Bridge girder erection machine girder transporting device for composite girder installation and construction

By designing a bridge-mounted beam transport device for the installation and construction of combined beams, the problems of slow installation progress of combined beams and personal safety hazards in the existing technology are solved, efficient installation and automatic spraying are achieved, and construction efficiency and safety are improved.

CN119711365APending Publication Date: 2025-03-28CCCC SECOND HARBOR ENGINEERING CO LTD +1
View PDF 3 Cites 0 Cited by

Patent Information

Application Number
CN202411927877.5
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-12-25
Publication Date
2025-03-28

AI Technical Summary

Technical Problem

When installing the existing bridge frame, the operator needs to carry out construction in an environment where the sling is extended too long, resulting in shaking, slow installation progress and personal safety risks. At the same time, additional manpower is required to spray waterproof coatings after installation, which wastes manpower and affects the construction progress.

Method used

A bridge-mounted beam transport device for combined beam installation and construction is designed, including installation beams, installation components, auxiliary components and spraying components. The force transmission mechanism of the installation assembly improves the alignment efficiency of the installation beam and the bridge pier. The auxiliary assembly provides installation assistance and positioning functions, and the spraying assembly realizes automatic spraying of waterproof coating.

Benefits of technology

The installation alignment efficiency of the installation beam and the bridge pier is improved, the safety hazards of manual operation are reduced, and the automatic spraying of waterproof coatings is realized, and the construction efficiency and resource utilization are improved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119711365A_ABST
    Figure CN119711365A_ABST
Patent Text Reader

Abstract

The invention provides a bridge girder erection machine girder transporting device for composite girder installation and construction, and belongs to the technical field of bridges. Comprising a mounting beam, drainage holes are symmetrically formed in the two sides of the mounting beam, four sets of mounting frames are distributed at the top end of the mounting beam at equal angles, a sling is arranged at the top end of each set of mounting frame, two lifting bolts are symmetrically arranged at the bottom end of each mounting frame, and eight mounting shafts are distributed at the bottom end of the mounting beam at equal angles; the outer side of the mounting shaft is sleeved with a first gear, and the mounting assemblies are mounted at the bottom of the mounting beam and distributed at equal angles and used for mounting the mounting beam. By arranging the mounting assembly, the mounting alignment efficiency of the mounting beam and the bridge pier is improved, and the situation that uneven impurities possibly exist in the bridge pier hole and cannot completely enter the bridge pier hole, so that a cavity exists in the final grouting fixing stage, and incomplete fixing is avoided.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of bridges, and in particular to a bridge erecting machine beam transporting device for composite beam installation construction. Background Art

[0002] A bridge-erecting machine is a device that places prefabricated beams onto prefabricated bridge piers. Bridge-erecting machines belong to the category of cranes because their main function is to lift the beams, transport them to the location and then lower them. Bridge-erecting machines are divided into several types, such as those for erecting highway bridges, conventional railway bridges, and passenger-dedicated railway bridges. From installation, commissioning, operation, warehousing and storage, each link has strict management methods to ensure that the bridge-erecting machine is always in good technical condition.

[0003] When installing a combined installation beam, an existing bridge-building machine usually uses a lifting device on the bridge-building machine to lift the installation beam to the pier installation position, and transports the operator to the pier position by the lifting device. With the assistance of the operator, the installation beam is aligned with the pier installation hole for installation. This installation method requires the operator to perform construction under the installation beam lifted by the lifting device, and align the mounting seat at the bottom of the installation beam with the mounting hole on the pier for installation. In this working environment, since the sling is extended too long, it is easy to shake during the operation. The installation beam needs to be slowly lowered and installed by multiple people in collaboration. The installation progress is slow, and there are safety hazards to the personal safety of the operators during the installation. At the same time, after the installation is completed, it is necessary to spray waterproof paint on the arc surfaces on both sides of the bottom of the installation beam, and the operator needs to take a lift to spray, which wastes manpower and affects the construction progress of the bridge-building machine.

