Integrated rock drilling and guniting equipment for vertical shaft anchoring and shotcreting support

By designing a vertical shaft anchor spraying support equipment that integrates rock drilling and grouting functions, the work difficulty and drilling quality problems caused by the separation of traditional equipment are solved, and the continuous operation and construction efficiency of the equipment are improved.

CN119466807APending Publication Date: 2025-02-18SINOHYDRO ENG BUREAU 4
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202411747288.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-12-02
Publication Date
2025-02-18

AI Technical Summary

Technical Problem

During the construction of traditional vertical shaft anchor spraying support, rock drilling and sprinkler equipment are separated, making it difficult to cooperate with each other, increasing the difficulty of work. Moreover, the adaptability of different types of equipment is limited in complex geological environments, which makes it difficult to ensure the quality of the drilling, which is very labor-intensive and dangerous. High coefficient.

Method used

An integrated rock drilling and slurry equipment with vertical shaft anchor spraying support was designed, including upper hanging disks, hydraulic stations, rotary tables, working connection frames, rock drilling and slurry components, etc., to achieve the integration of rock drilling and slurry functions. Through structures such as rotary table and telescopic cylinder, free adjustment of depth and bore angle is achieved.

Benefits of technology

This equipment allows rock drilling and sprinkler functions to achieve continuous operation without frequent equipment replacement, shorten the construction cycle, improve work efficiency, reduce labor intensity and risk coefficient, and ensure the quality of the drilling.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119466807A_ABST
    Figure CN119466807A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of shaft construction supporting, and discloses a shaft anchor-shotcrete supporting integrated rock drilling and shotcrete device which comprises an upper layer hanging scaffold which is of a metal plate-shaped structure placed in a shaft, the lower end of the upper layer hanging scaffold is connected with a lower layer hanging scaffold through a traction column, and hanging scaffold stabilizing oil cylinders are symmetrically arranged on the two sides of the lower layer hanging scaffold; and a main payment main body framework installed in the vertical shaft for rock drilling construction is formed. According to the integrated rock drilling and guniting equipment for the vertical shaft anchoring and shotcreting support, work of the hydraulic rock drilling machine and the guniting nozzle pipe is combined through the sliding frame supporting frame, the rock drilling function and the guniting function are integrated, integrated installation is provided for the main supporting beam through the work connecting frame and the supporting bottom plate, and therefore the occupied area of the equipment is reduced, and the installation time of the equipment is shortened; with the integrated design of rock drilling and guniting working equipment, the equipment conversion and preparation time is shortened, and continuous operation can be achieved without frequent equipment replacement through integrated installation and integrated design.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of shaft construction support, in particular to an integrated rock drilling and grouting equipment for shaft anchor spraying support. Background Art

[0002] When constructing the water diversion shaft, the initial support of the shaft excavation adopts anchor net spraying support, the shaft is constructed by the reverse well method, the excavation is carried out by umbrella drilling and smooth blasting, and the excavation depth of one blasting is more than 4.5m. When operating, traditional rock drilling equipment often takes a lot of time to install and debug the equipment. During the rock drilling process, the technical requirements for operators are high, and the work efficiency is relatively low. At the same time, as the rock drilling work gradually deepens, the traditional payment equipment has defects in the payment work, such as:

[0003] Traditional shaft anchor spraying support construction uses manual air drills to drill holes and manual spray heads for grouting. When the excavation depth exceeds 4m, work can only be done on a hanging platform. The overall working environment is affected by aspects such as the drilling angle, making it difficult to ensure the quality of the drilling. Different types of rock drilling equipment may have limitations when adapting to different geological conditions, and it is difficult to meet the needs of shaft construction in complex geological environments. The use of a supporting spray head for spraying affects the working scope during work by the hanging platform working environment. Not only is the overall labor intensity high, but the rebound amount during the spraying is large, which easily increases the difficulty of paying attention between rock drilling and spraying.

