Dynamic construction management method based on BIM technology
By building an information sharing platform based on BIM technology in construction management, real-time safe synchronization and intelligent analysis of construction site data is achieved, and the problems of untimely information sharing and lagging construction decisions in construction management are solved, and the efficiency and safety of construction management are improved.
Patent Information
- Application Number
- CN202411626910.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-11-14
- Publication Date
- 2025-03-11
AI Technical Summary
In the construction management of existing technologies, there are problems such as untimely information sharing, lagging construction decisions, unreasonable resource allocation, and insufficient construction risk monitoring, resulting in delays in construction progress, cost overruns and an increase in safety accidents.
By building an information sharing platform based on BIM technology, real-time safe synchronization of construction site data is achieved, combining sensor networks, drones and inspection robots to collect data in real time, conduct intelligent analysis and risk assessment, formulate and adjust construction decisions, automatically adjust construction plans and resource allocation, and regularly communicate through instant communication, video conferencing and shared document communication tools.
Real-time safe synchronization of construction site data is achieved, the efficiency and coordination of construction management is improved, construction safety is enhanced, the scientificity and accuracy of construction plans are improved, and the collaboration efficiency of the construction team and the transparency of project management are improved.
Smart Images

Figure CN119599833A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of BIM, and in particular to a dynamic construction management method based on BIM technology. Background Art
[0002] The construction industry is an important pillar of the national economy, but there are often many problems in traditional construction management. For example, there is a lack of effective information sharing mechanism between various departments on the construction site, which leads to untimely information transmission, thus affecting construction efficiency; the construction site management department is unable to grasp the actual situation of the construction site in real time, resulting in delayed construction decisions, which in turn affects the construction progress and quality; due to information opacity, resource allocation is unreasonable during the construction process, leading to project delays, cost overruns and safety accidents.
[0003] The emergence of BIM technology has made it possible to solve the limitations of traditional construction management. With its powerful information integration, visualization, simulation and analysis capabilities, BIM technology has provided strong support for the informatization of the construction industry.
[0004] At present, many projects only use BIM for static display, fail to effectively combine real-time data, lack of systematic dynamic management solutions, and thus cannot timely reflect the complex and changing environment of the construction site, increasing management risks. Therefore, a dynamic construction management method based on BIM technology is extremely important.
[0005] 1. Patent document CN111460570B discloses a complex structure node auxiliary construction method based on BIM technology. The above patent realizes the accurate construction of each node component and ensures the authenticity, accuracy, timeliness and traceability of engineering data. However, the above patent cannot realize the real-time and secure synchronization function of construction site data.
[0006] 2. Patent document CN116030229B discloses an AR-based construction BIM model visualization method and system. The above patent realizes the visualization of the construction BIM model and improves the guiding effect of the construction BIM model on building construction. However, the above patent cannot realize the real-time monitoring function of construction operation risks.
[0007] 3. Patent document CN113360583B discloses a construction progress visualization method based on the comparison between BIM model and monitoring image. The above patent realizes the expansion of the application path of BIM model and monitoring equipment in construction, and provides an intuitive and integrated information solution for construction progress management. However, the above patent cannot realize the function of formulating the optimal construction plan.
[0008] 4. Patent document CN118313640B discloses an intelligent construction operation and maintenance management system and method based on BIM technology. The above patent realizes real-time monitoring of various data on the construction site, timely detection of abnormal situations, and provides early warning and tracking functions, but the above patent cannot realize the regular communication function of construction team members.
[0009] In summary, the above patents cannot realize the real-time and secure synchronization of construction site data, the real-time monitoring of construction operation risks, the formulation of the optimal construction plan, and the regular communication of construction team members, which leads to problems such as untimely data transmission leading to project delays, construction accidents affecting construction progress, high construction costs, and low construction efficiency;
[0010] To this end, this application proposes a dynamic construction management method based on BIM technology to achieve real-time and secure synchronization of construction site data, real-time monitoring of construction operation risks, formulation of optimal construction plans, and regular communication among construction team members. Summary of the invention
[0011] The purpose of the present invention is to provide a dynamic construction management method based on BIM technology to solve the technical problems raised in the above background technology.
[0012] To achieve the above object, the present invention provides the following technical solution: a dynamic construction management method based on BIM technology, comprising the following steps:
[0013] S1. Construction of information sharing platform: Based on the needs of the construction site and construction operations, cloud computing technology is used to build a platform for multi-user real-time access, update and storage data, build a security system for the information sharing platform, and set up a permission management mechanism;
[0014] S2. Real-time data sharing: Use sensor networks, drones and inspection robots to collect data from the construction site in real time, including construction progress, material usage and equipment status. Through the designed standardized data interface, the collected data from the construction site is transmitted to the information sharing platform in real time. The information sharing platform standardizes the data and adds an accurate timestamp to the data. The processed data is shared with the software and equipment of different departments at the construction site through the standardized data interface.