[0004] Therefore, the present application provides a bridge erection machine beam transport device for composite beam installation construction to meet the needs. Summary of the invention

[0005] The technical problem to be solved by the present invention is to provide a bridge-erecting machine beam transporting device for composite beam installation construction, so as to solve the problem that the existing method of usually using the lifting equipment on the bridge-erecting machine to lift the installation beam to the pier installation position, transporting the operator to the pier position by the lifting equipment, and aligning the installation beam with the pier installation hole for installation with the assistance of the operator. This installation method requires the operator to carry out construction under the installation beam lifted by the lifting equipment, and align the mounting seat at the bottom of the installation beam with the mounting hole on the pier. In this working environment, since the sling is extended too long, it is easy to shake during the operation. The installation beam needs to be slowly lowered and installed by the cooperation of multiple people, and the installation progress is slow. There are safety hazards to the personal safety of the operators during the installation. At the same time, after the installation is completed, it is necessary to spray waterproof coating on the arc surface positions on both sides of the bottom of the installation beam, and the operator needs to take the elevator to spray, which wastes manpower and affects the construction progress of the bridge-erecting machine.

[0006] In order to solve the above technical problems, the present invention provides the following technical solutions:

[0007] A bridge-erecting beam-transporting device for composite beam installation construction comprises a mounting beam, drainage holes are symmetrically arranged on both sides of the mounting beam, four groups of mounting frames are equiangularly distributed at the top of the mounting beam, a sling is arranged at the top of each group of mounting frames, two lifting bolts are symmetrically arranged at the bottom end of the mounting frame, eight mounting shafts are equiangularly distributed at the bottom end of the mounting beam, a gear is sleeved on the outer side of the mounting shaft, and the device also comprises a mounting assembly, the mounting assembly is equiangularly installed at the bottom of the mounting beam, the mounting assembly is used to install the mounting beam, an auxiliary assembly, the auxiliary assembly is installed at one side of the mounting assembly, the auxiliary assembly is used to assist in installing the mounting beam on a bridge pier, and a spraying assembly, the spraying assembly is installed at one side of the mounting assembly, and the spraying assembly is used to spray waterproof coating on the side wall of the mounting beam.

[0008] Optionally, the mounting assembly includes an elastic telescopic rod 1, which is mounted on the bottom of one side of the mounting frame, the bottom end of the elastic telescopic rod 1 is connected to an electric push rod, and one side of the electric push rod is connected to a connecting plate.

[0009] Optionally, two screw rods are symmetrically nested inside the connecting plate, and a contact plate is connected between the two screw rods.

[0010] Optionally, a threaded sleeve is sleeved on the outer side of the screw rod, the threaded sleeve is mounted on the bottom end of the mounting beam, a gear shaft is sleeved on the outer side of the threaded sleeve, and a pulley set is connected to the top of the gear shaft.

[0011] Optionally, the auxiliary component includes a mounting seat, which is installed on the top of the connecting plate, the top of the mounting seat is connected to an elastic telescopic rod three, the top of the elastic telescopic rod three is connected to a connecting rod one, the connecting rod one rotates at the end of the elastic telescopic rod three, and the end of the connecting rod one is connected to a connecting rod two.

[0012] Optionally, the connecting rod 2 rotates at the end of the connecting rod 1, an auxiliary roller is installed at the end of the connecting rod 2, one end of the connecting rod 2 is connected to the connecting rod 3, the connecting rod 3 rotates at the end of the connecting rod 2, the end of the connecting rod 3 is connected to the connecting rod 4, and the connecting rod 4 rotates at the end of the connecting rod 3.

[0013] Optionally, the end of the connecting rod four is connected to a rotating wheel, and elastic telescopic rods four are installed on the inner side of the rotating wheel at equal angles. The top of the elastic telescopic rod four is connected to a contact block, and the surface of the contact block is provided with an anti-slip layer. One side of the connecting rod four is connected to a rack one, and the rack one is meshed with gear two, and the gear two is installed on one side of the connecting rod two.

[0014] Optionally, the spraying assembly includes a ratchet, which is installed at the end of the second connecting rod and is coaxially installed with the auxiliary roller. The ratchet is meshed with the second rack, one end of the second rack is connected to a spring, and the tail end of the spring is connected to a slide frame.

[0015] Optionally, the end of the rack 2 is connected to a piston 1, which slides on the inner side of the slide frame. The end of the slide frame is connected to a one-way valve through a pipeline. The tail end of the one-way valve is connected to a storage box, which is installed on the top of the connecting plate.