[0004] In view of the above problems, it is urgent to carry out innovative design based on the original shaft construction support. Summary of the invention

[0005] The object of the present invention is to provide an integrated rock drilling and grouting equipment for shaft anchor spraying support, so as to solve the problems proposed in the above background technology that traditional rock drilling and grouting are separate structures, the equipment is difficult to cooperate with each other in the shaft construction environment, which increases the difficulty of work, and because different types of rock drilling equipment have limited operating environments when adapting to different geological conditions, the drilling angle and inclination are affected, the labor intensity is high, the risk factor is high, and the drilling quality is difficult to guarantee.

[0006] To achieve the above-mentioned purpose, the present invention provides the following technical solutions: an integrated rock drilling and grouting equipment for vertical shaft anchor spraying support, comprising an upper hanging plate, which is a metal plate-shaped structure placed in the vertical shaft, the lower end of the upper hanging plate is connected to the lower hanging plate through a pulling column, and hanging plate stabilizing cylinders are symmetrically arranged on both sides of the lower hanging plate, constituting the main payment main body structure installed in the vertical shaft rock drilling construction;

[0007] A hydraulic station is arranged at the upper end of the upper hanging plate, and the pipeline of the hydraulic station runs through the upper hanging plate and the lower hanging plate, and the pipeline of the hydraulic station is connected to the hydraulic rock drill located in the vertical shaft for rock drilling, and a turntable is arranged at the lower end of the lower hanging plate, and a working connection frame is installed on the turntable at the output end of the turntable, and a return-shaped supporting bottom plate is installed at the bottom end of the working connection frame, and a rock drilling and grouting assembly is installed on the upper surface of the supporting bottom plate, which is used for performing grouting while performing rock drilling construction in the vertical shaft, forming an integrated payment device;

[0008] The upper hanging tray is penetrated by the protective turning platform, and the bottom end of the protective turning platform is located parallel to the lower hanging tray. A guide step is provided at the upper end of the lower hanging tray, and the guide step is spirally arranged, and a positioning plate frame is installed on the top of the guide step. A slide groove rotatably connected to the protective turning platform is provided at the bottom end of the positioning plate frame, and the protective turning platform is arranged as a C-shaped dam structure. The guide step penetrates the upper hanging tray, and a parallel steering pedal platform is provided at the place where the guide step penetrates the upper hanging tray.

[0009] By adopting the above technical solution, the support equipment can have both rock drilling and grouting functions, eliminating the need to purchase and maintain multiple different equipment, thereby reducing purchase and maintenance costs.

[0010] Preferably, the upper hanging tray is arranged in parallel with the lower hanging tray, and the turntable at the bottom end of the lower hanging tray is arranged in a vertical direction.

[0011] By adopting the above technical solution, the upper hanging plate and the lower hanging plate are used as the main supporting structures for supporting the entire device.

[0012] Preferably, the rock drilling and grouting assembly comprises:

[0013] A main support beam installed above the support base plate;

[0014] A drilling rig slide, which is installed on the surface of the main support beam, and the drilling rig slide is installed between the columns of the working connecting frame;

[0015] A hydraulic rock drill, which is located on the slide mounting connection of the drilling rig slide;

[0016] A rock drill rod, which is installed at the output end of the hydraulic rock drill, and the rock drill rod is arranged parallel to the drilling rig slide;

[0017] A drill rod guide is installed at one end of the drilling rig slide, and the drill rod passes through the inside of the drill rod guide;

[0018] A hydraulic pipe guide frame mounted on the other end of the drilling rig slide;

[0019] A telescopic oil cylinder is installed in the main support beam and connected to the bottom end of the drilling rig slide;

[0020] A carriage support beam is mounted on the bottom end of the main support beam, and a rotating support is provided at the connection between the bottom end of the carriage support beam and the support bottom plate;

[0021] A rocker is installed at the bottom end of the slide support beam, and the rocker is arranged at the bottom end of the slide support beam near the rock drilling end of the rock drilling drill rod.

[0022] By adopting the above technical solution, the integrated design of the rock drilling and shotcrete spraying components reduces equipment conversion and preparation time. By integrating the two, there is no need to frequently replace equipment, which can significantly shorten the construction period.

[0023] Preferably, the main support beam and the telescopic cylinder are arranged in parallel at the bottom end of the drilling rig slide.

