Wharf structure construction method

Through a dock structure construction method, the first lifting device and steel pipe pile operation platform are used to solve the problem of low utilization rate of construction equipment in high pile dock construction, and the effect of improving equipment utilization rate and construction efficiency is achieved, and the construction cost is reduced.

CN119711399AActive Publication Date: 2025-03-28CCCC FOURTH HARBOR ENG CO LTD
View PDF 5 Cites 0 Cited by

Patent Information

Application Number
CN202411636499.5
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-11-15
Publication Date
2025-03-28
Estimated Expiration
2044-11-15

AI Technical Summary

Technical Problem

During the construction of high pile docks, some construction equipment has low utilization rates, which affects construction costs.

Method used

Through a dock structure construction method, the steel pipe is lifted and arranged vertically using the first lifting device, punched to a predetermined position, cut off the excess, process the steel bar cage, and pour concrete into the steel pipe to form steel pipe piles. Then, the bull legs are welded on the outside of the steel pipe through the steel pipe pile operation platform, and the bull legs are processed using the remaining steel pipe sections to improve equipment utilization and construction efficiency.

Benefits of technology

The utilization rate of the first lifting device and the steel pipe pile operation platform has been improved, the construction efficiency has been improved, and the construction cost of high-pile dock construction has been reduced.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119711399A_ABST
    Figure CN119711399A_ABST
Patent Text Reader

Abstract

The invention relates to the field of high-pile wharf construction, in particular to a wharf structure construction method. The wharf structure construction method comprises the steps that a steel pipe is hoisted and vertically arranged through a first hoisting device, and then the steel pipe is driven to a preset position; after the steel pipe is hit to a preset position, the interior of the steel pipe is treated; cutting off the redundant part of the upper part of the steel pipe to form a residual steel pipe section, and hoisting away the residual steel pipe section through a first hoisting device; processing a reinforcement cage, putting at least one part of the reinforcement cage into the steel pipe, and pouring concrete into the steel pipe to form a steel pipe pile; brackets are welded to the outer sides of the steel pipes through the steel pipe pile operation platform, at least part of structures on the brackets are formed by splitting the remaining steel pipe sections, and the steel pipe pile operation platform can transversely move relative to the steel pipes. According to the wharf structure construction method, the utilization rate of the first lifting device and the steel pipe pile operation platform is increased, the construction efficiency can be effectively improved by means of bracket machining through materials on the construction site, and therefore the construction cost of high-pile wharf construction is jointly reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the field of high-pile wharf construction, and in particular to a wharf structure construction method. Background Art

[0002] At present, the construction process of high-pile wharf mainly includes pile sinking, forming steel pipe piles, stone throwing and pouring pile top horizontal and longitudinal beams. Each process has separate construction equipment, resulting in low utilization rate of some construction equipment, which affects the construction cost of high-pile wharf construction. Summary of the Invention

[0003] The purpose of the present invention is to overcome the problem of low utilization rate of some construction equipment during the construction of high-pile docks in the background art, and to provide a dock structure construction method.

[0004] A wharf structure construction method comprises the following steps:

[0005] The steel pipe is lifted and placed vertically by a first lifting device, and then the steel pipe is driven to a predetermined position;

[0006] After the steel pipe is injected to the predetermined position, the inside of the steel pipe is processed;

[0007] Cutting off the excess portion of the upper portion of the steel pipe to form a remaining steel pipe section, and lifting the remaining steel pipe section away by the first lifting device;

[0008] Processing a steel cage, placing at least a portion of the steel cage into a steel pipe, and pouring concrete into the steel pipe to form a steel pipe pile;

[0009] A corbel is welded on the outside of the steel pipe through a steel pipe pile working platform, at least part of the structure on the corbel is formed by splitting the remaining steel pipe section, and the steel pipe pile working platform can move laterally relative to the steel pipe.

[0010] The present application describes a method for constructing a wharf structure, which can lift and vertically arrange the steel pipe through a first lifting device, and can also lift away the remaining steel pipe section. Moreover, according to the steel pipe pile working platform, it can move laterally relative to the steel pipe to realize the welding of multiple steel pipe outer side corbels, thereby improving the utilization rate of the first lifting device and the steel pipe pile working platform. At the same time, when making the corbels, the remaining steel pipe sections that have been cut off are used for further cutting and processing as at least a part of the corbels. The method of using construction site materials to process the corbels can effectively improve the construction efficiency, thereby jointly reducing the construction cost of high-pile wharf construction.

[0011] Preferably, at least three through holes are circumferentially opened at one end of the steel pipe, wherein the three through holes are a first through hole, a second through hole and a third through hole, and the first through hole, the second through hole and the third through hole are all located on the remaining steel pipe section; the first lifting device includes a first lifting rope assembly and a second lifting rope assembly, wherein the first lifting rope assembly includes a first main rope, the lower end of the first main rope is connected to the first lifting rope and the second lifting rope; the second lifting rope assembly includes a second main rope, the lower end of the second main rope is connected to the third lifting rope, the fourth lifting rope and the fifth lifting rope are connected to the free end of the third lifting rope;

[0012] Lifting and vertically arranging the steel pipe using the first lifting device includes the following steps: A1: inserting the first lifting hook into the first through hole, the second lifting hook into the second through hole, and the third lifting hook into the third through hole, and hooking the first, second, and third lifting hooks to each other, and wrapping the first and second lifting ropes around and fixing them to the other end of the steel pipe; A2: adjusting the steel pipe from a horizontal position to a vertical position by first lifting the second lifting rope assembly and then lifting the first lifting rope assembly, or by lifting the second lifting rope assembly faster than the first lifting rope assembly;

[0013] Lifting the remaining steel pipe section by the first lifting device includes the following steps: A3: lowering the third lifting rope, the fourth lifting rope and the fifth lifting rope from the steel pipe, and reversely hanging the first hook at the first through hole, reversely hanging the second hook at the second through hole, and reversely hanging the third hook at the third through hole; A4: lifting the second lifting rope assembly to adjust and remove the remaining steel pipe section.

[0014] Preferably, the steel pipe is provided with two through holes arranged opposite to each other, the two through holes being a first through hole and a second through hole respectively; the first lifting device comprises a first lifting rope assembly, a second lifting rope assembly and an auxiliary lifting assembly; the first lifting rope assembly comprises a first main rope, the lower part of the first main rope is connected to the first lifting rope and the second lifting rope; the second lifting rope assembly comprises a second main rope, the lower part of the second main rope is connected to the third lifting rope and the fourth lifting rope, the lower end of the third lifting rope is provided with a first lifting ring and a second lifting ring, the lower end of the fourth lifting rope is provided with a third lifting ring, the first lifting ring extends into the first through hole, and the second lifting ring extends into the second through hole; the auxiliary lifting assembly comprises an auxiliary lifting rope, the end of the auxiliary lifting rope is connected to an auxiliary pin, the auxiliary pin can pass through the first lifting ring, the second lifting ring and the third lifting ring, and can lock the third lifting ring between the first lifting ring and the second lifting ring when the third lifting rope and the fourth lifting rope are tensioned, and when the auxiliary lifting rope applies tension to the auxiliary pin, the auxiliary pin can detach from the first lifting ring, the second lifting ring and the third lifting ring.

[0015] The construction method comprises the following steps:

[0016] B1. Insert the first and second lifting rings into the first through-hole, and the third lifting ring into the second through-hole, so that the third lifting ring is set between the first and second lifting rings. Then, insert the auxiliary pin from the end of the steel pipe into the steel pipe, and pass the auxiliary pin through the first, third and second lifting rings in sequence. Then, tighten the third and fourth lifting ropes so that one side of the auxiliary pin is pressed against the first and second lifting rings, and the other side of the auxiliary pin is pressed against the third lifting ring; wrap the first and second lifting ropes around and fix them on the other end of the steel pipe; B2. Lift the second lifting rope first The method of lifting the first lifting rope assembly after the auxiliary lifting assembly, or the method of lifting the second lifting rope assembly faster than the first lifting rope assembly to change the steel pipe from horizontal to vertical, and lift it to a predetermined position and fix it; B3. The third lifting rope and the fourth lifting rope are in a relaxed state; B4. The auxiliary lifting assembly is raised so that the auxiliary lifting rope drives the auxiliary pin to rotate vertically and move upward, so that the auxiliary pin is separated from the first lifting ring, the second lifting ring and the third lifting ring, until the auxiliary pin lifts out the steel pipe; B5. Lift the second lifting rope assembly, and pull the first lifting ring out of the first through hole, and the second lifting ring out of the second through hole.

[0017] Preferably, after the steel pipe is injected into the predetermined position, the inside of the steel pipe is processed, and the inner bottom of the steel pipe is detected by a detection system, the detection system includes a cable retraction device, a detector and a control console connected by a data transmission cable; the detector includes a camera and a liquid level sensor suspended below the camera, the camera and the liquid level sensor are both communicatively connected to the control console via the data transmission cable; the cable retraction device includes a motor, a steering pulley and a drum, the data transmission cable is wound on the drum, the motor can drive the drum to rotate, so that the drum can retract and release the data transmission cable by forward or reverse rotation; the steering pulley is mounted on the top of the steel pipe; the control console is provided with a display screen for displaying the image taken by the camera and the liquid level height detected by the liquid level sensor.

[0018] Preferably, it further includes a steel bar rotating device; the steel bar cage includes two main threaded steel bars coaxially connected by a steel bar sleeve; the steel bar rotating device includes a driving device and a clamping mechanism, the clamping mechanism includes a connected clamp head structure and a clamp wall structure, the end of the clamp wall structure away from the clamp head structure is connected to a first rod, the first rod and the clamp wall structure are bent at the connection, a universal joint is connected between the end of the first rod away from the clamp wall structure and the output shaft of the driving device, the clamp head structure is correspondingly arranged, the clamp head structure clamps the main threaded steel bar from one side, and the clamp head structure is located at the end of the main threaded steel bar away from the steel bar sleeve;

[0019] The longitudinal reinforcement is driven to rotate by the reinforcement rotating device so that the main thread reinforcement and the adjacent main thread reinforcement are connected through the reinforcement sleeve;

[0020] Preferably, the cage clamp device includes a first structure and a second structure, the first structure and the second structure are connected by a connecting assembly, and there is a clamping space between the first structure and the second structure, and a threaded steel bar is provided on at least one side of the clamping space, and the threaded steel bar is connected to the first structure or the second structure.