[0016] Optionally, a connecting rod three is installed on the top of the storage box, a piston two is installed on the inner side of the storage box, the piston two slides on the inner side of the storage box, and a spray rack is connected to the top end between the two groups of storage boxes on the opposite side.

[0017] Compared with the prior art, the present invention has at least the following beneficial effects:

[0018] In the above scheme, by setting up the installation component, the gear shaft and gear one are driven to engage with each other through the downward force transmission of the installation beam, and gear one drives the installation shaft to rotate, and the installation shaft rotates and enters the pier hole, thereby improving the installation and alignment efficiency of the installation beam and the pier, preventing the presence of uneven impurities in the pier hole, and preventing the inability to completely enter the pier hole, resulting in cavities in the final grouting fixation stage, thereby avoiding incomplete fixation.

[0019] By setting up a spraying assembly, the ratchet is driven to rotate by an auxiliary roller, and the ratchet is meshed with rack 2 to transmit the transmission, so that piston 1 pushes piston 2 through hydraulic pressure, and piston 2 sprays the waterproof coating from the spray rack, thereby improving construction efficiency, eliminating the need for additional manpower for construction, and effectively utilizing construction resources.

[0020] By setting up an auxiliary component, when the rotating wheel moves to the drainage hole, the contact block enters the drainage hole. Since it is no longer blocked by the bottom wall of the installation beam, the elastic telescopic rod four in contraction returns to its original state, so that the elastic telescopic rod four limits the connecting rod four on the inner side of the drainage hole, and the rack one and the gear two are engaged with each other, so that the auxiliary roller can stably drive the ratchet to rotate, providing auxiliary triggering force for the spraying component. At the same time, during construction, auxiliary positioning is provided for the bottom end of the installation beam, which facilitates the installation of the installation beam. BRIEF DESCRIPTION OF THE DRAWINGS

[0021] The accompanying drawings, which are incorporated herein and constitute a part of the specification, illustrate embodiments of the invention and, together with the description, further serve to explain the principles of the invention and to enable those skilled in the relevant art to make and use the invention.

[0022] Figure 1A schematic diagram of the three-dimensional structure of the bridge erection machine beam transport device used for composite beam installation construction;

[0023] Figure 2 A bottom view of the three-dimensional structure of the bridge erection machine beam transport device used for composite beam installation construction;

[0024] Figure 3 for Figure 2 A schematic diagram of the enlarged three-dimensional structure at position A;

[0025] Figure 4 It is a schematic diagram of the three-dimensional structure of the installation component;

[0026] Figure 5 for Figure 4 A magnified schematic diagram of the three-dimensional structure at B in FIG.

[0027] Figure 6 is a schematic diagram of the three-dimensional structure of the contact block;

[0028] Figure 7 It is a schematic diagram of the three-dimensional structure of the auxiliary component;

[0029] Figure 8 for Figure 7 A magnified schematic diagram of the three-dimensional structure at C in FIG.

[0030] Fig. 9 It is a schematic diagram of the three-dimensional structure of the spraying component.

[0031] Reference numerals:

[0032] 1. Mounting beam; 2. Drain hole; 3. Mounting frame; 4. Lifting rope; 5. Lifting bolt; 6. Mounting assembly; 61. Elastic telescopic rod 1; 62. Electric push rod; 63. Connecting plate; 64. Screw; 65. Contact plate; 66. Threaded sleeve; 67. Gear shaft; 68. Pulley assembly; 7. Auxiliary assembly; 71. Mounting seat; 72. Elastic telescopic rod 3; 73. Connecting rod 1; 74. Connecting rod 2; 75. Auxiliary assembly Auxiliary roller; 76, connecting rod three; 77, connecting rod four; 78, rotating wheel; 79, elastic telescopic rod four; 710, contact block; 711, rack one; 712, gear two; 8, spray assembly; 81, ratchet; 82, rack two; 83, spring; 84, slide rack; 85, piston one; 86, one-way valve; 87, storage box; 88, piston two; 89, spray rack; 9, mounting shaft; 10, gear one.

