan blade; 15, stirring blade; 16, second spiral; 17, discharge pipe; 18, second motor; 19, third spiral; 21, first feed pipe; 22, first synchronous belt drive assembly; 23, fourth spiral; 24, second feed pipe; 25, base; 26, first sliding plate; 27, first rack; 28, spring rod; 29, clamping block; 31, gear; 32, connecting rod; 33, second synchronous belt drive assembly; 34, second rack plate. DETAILED DESCRIPTION

[0041] The following embodiments of the present invention are described in further detail in conjunction with the accompanying drawings and examples. The following examples are used to illustrate the present invention, but are not intended to limit the scope of the present invention.

[0042] See also Figure 1-Figure 11The present invention provides an asphalt concrete production stirring mechanism, including a heating barrel 11, a rotating mechanism is arranged inside the heating barrel 11, the rotating mechanism includes a first motor 12, a first spiral 13, a fan blade 14, a stirring blade 15, a second spiral 16 and a discharge pipe 17, the first motor 12 is fixedly mounted on the top of the heating barrel 11, the first spiral 13 is fixedly mounted on the output end of the first motor 12, the fan blade 14 is fixedly mounted on the side wall of the first spiral 13, the stirring blade 15 is fixedly mounted on the side wall of the first spiral 13, the second spiral 16 is fixedly mounted on the bottom of the first spiral 13, the discharge pipe 17 is fixedly mounted on the bottom of the discharge pipe 17, the second spiral 16 is arranged inside the discharge pipe 17, the first motor 12 drives the first spiral 13 to rotate clockwise, the first spiral 13 drives the fan blade 14 to rotate clockwise, the fan blade 14 blows the hot air generated by the heating barrel 11 to the asphalt and mineral aggregate, and The fan blades 14 will scrape the top of the heating barrel 11 to clean the top of the heating barrel 11, and the first spiral 13 drives the second spiral 16 to rotate clockwise, and the second spiral 16 will re-transmit the asphalt and mineral aggregate flowing into the discharge pipe 17 back to the heating barrel 11 to prevent the asphalt and mineral aggregate from leaking out of the heating barrel 11. When discharging is required, the first motor 12 is controlled to rotate counterclockwise, and the first motor 12 drives the first spiral 13 to rotate counterclockwise, and the first spiral 13 drives the second spiral 16 to rotate counterclockwise. When the first spiral 13 rotates counterclockwise, the mixed asphalt concrete in the heating barrel 11 is caused to surge from top to bottom, accelerating the asphalt concrete from the heating barrel 11. At the same time, the asphalt concrete is stirred to make the asphalt concrete mixed more evenly, and the counterclockwise rotation of the second spiral 16 will also accelerate the asphalt concrete from the heating barrel 11.

[0043] A second motor 18 is fixedly installed on the side wall of the heating barrel 11, and a third spiral 19 is fixedly installed on the output end of the second motor 18. A first feed pipe 21 is rotatably installed on the side wall of the third spiral 19. The first feed pipe 21 is fixedly installed on the side wall of the heating barrel 11. A first synchronous belt drive assembly 22 is installed on the side wall of the third spiral 19 for transmission. A fourth spiral 23 is installed for transmission inside the first synchronous belt drive assembly 22. A second feed pipe 24 is rotatably installed on the side wall of the fourth spiral 23. The second motor 18 drives the third spiral 19 to rotate clockwise to put asphalt into the first feed pipe 21. Inside, the third spiral 19 rotates clockwise to transfer the asphalt from the direction of the second motor 18 to the direction of the heating barrel 11. When the third spiral 19 transports the asphalt to the end of the first feed pipe 21, the asphalt will fall into the heating barrel 11. At this time, the third spiral 19 drives the first synchronous belt transmission assembly 22 to drive clockwise, and the first synchronous belt transmission assembly 22 drives the fourth spiral 23 to drive counterclockwise to place the mineral aggregate into the second feed pipe 24. The fourth spiral 23 rotates clockwise to bring the mineral aggregate into the heating barrel 11 to prevent the asphalt and the mineral aggregate from clogging the feed pipe.

