Rock mass - soil - plant - microorganism slope ecological restoration system and construction method

The method of multi-level slope cutting and drainage with anchored soil retention units and biotic soil mixtures addresses the challenges of unstable installation and low growth rates on steep rock slopes, enhancing ecological recovery and stability.

CN119571843BActive Publication Date: 2025-07-15ZHEJIANG SHIRUN JIANCHUANG TECH DEV CO LTD +1
View PDF 5 Cites 0 Cited by

Patent Information

Application Number
CN202510142490.7
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2025-02-10
Publication Date
2025-07-15
Estimated Expiration
2045-02-10

AI Technical Summary

Technical Problem

The prior art has low installation efficiency and poor fixity on high-steep rock slopes, rainwater flushing nutrient soil, large load weight, low plant survival rate, and difficult to quickly restore native plant community structure and ecosystem functions.

Method used

The multi-stage slope cutting platform and slope bottom pit groove are used to set up longitudinal and transverse drainage ditches, the anchor-string-cross-shaped rib structure is fixed in geogrid chambers, and ecological restoration is carried out through the integrated substrate of spray-sowed soil-plant-microbials, and adjacent grid chambers are connected with U-shaped steel bar nails, so that the joint action of microorganisms and plants is used to improve the re-green effect.

Benefits of technology

It improves the installation and fixation efficiency of geotextile chambers, reduces the flushing of nutrient soil by rainwater, reduces load weight, enhances plant survival rate and growth rate, and quickly restores the structure of native plant communities and ecosystem functions.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119571843B_ABST
    Figure CN119571843B_ABST
Patent Text Reader

Abstract

The present invention provides a rock mass - soil - plant - microorganism slope ecological restoration system and a construction method. It is characterized in that multi - level slope - cutting platforms are arranged on the rock mass slope for unloading, and longitudinal drainage ditches are arranged at the platforms to guide the collected water, reducing the flushing of the nutrient soil in the geocells and reducing the load weight of the geocells; by driving grouting anchor rods, the geocells are tightened and fixed by the anchor rods - tie bars - cross - shaped tie bars, and adjacent geocells are connected by U - shaped steel nails; the surface of the geocells is sprayed with an integrated matrix of soil - plant - microorganism, and the interaction between plants and microorganisms is utilized to improve the survival rate and growth rate of plants, and quickly restore the original plant community structure and ecosystem function.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of ecological restoration engineering for rocky slopes such as mines and highways, and particularly relates to a rock - soil - plant - microorganism slope ecological restoration system and a construction method thereof. Background Art

[0002] The development of social economy is inseparable from various development and construction projects. While promoting the rapid development of regional economy, development and construction projects also cause damage to the natural ecological environment in the construction area and its surrounding areas. High - fill and deep - cut in engineering construction such as railways, highways, water conservancy, and mines directly damage the ground surface, generating a large area of exposed high and steep slopes, leading to the deterioration of the ecological environment around the project area. Especially the newly increased large - area exposed slopes cause landscape disharmony and soil erosion, and even trigger secondary geological disasters such as landslides and collapses; mainly manifested as changing the topography and geomorphology, disturbing the soil structure, destroying the plant community, reducing biodiversity, affecting the regional climate, causing and intensifying soil erosion, etc. Therefore, the ecological restoration and reconstruction of exposed slopes (also known as slope greening) is extremely urgent.

[0003] At present, the slope greening treatment technologies for some special slopes at home and abroad are still relatively weak. For example, for high and steep rocky slopes dozens of meters or even hundreds of meters high, mainly slope cutting, setting up steps, spraying and sowing with net hanging and other greening technologies are used for treatment. There are still the following problems in using these technologies for greening: (1) Since the geocell serves as the root soil skeleton of the greening plants and has a large bearing capacity, it is easy to slide on large - area high and steep rocky slopes, and it is relatively difficult to install and fix; (2) Although traditional technologies also set up multi - level slope - cutting platforms, the platforms lack effective longitudinal drainage ditches for timely water diversion and collection, which is likely to cause two problems: ① Rainwater flushes the backfilled planting soil layer in the geocell, resulting in the washing away of a large amount of nutrient soil for plant growth; ② A large amount of collected water is contained in the geocell planting soil layer, increasing the load weight of the geocell, and seriously tearing the geocell when severe. (3) The installation efficiency at the splicing joints of each geocell is low, and the connection is not firm; (4) Only using plants to conduct ecological restoration on the exposed slope, the plant survival rate is low, the growth rate is slow, the greening efficiency is low, and it is difficult to restore the original plant community structure and ecosystem function.

