Slagging-off machine for tunnel blasting and blasting construction method

By designing a slag stripper for tunnel blasting and equipped with impact drilling, bucket and drilling machine, the problem of difficulty in cleaning large slag strippers and complex construction operations is solved, and efficient slash cleaning and simplified construction operations are achieved.

CN119712147APending Publication Date: 2025-03-28SINOHYDRO BUREAU 12 CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202510003327.2
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2025-01-02
Publication Date
2025-03-28

AI Technical Summary

Technical Problem

Traditional slag-removing machines are difficult to efficiently clean large gravel during tunnel blasting, and construction workers need to manually open holes for blasting, which is troublesome to operate.

Method used

A slag removal machine for tunnel blasting is designed, equipped with a walking device, a cab, a transmission structure and a slag removal rotating structure. The rotating structure of the slag is composed of impact drills, buckets and drilling machines, through which the slag can be cleaned and broken into pieces and holes can be made in the mountain.

Benefits of technology

It improves the efficiency of gravel cleaning, avoids damage to the digging bucket, simplifies construction operations, reduces dependence on the drilling platform, and improves construction efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119712147A_ABST
    Figure CN119712147A_ABST
Patent Text Reader

Abstract

The invention discloses a crawler loader for tunnel blasting and a blasting construction method. The device comprises a walking device, the walking device is composed of a crawler belt and a mounting seat, the walking device can move on different terrains through the crawler belt, and the stability can be improved; the cab is arranged on the mounting seat of the walking device, and a constructor can control the walking device through the cab; and the transmission structure is arranged on the mounting seat of the walking device, and the transmission structure is controlled by a cab, so that the transmission structure can clean broken stones. The drilling machine is arranged on the slagging-off rotating structure, if a hole for blasting needs to be formed in the mountain, a constructor only needs to control the slagging-off rotating structure to rotate, the drilling machine on the slagging-off rotating structure faces forwards, then the constructor can form the hole in the mountain through the drilling machine, the constructor does not need to erect a drilling platform, operation is convenient and rapid, and the construction efficiency is improved. And the construction efficiency is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of scraper machines, in particular to a scraper machine for tunnel blasting and a blasting construction method. Background Art

[0002] Mud scraper, also known as excavator loader, is a combination of a manipulator and a conveyor. It combines the functions of mucking and conveying and loading into one. It adopts an electric full hydraulic control system and production equipment, and is safe, environmentally friendly, low energy consumption and high efficiency.

[0003] During the tunnel blasting process, traditional scrapers can only clean up the gravel in the tunnel, and traditional scrapers can only clean up smaller gravel. When faced with larger gravel, they need to be broken up by the bucket on the scraper or manually, which can easily cause damage to the bucket and seriously affect work efficiency. In addition, during the tunnel blasting process, construction workers are required to manually open holes for blasting on the mountain, and construction workers need to set up drilling platforms, which is inconvenient to operate. Summary of the invention

[0004] The object of the present invention is to provide a slag scraper for tunnel blasting and a blasting construction method to solve the problems raised in the above-mentioned background technology.

[0005] To achieve the above object, the present invention provides the following technical solution: a slag scraper for tunnel blasting and a blasting construction method, comprising: A walking device, the walking device is composed of a crawler and a mounting seat, wherein the walking device can move on different terrains through the crawler and can also improve stability; A cab, which is arranged on a mounting seat of the traveling device, and a construction worker can control the traveling device through the cab; A transmission structure, wherein the transmission structure is arranged on a mounting seat of the traveling device, and the transmission structure is controlled by the cab so that the transmission structure can clean up the gravel; The slag scraper rotating structure is arranged on the transmission structure and consists of a slag scraper hole opening structure and a rotating structure. An impact drill, a bucket and a drilling machine are arranged on the slag scraper rotating structure. The slag scraper rotating structure is controlled by the cab. It can clean the gravel through the bucket, and can also crush larger gravel through the impact drill. At the same time, it can open holes for blasting on the mountain through the drilling machine.

