Connecting structure between transfer layer and main structure in arc-shaped suspended ceiling and construction method
By using grabbers and T-type connectors to connect the conversion layer and the main structure in the construction of curved aluminum plate ceilings, and using U-shaped steel plate to support the main structure, the difficulty of adjusting the elevation of the conversion layer and inaccurate dimensional control in the prior art is solved. The problem of this has improved construction efficiency and installation quality.
Patent Information
- Application Number
- CN202411416059.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-10-11
- Publication Date
- 2025-02-14
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
In the existing arc-shaped aluminum plate ceiling construction method, after the conversion layer is directly welded to the main structure, it is difficult to adjust the elevation, resulting in the difficulty of accurately controlling the size of the ambient surface of the surface aluminum plate, which is inefficient and has a low fault tolerance.
Two sets of grippers are used to connect to the conversion layer, and the conversion layer is connected to the main structure through the T-type connector, and the bottom of the main structure is supported by U-shaped steel plate and the base to achieve compensation for the error between the conversion layer and the main structure. .
It improves construction efficiency, ensures installation quality, accurately controls the size of the aluminium plate inclined surface, and reduces the complexity and error of later installation.
Smart Images

Figure CN119434525A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of suspended ceilings, and in particular to a connection structure between a conversion layer and a main structure in a curved suspended ceiling and a construction method. Background Art
[0002] In the current field of building technology, in the curved aluminum ceiling project, especially in the transition layer construction involving the curved aluminum plate and the inclined structure, the traditional construction method mostly relies on the direct steel frame welding on site according to the inclined cylindrical steel structure and the curved aluminum plate transition layer. The main installation method is that the transition layer steel frame is directly welded to the main structure without the use of combined clamps. Subsequently, the transition layer is connected to the aluminum plate through the hanger.
[0003] The disadvantage of the existing practice is that after the transfer layer is directly welded on the main steel structure, it is difficult to adjust the elevation of the transfer layer according to the height difference of the main steel structure on site. After welding, the size of the transfer layer is fixed and lacks room for adjustment, which makes it difficult to accurately control the size of the inclined surface of the surface aluminum plate.
[0004] This method is not only inefficient, but also has a low error tolerance rate, which further increases the complexity of the subsequent aluminum plate ordering and on-site installation. Especially during the installation stage, the gaps between aluminum plates are difficult to control accurately, resulting in unsatisfactory construction results and may even affect delivery. Especially when it comes to the corner treatment between multiple aluminum plates, it is more likely to have problems with height differences and misaligned seams. Summary of the invention
[0005] The purpose of the present invention is to overcome the defects of the prior art and provide a connection structure and construction method between a conversion layer in a curved ceiling and a main structure, so as to solve the problems of low efficiency and low fault tolerance of the existing method.
[0006] The technical solution for achieving the above-mentioned purpose is: a connection structure between the transition layer in the curved ceiling and the main structure, comprising: two groups of grabbing parts, the two groups of grabbing parts are respectively connected to the transition layer, and the two groups of grabbing parts are arranged opposite to each other; a T-shaped connecting part, the T-shaped connecting part is arranged between the two groups of the grabbing parts, and the two sides of the upper end of the T-shaped connecting part are respectively clamped on the two groups of the grabbing parts; a base, the base is horizontally arranged, and the upper end of the base is connected to the bottom end of the T-shaped connecting part; a U-shaped steel plate, the upper end of the U-shaped steel plate is connected to the bottom end of the base, and the inner wall of the U-shaped steel plate is supported on the bottom of the main structure.
[0007] In a connection structure between a transition layer and a main structure in a curved ceiling of the present invention, a grabbing piece is used to connect the transition layer, a U-shaped steel plate and a base are used to support the bottom of the main structure, and the transition layer and the main structure are connected by a T-shaped connecting piece, which can effectively compensate for the error between the main structure and the transition layer during on-site construction, improve construction efficiency, and ensure installation quality.