[0004] Therefore, how to improve the installation efficiency and fixity of geocells on large - area high and steep rocky slopes, reduce the washing of nutrient soil in the geocell by rainwater, reduce the load weight of the geocell, use new ecological restoration technologies to conduct ecological restoration on the exposed slope, improve the plant survival rate and growth rate, and quickly restore the original plant community structure and ecosystem function is the main problem to be solved currently. Summary of the Invention

[0005] The purpose of the present invention is to provide a rock - soil - plant - microorganism slope ecological restoration system and a construction method thereof to solve the above - mentioned technical problems.

[0006] To solve the above technical problems, the present invention provides a construction method for a rock mass - soil - plant - microorganism slope ecological restoration system, comprising the following steps:

[0007] Step 1, slope cleaning: Clean the floating stones on the rock slope, measure and lay out the positions for driving each anchor rod, the excavation line of the slope - cutting bench, the excavation line of the bottom pit of the slope, and the construction red line of the toe - slip wall;

[0008] Step 2, excavation of the bench and the pit: Grade - excavate the slope - cutting bench from the top of the slope downwards according to the excavation line of the slope - cutting bench. Excavate a longitudinal drainage ditch on each slope - cutting bench, and lay a layer of permeable geotextile on the top of the longitudinal drainage ditch of the bench;

[0009] Step 3, construction of the toe - slip wall and the drainage ditch: Excavate the bottom pit of the slope according to the excavation line of the bottom pit of the slope. Excavate several longitudinal drainage ditches at the bottom of the bottom pit of the slope, and excavate transverse drainage ditches at uniform intervals at the bottom of the pit; Construct the toe - slip wall according to the construction red line of the toe - slip wall;

[0010] Step 4, driving the anchor rods: Drill anchor rod holes according to the positioning line of the anchor rods, drive the anchor rods, and inject cement slurry for anchoring. Set up a slope - top anchor rod guardrail after the slope top is cut, and lay several layers of steel wire meshes on the rock slope;

[0011] Step 5, pouring ecological concrete: Pour an ecological concrete layer from the bottom of the slope to the top of the slope. The ecological concrete layer completely covers the steel wire mesh. The ecological concrete layer is poured in sections and sub - areas, and the pouring thickness on the rock slope, the slope - cutting bench, and the bottom pit of the slope is the same;

[0012] Step 6, installing the tie bars: Install anchor fittings on the anchor rods, fix multiple tie bars on the anchor fittings. The multiple tie bars are evenly and dispersedly arranged, and a threaded enlarged head is provided at the end of each tie bar;

[0013] Step 7, laying and fixing the geocell in blocks: Lay the geocell from top to bottom;

[0014] Step 8, preparing the nutrient soil layer: Prepare nutrient soil, and sieve the nutrient soil after it is evenly stirred;

[0015] Step 9, screening of plants and microorganisms: Select microorganisms and plant seeds according to the local meteorological conditions and the surrounding environment;

[0016] Step 10, spraying the nutrient soil layer: Evenly spray the prepared nutrient soil from the top of the slope to the bottom of the slope to fill the geocell;

[0017] Step Eleven: Spraying the integrated matrix of soil - plant - microorganism: Evenly mix the selected plant seeds, microorganisms, and nutrients into an integrated matrix, spray the integrated matrix of soil - plant - microorganism onto the surface of the geocell, cover it with a nutrient soil layer, and then lay a metal mesh on top of the integrated matrix of soil - plant - microorganism;

[0018] Step Twelve: Spraying water for maintenance: Use a sprayer to spray - maintain the integrated matrix of soil - plant - microorganism on the geocell. After the seeds germinate, water for maintenance. Under the interaction of plants and microorganisms, slope revegetation is achieved.

[0019] The beneficial effects of the present invention are as follows:

[0020] 1. In the present invention, multi - level slope - cutting benches and bottom pit grooves are set on the rock slope. Longitudinal drainage ditches are set in the benches, and longitudinal and transverse drainage ditches are set in the pit grooves, reducing the flushing of rainwater on the nutrient soil in the geocell and reducing the load weight of the geocell.

[0021] 2. The present invention uses a bolt - tie - bar - cross - shaped stiffener structure to fix the geocell. By adjusting the nuts, the tightness of the cross - shaped stiffener on the geocell is achieved, improving the installation and fixing efficiency of the geocell.

