Functional flow configuration method and device of electric power work project, computer equipment, readable storage medium and program product

By determining the promotion projects, incentive projects and reaching output methods of power operation projects and configuring their triggering processes, the problem of inaccurate flow charts caused by changes in functional processes is solved, and the accurate update of flow charts and improvement of user experience is achieved.

CN119515314AInactive Publication Date: 2025-02-25CHINA SOUTHERN POWER GRID INTERNET SERVICE CO LTD
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202411717509.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-11-27
Publication Date
2025-02-25
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

Changes in functional processes and system upgrades may lead to inaccurate information in the flowchart, and an effective update mechanism is required to ensure the accuracy of the flowchart.

Method used

By obtaining the target task set, target power operation projects, and the correlation rules of the target power operation projects and other historical projects, determine the promotion project, incentive project and reach the output methods, and configure the triggering process of the target power operation projects to achieve accurate update of the flow chart.

Benefits of technology

This method helps users quickly understand and operate the various functions and processes of the system, improves the accuracy and user experience of the flow chart, and ensures the safe and stable operation of the system.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119515314A_ABST
    Figure CN119515314A_ABST
Patent Text Reader

Abstract

The invention relates to a function flow configuration method, device and equipment of an electric power work project, a storage medium and a program product, and relates to the technical field of computers. By adopting the method, the accuracy of process configuration can be improved. The method comprises the following steps: determining a target task in a target task set and a preset target power operation project; according to the target task set, the target power operation project and an association rule of the target power operation project and other historical projects, determining a promotion project of the target power operation project; according to the target task set, the project information of the target electric power work project and the issuing and receiving condition of historical project resources, determining an excitation project of the target electric power work project; determining a touch output mode corresponding to the target electric power work project according to the project information of the target electric power work project and an association rule of historical project touch modes; and according to the target task, the promotion project, the excitation project and the touch output mode, configuring a trigger process of the target power operation project.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the field of computer technology, and in particular to a method, device, computer equipment, computer-readable storage medium and computer program product for configuring a functional process of an electric power operation project. Background Art

[0002] With the development of computer technology, the data analysis ability of computers has been improved. As a result, in the field of power operation projects, a technology has emerged in which the background maintains the pre-configured process information and the front end executes it. This technology is applied to all aspects of construction work in power operation projects.

[0003] However, changes in functional processes may cause inaccurate information in the flowchart. In addition, system upgrades and adjustments to business rules may affect the accuracy of the flowchart. Therefore, it is necessary to establish an effective update mechanism to update the flowchart in a timely manner according to system changes. Summary of the invention

[0004] Based on this, it is necessary to provide a functional process configuration method, device, computer equipment, computer-readable storage medium and computer program product for a power operation project in response to the above-mentioned technical problems.

[0005] In a first aspect, the present application provides a method for configuring a functional process of an electric power operation project, comprising:

[0006] Acquire a target task set determined according to the task tag information, determine the target task in the target task set, and determine a preset target power operation project;

[0007] Determine a promotion project for the target power operation project according to the target task set, the target power operation project, and a correlation rule between the target power operation project and other historical projects;

[0008] Determine the incentive project for the target power operation project according to the target task set, the project information of the target power operation project and the issuance and collection of historical project resources;

[0009] Determine the access output method corresponding to the target power operation project according to the correlation rule between the project information of the target power operation project and the access method of the historical project;

[0010] According to the target task, the promotion project, the incentive project and the contact output method, the triggering process of the target power operation project is configured.

[0011] In one embodiment, determining the target task in the target task set includes:

[0012] According to the task label information of each task in the target task set and the association rule between the target power operation project and the task label information, determine the multiple task indicator information corresponding to the target power operation project; analyze each task indicator information according to the historical indicator parameters corresponding to each task indicator information to obtain task subdivision indicator information; determine the target task in the target task set according to the task subdivision indicator information.

