Construction method of greenhouse supporting side column structure standing on embankment slope

By installing and anchoring the support platform on the outside of the greenhouse support side column, combined with the tightening design of the detachable hoop, the problem of insufficient load-bearing and impact resistance when the greenhouse support side column is fixed on the embankment slope in the prior art is solved, and the stability and impact resistance are significantly improved.

CN119711479APending Publication Date: 2025-03-28刘山健
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202510159687.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2025-02-13
Publication Date
2025-03-28

AI Technical Summary

Technical Problem

When the existing greenhouse support side columns are fixed on the slope of the embankment, the load-bearing and impact resistance are insufficient, and it is easy to be damaged by vehicle impact.

Method used

A construction method is adopted, which includes burying the greenhouse support side column on the slope of the embankment, fitting the support platform on the outside, and anchoring it with the embankment slope through anchors, and finally installing a detachable hoop piece on the opening side of the support platform to hold the support side column tightly.

Benefits of technology

The stability, safety, load-bearing capacity and impact resistance of the greenhouse support side columns standing on the embankment slope is improved, and the risk of damage due to vehicle impact is avoided.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119711479A_ABST
    Figure CN119711479A_ABST
Patent Text Reader

Abstract

The invention discloses a construction method of a greenhouse supporting side column structure standing on an embankment slope. The construction method comprises the following steps that S1, greenhouse supporting side columns are buried on the embankment slope; s2, a supporting platform is mounted on the outer sides of the greenhouse supporting side columns in an embedded mode; s3, the supporting platform and the embankment slope are anchored through anchoring parts; and S4, folding the opening side of the supporting platform to install a detachable hoop piece, and tightly holding the supporting side column. By the adoption of the construction method of the greenhouse supporting side column structure, the stability, safety, bearing capacity and impact resistance of the greenhouse supporting side columns standing on the embankment slope are improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of supports, and in particular relates to a construction method for a greenhouse support side column structure standing on a road embankment slope. Background Art

[0002] In the field of road construction, steel structure greenhouses need to be built for special purposes such as shading, sound insulation, toll collection, photovoltaic power generation, etc. During construction, the supporting side columns of the greenhouse (multiple columns are arranged in a row along the extension direction of the greenhouse) sometimes need to be located on the embankment slope outside the corrugated guardrail on the shoulder of the road.

[0003] At present, the supporting side columns of greenhouses are usually fixed on the embankment slope in a buried manner. The disadvantage of this method is that the earth and stone filled on the embankment slope usually have general compaction, which leads to limited bearing capacity and anti-collision performance of the supporting side columns. When a vehicle passes over the corrugated guardrail and hits the supporting side column, it is very easy to cause the supporting side column to deform outward and be damaged. Summary of the invention

[0004] In view of this, the object of the present invention is to provide a construction method for a greenhouse supporting side column structure standing on the embankment slope, so as to improve the stability, safety, bearing capacity and impact resistance of the greenhouse supporting side columns standing on the embankment slope.

[0005] The present invention solves the above problems by the following technical means:

[0006] A construction method for a greenhouse support side column structure standing on a road embankment slope comprises the following steps:

[0007] S1: bury the greenhouse support side columns on the embankment slope;

[0008] S2: Install the support platform on the outside of the greenhouse support column;

[0009] S3: Anchor the support platform to the embankment slope through anchors;

[0010] S4: Close and install the removable hoop on the open side of the supporting platform, and hold the supporting side column tightly.

[0011] Furthermore, the support platform is provided with a hoop opening, or a fixed hoop piece is fixedly provided, and the detachable hoop piece is closed with the hoop opening or the fixed hoop piece to tightly hold the greenhouse support side column.

[0012] Furthermore, both sides of the support platform are anchored to the embankment slope through anchor pieces.

[0013] Furthermore, the support platform is provided with anchor insertion holes.

[0014] Furthermore, a penetration hole guide wedge is provided on the support platform at a position corresponding to the anchor penetration hole.

[0015] Furthermore, the detachable hoop piece is closed and fixed with the hoop opening or the fixed hoop piece by bolts.

[0016] Furthermore, the suspended portion of the support platform is supported by support piles.

[0017] Furthermore, a rubber ring is provided at the matching position between the support platform and the greenhouse support side column.

[0018] Beneficial effects of the present invention:

[0019] The construction method of the greenhouse support side column structure standing on the embankment slope of the present invention comprises the following steps: S1: burying the greenhouse support side column on the embankment slope; S2: installing the support platform on the outer side of the greenhouse support side column; S3: anchoring the support platform to the embankment slope through anchoring pieces; S4: closing and installing the detachable hoop sheet on the open side of the support platform to hold the support side column tightly. The construction method of the greenhouse support side column structure of the present application improves the stability, safety, bearing capacity and impact resistance of the greenhouse support side column standing on the embankment slope. BRIEF DESCRIPTION OF THE DRAWINGS

[0020] The present invention will be further described below in conjunction with the accompanying drawings and embodiments.

[0021] Figure 1 A schematic top view of a preferred embodiment of the present invention;

[0022] Figure 2 for Figure 1 of - Schematic diagram;

[0023] Figure 3 for Figure 1 of - Schematic diagram;

[0024] Figure 4 for Figure 1 of - Schematic diagram;

[0025] Figure 5 for Figure 1 of - Schematic diagram. DETAILED DESCRIPTION

[0026] The present invention is further described in detail below through the accompanying drawings and embodiments. Through these descriptions, the characteristics and advantages of the present invention will become clearer and more specific. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments.

