Power construction monitoring method and system

Through the remote monitoring system of smart watches and construction monitoring servers, the problem of lack of full-process monitoring in the existing technology is solved, automatic compliance judgment and vital sign monitoring of construction personnel are realized, and the risk of safety accidents is reduced.

CN119692651APending Publication Date: 2025-03-25NANCHONG POWER SUPPLY COMPANY STATE GRID SICHUANELECTRIC POWER
View PDF 0 Cites 3 Cited by

Patent Information

Application Number
CN202411483579.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-23
Publication Date
2025-03-25

AI Technical Summary

Technical Problem

There is a lack of full-process monitoring methods for staff during power construction in the prior art, resulting in 88% of safety accidents caused by human causes.

Method used

Through the combination of smart watches and construction monitoring servers, remote monitoring of construction personnel is achieved. Construction workers obtain construction permit messages through smart watches before construction, and during this period, vital sign data is collected through smart watches and warnings are generated based on preset standards.

Benefits of technology

Automatic compliance judgment of construction personnel is achieved, the risk of safety accidents caused by human error is reduced, and the status abnormalities of construction personnel are promptly understood, improving construction safety.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119692651A_ABST
    Figure CN119692651A_ABST
Patent Text Reader

Abstract

The invention provides a power construction monitoring method and system. The power construction monitoring method is used for performing remote monitoring on a construction plan to be performed by a constructor, and comprises the following steps: S1, the constructor obtains a current construction site based on a smart watch, and sends the construction site to a construction monitoring server; s2, in response to the received construction site, the construction monitoring server retrieves a construction plan corresponding to the construction site from a preset construction plan library; and S3, based on the retrieval result, the construction monitoring server sends a construction permission message to the smart watch. Through on-site data acquisition and analysis and comparison of a remote server, automatic compliance judgment on construction operation is realized, and the risk of manual wrong operation is eliminated; and the state of the constructor is remotely monitored in the construction process, so that whether the state of the constructor is abnormal or not can be known in time.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of electric power monitoring, and in particular to an electric power construction monitoring method and system. Background Art

[0002] With the development of social economy, the scale of my country's power grid is expanding. As a pillar industry related to the national economy and people's livelihood, the safe production of the power industry is not only closely related to the benefits of power companies themselves, but also directly related to the development of our national economy and the stability of people's lives. At this stage, although the system of power safety management in my country has been greatly improved, it is still affected by various complex factors and there are still some problems that need to be improved.

[0003] According to statistics, about 88% of safety accidents are caused by human factors. Many accidents are apparently caused by mechanical equipment obstacles, but in the end, most of them are directly or indirectly caused by human factors. Therefore, strengthening the safety awareness of staff, standardizing the operation of staff, and implementing safety work to people are the core of safety production management. Therefore, a full-process monitoring method is needed during the entire process of staff operation. Summary of the invention

[0004] In view of the deficiencies in the prior art, the present invention provides a method and system for monitoring electric power construction, which mainly solves the problem in the prior art of lacking a full-process monitoring method during the entire process of operation by workers.

[0005] The objective of the present invention is achieved through the following solutions:

[0006] In a first aspect, according to an embodiment of the present invention, there is provided a method for monitoring electric power construction, which is used for remotely monitoring a construction plan to be carried out by construction personnel, and comprises the following steps: S1, the construction personnel obtain the current construction site based on a smart watch, and send the construction site to a construction monitoring server; S2, in response to receiving the construction site, the construction monitoring server retrieves a construction plan corresponding to the construction site from a preset construction plan library; S3, based on the retrieval result, the construction monitoring server sends a construction permission message to the smart watch.

[0007] According to an embodiment of the present invention, each construction plan in the construction plan library includes a construction site, a construction object and a construction content.

[0008] According to an embodiment of the present invention, the construction object includes power generation equipment and power supply equipment.

[0009] According to an embodiment of the present invention, the power generation equipment includes a power station boiler, a steam turbine, a gas turbine, a water turbine, and a generator.

[0010] According to an embodiment of the present invention, the power supply equipment includes a transformer, a transmission line, a mutual inductor and a contactor.

[0011] According to an embodiment of the present invention, the construction content includes detection, maintenance and replacement.