[0044] The second feed pipe 24 is fixedly mounted on the side wall of the heating barrel 11, the third spiral 19 and the fourth spiral 23 are rotatably mounted inside the heating barrel 11, the first spiral 13 rotates continuously, the side wall of the first spiral 13 will be wrapped by asphalt and mineral aggregates, the first spiral 13 will drive the asphalt and mineral aggregates to be transported from bottom to top, the asphalt and mineral aggregates will surge from bottom to top inside the heating barrel 11, at this time the third spiral 19 and the fourth spiral 23 rotate continuously clockwise, the third spiral 19 and the fourth spiral 23 are also wrapped by asphalt and The mineral aggregate is wrapped, and the third spiral 19 and the fourth spiral 23 transport the asphalt and the mineral aggregate inside the heating barrel 11 from the direction of the second motor 18 to the heating barrel 11. At this time, the asphalt and the mineral aggregate will surge in the horizontal direction. Due to the transmission of the third spiral 19 and the fourth spiral 23, the asphalt and the mineral aggregate will not flow back out from the first feed pipe 21 and the second feed pipe 24. The vertical and horizontal surges will make the asphalt and the mineral aggregate mix more evenly, reduce the mixing time, and improve the production efficiency.

[0045] A base 25 is fixedly installed on the side wall of the heating barrel 11, and a first sliding plate 26 is slidably installed inside the base 25. A first rack 27 is fixedly installed on the top of the first sliding plate 26, and a spring rod 28 is fixedly installed on the side wall of the first rack 27. A clamping block 29 is fixedly installed on the end of the spring rod 28 away from the first rack 27. A gear 31 is meshed on the top of the first rack 27, and the clamping block 29 is pushed from the middle to the left and right sides. At this time, the spring rod 28 will be forced to shrink. At this time, the collected barrel is placed above the first sliding plate 26. When the collection barrel is placed approximately at the center of the first sliding plate 26, the clamping block 29 is released. At this time, the spring rod 28 will extend, and the spring rod 28 drives the clamping block 29 to move from both sides to the middle, clamping the collection barrel by the clamping block 29, and the clamping block 29 will also correct the position of the collection barrel so that the collection barrel is at the center of the first sliding plate 26.

[0046] A connecting rod 32 is fixedly installed at one end of the gear 31 close to the heating barrel 11, and the connecting rod 32 is rotatably installed inside the heating barrel 11. A second synchronous belt transmission assembly 33 is installed on the side wall of the connecting rod 32, and a second rack plate 34 is meshed with the top of the gear 31, and the second rack plate 34 is slidably installed inside the heating barrel 11. The second rack plate 34 is slidably installed in the discharge pipe 17, and then the first sliding plate 26 is pushed toward the base 25, and the first sliding plate 26 drives the first rack 27, the spring rod 28, the clamping block 29 and the collection barrel to move from front to back. The first rack 27 is meshed with the gear 31, and the first rack 27 will drive the gear 31 to rotate counterclockwise, and the gear 31 drives the connecting rod 32 to rotate counterclockwise, and the connecting rod 32 drives the second synchronous belt transmission assembly 33 to drive counterclockwise, and the gear 31 drives the second rack plate 34 to move from front to back, and the second rack plate 34 will be separated from the bottom of the discharge pipe 17, and the asphalt concrete inside the discharge pipe 17 falls into the collection barrel.

[0047] Working principle:

[0048] The first step is to start the second motor 18. The second motor 18 drives the third spiral 19 to rotate clockwise to put the asphalt into the first feed pipe 21. The third spiral 19 rotates clockwise to transfer the asphalt from the direction of the second motor 18 to the direction of the heating barrel 11. When the third spiral 19 transports the asphalt to the end of the first feed pipe 21, the asphalt will fall into the heating barrel 11. At this time, the third spiral 19 drives the first synchronous belt drive assembly 22 to drive clockwise, and the first synchronous belt drive assembly 22 drives the fourth spiral 23 to drive counterclockwise to put the mineral aggregate into the second feed pipe 24. The fourth spiral 23 rotates clockwise to bring the mineral aggregate into the heating barrel 11 to prevent the asphalt and the mineral aggregate from clogging the feed pipe.