[0021] Preferably, the steel pipe pile working platform comprises at least two platform structures arranged at intervals, with a passage between adjacent platform structures, one of the adjacent platform structures is provided with a first slide, and the other is provided with a second slide, and the first slide and the second slide are both arranged along the direction of the passage; at least three first sliders are slidably fitted in the first slide, and at least three second sliders are slidably fitted in the second slide, and the first slider and the second slider are correspondingly arranged; the first slider and the second slider are both connected to a hook lock; the slider on the first slide can enter and exit the first slide from both ends of the first slide, and the slider on the second slide can enter and exit the second slide from both ends of the second slide; both ends of the first slide and the second slide are open; a door frame is fixedly connected between the adjacent platform structures, and the steel pipe and the corbel can pass through the door frame;

[0022] The specific steps of welding the brackets on the outside of the steel pipes by the steel pipe pile working platform are as follows: C1: For a number of steel pipes extending out of the water and distributed linearly, the hook lock can be installed on two or three steel pipes by a lifting machine, and the bracket welding operation can be performed on the two or three steel pipes, and the two or three steel pipes are located in the channel; C2: A pulling device is installed on the steel pipes on one side of the channel, and the pulling device is connected to the steel pipe pile working platform, and the steel pipe pile working platform is driven to move by the pulling device until one or several steel pipes in the foreground direction of the steel pipe pile working platform enter the channel; in this process, the steel pipes are When the hook lock is pulled, the hook lock will drag the first slider to slide in the first slide, and the second slider will slide in the second slide, thereby maintaining the hook state of the hook lock and the steel pipe during the movement of the steel pipe pile work platform; C3: during the movement of the steel pipe pile work platform, when the steel pipe located at the rear end of the forward direction of the steel pipe pile work platform corresponds to the end position of the first slide and the second slide, the hook lock and the corresponding first slider and second slide connected to the steel pipe are removed and installed on the steel pipe entering the channel from the front end of the forward direction of the steel pipe pile work platform, C4: loop steps C1-C3 until the bracket welding is completed.

[0023] Preferably, the step of throwing stones around the steel pipe piles is further included: the stones are lifted by the second lifting device, and the second lifting device includes: a male and female pin connection assembly, including a first sub-head, a second sub-head and a female head, the first sub-head and the second sub-head can be matched with the female head at the same time, and the first sub-head, the second sub-head and the female head can be connected by a pin; the main lifting assembly includes a first sling and a bottom chain, the first sling is connected to the first chain, the second chain and the third chain, wherein: the lower end of the first chain is connected to the hook 1, the lower end of the second chain is connected to the hook 1 There are a first branch chain and a second branch chain, the lower end of the first branch chain is connected to a hook 2, the lower end of the second branch chain is connected to a hook 3, one end of the bottom chain is connected to the female head, and the bottom of the third chain is connected to the first sub-head; the auxiliary lifting assembly includes a second sling, the second sling is connected to a lifting rope 1 and a fourth chain, wherein: the length of the fourth chain is longer than the length of the lifting rope 1, the lower end of the fourth chain is connected to the second sub-head, and the bottom of the lifting rope 1 is connected to one end of the pin; the end of the bottom chain away from the female head is connected to the first sling;

[0024] Lifting the stone includes the following steps: S1. Arranging the first chain, the second chain and the third chain along the circumference of the stone; S2. Matching the first sub-head, the second sub-head and the female head, and passing the pin through the first sub-head, the second sub-head and the female head, and the pin connecting one end of the lifting rope to the stone; S3. Forming an arc shape around the stone from the bottom of one side of the stone near the female head and tightening it, and hanging the hook one and the hook two on the bottom chain, so that the first chain, the second chain, the third chain and the bottom chain hold the stone from one side of the stone; S4. Forming an arc shape around the stone from the bottom of the other side of the stone near the second sub-head and tightening it, and hanging the hook three on the fourth chain, so that the second chain, the third chain and the fourth chain hold the stone from the other side of the stone. At this time, the first branch chain, the second branch chain, the part of the bottom chain between the hook two and the female head and the fourth chain on the hook and a third chain between the first and second sub-heads and the second sub-head, so that the bottom chain is in a relaxed state, and the portion of the fourth chain between the hook three and the second hoist is also in a relaxed state; S6. After the stone is lifted to the target position, the first hoist is continued to be lowered for a distance, so that the first chain, the second chain and the third chain are all in a relaxed state; S7. The second hoist is lifted, so that the first rope drives the pin to disengage from the first sub-head, the second sub-head and the female head, so that the bottom chain is in a relaxed state, and the portion of the fourth chain between the hook three and the second sub-head is also in a relaxed state; S8. The first hoist is lifted, and the second hoist is lifted, so that the first sub-head, the second sub-head and the female head are separated; S9. The first hoist is continued to be lifted, and the stone throwing device is separated from the stone.

[0025] Preferably, the corbel includes a first side plate and a second side plate arranged opposite to each other, one end of the first side plate is connected to the steel pipe, and the other end is connected to the end plate, one end of the second side plate is connected to the steel pipe, and the other end is connected to the end plate, and the first side plate and the second side plate are both formed by cutting the remaining steel pipe section.

[0026] Preferably, the beam grid includes at least two beam grid units arranged in sequence, and the beam grid unit includes three longitudinal beam grooves and four transverse beam grooves arranged in sequence, wherein the longitudinal beam grooves intersect with the transverse beam grooves at a groove node, and the longitudinal beam grooves of adjacent beam grid units correspond to and are connected; the three longitudinal beam grooves are numbered C, D and E in sequence, and the four transverse beam grooves are numbered 1, 2, 3, and 4 in sequence, and the groove nodes between the longitudinal beam grooves and the transverse beam grooves are numbered C1, C2, C3, and C4, D1, D2, D3, and D4, and E1, E2, E3, and E4; per unit time, the amount of concrete material pumped by the first pumping pipe is the same as the amount of concrete material pumped by the second pumping pipe;

[0027] The construction method comprises the following steps:

[0028] S1: Set the first pump pipe at the C1 slot node; set the second pump pipe at the D1 slot node, and start pouring at the C1 slot node and the D1 slot node at the same time, and the concrete at the C1 slot node and the D1 slot node are spread to the surroundings;

[0029] S2: Concrete delivery at the C1, C2, D2, D3, C3, and C4 slot nodes is completed in sequence through the first pump pipe, and concrete delivery at the D1, E1, E2, E3, E4, and D4 slot nodes is completed in sequence through the second pump pipe simultaneously;

[0030] S3: Move the first pumping pipe to the C1 slot node of the next beam grid unit, and at the same time move the second pumping pipe to the D1 slot node of the next beam grid unit; then repeat S1-S2 until the concrete feeding of all the transverse and longitudinal beam slot sections is completed to form the transverse and longitudinal beam slots.

[0031] Compared with the prior art, the present invention has the following beneficial effects:

[0032] The present application describes a method for constructing a wharf structure, which can lift and vertically arrange the steel pipe through a first lifting device, and can also lift away the remaining steel pipe section. Moreover, according to the steel pipe pile working platform, it can move laterally relative to the steel pipe to realize the welding of multiple steel pipe outer side corbels, thereby improving the utilization rate of the first lifting device and the steel pipe pile working platform. At the same time, when making the corbels, the remaining steel pipe sections that have been cut off are used for further cutting and processing as at least a part of the corbels. The method of using construction site materials to process the corbels can effectively improve the construction efficiency, thereby jointly reducing the construction cost of high-pile wharf construction. BRIEF DESCRIPTION OF THE DRAWINGS

[0033] Figure 1 This is a three-dimensional schematic diagram of the first lifting device of this application ( Figure 1 a is a direction, Figure 1 b is the other direction).

[0034] Figure 2 This is a schematic front view of the first lifting device of the present application.

[0035] Figure 3 This is a schematic structural diagram of the second suspension rope assembly of the present application.

[0036] Figure 4 This is a schematic diagram of the second lifting rope assembly of this application lifting the remaining steel pipe section.

[0037] Figure 5 This is a schematic diagram of the main view of the first lifting device of this application.

[0038] Figure 6 This is a right side schematic diagram of the setting of the first lifting device of this application.

[0039] Figure 7 For this application Figure 6 Enlarged schematic diagram of part A in the middle.

[0040] Figure 8 This is a schematic structural diagram of the auxiliary pin shaft of this application.

[0041] Figure 9 Schematic diagram of the detection system of this application.

[0042] Figure 10 This is a schematic diagram of the structure of the detector of this application.

[0043] Figure 11 This is a schematic structural diagram of the steel bar rotation device of this application.

[0044] Figure 12 This is a construction diagram of the main threaded steel bars and steel bar rotation device of this application.

[0045] Figure 13 This is a schematic structural diagram of the clamp head structure of this application.

[0046] Figure 14 This is a schematic diagram of the limiting coordination of the main threaded steel bars and threaded steel bars in this application.

[0047] Figure 15 This is a structural diagram of the cage card device of this application ( Figure 15 a is a direction, Figure 15 b is the other direction).

[0048] Figure 16 This is a schematic top view of the structure of the cage clamp device of the present application.

[0049] Figure 17 This is a schematic diagram of the structural coordination of the steel rod and bolts of this application.

[0050] Figure 18 This is a schematic top view of the second structure of the present application.

[0051] Figure 19 This is a top view schematic diagram of the matching structure of the steel cage, cage clamp device and steel pipe of this application.

[0052] Figure 20 This is a schematic diagram of the steel pipe pile operation platform of this application (working status);

[0053] Figure 21 This is a schematic diagram of the operation of the steel pipe pile operation platform of this application (the state when the steel pipe enters the channel);

[0054] Figure 22 This is a schematic diagram of the operation of the steel pipe pile operation platform of this application (steel pipes entering the channel);

[0055] Figure 23 This is a top view schematic diagram of the layout of the steel pipe pile working platform of this application;

[0056] Figure 24 This is a left side schematic diagram of the layout of the steel pipe pile working platform of this application;

[0057] Figure 25 For this application Figure 24 Enlarged schematic diagram of part A in the middle.

[0058] Figure 26 This is a schematic diagram of the welding between the bracket and the steel pipe in this application.

[0059] Figure 27 This is a schematic diagram of the main crane assembly structure of this application.

[0060] Figure 28 This is a schematic diagram of the auxiliary suspension component structure of this application.

[0061] Figure 29 For this application Figure 28 Enlarged schematic diagram of part A in the middle.

[0062] Figure 30 This is a schematic diagram of the main hanging assembly and auxiliary hanging assembly of this application.