[0033] As shown in the figure, in order to clearly implement the structure of the embodiment of the present invention, specific structures and devices are marked in the figure, but this is only for illustrative purposes and is not intended to limit the present invention to the specific structure, device and environment. According to specific needs, ordinary technicians in this field can adjust or modify these devices and environments. DETAILED DESCRIPTION

[0034] The following is a detailed description of a bridge erection machine beam transport device for composite beam installation and construction provided by the present invention in conjunction with the accompanying drawings and specific embodiments. At the same time, it is explained here that in order to make the embodiments more detailed, the following embodiments are the best and preferred embodiments, and those skilled in the art may also adopt other alternative methods to implement some known technologies; and the accompanying drawings are only for a more specific description of the embodiments, and are not intended to specifically limit the present invention.

[0035] It should be noted that the references to "one embodiment", "an embodiment", "an exemplary embodiment", "some embodiments" and the like in the specification indicate that the embodiments described may include specific features, structures or characteristics, but not every embodiment may include the specific features, structures or characteristics. In addition, when a specific feature, structure or characteristic is described in conjunction with an embodiment, it should be within the knowledge of a person skilled in the art to implement such feature, structure or characteristic in conjunction with other embodiments (whether or not explicitly described).

[0036] In general, a term can be understood, at least in part, from its use in context. For example, depending, at least in part, on the context, the term "one or more" as used herein can be used to describe any feature, structure, or characteristic in the singular sense, or can be used to describe a combination of features, structures, or characteristics in the plural sense. Additionally, the term "based on" can be understood as not necessarily intended to convey an exclusive set of factors, but can instead, depending, at least in part, on the context, allow for the presence of other factors that are not necessarily explicitly described.

[0037] It will be understood that the meanings of “on,” “over,” and “above” in the present invention should be interpreted in the broadest manner, so that “on” not only means “directly on” something, but also includes the meaning of being “on” something with intervening features or layers therebetween, and “on” or “over” not only means “on” or “above” something, but also includes the meaning of being “on” or “above” something with no intervening features or layers therebetween.

[0038] Additionally, spatially relative terms such as "under," "beneath," "lower," "above," "upper," and the like may be used herein for descriptive convenience to describe the relationship of one element or feature to another element or features, as shown in the accompanying drawings. Spatially relative terms are intended to encompass different orientations of the device in use or operation in addition to the orientation depicted in the accompanying drawings. The device may be oriented in other ways, and the spatially relative descriptors used herein may be similarly interpreted accordingly.

[0039] like Figures 1 to 9As shown, an embodiment of the present invention provides a bridge-erecting beam transporting device for composite beam installation construction, comprising an installation beam 1, drainage holes 2 are symmetrically arranged on both sides of the installation beam 1, four groups of installation frames 3 are equiangularly distributed at the top of the installation beam 1, a sling 4 is arranged at the top of each group of installation frames 3, two lifting bolts 5 are symmetrically arranged at the bottom end of the installation frame 3, eight installation shafts 9 are equiangularly distributed at the bottom end of the installation beam 1, a gear 10 is sleeved on the outer side of the installation shaft 9, and also includes an installation component 6, the installation component 6 is installed at an equiangular distribution at the bottom of the installation beam 1, the installation component 6 is used to install the installation beam 1, an auxiliary component 7, the auxiliary component 7 is installed on one side of the installation component 6, the auxiliary component 7 is used to assist the installation of the installation beam 1 on the bridge pier, and a spraying component 8, the spraying component 8 is installed on one side of the installation component 6, and the spraying component 8 is used to spray waterproof coating on the side wall of the installation beam 1.

[0040] like Figures 1 to 5 As shown, the mounting assembly 6 includes an elastic telescopic rod 61, which is mounted on the bottom of one side of the mounting frame 3, and the bottom end of the elastic telescopic rod 61 is connected to an electric push rod 62, and one side of the electric push rod 62 is connected to a connecting plate 63, and two screw rods 64 are symmetrically nested on the inner side of the connecting plate 63, and a contact plate 65 is connected between the two screw rods 64, and the outer side of the screw rod 64 is sleeved with a threaded sleeve 66, which is mounted on the bottom end of the mounting beam 1, and the outer side of the threaded sleeve 66 is sleeved with a gear shaft 67, and the top of the gear shaft 67 is connected to a pulley group 68;

