Wind-thermal bundled direct current delivery system planning method considering transient overvoltage constraint
By constructing a transient overvoltage constraint and a double-layer planning model, the transient overvoltage problem in the DC-transmitted system failure is solved, and the safe and stable operation of the system and reasonable planning of voltage support strength are achieved.
Patent Information
- Application Number
- CN202411633362.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-11-15
- Publication Date
- 2025-03-07
AI Technical Summary
The DC sending system may cause serious transient overvoltage in the event of a failure, threatening the safe and stable operation of the system.
By constructing a transient overvoltage constraint formula, combining the upper-layer planning model objective function and the lower-layer optimization model objective function, the upper-layer constraint and the lower-layer constraint are used to obtain the optimal planning scheme to solve the problem of transient overvoltage at the sending end after DC failure.
It effectively avoids the problem of reactive power being reversible to the AC system during DC lockout, realizes reasonable planning of operation safety and voltage support strength, and ensures the safe and stable operation of the system in the event of failure.
Smart Images

Figure CN119582336A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of new energy direct current transmission in power systems, and in particular to a planning method for a wind-fire bundled direct current transmission system taking transient overvoltage constraints into account. Background Art
[0002] Renewable energy sources such as wind power need to be transmitted on a large scale over long distances through ultra-high voltage direct current transmission technology to achieve cross-regional resource allocation. However, wind power has strong randomness and intermittency, and it is necessary to use dispatchable thermal power to compensate for the uncertainty of wind power. In recent years, various regions have built a wind-thermal bundled transmission model via direct current, which has become the main means of delivering clean electricity.
[0003] However, when a DC transmission system encounters a fault such as DC blocking, a large amount of surplus reactive power will be fed back to the AC system, causing severe transient overvoltage and threatening system safety. Summary of the invention
[0004] In order to overcome the shortcomings of the prior art, the purpose of the present invention is to provide a planning method for a wind-fire bundled DC transmission system taking into account transient overvoltage constraints. Through the transient overvoltage constraint formula, the problem of transient overvoltage at the sending end after a DC fault, which easily causes the wind turbine to be disconnected from the grid and threatens the safe and stable operation of the system, is solved; through the upper-level planning model objective function, the lower-level optimization model objective function, the upper-level constraints and the lower-level constraints, the optimal planning scheme is obtained.
[0005] To achieve the above object, the present invention provides the following solutions:
[0006] A planning method for a wind-thermal bundled DC transmission system taking into account transient overvoltage constraints comprises:
[0007] Construct the first short-circuit capacity calculation formula at the commutation bus of a thermal power plant;
[0008] Construct a calculation formula for the second short-circuit capacity of the wind farm at the commutation bus;
[0009] The first short-circuit capacity calculation formula and the second short-circuit capacity calculation formula are combined to obtain an overall short-circuit capacity calculation formula; the overall short-circuit capacity calculation formula is: Among them, S C is the calculation result of the overall short-circuit capacity; S w_L,i The wind farm is short-circuited locally at the commutation busbar; S T is the short-circuit capacity of the thermal power plant at the commutation bus; N w is the number of the wind farms; i represents the i-th wind farm;
[0010] A transient overvoltage constraint formula of the short circuit ratio is constructed; the transient overvoltage constraint formula is:
[0011]
[0012] Among them, k ST The total amount of short-circuit capacity provided for the thermal power plant; P T_total is the total installed capacity of the thermal power plant; S Cmin is the minimum short-circuit capacity; k Swi The short-circuit capacity factor provided by the wind farm at the grid connection point; P aw_totali is the equivalent operating capacity of the wind farm; U PCCi is the rated voltage;
[0013] Construct an upper-level planning model objective function; the upper-level planning model objective function includes:
[0014] minC total =C inv +C maint +C op and
[0015]
