Material and muck transfer system and transfer method for construction pile foundation in mountainous area

By designing a material and slag transfer system including side-by-side tracks and transfer trucks, the problem of difficult material and slag transfer in mountain bridge construction is solved, and efficient transportation of various types of materials is achieved.

CN119389690APending Publication Date: 2025-02-07CHINA RAILWAY 15TH BUREAU GROUP CORPORATION LIMITED +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411638987.X
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-11-18
Publication Date
2025-02-07

AI Technical Summary

Technical Problem

In mountainous bridge construction, due to the large lateral height difference and steep slope of the bridge, traditional manual transfer of materials and slag, the existing transport vehicles cannot effectively transport longer materials such as steel bars.

Method used

Design a material and slag transfer system including side-by-side tracks and transfer trucks. The transfer truck is equipped with installation plates, bearing plates, side baffles and barrier strips. Different types of barriers are installed and driven structures are realized. Transfer of materials.

Benefits of technology

The system simplifies the material transfer process, improves construction efficiency, and can effectively transport various types of materials and slag, especially long steel bars.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119389690A_ABST
    Figure CN119389690A_ABST
Patent Text Reader

Abstract

The invention discloses a material and muck transfer system and method for a construction pile foundation in a mountainous area, and belongs to the technical field of bridge construction. Comprising rails arranged side by side, a plurality of transfer trolleys are arranged on the rails, each transfer trolley comprises a frame, a driving structure is arranged on each frame, each driving structure is used for driving the corresponding frame to move on the corresponding rail, a mounting plate is arranged above each frame, each mounting plate is fixedly connected to the corresponding frame, a bearing plate is arranged above each mounting plate, and each bearing plate is fixedly connected to the corresponding frame. Side baffles are arranged at the two ends, perpendicular to the length direction of the track, of the bearing plate, one ends of the side baffles are fixed to the bearing plate, vertically-distributed limiting grooves are formed in the two edges of the oppositely-arranged surfaces of the two side baffles, and the limiting grooves communicate with the side faces, facing the middle of the bearing plate, of the two side baffles; and screw rods are arranged in the limiting grooves, and one ends of the screw rods are fixed to the bearing plate. The technical scheme is used for improving the material transportation effect during mountainous area bridge construction.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of bridge construction, and in particular relates to a material and slag transfer system and a transfer method for pile foundation construction in mountainous areas. Background Art

[0002] When constructing bridges in mountainous areas, it is difficult to build access roads due to the large lateral height difference of the bridges, steep slopes, and proximity to provincial roads. Traditionally, the materials required for construction (cement, aggregates, and steel bars, etc.) can only be transported manually, but the steepness of the mountains makes manual transfer and transportation very difficult.

[0003] In the prior art, although there are devices such as single-track transport vehicles or double-track transport vehicles that can be used for transporting materials in mountainous areas, in actual use, the structure of the material loading part of the transport vehicle is usually in the form of a fence to block and restrict the movement of the transported materials. Although this method can prevent the falling of materials, it cannot transport longer materials (rebars), which brings inconvenience to the construction of bridges in mountainous areas. Summary of the invention

[0004] In view of this, an object of the present invention is to provide a material and slag transfer system and transfer method for pile foundation construction in mountainous areas, so as to improve the material transportation effect during bridge construction in mountainous areas.

[0005] In order to achieve the above object, the present invention provides the following technical solutions:

[0006] The present invention discloses a material and slag transfer system for constructing pile foundations in mountainous areas, comprising tracks arranged side by side, a plurality of transfer vehicles being arranged on the tracks, the transfer vehicles comprising a frame, the frames being provided with a driving structure, the driving structure being used to drive the frames to move on the tracks, a mounting plate being provided above the frames, the mounting plate being fixedly connected to the frames, a bearing plate being provided above the mounting plate, side baffles being provided at both ends of the bearing plates being arranged perpendicular to the length direction of the tracks, one end of the side baffles being fixed to the bearing plates, two edges of the oppositely arranged surfaces of the two side baffles being provided with vertically distributed limiting grooves, the limiting grooves being connected to a side surface of the two side baffles facing the middle of the bearing plates, and a There is a screw rod, one end of the screw rod is fixed to the supporting plate, and the other end of the screw rod is provided with a locking nut, and a plurality of baffles are provided in the two limit grooves arranged opposite to each other in the two side baffles, and both ends of the baffles are provided with a first through hole penetrating therethrough, and the first through hole is sleeved on the screw rod, and a plurality of the baffles are stacked, and the locking nut presses the plurality of baffles tightly into the limit groove, and a plurality of clamping arc holes matching in position are provided on the contact surfaces of adjacent baffles, and the clamping arc holes are evenly distributed along the length direction of the baffles, a turntable is provided in the middle of the mounting plate, and the middle of the supporting plate is fixed on the turntable, and the mounting plate and the supporting plate are provided with limit holes matching in position, and limit pins are provided in the limit holes.