[0008] A further improvement of the connection structure between a conversion layer and a main structure in a curved ceiling of the present invention is that two square tubes are arranged opposite to each other in the conversion layer, and the connection structure includes: a groove is formed at one end of each group of the grabbing members, and the groove corresponds to the end of the square tube.
[0009] A further improvement of the connection structure between the conversion layer and the main structure in a curved ceiling of the present invention is that the frame structure of the main structure is arranged below the two square passages, and the connection structure includes: the frame structure is connected to the bottom end of the base.
[0010] A further improvement of the connection structure between the transfer layer and the main structure in a curved ceiling of the present invention comprises: a plurality of diagonal bracing angle steels are arranged between the frame structure and the base.
[0011] A further improvement of the connection structure between the conversion layer and the main structure in the arc-shaped ceiling of the present invention lies in that the frame structure is arranged in parallel with the base.
[0012] A further improvement of the connection structure between the transfer layer and the main structure in a curved ceiling of the present invention is that the curvature of the bottom of the frame structure matches and corresponds to the curvature of the U-shaped steel plate.
[0013] A further improvement of the connection structure between the inner transfer layer of the arc-shaped ceiling and the main structure of the present invention is that a gasket is provided between the inner wall of the U-shaped steel plate and the outer wall of the frame structure.
[0014] A further improvement of the connection structure between the inner conversion layer and the main structure of the arc-shaped suspended ceiling of the present invention lies in that the grabbing piece and the T-shaped connecting piece are connected by bolts.
[0015] A further improvement of the connection structure between the inner conversion layer and the main structure of the arc-shaped suspended ceiling of the present invention is that a plurality of connection holes are provided on the grabbing member for the bolts to pass through.
[0016] A construction method for a connection structure between a transition layer and a main structure in an arc-shaped suspended ceiling, comprising the following steps: laying a base on the upper side of a navigator structure of the main structure; installing a U-shaped steel plate on the periphery of the navigator structure, and fixing both ends of the U-shaped steel plate on the base; arranging a gasket between the U-shaped steel plate and the navigator structure; welding the bottom end of a T-shaped connector to the upper end of the base; connecting two groups of grabbing members to both sides of the upper end of the T-shaped connector with bolts; and respectively embedding two oppositely arranged square tubes in the transition layer into the grooves of the two groups of grabbing members. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] Figure 1 The present invention is a cross-sectional view of a connection structure between a conversion layer and a main structure in a curved ceiling.
[0018] Figure 2 The figure is a top view of a connection structure between a conversion layer and a main structure in a curved ceiling according to the present invention.
[0019] Figure 3 It is a top view of the grabbing member 11 of the present invention.
[0020] Figure 4 The present invention is a flow chart of a construction method of a connection structure between a transfer layer in a curved ceiling and a main structure.
[0021] In the figure: 10, square tube; 11, grab piece; 111, groove; 12, T-type connector; 13, base; 14, U-shaped steel plate; 15, diagonal bracing angle steel; 16, gasket; 17, bolt; 18, long rod bolt; 19, anti-rust layer; 20, frame structure. DETAILED DESCRIPTION
[0022] The present invention will be further described below in conjunction with the accompanying drawings and specific embodiments.
[0023] See also Figure 1 , showing a cross-sectional view of a connection structure between a conversion layer and a main structure in a curved ceiling of the present invention. The present invention provides a connection structure between a conversion layer and a main structure in a curved ceiling, comprising: two groups of grabbing members 11, the two groups of grabbing members 11 are respectively connected to the conversion layer, and the two groups of grabbing members 11 are arranged opposite to each other.
[0024] Each group of grabbing members 11 includes two straight-line grabbing members 11 , one end of each group of grabbing members 11 is arranged close to and in contact with each other, and the other end is arranged away from each other.