[0063] Figure 31 This is a rear view schematic diagram of the main hanging assembly and auxiliary hanging assembly of this application.

[0064] Figure 32 This is a schematic diagram of the structure of the parent-child pin connection assembly of this application.

[0065] Figure 33 This is a schematic diagram of the casting sequence of the longitudinal beam trough, transverse beam trough, and trough node of this application. DETAILED DESCRIPTION

[0066] The present invention will be further described in detail below with reference to specific embodiments. However, this should not be construed as limiting the scope of the present invention to the following embodiments, as all technologies implemented based on the present invention fall within the scope of the present invention.

[0067] Unless otherwise specified, in the description of the specific embodiments of the present invention, the terms indicating orientation or positional relationships such as "upper," "lower," "left," "right," "center," "inside," and "outside" are based on the orientation or positional relationships shown in the accompanying drawings, or are the orientation or positional relationships in which the invented product / device / apparatus is placed when it is conventionally used. These terms of orientation or positional relationships are merely for the purpose of facilitating the description of the present invention or simplifying the description of the specific embodiments to facilitate a quick understanding of the solutions by technicians. They do not indicate or imply that a particular device / component / element must have a specific orientation or be constructed and operated in a specific positional relationship. Therefore, they should not be construed as limitations on the present invention.

[0068] In addition, if the terms "horizontal", "vertical", "overhanging", "parallel" and the like appear, it does not mean that the corresponding devices / components / elements are required to be absolutely horizontal or vertical or overhanging or parallel, but may be slightly tilted or have deviations. For example, "horizontal" only means that its direction is more horizontal than "vertical", and does not mean that the structure must be completely horizontal, but may be slightly tilted. Alternatively, it can be simply understood that the corresponding devices / components / elements are set in directions such as "horizontal", "vertical", "overhanging", and "parallel", and can have an error / deviation of ±10% relative to the corresponding direction setting, more preferably an error / deviation within ±8%, more preferably an error / deviation within ±6%, more preferably an error / deviation within ±5%, and more preferably an error / deviation within ±4%. As long as the corresponding device / component / element is within the error / deviation range, it can still achieve its role in the solution of the present invention.

[0069] In addition, the expressions "first", "second", "third", etc. that appear in the terms are merely descriptions used to distinguish the same or similar components and should not be understood as emphasizing or implying the relative importance of specific components.

[0070] In addition, in the description of the embodiments of the present invention, "several," "plurality," and "a number" represent at least two. It can also be any number such as two, three, four, five, six, seven, eight, nine, or even more than nine.

[0071] Furthermore, in the description of the technical solution of the present invention, unless otherwise expressly specified, defined, or limited, the terms "disposed," "installed," "connected," "connected," "provided with," "laid," and "arranged" should be understood broadly. For example, they may refer to fixed connections, detachable connections, or integral connections. They may be welded, riveted, bolted, threaded, or other commonly used connection methods in the art. Such connections may be mechanical, electrical, or communicative; they may be direct, indirect via an intermediate medium, or internally connected between two components.

[0072] Example 1

[0073] like Figure 1-33 As shown, this embodiment provides a wharf structure construction method as described in the present application, comprising the following steps: lifting a steel pipe 1 by a first lifting device and vertically arranging it, then driving the steel pipe 1 to a predetermined position, cutting off the excess portion of the upper portion of the steel pipe 1 to form a remaining steel pipe section 11, and lifting the remaining steel pipe section 11 away by the first lifting device;

[0074] A preferred method is: after the steel pipe 1 is injected to a predetermined position, the inside of the steel pipe 1 is processed, and the bottom of the inner side of the steel pipe 1 is inspected by a detection system;

[0075] A preferred method is to process the steel cage 3, place at least a portion of the steel cage 3 into the steel pipe 1, and use a cage clamp device to position the relative depth of the bottom of the steel cage 3 and the steel pipe 1, and pour concrete into the steel pipe 1 to form a steel pipe pile;

[0076] A preferred method is to weld a corbel 4 on the outside of the steel pipe 1 through a steel pipe pile working platform, wherein at least part of the structure on the corbel 4 is formed by splitting the remaining steel pipe section 11, and the steel pipe pile working platform can move laterally relative to the steel pipe 1;

[0077] A preferred method is: using a second lifting device to perform riprap construction around the steel pipe piles;

[0078] A preferred method is to set up a formwork system on the corbel 4 to form a beam grid groove, and place steel bars in the beam grid groove and cast them to form transverse and longitudinal beams.

[0079] like Figure 1-5 As shown, a preferred embodiment is as follows: at least three through holes are circumferentially opened at one end of the steel pipe 1, wherein the three through holes are a first through hole 111, a second through hole 112 and a third through hole 113, and all of them are located on the remaining steel pipe section 11;

[0080] The first lifting device includes a first lifting rope assembly and a second lifting rope assembly. The first lifting rope assembly includes a first main rope 101, the lower end of which is connected to a first lifting rope 103 and a second lifting rope 104; the second lifting rope assembly includes a second main rope 102, the lower end of which is connected to a third lifting rope 105, a fourth lifting rope 106 and a fifth lifting rope 107, the free end of the third lifting rope 105 is connected to a first lifting hook 108, the free end of the fourth lifting rope 106 is connected to a second lifting hook 109, and the free end of the fifth lifting rope 107 is connected to a third lifting hook 110;

[0081] Lifting the steel pipe 1 and vertically arranging it by the first lifting device includes the following steps: A1: inserting the first hook 108 into the first through hole 111, the second hook 109 into the second through hole 112, and the third hook 110 into the third through hole 113, and hanging the first hook 108, the second hook 109, and the third hook 110 to each other, and winding and fixing the first lifting rope 103 and the second lifting rope 104 around the other end of the steel pipe 1; A2: adjusting the steel pipe 1 from the horizontal direction to the vertical direction by first lifting the second lifting rope assembly and then lifting the first lifting rope assembly, or by lifting the second lifting rope assembly faster than the first lifting rope assembly;

[0082] Lifting the remaining steel pipe section 11 by the first lifting device includes the following steps: A3: lowering the third lifting rope 105, the fourth lifting rope 106 and the fifth lifting rope 107 from the steel pipe 1, and reversely hanging the first hook 108 on the first through hole 111, the second hook 109 on the second through hole 112, and reversely hanging the third hook 110 on the third through hole 113; A4: lifting the second lifting rope assembly to adjust and remove the remaining steel pipe section 11.

[0083] During construction, the steel pipe 1 is changed from a horizontal state to a vertical state by first lifting the second lifting rope assembly and then lifting the first lifting rope assembly, or the lifting speed of the second lifting rope assembly is faster than that of the first lifting rope assembly, so that the steel pipe 1 can be placed on the piling equipment. In the above process, since the first hook 108, the second hook 109 and the third hook 110 are hung with each other in the steel pipe 1, and the first lifting rope 103 and the second lifting rope 104 are wrapped and fixed on the other end of the steel pipe 1, no lifting lugs are set on the outside of the steel pipe 1 throughout the whole process, thereby fundamentally avoiding the interference between the lifting lugs and the outer hoop equipment, and the problem that the lifting lugs are easily deformed by collision.

[0084] like Figure 5 As shown, in the later pile cutting process, the third lifting rope 105, the fourth lifting rope 106 and the fifth lifting rope 107 are lowered from the steel pipe 1, and the first lifting hook 108 is reversely hung at the first through hole 111, the second lifting hook 109 is reversely hung at the second through hole 112, and the third lifting hook 110 is reversely hung at the third through hole 113, so that the construction personnel can lift the part of the steel pipe 1 that has been cut by pulling out the hooks through the first through hole 111, the second through hole 112 and the third through hole 113, so that the steel pipe pile lifting device of the present application can not only be used for the lifting operation of the steel pipe 1, but also can take into account the lifting and moving operation of the remaining steel pipe section 11 cut during pile cutting, thereby making the second lifting rope assembly of the present application more universal.

[0085] The center of gravity of the steel pipe 1 is located between the first lifting rope assembly and the second lifting rope assembly; the first lifting rope 103 and the second lifting rope 104 are wound in opposite directions to reduce the swing amplitude of the steel pipe 1 during the lifting process; the first through hole 111 and the third through hole 113 are coaxially arranged; during the lifting process of the steel pipe 1, the friction between the parts of the third lifting rope 105 and the fifth lifting rope 107 located on the outside of the steel pipe 1 and the outer wall of the steel pipe 1 can be reduced or avoided, thereby effectively extending the service life of the third lifting rope 105 and the fifth lifting rope 107.

[0086] like Figure 6-9 As shown, in another preferred embodiment, two through holes are provided on the steel pipe 1, which are respectively a first through hole 111 and a second through hole 112; the first lifting device includes a first lifting rope assembly, a second lifting rope assembly and an auxiliary lifting assembly 114; the first lifting rope assembly includes a first main rope 101, the lower part of the first main rope 101 is connected to the first lifting rope 103 and the second lifting rope 104; the second lifting rope assembly includes a second main rope 102, the lower part of the second main rope 102 is connected to the third lifting rope 105 and the fourth lifting rope 106, the lower end of the third lifting rope 105 is provided with a first lifting ring 115 and a second lifting ring 116, and the lower end of the fourth lifting rope 106 is provided with a third lifting ring 117 The first lifting ring 115 extends into the first through hole 111, and the second lifting ring 116 extends into the second through hole 112; the auxiliary lifting assembly 114 includes an auxiliary lifting rope 118, and the end of the auxiliary lifting rope 118 is connected to an auxiliary pin 119, and the auxiliary pin 119 can pass through the first lifting ring 115, the second lifting ring 116 and the third lifting ring 117, and can lock the third lifting ring 117 between the first lifting ring 115 and the second lifting ring 116 when the third lifting rope 105 and the fourth lifting rope 106 are tensioned, and when the auxiliary lifting rope 118 applies tension to the auxiliary pin 119, the auxiliary pin 119 can detach from the first lifting ring 115, the second lifting ring 116 and the third lifting ring 117.

