Offshore wind power mooring system and mooring method
By using the first and second elastic cables in offshore wind power equipment, combined with inclination monitoring and preload adjustment mechanisms, the problem of tilt and vibration of offshore wind power equipment in harsh environments is solved, achieving higher stability and safety.
Patent Information
- Application Number
- CN202411636318.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-11-15
- Publication Date
- 2025-03-07
AI Technical Summary
It is difficult for existing offshore wind power equipment to effectively control the tilt of floating platforms in harsh marine environments, resulting in increased vibration of wind turbines and equipment damage, and the existing mooring system lacks a multi-platform coordination mechanism.
The first elastic cable and the second elastic cable are adopted, combined with the inclination monitoring system and the preload adjustment mechanism, and connect the floating platform, tower and ground anchor to monitor and adjust the preload force of the elastic cable in real time to reduce the inclination of the floating platform and the vibration of the wind turbine.
It effectively reduces the inclination of the floating platform in wind and waves, improves the stability of the wind turbine, avoids equipment damage, and enhances the stability of the entire wind farm through multi-point support and rebound force management.
Smart Images

Figure CN119568343A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of offshore wind power generation, and in particular to an offshore wind power mooring system and a mooring method. Background Art
[0002] As the global demand for renewable energy increases, offshore wind power has been widely used and developed as a clean and efficient form of energy. Offshore wind power equipment usually carries wind turbines on floating platforms, and connects the floating platforms to the seabed through cables and anchors to form a stable working platform. Offshore water electrolysis hydrogen production equipment is powered by wind power equipment on it, further improving energy efficiency and environmental protection performance.
[0003] Although offshore wind power equipment has made significant technological progress, it still faces some challenges in practical application, especially in harsh marine environments. Strong winds and waves at sea often cause the floating platform to tilt, which poses a serious threat to the stability and safety of wind power equipment. Existing solutions mainly focus on improving the buoyancy structure of the floating platform to improve its ability to resist tilting. However, due to the high center of gravity of the tower and blades supported on the top of the floating platform, the buoyancy structure of the floating platform alone cannot fully meet the requirements of resisting tilting, and there are mainly the following defects: 1. Although the existing floating platform design has improved its anti-tilting ability to a certain extent, it is still difficult to fully control the tilting of the platform in strong winds and waves due to the high center of gravity of the tower and blades; 2. When the platform of the traditional mooring system tilts, the resilience provided by the elastic cable may be too large, causing the vibration of the wind turbine to intensify and even damage the equipment; 3. In a wind farm composed of multiple floating platforms, the inclination of a single platform may affect the stability of the entire wind farm, and the existing mooring system lacks an effective multi-platform coordination mechanism. Summary of the invention
[0004] In view of the technical problems existing in the background technology, the present invention provides an offshore wind power mooring system and a mooring method; the system effectively improves the anti-tilt ability of the floating platform and the stability of the wind turbine by introducing a first elastic cable and a second elastic cable, as well as related monitoring and adjustment mechanisms. In order to solve the above technical problems, the present invention adopts the following technical solutions to achieve: An offshore wind power mooring system comprises a floating platform, a tower, a wind turbine and a ground anchor, wherein the lower end of the tower is vertically arranged at the center of the floating platform, the wind turbine is arranged on the upper end of the tower, a plurality of ground anchors are arranged on the seabed around the floating platform, a first elastic cable, a second elastic cable and a safety rope are connected between the tower, the floating platform and the ground anchor, and a tilt monitoring system is arranged on the first elastic cable, the second elastic cable and the ground anchor; One end of the first elastic cable is connected to a first bottom end point on the floating platform, and the other end of the first elastic cable is connected to a first side wall point on the tower, the first elastic cable passes through at least one ground anchor, and the first elastic cable is in an elastic tension state after being connected; One end of the second elastic cable is connected to the second bottom end point on the floating platform, and the other end of the second elastic cable is connected to the second side wall point on the tower, the second elastic cable passes through at least one ground anchor, and the second elastic cable is in an elastic tension state after being connected; The first bottom end point, the first side wall point and at least one ground anchor are all located on one side of the floating platform, and the second bottom end point, the second side wall point and at least one ground anchor are all located on the other side of the floating platform.
[0005] In a preferred solution, the tilt monitoring system includes a displacement sensor and a strain sensor sheet; the displacement sensor is arranged on the ground anchor, and the strain sensor sheet is arranged on the first elastic cable and the second elastic cable.