[0024] By adopting the above technical solution, the telescopic cylinder installed on the surface of the main support beam is used to further adjust the forward depth of the drilling rig slide.

[0025] Preferably, the drill rod guide and the hydraulic pipe guide frame at the upper end of the drilling rig slideway are both positioned and installed by bolts.

[0026] By adopting the above technical solution, the drill rod guide and the hydraulic pipe guide frame are installed in the slideway of the drilling rig slide to assist the work of the rock drilling drill rod while limiting the distance of pushing the hydraulic rock drill in the drilling rig slide.

[0027] Preferably, the drill rod guide is composed of two U-shaped frames symmetrically engaged, and the hole-shaped structure formed by the two U-shaped frames of the drill rod guide is provided with a bearing structure that rotates with the rock drilling drill rod.

[0028] By adopting the above technical solution, the drill rod guide installed at the output end of the rock drilling drill rod adopts an upper and lower wrapped structure to surround the outside of the rock drilling drill rod to guide the working of the rock drilling drill rod.

[0029] Preferably, the hydraulic pipe guide frame is composed of a U-shaped metal support and three roller rods installed in a triangle, and the roller rods rotating inside the hydraulic pipe guide frame are in contact with the pipelines of the hydraulic station.

[0030] By adopting the above technical solution, the roller rod structure inside the hydraulic pipe guide frame guides the pipeline of the hydraulic station to avoid jamming between the pipeline and the equipment.

[0031] Preferably, an adjusting and compensating oil cylinder is rotatably connected between the bottom end of the slide support beam and the opening of the steel frame supporting the bottom plate, and the adjusting and compensating oil cylinder is arranged in an inclined state.

[0032] By adopting the above technical solution, the slide support beam is supported by adjusting the compensation cylinder to achieve angle control.

[0033] Preferably, the limiting metal clamps are symmetrically installed on both sides of the oscillator, and the spray nozzle pipe is placed in the opening of the limiting metal clamp.

[0034] By adopting the above technical solution, the grouting nozzle pipe is limited and clamped by the limiting metal clamp, so as to control the grouting nozzle pipe to be at 75° to the key of the rock drilling part, thereby reducing the grouting rebound amount.

[0035] Preferably, a positioning stopper is provided on the surface of the limiting metal clamp, and the positioning stopper is a double-layer rotatably connected annular structure, and one side of the positioning stopper is against the surface of the spray nozzle pipe.

[0036] By adopting the above technical solution, the spray nozzle pipe is restricted to work through the limiting metal clamp and the positioning limiter sleeve.

[0037] Compared with the prior art, the invention has the following beneficial effects: the integrated rock drilling and grouting equipment for vertical shaft anchor spraying support:

[0038] 1. The hydraulic rock drill and the shotcrete nozzle pipe are composed of a slide support frame, so that the rock drilling and shotcrete functions are integrated into one. The main support beam of the working connection frame and the support base plate provides an integrated installation, thereby reducing the equipment footprint and installation time. With the integrated design of the rock drilling and shotcrete working equipment, the equipment conversion and preparation time are reduced. Compared with traditional construction, the switching between rock drilling and shotcrete requires different equipment to be carried out in sequence. In this application, the working position is adjusted by rotating the same turntable. After integrated installation and integrated design, continuous operation can be achieved without frequent equipment replacement. After the rock drilling is completed, it can be quickly switched to the shotcrete mode, avoiding construction interruption, greatly shortening the construction period, and improving the overall work efficiency.

[0039] 2. With the turntable, telescopic cylinder and adjusting compensation cylinder connected to the carriage support beam, the rock drilling rod and the shotcrete nozzle pipe at the upper end of the carriage support beam can realize free adjustment of the depth and drilling angle during work. When working underground, the number of personnel during construction is reduced, and the labor intensity of workers is reduced. With the limiting metal clips on both sides of the rocker, the spraying angle of the shotcrete nozzle pipe is adjusted to 75° to ensure the uniformity of the shotcrete, thereby controlling the rebound amount of the shotcrete, and further reducing the impact of the rebound on the work of the equipment. With the integrated and continuous construction operation, the exposure time of personnel in dangerous environments is reduced, and the risk factor of the operation is reduced. BRIEF DESCRIPTION OF THE DRAWINGS