[0015] S3. Update and display of BIM model: Use BIM software to build a three-dimensional model of the building according to construction requirements, upload the BIM model to the information sharing platform, and the information sharing platform will synchronize the data of the construction site to the BIM model in real time. According to the real-time synchronized data, the BIM model will be dynamically updated, and the dynamic BIM model will be displayed to various departments on the construction site in real time through the visual interface of the information sharing platform;
[0016] S4. Analysis and discussion of construction work: The information sharing platform conducts intelligent analysis of the data synchronized to the BIM model, performs risk analysis of construction work, makes and adjusts construction decisions, automatically adjusts construction plans and resource allocation, and introduces instant messaging, video conferencing and shared document communication tools on the information sharing platform. The information sharing platform formulates meeting schedules, regularly holds online discussion meetings for various departments and construction personnel, and evaluates project progress.
[0017] Preferably, the risk analysis of the construction work in step S4 includes the following steps:
[0018] Step 1: The information sharing platform formulates an inspection plan based on the construction environment data and construction needs. The platform shares the inspection plan with drones and inspection robots in real time. The inspection plan includes: regular inspection of the behavior of construction site personnel, equipment operation status, construction progress and material inventory;
[0019] Step 2: The information sharing platform collects inspection data and construction material transportation data in real time. The platform synchronizes environmental data, transportation data and inspection data to the BIM model in real time. The platform simulates and analyzes the data in the BIM model, evaluates the risks of construction material transportation, and identifies potential risks in the construction process, including: insufficient inventory of construction materials and failure to transport materials to the construction site in time, construction workers in dangerous environments and engaging in dangerous behaviors, and the construction site is in bad weather;
[0020] Step 3: The information sharing platform conducts a quantitative assessment of the identified risks, prioritizes the risks according to their severity and probability of occurrence, and develops emergency plans that prioritize high-priority risks.
[0021] Preferably, the making and adjusting of construction decisions in step S4 comprises the following steps:
[0022] Step 1: Based on the construction requirements and the analysis of the data in the BIM model, the information sharing platform initially formulates a construction plan, adjusts the personnel allocation of various departments on the construction site, plans the execution sequence of the construction projects, allocates construction equipment and materials for different construction projects, and designs a variety of different construction plans;
[0023] Step 2: The information sharing platform uses simulation and prediction technology to evaluate the impact of different construction plans on construction progress and construction costs. Based on the evaluation results of the construction plan, the information sharing platform selects the optimal construction plan. The information sharing platform synchronizes the construction plan to various departments on the construction site in real time and notifies the construction personnel to implement the construction plan as planned;
[0024] Step 3: The information sharing platform determines the actual construction progress of the construction site by analyzing the detection data and inspection data of the sensor network, and the planned progress of the construction site by predicting and analyzing the construction plan. The actual progress data is compared with the planned progress to determine the implementation of the construction plan. When the comparison result is large and the platform detects that there is a risk in the construction work, the information sharing platform analyzes and adjusts the construction plan.
[0025] Preferably, the preparation of the meeting schedule in step S4 includes the following steps:
[0026] Step 1: The information sharing platform plans the content of meetings on different topics based on construction needs, construction progress and construction risk information, and formulates a meeting schedule based on the importance and urgency of the meeting content and the time schedule of the construction project;
[0027] Step 2: Use the communication tools in the information sharing platform to send meeting notices to construction teams in different departments, including meeting agendas and meeting materials. The information sharing platform uses facial recognition technology to identify the identities of participants and determine their information;
[0028] Step 3: The information sharing platform records the meeting content in real time and promptly feeds back the meeting content to the management department. The information sharing platform regularly collects feedback from participants and replans the meeting schedule based on the feedback.
[0029] Preferably, the safety system construction in step S1 includes the following steps:
[0030] Step 1: According to the needs of construction work, design a data identification mechanism to identify the importance and sensitivity of data, use encryption algorithms to encrypt sensitive data and important data in the information sharing platform, and enable authorized users to access encrypted data through the set permission management mechanism;
[0031] Step 2: The information sharing platform formulates a data backup strategy based on the needs and progress of the construction work, automatically and regularly backs up the encrypted data, and standardizes the time for backing up data. It also sets a plan for automatically verifying the backup data, verifying the integrity and timeliness of the data, and formulating a plan for regularly cleaning up expired data based on the timeliness of the data.
[0032] Step 3: Deploy a network monitoring system to continuously monitor the network status and data transmission of the information sharing platform. When the network status is abnormal and the data is erroneous, quickly locate the fault location and notify the management staff to take recovery measures in time.
[0033] Preferably, the setting of the rights management mechanism in S1 includes the following steps:
[0034] Step 1: The information sharing platform provides different access channels for construction personnel according to their positions at the construction site, grants them different data access rights and modification rights, and uses a multi-factor authentication mechanism to verify user identities;
[0035] Step 2: The information sharing platform records the user’s data access and operation behavior in real time, including access time, access user, and modification record inspection and tracking.
[0036] Preferably, formulating the inspection plan in step 1 includes the following steps:
[0037] (1) The information sharing platform sets the inspection range and inspection route of the drone based on the environmental data of the construction site. The information sharing platform identifies the location information of construction equipment and construction personnel based on the inspection data shared by the drone.
