Point-line-plane integrated water seepage position repairing structure of rock slope and construction method
By designing an integrated seepage level repair structure of points, lines and surfaces on rocky slopes, the problem that traditional repair methods are easily washed out is solved, effective reinforcement of the slope and water drainage are achieved, and the stability and repair effect of the slope are significantly improved.
Patent Information
- Application Number
- CN202411970046.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-12-30
- Publication Date
- 2025-03-21
AI Technical Summary
Traditional rock slope restoration methods have the problem that sealing materials are easily washed out and the effects are difficult to guarantee, and may lead to further degradation of the slope and the risk of geological disasters.
A point, line and surface integrated seepage level repair structure is designed, including opening a reamer on the slope surface, installing a filter assembly and drainage tube inside, combining the shell assembly and filler to form an integral structure to reinforce the slope and drainage water.
By strengthening the slope and effectively draining water, preventing water accumulation and pressure concentration, the stability of the slope is significantly improved, the risks of landslides and collapses are reduced, and the long-term and long-term restoration effect is ensured.
Smart Images

Figure CN119663877A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of building construction, and in particular to a point-line-surface integrated seepage level repair structure for a rock slope and a construction method. Background Art
[0002] The stability of rock slopes has always been an important part of geotechnical engineering. In projects such as highways, railways, and water conservancy projects in mountainous areas and plateaus, the seepage points of rock slopes not only affect the stability of the slopes, but may also lead to further degradation of the slopes and even geological disasters such as landslides and collapses.
[0003] Traditional rock slope repair solutions usually use steel plates or plugging materials to directly seal the leakage points. However, after the plugging is completed, water accumulates at the plugging point, which will cause the slope pressure on the plugging position and even the surrounding area to increase, leading to unpredictable serious consequences. In addition, in many cases, when the water flow is large, the solidification speed of the plugging material is insufficient and it is easily washed out by the water flow, making it difficult to guarantee the plugging effect. Summary of the invention
[0004] The purpose of the present invention is to provide a reasonably designed point-line-surface integrated seepage level repair structure and construction method for a rock slope in view of the defects and shortcomings of the prior art, which can solve the above-mentioned defects.
[0005] In order to achieve the above object, the present invention adopts the following technical solutions:
[0006] A point-line-surface integrated seepage level repair structure for a rock slope comprises an expanded hole opened on the surface of the slope; the expanded hole is opened at the mouth of a seepage fissure on the slope, the angle between the expanded hole and the slope is 90°, a filter assembly is arranged in the expanded hole, a cover assembly is installed on the slope, the cover assembly is arranged outside the expanded hole, a drainage structure is arranged in the cover assembly, the drainage structure comprises a drainage pipe arranged through the cover assembly, the drainage pipe is connected to the filter assembly, and the extension direction of the drainage pipe is the same as the extension direction of the above-mentioned filter assembly, and the cover assembly is filled with filler.
[0007] Preferably, the cover shell assembly includes an annular mounting base plate, a semi-ellipsoidal fixed cover is connected to the front side of the mounting base plate, a plurality of anchor holes are evenly opened along the circumference of the mounting base plate, each anchor hole of the mounting base plate is provided with an anchor pile, and the mounting base plate is installed on the slope through the anchor pile, an annular fixing piece is provided at the center of the inner side of the mounting base plate, a plurality of connecting strips are connected between the inner side of the mounting base plate and the fixing piece, and each connecting strip is connected to the opposite side of the anchor hole on the mounting base plate, and the front side of the connecting strip is connected to an arc-shaped reinforcing beam.
[0008] Preferably, the filter assembly includes a filter tube arranged in the expanded hole, the outer diameter of the filter tube is the same as the diameter of the expanded hole, and tubular filter element 1 and filter element 2 with filter holes at both ends are arranged in the filter tube, and filter element 2 is arranged toward one end outside, and inward return edges are arranged at both ends of the filter tube, filter element 1 and filter element 2 are clamped between the two return edges, and filter material is respectively arranged in filter element 1 and filter element 2.
[0009] Preferably, the drainage structure includes a connecting auxiliary part arranged at the front end of the inner side of the fixing part, a step is formed between the rear side of the connecting auxiliary part and the inner wall of the fixing part, the filter tube is clamped at the step, the drainage tube is passed through the connecting auxiliary part, the end of the drainage tube is inserted into the mouth of the filter tube, and the outer diameter of the drainage tube matches the size of the mouth of the filter tube.
[0010] Preferably, the connection between the outer sides of the drainage tube and the filter tube and the fixing parts and the connection auxiliary parts is provided with epoxy resin for bonding and waterproofing, and the connection between the drainage tube and the filter tube is provided with silicone sealant.