[0087] The construction method comprises the following steps: B1. inserting the first lifting ring 115 and the second lifting ring 116 into the first through hole 111, and the third lifting ring 117 into the second through hole 112, with the third lifting ring 117 being arranged between the first lifting ring 115 and the second lifting ring 116; inserting the auxiliary pin 119 from the end of the steel pipe 1 into the steel pipe 1, and passing the auxiliary pin 119 through the first lifting ring 115, the third lifting ring 117 and the second lifting ring 116 in sequence; then tightening the third lifting rope 105 and the fourth lifting rope 106 so that one side of the auxiliary pin 119 is squeezed against the first lifting ring 115 and the second lifting ring 116, and the other side is squeezed against the third lifting ring 117; winding the first lifting rope 103 and the second lifting rope 104 around and fixing them to the other end of the steel pipe 1; B. 2. The steel pipe 1 is changed from horizontal to vertical by first lifting the second lifting rope assembly and then lifting the first lifting rope assembly, or by lifting the second lifting rope assembly faster than the first lifting rope assembly, and is lifted to a predetermined position and fixed; B3. The third lifting rope 105 and the fourth lifting rope 106 are in a relaxed state; B4. The auxiliary lifting assembly 114 is raised so that the auxiliary lifting rope 118 drives the auxiliary pin 119 to rotate vertically and move upward, so that the auxiliary pin 119 is separated from the first lifting ring 115, the second lifting ring 116 and the third lifting ring 117 until the auxiliary pin 119 lifts out the steel pipe 1; B5. Lift the second lifting rope assembly, and pull the first lifting ring 115 out of the first through hole 111, and the second lifting ring 116 out of the second through hole 112.

[0088] The present embodiment provides a steel pipe lifting construction method for steel pipe piles, which uses a first lifting rope assembly and a second lifting rope assembly to lift the steel pipe 1 to a predetermined position, and then uses the auxiliary pin 119 of the auxiliary lifting assembly 114 to disengage the auxiliary pin 119, the first lifting ring 115, the second lifting ring 116 and the third lifting ring 117, thereby achieving the purpose of automatically disengaging the second lifting rope assembly on the upper part of the steel pipe 1 from the steel pipe 1. Moreover, the entire process only requires setting the first through hole 111 and the second through hole 112 at one end of the steel pipe 1, and does not require setting a lifting ear on the outside of the steel pipe 1, thereby avoiding interference between the lifting ear and the outer hoop equipment, and reducing the impact of the lifting process on the downward movement of the steel pipe 1.

[0089] During the later pile cutting process, the first lifting ring 115, the second lifting ring 116 and the third lifting ring 117 are placed into the steel pipe 1 from the top, and then the first lifting ring 115 and the second lifting ring 116 are extended out of the first through hole 111, and the third lifting ring 117 is extended out of the second through hole 112, so that the third lifting ring 117 is set between the first lifting ring 115 and the second lifting ring 116, and then the auxiliary pin 119 is sequentially passed through the first lifting ring 115, the third lifting ring 117 and the second lifting ring 116, and then the lifting is carried out.

[0090] Moreover, in step B1, when one side of the auxiliary pin 119 is squeezed against the first lifting ring 115 and the second lifting ring 116, and the other side of the auxiliary pin 119 is squeezed against the third lifting ring 117, it can effectively ensure that the auxiliary pin 119 does not separate from the first lifting ring 115, the second lifting ring 116 and the third lifting ring 117 during the lifting process, thereby ensuring the construction safety of the lifting process.

[0091] Auxiliary pin 119 is provided with a first inner recess 120 that cooperates with first lifting ring 115; a second inner recess 121 that cooperates with second lifting ring 116; and a third inner recess 122 that cooperates with third lifting ring 117. This further effectively ensures that auxiliary pin 119 does not separate from first lifting ring 115, second lifting ring 116, and third lifting ring 117 during the lifting process, thereby ensuring construction safety during the lifting process.

[0092] like Figure 9 As shown, the auxiliary pin 119 includes a shaft body 123, one end of the shaft body 123 along the axial direction is connected to the auxiliary lifting rope 118, and the other end of the shaft body 123 along the axial direction is connected to the shaft end structure 124, the shaft end structure 124 can pass through the first lifting ring 115, the second lifting ring 116 and the third lifting ring 117, and at least one side of the shaft end structure 124 protrudes radially from the shaft body 123 along the auxiliary pin 119.

[0093] During the lifting process, the third lifting rope 105 and the fourth lifting rope 106 are tensioned, and one side of the auxiliary pin 119 is squeezed against the first lifting ring 115 and the second lifting ring 116, and the other side of the auxiliary pin 119 is squeezed against the third lifting ring 117. In this case, at least one side of the shaft end structure 124 protrudes radially along the shaft body 123 of the auxiliary pin 119, which can further ensure that the auxiliary pin 119 does not separate from the first lifting ring 115, the second lifting ring 116 and the third lifting ring 117 during the lifting process, thereby better ensuring the construction safety of the lifting process.

[0094] The shaft end structure 124 is a frustum structure, and the small end of the shaft end structure 124 is threadedly connected to the shaft body 123. The diameter of the small end of the shaft end structure 124 is adapted to the diameter of the shaft body 123. The shaft end structure 124 can be elastically deformed along the axial direction of the shaft body 123.

[0095] like Figure 10As shown, a preferred method is as follows: the detection system includes a cable retraction device 204, a detector 202 and a console 201 connected by a data transmission cable 203; the detector 202 includes a camera 207 and a liquid level sensor 208 suspended below the camera 207, and the camera 207 and the liquid level sensor 208 are both communicatively connected to the console 201 via the data transmission cable 203; the cable retraction device 204 includes a motor 216, a steering pulley 205 and a drum 206, the data transmission cable 203 is wound around the drum 206, and the motor 216 can drive the drum 206 to rotate, so that the drum 206 can realize the retraction and extension of the data transmission cable 203 by forward or reverse rotation; the steering pulley 205 is mounted on the top of the steel pipe 1; the console 201 is provided with a display screen 209 for displaying the image taken by the camera 207 and the liquid level height detected by the liquid level sensor 208.

[0096] In a preferred manner, the data transmission cable 203 is partially wound in a forward direction on one side of the reel 206 , and partially wound in a reverse direction on the other side, so as to realize the retraction and extension of the data transmission cable 203 .

[0097] like Figure 11 As shown, camera 207 includes a lens 210, a cylindrical housing 211, and a camera data cable 212. Lens 210 is embedded in one end of cylindrical housing 211, and the other end of cylindrical housing 211 is connected to console 201 via camera data cable 212. Liquid level sensor 208 includes a probe 213, a liquid level sensor data cable 215, and a mounting plate 214. Probe 213 is embedded in the center of mounting plate 214 and connected to console 201 via liquid level sensor data cable 215. The edge of mounting plate 214 is suspended from cylindrical housing 211. Data transmission cable 203 is an armored cable that encases camera data cable 212 and liquid level sensor data cable 215.

[0098] The liquid level sensor 208 is connected to the camera 207 in a suspended manner via a flexible rope 217 , so that when the camera 207 and the liquid level sensor 208 move in the well, the liquid level sensor 208 is always suspended directly below the camera 207 .

[0099] In one preferred embodiment, the data transmission cable 203 and the cable retraction device 204 together constitute a single-line winch. The data transmission cable 203 comprises a first cable and a second cable. One end of the first cable is connected to the detector 202, and the other end is connected to the cable retraction device 204. One end of the second cable is connected to the cable retraction device 204, and the other end is connected to the control console 201. The cable retraction device 204 is equipped with a communication converter, enabling communication between the first cable and the second cable.

[0100] The liquid level sensor 208 is used to detect whether there is water at the bottom of the steel pipe 1 and the liquid level, so as to prevent the camera 207 from being directly lowered into the water and causing damage.

[0101] like Figure 12-14 As shown, a preferred embodiment includes: a steel bar rotating device; the steel cage 3 includes two main threaded steel bars 301 coaxially connected by a steel sleeve 303; the steel bar rotating device includes a driving device 401 and a clamping mechanism, the clamping mechanism includes a clamp head structure 402 and a clamp wall structure 403 connected thereto, the end of the clamp wall structure 403 away from the clamp head structure 402 is connected to a first rod 404, the connection between the first rod 404 and the clamp wall structure 403 forms a bend, a universal joint 405 is connected between the end of the first rod 404 away from the clamp wall structure 403 and the output shaft 411 of the driving device 401, the clamp head structure 402 and the output shaft 411 are correspondingly arranged, the clamp head structure 402 clamps the main threaded steel bar 301 from one side of the main threaded steel bar 301, and the clamp head structure 402 is located at one end of the main threaded steel bar 301 away from the steel sleeve 303;

[0102] The longitudinal reinforcement is driven to rotate by the reinforcement rotating device so that adjacent main thread reinforcement bars 301 are connected through the reinforcement sleeves 303 .

[0103] During construction, the driving device 401 is installed at the end of the steel bar. Since the first rod 404 is bent at the connection with the clamp wall structure 403, the clamp head structure 402 can clamp the steel bar from the side of the steel bar. Compared with clamping along the axial direction of the steel bar, the clamping is more stable. In addition, a universal joint 405 is connected between the end of the first rod 404 away from the clamp wall structure 403 and the output shaft 411 of the driving device 401. The torsional force of the output shaft 411 of the driving device 401 is transmitted to the first rod 404, the clamp wall structure 403 and the clamp head structure 402 in sequence through the universal joint 405. 2 is provided corresponding to the output shaft 411, so that the clamp head structure 402 can rotate around the rotation center of the output shaft 411, thereby driving the steel bar to rotate. When the steel bar rotates and its own weight produces a large rotation deformation, which will drive the end of the steel bar to jump, the universal joint 405 is capable of rotating in two directions, so that the clamp head structure 402 can also swing within a certain range along the radial direction of the output shaft 411, thereby effectively reducing the clamping force of the clamp head structure 402 used to overcome the steel bar from escaping the clamp head structure 402, thereby greatly reducing the probability of the steel bar end escaping the clamp head structure 402 due to jumping.

[0104] The clamp head structure 402 includes a first clamp head 412 and a second clamp head 413 arranged opposite to each other. A clamping space 307 and an opening 15 are formed between the first clamp head 412 and the second clamp head 413. The opening 15 is arranged radially along the output shaft 411. The first rod 404 and the clamp wall structure 403 together form an arch structure. The clamp head structure 402 is also provided with a limit ring 406 protruding from one side of the first rod 404. The limit ring 406 is coaxially arranged with the output shaft 411 and rotates together with the clamp head structure 402. During construction, the end of the steel bar is inserted into the limit ring 406 to reduce the amplitude of the steel bar end's vibration. It can also help reduce the clamping force of the clamp head structure 402 used to overcome the steel bar's escape from the clamp head structure 402, thereby greatly reducing the probability of the steel bar end escaping the clamp head structure 402 due to vibration.