[0041] By setting the installation component 6, the operator pulls the sling 4 through the lifting hole of the installation beam 1 by operating the lifting equipment of the bridge erection machine, and fixes the bolt to the outer side of the bottom end of the sling 5, so that the lifting equipment can lift the installation beam 1. When reaching the position of the pier to be installed, the operator on the pier controls the lifting equipment through the wireless remote control device to move the sling 4 downward, so that the sling 5 drives the installation beam 1 to move toward the pier, and the installation frame 3 also moves with it, and the contact plate 65 contacts with the top of the pier. As the installation beam 1 moves downward, the threaded sleeve 66 moves downward with it, and the threaded sleeve 66 is threadedly meshed with the screw 64. The threaded sleeve 66 rotates at the bottom end of the installation beam 1, and the threaded sleeve 66 drives the gear shaft 67 to rotate. Under the synchronous transmission of the pulley group 68, the gear shaft 67 located at the bottom end of the installation beam 1 is driven by the gear shaft 67. The two screw rods 64 on the same contact plate 65 are kept horizontal, and the gear shaft 67 is meshed with the gear 10. The electric push rod 62 controls the left and right movement of the connecting plate 63 to align the installation shaft 9 with the pier hole, so that the installation shaft 9 is rotated to enter the pier hole to prevent the pier hole from being uneven and unable to fully enter the pier hole, so as to facilitate the operator to grout and fix the pier hole. As the installation beam 1 moves downward, the contact plate 65 and the connecting plate 63 gradually contact each other, and the elastic telescopic rod 61 connected between the mounting frame 3 and the electric push rod 62 is forced to shrink, thereby improving the installation alignment efficiency of the installation beam 1 and the pier, and preventing the pier hole from being uneven and impurities from being unable to fully enter the pier hole, resulting in cavities in the final grouting and fixing stage, thereby avoiding incomplete fixation.

[0042] like Figures 1 to 3 and Figures 6 to 8 As shown, the auxiliary component 7 includes a mounting seat 71, which is mounted on the top of the connecting plate 63, and the top of the mounting seat 71 is connected to an elastic telescopic rod 3 72, and the top of the elastic telescopic rod 3 72 is connected to a connecting rod 1 73, and the connecting rod 1 73 rotates at the end of the elastic telescopic rod 3 72, and the end of the connecting rod 1 73 is connected to a connecting rod 2 74, and the connecting rod 2 74 rotates at the end of the connecting rod 1 73, and an auxiliary roller 75 is installed at the end of the connecting rod 2 74, and one end of the connecting rod 2 74 is connected to a connecting rod 3 76, and the connecting rod 3 76 is connected to the connecting rod 3 The end of the second rod 74 rotates, the end of the third connecting rod 76 is connected to the fourth connecting rod 77, the fourth connecting rod 77 rotates at the end of the third connecting rod 76, the end of the fourth connecting rod 77 is connected to the rotating wheel 78, the inner side of the rotating wheel 78 is evenly distributed with elastic telescopic rods 4 79, the top of the elastic telescopic rods 4 79 is connected to the contact block 710, the surface of the contact block 710 is provided with an anti-skid layer, one side of the fourth connecting rod 77 is connected to the rack 1 711, the rack 1 711 and the gear 2 712 are meshed with each other, and the gear 2 712 is installed on one side of the second connecting rod 74;

[0043] By setting the auxiliary component 7, as the elastic telescopic rod 1 61 is forced to shrink, the auxiliary roller 75 and the rotating wheel 78 are at the bottom arc position of the mounting beam 1, and the elastic telescopic rod 4 79 inside the rotating wheel 78 is squeezed by the contact block 710 and the bottom of the mounting beam 1. The pressure is contracted, and as the mounting beam 1 moves downward, the connecting rod 4 77 rotates at the end of the connecting rod 3 76, driving the connecting rod 4 77 to drive the rotating wheel 78 to rotate in the direction of the drainage hole 2 on the corresponding side, and the rack 1 711 and the gear 2 712 are meshed with each other, so that the connecting rod 2 74 rotates in the direction close to the mounting shaft 9. The auxiliary roller 75 rolls on the arc surface of the mounting beam 1, and the connecting rod 2 74 drives the connecting rod 1 73 to rotate, so that the elastic telescopic rod 3 72 on the top of the mounting seat 71 contracts. When the rotating wheel 78 moves to the drainage hole 2, it enters the contact block 710 in the drainage hole 2. Since it is no longer blocked by the bottom wall of the mounting beam 1, the elastic telescopic rod 4 79 in contraction returns to its original state, so that the elastic telescopic rod 4 79 limits the connecting rod 4 77 on the inner side of the drainage hole 2, thereby improving the running stability of the spray assembly 8 and providing auxiliary positioning for the bottom end of the mounting beam 1, facilitating the installation of the mounting beam 1.