[0011] Preferably, epoxy resin is provided between the outer sides of the filter element 1 and the filter element 2 and the inner wall of the filter tube for reinforcement and sealing.
[0012] Preferably, an annular groove is opened outside the outer opening of the expanded hole, and the groove is filled with an initial positioning sealing filler for connecting the slope and the filter tube, and the initial positioning sealing filler is a quick-drying epoxy resin.
[0013] Preferably, gravel is filled at both sides of the filter element 1 and the filter element 2, sand and gravel are filled between the gravel at both sides, and the diameter of the sand and gravel in the filter element 1 is greater than the diameter of the sand and gravel in the filter element 2.
[0014] Preferably, the filler is high-strength foam concrete.
[0015] A construction method for a point-line-surface integrated seepage level repair structure for a rock slope comprises the following steps:
[0016] S1. Clean the slope;
[0017] S2. Confirm the location of the water seepage fissures, and dig at the mouth of the water seepage fissures on the slope to form an expansion hole at the water seepage fissures;
[0018] S3. With the expansion hole as the center, confirm the anchor hole position of the installation base plate, that is, the installation hole position, then drill a hole on the slope and arrange a grouting pipe, inject water-soluble polyurethane into the hole through the grouting pipe and drive in anchor piles;
[0019] S4, opening an annular groove at the opening of the expanded hole;
[0020] S5. Pre-install or install filter materials in filter element 1 and filter element 2 on site, install them in the filter tube and close the end, then drive the filter tube into the expanded hole, use friction to initially fix the filter tube, then fill the groove at the expanded hole mouth with quick-drying epoxy resin, seal the edge of the filter tube, and reinforce the filter tube;
[0021] S6. A small groove is opened on the side slope at the top of the mounting base plate, the housing assembly is assembled, the inner sides of the fixing parts and the connecting auxiliary parts are coated with epoxy resin, and the drainage tube is inserted and fixed, and the pipe mouth of the drainage tube is coated with silicone sealant, and then the drainage pipe mouth is aligned with the filter tube to install the housing assembly, the filter tube mouth is inserted into the inner side of the fixing part, the drainage tube is inserted into the mouth of the filter tube, and the anchor pile is connected to the mounting base plate;
[0022] S7. Insert the pump pipe through the small groove opened on the slope and inject foam concrete until it is sealed.
[0023] After adopting the above structure, the beneficial effects of the present invention are:
[0024] 1. The present invention designs a cover shell assembly, uses a plurality of anchor piles for installation, and designs connecting strips so that the anchor pile installation positions on the mounting base plate form a linear structure with each other, so that the cover shell assembly forms an integral structure, realizing a point-line-surface integrated structure, and further increases the strength of the cover shell assembly through foam concrete. The ellipsoidal fixed cover can distribute the pressure to prevent deformation caused by excessive local pressure generated inside or outside, and the arc-shaped reinforcement beam enhances the strength of the strength connecting strip. The cover shell assembly reinforces the rock mass around the seepage cracks on the slope through the anchor piles to prevent the cracks from further expanding.
[0025] 2. The drainage pipe designed in the present invention can discharge water from the seepage part in time to prevent water accumulation, thereby preventing the concentration of water pressure from causing the expansion of the seepage level caused by local stress on the slope and even damage to the slope.
[0026] 3. The modular filter assembly designed in the present invention can be quickly driven into the enlarged hole for installation. After installation, the filter assembly can filter the water flow, remove the larger sediment in the water flow, and prevent the sediment from entering the drainage pipe and causing blockage. BRIEF DESCRIPTION OF THE DRAWINGS
[0027] Figure 1 It is a schematic diagram of the structure of the present invention;
[0028] Figure 2 yes Figure 1 Enlarged view of part A in the middle;
[0029] Figure 3 It is a schematic diagram of the installation method of the housing assembly, the filter tube and the drainage tube in the present invention;
[0030] Figure 4 It is a simplified diagram of construction steps of the present invention.