[0049] The second step is to start the first motor 12, which drives the first spiral 13 to rotate clockwise, and the first spiral 13 drives the fan blade 14 to rotate clockwise. The fan blade 14 blows the hot air generated by the heating barrel 11 to the asphalt and mineral aggregate, and the fan blade 14 scrapes the top of the heating barrel 11 to clean the top of the heating barrel 11, and the first spiral 13 drives the second spiral 16 to rotate clockwise, and the second spiral 16 re-transmits the asphalt and mineral aggregate flowing into the discharge pipe 17 back to the heating barrel 11 to prevent the asphalt and mineral aggregate from flowing out of the heating barrel. 11, when discharging is required, the first motor 12 is controlled to rotate counterclockwise, the first motor 12 drives the first screw 13 to rotate counterclockwise, the first screw 13 drives the second screw 16 to rotate counterclockwise, when the first screw 13 rotates counterclockwise, the mixed asphalt concrete inside the heating barrel 11 is made to surge from top to bottom, speeding up the asphalt concrete from the heating barrel 11 to be transported out, and at the same time, the asphalt concrete is stirred to make the asphalt concrete mixed more evenly, and the counterclockwise rotation of the second screw 16 will also speed up the asphalt concrete from being transported out of the heating barrel 11.

[0050] In the third step, the first spiral 13 rotates continuously, and the side wall of the first spiral 13 will be wrapped by asphalt and mineral aggregate. The first spiral 13 will drive the asphalt and mineral aggregate to be transported from bottom to top, and the asphalt and mineral aggregate will surge from bottom to top inside the heating barrel 11. At this time, the third spiral 19 and the fourth spiral 23 rotate continuously clockwise, and the third spiral 19 and the fourth spiral 23 are also wrapped by asphalt and mineral aggregate. The third spiral 19 and the fourth spiral 23 transport the asphalt and mineral aggregate inside the heating barrel 11 from the direction of the second motor 18 to the heating barrel 11. At this time, the asphalt and mineral aggregate will surge in the horizontal direction. Due to the transmission of the third spiral 19 and the fourth spiral 23, the asphalt and mineral aggregate will not flow back from the first feed pipe 21 and the second feed pipe 24. The surge in the vertical and horizontal directions will make the asphalt and mineral aggregate mixed more evenly, reduce the mixing time, and improve the production efficiency.

[0051] The fourth step is to push the clamping block 29 from the middle to the left and right sides. At this time, the spring rod 28 will be forced to shrink. At this time, the collected barrel will be placed on top of the first sliding plate 26. When the collecting barrel is placed approximately at the center of the first sliding plate 26, the clamping block 29 is released. At this time, the spring rod 28 will extend, and the spring rod 28 drives the clamping block 29 to move from both sides to the middle, clamping the collecting barrel with the clamping block 29, and the clamping block 29 will also correct the position of the collecting barrel so that the collecting barrel is at the center of the first sliding plate 26.

[0052] The fifth step, at this time, the first sliding plate 26 is pushed toward the base 25, and the first sliding plate 26 drives the first rack 27, the spring rod 28, the clamping block 29 and the collecting bucket to move from front to back, and the first rack 27 is engaged with the gear 31, and the first rack 27 will drive the gear 31 to rotate counterclockwise, and the gear 31 drives the connecting rod 32 to rotate counterclockwise, and the connecting rod 32 drives the second synchronous belt drive assembly 33 to transmit counterclockwise, and the gear 31 drives the second rack plate 34 to move from front to back, and the second rack plate 34 will be separated from the bottom of the discharge pipe 17. At this time, the asphalt concrete inside the discharge pipe 17 falls into the collecting bucket.