[0016] Among them, C total is the total system cost; C inv is the power supply investment cost; C maint is the maintenance cost; C op is the operating cost; CRF is the coefficient of equal annual value; N w1 is the number of wind farms; C w N is the investment and construction cost of a single wind farm; g is the number of thermal power plants; C g is the investment and construction cost of a single thermal power plant; d is the discount rate; j represents the jth year; is the maintenance factor of the thermal power plant; r maint is the maintenance cost growth rate; Y is the planned life; D is the total number of operating days; d represents the dth operating day; is the typical daily operating cost of the system;
[0017] Constructing a lower-level optimization model objective function; the lower-level optimization model objective function includes:
[0018]
[0019] Among them, F = min () is the minimum value function; C g,t is the operating cost of the thermal power plant; is the cost of wind power abandonment; t represents the tth period; N T is the number of scheduling periods; Cost of curtailed wind power; for; a g , b g 、c g All are power generation cost coefficients; is the startup cost of the thermal power plant; is the shutdown cost of the thermal power plant; is the startup state variable of the thermal power plant; is the shutdown state variable of the thermal power plant; λ is the penalty cost coefficient for wind power abandonment; is the predicted power of the wind farm; t dw is the dispatching power of the wind farm;
[0020] The upper-level constraints and the lower-level constraints are respectively constructed according to the upper-level planning model objective function and the lower-level optimization model objective function; the upper-level constraints include: planning capacity constraints and power generation capacity constraints; the lower-level constraints include: power balance constraints, field output constraints, thermal power plant ramp rate constraints, spinning reserve constraints, power grid support power constraints, and new energy proportion constraints for transmission channels;
[0021] According to the upper-level constraints and the lower-level constraints, the overall short-circuit capacity calculation formula, the transient overvoltage constraint formula, the upper-level planning model objective function and the lower-level optimization model objective function are optimally solved to obtain the target investment capacity and system output parameters.
[0022] Preferably, the planned capacity constraint is:
[0023]
[0024] Among them, c w,min 、c w,max are the lower and upper limits of the installed capacity of the wind power station respectively; P w is the capacity of a single wind turbine; c g,min 、c g,max are the lower and upper limits of the installed capacity of the thermal power plant respectively; P T is the capacity of a single thermal power plant.
[0025] Preferably, the power generation capacity constraint of the power source is:
[0026]
[0027] Among them, k w_e is the average output level of wind power; P w_total,i is the installed capacity of a single wind farm; dN Rated DC power delivery.
[0028] Preferably, the power balance constraint is:
[0029]
[0030] in, Power for the grid support; P t HVDC is the DC transmission power.
[0031] Preferably, the field output constraint is:
[0032]
[0033] Among them, u g,t P is the running state; g,min , P g,m ax are respectively the lower limit and upper limit of the active output of the thermal power plant.
[0034] Preferably, the ramp rate constraint of the thermal power plant is:
[0035]
[0036] in, are the field upward climbing rate and the field downward climbing rate respectively; ΔT is the scheduling time interval.
[0037] Preferably, the spinning reserve constraint is:
[0038]
[0039] in, r t up are respectively the downward reserve capacity and the upward reserve capacity of the thermal power plant; r t dn They are the system downward spare capacity demand and the system upward spare capacity demand respectively.
[0040] Preferably, the grid support power constraint is:
[0041]
[0042] Among them, ξ is the power grid support coefficient.
[0043] Preferably, the new energy proportion constraint of the transmission channel is:
[0044]
[0045] Among them, P t HVDC is the DC transmission power; δ is the required proportion of new energy in the transmission channel.
[0046] The present invention discloses the following technical effects:
[0047] The present invention provides a planning method for a wind-fire bundled DC transmission system taking into account transient overvoltage constraints. Through the transient overvoltage constraint formula, the problem of transient overvoltage at the sending end after a DC fault easily causing the wind turbine to be disconnected from the grid and threatening the safe and stable operation of the system is solved, and reasonable planning of operation safety and voltage support strength is achieved; through the upper-level planning model objective function, the lower-level optimization model objective function, the upper-level constraints and the lower-level constraints, the problem of a large amount of surplus reactive power being fed back to the AC system during DC locking is avoided, and the optimal planning scheme is obtained. BRIEF DESCRIPTION OF THE DRAWINGS
[0048] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative labor.