[0040] Figure 1 It is a schematic diagram of the overall external three-dimensional structure of the present invention;

[0041] Figure 2 It is a schematic diagram of the overall internal side-section stereoscopic structure of the present invention;

[0042] Figure 3It is a schematic diagram of the overall internal three-dimensional structure of the present invention;

[0043] Figure 4 This is a schematic diagram of the three-dimensional structure of the upper hanging plate and the protective turning platform of the present invention;

[0044] Figure 5 It is a schematic diagram of the installation structure of the lower hanging plate and the rock drilling and shotcrete assembly of the present invention;

[0045] Figure 6 It is a schematic diagram of the installation structure of the rotary table and the rock drilling and shotcrete assembly of the present invention;

[0046] Figure 7 It is a schematic diagram of the three-dimensional structure of the hydraulic rock drill and the rocker of the present invention;

[0047] Figure 8 It is a schematic diagram of the three-dimensional structure of the rock drilling rod and the drill rod guide of the present invention;

[0048] Fig. 9 This is a schematic diagram of the three-dimensional structure of the slide support beam and the rocker installation of the present invention;

[0049] Fig.10 It is a schematic diagram of the three-dimensional structure of the installation of the oscillator and the spray nozzle pipe of the present invention.

[0050] In the figure: 1. Upper lifting platform; 2. Pulling column; 3. Lower lifting platform; 4. Lifting platform stabilizing cylinder; 5. Hydraulic station; 6. Turntable; 7. Working connecting frame; 8. Support base plate; 9. Main supporting beam; 10. Drilling rig slide; 11. Hydraulic rock drill; 12. Rock drilling rod; 13. Drill rod guide; 14. Hydraulic pipe guide frame; 15. Telescopic cylinder; 16. Slide support beam; 17. Rocker; 18. Limiting metal clamp; 19. Positioning limiter; 20. Spraying nozzle pipe; 21. Adjusting compensation cylinder; 22. Protective turning platform; 23. Guide ladder; 24. Positioning plate frame. DETAILED DESCRIPTION

[0051] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0052] See also Figure 1-Figure 10The present invention provides a technical solution: an integrated rock drilling and grouting equipment for vertical shaft anchor spraying support, including an upper hanging plate 1, a pulling column 2, a lower hanging plate 3, a hanging plate stabilizing cylinder 4, a hydraulic station 5, a rotary table 6, a working connecting frame 7, a supporting bottom plate 8, a main supporting beam 9, a drilling rig slide 10, a hydraulic rock drill 11, a rock drilling drill rod 12, a drill rod guide 13, a hydraulic pipe guide frame 14, a telescopic cylinder 15, a slide support beam 16, a rocker 17, a limit metal clamp 18, a positioning limiter 19, a grouting nozzle pipe 20, an adjustment compensation cylinder 21, a protective turning platform 22, a guide ladder 23 and a positioning plate frame 24;

[0053] Among them, the upper hanging plate 1 is a metal plate-shaped structure placed in the shaft, the lower end of the upper hanging plate 1 is connected to the lower hanging plate 3 through the pulling column 2, and the lower hanging plate 3 is symmetrically provided with hanging plate stabilizing cylinders 4 on both sides, forming the main payment body structure installed in the shaft rock drilling construction;

[0054] A hydraulic station 5 is arranged at the upper end of the upper hanging plate 1, and the pipeline of the hydraulic station 5 runs through the upper hanging plate 1 and the lower hanging plate 3, and the pipeline of the hydraulic station 5 is connected to the hydraulic rock drill 11 located in the vertical shaft rock drilling work, the upper hanging plate 1 and the lower hanging plate 3 are arranged in parallel, and the turntable 6 at the bottom end of the lower hanging plate 3 is arranged in a vertical direction, and a turntable 6 is arranged at the lower end of the lower hanging plate 3, and a working connecting frame 7 is installed on the turntable at the output end of the turntable 6, and a return support bottom plate 8 is installed at the bottom end of the working connecting frame 7, and a rock drilling and grouting assembly is installed on the upper end surface of the support bottom plate 8, which is used for performing grouting while performing rock drilling construction in the vertical shaft, forming an integrated payment device;

