Substation engineering intelligent construction site system cost listing method
By studying and formulating the cost calculation method for the substation engineering smart construction site system, the problem of unscientific and unreasonable smart construction site expenses in the existing technology has been solved, scientific expenditure and reasonable expenditures have been realized, operation and implementation have been standardized, and cost controllability has been improved.
Patent Information
- Application Number
- CN202411604131.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-11-11
- Publication Date
- 2025-03-04
AI Technical Summary
The existing technology lacks a systematic standard for calculating smart construction site expenses, which makes the power grid smart construction site expenses unscientific, unreasonable, and difficult to standardize.
By studying the cost range, cost calculation method and cost standards of substation engineering smart construction site system, a method for cost calculation of substation engineering smart construction site system is provided, including obtaining construction project documents, determining the cost range, calculating module costs, computing equipment supporting and operation and maintenance costs, and summarizing various types of expenses to obtain comprehensive expenses.
The scientific expenditure of smart construction site has been achieved, reasonable expenditures and reasonable operational standardization, and unified cost calculation guidance has been formed, which has improved the scientificity and rationality of expenses, and ensured that the cost of smart construction site is controllable under large-scale power grid construction.
Smart Images

Figure CN119556932A_ABST
Abstract
Description
Technical Field
[0001] The present invention belongs to the technical field of cost accounting for smart construction site systems, and specifically relates to a method for cost accounting for smart construction site systems for substation projects. Background Art
[0002] "Substation smart site system" refers to the installation of fixed or mobile information collection equipment and other software and hardware systems at the construction site of a new substation project, which comprehensively and in real time records the entry and exit information of personnel, vehicles, important tools and tools at the construction site, and the location information of personnel in important construction areas, and shares the relevant data information with infrastructure management departments at all levels through the infrastructure management system. At present, relevant technical standards have been promoted in an orderly manner, but there is still a lack of systematic results on the cost calculation standards for smart construction sites. Therefore, in order to further promote the smooth implementation of related work on power grid smart construction sites, standardize the calculation of related costs, and form standardized results, a method for calculating the costs of smart construction site systems for substation projects has been formed. Summary of the invention
[0003] The purpose of the present invention is to provide a method for calculating the costs of a smart construction site system for a substation project in order to solve the above-mentioned problems. According to the relevant design standards and technical standards of the smart construction site system for the substation project, the cost scope, cost calculation method, cost standard and other contents of the smart construction site system for the substation project are studied to form a method for calculating the costs of a smart construction site system for the substation project, so as to achieve scientific listing of smart construction site costs, reasonable expenditures, and reasonable and standardized operation, thereby solving the problems mentioned in the background technology.
[0004] In order to solve the above problems, the present invention provides a technical solution:
[0005] A method for calculating costs of a smart construction site system for a substation project, comprising the following steps:
[0006] S1. Obtain construction project documents and determine the cost scope of the smart construction site system for the new substation project;
[0007] S2. Obtain the module cost index of the smart construction site system project and calculate the cost based on the equipment usage;
[0008] S3. Calculate equipment support and operation and maintenance costs according to the construction budget standard;
[0009] S4. Calculate the cost of each cost category, summarize the costs of each cost category, and obtain the comprehensive cost of the smart construction site system of the substation project.
[0010] Preferably, the system cost range includes monitoring, identification, safety tools, machinery and instruments costs.
[0011] Preferably, the module cost indicators include equipment fees, installation and commissioning fees, supporting civil engineering fees, technical support fees and other fees.
[0012] Preferably, the equipment is used in two ways: purchasing and leasing;
[0013] The calculation formula for the rental equipment usage fee is as follows:
[0014]
[0015] Preferably, the other costs include daily operation and maintenance costs of the smart construction site system, later system dismantling and warehousing costs, and software costs.
[0016] Preferably, the software fee is calculated based on the number of developers and their unit price.
[0017] Preferably, the installation and commissioning fee includes on-site installation, commissioning, on-site wiring, installation of positioning antennas and positioning terminals, and adjustment of wiring of the smart construction site system.
[0018] The beneficial effects of the present invention are:
[0019] 1. Standardize engineering pricing behavior. Combined with the actual engineering project situation of the smart construction site of the substation project, standardize engineering pricing behavior, provide effective support for practitioners, reasonably determine the engineering cost, and provide a pricing basis for the construction of smart construction sites.
[0020] 2. Unified cost accounting guidance can be formed to provide a basis for the reasonable control of smart construction site costs, provide a normative basis for comprehensively improving the scientific nature of smart construction site costs and the rationality of expenditures, and comprehensively strengthen the controllable and under-control level of smart construction site costs under large-scale power grid construction, so as to achieve scientific cost listing, reasonable expenditure, and reasonable and standardized operation of smart construction site costs. BRIEF DESCRIPTION OF THE DRAWINGS
[0021] For ease of explanation, the present invention is described in detail with reference to the following specific implementations and the accompanying drawings.
[0022] Figure 1 It is a connection diagram of the smart construction site system of the present invention;
[0023] Figure 2 It is a schematic diagram of the smart construction site system of the present invention. DETAILED DESCRIPTION
[0024] like Figure 1-2 As shown, the specific implementation adopts the following technical solutions:
[0025] Example:
[0026] A method for calculating costs of a smart construction site system for a substation project, comprising the following steps:
[0027] S1. Obtain construction project documents and determine the cost scope of the smart construction site system for the new substation project;
[0028] S2. Obtain the module cost index of the smart construction site system project and calculate the cost based on the equipment usage;
[0029] S3. Calculate equipment support and operation and maintenance costs according to the construction budget standard;
[0030] S4. Calculate the cost of each cost category, summarize the costs of each cost category, and obtain the comprehensive cost of the smart construction site system of the substation project.