[0038] (2) The information sharing platform analyzes the movement of construction equipment and construction personnel through location information and generates inspection strategies for inspection robots. The inspection robots execute inspection plans according to the inspection strategies and detect the construction progress and equipment status information of the construction equipment.
[0039] Preferably, the step 2 of assessing the risk of construction material transportation comprises the following steps:
[0040] (1) The information sharing platform analyzes the probability of construction vehicles encountering traffic jams based on the location information and road information of construction vehicles, and determines the impact of traffic jams, bad weather, and road damage on construction vehicles;
[0041] (2) The information sharing platform analyzes data to assess the risk of construction vehicles arriving late at the construction site and simulates the time points at which delayed construction vehicles arrive.
[0042] Preferably, the analysis and adjustment of the construction plan in step 3 includes the following steps:
[0043] (1) When the planned progress of construction differs greatly from the actual progress, the information sharing platform analyzes the delay and advance of the construction process and determines the actual factors affecting the difference in construction progress based on the risk information of the construction operation;
[0044] (2) The information sharing platform adjusts and optimizes the construction plans under different circumstances based on the analysis results. When the construction progress is affected by bad weather, the human resources, equipment resources, and network resources of the construction project are reallocated according to the scope of the impact.
[0045] (3) In the case of insufficient inventory or excessive accumulation of construction materials, the information sharing platform adjusts the construction plan, giving priority to construction projects with accumulated materials and reducing resource allocation for construction projects with insufficient inventory of construction materials.
[0046] Preferably, the information sharing platform is designed with multiple functional modules, including BIM model management, construction progress management, department communication management, inspection plan management and risk management.
[0047] Compared with the prior art, the present invention has the following beneficial effects:
[0048] 1. The present invention realizes the real-time and secure synchronization function of construction site data by constructing an information sharing platform, realizes the real-time feedback of construction site data to the BIM model, solves the problem that the BIM model cannot be dynamically updated, and improves the efficiency and coordination of construction management;
[0049] 2. The present invention realizes the real-time monitoring function of construction operation risks by conducting risk analysis of construction operations, realizes risk assessment of construction sites, improves construction safety, and solves construction progress problems caused by construction interruptions or delays;
[0050] 3. The present invention formulates a construction plan by analyzing the data in the BIM model, realizes the function of formulating the optimal construction plan, improves the construction efficiency and construction management level, and improves the scientificity and accuracy of the construction plan;
[0051] 4. The present invention realizes the regular communication function of construction team members by holding construction meetings regularly, thereby improving team collaboration efficiency, enhancing the transparency of project management, improving the efficiency of problem handling, and improving construction efficiency. BRIEF DESCRIPTION OF THE DRAWINGS
[0052] Figure 1 It is a schematic diagram of the steps of the construction management method of the present invention;
[0053] Figure 2 It is a schematic diagram of the risk analysis steps of the construction operation of the present invention;
[0054] Figure 3 A schematic diagram for making and adjusting construction decisions for the present invention;
[0055] Figure 4 A schematic diagram of the steps of formulating a meeting plan of the present invention;
[0056] Figure 5 It is a schematic diagram of the steps of building the security system of the present invention;
[0057] Figure 6 A schematic diagram of the steps for formulating an inspection plan of the present invention;
[0058] Figure 7 A schematic diagram of the steps for assessing the transportation risk of construction materials according to the present invention;
[0059] Figure 8 It is a schematic diagram of the analysis and adjustment steps of the construction scheme of the present invention. DETAILED DESCRIPTION
[0060] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0061] Example 1, please refer to Figure 1 and Figure 5 , a dynamic construction management method based on BIM technology, comprising the following steps:
[0062] S1. Construction of information sharing platform: Based on the needs of the construction site and construction operations, cloud computing technology is used to build a platform for multi-user real-time access, update and storage data. A security system is built for the information sharing platform, and a permission management mechanism is set up. The information sharing platform provides different access channels for construction personnel according to their positions at the construction site, grants construction personnel different data access rights and modification rights, and uses a multiple authentication mechanism to verify user identity. The information sharing platform records users' data access and operation behaviors in real time, including access time, access users and modification record inspection and tracking;
[0063] S2. Real-time data sharing: Use sensor networks, drones and inspection robots to collect data from the construction site in real time, including construction progress, material usage and equipment status. Through the designed standardized data interface, the collected data from the construction site is transmitted to the information sharing platform in real time. The information sharing platform standardizes the data and adds an accurate timestamp to the data. The processed data is shared with the software and equipment of different departments at the construction site through the standardized data interface.