[0031] Description of reference numerals:
[0032] 1. Slope; 2. Seepage cracks; 3. Mounting plate; 4. Anchor piles; 5. Connecting strips; 6. Anchor holes; 7. Fixing covers; 8. Connecting auxiliary parts; 9. Hole expansion; 10. Filter tube; 11. Filter element 1; 12. Filter element 2; 13. Initial positioning, sealing and filling; 14. Drainage tube; 15. Arc-shaped reinforcement beam; 16. Fixing parts. DETAILED DESCRIPTION
[0033] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0034] See also Figure 1-Figure 3 As shown, a point-line-surface integrated seepage level repair structure for a rock slope comprises an expansion hole 9 opened on the surface of the slope 1; the expansion hole 9 is opened at the mouth of the seepage fissure 2 on the slope 1, and the angle between the expansion hole 9 and the slope 1 is 90°, a filter assembly is arranged in the expansion hole 9, a cover assembly is installed on the slope 1, the cover assembly is arranged outside the expansion hole 9, a drainage structure is arranged in the cover assembly, the drainage structure comprises a drainage pipe 14 arranged through the cover assembly, the drainage pipe 14 is connected to the filter assembly, and the extension direction of the drainage pipe 14 is the same as the extension direction of the above-mentioned filter assembly, and the cover assembly is filled with a filler, and the filler is a high-strength foam concrete;
[0035] The cover assembly includes an annular mounting base plate 3, a semi-ellipsoidal fixed cover 7 is connected to the front side of the mounting base plate 3, a plurality of anchor holes 6 are evenly opened along the circumference of the mounting base plate 3, each anchor hole 6 on the mounting base plate 3 is provided with an anchor pile 4, and is installed on the slope 1 through the anchor pile 4, an annular fixing part 16 is provided at the center of the inner side of the mounting base plate 3, a plurality of connecting strips 5 are connected between the inner side of the mounting base plate 3 and the fixing part 16, and each connecting strip 5 is connected to the opposite side of the anchor hole 6 on the mounting base plate 3, and the front side of the connecting strip 5 is connected to an arc-shaped reinforcing beam 15.
[0036] The mounting plate 3 is installed by means of anchor piles 4, and connecting strips 5 are provided so that the mounting plate 3 forms an integral structure with the fixing member 16 from all directions, and the cover assembly forms an integrated structure by means of filled foam concrete. The ellipsoidal fixing cover 7 can distribute the pressure to prevent deformation caused by excessive local pressure inside or outside, and the connecting strips 5 increase the contact area between the concrete and the structure, thereby enhancing the overall strength of the cover assembly. The cover assembly reinforces the rock mass around the seepage cracks 2 on the slope 1 through the anchor piles 4.
[0037] See also Figure 1-Figure 4 As shown, the filter assembly includes a filter tube 10 arranged in the expansion hole 9, the outer diameter of the filter tube 10 is the same as the diameter of the expansion hole 9, and a tubular filter element 11 and a filter element 2 12 with filter holes at both ends are arranged in the filter tube 10, and the filter element 2 12 is arranged toward the outer end, and both ends of the filter tube 10 are provided with inward return edges, and the filter element 11 and the filter element 2 12 are stuck between the two return edges, and epoxy resin is provided between the outer sides of the filter element 11 and the filter element 2 12 and the inner wall of the filter tube 10 for reinforcement and sealing, and gravel is filled on both sides of the filter element 11 and the filter element 2 12, and sand and gravel are filled between the gravel on both sides, and the diameter of the sand and gravel in the filter element 11 is larger than the diameter of the sand and gravel in the filter element 2 12.
[0038] By installing the filter tube 10, water flows through the inside, the gravel supports the internal sand and gravel, and the sand and gravel perform coarse filtration on the water flow to reduce the sediment content in the water and prevent a large amount of sediment from entering the drainage tube 14 to cause blockage. The filter element 11 and the filter element 2 12 can perform secondary filtration to ensure the filtering effect. The sand and gravel materials are low in cost and can be easily obtained from the construction site. The filter components can also be pre-installed before construction to improve the repair rate of water seepage. The diameter of the sand and gravel can be determined according to the needs of the leakage site.
[0039] See also Figure 1-Figure 3 As shown, the drainage structure includes a connection auxiliary member 8 disposed at the front end of the inner side of the fixing member 16, a step is formed between the rear side of the connection auxiliary member 8 and the inner side wall of the fixing member 16, the filter tube 10 is clamped at the step, the drainage tube 14 is inserted into the connection auxiliary member 8, the end of the drainage tube 14 is inserted into the mouth of the filter tube 10, and the outer diameter of the drainage tube 14 matches the size of the mouth of the filter tube 10;
[0040] The connection between the drainage tube 14 and the outer side of the filter tube 10 and the fixing member 16 and the connection auxiliary member 8 is provided with epoxy resin for bonding and waterproofing, and the connection between the drainage tube 14 and the filter tube 10 is provided with silicone sealant.
[0041] Through the design of the fixing part 16 and the connecting auxiliary part 8, the filter tube 10, the cover shell assembly and the drainage tube 14 can be connected as a whole to ensure that after the repair is completed, the filter tube 10 can be supported to prevent it from displacement, and the sealing of the connection is ensured by the adhesive. The epoxy resin can provide a high-strength seal, and the silicone sealant can quickly achieve sealing when encountering water, so that efficient construction can be carried out even in water.