[0031] Among them, the system costs include monitoring, identification, safety tools, machinery and instruments.
[0032] Among them, module cost indicators include equipment fees, installation and commissioning fees, supporting civil engineering fees, technical support fees and other fees.
[0033] Among them, the equipment use methods are divided into purchase and leasing;
[0034] The calculation formula for rental equipment usage fee is as follows:
[0035]
[0036] Among them, other costs include daily operation and maintenance costs of the smart construction site system, later dismantling and storage costs of the system, and software costs.
[0037] Among them, the software cost is calculated based on the number of developers and the unit price of each person.
[0038] Among them, the installation and debugging fees include the on-site installation, debugging, on-site wiring, installation and adjustment of wiring of positioning antennas and positioning terminals of the smart construction site system.
[0039] Specific:
[0040] The cost of the smart site system for substation projects includes the purchase (amortization) or leasing of corresponding equipment, installation and commissioning, supporting civil engineering, technical support, operation and maintenance, and subsequent disposal. Among them, the equipment usage fee is calculated according to the amortization principle by comprehensively considering factors such as equipment depreciation, residual value recovery, and project construction cycle. If it is obtained through leasing, the hardware cost is determined by multiplying the leasing unit price by the leasing period;
[0041] The cost of the smart construction site system for the new substation project includes monitoring, identification, safety tools and machinery, instruments, etc. The system costs are amortized based on the current market price of the equipment;
[0042] The module cost index includes the costs of equipment purchase (amortization) or leasing, installation and commissioning, supporting civil engineering, technical support, operation and maintenance, and subsequent disposal. The calculation formula is as follows:
[0043] Hardware costs:
[0044] Smart site cost (obtained through purchase) = equipment cost + material cost + installation and commissioning, demolition cost + construction cost + operation and maintenance service fee;
[0045] Equipment Fee:
[0046] The equipment price level is determined by issuing survey forms, inviting experienced suppliers to quote and calculating the average price after tax. At the same time, the average life method is used to calculate depreciation. According to the "Implementation Regulations of the Enterprise Income Tax Law of the People's Republic of China", the minimum depreciation period of electronic equipment is 3 years (after investigation, the average depreciation period of most electronic equipment is 3-5 years, so this study selects the average depreciation period of 4 years), and considers 5% of the residual value to amortize the equipment;
[0047]
[0048] Among them, the "purchase price" includes 0.7% unloading storage fee; "use time" is determined according to the construction period, use time = construction period (month) * 30;
[0049] Among them, the material cost, on-site installation and commissioning fee (including equipment secondary transfer fee), equipment later removal fee and supporting construction engineering fee of the smart construction site management system are calculated based on the actual survey data and in combination with the "Regulations on the Preparation and Calculation of Power Grid Engineering Construction Budget (2018 Edition)";
[0050] The operation and maintenance service fee refers to the daily operation and maintenance fee of the hardware of the smart construction site management system, which is determined by combining the data reported by experts and manufacturers after issuing the survey form and taking the average value;
[0051] The number of developers invested in the smart construction site system software costs was obtained through investigation, and the unit price level of personnel was referred to the "Notice of State Grid Corporation of China on Printing Workload Measurement Specifications and Application Guidelines for Power Grid Digitalization Projects" (State Grid Interconnection
[2020] No. 606). Finally, the costs of each of the above cost categories were summarized to obtain the comprehensive cost of the smart construction site system for the substation project.
[0052] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. A method for calculating costs of a smart construction site system for a substation project, characterized in that: The following steps are involved: S1. Obtain construction project documents and determine the cost scope of the smart construction site system for the new substation project; S2. Obtain the module cost index of the smart construction site system project and calculate the cost based on the equipment usage; S3. Calculate equipment support and operation and maintenance costs according to the construction budget standard; S4. Calculate the cost of each cost category, summarize the costs of each cost category, and obtain the comprehensive cost of the smart construction site system of the substation project.
2. A method for calculating costs of a smart construction site system for a substation project according to claim 1, characterized in that: The system costs include monitoring, identification, safety tools, machinery and instruments.
3. A method for calculating costs of a smart construction site system for a substation project according to claim 1, characterized in that: The module cost indicators include equipment fees, installation and commissioning fees, supporting civil engineering fees, technical support fees and other fees.
4. A method for calculating costs of a smart construction site system for a substation project according to claim 1, characterized in that: The equipment usage methods are divided into purchase method and lease method; The calculation formula for the rental equipment usage fee is as follows:
5. A method for calculating costs of a smart construction site system for a substation project according to claim 3, characterized in that: The other costs mentioned include daily operation and maintenance costs of the smart construction site system, subsequent dismantling and storage costs of the system, and software costs.
6. A method for calculating costs of a smart construction site system for a substation project according to claim 5, characterized in that: The software fee is calculated based on the number of developers and their unit price.
7. A method for calculating costs of a smart construction site system for a substation project according to claim 3, characterized in that: The installation and debugging fees include the on-site installation, debugging, on-site wiring, installation and adjustment of the positioning antenna and positioning terminal of the smart construction site system.