Pressure relief device for water supply pipeline
By designing a water supply pipeline pressure relief device including a connecting pipe, a pressure relief box and a power generation box, the existing pressure relief device wastes water resources and valve bursts are solved, and the combination of water resource conservation, valve safety and self-generating function is achieved.
Patent Information
- Application Number
- CN202411933630.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-12-26
- Publication Date
- 2025-03-11
AI Technical Summary
The existing water supply pipeline pressure relief device will cause a large amount of water resources to be wasted during pressure relief operation, and it is easy to cause valve burst when the water pressure is high, affecting water safety.
A water supply pipe pressure relief device is designed, including a communication pipe, a first pressure relief box, a second pressure relief box and a power generation box. By setting up a water barrier and a blocking ball in the communication pipe, the threaded rod and belt system is driven by a motor to achieve water diversion and re-sinking, saving water resources, and monitoring water pressure, early warning and pressure relief through self-generating functions.
It effectively saves water resources, prevents the valve from bursting under high water pressure, provides early warning time, and realizes self-generating function without external power supply, improving the safety and efficiency of pressure relief operations.
Smart Images

Figure CN119594343A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of pressure relief devices, in particular to a water supply pipeline pressure relief device. Background Art
[0002] The valve is a control component in the fluid conveying system, which has the functions of shutoff, regulation, diversion, backflow prevention, pressure stabilization, diversion or overflow pressure relief. The valves used in fluid control systems are of various types and specifications, from the simplest shut-off valve to the various valves used in extremely complex automatic control systems. Valves can be used to control the flow of various types of fluids such as air, water, steam, various corrosive media, mud, oil, liquid metal and radioactive media. Valves are also divided into cast iron valves, cast steel valves, stainless steel valves, chrome-molybdenum steel valves, chrome-molybdenum-vanadium steel valves, duplex steel valves, plastic valves, non-standard custom valves, etc. according to the material. When the water flow inside the pipeline is fast, the impact of the water flow is too large, and the sudden large amount of water flow may cause the water valve to burst, etc., which will seriously affect the residents' domestic water use. Based on the above possible situations, a valve that can effectively prevent the water valve from bursting under the action of water pressure is needed.
[0003] When performing pressure relief operations, the existing technologies mostly achieve pressure relief by directly releasing the domestic water in the pipes, but this will result in a large amount of water resource waste. Therefore, when the pressure requirement is not exceeded by much, the water in the pipes can be diverted to reduce the water volume in the pipes at the same time. After adjusting the water pressure at the source, the diverted water can be reintegrated to save water resources. Summary of the invention
[0004] The purpose of the present invention is to provide a water supply pipeline pressure relief device to solve the problems raised in the background technology.
[0005] An embodiment of the present application provides a water supply pipe pressure relief device, including a connecting pipe, a first pressure relief tank is fixedly installed on the connecting pipe, a first motor is fixedly installed on the first pressure relief tank, a flange is fixedly installed on the connecting pipe, an installation box is provided on the connecting pipe, a pressure gauge is provided on the installation box, a second pressure relief tank is fixedly installed on the connecting pipe, and a pipeline is provided between the first pressure relief tank and the second pressure relief tank.
[0006] By adopting the above technical scheme, the device is installed on the water supply pipe. When the water pressure in the water supply pipe is relatively large, the water pressure in the connecting pipe will increase. When the water pressure in the connecting pipe is relatively large, the water baffle in the first pressure relief box will be squeezed to move. When the water baffle moves to the top of the water outlet, water can enter the pipe through the water outlet. When water enters the second pressure relief box through the pipe and the water inlet, it will squeeze the blocking ball. When the amount of water in the second pressure relief box is large enough to squeeze the blocking ball downward, the second spring will contract, so that the blocking ball will move out of the circular groove, and water can flow into the connecting pipe again through the circular groove and the water outlet groove. When connecting to different water supply pipes, personnel can make adjustments according to the maximum water pressure value that the water supply pipe to be processed can withstand. Starting the first motor can drive the threaded rod to rotate. When the threaded rod rotates, it will drive the sleeve to move, thereby driving the moving block to move, thereby squeezing the first spring. When the first spring is squeezed, its impact on the bottom will increase. The pressure of the movable plate can be adjusted to adjust the pressure that the pressure relief box can release. At the same time, when the amount of water in the pipeline is large, it will drive the blades to rotate, thereby driving the first rotating wheel to rotate, thereby driving the first belt to rotate, thereby driving the second rotating wheel to rotate. When the second rotating wheel rotates, it will drive the rotating block to rotate, thereby driving the mechanism in the placement box to rotate, so that self-generation can be performed. The electricity generated by self-generation can be used for structures such as the PLC control board. A speed test sensor is provided on the first rotating wheel. When the sensor sends a large signal, it means that the water pressure in the pipeline is also large. At this time, the PLC control board can open the electric baffle on the second pressure relief box to release the internal pressure. After the above operation, when the pressure in the connecting pipe is large, it can be diverted, and the diverted water can be re-entered into the connecting pipe at the rear, saving water resources and providing a certain warning time. If the source of the connecting pipe is not processed in time, when the pressure in the pipeline also increases, the final water discharge and pressure relief operation will be performed on it.