[0055] The upper hanging tray 1 is penetrated by the protective turning platform 22, and the bottom end of the protective turning platform 22 is located in parallel with the lower hanging tray 3, and the upper end of the lower hanging tray 3 is provided with a guide ladder 23, and the guide ladder 23 is arranged in a spiral shape, and a positioning plate frame 24 is installed at the top of the guide ladder 23, and a slide groove rotatably connected to the protective turning platform 22 is arranged at the bottom of the positioning plate frame 24, and the protective turning platform 22 is set as a C-shaped dam structure, and the guide ladder 23 penetrates the upper hanging tray 1, and a parallel steering pedal platform is arranged at the place where the guide ladder 23 penetrates the upper hanging tray 1;

[0056] In conjunction with the accompanying drawings Figure 1-Figure 10As shown, when in use, the upper hanging plate 1 and the lower hanging plate 3 are connected through the pulling column 2 to keep the two parallel. The top of the pulling column 2 passes through the position of the upper hanging plate 1 and is connected to the external suspension and traction equipment, so that the height of the upper hanging plate 1 and the lower hanging plate 3 are linked with the external lifting equipment. The support work in the shaft provides corresponding work. The hanging plate stabilizing cylinder 4 located on both sides of the lower hanging plate 3 is started to insert the hanging plate stabilizing cylinder 4 into the inner wall part of the shaft after the equipment reaches the specified position height to maintain the stability of the device. The turntable 6 at the bottom end of the lower hanging plate 3 is an electrically driven large rotating platform equipment, which is used to drive the working connecting frame 7 and the supporting bottom plate 8 of the status plate to rotate. The protective turning platform 22 arranged between the upper hanging plate 1 and the lower hanging plate 3 is used to cooperate with the installation of the guide ladder 23, as shown in FIG. Figure 1-Figure 3 As shown, as the protection turning platform 22 is pushed and rotated at the bottom of the positioning plate frame 24, the opening direction of the protection turning platform 22 is adjusted, so that the staff can shuttle between the upper hanging plate 1 and the lower hanging plate 3 through the guide ladder 23 to install the internal structure and equipment. The top of the pulling column 2 and the positioning plate frame 24 provide traction, which is convenient for the lifting and lowering control of the device in the shaft, reducing the exposure time of personnel in dangerous environments, shortening the working time of personnel in the shaft, and reducing the risk of safety accidents.

[0057] The rock drilling and shotcrete assembly includes:

[0058] A main support beam 9 is installed above the support base plate 8, and the main support beam 9 and the telescopic cylinder 15 are arranged parallel to the bottom end of the drilling rig slide 10;

[0059] The drilling rig slide 10 is installed on the surface of the main support beam 9, and the drilling rig slide 10 is installed between the columns of the working connection frame 7. The drill rod guide 13 and the hydraulic pipe guide frame 14 at the upper end of the slideway of the drilling rig slide 10 are both positioned and installed by bolts;

[0060] A hydraulic rock drill 11, which is mounted on a slide of the drilling rig slide 10;

[0061] A rock drill rod 12, which is installed at the output end of the hydraulic rock drill 11, and the rock drill rod 12 is arranged parallel to the drilling rig slide 10;

[0062] A drill rod guide 13 is installed at one end of the drilling rig slide 10, and the drill rod 12 penetrates the drill rod guide 13. The drill rod guide 13 is composed of two U-shaped frames symmetrically engaged, and the hole-shaped structure formed by the two U-shaped frames of the drill rod guide 13 is provided with a bearing structure that rotates with the rock drilling rod 12;

[0063] A hydraulic pipe guide frame 14 is installed at the other end of the drilling rig slide 10. The hydraulic pipe guide frame 14 is composed of a U-shaped metal support and three rollers installed in a triangle, and the rollers rotating inside the hydraulic pipe guide frame 14 are in contact with the pipes of the hydraulic station 5;

[0064] A telescopic cylinder 15 is installed in the main support beam 9, and the telescopic cylinder 15 is connected to the bottom end of the drilling rig slide 10;