[0006] By adopting the above technical scheme, construction workers control the walking device, transmission structure and scraper rotating structure through the cab. In the process of cleaning gravel, smaller gravel is cleaned through the scraper rotating structure and transmission structure. When encountering larger gravel, it is cleaned through an impact drill. After the gravel is cleaned, the mountain is drilled through the drilling machine on the scraper rotating structure. The operation is convenient and there is no need for construction workers to set up a drilling platform.

[0007] Preferably, the transmission structure includes a bracket, a servo motor is installed at one end of both sides of the bracket, a first conveyor belt is installed inside the bracket, support ears are installed at the other end of both sides of the bracket, a front shovel is installed at the other end of the bracket, a second conveyor belt is installed on the front shovel, baffles are rotatably installed on both sides of the other end of the front shovel, and a limit block is installed at one end of the front shovel close to the baffle.

[0008] By adopting the above technical solution, after the crushed stone enters the front shovel, it is moved to the bracket by the second conveyor belt, and then sent to the transport vehicle by the first conveyor belt. During this process, the baffle can be used to prevent the crushed stone from sliding off the conveying structure.

[0009] Preferably, the servo motor is connected to the first conveyor belt, and the first conveyor belt can move on the bracket, and the second conveyor belt can move on the front shovel. A power source is provided at the bottom of the front shovel to drive the second conveyor belt to move.

[0010] By adopting the above technical solution, the first conveyor belt and the second conveyor belt are moved by the servo motor and the power source at the bottom of the front shovel respectively.

[0011] Preferably, connecting blocks are provided on both sides of the other end of the front shovel, the front shovel is rotatably connected to the baffle through the connecting blocks, and the front shovel limits the rotation angle of the baffle through a limiting block.

[0012] By adopting the above technical solution, when the crushed stone enters the front shovel, the baffle moves in the direction of the first conveyor belt. After the crushed stone enters the front shovel, the baffle returns to its original position due to gravity, and then the limit block blocks the rotation range of the baffle, and enables the baffle to block the feeding point of the front shovel.

[0013] Preferably, the rotating structure in the slag scraping rotating structure includes a mounting frame, motors are arranged at both ends of the top of the mounting frame, a rotating part is rotatably installed at the middle position of the top of the mounting frame, a lifting plate is rotatably installed on the top of the rotating part, a connecting part is installed at the middle position of the top of the lifting plate, a fourth hydraulic cylinder is arranged inside the rotating part, and a dust reduction part is arranged inside the mounting frame.

[0014] By adopting the above technical solution, the rotating part in the rotating structure is rotated by being driven by the output end of the motor, thereby adjusting the direction of the slag scraping opening structure on the slag scraping rotating structure, and the fourth hydraulic cylinder can drive the slag scraping opening structure on the lifting plate to rise and fall, thereby assisting in adjusting the direction of the slag scraping opening structure.

[0015] Preferably, the mounting frame is mounted on the bracket through a support ear, the output end of the fourth hydraulic cylinder is connected to the lifting plate, both ends of the dust reduction component penetrate the side wall of the mounting frame and extend to the outside, a rotating opening is opened on the top of the mounting frame, and the rotating component is rotatably connected to the mounting frame through the rotating opening.

[0016] By adopting the above technical solution, the rotating structure is stably and firmly installed on the bracket through the support ears, and the construction workers inject clean water into the dust reduction component, and then the clean water flows out through the dust reduction component and sprays on the gravel, preventing the smoke and dust on the gravel from being raised during the transmission process.

[0017] Preferably, teeth are provided at the bottom of the outer surface of the rotating member, bevel teeth are provided at the output end of the motor, the output end of the motor is meshed with the teeth on the rotating member through the bevel teeth, and movable grooves are provided at both ends of the top of the lifting plate.

[0018] By adopting the above technical solution, the motor drives the rotating part to rotate through the cooperation between the bevel teeth and the teeth, and the movable groove on the lifting plate can assist in the use of the slag removal and hole opening structure.