[0049] Figure 1 A schematic diagram of the planning process of a wind-fire bundled DC transmission system provided in an embodiment of the present invention;
[0050] Figure 2 A schematic diagram of a typical wind-fire bundled DC transmission system provided in an embodiment of the present invention;
[0051] Figure 3 A schematic diagram of transient overvoltage conditions under a DC system blocking fault provided by an embodiment of the present invention;
[0052] Figure 4 A schematic diagram of changes in wind power indicators under different thermal power capacities provided by an embodiment of the present invention. DETAILED DESCRIPTION
[0053] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0054] The purpose of the present invention is to provide a planning method for a wind-fire bundled DC transmission system taking into account transient overvoltage constraints. Through the transient overvoltage constraint formula, the problem of transient overvoltage at the sending end after a DC fault easily causes the wind turbine to be disconnected from the grid and threatens the safe and stable operation of the system is solved; through the upper-level planning model objective function, the lower-level optimization model objective function, the upper-level constraints and the lower-level constraints, the optimal planning scheme is obtained.
[0055] In order to make the above-mentioned objects, features and advantages of the present invention more obvious and easy to understand, the present invention is further described in detail below with reference to the accompanying drawings and specific embodiments.
[0056] Figure 1 A schematic diagram of the planning process of the wind-fire bundled DC transmission system provided in an embodiment of the present invention is shown in FIG. Figure 1 As shown, the present invention provides a planning method for a wind-thermal bundled DC transmission system taking into account transient overvoltage constraints, comprising:
[0057] Construct the first short-circuit capacity calculation formula at the commutation bus of a thermal power plant;
[0058] Construct a calculation formula for the second short-circuit capacity of the wind farm at the commutation bus;
[0059] The first short-circuit capacity calculation formula and the second short-circuit capacity calculation formula are combined to obtain an overall short-circuit capacity calculation formula; the overall short-circuit capacity calculation formula is: Among them, S C is the calculation result of the overall short-circuit capacity; S w_L,i The wind farm is short-circuited locally at the commutation busbar; S T is the short-circuit capacity of the thermal power plant at the commutation bus; N w is the number of the wind farms; i represents the i-th wind farm;
[0060] A transient overvoltage constraint formula of the short circuit ratio is constructed; the transient overvoltage constraint formula is:
[0061]
[0062] Among them, k ST The total amount of short-circuit capacity provided for the thermal power plant; P T_total is the total installed capacity of the thermal power plant; S Cmin is the minimum short-circuit capacity; k Swi The short-circuit capacity factor provided by the wind farm at the grid connection point; P aw_totali is the equivalent operating capacity of the wind farm; U PCCi is the rated voltage;
[0063] Construct an upper-level planning model objective function; the upper-level planning model objective function includes:
[0064] minC total =C inv +C maint +C op and
[0065]
[0066] Among them, C total is the total system cost; C inv is the power supply investment cost; C maint is the maintenance cost; C op is the operating cost; CRF is the coefficient of equal annual value; N w1 is the number of wind farms; C w N is the investment and construction cost of a single wind farm; g is the number of thermal power plants; C g is the investment and construction cost of a single thermal power plant; d is the discount rate; j represents the jth year; is the maintenance factor of the thermal power plant; r maint is the maintenance cost growth rate; Y is the planned life; D is the total number of operating days; d represents the dth operating day; is the typical daily operating cost of the system;
[0067] Constructing a lower-level optimization model objective function; the lower-level optimization model objective function includes:
[0068]
[0069] Among them, F = min () is the minimum value function; C g,t is the operating cost of the thermal power plant; is the cost of wind power abandonment; t represents the tth period; N T is the number of scheduling periods; Cost of curtailed wind power; for; a g , b g 、c g All are power generation cost coefficients; is the startup cost of the thermal power plant; is the shutdown cost of the thermal power plant; is the startup state variable of the thermal power plant; is the shutdown state variable of the thermal power plant; λ is the penalty cost coefficient for wind power abandonment; is the predicted power of the wind farm; t dw is the dispatching power of the wind farm;
[0070] The upper-level constraints and the lower-level constraints are respectively constructed according to the upper-level planning model objective function and the lower-level optimization model objective function; the upper-level constraints include: planning capacity constraints and power generation capacity constraints; the lower-level constraints include: power balance constraints, field output constraints, thermal power plant ramp rate constraints, spinning reserve constraints, power grid support power constraints, and new energy proportion constraints for transmission channels;
[0071] According to the upper-level constraints and the lower-level constraints, the overall short-circuit capacity calculation formula, the transient overvoltage constraint formula, the upper-level planning model objective function and the lower-level optimization model objective function are optimally solved to obtain the target investment capacity and system output parameters.