[0013] In one embodiment, determining the promotion project of the target power operation project according to the target task set, the target power operation project, and the association rule between the target power operation project and other historical projects includes:

[0014] Determine multiple candidate promotion projects based on the target task set, the target power operation project, and the correlation rules between the target power operation project and other historical projects; sort each of the candidate promotion projects according to the historical project parameters corresponding to each of the candidate promotion projects, and determine the promotion project for the target power operation project based on the sorted candidate promotion projects.

[0015] In one embodiment, determining the incentive project of the target power operation project according to the target task set, the project information of the target power operation project and the issuance and collection of historical project resources includes:

[0016] Determine multiple candidate incentive projects based on the target task set, the project information of the target power operation project and the issuance and collection of historical project resources; determine the incentive project of the target power operation project based on the historical project parameters corresponding to each of the candidate incentive projects.

[0017] In one embodiment, determining the access output method corresponding to the target power operation project according to the association rule between the project information of the target power operation project and the access method of the historical project includes:

[0018] Based on the association rules between the project information of the target power operation project and the historical project access methods, multiple candidate access output methods are determined; based on the historical project parameters corresponding to each of the candidate access output methods, the access output method corresponding to the target power operation project is determined.

[0019] In one embodiment, the method further comprises:

[0020] Obtain the associated project operation habits of each task in the target task set for the target power operation project; determine the target associated project and the contact information of the target associated project based on the statistical results of the associated project operation habits; and supplement the triggering process of the target power operation project based on the contact information of the target associated project.

[0021] In a second aspect, the present application also provides a functional process configuration device for an electric power operation project, comprising:

[0022] A task determination module is used to obtain a target task set determined according to task tag information, determine a target task in the target task set, and determine a preset target power operation project;

[0023] A first project module, for determining a promotion project for the target power operation project according to the target task set, the target power operation project, and a correlation rule between the target power operation project and other historical projects;

[0024] A second project module is used to determine the incentive project of the target power operation project according to the target task set, the project information of the target power operation project and the issuance and collection of historical project resources;

[0025] A method determination module, used to determine the access output method corresponding to the target power operation project according to the project information of the target power operation project and the association rule of the historical project access method;

[0026] A process configuration module is used to configure the triggering process of the target power operation project according to the target task, the promotion project, the incentive project and the contact output method.

[0027] In a third aspect, the present application further provides a computer device, including a memory and a processor, wherein the memory stores a computer program, and when the processor executes the computer program, the following steps are implemented:

[0028] Obtain a target task set determined according to task tag information, determine the target tasks in the target task set, and determine the preset target power operation project; determine the promotion project of the target power operation project according to the target task set, the target power operation project, and the association between the target power operation project and other historical projects; determine the incentive project of the target power operation project according to the target task set, the project information of the target power operation project and the issuance and collection of historical project resources; determine the access output method corresponding to the target power operation project according to the association between the project information of the target power operation project and the access method of historical projects; configure the trigger process of the target power operation project according to the target task, the promotion project, the incentive project and the access output method.

[0029] In a fourth aspect, the present application further provides a computer-readable storage medium having a computer program stored thereon, wherein when the computer program is executed by a processor, the following steps are implemented:

[0030] Obtain a target task set determined according to task tag information, determine the target tasks in the target task set, and determine the preset target power operation project; determine the promotion project of the target power operation project according to the target task set, the target power operation project, and the association between the target power operation project and other historical projects; determine the incentive project of the target power operation project according to the target task set, the project information of the target power operation project and the issuance and collection of historical project resources; determine the access output method corresponding to the target power operation project according to the association between the project information of the target power operation project and the access method of historical projects; configure the trigger process of the target power operation project according to the target task, the promotion project, the incentive project and the access output method.

[0031] In a fifth aspect, the present application further provides a computer program product, including a computer program, which implements the following steps when executed by a processor:

[0032] Obtain a target task set determined according to task tag information, determine the target tasks in the target task set, and determine the preset target power operation project; determine the promotion project of the target power operation project according to the target task set, the target power operation project, and the association between the target power operation project and other historical projects; determine the incentive project of the target power operation project according to the target task set, the project information of the target power operation project and the issuance and collection of historical project resources; determine the access output method corresponding to the target power operation project according to the association between the project information of the target power operation project and the access method of historical projects; configure the trigger process of the target power operation project according to the target task, the promotion project, the incentive project and the access output method.