[0065] The carriage support beam 16 is installed at the bottom end of the main support beam 9, and a rotating support is provided at the connection between the bottom end of the carriage support beam 16 and the support bottom plate 8, and an adjusting compensation oil cylinder 21 is rotatably connected at the steel frame opening between the bottom end of the carriage support beam 16 and the support bottom plate 8, and the adjusting compensation oil cylinder 21 is arranged in an inclined shape;

[0066] A rocker 17 is installed at the bottom of the carriage support beam 16, and the rocker 17 is arranged at the bottom of the carriage support beam 16 near the rock drilling end of the rock drilling rod 12. The limiting metal clamps 18 are symmetrically installed on both sides of the rocker 17, and a grouting nozzle pipe 20 is placed in the opening of the limiting metal clamp 18. A positioning limiter 19 is sleeved on the surface of the limiting metal clamp 18, and the positioning limiter 19 is a double-layer rotatably connected annular structure, and one side of the positioning limiter 19 is against the surface of the grouting nozzle pipe 20;

[0067] In conjunction with the accompanying drawings Figure 1-Figure 10 As shown, the rock drilling and grouting assembly is installed between the working connection frame 7 installed on the turntable plate surface at the output end of the turntable 6 and the supporting bottom plate 8, as shown in FIG. Figure 1-Figure 4 As shown, when rock drilling is carried out, the externally connected crane or other traction equipment lifts the upper hanging plate 1 and the lower hanging plate 3 to the appropriate position, then starts the hanging plate stabilizing cylinder 4 to fix the hanging plate and maintain stability, and the compensation cylinder 21 is connected to the bottom end of the slide support beam 16. When in use, the slide support beam 16 rotates the support at the bottom end to support and adjust the angle of the rock drilling rod 12 during operation for compensation. The main support beam 9 located at the top of the slide support beam 16 provides installation assistance for the telescopic cylinder 15. When in use, the telescopic cylinder 15 drives the drilling rig slide 10 to move to cooperate with the rock drilling rod 12 to adjust the rock drilling working depth. The rock drilling rod 12 installed on the slide of the drilling rig slide 10 pushes the rock drilling rod 12 to the specified direction for rock drilling. The drill rod guide 13 located at the output end of the rock drilling rod 12, as shown in FIG. Figure 8As shown in the installation, the bearing structure located inside the drill rod guide 13 assists the rotation of the rock drilling rod 12 and guides the rock drilling depth. After the drilling of the rock drilling rod 12, the precise processing of the shaft position is achieved. When the vertical shaft is used for shotcrete operation, the externally connected crane and other traction equipment lift the upper hanging plate 1 and the lower hanging plate 3 to a suitable position, and then the hanging plate stabilizing cylinder 4 is started to fix the hanging plate to maintain stability. The support base plate 8 is rotated by the turntable 6 to adjust the angle of the whole. After the shotcrete nozzle pipe 20 is connected to the working shotcrete machine and started, the limiting metal clamps 18 on both sides of the rocker 17 drive the nozzle part of the shotcrete nozzle pipe 20 to operate, and the turntable 6 is controlled to rotate the shotcrete position. When the limiting metal clamp 18 clamps the shotcrete nozzle pipe 20, the sleeve in the opening of the limiting metal clamp 18 is set with the shotcrete nozzle pipe 20, and then the internal hole of the positioning limiter 19 is inserted into the surface of the limiting metal clamp 18, as shown in FIG. Figure 9-10 As shown, as the sealing ring and the damping ring inside the annular structure of the outer layer of the rotating positioning limiter 19 are clamped with the damping ring on the surface of the limiting metal clip 18, the positioning limiter 19 limits the position of the shotcrete nozzle pipe 20. After one circle of spraying is completed, the hanging plate stabilizing cylinder 4 is retracted and the hanging plate is lowered to the next position to continue spraying. During the spraying operation, the distance angle between the spraying nozzle pipe 20 and the rock surface is basically always within 75°, and the rebound amount of the shotcrete is controlled, thereby reducing the risk factor of the operation.