[0006] In a preferred solution, a third elastic cable is provided between adjacent floating platforms and ground anchors, one end of the third elastic cable is connected to the bottom of the floating platform, and the other end of the third elastic cable is connected to the bottom of another adjacent floating platform. The third elastic cable passes through at least one ground anchor, and the third elastic cable is in an elastically taut state after being connected.
[0007] In a preferred solution, a fourth elastic cable is provided between adjacent floating platforms, one end of the fourth elastic cable is connected to the top-view endpoint of the floating platform, and the other end of the fourth elastic cable is connected to the same top-view endpoint of another adjacent floating platform, and the fourth elastic cable passes through at least one ground anchor, and the ground anchors are both far away from the positions of the two end points; the floating platform is triangular in a top view, and the connection points of the fourth elastic cables are all vertices of the triangle.
[0008] In a preferred solution, a safety cable is connected between the floating platform and the ground anchor, and the connection point of the safety cable is the same as the connection point of the first elastic cable and the second elastic cable.
[0009] In a preferred solution, detection cables are connected between adjacent towers, and detection slip rings are sleeved on the detection cables. The detection slip rings slide along the detection cables in a limited manner.
[0010] A mooring method for an offshore wind power mooring system, the method comprising the following steps: S1. elastically tensioning and connecting the first elastic cable and the second elastic cable between the floating platform and the tower; S2, providing a displacement sensor on the ground anchor to detect the displacement distance of the first elastic cable or the second elastic cable relative to the ground anchor; S3, attaching a strain sensor sheet on the first elastic cable or the second elastic cable to detect the elastic elongation of the elastic cable; S4, real-time monitoring of the displacement and elongation of the elastic cable, recording the data and transmitting it to a data processing unit, and the data processing unit calculates the real-time tilt angle of the floating platform according to the monitoring data; S5. According to the calculated tilt angle, adjust the preload force of the first elastic cable and the second elastic cable to minimize the tilt angle and displacement of the floating platform; S6. When the wind turbine equipment tilts to one side, the corresponding elastic cable is pulled, and one end of the elastic cable pulls the side wall point through the rebound force to prevent the tower from tilting too much and overturning; the elastic cable pulls the cable length close to the bottom end point to the side of the tower, releasing the rebound force to a certain extent to prevent the tower from vibrating too much.
[0011] In the preferred solution, in S4, the real-time tilt angle calculation method of the floating platform is as follows: 8.1. Collect data of the tilt monitoring system, including the displacement distance of the first elastic cable and the second elastic cable relative to the anchor detected by the displacement sensor, and the elastic elongation of the elastic cable detected by the strain gauge; 8.2. Determine the displacement distances d1 and d2 of the first elastic cable and the second elastic cable relative to the ground anchor according to the data of the displacement sensor; 8.3. Determine the elastic elongation △L1 and △L2 of the first elastic cable and the second elastic cable according to the data of the strain gauge; 8.4. Calculate the actual length change of the elastic cable L1 = L 01 +△L1 and L2 = L 02 +△L2; Where: L 01 and L 02 is the initial length of the elastic cable; 8.5. Calculate the inclination angle of the floating platform based on the geometric relationship ; Set the width of the floating platform to W and the height to H Calculate the tilt angle The tangent value of : ; Calculate the tilt angle : ; 8.6. The data processing unit calculates the tilt angle Stored together with other monitoring data and displayed in real time.
[0012] In a preferred solution, in S5, the preload force of the first elastic cable and the second elastic cable is adjusted as follows: 9.1. Calculate the real-time tilt angle of the floating platform based on the data collected in S4; 9.2. Regularly evaluate the performance of the mooring system, including the maximum displacement and maximum tilt angle of the floating platform; determine whether the preload of the elastic cable needs to be adjusted based on the evaluation results. 9.3. If the preload force needs to be adjusted, the preload force of the first elastic cable and the second elastic cable is adjusted manually or automatically; During manual adjustment, the operator uses a tensioning tool to adjust the preload of the elastic cable based on the tilt angle information provided by the data processing unit; During automatic adjustment, the preload force adjustment device is used to automatically adjust the preload force of the elastic cable according to the instructions sent by the data processing unit; 9.4. Continue to monitor the displacement and elongation of the elastic cable to verify the adjustment effect; 9.5. If the effect after adjustment is not ideal, repeat the above steps until the best mooring effect is achieved.