[0033] The functional process configuration method, device, computer equipment, computer-readable storage medium and computer program product of the above-mentioned power operation project determine the promotion project of the target power operation project according to the target task set, the target power operation project, and the association law between the target power operation project and other historical projects; then determine the incentive project of the target power operation project according to the target task set, the project information of the target power operation project and the issuance and collection of historical project resources; then determine the corresponding contact output method of the target power operation project according to the association law of the project information of the target power operation project and the contact method of the historical project; finally, configure the trigger process of the target power operation project according to the target task, promotion project, incentive project and contact output method, so as to help users quickly understand and operate the various functions and processes of the system, and at the same time put forward clear requirements for the performance, operation and maintenance and fault handling of the system to ensure that users can use the flowchart function smoothly, and at the same time improve the accuracy of the flowchart. In summary, the solution helps users quickly understand and operate the various functions and processes of the system by providing a comprehensive and visual flowchart, improves work efficiency and user experience, and ensures the safe and stable operation of the system. BRIEF DESCRIPTION OF THE DRAWINGS

[0034] In order to more clearly illustrate the technical solutions in the embodiments of the present application or related technologies, the drawings required for use in the embodiments of the present application or related technical descriptions will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present application. For ordinary technicians in this field, other related drawings can be obtained based on these drawings without paying creative work.

[0035] FIG1 is an application environment diagram of a method for configuring a functional flow of an electric power operation project in one embodiment;

[0036] Figure 2A flowchart of a method for configuring a functional process of an electric power operation project in one embodiment;

[0037] Figure 3 A schematic diagram of a process for determining a target task in an embodiment;

[0038] Figure 4 A flowchart of a method for configuring a functional process of an electric power operation project in a specific embodiment;

[0039] Figure 5 A structural block diagram of a functional flow configuration device for an electric power operation project in one embodiment;

[0040] FIG. 6 is a diagram showing the internal structure of a computer device in one embodiment. DETAILED DESCRIPTION

[0041] In order to make the purpose, technical solution and advantages of the present application more clearly understood, the present application is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present application and are not used to limit the present application.

[0042] The functional process configuration method of the power operation project provided in the embodiment of the present application can be applied to the application environment shown in Figure 1. Among them, the terminal communicates with the server through the network. The data storage system can store data that the server needs to process. The data storage system can be integrated on the server, or it can be placed on the cloud or other network servers.

[0043] Specifically, the functional process configuration method of the power operation project provided in the embodiment of the present application can be executed by a server.

[0044] Exemplarily, the server obtains a target task set determined according to task tag information, determines the target tasks in the target task set, and determines a preset target power operation project; the server determines a promotion project for the target power operation project based on the target task set, the target power operation project, and the association between the target power operation project and other historical projects; the server determines an incentive project for the target power operation project based on the target task set, project information of the target power operation project, and the issuance and receipt of historical project resources; the server determines a corresponding access output method for the target power operation project based on the association between the project information of the target power operation project and the access methods of historical projects; the server configures the triggering process of the target power operation project based on the target task, promotion project, incentive project, and access output method.

[0045] In the application environment shown in FIG1 , the terminal may be, but is not limited to, various personal computers, notebook computers, smart phones, and tablet computers. The server may be implemented as an independent server or a server cluster consisting of multiple servers.

[0046] In one embodiment, Figure 2 As shown, a method for configuring a functional process of an electric power operation project is provided, and the method is applied to the server in FIG1 as an example for explanation, and includes the following steps:

[0047] Step S201, obtaining a target task set determined according to task tag information, determining a target task in the target task set, and determining a preset target power operation project.

[0048] The task tag information may be a tag or keyword attached to a task or item in task management, project management or a specific workflow to help classify, identify, sort or filter tasks.

[0049] Specifically, the server obtains a target task set determined according to the task tag information, determines the target task in the target task set, and determines a preset target power operation project according to a user instruction.

[0050] Step S202, determining a promotion project for the target power operation project according to the target task set, the target power operation project, and the association rule between the target power operation project and other historical projects.