[0022] 3. At the splicing joints of adjacent geocells of the present invention, U - shaped steel nails are used for connection and fixation. The connection efficiency of adjacent geocells is high, the connection is firm, and there will be no disconnection phenomenon.

[0023] 4. Through various tests, excellent microbial agents and plant seeds with high survival rate and strong metabolic ability are selected in the present invention. The selected plant seeds, microorganisms, and nutrients are evenly mixed into an integrated matrix and sprayed on the surface of the geocell. Different types of vegetation provide good conditions for the growth of microorganisms. The roots of plants release a large amount of carbon sources, and the decomposition and transformation of plant litter improve the contents of nutrients such as carbon, nitrogen, and phosphorus in the soil, affecting the metabolic activity of the soil microbial community. The development of the soil microbial community in turn promotes the growth of plants. The combined action of plants and microorganisms effectively improves the slope revegetation effect. Brief Description of the Drawings

[0024] Figure 1 is the overall structure diagram of the rock - soil - plant - microorganism slope ecological restoration system of the present invention;

[0025] Figure 2 is the partial detailed drawing of the bolt - tie - bar - cross - shaped stiffener for tightening and fixing the geocell of the present invention;

[0026] Figure 3 is the detailed drawing of the slope - cutting bench ecological restoration structure of the present invention;

[0027] Figure 4It is the detailed drawing of the combined structure of the bottom slope pit and the toe slip wall of the present invention;

[0028] Figure 5 It is the schematic diagram of zoning and block division of geocells on the rock slope of the present invention;

[0029] Figure 6 It is the schematic diagram of splicing of adjacent geocells of the present invention;

[0030] Figure 7 It is the fixed connection drawing of adjacent geocells with U-shaped steel nails of the present invention;

[0031] Figure 8 It is the structural drawing of the cross-shaped clamping bar pressing the geocell of the present invention;

[0032] Figure 9 It is the plan view of the connection between the cross-shaped clamping bar and the threaded enlarged head of the tension bar of the present invention;

[0033] Figure 10 It is the structural drawing of the connection between the cross-shaped clamping bar and the threaded enlarged head of the tension bar of the present invention.

[0034] Wherein: 1-rock slope; 2-anchor hole; 3-cement slurry; 4-anchor rod; 5-anchor rod guardrail at the slope top; 6-steel wire mesh; 7-eco-concrete layer; 8-steel wire rope; 9-steel backing plate; 10-anchorage; 11-tension bar; 12-cross-shaped clamping bar; 13-geocell; 14-U-shaped steel nail; 15-bench nail; 16-cut slope bench; 17-permeable geotextile; 18-longitudinal drainage ditch on the bench; 19-bottom slope pit; 20-transverse drainage ditch at the bottom of the pit; 21-toe slip wall; 22-PVC pipe; 23-drainage ditch; 24-natural ground; 25-longitudinal drainage ditch at the bottom of the pit; 26-nut; 27-gasket; 28-threaded enlarged head; 29-thread. Specific implementation manners

[0035] Next, the technical solutions in the embodiments of the present invention will be clearly and completely described in conjunction with the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are only a part of the embodiments of the present invention, rather than all the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those of ordinary skill in the art belong to the scope of protection of the present invention.

[0036] Those skilled in the art should understand that in the disclosure of the present invention, the orientation or positional relationships indicated by the terms "longitudinal", "transverse", "upper", "lower", "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outer", etc. are based on the orientation or positional relationships shown in the drawings. These are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation. Therefore, the above terms should not be construed as limiting the present invention.

[0037] It can be understood that the term "a" should be understood as "at least one" or "one or more". That is, in one embodiment, the number of an element can be one, while in other embodiments, the number of this element can be multiple. The term "a" should not be construed as a limitation on the quantity.

[0038] As Figures 1 - 10 described above, the present invention provides a rock mass - soil - plant - microorganism slope ecological restoration system and construction method, including the following steps:

[0039] Step 1. Slope cleaning: Familiarize with the requirements of the design drawings and relevant documents, prepare the construction plan for the rock mass - soil - plant - microorganism slope ecological restoration system and the special safety plan for high - altitude operations. Clean the loose stones on the rock slope 1, and on - site measure and set out the driving positions of each anchor rod 4, the excavation line of the slope - cutting bench 16, the excavation line of the bottom pit 19 of the slope, and the construction red line of the toe - slide wall 21. Determine the number of blocks of the geocell 13 and the dimensions of each block according to the size and slope of the rock slope 1.