[0025] The T-shaped connecting piece 12 is disposed between the two groups of grabbing pieces 11 , and both sides of the upper end of the T-shaped connecting piece 12 are clamped on the two groups of grabbing pieces 11 respectively.
[0026] The T-shaped connector 12 is vertically arranged, and circular holes are respectively arranged on both sides of the upper end of the T-shaped connector 12 . The T-shaped connector 12 is connected to the two groups of grabbing members 11 on both sides by bolts 17 .
[0027] The base 13 is horizontally arranged, and the upper end of the base 13 is connected to the bottom end of the T-shaped connector 12 .
[0028] The base 13 is a galvanized steel plate, and the bottom of the T-shaped connector 12 is fixed to the base 13 by welding.
[0029] The U-shaped steel plate 14 has its upper end connected to the bottom end of the base 13 , and its inner wall is supported on the bottom of the main structure.
[0030] The bottom of the U-shaped steel plate 14 supports the main structure, and both ends of the U-shaped steel plate 14 are connected to the base 13 by bolts 17 respectively.
[0031] See also Figure 2 and Figure 3 , Figure 2 A top view of a connection structure between a conversion layer and a main structure in a curved ceiling according to the present invention is shown. Figure 3 The present invention provides a connection structure between a conversion layer and a main structure in a curved ceiling, wherein two square tubes 10 are arranged opposite to each other in the conversion layer, and the connection structure comprises: a groove 111 is formed at one end of each group of the connection members 11, and the groove 111 corresponds to the end of the square tube 10.
[0032] The ends of the two square tubes 10 are both provided with transverse through holes, and the square tubes 10 are clamped in the grooves 111 formed by the grabbing parts 11 and connected and fixed by long rod bolts 18 .
[0033] In this embodiment, two groups of transverse through holes are provided at the end of the square tube 10, and the two groups of transverse through holes are parallel to each other. Corresponding to the transverse through holes, two groups of wide connecting holes are provided on each group of grabbing pieces 11, so as to facilitate the adjustment of the position of the square tube 10 and the connecting piece within a small range during connection. The provision of two groups of parallel transverse through holes strengthens the stability of the connection between the square tube 10 and the connecting piece.
[0034] See also Figure 1 , showing a cross-sectional view of a connection structure between a conversion layer and a main structure in a curved ceiling of the present invention. The present invention provides a connection structure between a conversion layer and a main structure in a curved ceiling, wherein a frame structure 20 of the main structure is arranged below two square passages 10, and the connection structure comprises: the frame structure 20 is connected to the bottom end of a base 13.
[0035] The frame structure 20 is a circular tube structure, and the curvature of the U-shaped steel plate 14 corresponds to and matches the frame structure 20 .
[0036] See also Figure 1 , showing a cross-sectional view of a connection structure between a transfer layer and a main structure in a curved ceiling of the present invention. The present invention provides a connection structure between a transfer layer and a main structure in a curved ceiling, comprising: a plurality of diagonal bracing angle steels 15 are arranged between a navigating frame structure 20 and a base 13.
[0037] The connection point between the diagonal bracing angle steel 15 and the base 13 is arranged on the inner side of the U-shaped steel plate 14 , and the diagonal bracing angle steel 15 is symmetrically distributed on both sides of the frame structure 20 .
[0038] See also Figure 1, showing a cross-sectional view of a connection structure between a transfer layer and a main structure in a curved ceiling of the present invention. The present invention provides a connection structure between a transfer layer and a main structure in a curved ceiling, wherein a frame structure 20 is arranged parallel to a base 13.
[0039] The base 13 is horizontally arranged on the upper side of the frame structure 20 .
[0040] See also Figure 1 , showing a cross-sectional view of a connection structure between a transfer layer and a main structure in a curved ceiling of the present invention. The present invention provides a connection structure between a transfer layer and a main structure in a curved ceiling, wherein the bottom curvature of the frame structure 20 matches the curvature of the U-shaped steel plate 14.