[0051] Among them, promoting projects can be a series of measures or actions taken during project management and power construction operations to accelerate project progress, ensure the achievement of project goals and improve project efficiency.

[0052] Specifically, the server analyzes the association rules according to the target task set, the target power operation project, and the association rules between the target power operation project and other historical projects, and determines the promotion project of the target power operation project according to the analysis results.

[0053] Step S203, determining the incentive project of the target power operation project according to the target task set, the project information of the target power operation project and the issuance and collection of historical project resources.

[0054] Among them, an incentive program can be a program that promotes specific goals, behaviors or results through incentive mechanisms.

[0055] Specifically, the server analyzes the issuance and receipt of resources based on the target task set, project information of the target power operation project, and the issuance and receipt of historical project resources, and determines the incentive project for the target power operation project based on the analysis results.

[0056] Step S204, determining the access output method corresponding to the target power operation project according to the project information of the target power operation project and the association rule of the historical project access methods.

[0057] The output method may refer to a method of delivering analysis results or reports to relevant personnel in the power operation project.

[0058] Specifically, the server analyzes the correlation rules based on the project information of the target power operation project and the correlation rules of the historical project access methods, and determines the access output method corresponding to the target power operation project based on the analysis results.

[0059] Step S205, configuring the triggering process of the target power operation project according to the target task, promotion project, incentive project and contact output method.

[0060] Among them, the trigger process can automatically start or activate a series of preset actions or processes when a specific event or condition occurs. This process is usually used for automated operations, task scheduling or system response, with the aim of simplifying operations, improving efficiency and reducing human intervention.

[0061] Specifically, the server comprehensively considers various factors and configures the triggering process of the target power operation project according to the target tasks, promotion projects, incentive projects and contact output methods.

[0062] In the functional process configuration method of the above-mentioned power operation project, the promotion project of the target power operation project is determined according to the target task set, the target power operation project, and the association law between the target power operation project and other historical projects; then the incentive project of the target power operation project is determined according to the target task set, the project information of the target power operation project and the issuance and collection of historical project resources; then the corresponding contact output method of the target power operation project is determined according to the association law of the project information of the target power operation project and the contact method of the historical project; finally, according to the target task, promotion project, incentive project and contact output method, the trigger process of the target power operation project is configured, so as to help users quickly understand and operate the various functions and processes of the system, and at the same time put forward clear requirements for the performance, operation and maintenance and fault handling of the system to ensure that users can use the flowchart function smoothly, and at the same time improve the accuracy of the flowchart. In summary, the solution helps users quickly understand and operate the various functions and processes of the system by providing a comprehensive and visual flowchart, improves work efficiency and user experience, and ensures the safe and stable operation of the system.

[0063] In one embodiment, if Figure 3 As shown, in the above step S201, determining the target task in the target task set specifically includes the following steps:

[0064] Step S301, determining a plurality of task indicator information corresponding to a target power operation project according to the task label information of each task in the target task set and the association rule between the target power operation project and the task label information.

[0065] Step S302: Analyze each task indicator information according to the historical indicator parameters corresponding to each task indicator information to obtain task subdivision indicator information.

[0066] Step S303: determining a target task in a target task set according to the task subdivision indicator information.

[0067] Specifically, the server determines multiple task indicator information corresponding to the target power operation project based on the task label information of each task in the target task set and the association rules between the target power operation project and the task label information; then analyzes each task indicator information according to the historical indicator parameters corresponding to each task indicator information to obtain task subdivision indicator information; finally, determines the target task in the target task set based on the task subdivision indicator information, thereby scientifically and rationally determining the target task in the target task set.

[0068] In one embodiment, in the above step S202, determining the promotion project of the target power operation project according to the target task set, the target power operation project, and the association rule between the target power operation project and other historical projects specifically includes the following steps:

[0069] According to the target task set, the target power operation project, and the correlation rules between the target power operation project and other historical projects, multiple candidate promotion projects are determined; each candidate promotion project is sorted according to the historical project parameters corresponding to each candidate promotion project, and the promotion project of the target power operation project is determined based on the sorted candidate promotion projects.