[0042] See also Figure 1-Figure 3 As shown, an annular groove is opened outside the outer opening of the expansion hole 9, and the groove is filled with an initial positioning sealing filler 13 for connecting the slope 1 and the filter tube 10, and the initial positioning sealing filler 13 is a quick-drying epoxy resin.
[0043] The initial positioning sealing filling 13 can prevent the filter tube 10 from shifting under the action of water flow during the construction process, and can also seal the gaps around the filter tube 10 to prevent water from seeping out of the gaps.
[0044] See also Figure 1-Figure 4 As shown, a construction method of a point-line-surface integrated seepage level repair structure for a rock slope comprises the following steps:
[0045] S1. Clean the slope;
[0046] S2, confirming the position of the water seepage fissure 2, and excavating at the mouth of the water seepage fissure 2 on the slope 1 to form an expansion hole 9 at the water seepage fissure 2;
[0047] S3, with the expansion hole 9 as the center, confirm the position of the anchor hole 6 of the installation base plate 3, that is, the installation hole position, then drill a hole on the slope 1 and arrange a grouting pipe, pour water-soluble polyurethane into the hole through the grouting pipe and drive the anchor pile 4;
[0048] S4, opening an annular groove at the mouth of the reamer 9;
[0049] S5, pre-install or on-site install filter materials in the filter element 11 and the filter element 2 12, and install them into the filter tube 10 and close the mouth, wherein the filter materials can be collected on-site, and then the filter tube 10 is driven into the expanded hole 9, and the filter tube 10 is initially fixed by friction, and then the groove at the mouth of the expanded hole 9 is filled with quick-drying epoxy resin, the edge of the filter tube 10 is sealed, and the filter tube 10 is reinforced;
[0050] S6. A small groove is made on the slope 1 at the top of the mounting base plate 3, and the housing assembly is assembled. The fixing member 16 and the inner side of the connecting auxiliary member 8 are coated with epoxy resin, and then the drainage tube 14 is inserted and fixed. The pipe mouth of the drainage tube 14 is coated with silicone sealant, and then the mouth of the drainage tube 14 is aligned with the filter tube 10 to install the housing assembly. The mouth of the filter tube 10 is inserted into the inner side of the fixing member 16, and the drainage tube 14 is inserted into the mouth of the filter tube 10, and the anchor pile 4 is connected to the mounting base plate 3.
[0051] S7. Insert the pump pipe through the small groove opened on the slope 1 and inject foam concrete until it is sealed.
[0052] It should be understood that the above specific embodiments of the present invention are only used to illustrate or explain the principles of the present invention, and do not constitute a limitation of the present invention. Therefore, any modifications, equivalent substitutions, improvements, etc. made without departing from the spirit and scope of the present invention should be included in the protection scope of the present invention. In addition, the appended claims of the present invention are intended to cover all changes and modifications that fall within the scope and boundaries of the appended claims, or the equivalent forms of such scope and boundaries.
Claims
1. A point-line-surface integrated seepage level repair structure for a rock slope, characterized by: The invention comprises an expansion hole (9) opened on the surface of a slope (1), wherein the expansion hole (9) is opened at the mouth of a water seepage fissure (2) on the slope (1), and the angle between the expansion hole (9) and the slope (1) is 90 degrees. A filter assembly is arranged in the expansion hole (9), and a cover assembly is installed on the slope (1). The cover assembly is arranged outside the expansion hole (9). A drainage structure is arranged in the cover assembly, and the drainage structure comprises a drainage pipe (14) arranged through the cover assembly. The drainage pipe (14) is connected to the filter assembly, and the extension direction of the drainage pipe (14) is the same as the extension direction of the above-mentioned filter assembly. The cover assembly is filled with a filling material.
2. The point-line-surface integrated seepage level repair structure for a rock slope according to claim 1, characterized in that: The housing assembly comprises an annular mounting base plate (3), a semi-ellipsoidal fixed cover (7) is connected to the front side of the mounting base plate (3), a plurality of anchor holes (6) are evenly opened along the circumference of the mounting base plate (3), each anchor hole (6) on the mounting base plate (3) is provided with an anchor pile (4), and the mounting base plate (3) is installed on the slope (1) through the anchor pile (4), an annular fixing member (16) is provided at the center of the inner side of the mounting base plate (3), a plurality of connecting strips (5) are connected between the inner side of the mounting base plate (3) and the fixing member (16), and each connecting strip (5) is connected to the opposite side of the anchor hole (6) on the mounting base plate (3), and the front side of the connecting strip (5) is connected to an arc-shaped reinforcing beam (15).