[0105] The retaining ring 406 is connected to the first rod 404. Specifically, the retaining ring 406 is hingedly connected to the first rod 404, allowing the retaining ring 406 to swing toward or away from the output shaft 411. The retaining ring 406 is located between the clamp head structure 402 and the drive device 401. The clamp assembly is located at the end of the main threaded steel bar 301, and the output shaft 411 is coaxially spaced from the main threaded steel bar 301.

[0106] like Figure 15-21 As shown, a preferred solution is as follows: the cage clamp device includes a first structure 304 and a second structure 305, the first structure 304 and the second structure 305 are connected by a connecting component 306, and a clamping space 307 is provided between the first structure 304 and the second structure 305, and a threaded steel bar 308 is provided on at least one side of the clamping space 307, and the threaded steel bar 308 is connected to the first structure 304 or the second structure 305.

[0107] The steel cage 3 includes a plurality of longitudinally arranged main threaded steel bars 301 and circumferentially arranged connecting steel bars 302 . The connecting steel bars 302 are used to connect adjacent main threaded steel bars 301 . The connecting steel bars 302 are spaced apart from the steel pipe pile steel cage 3 .

[0108] By utilizing the semi-annular protrusions and grooves on the side of the threaded steel bar 308 itself, they are matched with the semi-annular protrusions and grooves on the side of the main threaded steel bar 301 of the steel cage 3 during use, so that the threaded steel bar 308 can limit the movement of the main threaded steel bar 301 relative to the first structure 304 and the second structure 305, thereby ensuring that when the first structure 304 and the second structure 305 clamp the main threaded steel bar 301, the main threaded steel bar 301 and the first structure 304 and the second structure 305 do not move relative to each other, so that the steel cage 3 does not move relative to the cage clamping device of the present application, so as to ensure the relative height between the bottom of the steel cage 3 and the bottom of the steel pipe 1 pile, thereby effectively improving the construction quality of the steel pipe 1 forming.

[0109] Threaded steel bars 308 are provided on both sides of the clamping space 307, and recessed portions 309 are provided on the first structure 304 and / or the second structure 305. The recessed portions 309 cooperate with the threaded steel bars 308. This enables accurate positioning of the threaded steel bars 308, thereby making the threaded steel bars 308 easier to install.

[0110] The connecting assembly 306 includes at least two bolt assemblies, and the clamping space 307 is between the at least two bolt assemblies. A steel rod 311 is connected between the bolt caps 310 of the at least two bolt assemblies located on either side of the clamping space 307. This allows the bolt 313 to not rotate when tightening the nut 312 at the other end, or to not rotate after rotating a certain angle, making the construction of the bolt assembly more convenient. The first structure 304 includes a first plate 314 and a first rib 315, which are connected to each other. The first rib 315 is connected to the side of the first plate 314 away from the clamping space 307. The first plate 314 and the first rib 315 are perpendicular to each other.

[0111] A portion of the steel cage 3 extends into the steel pipe 1. The steel pipe 1 and the steel cage 3 are both arranged vertically. The steel cage 3 includes several main threaded steel bars 301 arranged along the length of the steel cage 3. At least one main threaded steel bar 301 extends through the clamping space 307. The side of the main threaded steel bar 301 and the threaded steel bar 308 are positioned in a concave and convex manner. The first structure 304 abuts the top of the steel pipe 1. The main threaded steel bars 301 and the threaded steel bars 308 have the same diameter.

[0112] like Figure 22-25 As shown, the steel pipe pile work platform includes at least two platform structures 501 arranged at intervals, and a channel 502 is provided between adjacent platform structures 501. One of the adjacent platform structures 501 is provided with a first slide 503, and the other is provided with a second slide 504. The first slide 503 and the second slide 504 are both arranged along the direction of the channel 502; at least three first sliders 505 are slidably fitted in the first slide 503, and at least three second sliders 506 are slidably fitted in the second slide 504, and the first slider 505 and the second slider 506 are arranged correspondingly; the first slider 505 and the second slider 506 are both connected to a hook lock 507; the slider 14 on the first slide 503 can enter and exit the first slide 503 from both ends of the first slide 503, and the slider 14 on the second slide 504 can enter and exit the second slide 504 from both ends of the second slide 504.

[0113] Both ends of the first slide 503 and the second slide 504 are open; a door frame 508 is fixedly connected between adjacent platform structures 501, and the steel pipe 1 and the corbel 4 can pass through the door frame 508.

[0114] The welding of the brackets 4 on the outside of the steel pipe 1 by the steel pipe pile working platform specifically includes the following steps: C1: For a number of steel pipes 1 extending out of the water and distributed linearly, the hook lock 507 can be installed on two or three steel pipes 1 by a lifting machine, and the bracket 4 welding operation is performed on the two or three steel pipes 1, wherein the two or three steel pipes 1 are located in the channel 502; C2: A pulling device 514 is installed on the steel pipe 1 on one side of the channel 502, and the pulling device 514 is connected to the steel pipe pile working platform. The pulling device 514 drives the steel pipe pile working platform to move until one or more steel pipes 1 in the foreground direction of the steel pipe pile working platform enters the channel 502; during this process, the hook lock 507 is pulled by the steel pipe 1, and the hook lock 507 drags the first slider 505 to slide in the first slide 503, and the second slider 506 to slide in the second slide 504, thereby maintaining the hooking state of the hook lock 507 and the steel pipe 1 during the movement of the steel pipe pile working platform. C3: During the movement of the steel pipe pile work platform, when the steel pipe 1 located at the rear end of the steel pipe pile work platform in the forward direction corresponds to the end position of the first slide 503 and the second slide 504, the hook lock 507 and the corresponding first slider 505 and second slide 504 connected to the steel pipe 1 are removed and installed on the steel pipe 1 entering the channel 502 from the front end of the steel pipe pile work platform in the forward direction. C4: Repeat steps C1-C3 until the welding of the bracket 4 is completed.

[0115] At least three first sliders 505 are slidably matched in the first slideway 503, and at least three second sliders 506 are slidably matched in the second slideway 504. The first sliders 505 and the second sliders 506 are correspondingly arranged. The first sliders 505 and the second sliders 506 are both connected with hook locks 507. The hook locks 507 can be used to hook the top of the steel pipe 1, thereby providing support for the steel pipe pile work platform. At least four hook locks 507 distributed on both sides of the channel 502 can more firmly hang and fix the steel pipe pile work platform on the steel pipe 1, thereby forming a support for the steel pipe 1. Working platform; through the sliding cooperation of the first slider 505 and the first slide 503, and the sliding cooperation of the second slider 506 and the second slide 504, the end of the hook lock 507 close to the platform structure 501 can move relative to the platform structure 501, so that the platform structure 501 can move relative to the steel pipe 1 to advance to the next working area, and maintain the hooking state with the steel pipe 1 during the movement, so that the working platform can be flexibly and conveniently formed between multiple consecutive steel pipes 1 through the moving movement of the steel pipe pile working platform, thereby realizing the processing operation of several steel pipes 1.

[0116] The steel pipe pile working platform of the present invention can be used to provide a working platform for a number of steel pipe piles 3 arranged in a straight line. When in use, the steel pipe pile working platform can be suspended on two adjacent steel pipe piles 3 by at least four hook locks 507 to form a working platform for the two steel pipe piles 3; after the operation is completed, the steel pipe pile working platform is pushed and pulled to move in the first direction, so that the next steel pipe pile 3 enters the steel pipe pile working platform along the channel 502, forming a working platform for the next steel pipe pile 3. The pulling equipment 514 is preferably a hand hoist, a winch, etc.

[0117] During the movement of the steel pipe pile work platform, the first slider 505 and the second slider 506 sliding out from the rear end of the movement direction can be used to connect with the next steel pipe 1 and re-enter the slideway from the front end of the movement direction, thereby realizing the recycling of the first slider 505 and the second slider 506; at least three first sliders 505 are slidably fitted in the first slideway 503, and at least three second sliders 506 are slidably fitted in the second slideway 504, so that when the first slider 505 and the second slider 506 circulate, there can still be at least two first sliders 505 and at least two second sliders 506 and their upper hook locks 507 connected to the steel pipe 1, thereby maintaining the stable hooking of the steel pipe pile work platform.

[0118] To facilitate the application of force by the pulling device 514, for the steel pipe 1 that is closer to the steel pipe pile working platform, a transverse support rod 515 can be set on the side away from the steel pipe pile working platform, and the pulling device 514 is connected to the long rod; for the steel pipe 1 that is farther away from the steel pipe pile working platform, the pulling device 514 can be directly connected to the steel pipe 1.

[0119] The slider 14 can be struck with a hammer to assist in inserting or removing it from the ends of the first slide 503 and the second slide 504. The door frame 508 is positioned to avoid the steel pipe 1 and the corbel 4 while ensuring the connection rigidity between the two platform structures 501, thus preventing the platform structures 501 from becoming unstable. A scaffolding board 509 is provided between the two platform structures 501. Both the first slide 503 and the second slide 504 include a slide cavity 510 and an opening 511 located above the slide cavity 510.

[0120] At least two steel pipe piles 3 are positioned within the passage 502. At least two hook locks 507 are mounted on the steel pipe piles 3. At least one hook lock 507 is connected to a first slider 505, and at least one hook lock 507 is connected to a second slider 506. By using a steel pipe pile work platform, a work platform can be flexibly and conveniently arranged around the steel pipe piles 3 at a low cost, allowing workers to weld corbels 4 or perform other processing on the steel pipe piles 3. Furthermore, by sliding the first slider 505 against the first slideway 503, and the second slider 506 against the second slideway 504, the steel pipe pile work platform can be used to flexibly and conveniently form a work platform between a plurality of consecutive steel pipe piles 3, thereby enabling processing of a plurality of steel pipe piles 3. At least three steel pipe piles 3 are arranged along a straight line.

[0121] The hook lock member 507 includes a second flexible rope 512 and a hook claw 513 . One end of the flexible rope is connected to the slider 14 , and the other end is connected to the hook claw 513 . The hook claw 513 is clamped to the upper pipe opening of the steel pipe pile 3 .