[0072] Specifically, the planned capacity constraint is:
[0073]
[0074] Among them, c w,min 、c w,max are the lower and upper limits of the installed capacity of the wind power station respectively; P w is the capacity of a single wind turbine; c g,min 、c g,max are the lower and upper limits of the installed capacity of the thermal power plant respectively; P T is the capacity of a single thermal power plant.
[0075] Furthermore, the power generation capacity constraint of the power source is:
[0076]
[0077] Among them, k w_e is the average output level of wind power; P w_total,i is the installed capacity of a single wind farm; dN Rated DC power delivery.
[0078] Specifically, the power balance constraint is:
[0079]
[0080] in, Power for the grid support; P t HVDC is the DC transmission power.
[0081] Furthermore, the field output constraint is:
[0082]
[0083] Among them, u g,t P is the running state; g,min , P g,m ax are respectively the lower limit and upper limit of the active output of the thermal power plant.
[0084] Specifically, the ramp rate constraint of the thermal power plant is:
[0085]
[0086] in, are the field upward climbing rate and the field downward climbing rate respectively; ΔT is the scheduling time interval.
[0087] Furthermore, the spinning reserve constraint is:
[0088]
[0089] in, r t up are respectively the downward reserve capacity and the upward reserve capacity of the thermal power plant; r t dn They are the system downward spare capacity demand and the system upward spare capacity demand respectively.
[0090] Specifically, the grid support power constraint is:
[0091]
[0092] Among them, ξ is the power grid support coefficient.
[0093] Furthermore, the new energy proportion constraint of the transmission channel is:
[0094]
[0095] Among them, P t HVDC is the DC transmission power; δ is the required proportion of new energy in the transmission channel.
[0096] Specifically, the wind power and thermal power plants model the system voltage strength support capability. Typical wind-thermal bundled DC transmission systems are as follows: Figure 2 The reactive power consumed by the UHV DC converter during normal operation is provided by the capacitor bank and AC filter bank in the converter station. The power balance relationship between the AC and DC systems during normal operation can be expressed as:
[0097]
[0098] Among them, P ac_N , Q ac_N are respectively the active power and reactive power fed into the rectifier station by AC; P d_N , Q d_N are the active power and reactive power of DC transmission respectively; Q Cr_N Reactive power provided by the reactive power compensation device in the converter station; the subscript N indicates the normal operating state.
[0099] When a DC blocking fault occurs, the converter will no longer consume reactive power, and a large amount of reactive power surplus will appear in the wind-fire bundling system at the sending end, which can be expressed as:
[0100] ΔQ=Q ac_N +Q Cr
[0101] The commutation bus voltage U on the rectifier side after DC blocking Lr,pu As shown below:
[0102]
[0103] Among them, Q Cr_rated is the rated value of the reactive power compensation device in the converter station; S C is the short-circuit capacity of the AC system.
[0104] Furthermore, the transient overvoltage amplitude after DC blocking is mainly affected by the rated value Q of the reactive power compensation device in the converter station. Cr_rated The reactive power consumed by the rectifier during normal operation is related to Q Cr_rated Basically, there will be no significant changes. The short-circuit capacity S at the commutation bus C It is the dominant factor affecting transient overvoltage.
[0105] Preferably, taking a single wind farm as an example, the capacity of a single wind farm is expressed as P w , the number of wind farms is n w , then the installed capacity of the wind farm P w_total It can be expressed as:
[0106] P w_total =n w P w
[0107] The number of supporting power stations in the DC transmission system is N g , the capacity of a single unit is P T , assuming that the short-circuit capacity factor provided by the thermal power plant is k ST , the total installed capacity of thermal power is P T_total , the short-circuit capacity S provided by the thermal power plant at the commutation bus T As shown below:
[0108] S T =k ST P T_total =k ST N g P T
[0109] The short-circuit capacity provided by the wind farm at the grid connection point is proportional to its own capacity k Sw The equivalent operating capacity of the wind farm is P aw_total , the rated voltage of PCC point is U PCC , Z wis the equivalent impedance of the wind farm, Z P_L is the equivalent impedance from the wind farm to the converter busbar, and the short-circuit capacity S provided by the wind farm at the grid connection point w The short-circuit capacity provided at the commutation bus is as follows:
[0110]
[0111] Then the short-circuit capacity provided by the wind power bundling system at the commutation busbar can be expressed as:
[0112]
[0113] Among them, N w is the number of wind farms; S w_L,i Short-circuit capacity provided for wind farms.
