Track laying method for mining

By burying the sleepers to the bottom of the track bed in the mining tracks and setting buffer blocks between the rails, the track stability and safety issues are solved, and safe and efficient mineral transportation is achieved.

CN119434043APending Publication Date: 2025-02-14GANSU HEZUO ZAOZIGOU MINING IND CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411947635.2
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-12-27
Publication Date
2025-02-14

AI Technical Summary

Technical Problem

When mining tracks transport large amounts of minerals, they are prone to stability and safety problems, and vibration and wear between the rails will affect safety.

Method used

The design of sleepers buried to the bottom of the track bed ensures the stability and load-bearing capacity of the track, and a buffer block is installed between the two adjacent rails to reduce vibration and wear.

Benefits of technology

It improves the overall stability and load-bearing capacity of the track, ensures the safe transportation of minerals, reduces vibration and wear between the rails, and reduces safety hazards.

✦ Generated by Eureka AI based on patent content.
Patent Text Reader

Abstract

The invention discloses a track laying method for mining, and relates to the technical field of mine track optimization. The method comprises the following steps: S100, checking a construction site; s200, a ballast bed is cleaned, a sleeper is embedded, and the sleeper is embedded into the bottom end of the ballast bed; s300, steel rails are installed, every two adjacent steel rails are arranged in a spaced mode, and the space between every two adjacent steel rails is filled with buffer blocks; and S400, the gauge and the elevation of the two opposite steel rails are adjusted.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of mine track optimization, in particular to a track laying method for mine development. Background Art

[0002] Mine tracks are mainly used for the transportation of ore, which is transported from the mining face to the ground or other processing sites by mine cars. For example, in some mines in Indonesia, rail transportation systems are used to process broken ore after ring blasting. In addition, tracks are also used to connect tunnels at different levels or areas to form a complex underground transportation network.

[0003] The mining track is an important part of the mine transportation system. Its design and layout directly affect the transportation efficiency and safety of the mine. The mine track consists of two parts: the substructure and the superstructure. The substructure includes the roadbed, drainage ditch and protection and reinforcement facilities; the superstructure includes the ballast, rails, sleepers, connecting parts (such as fish plates, bolts, spring pads, spikes, etc.), safety equipment (such as pull rods, anti-climbers) and turnouts.

[0004] Mine tracks can be divided into main transport lines and general transport lines according to transportation needs. Commonly used rail types include 24kg / m, 18kg / m, 15kg / m, 11kg / m, etc., which are suitable for mines of different sizes and transportation volumes.

[0005] Track line design includes steps such as determining the yard form, drawing a plan layout sketch, calculating line connection points and parameter design, calculating the overall dimensions, and drawing a line layout diagram. When designing, factors such as curve radius, curve angle, and track center distance widening must be considered to ensure the stability and safety of the line.

[0006] The mining track is the core part of the mine transportation system. Its design and maintenance directly affect the production efficiency and safety level of the mine. Through reasonable track design and scientific maintenance management, the transportation capacity and safety of the mine can be effectively improved. Summary of the invention

[0007] The purpose of the present invention is to provide a track laying method for mining, so as to achieve the purpose of high safety and good adaptability of mining tracks.

[0008] In order to achieve the above object, the present invention adopts the following technical means: A mine track laying method comprises the following steps: S100. Check the construction site; S200. Cleaning the ballast bed and burying the sleepers, wherein the sleepers are buried to the bottom of the ballast bed; S300. Load the rails, set the adjacent rails at intervals, and fill and install buffer blocks between the adjacent rails; S400. Adjust the gauge and elevation of the two rails relative to each other.

[0009] Preferably, the step S100 includes: S110. Check the laneway, track centerline, waistline and turnout position; S120. Prepare rails and sleepers.

[0010] Furthermore, the step S200 includes: S210. When cleaning the roadbed, level the roadbed once; S220. Grooving is performed on the ballast bed to form a groove for embedding the sleeper; S230. Place a placeholder in the groove, and then perform secondary leveling on the ballast bed; S240. After taking out the station block, install it into the sleeper.