[0040] Step 2. Excavate the bench and the pit: Use an excavator to carry out graded excavation of the slope - cutting bench 16 from the top of the slope to the bottom according to the excavation line of the slope - cutting bench 16. Excavate the longitudinal drainage ditch 18 on each slope - cutting bench 16, and lay a layer of permeable geotextile 17 on the top of the longitudinal drainage ditch 18 on the bench.

[0041] Step 3. Construction of the toe - slide wall and the drainage ditch: Excavate the bottom pit 19 of the slope according to the excavation line of the bottom pit 19 of the slope. Excavate three longitudinal drainage ditches 25 at the bottom of the bottom pit 19 of the slope, and excavate transverse drainage ditches 20 at uniform intervals at the bottom. The longitudinal drainage ditches 25 at the bottom and the transverse drainage ditches 20 at the bottom intersect with each other, and lay a layer of permeable geotextile 17 on the upper part of the longitudinal and transverse drainage ditches at the bottom. Build the toe - slide wall 21 according to the construction red line of the toe - slide wall 21, install a PVC pipe 22 inside the toe - slide wall 21, connect the PVC pipe 22 with the transverse drainage ditch 20 at the bottom, and pour a drainage ditch 23 outside the toe - slide wall 21 to overlap with the natural ground 24.

[0042] Step 4: Install anchor bolts: Drill anchor bolt holes 2 according to the positioning line of the anchor bolts 4, install the anchor bolts 4, and inject cement slurry 3 for anchoring. After the slope top is trimmed, set up the slope top anchor bolt guardrail 5. Lay a steel mesh 6 on the rock slope 1. The steel mesh 6 is laid in three layers. The top of the steel mesh 6 is wound around the slope top anchor bolt guardrail 5. Each anchor bolt 4 passes through the grid of the steel mesh 6. Install steel backing plates 9 on the anchor bolts 4 to press the steel mesh 6 tightly to prevent it from rebounding and bulging.

[0043] Step 5: Pour ecological concrete: Pour the ecological concrete layer 7 from the bottom of the slope to the top of the slope. The ecological concrete layer 7 completely covers the steel mesh 6. The ecological concrete layer 7 is poured in sections and subsections, and the pouring thickness on the rock slope 1, the trimmed slope bench 16, and the bottom pit 19 is the same.

[0044] Step 6: Install tie bars: Install anchor fittings 10 on the anchor bolts 4, fix multiple tie bars 11 on the anchor fittings 10. The multiple tie bars 11 are evenly and dispersedly arranged, and a threaded enlarged head 28 is provided at the end of each tie bar 11.

[0045] Step 7: Lay and fix geocells in blocks: Lay the geocells 13 from top to bottom according to the designed number and size of the geocell 13 blocks, and lay them in sequence: block A1, block B1, block C1 → block A2, block B2, block C2 → block A3, block B3, block C3 → block A4, block B5, block C4. The top blocks A1, B1, and C1 are all tied to the slope top anchor bolt guardrail 5 by steel wires 8. After the tie bars 11 pass through the cells of the geocells 13, put a cross-shaped clamping bar 12 on the threaded enlarged head 28 at the end of the tie bar 11, and install a nut 26 and a gasket 27. After the cross-shaped clamping bar 12 is clamped on the cells of the geocells 13, adjust the tightness of the nut 26 to make the cross-shaped clamping bar 12 press the geocells 13 tightly, so as to realize the function of fixing the geocells 13 by the anchor bolt - tie bar - cross-shaped clamping bar structure. U-shaped steel nails 14 are installed between adjacent geocell blocks, such as between block A1 and block B1, and between block A1 and block A2, for connection. At the same time, vertical bench nails 15 are driven at the trimmed slope bench 16 for enhanced locking. Both the U-shaped steel nails 14 and the bench nails 15 need to be driven into the rock slope 1 to a certain depth.

[0046] Step 8: Prepare the nutrient soil layer: Prepare nutrient soil by mixing local fertile soil, microbial organic fertilizer, compound fertilizer, water retention agent, soil conditioner and other materials in a certain proportion. After the nutrient soil is evenly stirred, it needs to pass through a 1 cm sieve to keep the prepared nutrient soil layer delicate and uniform.