[0070] Specifically, the server determines multiple candidate promotion projects based on the target task set, the target power operation project, and the correlation rules between the target power operation project and other historical projects; then sorts each candidate promotion project according to the historical project parameters corresponding to each candidate promotion project, and based on the sorted candidate promotion projects, determines the promotion project of the target power operation project according to preset screening conditions, thereby scientifically and rationally determining the promotion project of the target power operation project.

[0071] In one embodiment, in the above step S203, determining the incentive project of the target power operation project according to the target task set, the project information of the target power operation project and the issuance and collection of historical project resources specifically includes the following steps:

[0072] Based on the target task set, project information of the target power operation project and the issuance and collection of historical project resources, multiple candidate incentive projects are determined; then, based on the historical project parameters corresponding to each candidate incentive project, the incentive project for the target power operation project is determined.

[0073] Among them, historical project parameters can be various data and indicators used to describe or review the past status, performance and details of a project when managing or analyzing a project.

[0074] Specifically, the server determines multiple candidate incentive projects based on the target task set, project information of the target power operation project, and the issuance and receipt of historical project resources; determines the incentive project of the target power operation project based on the historical project parameters corresponding to each candidate incentive project, thereby scientifically and reasonably determining the incentive project of the target power operation project.

[0075] In one embodiment, in the above step S204, according to the project information of the target power operation project and the correlation rule of the historical project access methods, determining the access output method corresponding to the target power operation project specifically includes the following steps:

[0076] Based on the correlation between the project information of the target power operation project and the historical project access methods, multiple candidate access output methods are determined; based on the historical project parameters corresponding to each candidate access output method, the access output method corresponding to the target power operation project is determined.

[0077] Specifically, the server determines multiple candidate access output methods based on the project information of the target power operation project and the correlation rules between the historical project access methods; then determines the access output method corresponding to the target power operation project based on the historical project parameters corresponding to each candidate access output method, thereby comprehensively considering various factors and scientifically and rationally determining the access output method corresponding to the target power operation project.

[0078] In one embodiment, after configuring the triggering process of the target power operation project according to the target task, promotion project, incentive project and contact output mode, the method of the present application further includes the following steps:

[0079] Obtain the associated project operation habits of each task in the target task set for the target power operation project; determine the target associated project and the contact information of the target associated project based on the statistical results of the associated project operation habits; and supplement the triggering process of the target power operation project based on the contact information of the target associated project.

[0080] The contact information may be information about various contact points involved in the process of interacting with customers or users.

[0081] Specifically, the server obtains the associated project operation habits of each task in the target task set for the target power operation project, and then determines the target associated project and the contact information of the target associated project based on the statistical results of the associated project operation habits. Finally, based on the contact information of the target associated project, the triggering process of the target power operation project is supplemented, thereby increasing the flexibility and intelligence of the solution and helping to ensure the safe and stable operation of the system.

[0082] In one embodiment, Figure 4 As shown, a method for configuring a functional process of an electric power operation project in a specific embodiment is provided, which specifically includes the following steps:

[0083] Step S401, obtaining a target task set determined according to task label information, and determining multiple task indicator information corresponding to the target power operation project according to the task label information of each task in the target task set and the association rule between the target power operation project and the task label information.

[0084] Step S402, analyzing each task indicator information according to the historical indicator parameters corresponding to each task indicator information to obtain task subdivision indicator information; determining the target task in the target task set according to the task subdivision indicator information, and determining the preset target power operation project.

[0085] Step S403, determining multiple candidate promotion projects according to the target task set, the target power operation project, and the correlation rules between the target power operation project and other historical projects; sorting each candidate promotion project according to the historical project parameters corresponding to each candidate promotion project, and determining the promotion project for the target power operation project based on the sorted candidate promotion projects.

[0086] Step S404, determining multiple candidate incentive projects based on the target task set, project information of the target power operation project and the issuance and collection of historical project resources; determining the incentive project of the target power operation project based on the historical project parameters corresponding to each candidate incentive project.