[0122] like Figure 26-31 As shown, a preferred solution is as follows: the stone 10 is lifted by a second lifting device, the second lifting device includes a parent-child pin shaft connection assembly 6, a main lifting assembly and an auxiliary lifting assembly, wherein the parent-child pin shaft connection assembly 6 includes a first sub-head 63 and a second sub-head 64 that can simultaneously cooperate with the female head 62, and the first sub-head 63, the second sub-head 64 and the female head 62 can be connected by a pin 65; the main lifting assembly includes a first sling 601 and a bottom chain 602, and the first sling 601 is connected to a first chain 611, a second chain 613 and a third chain 614, wherein: the lower end of the first chain 611 is connected to a hook 631, and the lower part of the second chain 613 is connected to a first branch chain 6 16 and the second branch chain 617, the lower end of the first branch chain 616 is connected to the hook 2 632, the lower end of the second branch chain 617 is connected to the hook 3 633, one end of the bottom chain 602 is connected to the female head 62, and the bottom of the third chain 614 is connected to the first sub-head 63; the auxiliary lifting assembly includes a second sling 600, and the second sling 600 is connected to the rope 1 621 and the fourth chain 622, wherein: the length of the fourth chain 622 is longer than the length of the rope 1 621, the lower end of the fourth chain 622 is connected to the second sub-head 64, and the bottom of the rope 1 621 is connected to one end of the pin 65; the end of the bottom chain 602 away from the female head 62 is connected to the first sling 601;

[0123] Lifting the stone 10 includes the following steps: S1. Arrange the first chain 611, the second chain 613 and the third chain 614 along the circumference of the stone 10; S2. Match the first sub-head 63, the second sub-head 64 and the female head 62, and pass the pin 65 through the first sub-head 63, the second sub-head 64 and the female head 62, and the pin 65 is connected to the end of the lifting rope 1 621 toward the stone 10; S3. Form an arc shape around the stone 10 from the bottom side of the stone 10 near the female head 62 and tighten it, and hang the hook 1 631 and the hook 2 632 on the bottom chain 602 so that the first The first chain 611, the second chain 613, the third chain 614 and the bottom chain 602 hold the stone 10 from one side of the stone 10; S4. The fourth chain 622, which is close to the second sub-head 64, is formed into an arc shape around the stone 10 from the other side and tightened, and the third hook 633 is hung with the fourth chain 622, so that the second chain 613, the third chain 614 and the fourth chain 622 hold the stone 10 from the other side of the stone 10. At this time, the first sub-chain 616, the second sub-chain 617, the part of the bottom chain 602 located between the second hook 632 and the female head 62 and the fourth chain The portion of the rope 622 between the hook 3 633 and the second sub-head 64 forms a ring structure; S5. Lift the first sling 601 and the second sling 600, so that the first chain 611, the second chain 613, the third chain 614, the fourth chain 622 and the bottom chain 602 jointly lift the stone 10. At this time, the rope 1 621 is in a relaxed state, and the portion of the fourth chain 622 between the hook 3 633 and the second sling 600 is also in a relaxed state; S6. After the stone 10 is lifted to the target position, continue to lower the first sling 601 for a distance so that the first chain 611, the second chain 613, the third chain 614, the fourth chain 622 and the bottom chain 602 can lift the stone 10. 613 and the third chain 614 are both in a relaxed state; S7. Lift the second sling 600, so that the rope 1 621 drives the pin 65 to disengage from the first sub-head 63, the second sub-head 64 and the female head 62, so that the bottom chain 602 is in a relaxed state, and the part of the fourth chain 622 located between the hook 3 633 and the second sub-head 64 is also in a relaxed state; S8. Lift the first sling 601 and the second sling 600, so that the first sub-head 63, the second sub-head 64 and the female head 62 are disengaged; S9. Continue to lift the first sling 601 and the second sling 600, and disengage the stone throwing device from the stone 10.

[0124] The main purpose of using a lifting rope 621 instead of a chain is to avoid interference between the chain links and the first sub-head 63, the second sub-head 64, the female head 62 or the chain links of the bottom chain 602 or the chain links of the fourth chain 622 when the pin 65 is pulled out of the female head 62, resulting in the main lifting component or the auxiliary lifting component being unable to separate from the stone.

[0125] The stone is lifted to the predetermined position by the main lifting assembly and the auxiliary lifting assembly, and then the auxiliary lifting assembly is used to separate the main lifting assembly from the stone, thereby achieving the purpose of separating the main lifting assembly from the stone. The entire process of separating the main lifting assembly from the stone does not require human participation, avoiding safety risks to personnel during the lifting process.

[0126] The first sub-head 63, the second sub-head 64, and the female head 62 are connected by a latch 65. Hook 1 631 is connected to the bottom chain 602, hook 2 632 is connected to the bottom chain 602, and hook 3 633 is connected to the fourth chain 622. Along the length of the bottom chain 602, hook 1 631 is located between the female head 62 and hook 2 632. When the first chain 611, the second chain 613, the third chain 614, the portion of the bottom chain 602 between hook 2 632 and the female head 62, and the portion of the fourth chain 622 between hook 3 633 and the second sub-head 64 are all tensioned, the first branch chain 616, the second branch chain 617, the portion of the bottom chain 602 between hook 2 632 and the female head 62, and the portion of the fourth chain 622 between hook 3 633 and the second sub-head 64 form a ring structure. The end of the bottom chain 602 away from the female head 62 is connected to the first sling 601 .

[0127] The lifting rope 621 includes a first flexible rope, a first chain segment, and a second flexible rope connected in sequence. The end of the second flexible rope away from the first chain segment is connected to the latch 65, and the length of the second flexible rope is ≥0.5m. When lifting stones, the lifting rope 621 will have a certain torsional force during use, which will bring a small risk of rotating the latch 65. In this case, by configuring the lifting rope 621 to include the first flexible rope, the first chain segment, and the second flexible rope connected in sequence, the torsional force on the first flexible rope is released. At the same time, since the length of the second flexible rope is ≥0.5m, when the latch 65 is pulled out of the female head 62, the chain links of the first chain segment are prevented from interfering with the chain links of the first sub-head 63, the second sub-head 64, the female head 62, or the bottom chain 602 or the fourth chain 622, resulting in the main lifting assembly or the auxiliary lifting assembly being unable to separate from the stone.

[0128] In a preferred embodiment, the first chain 611 comprises at least two pieces, and the first rope 621 is preferably a steel strand. A connector is connected between the first rope 621 and the latch 65. The connector includes a first structure 671 and a second structure 672 that are rotatably coupled. The second structure 672 is rotatably coupled to the latch 65. The first structure 671 is connected to the first rope 621, and the relative rotation direction of the first structure 671 and the second structure 672 is perpendicular to the relative rotation direction of the second structure 672 and the latch 65. This eliminates torsional forces on the steel strand during use.

[0129] A specific preferred method: a first rotating shaft 673 extends from the end of the first structure 671 away from the lifting rope 621, and a first through hole and a second rotating shaft 674 are provided on the second structure 672. The first rotating shaft 673 rotates with the first through hole so that the second structure 672 can swing or rotate around the first rotating shaft 673. A second through hole is radially provided at the rear end of the pin 65. The second through hole rotates with the second rotating shaft 674 so that the pin 65 swings or rotates around the second rotating shaft 674.

[0130] In a preferred embodiment, the end of the latch 65 connected to the lifting rope 1 621 is directed toward the stone 10. During the lifting process, since the fourth chain 622 and the bottom chain 602 are both in close contact with the stone 10 and in a tensioned state, the end of the latch 65 connected to the lifting rope 1 621 is directed toward the stone 10 to ensure that the latch 65 does not separate from the female head 62 during the lifting process. After the stone 10 is lifted to the target position, the second lifting device 600 is lifted, so that the lifting rope 1 621 drives the latch 65 to rotate vertically, and then the second lifting device 600 continues to lift, thereby driving the latch 65 to smoothly separate from the first sub-head 63, the second sub-head 64, and the female head 62.

[0131] like Figure 26 As shown, in a preferred embodiment, the corbel 4 includes a first side plate 420 and a second side plate 421 arranged opposite to each other, one end of the first side plate 420 is connected to the steel pipe 1, and the other end is connected to the end plate 422, one end of the second side plate 421 is connected to the steel pipe 1, and the other end is connected to the end plate 422, and the first side plate 420 and the second side plate 421 are both formed by cutting the remaining steel pipe section 11.

[0132] The concave surface of the first side plate 420 is positioned opposite the concave surface of the second side plate 421. Upper end plates are provided at the axially upper ends of the first and second side plates 420, 421, with the upper end plate 214 connected between the first and second side plates 420, 421. The first and second side plates 420, 421 are welded to the steel pipe 1. Four corbels 4 are evenly distributed along the circumference of the steel pipe 1.

[0133] For the sunken pipe piles whose upper ends need to be cut, the steel pipe 1 can be divided into the pile body 12 and the remaining steel pipe section 11. The remaining steel pipe section 11 can be located at the upper end of the pile body 12. When cutting the steel pipe 1, the remaining steel pipe section 11 needs to be cut and separated from the pile body 12. When the corbel 4 is made on site, the cut remaining steel pipe section 11 can be used to cut and process again as at least a part of the corbel 4. The corbel 4 is used to support the formwork system. The method of using construction site materials to process the corbel 4 can effectively improve construction efficiency and reduce construction costs.

[0134] like Figures 32-33As shown, in a preferred embodiment, the beam grid includes at least two beam grid units 701 arranged in sequence, and the beam grid unit 701 includes three longitudinal beam grooves 702 arranged at intervals and four transverse beam grooves 703 arranged at intervals. A groove node 704 intersects the longitudinal beam grooves 702 and the transverse beam grooves 703, and the longitudinal beam grooves 702 of adjacent beam grid units 701 correspond to and are connected. The three longitudinal beam grooves 702 are numbered C, D and E in sequence, and the four transverse beam grooves 703 are numbered 1, 2, 3, and 4 in sequence. The groove nodes 704 between the longitudinal beam grooves 702 and the transverse beam grooves 703 are numbered C1, C2, C3, C4, D1, D2, D3, D4, and E1, E2, E3, and E4. In unit time, the amount of concrete pumped by the first pumping pipe is the same as the amount of concrete pumped by the second pumping pipe.

[0135] The construction method includes the following steps: S1: setting a first pumping pipe at the C1 slot node 704; setting a second pumping pipe at the D1 slot node 704, and starting to pour concrete at the C1 slot node 704 and the D1 slot node 704 at the same time, at this time, the concrete at the C1 slot node 704 and the concrete at the D1 slot node 704 are both diffused toward the surroundings; S2: completing the concrete delivery at the C1, C2, D2, D3, C3, and C4 slot nodes 704 in sequence through the first pumping pipe, and synchronously completing the concrete delivery at the D1, E1, E2, E3, E4, and D4 slot nodes 704 in sequence through the second pumping pipe; S3: moving the first pumping pipe to the C1 slot node 704 of the next beam grid unit 701, and at the same time moving the second pumping pipe to the D1 slot node 704 of the next beam grid unit 701; then repeating S1-S2 until the concrete delivery of all 10 sections of the transverse and longitudinal beam slots 702 is completed to form transverse and longitudinal beams.