[0047] Step 9: Screen plants and microorganisms: Cultivate different kinds of microbial strains in the laboratory in combination with the local climate conditions, and select the strains with high activity and strong vitality through relevant tests; at the same time, mix plant seeds according to the local meteorological conditions and the surrounding environment, and select plant seeds that can promote the growth of each other with the microorganisms.

[0048] Step Ten: Spraying the nutrient soil layer: The prepared nutrient soil layer is evenly sprayed from the top of the slope to the bottom of the slope by a spraying machine to fill the geocell 13. The thickness of the sprayed nutrient soil layer must be uniform, which is 15 cm - 20 cm.

[0049] Step Eleven: Spraying the soil-plant-microorganism integrated matrix: The selected plant seeds, microorganisms, and nutrients are evenly mixed into an integrated matrix, and the soil-plant-microorganism integrated matrix is sprayed onto the surface layer of the geocell 13 to cover the nutrient soil layer, and a metal mesh is laid on the soil-plant-microorganism integrated matrix.

[0050] Step Twelve: Spraying water for maintenance: A sprayer is used to spray and maintain the soil-plant-microorganism integrated matrix on the geocell 13. After the seeds germinate, water is used for maintenance. Under the interaction of plants and microorganisms, rapid revegetation of the slope is achieved.

[0051] The present invention also discloses a rock mass-soil-plant-microorganism slope ecological restoration system, as Figures 1 - 2 shown in the partial detailed drawing of the geocell tightened and fixed by anchor bolts - tie bars - cross-shaped tie bars, mainly including a rock mass slope 1, anchor bolts 4, a slope top anchor bolt guardrail 5, a steel bar mesh 6, an ecological concrete layer 7, a steel backing plate 9, a geocell 13, etc. A plurality of anchor bolts 4 are driven on the rock mass slope 1, and the anchor bolts 4 are driven at uniform intervals. A steel bar mesh 6 is laid on the rock mass slope 1, the upper part of the steel bar mesh 6 is wound around the slope top anchor bolt guardrail 5, the steel bar mesh 6 is pressed by the steel backing plate 9 on the anchor bolts 4, an ecological concrete layer 7 is poured on the steel bar mesh 6, and a geocell 13 is laid on the ecological concrete layer 7.

[0052] As Figure 3 shown in the detailed drawing of the ecological restoration structure of the slope cutting bench, mainly including a rock mass slope 1, a steel bar mesh 6, an ecological concrete layer 7, a geocell 13, bench nails 15, a slope cutting bench 16, a permeable geotextile 17, a longitudinal drainage ditch 18 on the bench. A plurality of slope cutting benches 16 are excavated on the rock mass slope 1, a longitudinal drainage ditch 18 on the bench is excavated on the slope cutting bench 16, a permeable geotextile 17 is laid on the top of the longitudinal drainage ditch 18 on the bench, and the steel bar mesh 6 and the ecological concrete layer 7 are located above the permeable geotextile 17. Bench nails 15 are driven on the side of the longitudinal drainage ditch 18 on the bench, and the geocell 13 is strengthened and fixed through the bench nails 15.

[0053] As Figure 4Detailed drawing of the combined structure of the slope bottom pit - toe slip wall, mainly including rock slope 1, geocell 13 - A4 block, geocell 13 - B4 block, geocell 13 - C4 block, slope bottom pit 19, transverse drain 20 at the bottom of the pit, toe slip wall 21, PVC pipe 22, drain 23, natural ground 24, longitudinal drain 25 at the bottom of the pit, etc. A slope bottom pit 19 is excavated at the bottom of the rock slope 1. A transverse drain 20 at the bottom of the pit and a longitudinal drain 25 at the bottom of the pit are excavated at the bottom of the slope bottom pit 19. Three longitudinal drains 25 at the bottom of the pit are arranged, and multiple transverse drains 20 at the bottom of the pit are evenly spaced. The longitudinal drain 25 at the bottom of the pit intersects with the transverse drain 20 at the bottom of the pit. A toe slip wall 21 is arranged outside the slope bottom pit 19. A drain 23 is arranged outside the toe slip wall 21 to lap with the natural ground 24. A PVC pipe 22 is arranged inside the toe slip wall 21, and the PVC pipe 22 communicates with the transverse drain 20 at the bottom of the pit. The geocell 13 - A4 block, geocell 13 - B4 block, and geocell 13 - C4 block at the bottom of the geocell 13 are all placed in the slope bottom pit 19.