[0007] Furthermore, one end of the limit pin is arranged to pass through the mounting plate, and the limit pin is detachably connected to the mounting plate.

[0008] Furthermore, a thread is provided on the inner wall of the limiting hole arranged on the mounting plate, and the limiting pin is threadedly connected to the mounting plate.

[0009] Furthermore, the driving structure includes a gasoline engine and a clamping roller, the clamping roller is connected to the mounting plate, and the clamping roller is clamped on the track, and the gasoline engine is used to drive the clamping roller to rotate.

[0010] Furthermore, the cross section of the baffle is square, and a second through hole is provided on the end of the baffle, and the second through hole is vertically connected to the first through hole.

[0011] Furthermore, a rubber anti-slip layer is provided on the inner wall of the clamping arc hole, and the rubber anti-slip layer is bonded inside the clamping arc hole.

[0012] Furthermore, the laying path of the track passes through the slag accumulation area of ​​the pile foundation construction, and a lifting device is provided in the slag accumulation area.

[0013] A method for transferring materials and slag for pile foundation construction in mountainous areas, comprising the following steps:

[0014] S1. Confirm the type of goods being transferred and install the baffles adaptively according to the type of goods being transferred;

[0015] S2. When the transported object is slag, the second through hole of the baffle is sleeved on the screw, and the clamping arc holes provided on the baffle are arranged in an upper and lower distribution, that is, at this time, the contact surfaces of adjacent baffles are sealed;

[0016] S21, then the slag is moved to the space surrounded by the baffle bars and the side baffles by manual labor or lifting equipment, and then the frame is driven by the driving structure to move on the track, thereby transporting and transferring the slag;

[0017] S3. When the transported object is a steel bar, the first through hole of the baffle is sleeved on the screw rod, and the clamping arc holes on adjacent baffles are arranged opposite to each other;

[0018] S31, move the positions of two adjacent transfer vehicles to match the length of the steel bars, and then place the two ends of the steel bars in the clamping arc holes arranged opposite to each other on the two transfer vehicles. After the placement is completed, rotate the locking nut to lock the position of the stop bar;

[0019] S32, then pull out the limit pin, and then drive the frame to move on the track through the driving structure, so as to transport and transfer the steel bars.

[0020] The beneficial effects of the present invention are:

[0021] (1) In this technical solution, tracks are laid on the mountain, and then the materials required for bridge pile foundation construction and the resulting slag are transported by means of transfer vehicles, which provides greater convenience for mountain bridge construction, simplifies the material transfer process, and improves construction efficiency;

[0022] (2) In the present technical solution, the baffle bar, and the first through hole, the second through hole and the clamping arc hole on the baffle bar enable construction workers to transport different types of materials or debris through different assembly methods, which greatly improves the convenience of construction.

[0023] Other advantages, objectives and features of the present invention will be described in the following description and will be apparent to those skilled in the art to some extent, or those skilled in the art may be taught from the practice of the present invention. The objectives and other advantages of the present invention may be realized and obtained through the following description. BRIEF DESCRIPTION OF THE DRAWINGS

[0024] In order to make the purpose, technical solution and beneficial effects of the present invention clearer, the present invention provides the following drawings for illustration:

[0025] Figure 1It is a three-dimensional schematic diagram of the material and slag transfer system of the present invention;

[0026] Figure 2 It is a three-dimensional schematic diagram of the transfer vehicle in the present invention;

[0027] Figure 3 It is a schematic front view of the transfer vehicle in the present invention;

[0028] Figure 4 It is a schematic diagram of an exploded view of the transfer vehicle in the present invention;

[0029] Figure 5 For the present invention Figure 4 A local enlarged schematic diagram of the middle A;

[0030] Figure 6 It is a schematic diagram of the material and slag transfer system of the present invention transporting steel bars.