[0136] A method for casting a cast-in-place beam grid in the present application uses a pumping method similar to the above-mentioned concave-convex matching casting route, so that there are only two positions of the four spaced-apart beam grooves 703, where the pumping time of the concrete material pumped out by the first pumping pipe and the concrete material pumped out by the second pumping pipe is the same as that of the three groove nodes 704, and the pumping time of the concrete material pumped out by the first pumping pipe and the concrete material pumped out by the second pumping pipe at the rest of the positions is less than the pumping time of the three groove nodes 704, thereby effectively reducing the probability of cold joints.

[0137] Preferably, the first pumping pipe moves toward the less-material area and returns when pumping concrete at the slot node 704; the first pumping pipe moves along the first direction of the less-material area and returns when pumping concrete at the slot node 704, and the first direction is perpendicular to the direction when the first pumping pipe reaches the slot node 704; the first pumping pipe moves toward the D1 slot node 704 and returns when pumping concrete to the D2 slot node 704; the first pumping pipe moves toward the E3 slot node 704 and returns when pumping concrete to the D3 slot node 704; the first pumping pipe moves toward the C2 slot node 704 and returns when pumping concrete to the C3 slot node 704; the first pumping pipe moves toward the C4 slot node 704. When the slot node 704 pumps concrete, it moves toward the D4 slot node 704 and returns; when the second pumping pipe pumps concrete to the E2 slot node 704, it moves toward the D2 slot node 704 and returns; when the second pumping pipe pumps concrete to the D4 slot node 704, it moves toward the D3 slot node 704 and returns; in the two sequentially arranged beam grid units 701, when the second pumping pipe pumps concrete to the E1 slot node 704 in the later-cast beam grid unit 701, it moves toward the E4 slot node 704 in the first-cast beam grid unit 701 and returns; the width of the crossbeam slot 703 is equal to the width of the longitudinal beam slot 702, and the thickness of the crossbeam slot 703 is equal to the thickness of the longitudinal beam slot 702.

[0138] The above are only preferred embodiments of the present invention and are not intended to limit the present invention. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present invention should be included in the scope of protection of the present invention.

Claims

1. A method for constructing a wharf structure, characterized in that: The following steps are involved: The steel pipe (1) is lifted and arranged vertically by a first lifting device, and then the steel pipe (1) is driven to a predetermined position; After the steel pipe (1) is injected to a predetermined position, the inside of the steel pipe (1) is processed; Cutting off the excess portion of the upper portion of the steel pipe (1) to form a remaining steel pipe section (11), and lifting the remaining steel pipe section (11) away by means of the first lifting device; Processing a steel cage (3), placing at least a portion of the steel cage (3) into a steel pipe (1), and pouring concrete into the steel pipe (1) to form a steel pipe pile; A corbel (4) is welded to the outside of a steel pipe (1) via a steel pipe pile working platform, wherein at least part of the structure on the corbel (4) is formed by splitting the remaining steel pipe section (11), and the steel pipe pile working platform is capable of moving laterally relative to the steel pipe (1).

2. A dock structure construction method according to claim 1, characterized in that: One end of the steel pipe (1) is provided with at least three through holes in a circumferential direction, wherein the three through holes are a first through hole (111), a second through hole (112) and a third through hole (113), and the first through hole (111), the second through hole (112) and the third through hole (113) are all located on the remaining steel pipe section (11); The first lifting device comprises a first lifting rope assembly and a second lifting rope assembly, wherein: The first suspension rope assembly comprises a first main rope (101), and the lower end of the first main rope (101) is connected to a first suspension rope (103) and a second suspension rope (104); The second suspension rope assembly comprises a second main rope (102), the lower end of the second main rope (102) is connected to a third suspension rope (105), a fourth suspension rope (106) and a fifth suspension rope (107), the free end of the third suspension rope (105) is connected to a first suspension hook (108), the free end of the fourth suspension rope (106) is connected to a second suspension hook (109), and the free end of the fifth suspension rope (107) is connected to a third suspension hook (110); Lifting the steel pipe (1) by a first lifting device and vertically arranging it comprises the following steps: A1: insert the first hook (108) into the first through hole (111), insert the second hook (109) into the second through hole (112), insert the third hook (110) into the third through hole (113), and connect the first hook (108), the second hook (109) and the third hook (110) to each other, and wind and fix the first lifting rope (103) and the second lifting rope (104) around the other end of the steel pipe (1); A2: The steel pipe (1) is changed from horizontal to vertical by first lifting the second lifting rope assembly and then lifting the first lifting rope assembly, or by lifting the second lifting rope assembly faster than the first lifting rope assembly; Lifting the remaining steel pipe section (11) by the first lifting device comprises the following steps: A3: lowering the third lifting rope (105), the fourth lifting rope (106) and the fifth lifting rope (107) from the steel pipe (1), and reversely hanging the first lifting hook (108) on the first through hole (111), reversely hanging the second lifting hook (109) on the second through hole (112), and reversely hanging the third lifting hook (110) on the third through hole (113); A4: The second lifting rope assembly is lifted to move away from the remaining steel pipe section (11).

3. A wharf structure construction method according to claim 1, characterized in that: The steel pipe (1) is provided with two through holes arranged opposite to each other, the two through holes being respectively a first through hole (111) and a second through hole (112); The first lifting device comprises a first lifting rope assembly, a second lifting rope assembly and an auxiliary lifting assembly (114); The first suspension rope assembly comprises a first main rope (101), and the first suspension rope (103) and the second suspension rope (104) are connected to the lower part of the first main rope (101); The second lifting rope assembly comprises a second main rope (102), the lower part of the second main rope (102) is connected to a third lifting rope (105) and a fourth lifting rope (106), the lower end of the third lifting rope (105) is provided with a first lifting ring (115) and a second lifting ring (116), the lower end of the fourth lifting rope (106) is provided with a third lifting ring (117), the first lifting ring (115) extends into the first through hole (111), and the second lifting ring (116) extends into the second through hole (112); The auxiliary lifting assembly (114) comprises an auxiliary lifting rope (118), the end of which is connected with an auxiliary pin (119), the auxiliary pin (119) being capable of passing through the first lifting ring (115), the second lifting ring (116) and the third lifting ring (117), and being capable of locking the third lifting ring (117) between the first lifting ring (115) and the second lifting ring (116) when the third lifting rope (105) and the fourth lifting rope (106) are tensioned, and when the auxiliary lifting rope (118) applies a pulling force to the auxiliary pin (119), the auxiliary pin (119) is capable of detaching from the first lifting ring (115), the second lifting ring (116) and the third lifting ring (117); Lifting the steel pipe (1) by a first lifting device and vertically arranging it comprises the following steps: B1. Extend the first lifting ring (115) and the second lifting ring (116) into the first through hole (111), and extend the third lifting ring (117) into the second through hole (112), so that the third lifting ring (117) is arranged between the first lifting ring (115) and the second lifting ring (116), and then extend the auxiliary pin (119) from the end of the steel pipe (1) into the steel pipe (1), and the auxiliary pin (119) passes through the first lifting ring (115), the third lifting ring (117) and the second lifting ring (116) in sequence, and then tighten the third lifting rope (105) and the fourth lifting rope (106), so that one side of the auxiliary pin (119) is pressed against the first lifting ring (115) and the second lifting ring (116), and the other side of the auxiliary pin (119) is pressed against the third lifting ring (117); Winding and fixing the first lifting rope (103) and the second lifting rope (104) on the other end of the steel pipe (1); B2. The steel pipe (1) is changed from horizontal to vertical by first lifting the second lifting rope assembly and then lifting the first lifting rope assembly, or the lifting speed of the second lifting rope assembly is faster than that of the first lifting rope assembly, and is lifted to a predetermined position and fixed; B3. The third suspension rope (105) and the fourth suspension rope (106) are in a relaxed state; B4. Raise the auxiliary lifting assembly (114) so ​​that the auxiliary lifting rope (118) drives the auxiliary pin (119) to rotate vertically and move upward, so that the auxiliary pin (119) is separated from the first lifting ring (115), the second lifting ring (116) and the third lifting ring (117), until the auxiliary pin (119) is lifted out of the steel pipe (1); B5. Lift the second lifting rope assembly, and pull the first lifting ring (115) out of the first through hole (111), and pull the second lifting ring (116) out of the second through hole (112).

4. A dock structure construction method according to claim 1, characterized in that: After the steel pipe (1) is injected to a predetermined position, the inside of the steel pipe (1) is processed, and the bottom of the inside of the steel pipe (1) is inspected by a detection system, wherein the detection system comprises a cable retracting device (204), a detector (202), and a control console (201) connected via a data transmission cable (203); The detector (202) comprises a camera (207) and a liquid level sensor (208) suspended below the camera (207), and both the camera (207) and the liquid level sensor (208) are communicatively connected to the console (201) via the data transmission cable (203); The cable retracting device (204) comprises a motor (216), a steering pulley (205) and a drum (206); the data transmission cable (203) is wound on the drum (206); the motor (216) can drive the drum (206) to rotate, so that the drum (206) can retract and extend the data transmission cable (203) by forward or reverse rotation; the steering pulley (205) is mounted on the top of the steel pipe (1); The console (201) is provided with a display screen (209) for displaying the image captured by the camera (207) and the liquid level detected by the liquid level sensor (208).

5. A dock structure construction method according to claim 1, characterized in that: It also includes a steel bar rotation device; The steel cage (3) comprises two main threaded steel bars (301) coaxially connected via a steel sleeve (303); The steel bar rotating device comprises a driving device (401) and a clamp mechanism, wherein the clamp mechanism comprises a clamp head structure (402) and a clamp wall structure (403) connected to each other, wherein the end of the clamp wall structure (403) away from the clamp head structure (402) is connected to a first rod (404), a bend is formed at the connection between the first rod (404) and the clamp wall structure (403), a universal joint (405) is connected between the end of the first rod (404) away from the clamp wall structure (403) and an output shaft (411) of the driving device (401), the clamp head structure (402) and the output shaft (411) are arranged correspondingly, the clamp head structure (402) clamps a main threaded steel bar (301) from one side of the main threaded steel bar (301), and the clamp head structure (402) is located at one end of the main threaded steel bar (301) away from the steel bar sleeve (303); The longitudinal reinforcement is driven to rotate by the reinforcement rotating device so that the main thread reinforcement (301) is connected with the adjacent main thread reinforcement (301) through the reinforcement sleeve (303).