[0064] S3. Update and display of BIM model: Use BIM software to build a three-dimensional model of the building according to construction requirements, upload the BIM model to the information sharing platform, and the information sharing platform will synchronize the data of the construction site to the BIM model in real time. According to the real-time synchronized data, the BIM model will be dynamically updated, and the dynamic BIM model will be displayed to various departments on the construction site in real time through the visual interface of the information sharing platform;
[0065] S4. Analysis and discussion of construction work: The information sharing platform conducts intelligent analysis of the data synchronized to the BIM model, conducts risk analysis of construction work, makes and adjusts construction decisions, automatically adjusts construction plans and resource allocation, and introduces instant messaging, video conferencing and shared document communication tools on the information sharing platform. The information sharing platform formulates a meeting schedule, regularly holds online discussion meetings between departments and construction personnel, and evaluates project progress;
[0066] Furthermore, an information sharing platform is established to enable departments of construction projects to obtain the latest data and progress of the construction site at any time. The information sharing platform integrates the data of various equipment on the construction site through standardized data interfaces, and shares the data with various departments on the construction site in real time, so that each department can obtain the required information in a timely manner, reducing delays and misunderstandings in information transmission and breaking down information barriers between departments. The information sharing platform accurately timestamps the data, realizes time synchronization processing of the data, and ensures the real-time nature of the shared data;
[0067] By setting up a permission management mechanism, the information sharing platform ensures that sensitive data on the construction site can only be accessed and modified by authorized personnel, avoiding data leakage and abuse. The use of a multi-authentication mechanism further improves the security of the platform. The information sharing platform records users' data access and operation behaviors, helping construction project managers to promptly discover and respond to potential safety hazards.
[0068] The information sharing platform feeds back real-time data from the construction site to the BIM model, so that the BIM model is always synchronized with the actual situation on the construction site, thereby improving the accuracy of the BIM model. The visual interface of the information sharing platform intuitively displays the specific information of the BIM model, so that construction personnel can obtain the latest data from the construction site in real time, such as construction progress, quality status, safety hazards, etc., so that construction managers can make more timely and accurate decisions. Based on the real-time updated BIM model, different construction teams can clearly understand their respective work content and the connections between the teams, and evaluate the progress of the project through regular online discussion meetings, thereby achieving more efficient collaborative work.
[0069] Example 2, please refer to Figure 1 and Figure 5 , a dynamic construction management method based on BIM technology, comprising the following steps:
[0070] Step 1: Use cloud computing technology to build an integrated cloud platform and design the overall architecture of the cloud platform, including network architecture, data architecture, storage architecture, and computing resource allocation. The cloud platform is used for real-time access and update of storage data by multiple users, and the platform is divided into multiple functional modules;
[0071] Step 2: According to the needs of construction work, design a data identification mechanism to identify the importance and sensitivity of data, use encryption algorithms to encrypt sensitive data and important data in the information sharing platform, and enable authorized users to access encrypted data through the set permission management mechanism;
[0072] Step 3: The information sharing platform formulates a data backup strategy based on the needs and progress of the construction work, automatically and regularly backs up the encrypted data, and standardizes the time for backing up data. It also sets a plan for automatically verifying the backup data, verifying the integrity and timeliness of the data, and formulating a plan for regularly cleaning up expired data based on the timeliness of the data.
[0073] Step 4: Deploy a network monitoring system to continuously monitor the network status and data transmission of the information sharing platform. When the network status is abnormal or the data is wrong, quickly locate the fault location and notify the management staff to take recovery measures in time.
[0074] Furthermore, the information sharing platform collects data from various equipment on the construction site through standardized data interfaces. The information sharing platform identifies data involving commercial privacy as sensitive data and data that affects the construction progress as important data. The identified sensitive data and important data are encrypted to prevent unauthorized access and tampering, thereby ensuring the security of data during transmission and storage.
[0075] According to the needs of construction work and the actual progress of construction, the information sharing platform formulates a data backup strategy and regularly backs up data to ensure that the data, construction progress, quality control and other information in the BIM model are fully preserved. When construction personnel view historical BIM model data, it is to avoid that the management personnel cannot understand the construction progress due to data loss. The backup data is checked regularly or as needed to ensure the validity and reliability of the backup data, thereby ensuring the accuracy of the BIM model data, cleaning up data that has not been used for a long time or has lost its value, and avoiding useless data from occupying the storage resources of the information sharing platform;
[0076] The network status and data transmission of the information sharing platform are continuously monitored through the network monitoring system, thereby ensuring the stability of the network signal quality, and then ensuring the real-time data transmission, solving the problem of data transmission delay caused by unstable signal quality, thereby further improving construction management efficiency. When data errors occur, managers can locate the fault location and take timely action, thereby improving the accuracy of the BIM model and avoiding data errors from affecting the construction progress.