[0031] The following are marked in the accompanying drawings:

[0032] 1. Track; 2. Frame; 3. Load-bearing plate; 4. Side baffle; 5. Limiting groove; 6. Screw; 7. Locking nut; 8. Limiting hole; 9. Limiting pin; 10. Turntable; 11. Baffle bar; 12. Clamping arc hole; 13. First through hole; 14. Second through hole; 15. Rebar; 16. Mounting plate. DETAILED DESCRIPTION

[0033] like Figure 1 to Figure 6 As shown, the present invention is a material and slag transfer system for pile foundation construction in mountainous areas, including rails 1 arranged side by side, a plurality of transfer vehicles are arranged on the rails 1, and the transfer vehicles include a frame 2, and the frame 2 is provided with a driving structure, and the driving structure is used to drive the frame 2 to move on the rail 1, and a mounting plate 16 is provided above the frame 2, and the mounting plate 16 is fixedly connected to the frame 2, and a bearing plate 3 is provided above the mounting plate 16, and side baffles 4 are provided on both ends of the bearing plate 3 arranged perpendicular to the length direction of the rail 1, and one end of the side baffle 4 is fixed on the bearing plate 3, and the two side baffles 4 are arranged opposite to each other. Vertically distributed limiting grooves 5 are provided on both edges of the surface, and the limiting grooves 5 are connected to one side of the two side baffles 4 facing the middle of the bearing plate 3. Screws 6 are provided in the limiting grooves 5, one end of the screw 6 is fixed to the bearing plate 3, and a locking nut 7 is provided on the other end of the screw 6. A plurality of baffles 11 are provided in the two limiting grooves 5 arranged opposite to each other of the two side baffles 4, and a first through hole 13 is penetrated at both ends of the baffle 11, and the first through hole 13 is sleeved on the screw 6, and a plurality of baffles 11 are stacked, and the locking nut 7 presses the plurality of baffles 11 tightly into the limiting grooves 5.

[0034] The working principle of this technical solution is:

[0035] The track 1 is erected on the mountain from the foot of the mountain to the construction site, and its erection path should pass through several construction sites. Therefore, when transporting small materials or slag, it is only necessary to lift the materials into the space formed by the side baffles 4 and the baffle bars 11, and then drive the transfer vehicle to travel on the track 1 through the driving device, so that the materials or slag can be transported to the designated location. It is not difficult to understand that the advantage of installing several baffle bars 11 on the side panels of the row layer is that the baffle bars 11 can be removed at any time, which is convenient for the transportation of longer materials and for loading and unloading. At the same time, the setting of the screw rod 6 can not only limit the deflection of the baffle bar 11, but also fix the position of the baffle bar 11 by cooperating with the locking nut 7. That is, the technical solution provides greater convenience for the transportation of materials or slag during construction in mountainous areas, simplifies the material transportation process, and improves construction efficiency.

[0036] In one feasible embodiment, a plurality of position-matched clamping arc holes 12 are provided on the contact surfaces of adjacent baffles 11, and the clamping arc holes 12 are evenly distributed along the length direction of the baffles 11. A turntable 10 is provided in the middle of the mounting plate 16, and the middle of the supporting plate 3 is fixed on the turntable 10. Position-matched limit holes 8 are provided on the mounting plate 16 and the supporting plate 3, and limit pins 9 are provided in the limit holes 8.

[0037] The advantage of providing the clamping arc hole 12 is that the end of the steel bar 15 can be clamped in the space formed by the clamping arc hole 12 of the adjacent retaining bar 11, that is, with the effect of the locking nut 7, the clamping arc hole 12 can be squeezed and pressed against the steel bar 15, that is, at this time, only two adjacent transfer vehicles need to be used in coordination to clamp the ends of the steel bar 15, thereby achieving the limit and fixation of the steel bar 15;

[0038] At the same time, it is not difficult to understand that the layout path of the track 1 cannot be completely straight. Therefore, in the curved part of the track 1, since the steel bars 15 are long, in order to prevent the steel bars 15 from falling off due to the inclination or shaking of the track 1 during transportation, the two ends of the steel bars 15 should be firmly fixed on the transfer vehicle. This will cause the transfer vehicle to be turned. Due to the long distance between the two adjacent transfer vehicles, the steel bars 15 will be subjected to a torsional moment, which will cause the movement of the two transfer vehicles to be stuck by the steel bars 15. Therefore, in this technical solution, a turntable 10 (existing technology, which can also be understood as a rotating shaft or bearing) is provided to enable the bearing plates 3 on the front and rear transfer vehicles to rotate relative to the mounting plate 16. Therefore, when the steel bars 15 are subjected to a torsional moment, the two ends of the steel bars 15 will respectively drive the bearing plates 3 to rotate, thereby unloading the torsional moment, and thus will not affect the movement of the two transfer vehicles;

[0039] Furthermore, the setting of the limit hole 8 and the limit pin 9 can control whether the bearing plate 3 rotates, that is, when transporting steel bars 15, the limit pin 9 is cancelled, and when transporting small materials, the limit pin 9 is inserted to ensure the stability of small materials during transportation.