[0068] Working principle: When using the integrated rock drilling and grouting equipment of the shaft anchor spraying support, firstly, the upper hanging plate 1, the pulling column 2 and the lower hanging plate 3 form a double-layer payment frame structure, and the device is installed as a whole at the rock drilling position of the shaft construction through the hanging plate stabilizing cylinder 4. The protective turning platform 22 located between the upper hanging plate 1 and the lower hanging plate 3 rotates to adjust the opening position, so that the staff can enter the equipment through the guide ladder 23 for daily maintenance and inspection. The positioning plate frame 24 located at the top of the protective turning platform 22 and the guide ladder 23 is connected with the metal steel frame used for external support and the corresponding lifting hanger to provide traction protection for the work of the device. The turntable 6 is driven by the store to drive the turntable at the output end and the hydraulic rock drill 11 below to rotate and adjust the appropriate angle and direction to the vertical shaft drilling position for processing. The drill rod guide 13 guides the rock drilling drill rod 12 in the opposite direction, and the drilling rig slide 10 pushes the hydraulic rock drill 1 to the rock drilling depth of the shaft surface. 1 The work is refined. The carriage support beam 16 located at the bottom of the main support beam 9 assists in controlling the rock drilling angle under the adjustment of the compensating oil cylinder 21 to realize the rock drilling work. When the shotcrete operation is carried out, the height of the lifting device of the external lifting equipment of the hoisting plate stabilizing oil cylinder 4 is retracted so that the shotcrete nozzle pipe 20 reaches the working height. The hoisting plate stabilizing oil cylinder 4 is opened and rooted again. The turntable 6 is used to adjust the main range of shotcrete. The rocker 17 located at the bottom of the carriage support beam 16 drives the shotcrete nozzle pipe 20 clamped inside the limiting metal clamp 18 to provide shotcrete operations in different directions in the shaft under the rotation of the turntable 6. When the shotcrete nozzle pipe 20 is operating, the nozzle is basically always at a distance angle of less than 75° from the rock surface, and the shotcrete rebound amount is controlled. By assembling the rock drilling and shotcrete working equipment, the working rhythm of rock drilling and shotcrete is smooth, and the rebound amount generated by the shotcrete work is further controlled, thereby improving the working efficiency and reducing the labor intensity and working risk factor of the workers.

[0069] While the embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that many changes, modifications, substitutions and variations can be made to the embodiments without departing from the principles and spirit of the invention.

Claims

1. An integrated rock drilling and grouting equipment for vertical shaft bolting and spraying support, comprising: An upper hanging plate (1) is a metal plate-shaped structure placed in the vertical shaft, the lower end of the upper hanging plate (1) is connected to the lower hanging plate (3) via a pulling column (2), and hanging plate stabilizing cylinders (4) are symmetrically arranged on both sides of the lower hanging plate (3), constituting a main payment body structure installed in the vertical shaft rock drilling construction; The invention is characterized in that: a hydraulic station (5) is arranged at the upper end of the upper hanging plate (1), and the pipeline of the hydraulic station (5) passes through the upper hanging plate (1) and the lower hanging plate (3), and the pipeline of the hydraulic station (5) is connected to a hydraulic rock drill (11) located in the vertical shaft for rock drilling, a turntable (6) is arranged at the lower end of the lower hanging plate (3), and a working connecting frame (7) is installed on the turntable at the output end of the turntable (6), and a return support base plate (8) is installed at the bottom end of the working connecting frame (7), and a rock drilling and grouting assembly is installed on the upper end surface of the support base plate (8), which is used for performing grouting while performing rock drilling construction in the vertical shaft, thereby forming an integrated payment device; The upper hanging tray (1) is penetrated by the protective turning platform (22), and the bottom end of the protective turning platform (22) is located parallel to the lower hanging tray (3), the upper end of the lower hanging tray (3) is provided with a guide ladder (23), and the guide ladder (23) is spirally arranged, and a positioning plate frame (24) is installed at the top of the guide ladder (23), and the bottom end of the positioning plate frame (24) is provided with a slide groove rotatably connected to the protective turning platform (22), and the protective turning platform (22) is set as a C-shaped dam structure, the guide ladder (23) penetrates the upper hanging tray (1), and a parallel steering pedal platform is provided at the place where the guide ladder (23) penetrates the upper hanging tray (1).