[0044] like Figures 1 to 3 and Fig. 9 As shown, the spray assembly 8 includes a ratchet 81, which is mounted on the end of the second connecting rod 74, and the ratchet 81 is coaxially mounted with the auxiliary roller 75, the ratchet 81 and the second rack 82 are meshed with each other, one end of the second rack 82 is connected with a spring 83, the tail end of the spring 83 is connected with a slide frame 84, the end of the second rack 82 is connected with a piston 1 85, the piston 1 85 slides on the inner side of the slide frame 84, the tail end of the one-way valve 86 is connected with a storage box 87, the storage box 87 is mounted on the top of the connecting plate 63, the top of the storage box 87 is mounted with a connecting rod 3 76, the inner side of the storage box 87 is mounted with a piston 2 88, the piston 2 88 slides on the inner side of the storage box 87, and the top end between the two groups of storage boxes 87 on the opposite side is connected with a spray rack 89;

[0045] By setting the spraying assembly 8, the auxiliary roller 75 rolls on the arc surface of the mounting beam 1, and the ratchet 81 coaxially connected to the auxiliary roller 75 rotates accordingly, and the ratchet 81 meshes with the rack 2 82. The piston 1 85 at the end of the rack 2 82 slides on the inner side of the slide rack 84 under the push of the rack 2 82, and the spring 83 is stretched by the force. The piston 1 85 pushes the waterproof coating in the pipeline to enter the interior of the storage box 87 through the one-way valve 86, and pushes the piston 2 88 to slide upward on the inside of the storage box 87, so that the spray rack 89 on the top of the two groups of storage boxes 87 on the same side sprays the waterproof coating on the arc surface of the mounting beam 1. When the elastic limit of the spring 83 is reached, the spring 83 returns to its original state, driving the rack 2 82 and the spring 83 to move. Plug 1 85 moves in the direction of returning to its original position. Due to the unidirectional transmission property of the ratchet 81, the ratchet 81 will not transmit the transmission to the auxiliary roller 75 during the resetting process of the rack 2 82. As the auxiliary roller 75 rolls on the arc surface of the mounting beam 1, the ratchet 81 continues to engage and transmit with the rack 2 82, so that the piston 1 85 pushes the waterproof coating in the pipeline and pushes the piston 2 88 to slide upward on the inside of the storage box 87. The two groups of storage boxes 87 on the same side push the waterproof coating located above the piston 2 88 into the inside of the spray rack 89, and the waterproof coating is sprayed from the spray rack 89 to continuously spray the arc surface of the mounting beam 1 with waterproof coating. No additional manpower is required for construction, which improves the construction efficiency of the bridge erection machine, speeds up the construction speed, and can effectively utilize construction resources.

[0046] The working principle of the technical solution provided by the present invention is as follows:

[0047] The operator pulls the sling 4 through the lifting hole of the installation beam 1 by operating the lifting equipment of the bridge erection machine, and fixes the bolt to the outer side of the bottom end of the sling 5, so that the lifting equipment can lift the installation beam 1. When the pier to be installed is reached, the operator on the pier controls the lifting equipment through the wireless remote control device to move the sling 4 downward, so that the sling 5 drives the installation beam 1 to move toward the pier, and the installation frame 3 also moves with it, and the contact plate 65 contacts the top of the pier. As the installation beam 1 moves downward, the threaded sleeve 66 moves downward with it, and the threaded sleeve 66 is threadedly engaged with the screw rod 64, and the threaded sleeve 66 rotates at the bottom end of the installation beam 1. 66 drives the gear shaft 67 to rotate. Under the synchronous transmission of the pulley group 68, the two screws 64 located on the same contact plate 65 are kept horizontal. The gear shaft 67 is meshed with the gear 10. The electric push rod 62 controls the left and right movement of the connecting plate 63 to align the installation shaft 9 with the pier hole. The installation shaft 9 is rotated to enter the pier hole to prevent the pier hole from being uneven and unable to fully enter the pier hole. It is convenient for operators to grout and fix the pier hole. As the installation beam 1 moves downward, the contact plate 65 gradually contacts the connecting plate 63, and the elastic telescopic rod 61 connected between the mounting frame 3 and the electric push rod 62 is forced to shrink.