[0040] In one feasible manner, one end of the limit pin 9 is arranged to pass through the mounting plate 16, and the limit pin 9 is detachably connected to the mounting plate 16. A thread is provided on the inner wall of the limit hole 8 arranged on the mounting plate 16, and the limit pin 9 is threadedly connected to the mounting plate 16. This arrangement makes it easy for construction personnel to operate the position of the limit pin 9.

[0041] In one practicable manner, the driving structure includes a gasoline engine and a clamping roller, the clamping roller is connected to the mounting plate 16, and the clamping roller is clamped on the track 1, and the gasoline engine is used to drive the clamping roller to rotate. Part of the driving structure can be understood as the prior art, and specific reference can be made to the design method of the single-track or double-track transport vehicle in the prior art.

[0042] In one feasible manner, the cross-section of the baffle bar 11 is square, and a second through hole 14 is further provided on the end of the baffle bar 11, and the second through hole 14 and the first through hole 13 are arranged to be vertically connected. The purpose of the square cross-section of the baffle bar 11 is that no matter how the baffle bar 11 rotates, it can be placed in the limit groove 5. At the same time, the advantage of the setting of the second through hole 14 is that when transporting powdered materials (cement, sand and gravel), the second through hole 14 can be sleeved on the screw 6 to stagger the clamping arc holes 12 set on two adjacent baffle bars 11, and the clamping arc holes 12 are arranged in an upper and lower position at this time. The advantage of this is that the contact between adjacent baffle bars 11 can achieve close contact (which can be understood as no gaps or voids), thereby ensuring that when transporting materials or slag, small individuals will not leak out from between adjacent baffle bars 11, thereby improving the environmental protection and safety of construction.

[0043] In one feasible method, a rubber anti-skid layer is provided on the inner wall of the clamping arc hole 12, and the rubber anti-skid layer is bonded inside the clamping arc hole 12, which can enhance the friction force on the contact part of the steel bar 15, ensure the limiting effect on the steel bar 15, and avoid slipping out at the inclined track 1.

[0044] In one feasible method, the laying path of the track 1 passes through the slag accumulation area of ​​the pile foundation construction, and a lifting device is provided in the slag accumulation area. The lifting device is existing technology, for example, it is composed of a mounting frame and a hand winch, and the mounting frame can rotate, that is, the track 1 can be set within its rotation radius, which can improve the loading and unloading efficiency of materials or slag.

[0045] A method for transferring materials and slag for pile foundation construction in mountainous areas, comprising the following steps:

[0046] S1. Confirm the type of the transferred article and adaptively install the barrier bar 11 according to the type of the transferred article;

[0047] S2. When the transported items are slag or small-volume materials, the second through hole 14 of the baffle 11 is sleeved on the screw 6, and the clamping arc holes 12 provided on the baffle 11 are arranged in an upper and lower distribution, that is, at this time, the contact surfaces of adjacent baffles 11 are sealed;

[0048] S21, then the slag is moved to the space surrounded by the baffle 11 and the side baffle 4 by manual labor or lifting equipment, and then the frame is driven by the driving structure to move on the track 1, thereby transporting and transferring the slag;

[0049] S3. When the transported object is a steel bar 15, the first through hole 13 of the blocking bar 11 is sleeved on the screw rod 6, and the clamping arc holes 12 provided on adjacent blocking bars 11 are arranged opposite to each other;

[0050] S31, move the positions of the two adjacent transfer vehicles to match the length of the steel bar 15, and then place the two ends of the steel bar 15 in the clamping arc holes 12 arranged opposite to each other on the two transfer vehicles. After the placement is completed, rotate the locking nut 7 to lock the position of the blocking bar 11;

[0051] S32, then pull out the limit pin 9, and then drive the frame to move on the track 1 through the driving structure, and then transport and transfer the steel bars 15.

[0052] Finally, it should be noted that the above preferred embodiments are only used to illustrate the technical solutions of the present invention rather than to limit it. Although the present invention has been described in detail through the above preferred embodiments, those skilled in the art should understand that various changes can be made in form and details without departing from the scope defined by the claims of the present invention.