[0087] Step S405, determine multiple candidate access output methods based on the project information of the target power operation project and the correlation rules between historical project access methods; determine the access output method corresponding to the target power operation project based on the historical project parameters corresponding to each candidate access output method.

[0088] Step S406, configuring the triggering process of the target power operation project according to the target task, promotion project, incentive project and contact output method.

[0089] The beneficial effects brought by the above embodiments are as follows:

[0090] This solution can help users quickly understand and operate the various functions and processes of the system, and at the same time puts forward clear requirements for the system's performance, operation and maintenance, and troubleshooting to ensure that users can use the flowchart function smoothly, while also improving the accuracy of the flowchart.

[0091] It should be understood that, although the various steps in the flowcharts involved in the above-mentioned embodiments are displayed in sequence according to the indication of the arrows, these steps are not necessarily executed in sequence according to the order indicated by the arrows. Unless there is a clear explanation in this article, the execution of these steps does not have a strict order restriction, and these steps can be executed in other orders. Moreover, at least a part of the steps in the flowcharts involved in the above-mentioned embodiments can include multiple steps or multiple stages, and these steps or stages are not necessarily executed at the same time, but can be executed at different times, and the execution order of these steps or stages is not necessarily to be carried out in sequence, but can be executed in turn or alternately with other steps or at least a part of the steps or stages in other steps.

[0092] Based on the same inventive concept, the embodiment of the present application also provides a functional flow configuration device for an electric power operation project for implementing the functional flow configuration method of the electric power operation project involved above. The implementation scheme for solving the problem provided by the device is similar to the implementation scheme recorded in the above method, so the specific limitations in the embodiments of the functional flow configuration device for one or more electric power operation projects provided below can refer to the limitations of the functional flow configuration method for electric power operation projects above, and will not be repeated here.

[0093] In an exemplary embodiment, Figure 5 As shown, a functional process configuration device for an electric power operation project is provided, comprising:

[0094] The task determination module 501 is used to obtain a target task set determined according to the task tag information, determine the target task in the target task set, and determine a preset target power operation project;

[0095] The first project module 502 is used to determine a promotion project for the target power operation project according to the target task set, the target power operation project, and the association law between the target power operation project and other historical projects;

[0096] The second project module 503 is used to determine the incentive project of the target power operation project according to the target task set, the project information of the target power operation project and the distribution and collection of historical project resources;

[0097] A method determination module 504 is used to determine the access output method corresponding to the target power operation project according to the project information of the target power operation project and the association rule of the historical project access methods;

[0098] The process configuration module 505 is used to configure the triggering process of the target power operation project according to the target task, promotion project, incentive project and contact output method.

[0099] In one embodiment, the task determination module 501 is also used to determine multiple task indicator information corresponding to the target power operation project based on the task label information of each task in the target task set, and the association law between the target power operation project and the task label information; analyze each task indicator information according to the historical indicator parameters corresponding to each task indicator information to obtain task subdivision indicator information; and determine the target task in the target task set based on the task subdivision indicator information.

[0100] In one embodiment, the first project module 502 is also used to determine multiple candidate promotion projects based on the target task set, the target power operation project, and the correlation rules between the target power operation project and other historical projects; sort each candidate promotion project according to the historical project parameters corresponding to each candidate promotion project, and determine the promotion project of the target power operation project based on the sorted candidate promotion projects.

[0101] In one embodiment, the second project module 503 is also used to determine multiple candidate incentive projects based on the target task set, project information of the target power operation project and the issuance and receipt of historical project resources; and determine the incentive project of the target power operation project based on the historical project parameters corresponding to each candidate incentive project.

[0102] In one embodiment, the method determination module 504 is also used to determine multiple candidate contact output methods based on the project information of the target power operation project and the correlation rules of the historical project contact methods; and determine the contact output method corresponding to the target power operation project based on the historical project parameters corresponding to each candidate contact output method.

[0103] In one embodiment, the functional process configuration device of the power operation project also includes a process supplement module, which is used to obtain the associated project operation habits of each task in the target task set for the target power operation project; determine the target associated project and the contact information of the target associated project based on the statistical results of the associated project operation habits; and supplement the trigger process of the target power operation project based on the contact information of the target associated project.