[0013] An offshore wind power mooring system and mooring method, the beneficial effects of the method include but are not limited to the following points: 1. The design of the first elastic cable and the second elastic cable of the present invention can effectively reduce the tilting amplitude of the floating platform in wind and waves. When the platform tilts, the elastic cable pulls the side wall point to reset through the rebound force, and releases part of the rebound force through the movement of the anchor point to avoid excessive force on the side wall point; the first elastic cable and the second elastic cable are respectively connected to different positions of the floating platform, forming a multi-point support, which further enhances the stability of the platform; 2. The design of the elastic cable can effectively manage the rebound force, avoid the wind turbine from vibrating violently due to the instantaneous excessive rebound force, and thus protect the wind turbine from damage; by attaching strain gauges on the elastic cable, the elongation of the elastic cable can be monitored in real time, and the preload force can be adjusted in time to maintain the stable operation of the system; 3. By setting displacement sensors on the anchors and strain gauges on the elastic cables, the displacement and elongation of the elastic cables are monitored in real time, and the real-time tilt angle of the floating platform is calculated. According to the calculated tilt angle, the preload of the elastic cables is adjusted manually or automatically to ensure that the platform always maintains the best stability. 4. By setting up safety cables, even if the elastic cables are broken due to long-term use or sea breeze erosion, they can temporarily prevent the wind turbines from overturning and play a role of insurance. By setting up detection cables and detection slip rings, the tilt state of adjacent wind turbines can be intuitively identified, problems can be discovered and solved in time, and the safety and reliability of the system can be improved. BRIEF DESCRIPTION OF THE DRAWINGS
[0014] Figure 1 It is a schematic diagram of the connection method of the ground anchor, floating platform and tower of the present invention; Figure 2 It is a schematic diagram of the connection mode of adjacent floating platforms through the third elastic cable of the present invention; Figure 3 This is a schematic diagram of the connection between the detection cable and the detection slip ring of the present invention; Figure 4 This is a schematic diagram of the connection method of adjacent floating platforms through the fourth elastic cable of the present invention.
[0015] In the figure: floating platform 1, first bottom end point 101, second bottom end point 102, tower 2, first side wall point 201, second side wall point 202, wind turbine 3, anchor 4, safety rope 5, first elastic cable 6, second elastic cable 7, third elastic cable 8, detection cable 9, detection slip ring 10, fourth elastic cable 11. DETAILED DESCRIPTION
[0016] like Figure 1 As shown, an offshore wind power mooring system includes a floating platform 1, a tower 2, a wind turbine 3 and a ground anchor 4. The lower end of the tower 2 is vertically installed at the center of the floating platform 1, and the wind turbine 3 is installed on the upper end of the tower 2. A plurality of ground anchors 4 are arranged on the seabed around the floating platform 1. A first elastic cable 6, a second elastic cable 7 and a safety rope 5 are connected between the tower 2, the floating platform 1 and the ground anchor 4. A tilt monitoring system is arranged on the first elastic cable 6, the second elastic cable 7 and the ground anchor 4. One end of the first elastic cable 6 is connected to the first bottom point 101 on the floating platform 1, and the other end of the first elastic cable 6 is connected to the first side wall point 201 on the tower 2. The first elastic cable 6 passes through at least one anchor 4. After the first elastic cable 6 is connected, it is in an elastic tension state. One end of the second elastic cable 7 is connected to the second bottom point 102 on the floating platform 1, and the other end of the second elastic cable 7 is connected to the second side wall point 202 on the tower 2. The second elastic cable 7 passes through at least one anchor 4. After the second elastic cable 7 is connected, it is in an elastic tension state. The first bottom end point 101, the first side wall point 201 and the at least one ground anchor 4 are all located on one side of the floating platform 1, and the second bottom end point 102, the second side wall point 202 and the at least one ground anchor 4 are all located on the other side of the floating platform 1; When the floating platform 1 is tilted by wind and waves, the first elastic cable 6 and the second elastic cable 7 pull the side wall point to reset through the rebound force, and at the same time release part of the rebound force through the movement of the anchor 4, so as to avoid excessive force on the side wall point and reduce the vibration of the wind turbine 3.