Claims

1. A material and slag transfer system for pile foundation construction in mountainous areas, characterized by: The invention comprises a track (1) arranged side by side, a plurality of transfer vehicles are arranged on the track (1), the transfer vehicle comprises a frame (2), the frame (2) is provided with a driving structure, the driving structure is used to drive the frame (2) to move on the track (1), a mounting plate (16) is arranged above the frame (2), the mounting plate (16) is fixedly connected to the frame (2), a bearing plate (3) is arranged above the mounting plate (16), side baffles (4) are arranged at both ends of the bearing plate (3) arranged perpendicular to the length direction of the track (1), one end of the side baffles (4) is fixed to the bearing plate (3), vertically distributed limiting grooves (5) are arranged on the two edges of the oppositely arranged surfaces of the two side baffles (4), the limiting grooves (5) are connected to a side surface of the two side baffles (4) facing the middle of the bearing plate (3), a screw rod (6) is arranged in the limiting groove (5), one end of the screw rod (6) is fixed to the bearing plate (3) A locking nut (7) is provided on the other end of the screw rod (6), a plurality of retaining bars (11) are provided in two limiting grooves (5) arranged opposite to each other on the two side baffles (4), both ends of the retaining bars (11) are provided with first through holes (13) penetrating therethrough, the first through holes (13) are sleeved on the screw rod (6), a plurality of retaining bars (11) are stacked, the locking nut (7) presses the plurality of retaining bars (11) against the limiting grooves (5), and adjacent retaining bars (11) are arranged in a stacked manner. A plurality of arc-shaped clamping holes (12) with matching positions are provided on the contact surface of the baffle (11), and the arc-shaped clamping holes (12) are evenly distributed along the length direction of the baffle (11). A turntable (10) is provided in the middle of the mounting plate (16), and the middle of the supporting plate (3) is fixed on the turntable (10). The mounting plate (16) and the supporting plate (3) are both provided with position-matching limiting holes (8), and a limiting pin (9) is provided in the limiting hole (8).

2. The material and slag transfer system for pile foundation construction in mountainous areas according to claim 1 is characterized by: One end of the limit pin (9) is arranged to pass through the mounting plate (16), and the limit pin (9) is detachably connected to the mounting plate (16).

3. A material and slag transfer system for pile foundation construction in mountainous areas according to claim 2, characterized in that: The inner wall of the limiting hole (8) arranged on the mounting plate (16) is provided with a thread, and the limiting pin (9) is threadedly connected to the mounting plate (16).

4. The material and slag transfer system for pile foundation construction in mountainous areas according to claim 1 is characterized by: The driving structure comprises a gasoline engine and a clamping roller, wherein the clamping roller is connected to a mounting plate (16) and clamped on a track (1), and the gasoline engine is used to drive the clamping roller to rotate.

5. The material and slag transfer system for pile foundation construction in mountainous areas according to claim 1 is characterized by: The cross section of the baffle (11) is square, and a second through hole (14) is provided on the end of the baffle (11), and the second through hole (14) and the first through hole (13) are vertically connected.

6. The material and slag transfer system for pile foundation construction in mountainous areas according to claim 1 is characterized by: A rubber anti-slip layer is provided on the inner wall of the clamping arc-shaped hole (12), and the rubber anti-slip layer is bonded inside the clamping arc-shaped hole (12).

7. The material and slag transfer system for pile foundation construction in mountainous areas according to claim 1 is characterized by: The laying path of the track (1) passes through a slag accumulation area of ​​pile foundation construction, and a lifting device is provided in the slag accumulation area.

8. A method for transporting materials and slag for pile foundation construction in mountainous areas according to any one of claims 1 to 7, characterized in that: The steps include: S1. Confirm the type of the transferred article and adaptively install the barrier bar (11) according to the type of the transferred article; S2. When the transported object is slag, the second through hole (14) of the baffle (11) is sleeved on the screw (6), and the clamping arc holes (12) provided on the baffle (11) are arranged in an upper and lower distribution, that is, at this time, the contact surfaces of adjacent baffles (11) are sealed; S21, the slag is then moved manually or with a lifting device to a space enclosed by the baffle (11) and the side baffle (4), and then the frame is driven by the driving structure to move on the track (1), thereby transporting and transferring the slag; S3. When the transported object is a steel bar (15), the first through hole (13) of the blocking bar (11) is sleeved on the screw rod (6), and the clamping arc holes (12) provided on adjacent blocking bars (11) are arranged opposite to each other; S31, move the positions of two adjacent transfer vehicles to match the length of the steel bar (15), and then place the two ends of the steel bar (15) in the clamping arc holes (12) arranged opposite to each other on the two transfer vehicles. After the placement is completed, rotate the locking nut (7) to lock the position of the blocking bar (11); S32, then pull out the limit pin (9), and then drive the frame to move on the track (1) through the driving structure, so as to transport and transfer the steel bars (15).