3. The point-line-surface integrated seepage level repair structure for a rock slope according to claim 2 is characterized by: The filter assembly comprises a filter tube (10) arranged in the expansion hole (9), the outer diameter of the filter tube (10) being the same as the diameter of the expansion hole (9), a tubular filter element (11) and a filter element (12) having filter holes at both ends being arranged in the filter tube (10), and the filter element (12) is arranged toward one end outside, both ends of the filter tube (10) are provided with inward return edges, the filter element (11) and the filter element (12) are clamped between the two return edges, and filter materials are respectively arranged in the filter element (11) and the filter element (12).
4. The point-line-surface integrated seepage level repair structure for a rock slope according to claim 3 is characterized by: The drainage structure comprises a connection auxiliary part (8) arranged at the front end of the inner side of the fixing part (16), a step is formed between the rear side of the connection auxiliary part (8) and the inner wall of the fixing part (16), the filter tube (10) is clamped at the step, the drainage tube (14) is inserted into the connection auxiliary part (8), the end of the drainage tube (14) is inserted into the mouth of the filter tube (10), and the outer diameter of the drainage tube (14) matches the size of the mouth of the filter tube (10).
5. The point-line-surface integrated seepage level repair structure for a rock slope according to claim 4 is characterized by: The connection points between the outer sides of the drainage tube (14) and the filter tube (10) and the fixing member (16) and the connection auxiliary member (8) are all provided with epoxy resin for bonding and waterproofing, and the connection point between the drainage tube (14) and the filter tube (10) is provided with silicone sealant.
6. The point-line-surface integrated seepage level repair structure for a rock slope according to claim 5, characterized in that: Epoxy resin is provided between the outer sides of the filter element 1 (11) and the filter element 2 (12) and the inner wall of the filter tube (10) for reinforcement and sealing.
7. The point-line-surface integrated seepage level repair structure for a rock slope according to claim 6, characterized in that: An annular groove is formed outside the outer opening of the expansion hole (9), and the groove is filled with an initial positioning sealing filler (13) for connecting the slope (1) and the filter tube (10), and the initial positioning sealing filler (13) is a quick-drying epoxy resin.
8. The point-line-surface integrated seepage level repair structure for a rock slope according to claim 7, characterized in that: Gravel is filled on both sides of the filter element 1 (11) and the filter element 2 (12), and sand and gravel are filled between the gravel on both sides, and the diameter of the sand and gravel in the filter element 1 (11) is greater than the diameter of the sand and gravel in the filter element 2 (12).
9. The point-line-surface integrated seepage level repair structure for a rock slope according to claim 1, characterized in that: The filling material is high-strength foam concrete.
10. The construction method of a point-line-surface integrated seepage level repair structure for a rock slope according to any one of claims 1 to 9, characterized in that: The following steps are involved: S1. Clean the slope; S2, confirming the position of the water seepage fissure (2), and excavating the mouth of the water seepage fissure (2) on the slope (1) to form an expansion hole (9) at the water seepage fissure (2); S3, with the expansion hole (9) as the center, confirm the position of the anchor hole (6) of the installation base plate (3), that is, the installation hole position, then drill a hole on the slope (1) and arrange a grouting pipe, pour water-soluble polyurethane into the hole through the grouting pipe and drive the anchor pile (4); S4, opening an annular groove at the mouth of the expansion hole (9); S5, pre-installing or on-site loading filter material into filter element 1 (11) and filter element 2 (12), installing them into the filter tube (10) and closing the mouth, then driving the filter tube (10) into the expanded hole (9), using friction to initially fix the filter tube (10), then filling the groove at the mouth of the expanded hole (9) with quick-drying epoxy resin, sealing the edge of the filter tube (10), and reinforcing the filter tube (10); S6. A small groove is made on the side slope (1) at the top of the mounting base plate (3), and the housing assembly is assembled. The inner sides of the fixing member (16) and the connecting auxiliary member (8) are coated with epoxy resin, and then the drainage tube (14) is inserted and fixed. The mouth of the drainage tube (14) is coated with silicone sealant, and then the mouth of the drainage tube (14) is aligned with the filter tube (10) to install the housing assembly. The mouth of the filter tube (10) is inserted into the inner side of the fixing member (16), and the drainage tube (14) is inserted into the mouth of the filter tube (10), and the anchor pile (4) is connected to the mounting base plate (3); S7. Insert the pump pipe through the small groove opened on the slope (1) and inject foam concrete until it is sealed.