[0017] The preferred solution is Figure 1 As shown, the tilt monitoring system includes a displacement sensor and a strain sensor; the displacement sensor is arranged on the anchor 4, and the strain sensor is arranged on the first elastic cable 6 and the second elastic cable 7. The displacement sensor is used to detect the displacement distance of the first elastic cable 6 and the second elastic cable 7 relative to the anchor 4, and the strain sensor is used to detect the elastic elongation of the elastic cable. The data processing unit calculates the real-time tilt angle of the floating platform 1 by geometric conversion based on the data of the displacement sensor and the strain sensor.
[0018] The preferred solution is Figure 2 As shown, a third elastic cable 8 is arranged between adjacent floating platforms 1 and ground anchors 4, one end of the third elastic cable 8 is connected to the bottom of the floating platform 1, and the other end of the third elastic cable 8 is connected to the bottom of another adjacent floating platform 1, and the third elastic cable 8 passes through at least one ground anchor 4. After the third elastic cable 8 is connected, it is in an elastically tight state. When adjacent floating platforms 1 tilt at the same time, the third elastic cable 8 can provide additional resilience to prevent the platforms from tilting excessively. Through the third elastic cable 8, adjacent floating platforms 1 can provide each other with resilience to prevent the platforms from tilting excessively.
[0019] The preferred solution is Figure 4 As shown, a fourth elastic cable 11 is arranged between adjacent floating platforms 1, one end of the fourth elastic cable 11 is connected to the top-view endpoint of the floating platform 1, and the other end of the fourth elastic cable 11 is connected to the same top-view endpoint of another adjacent floating platform 1, and the fourth elastic cable 11 passes through at least one anchor 4, and the anchor 4 is far away from the two end points; the floating platform 1 is triangular in top view, and the connection points of the fourth elastic cable 11 are all vertices of the triangle. The fourth elastic cable 11 can effectively prevent the floating platform 1 from rotating around the axis of the tower 2, further improving the stability of the system.
[0020] The preferred solution is Figure 1As shown, a safety cable 5 is connected between the floating platform 1 and the anchor 4, and the connection point of the safety cable 5 is the same as the connection point of the first elastic cable 6 and the second elastic cable 7. The safety cable 5 can temporarily prevent the wind power equipment from capsizing when the elastic cable is broken due to long-term use or sea wind erosion, thus playing a role of insurance.
[0021] The preferred solution is Figure 3 As shown, a detection cable 9 is connected between adjacent towers 2, and a detection slip ring 10 is sleeved on the detection cable 9, and the detection slip ring 10 slides along the detection cable 9. By detecting the position of the slip ring 10 on the detection cable 9, the tilt state of adjacent wind power equipment can be intuitively identified, problems can be discovered and solved in time, and the safety and reliability of the system can be improved.
[0022] Embodiment 1: A mooring method for an offshore wind power mooring system comprises the following steps: S1, elastically tensioning and connecting the first elastic cable 6 and the second elastic cable 7 between the floating platform 1 and the tower 2; S2, providing a displacement sensor on the ground anchor 4, for detecting the displacement distance of the first elastic cable 6 or the second elastic cable 7 relative to the ground anchor 4; S3, attaching a strain sensor sheet on the first elastic cable 6 or the second elastic cable 7 to detect the elastic elongation of the elastic cable; S4, real-time monitoring of the displacement and elongation of the elastic cable, recording the data and transmitting it to the data processing unit, which calculates the real-time tilt angle of the floating platform 1 based on the monitoring data; the specific calculation method is as follows: S4.1. Collect data of the tilt monitoring system, including the displacement distance of the first elastic cable 6 and the second elastic cable 7 relative to the anchor 4 detected by the displacement sensor, and the elastic elongation of the elastic cable detected by the strain gauge; S4.2, determining the displacement distances d1 and d2 of the first elastic cable 6 and the second elastic cable 7 relative to the ground anchor 4 according to the data of the displacement sensor; S4.3, determining elastic elongations △L1 and △L2 of the first elastic cable 6 and the second elastic cable 7 according to the data of the strain gauge; S4.4. Calculate the actual length change of the elastic cable L1 = L 01 +△L1 and L2 = L 02 +△L2; Where: L 01 and L 02 is the initial length of the elastic cable; S4.5. Calculate the inclination angle of floating platform 1 according to the geometric relationship : Set the width of floating platform 1 to W and the height to H; Calculate the tilt angle The tangent value of : ; Calculate the tilt angle : ; S4.6. The data processing unit calculates the tilt angle Stored together with other monitoring data and displayed in real time; S5. According to the calculated tilt angle, adjust the preload force of the first elastic cable 6 and the second elastic cable 7 to minimize the tilt angle and displacement of the floating platform 1. The specific adjustment method is as follows: S5.1. Calculate the real-time tilt angle of the floating platform 1 according to the data