2. The integrated rock drilling and grouting equipment for vertical shaft bolting and spraying support according to claim 1 is characterized in that: The upper hanging tray (1) and the lower hanging tray (3) are arranged in parallel, and the turntable (6) at the bottom end of the lower hanging tray (3) is arranged in a vertical direction.

3. The integrated rock drilling and grouting equipment for vertical shaft bolting and spraying support according to claim 1 is characterized in that: The rock drilling and grouting assembly comprises: A main support beam (9) mounted above the support base plate (8); A drilling rig slide (10), which is installed on the surface of the main support beam (9), and the drilling rig slide (10) is installed between the columns of the working connecting frame (7); A hydraulic rock drill (11) which is mounted on a slide of the drilling rig slide (10); A rock drilling rod (12) mounted at the output end of the hydraulic rock drill (11), and the rock drilling rod (12) is arranged in parallel with the drilling rig slide (10); A drill rod guide (13) is mounted on one end of the drilling rig slide (10), and the rock drilling rod (12) penetrates the interior of the drill rod guide (13); A hydraulic pipe guide frame (14) mounted on the other end of the drilling rig slide (10); A telescopic oil cylinder (15) is installed in the main support beam (9), and the telescopic oil cylinder (15) is connected to the bottom end of the drilling rig slide (10); A carriage support beam (16) is mounted on the bottom end of the main support beam (9), and a rotating support is provided at the connection between the bottom end of the carriage support beam (16) and the support bottom plate (8); A rocker (17) is mounted on the bottom end of the carriage support beam (16), and the rocker (17) is arranged on the bottom end of the carriage support beam (16) close to the rock drilling end of the rock drilling drill rod (12).

4. The integrated rock drilling and grouting equipment for vertical shaft bolting and spraying support according to claim 3 is characterized in that: The main support beam (9) and the telescopic oil cylinder (15) are arranged in parallel at the bottom end of the drilling rig slide (10).

5. The integrated rock drilling and grouting equipment for vertical shaft bolting and spraying support according to claim 3 is characterized in that: The drill rod guide (13) and the hydraulic pipe guide frame (14) at the upper end of the slideway of the drilling rig slide (10) are both positioned and installed by means of bolts.

6. The integrated rock drilling and grouting equipment for vertical shaft bolting and spraying support according to claim 3, characterized in that: The drill rod guide (13) is composed of two U-shaped frames symmetrically engaged, and a hole-shaped structure formed by the two U-shaped frames of the drill rod guide (13) is provided with a bearing structure that rotates with the rock drilling rod (12).

7. The integrated rock drilling and grouting equipment for vertical shaft bolting and spraying support according to claim 3 is characterized by: The hydraulic pipe guide frame (14) is composed of a U-shaped metal support and three roller rods installed in a triangular shape, and the roller rods rotating inside the hydraulic pipe guide frame (14) are in contact with the pipelines of the hydraulic station (5).

8. The integrated rock drilling and grouting equipment for vertical shaft bolting and spraying support according to claim 3, characterized in that: An adjusting and compensating oil cylinder (21) is rotatably connected between the bottom end of the slide support beam (16) and the steel frame opening of the supporting bottom plate (8), and the adjusting and compensating oil cylinder (21) is arranged in an inclined shape.

9. The integrated rock drilling and grouting equipment for vertical shaft bolting and spraying support according to claim 3, characterized in that: The two sides of the oscillator (17) are symmetrically mounted with limit metal clips (18), and a spray nozzle pipe (20) is placed in the opening of the limit metal clip (18).

10. The integrated rock drilling and grouting equipment for vertical shaft bolting and spraying support according to claim 9, characterized in that: The surface of the limiting metal clamp (18) is sleeved with a positioning stopper (19), and the positioning stopper (19) is a double-layer rotatably connected annular structure, and one side of the positioning stopper (19) abuts against the surface of the spray nozzle pipe (20).

Citation Information

Cited By

  • Oversized derrick fixing device for vertical shaft

    CN119957227A