[0027] like Figures 1 to 5 As shown, on the one hand, this embodiment provides a greenhouse support side column structure standing on the embankment slope, including a support platform 2, an anchor and a detachable hoop 4. The support platform is anchored to the embankment slope 11 through an anchor 13, and the suspended part of the support platform is supported by a support pile 7. Preferably, both sides of the support platform are anchored to the embankment slope through anchors to improve the stability and balance of the support platform anchoring. An anchor insertion hole 3 is provided on the support platform, and the anchor can be an anchor cable or an anchor rod. In this embodiment, an anchor cable is selected, and the anchor cable passes through the anchor insertion hole and is anchored into the embankment slope. An anchor cable pad ring 8 is provided at the outer end of the anchor cable; preferably, a insertion hole guide wedge 14 is provided at the position corresponding to the anchor insertion hole on the support platform, and the inclined surface of the insertion hole guide wedge is parallel to the inclined surface of the embankment slope, so as to provide guidance for the drilling direction of the anchor insertion hole (the drilling direction can be perpendicular to the inclined surface of the insertion hole guide wedge).

[0028] The support platform is provided with a hoop opening, or a fixed hoop sheet 12 is fixedly provided, and the removable hoop sheet is closed with the hoop opening or the fixed hoop sheet by bolts 5 to tightly hold the greenhouse support side column 1. In this embodiment, a fixed hoop sheet is integrally provided on the support platform, and the removable hoop sheet is closed with the fixed hoop sheet by bolts to tightly hold the greenhouse support side column. In the specific implementation process, in order to facilitate the installation of the bolts, connecting ear plates are formed on the removable hoop sheet and the fixed hoop sheet.

[0029] On the other hand, the present embodiment provides a construction method for a greenhouse support side column structure standing on a road embankment slope, comprising the following steps:

[0030] S1: burying the greenhouse support side column on the embankment slope; the embankment slope is located outside the corrugated guardrail, and the corrugated guardrail includes a corrugated plate 9 and a corrugated plate support column 10;

[0031] S2: The support platform is installed on the outer side of the greenhouse support column; specifically, the hoop mouth of the support platform or the opening of the fixed hoop piece is fixedly engaged with the support column;

[0032] S3: Anchor the support platform to the embankment slope through anchors;

[0033] S4: Close and install the removable hoop on the open side of the supporting platform, and hold the supporting side column tightly.

[0034] To sum up, the construction method of the greenhouse support side column structure of the present application is adopted, by adding a combination of a support platform and a detachable hoop plate to tightly hold the support side column, and then pulling and fixing the combination by anchoring, thereby improving the stability, safety, bearing capacity and impact resistance of the greenhouse support side column standing on the embankment slope.

[0035] As a further improvement to the above technical solution, a rubber ring 6 is provided at the joint between the support platform and the greenhouse support side column to cushion the influence of the unexpected impact load of the greenhouse support side column on the support platform.

[0036] Finally, it should be noted that the above embodiments are only used to illustrate the technical solution of the present invention rather than to limit it. Although the present invention has been described in detail with reference to the preferred embodiments, those skilled in the art should understand that the technical solution of the present invention can be modified or replaced by equivalents without departing from the purpose and scope of the technical solution of the present invention, which should be included in the scope of the claims of the present invention.

Claims

1. A construction method for a greenhouse support side column structure standing on a road embankment slope, characterized in that: The steps include: S1: burying the greenhouse support side column (1) on the embankment slope (11); S2: Install the support platform (2) on the outer side of the greenhouse support column; S3: Anchoring the supporting platform to the embankment slope through anchoring members (13); S4: Install the removable hoop (4) on the open side of the support platform and hold the supporting side column tightly.

2. The construction method of the greenhouse support side column structure standing on the embankment slope according to claim 1 is characterized in that: The support platform is provided with a hoop opening, or a fixed hoop piece is fixedly provided, and the detachable hoop piece and the hoop opening or the fixed hoop piece (12) are closed to tightly hold the greenhouse support side column (1).

3. The construction method of the greenhouse support side column structure standing on the embankment slope according to claim 2 is characterized by: Both sides of the support platform are anchored to the embankment slope through anchor pieces.

4. The construction method of the greenhouse support side column structure standing on the embankment slope according to claim 3 is characterized by: The support platform is provided with an anchor insertion hole (3).

5. The construction method of the greenhouse support side column structure standing on the embankment slope according to claim 4 is characterized in that: The support platform is provided with a penetration hole guide wedge at a position corresponding to the anchor piece penetration hole.

6. The construction method of the greenhouse support side column structure standing on the embankment slope according to claim 5 is characterized by: The detachable hoop piece is closed and fixed with the hoop opening or the fixed hoop piece by means of bolts (5).

7. The construction method of the greenhouse support side column structure standing on the embankment slope according to claim 6 is characterized by: The suspended portion of the support platform is supported by support piles (7).

8. The construction method of the greenhouse support side column structure standing on the embankment slope according to claim 7 is characterized by: A rubber ring (6) is provided at the matching position between the support platform and the greenhouse support side column.