[0007] Optionally, a power generation box is fixedly mounted on the second pressure relief box.
[0008] By adopting the technical solution, it is easy to use.
[0009] Optionally, the first pressure relief box is provided with an inner cavity, the output end of the first motor is fixedly mounted with a threaded rod passing through the first pressure relief box, a mounting plate is fixedly mounted on the inner wall of the first pressure relief box, and a control unit is fixedly mounted on the mounting plate.
[0010] By adopting the above technical solution, the first motor can be started to drive the threaded rod to rotate.
[0011] Optionally, a moving block is slidably installed in the control part, a sleeve is fixedly installed on the moving block, the threaded rod passes through the side wall of the control part and is threadedly connected to the sleeve, a first spring is fixedly installed at the lower end of the moving block, and a moving plate is fixedly installed at the lower end of the first spring.
[0012] By adopting the above technical solution, when the threaded rod rotates, it will drive the sleeve to move, thereby driving the moving block to move, thereby squeezing the first spring. When the first spring is squeezed, it will increase its pressure on the moving plate below, thereby adjusting the pressure that can be relieved by the pressure relief box.
[0013] Optionally, a connecting block is fixedly installed at the lower end of the movable plate, a water baffle is fixedly installed at the lower end of the connecting block, a water outlet is opened on the side wall of the first pressure relief box, and a pipe is arranged on the water outlet.
[0014] By adopting the above technical solution, when the water pressure in the connecting pipe is high, the water baffle in the first pressure relief box will be squeezed to move. When the water baffle moves to above the water outlet, water can enter the pipeline through the water outlet.
[0015] Optionally, a water inlet is provided on the side wall of the second pressure relief box, an inner cavity is provided in the second pressure relief box, a baffle is fixedly installed on the side wall of the inner cavity, a circular groove is provided on the baffle, a horizontal plate is fixedly installed on the side wall of the inner cavity below the baffle, a water outlet groove is provided on the horizontal plate, a second spring is fixedly installed on the horizontal plate, a blocking ball is fixedly installed on the second spring, and the diameter of the blocking ball is consistent with the diameter of the circular groove on the baffle.
[0016] By adopting the above technical solution, when water enters the second pressure relief tank through the pipe and the water inlet, it will squeeze the blocking ball. When the amount of water in the second pressure relief tank is large enough to squeeze the blocking ball downward, the second spring can contract, thereby moving the blocking ball out of the circular groove, and the water can flow into the connecting pipe again through the circular groove and the water outlet groove.
[0017] Optionally, a rotating shaft is rotatably mounted on the inner wall of one side of the pipeline close to the second pressure relief box, a blade is fixedly mounted on the rotating shaft, a first rotating wheel is fixedly mounted on the rotating shaft, a first belt is sleeved on the first rotating wheel, and a second rotating wheel is sleeved on the other end of the first belt.
[0018] By adopting the above technical solution, when the amount of water in the pipeline is large, it will drive the blades to rotate, thereby driving the first rotating wheel to rotate, thereby driving the first belt to rotate, and thereby driving the second rotating wheel to rotate.
[0019] Optionally, the second rotating wheel is rotatably mounted on the side wall of the generator box, a connecting shaft is fixedly mounted on the second rotating wheel, a rotating block is fixedly mounted on the connecting shaft passing through the side wall of the generator box, a placement box is fixedly mounted on the inner wall of the generator box next to the rotating block, a rotor and a stator are installed in the placement box, a mounting block is arranged next to the placement box, a PLC control panel is arranged on the mounting block, and an electric baffle is arranged on the side wall of the second pressure relief box.