[0114] Specifically, transient overvoltage constraints are constructed taking into account the safety of wind power operation. The high voltage ride-through capability of the wind farm is U HVRT , the commutation bus voltage caused by DC fault should satisfy the following formula:
[0115] U Lr,pu ≤U HVRT
[0116] Minimum short circuit capacity S Cmin It can be expressed as:
[0117]
[0118] Taking into account the safety of wind power operation, the transient overvoltage constraint formula based on the short-circuit ratio is:
[0119]
[0120] Specifically, a transmission system collaborative planning model considering transient overvoltage constraints is constructed. A two-level planning model for wind-thermal bundled DC transmission system considering transient overvoltage constraints is established. The upper-level planning model is based on the total system cost C total The goal is to minimize the cost of the power supply, as shown in the following formula, including the power supply investment cost C inv , Maintenance cost C maint and operating cost C op .
[0121] min C total =C inv +C maint +C op
[0122]
[0123] Among them, C w and C gN is the investment and construction cost of a single wind power plant and thermal power plant; w1 and N g is the number of wind power and thermal power plants; Y is the planning period; is the maintenance factor of thermal power plant g; r d is the discount rate; r maint is the growth rate of maintenance cost; is the typical daily operating cost of the system.
[0124] Furthermore, the model constraints are as follows:
[0125] 1) Planning capacity constraints:
[0126]
[0127] 2) Power generation capacity constraints:
[0128]
[0129] Specifically, the objective function of the lower-level optimization model is as follows. It aims to minimize the comprehensive cost consisting of the operating cost of the thermal power plant, the start-up and shutdown cost, and the penalty cost for wind power abandonment, so as to achieve the goals of minimizing the system operating cost and maximizing the wind power consumption.
[0130]
[0131] Furthermore, the operating constraints of the lower-level scheduling model are as follows:
[0132] 1) Power balance constraints:
[0133]
[0134] 2) Field output constraints:
[0135]
[0136] 3) Thermal power plant ramp rate constraints:
[0137]
[0138] 4) Spinning reserve constraints:
[0139]
[0140] 5) Grid support power constraints:
[0141]
[0142] 6) Constraints on the proportion of new energy in the transmission channel:
[0143]
[0144] Specifically, based on the constructed optimization model and objective function, the Yalmip toolbox combined with the commercial optimization software GUROBI is used to solve the problem, and the economically optimal thermal power plant and wind power investment capacity that meet the system constraints, as well as the operating status u of a typical thermal power plant g during period t are obtained. g,t , power generation P g,t ; Wind power output P during period t t dw , realizing the effective output of new energy from the wind-fire bundled DC transmission system.
[0145] Furthermore, the following two planning schemes are set up for analysis and comparison:
[0146] Scheme 1: Planning scheme for wind-fire bundling system without considering transient overvoltage constraints.
[0147] Scheme 2: Wind-fire bundling system planning scheme considering transient overvoltage constraints. The grid support coefficient is set to 0 (i.e., grid support is not considered).