[0104] Each module in the functional process configuration device of the above-mentioned power operation project can be implemented in whole or in part by software, hardware and a combination thereof. The above-mentioned modules can be embedded in or independent of the processor in the computer device in the form of hardware, or can be stored in the memory of the computer device in the form of software, so that the processor can call and execute the operations corresponding to the above-mentioned modules.

[0105] In an exemplary embodiment, a computer device is provided, which may be a server, and its internal structure diagram may be shown in FIG6. The computer device includes a processor, a memory, an input / output interface (Input / Output, referred to as I / O) and a communication interface. The processor, the memory and the input / output interface are connected via a system bus, and the communication interface is connected to the system bus via the input / output interface. The processor of the computer device is used to provide computing and control capabilities. The memory of the computer device includes a non-volatile storage medium and an internal memory. The non-volatile storage medium stores an operating system, a computer program and a database. The internal memory provides an environment for the operation of the operating system and the computer program in the non-volatile storage medium. The input / output interface of the computer device is used to exchange information between the processor and an external device. The communication interface of the computer device is used to communicate with an external terminal through a network connection. When the computer program is executed by the processor, a functional process configuration method for an electric power operation project is implemented.

[0106] Those skilled in the art will understand that the structure shown in FIG. 6 is merely a block diagram of a partial structure related to the solution of the present application, and does not constitute a limitation on the computer device to which the solution of the present application is applied. The specific computer device may include more or fewer components than shown in the figure, or combine certain components, or have a different arrangement of components.

[0107] In one embodiment, a computer device is further provided, including a memory and a processor, wherein a computer program is stored in the memory, and the processor implements the steps in the above method embodiments when executing the computer program.

[0108] In one embodiment, a computer-readable storage medium is provided, on which a computer program is stored. When the computer program is executed by a processor, the steps in the above-mentioned method embodiments are implemented.

[0109] In one embodiment, a computer program product is provided, including a computer program, which implements the steps in the above method embodiments when executed by a processor.

[0110] It should be noted that the user information (including but not limited to user device information, user personal information, etc.) and data (including but not limited to data used for analysis, stored data, displayed data, etc.) involved in this application are all information and data authorized by the user or fully authorized by all parties, and the collection, use and processing of relevant data must comply with relevant regulations.

[0111] A person of ordinary skill in the art can understand that all or part of the processes in the above-mentioned embodiment method can be completed by instructing the relevant hardware through a computer program, and the computer program can be stored in a non-volatile computer-readable storage medium. When the computer program is executed, it can include the processes of the embodiments of the above-mentioned methods. Among them, any reference to the memory, database or other medium used in the embodiments provided in the present application can include at least one of non-volatile memory and volatile memory. Non-volatile memory can include read-only memory (ROM), magnetic tape, floppy disk, flash memory, optical memory, high-density embedded non-volatile memory, resistive random access memory (ReRAM), magnetic random access memory (MRAM), ferroelectric random access memory (FRAM), phase change memory (PCM), graphene memory, etc. Volatile memory can include random access memory (RAM) or external cache memory, etc. As an illustration and not limitation, RAM can be in various forms, such as static random access memory (SRAM) or dynamic random access memory (DRAM). The database involved in each embodiment provided in this application may include at least one of a relational database and a non-relational database. Non-relational databases may include distributed databases based on blockchains, etc., but are not limited to this. The processor involved in each embodiment provided in this application may be a general-purpose processor, a central processing unit, a graphics processor, a digital signal processor, a programmable logic device, a data processing logic device based on quantum computing, an artificial intelligence (AI) processor, etc., but are not limited to this.

[0112] The technical features of the above embodiments may be combined arbitrarily. To make the description concise, not all possible combinations of the technical features in the above embodiments are described. However, as long as there is no contradiction in the combination of these technical features, they should be considered to be within the scope of this application.