[0041] The width of the frame structure 20 is smaller than or equal to the inner wall spacing of the U-shaped steel plate 14 .
[0042] See also Figure 1 , showing a cross-sectional view of a connection structure between a transfer layer and a main structure in a curved ceiling of the present invention. The present invention provides a connection structure between a transfer layer and a main structure in a curved ceiling, wherein a gasket 16 is provided between the inner wall of a U-shaped steel plate 14 and the outer wall of a navigating frame structure 20.
[0043] The gasket 16 is made of rubber material and is disposed on one side of the bottom of the frame structure 20 to serve as a buffer structure between the frame structure 20 and the U-shaped steel plate 14 to prevent structural instability caused by collision and friction.
[0044] See also Figure 2 , showing a top view of a connection structure between a transition layer and a main structure in a curved ceiling according to the present invention. The present invention provides a connection structure between a transition layer and a main structure in a curved ceiling, wherein a grabbing member 11 and a T-shaped connecting member 12 are connected by bolts 17.
[0045] A plurality of bolts 17 are disposed in the middle of one end of the grabbing member 11 , thereby enhancing the stability of the connection between the grabbing member 11 and the T-shaped connecting member 12 .
[0046] The present invention provides a connection structure between a conversion layer and a main structure in an arc-shaped suspended ceiling. A plurality of connection holes are provided on a grabbing member 11 for bolts 17 to pass through.
[0047] Among them, the connecting holes include ordinary connecting holes for connecting the grabbing piece 11 and the T-shaped connecting piece 12 and wide connecting holes for connecting the grabbing piece 11 and the square tube 10. The wide connecting holes facilitate the bolts 17 to adjust the connection position of the grabbing piece 11 and the square tube 10 within the range of the wide connecting holes, and can adapt to errors within a small range.
[0048] See also Figure 4, showing a schematic flow chart of a construction method of a connection structure between a transfer layer in a curved ceiling and a main structure of the present invention. The present invention provides a construction method of a connection structure between a transfer layer in a curved ceiling and a main structure, comprising the following steps:
[0049] Execute step S210: lay the base 13 on the upper side of the main structure of the frame structure 20.
[0050] The base 13 is horizontally laid on the upper side of the frame structure 20 , correspondingly arranged directly below the two oppositely arranged square tubes 10 , and the width of the base 13 is set to be greater than the distance between the two square tubes 10 , and then step S220 is executed.
[0051] Execute step S220 : install the U-shaped steel plate 14 on the outer periphery of the frame structure 20 , and fix both ends of the U-shaped steel plate 14 on the base 13 .
[0052] The U-shaped steel plate 14 is supported on the periphery of the navigator frame structure 20 and connected and fixed by bolts 17 that penetrate the base 13 and the two wings of the U-shaped steel plate 14 from top to bottom, thereby strengthening the connection between the U-shaped steel plate 14 and the base 13. Then, step S230 is executed.
[0053] Execute step S230: arrange a gasket 16 between the U-shaped steel plate 14 and the frame structure 20 .
[0054] The gasket 16 is wrapped around the lower half of the outer wall of the frame structure 20 . The size of the gasket 16 is selected according to the size of the frame structure 20 , and is not specifically limited here. Next, step S240 is executed.
[0055] Execute step S240: weld the bottom end of the T-shaped connector 12 to the upper end of the base 13 .
[0056] Among them, anti-rust treatment is performed on the welding connection to form an anti-rust layer 19 to extend the life of the structure, and then step S250 is executed.
[0057] Execute step S250: connect the two sets of grabbing members 11 to the two sides of the upper end of the T-shaped connecting member 12 respectively with bolts 17 .
[0058] Among them, two straight-line grabbing members 11 are used to clamp one end of the T-shaped connecting member 12, and the round hole of the straight-line grabbing member 11 and the common connecting hole on the T-shaped connecting member 12 are aligned and connected and fixed with bolts 17, and then step S260 is performed. .