[0148] Furthermore, Table 1 shows the optimization results of different planning schemes. As shown in Table 1, Scheme 2 takes into account transient overvoltage constraints. To ensure that the system has sufficient short-circuit capacity, the installed capacity of thermal power and wind power in the planning results increased by 12.5% and 37% respectively compared with Scheme 1. At the same time, the annual average operating cost and total investment cost increased by 1.77 billion yuan and 17.12 billion yuan respectively, corresponding to a ratio of 18.5% and 28.0%. Figure 3 As shown in the figure, when a lockout fault occurs in the transmission system, the transient overvoltage of the wind-fire bundled system planned in Scheme 2 is relatively low, which can ensure the system safety during severe DC faults and ensure that the transient overvoltage level after the DC fault basically meets the requirements, sacrificing a certain degree of economic efficiency to ensure the safe operation of the system. On the other hand, although the economic efficiency of Scheme 2 is lower than that of Scheme 1, the proportion of wind power in the transmitted electricity (i.e., penetration rate) is 63.81%, and the rate of abandoned electricity of new energy is 32.64%, which is an increase of 11.31% and 7.75% respectively compared with Scheme 1, which effectively improves the green electricity penetration rate of the transmission channel and ensures the efficient transmission and cross-regional sharing of new energy. Therefore, although the economic efficiency of the proposed planning scheme has been reduced, it effectively guarantees the operational safety and wind power penetration rate in the case of transmission system failure, and can provide guidance for gradually increasing the proportion of transmitted new energy electricity.
[0149] Table 1
[0150]
[0151] Furthermore, in order to analyze the impact characteristics of thermal power installed capacity in the planning of wind-thermal bundled transmission system, Figure 4 The changes in wind power penetration rate, consumption rate and installed capacity under different thermal power installed capacities. Figure 4It can be seen that with the increase of thermal power installed capacity, the installed capacity of supporting wind power gradually decreases. At the same time, the penetration rate of wind power in the transmission system also gradually decreases, and the wind power consumption rate gradually increases. This is because the effective output of wind power gradually decreases, and the difficulty of consumption is reduced. However, it also makes the wind power included in the transmitted power significantly reduced, which makes it difficult to meet the requirements of gradually increasing the penetration rate of green electricity. Therefore, the proposed method takes into account the system transient overvoltage safety, wind power penetration rate and consumption rate requirements, and formulates the capacity of the wind-fire bundled transmission system. The installed capacities of thermal power and wind power are 5760MW and 13228MW respectively, the wind-fire bundling ratio is 2.29:1, and the wind power penetration rate is 63.81%, which has good practicality.
[0152] The beneficial effects of the present invention are as follows:
[0153] The present invention solves the problem that transient overvoltage at the sending end after a DC fault easily causes the wind turbine to be disconnected from the grid and threatens the safe and stable operation of the system through the transient overvoltage constraint formula; and realizes the acquisition of the optimal planning scheme through the upper-level planning model objective function, the lower-level optimization model objective function, the upper-level constraints and the lower-level constraints.
[0154] The various embodiments in this specification are described in a progressive manner, and each embodiment focuses on the differences from other embodiments. The same or similar parts between the various embodiments can be referenced to each other.
[0155] The principles and implementation methods of the present invention are described in this article using specific examples. The description of the above embodiments is only used to help understand the method and core idea of the present invention. At the same time, for those skilled in the art, according to the idea of the present invention, there will be changes in the specific implementation methods and application scope. In summary, the content of this specification should not be understood as limiting the present invention.