[0077] Example 3, please refer to Figure 1 , Figure 2 and Figure 7 , a dynamic construction management method based on BIM technology, comprising the following steps:
[0078] Step 1: According to the needs of the construction site and construction operations, use cloud computing technology to build a platform for multi-user real-time access, update and storage data, build a security system for the information sharing platform, set up a permission management mechanism, use sensor networks, drones and inspection robots to collect data from the construction site in real time, including construction progress, material usage and equipment status, and transmit the collected data from the construction site to the information sharing platform in real time through the designed standardized data interface. The information sharing platform standardizes the data and adds an accurate timestamp to the data. The processed data is shared with the software and equipment of different departments at the construction site through the standardized data interface. Use BIM software to build a three-dimensional model of the building according to construction requirements, upload the BIM model to the information sharing platform, and the information sharing platform synchronizes the data from the construction site to the BIM model in real time. According to the real-time synchronized data, the BIM model is dynamically updated, and the dynamic BIM model is displayed to various departments at the construction site in real time through the visual interface of the information sharing platform. The information sharing platform performs intelligent analysis on the data synchronized to the BIM model and conducts risk analysis of construction operations;
[0079] Step 2: The information sharing platform formulates an inspection plan based on the construction environment data and construction needs. The platform shares the inspection plan with drones and inspection robots in real time. The inspection plan includes: regular inspection of the behavior of construction site personnel, equipment operation status, construction progress and material inventory;
[0080] Step 3: The information sharing platform collects inspection data and construction material transportation data in real time. The platform synchronizes environmental data, transportation data and inspection data to the BIM model in real time. The platform simulates and analyzes the data in the BIM model to assess the risks of construction material transportation. The information sharing platform analyzes the probability of construction vehicles encountering congestion based on the location information and road information of the construction vehicles, and determines the impact of traffic congestion, bad weather and road damage on construction vehicles. The information sharing platform evaluates the risk of construction vehicles arriving at the construction site late by analyzing data, simulates the time point of delayed arrival of construction vehicles, and identifies potential risks in the construction process, including: insufficient inventory of construction materials and the inability to transport materials to the construction site in time, construction personnel in dangerous environments and engaging in dangerous behaviors, and the construction site is in bad weather;
[0081] Step 4: The information sharing platform conducts quantitative assessment of the identified risks, prioritizes the risks according to their severity and probability of occurrence, formulates emergency plans to prioritize high-priority risks, formulates and adjusts construction decisions, and automatically adjusts construction plans and resource allocation. By introducing instant messaging, video conferencing, and shared document communication tools on the information sharing platform, the information sharing platform formulates a meeting schedule, regularly holds online discussion meetings between departments and construction personnel, and evaluates project progress;
[0082] Furthermore, the information sharing platform synchronizes environmental data, transportation data and inspection data to the BIM model in real time, and simulates and analyzes the data in the BIM model to predict the consumption and delivery of construction materials. When the inventory of construction materials is insufficient and the construction materials cannot be delivered to the construction site in time, or the construction workers are in a dangerous environment and engage in dangerous behavior, or the construction site is in bad weather, the information sharing platform will evaluate the impact and probability of the risk based on the risk prediction information, and formulate emergency plans that give priority to those with the greatest impact on the construction progress and the highest probability of risk occurrence. The information sharing platform will transmit the emergency plans to the corresponding departments in real time;
[0083] The information sharing platform will adjust the construction plan according to the scope and degree of risk impact, so as to prevent construction hazards from affecting the construction progress and avoid the suspension of construction projects. At the same time, the information sharing platform will formulate meeting plans to discuss issues related to construction site risks to avoid the occurrence of risks or hidden dangers, ensure the safety of construction personnel, improve construction management efficiency, ensure the uninterrupted progress of construction projects, and ensure that enterprises can complete construction work on schedule.
[0084] Example 4, please refer to Figure 1 and Figure 4 , a dynamic construction management method based on BIM technology, comprising the following steps:
[0085] Step 1: The information sharing platform conducts intelligent analysis of the data synchronized to the BIM model, conducts risk analysis of construction operations, formulates and adjusts construction decisions, and automatically adjusts construction plans and resource allocation. By introducing instant messaging, video conferencing, and shared document communication tools on the information sharing platform, the information sharing platform plans meeting contents of different topics based on construction needs, construction progress, and construction risk information. According to the importance and urgency of the meeting content and the time schedule of the construction project, a meeting schedule is formulated;
[0086] Step 2: Use the communication tools in the information sharing platform to send meeting notices to construction teams in different departments, including meeting agendas and meeting materials. The information sharing platform uses facial recognition technology to identify the identities of participants and determine their information;
[0087] Step 3: The information sharing platform records the meeting content in real time and promptly feeds back the meeting content to the management department. The information sharing platform regularly collects feedback from participants and replans the meeting schedule based on the feedback;
[0088] Furthermore, the information sharing platform integrates a variety of communication tools, breaks down the barriers between different departments of the construction project, promotes information sharing and collaboration among construction teams, and improves overall work efficiency. The information sharing platform conducts intelligent analysis of the data in the BIM model, identifies potential risk points and efficiency bottlenecks in the construction process, and automatically generates meeting content on different topics based on construction needs, progress and risk information to ensure the pertinence and effectiveness of the meeting. Combined with the construction project schedule, a meeting schedule is formulated to reasonably arrange meeting time and thus improve meeting efficiency.