[0020] By adopting the above technical solution, when the second rotating wheel rotates, it will drive the rotating block to rotate, thereby driving the mechanism in the placement box to rotate, so that self-generation can be performed. The electricity generated by self-generation can be used for structures such as the PLC control board. A speed test sensor is provided on the first rotating wheel. When the sensor transmits a large signal, it means that the water pressure in the pipeline is also large. At this time, the PLC control board can open the electric baffle on the second pressure relief box to release the pressure inside it.
[0021] Compared with the prior art, the technical solution of this application has the following beneficial effects: The present invention can generate electricity while diverting the pipeline by setting up a power generation box, so that it is easy to use and does not need to be connected to an external power source; the present invention can divert the connecting pipe when the pressure in the connecting pipe is relatively high by setting up a pipeline, and at the same time, the diverted water can be re-integrated into the connecting pipe at the rear, saving water resources and providing a certain amount of warning time. If the source of the connecting pipe is not processed in time, when the pressure in the pipeline also increases, the final water release and pressure relief operation will be performed on it. Other features, objects and advantages of the present invention will become more apparent from the detailed description of non-limiting embodiments made with reference to the following drawings: Figure 1 It is a structural schematic diagram of the present invention; Figure 2 It is a schematic diagram of the top view structure of the present invention; Figure 3 It is a schematic diagram of the internal structure of the first pressure relief tank of the present invention; Figure 4 Schematic diagram of the internal structure of the control unit in the present invention; Figure 5 It is a schematic diagram of the internal structure of the second pressure relief tank in the present invention; Figure 6 It is a schematic diagram of the structure of the rotating wheel in the present invention; Figure 7 It is a schematic diagram of the internal structure of the power generation box in the present invention.
[0022] In the figure: 1. connecting pipe; 2. flange; 3. first pressure relief box; 4. first motor; 5. pipeline; 6. pressure gauge; 7. second pressure relief box; 8. generator box; 9. mounting plate; 10. threaded rod; 11. control unit; 12. water baffle; 13. water outlet; 14. sleeve; 15. first spring; 16. moving plate; 17. baffle; 18. blocking ball; 19. second spring; 20. horizontal plate; 21. first rotating wheel; 22. first belt; 23. second rotating wheel; 24. blade; 25. rotating block; 26. placement box. DETAILED DESCRIPTION
[0023] See also Figure 1-7The present invention provides a technical solution: a water supply pipeline pressure relief device, comprising a connecting pipe 1, a first pressure relief tank 3 is fixedly installed on the connecting pipe 1, a first motor 4 is fixedly installed on the first pressure relief tank 3, a flange 2 is fixedly installed on the connecting pipe 1, an installation box is provided on the connecting pipe 1, a pressure gauge 6 is provided on the installation box, a second pressure relief tank 7 is fixedly installed on the connecting pipe 1, and a pipeline 5 is provided between the first pressure relief tank 3 and the second pressure relief tank 7.
[0024] In the technical solution of the present invention, Figure 2 As shown, a power generation box 8 is fixedly mounted on the second pressure relief box 7 for easy use.
[0025] In the technical solution of the present invention, Figure 3 As shown, the first pressure relief box 3 is provided with an inner cavity, and the output end of the first motor 4 passes through the first pressure relief box 3 and is fixedly installed with a threaded rod 10, and a mounting plate 9 is fixedly installed on the inner wall of the first pressure relief box 3, and a control unit 11 is fixedly installed on the mounting plate 9. When the first motor 4 is started, the threaded rod 10 can be driven to rotate.
[0026] In the technical solution of the present invention, Figure 4 As shown, a moving block is slidably installed in the control part 11, and a sleeve 14 is fixedly installed on the moving block. The threaded rod 10 passes through the side wall of the control part 11 and is threadedly connected with the sleeve 14. A first spring 15 is fixedly installed at the lower end of the moving block, and a moving plate 16 is fixedly installed at the lower end of the first spring 15. When the threaded rod 10 rotates, the sleeve 14 is driven to move, thereby driving the moving block to move, thereby squeezing the first spring 15. When the first spring 15 is squeezed, the pressure on the lower moving plate 16 is increased, thereby adjusting the pressure that can be relieved by the pressure relief box.
[0027] In the technical solution of the present invention, Figure 3 As shown, a connecting block is fixedly installed at the lower end of the movable plate 16, and a water baffle 12 is fixedly installed at the lower end of the connecting block. A water outlet 13 is opened on the side wall of the first pressure relief box 3, and a pipe 5 is arranged on the water outlet 13. When the water pressure in the connecting pipe 1 is relatively large, the water baffle 12 in the first pressure relief box 3 will be squeezed to move. When the water baffle 12 moves to above the water outlet 13, water can enter the pipe 5 through the water outlet 13.