[0012] According to an embodiment of the present invention, the power construction monitoring method further includes: S4, during the construction process, obtaining the vital signs data of the construction personnel through a smart watch, and generating a warning according to a preset vital signs standard.

[0013] According to an embodiment of the present invention, the vital sign data includes heart rate, body temperature, and blood pressure.

[0014] According to an embodiment of the present invention, the power construction monitoring method further includes: S5, generating a continuous working duration warning after a preset time interval from the start of construction.

[0015] In a second aspect, according to another embodiment of the present invention, there is provided an electric power construction monitoring system, which adopts an electric power construction monitoring method as described in the first aspect to remotely monitor the construction plan to be carried out by construction personnel, and the electric power construction monitoring system comprises: a smart watch, including a positioning module, a WIFI module and a vital sign sensor, wherein the vital sign sensor includes a heart rate sensor, a body temperature sensor and a blood pressure sensor; a construction monitoring server, including a preset construction plan library and vital sign standards; wherein the smart watch and the construction monitoring server transmit data to each other via a network.

[0016] Compared with the prior art, the present invention has the following beneficial effects: through on-site data collection and analysis and comparison by remote servers, automatic compliance judgment of construction operations is achieved, eliminating the risk of human error in operations; and by remotely monitoring the status of construction personnel during the construction process, it is possible to timely understand whether the construction personnel are in abnormal conditions. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] The embodiments of the present invention are further described below with reference to the accompanying drawings:

[0018] Figure 1 A schematic diagram of a flow chart of a power construction monitoring method according to an embodiment of the present invention;

[0019] Figure 2 The figure is a block diagram of the composition of the electric power construction monitoring system according to an embodiment of the present invention. DETAILED DESCRIPTION

[0020] Before proceeding to the following detailed description, it may be advantageous to set forth the definitions of certain words and phrases used throughout this patent document. The terms "coupling", "connection" and their derivatives refer to any direct or indirect communication or connection between two or more elements, regardless of whether those elements are in physical contact with each other. The terms "transmission", "reception" and "communication" and their derivatives cover direct and indirect communication. The terms "include" and "comprising" and their derivatives refer to including but not limited to. The term "or" is inclusive, meaning and / or. The phrase "associated with..." and its derivatives refer to including, including within, interconnecting, containing, contained within, connecting or connecting with, coupling or coupling with, communicating with, cooperating, interweaving, parallel, close to, binding or binding with, having, having attributes, having a relationship or having a relationship with, etc. The term "controller" refers to any device, system or part thereof that controls at least one operation. Such a controller can be implemented with hardware, or a combination of hardware and software and / or firmware. The functions associated with any particular controller can be centralized or distributed, whether local or remote. The phrase "at least one of", when used with a list of items, means that different combinations of one or more of the listed items may be used, and only one of the items in the list may be required. For example, "at least one of A, B, C" includes any of the following combinations: A, B, C, A and B, A and C, B and C, A and B and C.

[0021] Definitions for other specific words and phrases are provided throughout this patent document. Those of ordinary skill in the art should understand that in many, if not most instances, such definitions apply to prior and future uses of such defined words and phrases.

[0022] In this patent document, the application combination of modules and the division level of sub-modules are only used for illustration, and the application combination of modules and the division level of sub-modules may have different forms without departing from the scope of the present disclosure.

[0023] In order to make the purpose, technical solutions and advantages of the present invention more clearly understood, the present invention is further described in detail below through specific embodiments in conjunction with the accompanying drawings. It should be understood that the specific embodiments described herein are only used to explain the present invention and are not intended to limit the present invention.

[0024] As described in the background technology, the prior art lacks a method for monitoring the entire process of the worker's operation. Figure 1As shown, according to an embodiment of the present invention, a power construction monitoring method is provided for remotely monitoring the construction plan to be carried out by construction personnel, comprising the following steps: S1, the construction personnel obtain the current construction site based on the smart watch, and send the construction site to the construction monitoring server; S2, in response to receiving the construction site, the construction monitoring server retrieves the construction plan corresponding to the construction site from the preset construction plan library; S3, based on the retrieval result, the construction monitoring server sends a construction permission message to the smart watch. Through the on-site data collection and the analysis and comparison of the remote server, the automatic compliance judgment of the construction work is realized, eliminating the risk of human error operation.