[0089] Through the communication tools within the information sharing platform, the platform sends meeting notices to construction teams in different departments, including meeting agendas and meeting materials, so that participants can prepare in advance. Facial recognition technology is used to identify the identities of participants to ensure the safety and order of the meeting. The recorded meeting content helps management quickly obtain information, thereby making more scientific and reasonable construction decisions, preparing for subsequent construction work, and improving the efficiency and quality of construction work. The platform optimizes the meeting process and content based on the feedback from the meeting, thereby improving the actual effect of the meeting, ensuring effective feedback on construction site problems, and ensuring the rapid resolution of construction problems. The real-time recording and feedback mechanism of construction meeting content helps to improve the transparency of construction management and ensure that decisions are effectively implemented.
[0090] Example 5, please refer to Figure 3 and Figure 8 , a dynamic construction management method based on BIM technology, comprising the following steps:
[0091] Step 1: Based on the construction requirements and the analysis of the data in the BIM model, the information sharing platform initially formulates a construction plan, adjusts the personnel allocation of various departments on the construction site, plans the execution sequence of the construction projects, allocates construction equipment and materials for different construction projects, and designs a variety of different construction plans;
[0092] Step 2: The information sharing platform uses simulation and prediction technology to evaluate the impact of different construction plans on construction progress and construction costs. Based on the evaluation results of the construction plan, the information sharing platform selects the optimal construction plan. The information sharing platform synchronizes the construction plan to various departments on the construction site in real time and notifies the construction personnel to implement the construction plan as planned;
[0093] Step 3: The information sharing platform determines the actual construction progress of the construction site by analyzing the detection data and inspection data of the sensor network, and compares the actual progress data with the planned progress by predicting and analyzing the construction plan. When the planned progress of the construction differs greatly from the actual progress, the information sharing platform analyzes the lag and advance of the construction link, and determines the actual factors affecting the difference in construction progress by combining the risk information of the construction operation;
[0094] Step 4: The information sharing platform adjusts and optimizes the construction plans under different circumstances based on the analysis results. When the construction progress is affected by bad weather, the human resources, equipment resources and network resources of the construction project are reallocated according to the scope of impact.
[0095] Step 5: In the case of insufficient inventory and excessive accumulation of construction materials, the information sharing platform adjusts the construction plan, giving priority to construction projects with accumulated materials and reducing resource allocation for construction projects with insufficient inventory of construction materials;
[0096] Furthermore, the information sharing platform initially formulates a variety of different construction plans based on the construction requirements and real-time data in the BIM model. By analyzing the allocation of construction site personnel, the execution sequence of construction projects, and the allocation of construction equipment and materials, the platform predicts the impact of different plans on construction progress, construction cost, construction quality, etc. Based on the evaluation results, the platform selects the best construction plan and accurately formulates the construction plan, thereby improving construction efficiency and avoiding problems such as low construction quality and construction delays caused by poor construction plans.
[0097] The information sharing platform compares the actual progress of the construction with the planned progress, determines the lag or advance of the construction link, and combines the risk assessment information to determine the actual factors affecting the difference in construction progress, and then adjusts the construction plan and reallocates the human resources, equipment resources and network resources of the construction project to ensure that the construction work can be completed on schedule. In the case of insufficient inventory of construction materials or excessive accumulation of materials, the resource allocation of the construction project is adjusted to solve the problem of excess or insufficient inventory, avoid waste and idle resources, and effectively reduce construction risks.
[0098] Example 6, please refer to Figure 2 and Figure 6 , a dynamic construction management method based on BIM technology, comprising the following steps:
[0099] Step 1: The information sharing platform formulates an inspection plan based on the construction environment data and construction needs. The information sharing platform sets the inspection range and inspection route of the drone based on the environmental data of the construction site. The information sharing platform identifies the location information of construction equipment and construction personnel based on the inspection data shared by the drone. The information sharing platform analyzes the mobilization of construction equipment and construction personnel through the location information and generates the inspection strategy of the inspection robot. The inspection robot executes the inspection plan according to the inspection strategy and detects the construction progress and equipment status information of the construction equipment.
[0100] Step 2: The information sharing platform collects inspection data and construction material transportation data in real time. The platform synchronizes environmental data, transportation data and inspection data to the BIM model in real time. The platform simulates and analyzes the data in the BIM model, evaluates the risks of construction material transportation, and identifies potential risks in the construction process, including: insufficient inventory of construction materials and failure to transport materials to the construction site in time, construction workers in dangerous environments and engaging in dangerous behaviors, and the construction site is in bad weather;
[0101] Step 3: The information sharing platform conducts quantitative assessment of the identified risks, prioritizes the risks according to their severity and probability of occurrence, and formulates emergency plans that prioritize high-priority risks;
[0102] Furthermore, the information sharing platform sets the inspection plan of the drone based on the construction environment data and construction requirements, ensuring that the drone can prepare and completely collect the real-time data of the construction site to avoid the problem of blind inspection areas. The information sharing platform synchronizes the inspection data to the BIM model in real time to ensure that the model can accurately reflect the location information of each equipment and personnel change information on the construction site;
[0103] The information sharing platform generates an inspection plan for the inspection robot based on the equipment’s location information and personnel change information, ensuring that the inspection robot can accurately detect the status information and construction progress of the construction equipment, and avoids the inspection robot affecting the work of equipment and construction personnel during the inspection process. It ensures that the data synchronized to the BIM model can reflect the real-time progress data of the construction site, and ensures the accuracy and real-time nature of the construction progress data. By analyzing the data in the BIM model, the environmental information, material inventory information, construction personnel behavior information, etc. of the construction site can be determined, thereby providing data support for risk assessment of the construction site.