collected in S4; S5.2. Regularly evaluate the performance of the mooring system, including the maximum displacement and maximum inclination angle of the floating platform 1, and determine whether the preload of the elastic cable needs to be adjusted based on the evaluation results; S5.3. If the preload force needs to be adjusted, the preload force of the first elastic cable 6 and the second elastic cable 7 is adjusted manually or automatically: Manual adjustment: The operator uses a tensioning tool to adjust the preload of the elastic cable according to the tilt angle information provided by the data processing unit; Automatic adjustment: Use the preload adjustment device to automatically adjust the preload of the elastic cable according to the instructions sent by the data processing unit; S5.4. Continue to monitor the displacement and elongation of the elastic cable to verify the adjustment effect; S5.5. If the effect after adjustment is not ideal, repeat the above steps until the best mooring effect is achieved; S6. When the wind turbine equipment tilts to one side, the corresponding elastic cable is pulled, and one end of the elastic cable pulls the side wall point through the rebound force to prevent the tower 2 from tilting too much and thus overturning; the elastic cable pulls the cable length close to the bottom end point to the side of the tower 2, releasing the rebound force to a certain extent to prevent the tower 2 from vibrating too much.
[0023] It is obvious to those skilled in the art that the present invention is not limited to the details of the exemplary embodiments described above, and that the present invention can be implemented in other specific forms without departing from the spirit or essential features of the present invention. Therefore, the embodiments should be regarded as exemplary and non-restrictive from all points of view, and the scope of the present invention is defined by the appended claims rather than the above description, and it is intended that all changes falling within the meaning and scope of the equivalent elements of the claims are included in the present invention; any reference numerals in the claims should not be regarded as limiting the claims involved.
Claims
1. An offshore wind power mooring system, comprising a floating platform (1), a tower (2), a wind turbine (3) and a ground anchor (4), characterized in that: The lower end of the tower (2) is vertically installed at the center of the floating platform (1), and a wind turbine set (3) is installed at the upper end of the tower (2). A plurality of ground anchors (4) are arranged on the seabed around the floating platform (1). A first elastic cable (6), a second elastic cable (7) and a safety rope (5) are connected between the tower (2), the floating platform (1) and the ground anchor (4). A tilt monitoring system is arranged on the first elastic cable (6), the second elastic cable (7) and the ground anchor (4); One end of the first elastic cable (6) is connected to a first bottom end point (101) on the floating platform (1), and the other end of the first elastic cable (6) is connected to a first side wall point (201) on the tower (2); the first elastic cable (6) passes through at least one ground anchor (4); and the first elastic cable (6) is in an elastically tight state after being connected; One end of the second elastic cable (7) is connected to a second bottom end point (102) on the floating platform (1), and the other end of the second elastic cable (7) is connected to a second side wall point (202) on the tower (2); the second elastic cable (7) passes through at least one ground anchor (4); and the second elastic cable (7) is in an elastically taut state after being connected; The first bottom end point (101), the first side wall point (201) and at least one ground anchor (4) are all located on one side of the floating platform (1), and the second bottom end point (102), the second side wall point (202) and at least one ground anchor (4) are all located on the other side of the floating platform (1).
2. The offshore wind power mooring system according to claim 1, characterized in that: The tilt monitoring system comprises a displacement sensor and a strain sensor sheet; the displacement sensor is arranged on a ground anchor (4), and the strain sensor sheet is arranged on a first elastic cable (6) and a second elastic cable (7).
3. The offshore wind power mooring system according to claim 1, characterized in that: A third elastic cable (8) is provided between adjacent floating platforms (1) and ground anchors (4); one end of the third elastic cable (8) is connected to the bottom of the floating platform (1); the other end of the third elastic cable (8) is connected to the bottom of another adjacent floating platform (1); the third elastic cable (8) passes through at least one ground anchor (4); and the third elastic cable (8) is in an elastically tight state after being connected.
4. The offshore wind power mooring system according to claim 1, characterized in that: A fourth elastic cable (11) is provided between adjacent floating platforms (1), one end of the fourth elastic cable (11) being connected to a top-view endpoint of the floating platform (1), and the other end of the fourth elastic cable (11) being connected to the same top-view endpoint of another adjacent floating platform (1), the fourth elastic cable (11) passing through at least one ground anchor (4), and the ground anchor (4) is located away from both end points; The floating platform (1) is in the shape of a triangle when viewed from above, and the connection points of the fourth elastic cables (11) are all vertices of the triangle.