[0054] As Figure 5 Shown in the schematic diagram of the zoning and block division of the geocell on the rock slope. Multiple blocks of geocell 13 are arranged along the rock slope 1, which are geocell 13 - A1 block, geocell 13 - A2 block, geocell 13 - A3 block, geocell 13 - A4 block, geocell 13 - B1 block, geocell 13 - B2 block, geocell 13 - B3 block, geocell 13 - B4 block, geocell 13 - C1 block, geocell 13 - C2 block, geocell 13 - C3 block, and geocell 13 - C4 block respectively. The geocell 13 - A1 block, geocell 13 - B1 block, and geocell 13 - C1 block at the top of the geocell 13 are fixed on the slope top anchor guardrail 5 by steel wire ropes 8.

[0055] As Figures 6 - 7 Shown in the schematic diagram of the splicing of adjacent geocell blocks. Between the adjacent geocell 13 - A1 block and geocell 13 - A2 block of the geocell 13, and between the geocell 13 - A1 block and geocell 13 - B1 block, U - shaped steel nails 14 are used for fixation, and the U - shaped steel nails 14 must be driven into the rock slope 1.

[0056] As Figure 2 、 8 Shown in the partial detailed drawing of the geocell tightened and fixed by the anchor - tie - bar - cross - shaped stiffener, including anchor 4, anchor fitting 10, tie - bar 11, cross - shaped stiffener 12, geocell 13, etc. An anchor fitting 10 is arranged at the end of the anchor 4. Multiple tie - bars 11 are arranged at the end of the anchor fitting 10. The tie - bars 11 are dispersed along the slope surface. The cross - shaped stiffener 12 is fixed at the end of the tie - bar 11, and the cross - shaped stiffener 12 is stuck on the cells of the geocell 13.

[0057] As shown in Figures 9 - 10 the connection diagram of the cross-shaped rib and the threaded enlarged head of the tie bar, which includes the tie bar 11, the cross-shaped rib 12, the geocell 13, the nut 26, the gasket 27, the threaded enlarged head 28, the thread 29, etc. The end of the tie bar 11 is provided with the threaded enlarged head 28, and the threaded enlarged head 28 is provided with the thread 29. The cross-shaped rib 12 is sleeved on the threaded enlarged head 28. A gasket 27 is arranged on the back of the cross-shaped rib 12, and a nut 26 is arranged on the back of the gasket 27. The nut 26 can adjust the position of the cross-shaped rib 12 on the threaded enlarged head 28. The geocell 13 is fixed by tightening the cross-shaped rib 12 through the tie bar 11. By adjusting the nut 26, the purpose of pressing and adjusting the geocell 13 by the cross-shaped rib 12 is achieved, and the function of tightening and fixing the geocell by the anchor-tie bar structure is realized.

[0058] As shown in Figure 1 the overall structure diagram of the rock mass-soil-plant-microorganism slope ecological restoration system. The nutrient soil layer is sprayed in the geocell 13, and the matrix of the integrated soil-plant-microorganism after improvement is sprayed on the surface layer. The revegetation effect of the rock slope is improved through the interaction between plants and microorganisms.

[0059] The present invention is not limited to the above best implementation mode. Anyone can obtain other various forms of products under the inspiration of the present invention. However, no matter what changes are made in its shape or structure, as long as it has the same or similar technical solutions as this application, it falls within the protection scope of the present invention.