[0053] The embodiments of the present invention are given for the purpose of illustration and description, and are not intended to be exhaustive or to limit the invention to the disclosed forms. Many modifications and variations will be apparent to those of ordinary skill in the art. The embodiments are selected and described in order to better illustrate the principles and practical applications of the present invention and to enable those of ordinary skill in the art to understand the present invention and thereby design various embodiments with various modifications suitable for specific uses.

Claims

1. An asphalt concrete production mixing mechanism, comprising a heating barrel (11), characterized in that: A rotating mechanism is arranged inside the heating barrel (11), and the rotating mechanism comprises a first motor (12), a first spiral (13), a fan blade (14), a stirring blade (15), a second spiral (16) and a discharge pipe (17), wherein the first motor (12) is fixedly mounted on the top of the heating barrel (11), the first spiral (13) is fixedly mounted on the output end of the first motor (12), the fan blade (14) is fixedly mounted on the side wall of the first spiral (13), the stirring blade (15) is fixedly mounted on the side wall of the first spiral (13), the second spiral (16) is fixedly mounted on the bottom of the first spiral (13), and the discharge pipe (17) is fixedly mounted on the bottom of the discharge pipe (17), and the second spiral (16) is arranged inside the discharge pipe (17).

2. An asphalt concrete production mixing mechanism as claimed in claim 1, characterized in that: A second motor (18) is fixedly mounted on the side wall of the heating barrel (11); Wherein, a third spiral (19) is fixedly mounted on the output end of the second motor (18), a first feed pipe (21) is rotatably mounted on the side wall of the third spiral (19), and the first feed pipe (21) is fixedly mounted on the side wall of the heating barrel (11).

3. An asphalt concrete production mixing mechanism as claimed in claim 2, characterized in that: The side wall of the third spiral body (19) is driven by a first synchronous belt drive assembly (22); The first synchronous belt transmission component (22) is internally provided with a fourth spiral body (23) for transmission, and a second feed pipe (24) is rotatably provided on the side wall of the fourth spiral body (23).

4. An asphalt concrete production mixing mechanism as claimed in claim 3, characterized in that: The second feed pipe (24) is fixedly mounted on the side wall of the heating barrel (11); Wherein, the third spiral (19) and the fourth spiral (23) are rotatably installed inside the heating barrel (11).

5. An asphalt concrete production mixing mechanism as claimed in claim 4, characterized in that: A base (25) is fixedly mounted on the side wall of the heating barrel (11); Wherein, a first sliding plate (26) is slidably mounted inside the base (25).

6. An asphalt concrete production mixing mechanism as claimed in claim 5, characterized in that: A first rack (27) is fixedly mounted on the top of the first sliding plate (26); Wherein, a spring rod (28) is fixedly mounted on the side wall of the first rack (27).

7. An asphalt concrete production mixing mechanism as claimed in claim 6, characterized in that: A clamping block (29) is fixedly mounted on one end of the spring rod (28) away from the first rack (27); Wherein, a gear (31) is meshed at the top of the first rack (27).

8. An asphalt concrete production mixing mechanism as claimed in claim 7, characterized in that: A connecting rod (32) is fixedly mounted on one end of the gear (31) close to the heating barrel (11); Wherein, the connecting rod (32) is rotatably installed inside the heating barrel (11).

9. An asphalt concrete production mixing mechanism as claimed in claim 8, characterized in that: The side wall of the connecting rod (32) is provided with a second synchronous belt transmission assembly (33); Wherein, a second rack plate (34) is meshed at the top of the gear (31), the second rack plate (34) is slidably mounted inside the heating barrel (11), and the second rack plate (34) is slidably mounted on the discharge pipe (17).