[0025] When the construction permission message indicates prohibition, construction personnel can be effectively prevented from performing incorrect construction operations. This not only prevents redundant operations on equipment that was not originally scheduled, but also allows timely recognition of possible errors and inquiries to correct the correct operation plan so that the target equipment that needs to be operated can be repaired in time, especially when the operation to be performed takes a long time. For example, when the equipment is, for example, a power generation equipment in a hydropower station that is far away and urgently needs to be processed, the long-term inspection or maintenance at another hydropower station that is also far away will greatly delay the correct maintenance of the target hydropower station. In addition, when the construction permission message indicates permission, specific construction operation information can be sent with the construction permission message so that construction personnel can further confirm the specific construction operations before construction begins.

[0026] According to an embodiment of the present invention, each construction plan in the construction plan library includes a construction site, a construction object, and a construction content. Each construction plan is created in advance by a manager according to demand and is issued to relevant staff for construction work guidance. The format of the construction site can be a coordinate or a site number in the power grid system, such as the No. xxx substation in xx village, xx town.

[0027] In detail, according to an embodiment of the present invention, the construction object includes power generation equipment and power supply equipment. The construction object in each construction plan can be one or more, depending on the state indicated by the status monitoring information of the equipment. Of course, multiple objects in a construction plan are usually in the same place to facilitate one-time problem solving. In addition, according to an embodiment of the present invention, the power generation equipment includes power station boilers, steam turbines, gas turbines, water turbines, and generators. As is known to all, power generation equipment refers to mechanical equipment that converts mechanical energy into electrical energy. It is driven by a water turbine, a steam turbine, a diesel engine or other power machinery, and converts the energy generated by water flow, air flow, fuel combustion or nuclear fission into mechanical energy and transmits it to a generator, which is then converted into electrical energy by the generator. Therefore, any other power generation equipment that can achieve this function is also included. In addition, according to an embodiment of the present invention, the power supply equipment includes transformers, transmission lines, mutual inductors and contactors. Of course, it also includes equipment for transmitting and distributing electrical energy, such as circuit breakers, disconnectors, automatic switches, knife switches, busbar power cables and reactors.

[0028] According to an embodiment of the present invention, the construction content includes detection, maintenance and replacement. Similarly, this depends on the status monitoring result of the target equipment and is set by the management personnel according to the situation.

[0029] In order to better monitor the status of construction workers during the operation process, according to an embodiment of the present invention, the power construction monitoring method further includes: S4, during the construction process, the vital signs data of the construction workers are obtained through a smart watch, and a warning is generated according to a preset vital signs standard. In detail, according to an embodiment of the present invention, the vital signs data include heart rate, body temperature, and blood pressure. For example, the standard range of heart rate is 60 to 100 beats per minute. Normal body temperature is generally between 36°C and 37°C. Blood pressure includes systolic pressure and diastolic pressure, and under normal circumstances, the blood pressure value is 90-140 / 60-90mmHg. When the value of a certain sign deviates from the normal range, a warning to pay attention to rest can be generated. In addition, the alarm danger value can be further set. If the value is at a dangerous value, the smart bracelet can contact the relevant emergency contact through the construction monitoring server, and the emergency contact can contact the construction personnel for processing or call 120 emergency number when necessary. This function is extremely helpful for operations in severe weather. When the weather is sunny, the temperature of the construction workers may rise, and the warning can remind the construction workers to avoid heat stroke; when the weather is rainy, the temperature of the construction workers may drop, and the warning can remind the construction workers to avoid hypothermia.

[0030] In addition, in order to avoid fatigue problems caused by construction workers working too long, according to an embodiment of the present invention, the power construction monitoring method also includes: S5, generating a warning of continuous working time after a preset time interval at the start of construction. For example, after the construction personnel receive the construction permit message, when the workers have been working for two consecutive hours, the monitoring server can issue a warning of continuous working time to the smart bracelet to remind the workers to take a rest and prevent safety accidents caused by long-term fatigue work. This function is extremely useful for working at heights because the risks are greater when working at heights. In particular, for dangerous scenarios such as working at heights, the reminder time interval can be shortened to provide more frequent reminders, such as once every half an hour.