[0028] In the technical solution of the present invention, Figure 5As shown, a water inlet is provided on the side wall of the second pressure relief box 7, an inner cavity is provided in the second pressure relief box 7, a baffle 17 is fixedly installed on the side wall of the inner cavity, a circular groove is provided on the baffle 17, a transverse plate 20 is fixedly installed on the side wall of the inner cavity below the baffle 17, a water outlet groove is provided on the transverse plate 20, a second spring 19 is fixedly installed on the transverse plate 20, a blocking ball 18 is fixedly installed on the second spring 19, and the diameter of the blocking ball 18 is consistent with the diameter of the circular groove on the baffle 17. When water enters the second pressure relief box 7 through the pipeline 5 and the water inlet, the blocking ball 18 will be squeezed. When the amount of water in the second pressure relief box 7 is large enough to squeeze the blocking ball 18 downward, the second spring 19 can be contracted, thereby causing the blocking ball 18 to move out of the circular groove, and the water can flow into the connecting pipe 1 again through the circular groove and the water outlet groove.
[0029] In the technical solution of the present invention, Figure 6 and 7 As shown, a rotating shaft is rotatably mounted on the inner wall of one side of the pipeline 5 close to the second pressure relief box 7, a blade 24 is fixedly mounted on the rotating shaft, a first rotating wheel 21 is fixedly mounted on the rotating shaft, a first belt 22 is sleeved on the first rotating wheel 21, and a second rotating wheel 23 is sleeved on the other end of the first belt 22. When the amount of water in the pipeline 5 is large, the blade 24 will be driven to rotate, thereby driving the first rotating wheel 21 to rotate, thereby driving the first belt 22 to rotate, and thereby driving the second rotating wheel 23 to rotate.
[0030] In the technical solution of the present invention, Figure 7 As shown, the second rotating wheel 23 is rotatably mounted on the side wall of the power generation box 8, and a connecting shaft is fixedly mounted on the second rotating wheel 23. A rotating block 25 is fixedly mounted on the connecting shaft passing through the side wall of the power generation box 8, and a placement box 26 is fixedly mounted on the inner wall of the power generation box 8 next to the rotating block 25. A rotor and a stator are installed in the placement box 26, and a mounting block is arranged next to the placement box 26. A PLC control board is arranged on the mounting block. An electric baffle is arranged on the side wall of the second pressure relief box 7. When the second rotating wheel 23 rotates, the rotating block 25 is driven to rotate, thereby driving the mechanism in the placement box 26 to rotate, so that self-generation can be performed. The electricity generated by self-generation can be used for structures such as the PLC control board. A speed test sensor is arranged on the first rotating wheel 21. When the sensor transmits a large signal, it indicates that the water pressure in the pipeline 5 is also large. At this time, the PLC control board can open the electric baffle on the second pressure relief box 7 to release the pressure inside it.
[0031] By adopting the above technical solution, the device is installed on the water supply pipeline. When the water pressure in the water supply pipeline is large, the water pressure in the connecting pipe 1 will increase. When the water pressure in the connecting pipe 1 is large, the water baffle 12 in the first pressure relief box 3 will be squeezed to move. When the water baffle 12 moves to above the water outlet 13, water can enter the pipeline 5 through the water outlet 13. When water enters the second pressure relief box 7 through the pipeline 5 and the water inlet, it will squeeze the blocking ball 18. When the water volume in the second pressure relief box 7 is large enough to squeeze the blocking ball 18 downward, The second spring 19 contracts, so that the blocking ball 18 moves out of the circular groove, and the water can flow into the connecting pipe 1 again through the circular groove and the water outlet groove. When connecting different water supply pipes, the personnel can adjust according to the maximum water pressure value that the water supply pipe that needs to be processed can withstand. Starting the first motor 4 can drive the threaded rod 10 to rotate. When the threaded rod 10 rotates, it will drive the sleeve 14 to move, thereby driving the moving block to move, thereby squeezing the first spring 15. When the first spring 15 is squeezed, it will increase. The pressure on the lower moving plate 16 can be increased, so that the pressure that can be released by the pressure relief box can be adjusted. At the same time, when the amount of water in the pipeline 5 is large, it will drive the blade 24 to rotate, thereby driving the first rotating wheel 21 to rotate, thereby driving the first belt 22 to rotate, thereby driving the second rotating wheel 23 to rotate. When the second rotating wheel 23 rotates, it will drive the rotating block 25 to rotate, thereby driving the mechanism in the placement box 26 to rotate, so that self-generation can be performed. The electricity generated by self-generation can be used for structures such as the PLC control board. A speed test sensor is provided on the first rotating wheel 21. When the sensor sends a large signal, it means that the water pressure in the pipeline 5 is also large. At this time, the PLC control board can open the electric baffle on the second pressure relief box 7 to release the pressure inside it. After the above operation, when the pressure in the connecting pipe 1 is large, it can be diverted, and the diverted water can be re-entered into the connecting pipe 1 at the rear, saving water resources and providing a certain warning time. If the source of the connecting pipe 1 is not processed in time, when the pressure in the pipeline 5 is also increased, the final water discharge and pressure relief operation will be performed on it.