Claims

1. The construction method of the rock mass - soil - plant - microorganism slope ecological restoration system is characterized in that It includes the following steps: Step 1, Slope cleaning: Remove the loose stones on the rock slope (1), measure and lay out the driving positions of each anchor rod (4), the excavation lines of the slope-cutting benches (16), the excavation lines of the bottom pits (19) at the slope bottom, and the construction red lines of the toe slip walls (21); Step 2, Excavating the benches and pits: Gradually excavate the slope-cutting benches (16) from the top of the slope downwards according to the excavation lines of the slope-cutting benches (16). Excavate longitudinal drainage ditches (18) on each level of the slope-cutting benches (16), and lay a layer of permeable geotextile (17) on the top of the longitudinal drainage ditches (18) on the benches; Step 3, Construction of the toe slip wall and drainage ditches: Excavate the bottom pits (19) at the slope bottom according to the excavation lines of the bottom pits (19) at the slope bottom. Excavate several longitudinal drainage ditches (25) at the bottom of the bottom pits (19) at the slope bottom, and excavate transverse drainage ditches (20) at uniform intervals; Construct the toe slip walls (21) according to the construction red lines of the toe slip walls (21); Step 4, Driving the anchor rods: Drill anchor rod holes (2) according to the positioning lines of the anchor rods (4), drive the anchor rods (4), and inject cement slurry (3) for anchoring. After the slope top is trimmed, set up a slope top anchor rod guardrail (5), and lay several layers of steel mesh (6) on the rock slope (1); Step 5, Pouring ecological concrete: Pour the ecological concrete layer (7) from the slope bottom to the slope top. The ecological concrete layer (7) completely covers the steel mesh (6), and the ecological concrete layer (7) is poured in sections and partitions; Step 6, Installing the tie bars: Install anchor fittings (10) on the anchor rods (4), fix multiple tie bars (11) on the anchor fittings (10), and the multiple tie bars (11) are evenly and dispersedly arranged. A threaded enlarged head (28) is provided at the end of each tie bar (11); Step 7, Laying and fixing the geocells in blocks: Lay the geocells (13) from top to bottom; Lay the A1 block, B1 block, C1 block → A2 block, B2 block, C2 block → A3 block, B3 block, C3 block → A4 block, B4 block, C4 block in sequence from top to bottom. The top A1 block, B1 block, and C1 block are all tied to the slope top anchor rod guardrail (5) by steel wires (8); Install U-shaped steel nails (14) for connection between adjacent A1 block and B1 block, and between A1 block and A2 block. At the same time, drive vertical bench nails (15) at the slope-cutting benches (16). The U-shaped steel nails (14) and the bench nails (15) are all driven into the rock slope (1); After the tie bars (11) pass through the cells of the geocells (13), put on cross-shaped clamping bars (12) on the threaded enlarged heads (28) at the ends of the tie bars (11), and install nuts (26) and washers (27). After the cross-shaped clamping bars (12) are clamped on the cells of the geocells (13), adjust the tightness of the nuts (26) to make the cross-shaped clamping bars (12) press the geocells (13), so as to fix the geocells (13) by the anchor rod - tie bar - cross-shaped clamping bar structure; Step 8, Preparing the nutrient soil layer; Step 9, Screening plants and microorganisms; Step 10, Spraying the nutrient soil layer; Step 11, Spraying the soil - plant - microorganism integrated substrate, and then laying the metal mesh; Step Twelve: Spraying and curing: Spray and cure the soil-plant-microbial integrated substrate on the geocell (13).

2. The construction method of the rock mass - soil - plant - microorganism slope ecological restoration system according to claim 1, characterized in that: In Step Three, the longitudinal drain ditch (25) at the bottom of the trench intersects with the transverse drain ditch (20) at the bottom of the trench. A permeable geotextile (17) is laid on the upper parts of the longitudinal and transverse drain ditches at the bottom of the trench. A PVC pipe (22) is installed inside the toe slip wall (21). The PVC pipe (22) is connected to the transverse drain ditch (20) at the bottom of the trench. A drain ditch (23) is poured on the outer side of the toe slip wall (21) and lapped with the natural ground (24).

3. The construction method of the rock mass - soil - plant - microorganism slope ecological restoration system according to claim 1, characterized in that: In Step Four, the top of the steel mesh (6) is wound around the slope top anchor rod guardrail (5). Each anchor rod (4) passes through the mesh of the steel mesh (6). A steel backing plate (9) is arranged on the anchor rod (4) to press the steel mesh (6).

4. The construction method of the rock mass - soil - plant - microorganism slope ecological restoration system according to claim 1, characterized in that: In Step Ten, the thickness of the sprayed nutrient soil layer is 15 cm - 20 cm.

5. A rock mass - soil - plant - microorganism slope ecological restoration system, characterized in that: Obtained by constructing according to the construction method of the rock-soil-plant-microbial slope ecological restoration system described in any one of Claims 1 - 4.

Citation Information

Patent Citations

  • Loess landslide control system based on ecological remediation

    CN106168030A

  • High and steep hard side slope repairing system based on landscape reconstruction and repairing method thereof

    CN113089691A

  • Grating chamber structure for ecological restoration of high and steep side slope of mine

    CN116950097A

  • Excavation slope supporting structure for sloping construction

    CN202925554U

  • High and steep slope soil conservation and slope protection structure applying geocell

    CN213773415U