5. The offshore wind power mooring system according to claim 1, characterized in that: A safety cable (5) is connected between the floating platform (1) and the ground anchor (4), and the connection point of the safety cable (5) is the same as the connection point of the first elastic cable (6) and the second elastic cable (7).
6. The offshore wind power mooring system according to claim 1, characterized in that: A detection cable (9) is connected between adjacent towers (2), a detection slip ring (10) is sleeved on the detection cable (9), and the detection slip ring (10) slides along the detection cable (9) in a limited manner.
7. A mooring method for an offshore wind power mooring system, characterized in that: The method comprises the following steps: S1. elastically tensioning and connecting the first elastic cable (6) and the second elastic cable (7) between the floating platform (1) and the tower (2); S2, arranging a displacement sensor on the ground anchor (4) to detect the displacement distance of the first elastic cable (6) or the second elastic cable (7) relative to the ground anchor (4); S3, attaching a strain sensor sheet to the first elastic cable (6) or the second elastic cable (7) to detect the elastic elongation of the elastic cable; S4, real-time monitoring of the displacement and elongation of the elastic cable, recording the data and transmitting the data to a data processing unit, the data processing unit calculating the real-time tilt angle of the floating platform (1) based on the monitoring data; S5. According to the calculated tilt angle, adjusting the preload force of the first elastic cable (6) and the second elastic cable (7) to minimize the tilt angle and displacement of the floating platform (1); S6. When the wind turbine equipment tilts to one side, the corresponding elastic cable is pulled, and one end of the elastic cable pulls the side wall point through the rebound force to prevent the tower (2) from tilting too much and thus overturning; the elastic cable pulls the cable length close to the bottom end point to the side of the tower (2), releasing the rebound force to a certain extent, thereby preventing the tower (2) from vibrating too much.
8. The mooring method for an offshore wind power mooring system according to claim 7, characterized in that: In S4, the real-time tilt angle of the floating platform (1) is calculated as follows: 8.
1. Collect data of the tilt monitoring system, including the displacement distance of the first elastic cable (6) and the second elastic cable (7) relative to the anchor detected by the displacement sensor, and the elastic elongation of the elastic cable detected by the strain gauge; 8.
2. Determine the displacement distances d1 and d2 of the first elastic cable (6) and the second elastic cable (7) relative to the ground anchor (4) based on the data of the displacement sensor; 8.
3. Determine the elastic elongation △L1 and △L2 of the first elastic cable (6) and the second elastic cable (7) based on the data of the strain gauge; 8.
4. Calculate the actual length change of the elastic cable L1 = L 01 +△L1 and L2 = L 02 +△L2; Where: L 01 and L 02 is the initial length of the elastic cable; 8.
5. Calculate the inclination angle of the floating platform (1) based on the geometric relationship ; Set the width of the floating platform (1) to W and the height to H Calculate the tilt angle The tangent value of : ; Calculate the tilt angle : ; 8.
6. The data processing unit calculates the tilt angle Stored together with other monitoring data and displayed in real time.
9. The mooring method of the offshore wind power mooring system according to claim 7, characterized in that: In S5, the pre-tightening force of the first elastic cable (6) and the second elastic cable (7) is adjusted as follows: 9.
1. Calculate the real-time tilt angle of the floating platform (1) based on the data collected in S4; 9.
2. Regularly evaluate the performance of the mooring system, including the maximum displacement and maximum tilt angle of the floating platform (1); based on the evaluation results, determine whether the preload of the elastic cable needs to be adjusted. 9.
3. If the preload force needs to be adjusted, the preload force of the first elastic cable (6) and the second elastic cable (7) is adjusted manually or automatically; During manual adjustment, the operator uses a tensioning tool to adjust the preload of the elastic cable based on the tilt angle information provided by the data processing unit; During automatic adjustment, the preload force adjustment device is used to automatically adjust the preload force of the elastic cable according to the instructions sent by the data processing unit; 9.
4. Continue to monitor the displacement and elongation of the elastic cable to verify the adjustment effect; 9.
5. If the effect after adjustment is not ideal, repeat the above steps until the best mooring effect is achieved.