10. A method for using an asphalt concrete production mixing mechanism, characterized in that: The following steps are involved: S1, start the second motor (18), the second motor (18) drives the third screw (19) to rotate clockwise, and puts the asphalt into the first feed pipe (21). The third screw (19) rotates clockwise to transfer the asphalt from the direction of the second motor (18) to the direction of the heating barrel (11). When the third screw (19) transfers the asphalt to the end of the first feed pipe (21), the asphalt falls into the heating barrel (11). At this time, the third screw (19) drives the first synchronous belt transmission component (22) to drive clockwise, and the first synchronous belt transmission component (22) drives the fourth screw (23) to drive counterclockwise, and the mineral aggregate is placed in the second feed pipe (24). The fourth screw (23) rotates clockwise to bring the mineral aggregate into the heating barrel (11), so as to prevent the asphalt and the mineral aggregate from clogging the feed pipe; S2, start the first motor (12), the first motor (12) drives the first spiral (13) to rotate clockwise, the first spiral (13) drives the fan blade (14) to rotate clockwise, the fan blade (14) blows the hot air generated by the heating barrel (11) toward the asphalt and mineral aggregate, and the fan blade (14) scrapes the top of the heating barrel (11) to clean the top of the heating barrel (11), and the first spiral (13) drives the second spiral (16) to rotate clockwise, the second spiral (16) transfers the asphalt and mineral aggregate flowing into the discharge pipe (17) back to the heating barrel (11) to prevent the asphalt and mineral aggregate from leaking. When the material needs to be discharged, the first motor (12) is controlled to rotate counterclockwise, the first motor (12) drives the first spiral (13) to rotate counterclockwise, the first spiral (13) drives the second spiral (16) to rotate counterclockwise, when the first spiral (13) rotates counterclockwise, the mixed asphalt concrete in the heating barrel (11) is caused to surge from top to bottom, accelerating the asphalt concrete to be transported out of the heating barrel (11) while stirring the asphalt concrete, so that the asphalt concrete is mixed more evenly, and the counterclockwise rotation of the second spiral (16) will also accelerate the asphalt concrete to be transported out of the heating barrel (11); S3, the first spiral (13) continues to rotate, the side wall of the first spiral (13) will be wrapped by asphalt and mineral aggregate, the first spiral (13) will drive the asphalt and mineral aggregate to be transported from bottom to top, the asphalt and mineral aggregate will surge from bottom to top inside the heating barrel (11), at this time, the third spiral (19) and the fourth spiral (23) continue to rotate clockwise, the third spiral (19) and the fourth spiral (23) are also wrapped by asphalt and mineral aggregate, the third spiral (19) and the fourth spiral (23) transport the asphalt and mineral aggregate inside the heating barrel (11) from the direction of the second motor (18) to the direction of the heating barrel (11), at this time the asphalt and mineral aggregate will surge in the horizontal direction; S4, the clamping block (29) is pushed from the middle to the left and right sides, and the spring rod (28) is forced to shrink. The collected bucket is placed above the first sliding plate (26). When the collection bucket is placed approximately at the center of the first sliding plate (26), the clamping block (29) is released. The spring rod (28) is stretched, and the spring rod (28) drives the clamping block (29) to move from both sides to the middle, and the clamping block (29) clamps the collection bucket. The clamping block (29) also corrects the position of the collection bucket so that the collection bucket is at the center of the first sliding plate (26); S5, at this time, the first sliding plate (26) is pushed toward the base (25), and the first sliding plate (26) drives the first rack (27), the spring rod (28), the clamping block (29) and the collecting bucket to move from front to back, and the first rack (27) is meshed with the gear (31), and the first rack (27) drives the gear (31) to rotate counterclockwise, and the gear (31) drives the connecting rod (32) to rotate counterclockwise, and the connecting rod (32) drives the second synchronous belt drive assembly (33) to transmit counterclockwise, and the gear (31) drives the second rack plate (34) to move from front to back, and the second rack plate (34) will be separated from the bottom of the discharge pipe (17), and the asphalt concrete inside the discharge pipe (17) falls into the collecting bucket.