[0104] Working principle: Establish an information sharing platform to ensure that the platform can handle a large number of concurrent access and data storage requirements, set up a permission management mechanism to ensure the security of the information sharing platform data, monitor the relevant information of the construction site in real time through intelligent devices such as sensor networks, drones and inspection robots, and design standardized data interfaces to ensure that the data collected by different devices can be transmitted to the information sharing platform in a unified format;
[0105] Through standardized data interfaces, the processed data is shared in real time with the software and equipment of different departments on the construction site to ensure data compatibility between different software and equipment. The BIM model is uploaded to the information sharing platform, and the construction site data is synchronized in real time, and the dynamic BIM model is displayed to various departments on the construction site in real time;
[0106] The information sharing platform conducts intelligent analysis of data synchronized to the BIM model, identifies potential risks and efficiency bottlenecks in the construction process, makes and adjusts construction decisions, conducts regular online meetings on the information sharing platform, evaluates project progress, coordinates solutions to problems encountered during construction, and ensures that the project proceeds smoothly as planned.
[0107] It will be apparent to those skilled in the art that the invention is not limited to the details of the exemplary embodiments described above and that the invention can be implemented in other specific forms without departing from the spirit or essential features of the invention. Therefore, the embodiments should be considered exemplary and non-limiting in all respects, and the scope of the invention is defined by the appended claims rather than the foregoing description, and it is intended that all variations falling within the meaning and scope of the equivalent elements of the claims be included in the invention. Any reference numeral in a claim should not be considered as limiting the claim to which it relates.
Claims
1. A dynamic construction management method based on BIM technology, characterized by: The following steps are involved: S1. Construction of information sharing platform: Based on the needs of the construction site and construction operations, cloud computing technology is used to build a platform for multi-user real-time access, update and storage data, build a security system for the information sharing platform, and set up a permission management mechanism; S2. Real-time data sharing: Use sensor networks, drones and inspection robots to collect data from the construction site in real time, including construction progress, material usage and equipment status. Through the designed standardized data interface, the collected data from the construction site is transmitted to the information sharing platform in real time. The information sharing platform standardizes the data and adds an accurate timestamp to the data. The processed data is shared with the software and equipment of different departments at the construction site through the standardized data interface. S3. Update and display of BIM model: Use BIM software to build a three-dimensional model of the building according to construction requirements, upload the BIM model to the information sharing platform, and the information sharing platform will synchronize the data of the construction site to the BIM model in real time. According to the real-time synchronized data, the BIM model will be dynamically updated, and the dynamic BIM model will be displayed to various departments on the construction site in real time through the visual interface of the information sharing platform; S4. Analysis and discussion of construction work: The information sharing platform conducts intelligent analysis of the data synchronized to the BIM model, performs risk analysis of construction work, makes and adjusts construction decisions, automatically adjusts construction plans and resource allocation, and introduces instant messaging, video conferencing and shared document communication tools on the information sharing platform. The information sharing platform formulates meeting schedules, regularly holds online discussion meetings for various departments and construction personnel, and evaluates project progress.
2. A dynamic construction management method based on BIM technology according to claim 1, characterized in that: The risk analysis of the construction work in step S4 includes the following steps: Step 1: The information sharing platform formulates an inspection plan based on the construction environment data and construction needs. The platform shares the inspection plan with drones and inspection robots in real time. The inspection plan includes: regular inspection of the behavior of construction site personnel, equipment operation status, construction progress and material inventory; Step 2: The information sharing platform collects inspection data and construction material transportation data in real time. The platform synchronizes environmental data, transportation data and inspection data to the BIM model in real time. The platform simulates and analyzes the data in the BIM model, evaluates the risks of construction material transportation, and identifies potential risks in the construction process, including: insufficient inventory of construction materials and failure to transport materials to the construction site in time, construction workers in dangerous environments and engaging in dangerous behaviors, and the construction site is in bad weather; Step 3: The information sharing platform conducts a quantitative assessment of the identified risks, prioritizes the risks according to their severity and probability of occurrence, and develops emergency plans that prioritize high-priority risks.
3. A dynamic construction management method based on BIM technology according to claim 1, characterized in that: The making and adjusting of construction decisions in step S4 includes the following steps: Step 1: Based on the construction requirements and the analysis of the data in the BIM model, the information sharing platform initially formulates a construction plan, adjusts the personnel allocation of various departments on the construction site, plans the execution sequence of the construction projects, allocates construction equipment and materials for different construction projects, and designs a variety of different construction plans; Step 2: The information sharing platform uses simulation and prediction technology to evaluate the impact of different construction plans on construction progress and construction costs. Based on the evaluation results of the construction plan, the information sharing platform selects the optimal construction plan. The information sharing platform synchronizes the construction plan to various departments on the construction site in real time and notifies the construction personnel to implement the construction plan as planned; Step 3: The information sharing platform determines the actual construction progress of the construction site by analyzing the detection data and inspection data of the sensor network, and the planned progress of the construction site by predicting and analyzing the construction plan. The actual progress data is compared with the planned progress to determine the implementation of the construction plan. When the comparison result is large and the platform detects that there is a risk in the construction work, the information sharing platform analyzes and adjusts the construction plan.