6. A dock structure construction method according to claim 1, characterized in that: At least a portion of the steel cage (3) is placed in the steel pipe (1), and the relative depth between the bottom of the steel cage (3) and the steel pipe (1) is positioned by a cage clamping device; the cage clamping device comprises a first structure (304) and a second structure (305), the first structure (304) and the second structure (305) are connected by a connecting assembly (306), and a clamping space (307) is provided between the first structure (304) and the second structure (305), and a threaded steel bar (308) is provided on at least one side of the clamping space (307), and the threaded steel bar (308) is connected to the first structure (304) or the second structure (305).

7. A dock structure construction method according to claim 1, characterized in that: The steel pipe pile operation platform comprises at least two platform structures (501) arranged at intervals, a passage (502) is provided between adjacent platform structures (501), one of the adjacent platform structures (501) is provided with a first slideway (503), and the other is provided with a second slideway (504), and both the first slideway (503) and the second slideway (504) are provided along the direction of the passage (502); At least three first sliders (505) are slidably matched in the first slideway (503), and at least three second sliders (506) are slidably matched in the second slideway (504), and the first sliders (505) and the second sliders (506) are arranged correspondingly; The first sliding block (505) and the second sliding block (506) are both connected with a hook locking member (507); The slider (14) on the first slideway (503) can enter and exit the first slideway (503) from both ends of the first slideway (503), and the slider (14) on the second slideway (504) can enter and exit the second slideway (504) from both ends of the second slideway (504); Both ends of the first slideway (503) and both ends of the second slideway (504) are open; A door frame (508) is fixedly connected between adjacent platform structures (501), and the steel pipe (1) and the bracket (4) can pass through the door frame (508); The method of welding a bracket (4) on the outside of a steel pipe (1) by means of a steel pipe pile working platform specifically comprises the following steps: C1: For a plurality of steel pipes (1) extending out of the water surface and distributed along a linear path, the hook lock (507) can be installed on two or three steel pipes (1) by means of a lifting machine, and the two or three steel pipes (1) are subjected to a bracket (4) welding operation, wherein the two or three steel pipes (1) are located in the passage (502); C2: Install a pulling device (514) on the steel pipe (1) on one side of the channel (502), connect the pulling device (514) to the steel pipe pile work platform, and drive the steel pipe pile work platform to move through the pulling device (514) until one or more steel pipes (1) in the foreground direction of the steel pipe pile work platform enter the channel (502); during this process, the hook lock (507) is pulled by the steel pipe (1), and the hook lock (507) will drag the first slider (505) to slide in the first slideway (503), and the second slider (506) to slide in the second slideway (504), so as to maintain the hooking state of the hook lock (507) and the steel pipe (1) during the movement of the steel pipe pile work platform; C3: During the movement of the steel pipe pile work platform, when the steel pipe (1) at the rear end of the steel pipe pile work platform in the forward direction corresponds to the end positions of the first slideway (503) and the second slideway (504), the hook lock (507) and the corresponding first slide block (505) and the second slideway (504) connected to the steel pipe (1) are removed and installed on the steel pipe (1) entering the channel (502) from the front end of the steel pipe pile work platform in the forward direction; C4: Repeat steps C1-C3 until the welding of the bracket (4) is completed.

8. A dock structure construction method according to claim 1, characterized in that: The method further comprises the step of performing stone throwing around the steel pipe pile by using a second lifting device: lifting stones (10) by using the second lifting device, wherein the second lifting device comprises: The male and female pin connection assembly (6) comprises a first male head (63), a second male head (64) and a female head (62); the first male head (63) and the second male head (64) can be matched with the female head (62) at the same time, and the first male head (63), the second male head (64) and the female head (62) can be connected via a latch (65); The main lifting assembly comprises a first lifting device (601) and a bottom chain (602), wherein the first lifting device (601) is connected to a first chain (611), a second chain (613) and a third chain (614), wherein: the lower end of the first chain (611) is connected to a hook 1 (631), the lower part of the second chain (613) is connected to a first sub-chain (616) and a second sub-chain (617), the lower end of the first sub-chain (616) is connected to a hook 2 (632), the lower end of the second sub-chain (617) is connected to a hook 3 (633), one end of the bottom chain (602) is connected to the female head (62), and the bottom of the third chain (614) is connected to the first sub-head (63); The auxiliary lifting assembly comprises a second lifting device (600), the second lifting device (600) is connected with a lifting rope 1 (621) and a fourth chain (622), wherein: the length of the fourth chain (622) is longer than the length of the lifting rope 1 (621), the lower end of the fourth chain (622) is connected to the second sub-head (64), and the bottom of the lifting rope 1 (621) is connected to one end of a latch (65); The end of the bottom chain (602) away from the female head (62) is connected to the first sling (601); Lifting stones (10) comprises the following steps: S1. Arranging the first chain (611), the second chain (613) and the third chain (614) along the circumference of the stone (10); S2. Match the first sub-head (63), the second sub-head (64) and the female head (62), and pass the latch (65) through the first sub-head (63), the second sub-head (64) and the female head (62), wherein one end of the latch (65) connected to the suspension rope (621) is directed toward the stone (10); S3. A section of the bottom chain (602) close to the female head (62) is formed into an arc shape around the stone (10) from below one side of the stone (10) and tightened, and the first hook (631) and the second hook (632) are both connected to the bottom chain (602), so that the first chain (611), the second chain (613), the third chain (614) and the bottom chain (602) hold the stone (10) from one side of the stone (10); S4. A section of the fourth chain (622) close to the second sub-head (64) is formed into an arc shape from the other side of the stone (10) below and around the stone (10), and is tightened, and the third hook (633) is connected to the fourth chain (622), so that the second chain (613), the third chain (614) and the fourth chain (622) hold the stone (10) from the other side of the stone (10). At this time, the first sub-chain (616), the second sub-chain (617), the part of the bottom chain (602) located between the second hook (632) and the female head (62) and the part of the fourth chain (622) located between the third hook (633) and the second sub-head (64) form a ring structure; S5. Lift the first lifting device (601) and the second lifting device (600), so that the first chain (611), the second chain (613), the third chain (614), the fourth chain (622) and the bottom chain (602) jointly lift the stone (10), at which time, the lifting rope (621) is in a relaxed state, and the portion of the fourth chain (622) between the hook (633) and the second lifting device (600) is also in a relaxed state; S6. After the stone (10) is hoisted to the target position, the first hoist (601) is lowered for a distance so that the first chain (611), the second chain (613) and the third chain (614) are all in a relaxed state; S7. Lift the second lifting device (600) so that the first lifting rope (621) drives the latch (65) to be disengaged from the first sub-head (63), the second sub-head (64) and the female head (62), so that the bottom chain (602) is in a relaxed state, and the portion of the fourth chain (622) between the third hook (633) and the second sub-head (64) is also in a relaxed state; S8. Lift the first sling (601) and the second sling (600) so that the first sub-head (63), the second sub-head (64) and the female head (62) are separated; S9. Continue to lift the first lifting device (601) and the second lifting device (600), and separate the stone throwing device from the stone (10).

9. A dock structure construction method according to claim 1, characterized in that: The corbel (4) comprises a first side plate (420) and a second side plate (421) which are arranged opposite to each other, one end of the first side plate (420) is connected to the steel pipe (1), and the other end is connected to an end plate (422), one end of the second side plate (421) is connected to the steel pipe (1), and the other end is connected to the end plate (422), and the first side plate (420) and the second side plate (421) are both formed by cutting the remaining steel pipe section (11).

10. A dock structure construction method according to claim 1, characterized in that: The method also includes the steps of casting transverse and longitudinal beams: setting up beam grid grooves on the corbels (4), placing steel bars in the beam grid grooves and casting to form transverse and longitudinal beams, wherein the beam grid grooves include at least two beam grid units (701) arranged in sequence, wherein the beam grid unit (701) includes three longitudinal beam grooves (702) arranged at intervals and four transverse beam grooves (703) arranged at intervals, wherein a groove node (704) intersects between the longitudinal beam grooves (702) and the transverse beam grooves (703), and the longitudinal beam grooves (702) of adjacent beam grid units (701) are arranged to correspond to and be in communication with each other; The three longitudinal beam grooves (702) are numbered C, D and E in sequence, the four transverse beam grooves (703) are numbered 1, 2, 3 and 4 in sequence, and the groove nodes (704) between the longitudinal beam grooves (702) and the transverse beam grooves (703) are numbered C1, C2, C3, C4, D1, D2, D3, D4, E1, E2, E3 and E4; In a unit time, the amount of concrete material pumped by the first pumping pipe is the same as the amount of concrete material pumped by the second pumping pipe; The construction method comprises the following steps: S1: The first pumping pipe is set at the C1 slot node (704); the second pumping pipe is set at the D1 slot node (704), and the pouring at the C1 slot node (704) and the D1 slot node (704) is started at the same time. At this time, the concrete at the C1 slot node (704) and the concrete at the D1 slot node (704) are diffused in all directions; S2: sequentially completing the concrete delivery at the C1, C2, D2, D3, C3, and C4 slot nodes (704) through the first pumping pipe, and synchronously completing the concrete delivery at the D1, E1, E2, E3, E4, and D4 slot nodes (704) through the second pumping pipe; S3: Move the first pumping pipe to the C1 slot node (704) of the next beam grid unit (701), and move the second pumping pipe to the D1 slot node (704) of the next beam grid unit (701); then repeat S1-S2 until the concrete delivery of all the transverse and longitudinal beam slot (702) sections (10) is completed to form transverse and longitudinal beams.

Citation Information

Patent Citations

  • Steel tube pile construction guide rack and construction method

    CN109083147A

  • Wharf integrated construction system and method based on pile top pushing platform

    CN109208533A

  • Working platform and working method for dredging and riprapping between piles of long-piled wharf

    CN114991072A

  • Urban rail viaduct Y-shaped vase pier body reinforcement cage integral hoisting construction method

    CN117536127A

  • Method for building platform for construction of cast-in-place piles of high-piled wharf

    WO2023071518A1