Claims
1. A water supply pipeline pressure relief device, characterized in that: The invention comprises a connecting pipe (1), a first pressure relief box (3) is fixedly mounted on the connecting pipe (1), a first motor (4) is fixedly mounted on the first pressure relief box (3), a flange (2) is fixedly mounted on the connecting pipe (1), a mounting box is provided on the connecting pipe (1), a pressure gauge (6) is provided on the mounting box, a second pressure relief box (7) is fixedly mounted on the connecting pipe (1), and a pipeline (5) is provided between the first pressure relief box (3) and the second pressure relief box (7).
2. A water supply pipeline pressure relief device according to claim 1, characterized in that: A power generation box (8) is fixedly mounted on the second pressure relief box (7).
3. A water supply pipeline pressure relief device according to claim 1, characterized in that: The first pressure relief box (3) is provided with an inner cavity, the output end of the first motor (4) passes through the first pressure relief box (3) and is fixedly mounted with a threaded rod (10), a mounting plate (9) is fixedly mounted on the inner wall of the first pressure relief box (3), and a control unit (11) is fixedly mounted on the mounting plate (9).
4. A water supply pipeline pressure relief device according to claim 3, characterized in that: A moving block is slidably mounted in the control portion (11), a sleeve (14) is fixedly mounted on the moving block, the threaded rod (10) passes through the side wall of the control portion (11) and is threadedly connected to the sleeve (14), a first spring (15) is fixedly mounted on the lower end of the moving block, and a moving plate (16) is fixedly mounted on the lower end of the first spring (15).
5. A water supply pipeline pressure relief device according to claim 4, characterized in that: A connecting block is fixedly mounted on the lower end of the movable plate (16), and a water baffle (12) is fixedly mounted on the lower end of the connecting block. A water outlet (13) is provided on the side wall of the first pressure relief box (3), and a pipe (5) is provided on the water outlet (13).
6. A water supply pipeline pressure relief device according to claim 1, characterized in that: A water inlet is provided on the side wall of the second pressure relief box (7), an inner cavity is provided in the second pressure relief box (7), a baffle (17) is fixedly mounted on the side wall of the inner cavity, a circular groove is provided on the baffle (17), a horizontal plate (20) is fixedly mounted on the side wall of the inner cavity below the baffle (17), a water outlet groove is provided on the horizontal plate (20), a second spring (19) is fixedly mounted on the horizontal plate (20), a blocking ball (18) is fixedly mounted on the second spring (19), and the diameter of the blocking ball (18) is consistent with the diameter of the circular groove on the baffle (17).
7. A water supply pipeline pressure relief device according to claim 1, characterized in that: A rotating shaft is rotatably mounted on an inner wall of one side of the pipeline (5) close to the second pressure relief box (7), a blade (24) is fixedly mounted on the rotating shaft, a first rotating wheel (21) is fixedly mounted on the rotating shaft, a first belt (22) is sleeved on the first rotating wheel (21), and a second rotating wheel (23) is sleeved on the other end of the first belt (22).
8. A water supply pipeline pressure relief device according to claim 7, characterized in that: The second rotating wheel (23) is rotatably mounted on the side wall of the power generation box (8); a connecting shaft is fixedly mounted on the second rotating wheel (23); a rotating block (25) is fixedly mounted on the connecting shaft passing through the side wall of the power generation box (8); a placement box (26) is fixedly mounted on the inner wall of the power generation box (8) next to the rotating block (25); a rotor and a stator are mounted in the placement box (26); a mounting block is arranged next to the placement box (26); a PLC control panel is arranged on the mounting block; and an electric baffle is arranged on the side wall of the second pressure relief box (7).