[0011] Furthermore, the height of the placeholder is the same as the depth of the groove.

[0012] Furthermore, in step S300, the distance between two adjacent rails is 5-10 cm, and both ends of the buffer block are interference fit with the rails.

[0013] Furthermore, the buffer block is a polytetrafluoroethylene block.

[0014] Furthermore, in step S400, the track gauge of the two tracks is greater than half of the channel width and less than three quarters of the channel width.

[0015] During use, the present invention has the following beneficial effects: The sleepers are designed to be buried at the bottom of the ballast bed, which can greatly improve the overall stability and load-bearing capacity of the track, and ensure the safe transportation of large quantities of minerals. In addition, the adjacent rails are spaced apart and buffer blocks are set, which can reduce the vibration between the rails while ensuring the overall load-bearing capacity of the track, and avoid the problem of adjacent rails being worn out for a long time and causing safety hazards. DETAILED DESCRIPTION

[0016] In order to make the purpose, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below in combination with the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments.

[0017] Therefore, the following detailed description of the embodiments of the present invention is not intended to limit the scope of the invention claimed for protection, but merely represents selected embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0018] It should be noted that, in the absence of conflict, the embodiments of the present invention and the features of the embodiments may be combined with each other.

[0019] Example 1 A mine track laying method comprises the following steps: S100. Check the construction site; S200. Cleaning the ballast bed and burying the sleepers, wherein the sleepers are buried to the bottom of the ballast bed; S300. Install the rails, set two adjacent rails at intervals, and fill and install buffer blocks between the two adjacent rails.

[0020] S400. Adjust the gauge and elevation of the two rails relative to each other.

[0021] Preferably, the step S100 includes: S110. Check the laneway, track centerline, waistline and turnout position; S120. Prepare rails and sleepers.

[0022] Furthermore, the step S200 includes: S210. When cleaning the roadbed, level the roadbed once; S220. Grooving is performed on the ballast bed to form a groove for embedding the sleeper; S230. Place a placeholder in the groove, and then perform secondary leveling on the ballast bed; S240. After taking out the station block, install it into the sleeper.

[0023] Furthermore, the height of the placeholder is the same as the depth of the groove.

[0024] Furthermore, in step S300, the distance between two adjacent rails is 5 cm, and both ends of the buffer block are interference fit with the rails.

[0025] Furthermore, the buffer block is a polytetrafluoroethylene block.

[0026] Furthermore, in step S400, the track gauge of the two tracks is greater than half of the channel width and less than three quarters of the channel width.

[0027] During use, the present invention has the following beneficial effects: The sleepers are designed to be buried at the bottom of the ballast bed, which can greatly improve the overall stability and load-bearing capacity of the track, and ensure the safe transportation of large quantities of minerals. In addition, the adjacent rails are spaced apart and buffer blocks are set, which can reduce the vibration between the rails while ensuring the overall load-bearing capacity of the track, and avoid the problem of adjacent rails being worn out for a long time and causing safety hazards.

[0028] Example 2 A mine track laying method comprises the following steps: S100. Check the construction site; S200. Cleaning the ballast bed and burying the sleepers, wherein the sleepers are buried to the bottom of the ballast bed; S300. Install the rails, set two adjacent rails at intervals, and fill and install buffer blocks between the two adjacent rails.

[0029] S400. Adjust the gauge and elevation of the two rails relative to each other.

[0030] Preferably, the step S100 includes: S110. Check the laneway, track centerline, waistline and turnout position; S120. Prepare rails and sleepers.

[0031] Furthermore, the step S200 includes: S210. When cleaning the roadbed, level the roadbed once; S220. Grooving is performed on the ballast bed to form a groove for embedding the sleeper; S230. Place a placeholder in the groove, and then perform secondary leveling on the ballast bed; S240. After taking out the station block, install it into the sleeper.

[0032] Furthermore, the height of the placeholder is the same as the depth of the groove.

[0033] Furthermore, in step S300, the distance between two adjacent rails is 8 cm, and both ends of the buffer block are interference fit with the rails.