[0031] like Figure 2 As shown, according to another embodiment of the present invention, there is provided an electric power construction monitoring system, which adopts an electric power construction monitoring method as described above to remotely monitor the construction plan to be carried out by construction personnel, and the electric power construction monitoring system 100 includes: a smart watch 110, including a positioning module 111, a WIFI module 112 and a vital sign sensor 113, wherein the vital sign sensor 113 includes a heart rate sensor 1131, a body temperature sensor 1132 and a blood pressure sensor 1133; a construction monitoring server 120, including a preset construction plan library and vital sign standards; wherein the smart watch 110 and the construction monitoring server 120 transmit data to each other via a network.

[0032] The present invention may be a system, a method and / or a computer program product. The computer program product may include a computer-readable storage medium carrying computer-readable program instructions for causing a processor to implement various aspects of the present invention.

[0033] Computer readable storage medium can be a tangible device that holds and stores instructions used by an instruction execution device. Computer readable storage medium can include, for example, but is not limited to, an electrical storage device, a magnetic storage device, an optical storage device, an electromagnetic storage device, a semiconductor storage device, or any suitable combination thereof. More specific examples (non-exhaustive list) of computer readable storage medium include: a portable computer disk, a hard disk, a random access memory (RAM), a read-only memory (ROM), an erasable programmable read-only memory (EPROM or flash memory), a static random access memory (SRAM), a portable compact disk read-only memory (CD-ROM), a digital versatile disk (DVD), a memory stick, a floppy disk, a mechanical encoding device, for example, a punch card or a protruding structure in a groove on which instructions are stored, and any suitable combination thereof.

[0034] The embodiments of the present invention have been described above, and the above description is exemplary, not exhaustive, and is not limited to the disclosed embodiments. Many modifications and variations will be apparent to those of ordinary skill in the art without departing from the scope and spirit of the described embodiments. The selection of terms used herein is intended to best explain the principles of the embodiments, practical applications, or technical improvements in the market, or to enable other persons of ordinary skill in the art to understand the embodiments disclosed herein.

Claims

1. A power construction monitoring method for remotely monitoring a construction plan to be carried out by construction personnel, characterized in that: The following steps are involved: S1. A construction worker obtains the current construction location based on a smart watch and sends the construction location to a construction monitoring server; S2, in response to receiving the construction site, the construction monitoring server retrieves a construction plan corresponding to the construction site from a preset construction plan library; S3. Based on the search result, the construction monitoring server sends a construction permission message to the smart watch.

2. A method for monitoring electric power construction according to claim 1, characterized in that: Each construction plan in the construction plan library includes a construction site, a construction object and a construction content.

3. A method for monitoring electric power construction according to claim 2, characterized in that: The construction objects include power generation equipment and power supply equipment.

4. A method for monitoring electric power construction according to claim 3, characterized in that: The power generation equipment includes power station boilers, steam turbines, gas turbines, water turbines, and generators.

5. A method for monitoring electric power construction according to claim 3, characterized in that: The power supply equipment includes a transformer, a transmission line, a mutual inductor and a contactor.

6. A method for monitoring electric power construction according to claim 2, characterized in that: The construction content includes inspection, repair and replacement.

7. A method for monitoring electric power construction according to claim 1, characterized in that: Also includes: S4. During the construction process, the vital signs data of the construction workers are obtained through smart watches, and warnings are generated according to the preset vital signs standards.

8. According to the electric power construction monitoring method of claim 7, the vital signs data include heart rate, body temperature, and blood pressure.

9. The electric power construction monitoring method according to claim 7, further comprising: S5. Generate a continuous working time warning after a preset time interval from the start of construction.

10. An electric power construction monitoring system, which uses an electric power construction monitoring method as claimed in any one of claims 1 to 9 to remotely monitor the construction plan to be carried out by construction personnel, characterized in that: The electric power construction monitoring system comprises: A smart watch, comprising a positioning module, a WIFI module and a vital sign sensor, wherein the vital sign sensor comprises a heart rate sensor, a body temperature sensor and a blood pressure sensor; Construction monitoring server, including a library of preset construction plans and vital signs standards; Wherein, the smart watch and the construction monitoring server transmit data to each other through the network.

Citation Information

Cited By

  • Electric power construction site safety monitoring and early warning system based on Internet of Things

    CN120689974A

  • Power construction method based on intelligent monitoring

    CN121390828A

  • A power construction method based on intelligent monitoring

    CN121390828B