4. The dynamic construction management method based on BIM technology according to claim 1 is characterized by: The step S4 of formulating the meeting schedule includes the following steps: Step 1: The information sharing platform plans the content of meetings on different topics based on construction needs, construction progress and construction risk information, and formulates a meeting schedule based on the importance and urgency of the meeting content and the time schedule of the construction project; Step 2: Use the communication tools in the information sharing platform to send meeting notices to construction teams in different departments, including meeting agendas and meeting materials. The information sharing platform uses facial recognition technology to identify the identities of participants and determine their information; Step 3: The information sharing platform records the meeting content in real time and promptly feeds back the meeting content to the management department. The information sharing platform regularly collects feedback from participants and replans the meeting schedule based on the feedback.
5. The dynamic construction management method based on BIM technology according to claim 1 is characterized by: The safety system construction in step S1 includes the following steps: Step 1: According to the needs of construction work, design a data identification mechanism to identify the importance and sensitivity of data, use encryption algorithms to encrypt sensitive data and important data in the information sharing platform, and enable authorized users to access encrypted data through the set permission management mechanism; Step 2: The information sharing platform formulates a data backup strategy based on the needs and progress of the construction work, automatically and regularly backs up the encrypted data, and standardizes the time for backing up data. It also sets a plan for automatically verifying the backup data, verifying the integrity and timeliness of the data, and formulating a plan for regularly cleaning up expired data based on the timeliness of the data. Step 3: Deploy a network monitoring system to continuously monitor the network status and data transmission of the information sharing platform. When the network status is abnormal and the data is erroneous, quickly locate the fault location and notify the management staff to take recovery measures in time.
6. The dynamic construction management method based on BIM technology according to claim 1 is characterized by: The setting of the rights management mechanism in S1 includes the following steps: Step 1: The information sharing platform provides different access channels for construction personnel according to their positions at the construction site, grants them different data access rights and modification rights, and uses a multi-factor authentication mechanism to verify user identities; Step 2: The information sharing platform records the user’s data access and operation behavior in real time, including access time, access user, and modification record inspection and tracking.
7. The dynamic construction management method based on BIM technology according to claim 2 is characterized by: The inspection plan formulated in step 1 includes the following steps: (1) The information sharing platform sets the inspection range and inspection route of the drone based on the environmental data of the construction site. The information sharing platform identifies the location information of construction equipment and construction personnel based on the inspection data shared by the drone. (2) The information sharing platform analyzes the movement of construction equipment and construction personnel through location information and generates inspection strategies for inspection robots. The inspection robots execute inspection plans according to the inspection strategies and detect the construction progress and equipment status information of the construction equipment.
8. The dynamic construction management method based on BIM technology according to claim 3 is characterized by: The assessment of construction material transportation risk in step 2 includes the following steps: (1) The information sharing platform analyzes the probability of construction vehicles encountering traffic jams based on the location information and road information of construction vehicles, and determines the impact of traffic jams, bad weather, and road damage on construction vehicles; (2) The information sharing platform analyzes data to assess the risk of construction vehicles arriving late at the construction site and simulates the time points at which delayed construction vehicles arrive.
9. The dynamic construction management method based on BIM technology according to claim 3 is characterized by: The analysis and adjustment of the construction plan in step 3 includes the following steps: (1) When the planned progress of construction differs greatly from the actual progress, the information sharing platform analyzes the delay and advance of the construction process and determines the actual factors affecting the difference in construction progress based on the risk information of the construction operation; (2) The information sharing platform adjusts and optimizes the construction plans under different circumstances based on the analysis results. When the construction progress is affected by bad weather, the human resources, equipment resources, and network resources of the construction project are reallocated according to the scope of the impact. (3) In the case of insufficient inventory or excessive accumulation of construction materials, the information sharing platform adjusts the construction plan, giving priority to construction projects with accumulated materials and reducing resource allocation for construction projects with insufficient inventory of construction materials.
10. The dynamic construction management method based on BIM technology according to claim 1, characterized in that: The information sharing platform is designed with multiple functional modules, including BIM model management, construction progress management, department communication management, inspection plan management and risk management.
Citation Information
Patent Citations
A BIM-based construction method for complex structural nodes
CN111460570B
A construction progress visualization method based on comparison between BIM model and monitoring images
CN113360583B
An AR-based method and system for visualizing construction BIM models
CN116030229B
A smart construction operation and maintenance management system and method based on BIM technology
CN118313640B
Cited By
Intelligent construction site management method and platform
CN120494747A