[0048] As the elastic telescopic rod 1 61 is forced to shrink, the auxiliary roller 75 and the rotating wheel 78 are at the bottom arc position of the mounting beam 1, and the elastic telescopic rod 4 79 inside the rotating wheel 78 is squeezed by the contact block 710 and the bottom of the mounting beam 1. As the mounting beam 1 moves downward, the connecting rod 4 77 rotates at the end of the connecting rod 3 76, driving the connecting rod 4 77 to drive the rotating wheel 78 to rotate toward the drainage hole 2 on the corresponding side, and the rack 1 711 and the gear 2 712 are meshed with each other, so that the connecting rod 2 77 4 is rotated in the direction close to the mounting shaft 9, so that the auxiliary roller 75 rolls on the arc surface of the mounting beam 1, and the connecting rod 2 74 drives the connecting rod 1 73 to rotate, so that the elastic telescopic rod 3 72 on the top of the mounting seat 71 is contracted. When the rotating wheel 78 moves to the drain hole 2, it enters the contact block 710 in the drain hole 2. Since it is no longer blocked by the bottom wall of the mounting beam 1, the contracted elastic telescopic rod 4 79 returns to its original state, so that the elastic telescopic rod 4 79 limits the connecting rod 4 77 on the inner side of the drain hole 2.

[0049] The auxiliary roller 75 rolls on the arc surface of the mounting beam 1, and the ratchet 81 coaxially connected to the auxiliary roller 75 rotates accordingly, and the ratchet 81 meshes with the rack 2 82. The piston 1 85 at the end of the rack 2 82 slides on the inner side of the slide frame 84 under the push of the rack 2 82, and the spring 83 is stretched by the force. The piston 1 85 pushes the waterproof coating in the pipeline to enter the interior of the storage box 87 through the one-way valve 86, and pushes the piston 2 88 to slide upward on the inside of the storage box 87, so that the spraying frame 89 on the top of the two groups of storage boxes 87 on the same side sprays the waterproof coating on the arc surface of the mounting beam 1. When the elastic limit of the spring 83 is reached, the spring 83 returns to its original state, driving rack two 82 and piston one 85 to move in the direction of returning to their original positions. Due to the unidirectional transmission property of the ratchet 81, during the resetting process of rack two 82, the ratchet 81 will not transmit the transmission to the auxiliary roller 75. As the auxiliary roller 75 rolls on the arc surface of the mounting beam 1, the ratchet 81 continues to mesh with the rack two 82 for transmission, so that the piston one 85 pushes the waterproof coating in the pipeline and pushes the piston two 88 to slide upward on the inside of the storage box 87. The two groups of storage boxes 87 on the same side push the waterproof coating located above the piston two 88 into the inside of the spray rack 89, and the coating is sprayed from the spray rack 89 to continuously spray the arc surface of the mounting beam 1 with waterproof coating.

[0050] The present invention covers any substitution, modification, equivalent method and scheme made on the essence and scope of the present invention. In order to make the public have a thorough understanding of the present invention, specific details are described in detail in the following preferred embodiments of the present invention, but those skilled in the art can fully understand the present invention without the description of these details. In addition, in order to avoid unnecessary confusion about the essence of the present invention, well-known methods, processes, procedures, components and circuits are not described in detail.

[0051] The above is only a preferred embodiment of the present invention. It should be pointed out that for ordinary technicians in this technical field, several improvements and modifications can be made without departing from the principle of the present invention. These improvements and modifications should also be regarded as the scope of protection of the present invention.