[0059] Execute step S260: embed two oppositely disposed square tubes 10 in the conversion layer into the grooves 111 of the two groups of grabbing members 11 respectively.
[0060] The square tube 10 is placed in the groove 111 formed at the other end of each group of the grabbing members 11 , and bolts 17 are passed through the transverse through holes on the square tube 10 and the wide connecting holes of the grabbing members 11 on both sides.
[0061] The present invention is described in detail above in conjunction with the embodiments of the drawings. A person skilled in the art can make various changes to the present invention according to the above description. Therefore, certain details in the embodiments should not be construed as limiting the present invention, and the scope of protection of the present invention shall be the scope defined by the attached claims.
Claims
1. A connection structure between a transfer layer and a main structure in a curved ceiling, characterized in that: include: Two groups of grabbing members, the two groups of grabbing members are respectively connected to the conversion layer, and the two groups of grabbing members are arranged opposite to each other; A T-shaped connecting piece, the T-shaped connecting piece is arranged between the two groups of the grabbing pieces, and the two sides of the upper end of the T-shaped connecting piece are respectively clamped on the two groups of the grabbing pieces; A base, the base is arranged horizontally, and the upper end of the base is connected to the bottom end of the T-shaped connector; A U-shaped steel plate, the upper end of which is connected to the bottom end of the base, and the inner wall of which is supported on the bottom of the main structure.
2. The connection structure between the conversion layer and the main structure in the curved ceiling according to claim 1, characterized in that: The two square passages in the conversion layer are arranged opposite to each other, and the connection structure includes: A groove is formed at one end of each group of the grabbing members, and the groove corresponds to the end of the square tube.
3. The connection structure between the conversion layer and the main structure in the curved ceiling according to claim 2, characterized in that: The main structure of the frame structure is arranged below the two square passages, and the connection structure includes: The frame structure is connected to the bottom end of the base.
4. The connection structure between the conversion layer and the main structure in the curved ceiling according to claim 3 is characterized in that: include: A plurality of diagonal bracing angle steels are arranged between the frame structure and the base.
5. The connection structure between the conversion layer and the main structure in the curved ceiling according to claim 3, characterized in that: The frame structure is arranged parallel to the base.
6. According to the connection structure between the transfer layer and the main structure in the curved ceiling as described in claim 3, the bottom curvature of the frame structure matches and corresponds to the curvature of the U-shaped steel plate.
7. The connection structure between the conversion layer and the main structure in the curved ceiling according to claim 3, characterized in that: A gasket is provided between the inner wall of the U-shaped steel plate and the outer wall of the frame structure.
8. The connection structure between the transfer layer and the main structure in the curved ceiling according to claim 1, characterized in that: The grabbing piece is connected to the T-shaped connecting piece by bolts.
9. The connection structure between the transfer layer and the main structure in the curved ceiling according to claim 3, characterized in that: The grabbing member is provided with a plurality of connecting holes for the bolts to pass through.
10. A construction method for a connection structure between a transfer layer and a main structure in a curved ceiling, characterized in that: The steps include: Lay the base on the upper side of the main structure's frame structure; Installing a U-shaped steel plate on the periphery of the frame structure, and fixing both ends of the U-shaped steel plate on the base; A gasket is provided between the U-shaped steel plate and the frame structure; Welding the bottom end of the T-shaped connector to the upper end of the base; Connecting two sets of grabbing pieces to both sides of the upper end of the T-shaped connecting piece with bolts respectively; Two oppositely arranged square tubes in the conversion layer are respectively embedded in the grooves of the two groups of the grabbing members.
Citation Information
Patent Citations
Steel construction conversion layer pendant with adjustable
CN206769169U
Reverse non-welding adjustable mounting device for conversion layer of large suspended ceiling
CN221778793U