[0113] The above-described embodiments only express several implementation methods of the present application, and the descriptions thereof are relatively specific and detailed, but they cannot be construed as limiting the scope of the present application. It should be noted that, for a person of ordinary skill in the art, several modifications and improvements can be made without departing from the concept of the present application, and these all belong to the protection scope of the present application. Therefore, the protection scope of the present application shall be subject to the attached claims.

Claims

1. A method for configuring a functional process of an electric power operation project, characterized in that: The method comprises: Acquire a target task set determined according to the task tag information, determine the target task in the target task set, and determine a preset target power operation project; Determine a promotion project for the target power operation project according to the target task set, the target power operation project, and a correlation rule between the target power operation project and other historical projects; Determine the incentive project for the target power operation project according to the target task set, the project information of the target power operation project and the issuance and collection of historical project resources; Determine the access output method corresponding to the target power operation project according to the correlation rule between the project information of the target power operation project and the access method of the historical project; According to the target task, the promotion project, the incentive project and the contact output method, the triggering process of the target power operation project is configured.

2. The method according to claim 1, characterized in that: The determining of the target task in the target task set includes: Determine a plurality of task indicator information corresponding to the target power operation project according to the task label information of each task in the target task set and the association rule between the target power operation project and the task label information; Analyze each of the task indicator information according to the historical indicator parameters corresponding to each of the task indicator information to obtain task subdivision indicator information; The target task is determined in the target task set according to the task segmentation indicator information.

3. The method according to claim 1, characterized in that: The step of determining the promotion project of the target power operation project according to the target task set, the target power operation project, and the association rule between the target power operation project and other historical projects includes: Determine a plurality of candidate promotion projects according to the target task set, the target power operation project, and the association rule between the target power operation project and other historical projects; The candidate promotion projects are sorted according to the historical project parameters corresponding to each of the candidate promotion projects, and the promotion project of the target power operation project is determined based on the sorted candidate promotion projects.

4. The method according to claim 1, characterized in that: The step of determining the incentive project for the target power operation project according to the target task set, the project information of the target power operation project and the issuance and collection of historical project resources includes: Determine a plurality of candidate incentive projects according to the target task set, the project information of the target power operation project and the issuance and collection of historical project resources; An incentive project for the target power operation project is determined according to the historical project parameters corresponding to each of the candidate incentive projects.

5. The method according to claim 1, characterized in that The determining, according to the association rule between the project information of the target power operation project and the historical project access mode, the access output mode corresponding to the target power operation project includes: Determine multiple candidate access output methods according to the project information of the target power operation project and the association rule of the historical project access methods; According to the historical project parameters corresponding to each of the candidate reach output methods, the reach output method corresponding to the target power operation project is determined.

6. The method according to any one of claims 1 to 5, characterized in that: The method further comprises: Acquire the associated project operation habits of each task in the target task set for the target power operation project; Determining a target associated item and touch point information of the target associated item according to the statistical results of the associated item operation habits; The triggering process of the target power operation project is supplemented according to the contact information of the target associated project.

7. A functional process configuration device for an electric power operation project, characterized in that: The device comprises: A task determination module is used to obtain a target task set determined according to task tag information, determine a target task in the target task set, and determine a preset target power operation project; A first project module, for determining a promotion project for the target power operation project according to the target task set, the target power operation project, and a correlation rule between the target power operation project and other historical projects; A second project module is used to determine the incentive project of the target power operation project according to the target task set, the project information of the target power operation project and the issuance and collection of historical project resources; A method determination module, used to determine the access output method corresponding to the target power operation project according to the project information of the target power operation project and the association rule of the historical project access methods; A process configuration module is used to configure the triggering process of the target power operation project according to the target task, the promotion project, the incentive project and the contact output method.

8. A computer device comprising a memory and a processor, wherein the memory stores a computer program, wherein: When the processor executes the computer program, the steps of the method according to any one of claims 1 to 6 are implemented.

9. A computer-readable storage medium having a computer program stored thereon, characterized in that: When the computer program is executed by a processor, the steps of the method according to any one of claims 1 to 6 are implemented.

10. A computer program product, comprising a computer program, characterized in that When the computer program is executed by a processor, the steps of the method according to any one of claims 1 to 6 are implemented.