Claims
1. A planning method for a wind-fired bundled DC transmission system taking into account transient overvoltage constraints, characterized in that: include: Construct the first short-circuit capacity calculation formula at the commutation busbar of a thermal power plant; Construct a calculation formula for the second short-circuit capacity of the wind farm at the commutation bus; The first short-circuit capacity calculation formula and the second short-circuit capacity calculation formula are combined to obtain an overall short-circuit capacity calculation formula; the overall short-circuit capacity calculation formula is: Among them, S C is the calculation result of the overall short-circuit capacity; S w_L,i The wind farm is short-circuited locally at the commutation busbar; S T is the short-circuit capacity of the thermal power plant at the commutation bus; N w is the number of the wind farms; i represents the i-th wind farm; A transient overvoltage constraint formula of the short circuit ratio is constructed; the transient overvoltage constraint formula is: Among them, k ST The total amount of short-circuit capacity provided for the thermal power plant; P T_total is the total installed capacity of the thermal power plant; S Cmin is the minimum short-circuit capacity; k Swi The short-circuit capacity factor provided by the wind farm at the grid connection point; P aw_totali is the equivalent operating capacity of the wind farm; U PCCi is the rated voltage; Construct an upper-level planning model objective function; the upper-level planning model objective function includes: minC total =C inv +C maint +C op and Among them, C total is the total system cost; C inv is the power supply investment cost; C maint is the maintenance cost; C op is the operating cost; CRF is the coefficient of equal annual value; N w1 is the number of wind farms; C w N is the investment and construction cost of a single wind farm; g is the number of thermal power plants; C g is the investment and construction cost of a single thermal power plant; d is the discount rate; j represents the jth year; is the maintenance factor of the thermal power plant; r maint is the maintenance cost growth rate; Y is the planned life; D is the total number of operating days; d represents the dth operating day; is the typical daily operating cost of the system; Constructing a lower-level optimization model objective function; the lower-level optimization model objective function includes: Among them, F = min () is the minimum value function; C g,t is the operating cost of the thermal power plant; is the cost of wind power abandonment; t represents the tth period; N T is the number of scheduling periods; Cost of curtailed wind power; for; a g , b g 、c g All are power generation cost coefficients; is the startup cost of the thermal power plant; is the shutdown cost of the thermal power plant; is the startup state variable of the thermal power plant; is the shutdown state variable of the thermal power plant; λ is the penalty cost coefficient for wind power abandonment; is the predicted power of the wind farm; is the dispatching power of the wind farm; The upper-level constraints and the lower-level constraints are respectively constructed according to the upper-level planning model objective function and the lower-level optimization model objective function; the upper-level constraints include: planning capacity constraints and power generation capacity constraints; the lower-level constraints include: power balance constraints, field output constraints, thermal power plant ramp rate constraints, spinning reserve constraints, power grid support power constraints, and new energy proportion constraints for transmission channels; According to the upper-level constraints and the lower-level constraints, the overall short-circuit capacity calculation formula, the transient overvoltage constraint formula, the upper-level planning model objective function and the lower-level optimization model objective function are optimally solved to obtain the target investment capacity and system output parameters.
2. According to the method for planning a wind-fired bundled DC transmission system taking into account transient overvoltage constraints as described in claim 1, it is characterized in that: The planned capacity constraint is: Among them, c w,min 、c w,max are the lower and upper limits of the installed capacity of the wind power station respectively; P w is the capacity of a single wind turbine; c g,min 、c g,max are the lower and upper limits of the installed capacity of the thermal power plant respectively; P T is the capacity of a single thermal power plant.
3. According to the method for planning a wind-fired bundled DC transmission system taking into account transient overvoltage constraints as described in claim 2, it is characterized in that: The power generation capacity constraint is: Among them, k w_e is the average output level of wind power; P w_total,i is the installed capacity of a single wind farm; P dN Rated DC power delivery.
4. According to the method for planning a wind-fired bundled DC transmission system taking into account transient overvoltage constraints as described in claim 3, it is characterized in that: The power balance constraint is: in, Power for the grid support; P t HVDC is the DC transmission power.
5. According to the method for planning a wind-fired bundled DC transmission system taking into account transient overvoltage constraints as described in claim 4, it is characterized in that: The field output constraint is: Among them, u g,t P is the running state; g,min , P g,max are respectively the lower limit and upper limit of the active output of the thermal power plant.
6. A planning method for a wind-fired bundled DC transmission system taking into account transient overvoltage constraints according to claim 5, characterized in that: The thermal power plant ramp rate constraint is: in, are the field upward climbing rate and the field downward climbing rate respectively; ΔT is the scheduling time interval.
7. A planning method for a wind-fired bundled DC transmission system taking into account transient overvoltage constraints according to claim 6, characterized in that: The spinning reserve constraints are: in, are respectively the downward reserve capacity and the upward reserve capacity of the thermal power plant; They are the system downward spare capacity demand and the system upward spare capacity demand respectively.
8. The method for planning a wind-fired bundled DC transmission system taking into account transient overvoltage constraints according to claim 7 is characterized in that: The grid support power constraint is: Among them, ξ is the power grid support coefficient.
9. A planning method for a wind-fired bundled DC transmission system taking into account transient overvoltage constraints according to claim 8, characterized in that: The constraint on the proportion of new energy in the transmission channel is: in, is the DC transmission power; δ is the required proportion of new energy in the transmission channel.