[0034] Furthermore, the buffer block is a polytetrafluoroethylene block.

[0035] Furthermore, in step S400, the track gauge of the two tracks is greater than half of the channel width and less than three quarters of the channel width.

[0036] During use, the present invention has the following beneficial effects: The sleepers are designed to be buried at the bottom of the ballast bed, which can greatly improve the overall stability and load-bearing capacity of the track, and ensure the safe transportation of large quantities of minerals. In addition, the adjacent rails are spaced apart and buffer blocks are set, which can reduce the vibration between the rails while ensuring the overall load-bearing capacity of the track, and avoid the problem of adjacent rails being worn out for a long time and causing safety hazards.

[0037] Example 3 A mine track laying method comprises the following steps: S100. Check the construction site; S200. Cleaning the ballast bed and burying the sleepers, wherein the sleepers are buried to the bottom of the ballast bed; S300. Install the rails, set two adjacent rails at intervals, and fill and install buffer blocks between the two adjacent rails.

[0038] S400. Adjust the gauge and elevation of the two rails relative to each other.

[0039] Preferably, the step S100 includes: S110. Check the laneway, track centerline, waistline and turnout position; S120. Prepare rails and sleepers.

[0040] Furthermore, the step S200 includes: S210. When cleaning the roadbed, level the roadbed once; S220. Grooving is performed on the ballast bed to form a groove for embedding the sleeper; S230. Place a placeholder in the groove, and then perform secondary leveling on the ballast bed; S240. After taking out the station block, install it into the sleeper.

[0041] Furthermore, the height of the placeholder is the same as the depth of the groove.

[0042] Furthermore, in step S300, the distance between two adjacent rails is 10 cm, and both ends of the buffer block are interference fit with the rails.

[0043] Furthermore, the buffer block is a polytetrafluoroethylene block.

[0044] Furthermore, in step S400, the track gauge of the two tracks is greater than half of the channel width and less than three quarters of the channel width.

[0045] During use, the present invention has the following beneficial effects: The sleepers are designed to be buried at the bottom of the ballast bed, which can greatly improve the overall stability and load-bearing capacity of the track, and ensure the safe transportation of large quantities of minerals. In addition, the adjacent rails are spaced apart and buffer blocks are set, which can reduce the vibration between the rails while ensuring the overall load-bearing capacity of the track, and avoid the problem of adjacent rails being worn out for a long time and causing safety hazards.

[0046] Although the present invention has been described in detail with reference to the aforementioned embodiments, it is still possible for those skilled in the art to modify the technical solutions described in the aforementioned embodiments, or to make equivalent substitutions for some of the technical features therein. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.

Claims

1. A method for laying track for mining, characterized in that: The following steps are involved: S100. Check the construction site; S200. Cleaning the ballast bed and burying the sleepers, wherein the sleepers are buried to the bottom of the ballast bed; S300. Load the rails, set the adjacent rails at intervals, and fill and install buffer blocks between the adjacent rails; S400. Adjust the gauge and elevation of the two rails relative to each other.

2. A mine track laying method according to claim 1, characterized in that: The step S100 includes: S110. Check the laneway, track centerline, waistline and turnout position; S120. Prepare rails and sleepers.

3. A mine track laying method according to claim 1, characterized in that: The step S200 includes: S210. When cleaning the roadbed, level the roadbed once; S220. Grooving is performed on the ballast bed to form a groove for embedding the sleeper; S230. Place a placeholder in the groove, and then perform secondary leveling on the ballast bed; S240. After taking out the station block, install it into the sleeper.

4. A mine track laying method according to claim 3, characterized in that: The height of the placeholder is the same as the depth of the groove.

5. The track laying method for mining according to claim 1, characterized in that: In step S300, the distance between two adjacent rails is 5-10 cm, and both ends of the buffer block are interference fit with the rails.

6. A mine track laying method according to claim 1 or 5, characterized in that: The buffer block is a polytetrafluoroethylene block.

7. A mine track laying method according to claim 1, characterized in that: In step S400, the track gauges of the two relative tracks are greater than half of the channel width and less than three quarters of the channel width.