Claims

1. A bridge erection machine beam transport device for composite beam installation construction, characterized in that: It comprises a mounting beam, drainage holes are symmetrically arranged on both sides of the mounting beam, four groups of mounting frames are evenly distributed at the top of the mounting beam, a sling is arranged at the top of each group of mounting frames, two lifting bolts are symmetrically arranged at the bottom of the mounting frame, eight mounting shafts are evenly distributed at the bottom of the mounting beam, and a gear 1 is sleeved on the outer side of the mounting shaft; Also included are mounting components, which are installed at equal angles at the bottom of the mounting beam, and are used to install the mounting beam; An auxiliary component, the auxiliary component is installed on one side of the installation component, and the auxiliary component is used to assist the installation beam in being installed on the bridge pier; A spraying assembly is installed on one side of the mounting assembly and is used to spray waterproof coating on the side wall of the mounting beam.

2. The bridge erection machine beam transport device for composite beam installation construction according to claim 1, characterized in that: The mounting assembly comprises an elastic telescopic rod 1, which is mounted on the bottom of one side of the mounting frame, the bottom end of the elastic telescopic rod 1 is connected to an electric push rod, and one side of the electric push rod is connected to a connecting plate.

3. The bridge erection machine beam transport device for composite beam installation construction according to claim 2, characterized in that: Two screw rods are symmetrically nested inside the connecting plate, and a contact plate is connected between the two screw rods.

4. The bridge erection machine beam transport device for composite beam installation construction according to claim 3, characterized in that: The outer side of the screw rod is sleeved with a threaded sleeve, the threaded sleeve is installed at the bottom end of the mounting beam, the outer side of the threaded sleeve is sleeved with a gear shaft, and the top of the gear shaft is connected with a pulley group.

5. The bridge erection machine beam transport device for composite beam installation construction according to claim 4, characterized in that: The auxiliary component includes a mounting seat, which is mounted on the top of the connecting plate. The top of the mounting seat is connected to an elastic telescopic rod three, the top of the elastic telescopic rod three is connected to a connecting rod one, the connecting rod one rotates at the end of the elastic telescopic rod three, and the end of the connecting rod one is connected to a connecting rod two.

6. The bridge erection machine beam transport device for composite beam installation construction according to claim 5, characterized in that: The connecting rod 2 rotates at the end of the connecting rod 1, and an auxiliary roller is installed at the end of the connecting rod 2. One end of the connecting rod 2 is connected to the connecting rod 3, and the connecting rod 3 rotates at the end of the connecting rod 2. The end of the connecting rod 3 is connected to the connecting rod 4, and the connecting rod 4 rotates at the end of the connecting rod 3.

7. The bridge erection machine beam transport device for composite beam installation construction according to claim 6, characterized in that: The end of the connecting rod four is connected to a rotating wheel, and elastic telescopic rods four are installed on the inner side of the rotating wheel at equal angles. The top of the elastic telescopic rod four is connected to a contact block, and the surface of the contact block is provided with an anti-slip layer. One side of the connecting rod four is connected to a rack one, and the rack one is meshed with a gear two, and the gear two is installed on one side of the connecting rod two.

8. The bridge erection machine beam transport device for composite beam installation construction according to claim 7, characterized in that: The spraying assembly includes a ratchet, which is installed at the end of the second connecting rod and is coaxially installed with the auxiliary roller. The ratchet is meshed with the second rack, one end of the second rack is connected to a spring, and the tail end of the spring is connected to a slide frame.

9. The bridge erection machine beam transport device for composite beam installation construction according to claim 8, characterized in that: The end of the rack 2 is connected to a piston 1, which slides on the inner side of the slide frame. The end of the slide frame is connected to a one-way valve through a pipeline. The tail end of the one-way valve is connected to a storage box, which is installed on the top of the connecting plate.

10. The bridge erection machine beam transport device for composite beam installation construction according to claim 9, characterized in that: A connecting rod three is installed on the top of the storage box, a piston two is installed on the inner side of the storage box, and the piston two slides on the inner side of the storage box. A spray rack is connected to the top end between the two groups of storage boxes on the opposite side.

Citation Information

Patent Citations

  • Bridge steel structure coating auxiliary device

    CN210875942U

  • Railway T-beam bridge girder erection machine hoisting auxiliary device

    CN218754507U

  • Connecting frame for carrier transport vehicle for transporting bridge erection machine

    DE202023106092U1