[0019] Preferably, the slag scraping hole opening structure in the slag scraping rotating structure includes a connecting rod, connecting rods are rotatably provided at both ends of the connecting piece, a first hydraulic cylinder is rotatably installed at one end of the bottom of the connecting rod away from the connecting piece, and a second hydraulic cylinder is rotatably provided at the top of the connecting rod, a first rotating rod and a second rotating rod are rotatably installed at one end of the two connecting rods away from the connecting piece respectively, an impact drill is installed at the end of the first rotating rod away from the connecting piece, a bucket is rotatably installed at the bottom of the first rotating rod, a third hydraulic cylinder is installed at one end of the first rotating rod close to the connecting piece, and a drilling machine is rotatably installed at the bottom of the second rotating rod.

[0020] By adopting the above technical solution, the scraping and hole-opening structure drives the bucket and the drilling machine to move through the assistance of multiple hydraulic cylinders, so that the bucket can send the gravel into the transmission structure. When encountering larger gravel, the gravel can be broken up by an impact drill to facilitate the cleaning of the gravel. When it is necessary to open a hole in the mountain, the construction workers can use the drilling machine to open a hole in the mountain.

[0021] Preferably, both ends of the first hydraulic cylinder are rotatably connected to the lifting plate and the connecting rod respectively, the output end of the second hydraulic cylinder is connected to the first rotating rod or the second rotating rod, and the output end of the third hydraulic cylinder is connected to the bucket.

[0022] By adopting the above technical solution, construction workers drive the connecting rod to rotate on the lifting plate through the first hydraulic cylinder, and the second hydraulic cylinder can drive the first rotating rod or the second rotating rod to rotate on the connecting rod, and the third hydraulic cylinder can drive the bucket to rotate on the first rotating rod.

[0023] A tunnel blasting construction method, characterized in that it comprises the following steps: S1: Survey and set out, test soil samples to determine rock grade, and plan blasting plans; S2: The drilling platform is in place, and the construction workers build the drilling platform in front of the mountain; S3: Drilling: construction workers use drilling platforms to open holes for blasting on the mountain; S4: Hole cleaning: construction workers clean the holes used for blasting; S5: Loading, networking, detonation. Construction workers place explosives into the holes, connect the fuses of the explosives together, and then detonate them simultaneously; S6: Ventilation and exhaust of smoke (dust). Construction workers use ventilation devices to remove the smoke and dust generated by blasting; S7: Risk elimination: construction personnel conduct risk elimination on the tunnels created by blasting; S8: Slag removal, using a slag scraper to clean up the gravel in the tunnel; S9: Enter the next cycle.

[0024] By adopting the above technical solution, construction workers no longer need to set up a drilling platform when entering the next cycle, and can directly drill holes in the mountain through the drilling machine 413 on the slag removal and drilling structure. The operation is convenient and fast, and the construction efficiency is improved.

[0025] Compared with the prior art, the present invention has the following beneficial effects: The scraper and blasting construction method for tunnel blasting are provided with an impact drill on the scraper rotating structure. If a large volume of gravel needs to be cleaned, the construction workers can crush the large volume of gravel through the impact drill on the scraper rotating structure. There is no need for the construction workers to manually break the gravel, which will not cause damage to the bucket and improves the efficiency of gravel cleaning.

[0026] The slag scraper and blasting construction method for tunnel blasting are provided with a drilling machine on the slag scraper rotating structure. If it is necessary to open a hole for blasting on the mountain, the construction workers only need to control the slag scraper rotating structure to rotate so that the drilling machine on the slag scraper rotating structure faces forward. Then the construction workers can open a hole in the mountain through the drilling machine. There is no need for the construction workers to set up a drilling platform. The operation is convenient and quick, which improves the construction efficiency. BRIEF DESCRIPTION OF THE DRAWINGS

[0027] Figure 1 It is a side structural diagram of the present invention; Figure 2 This is a side view of the slag removal opening structure of the present invention; Figure 3 It is a front cross-sectional view of the rotating structure of the present invention; Figure 4 It is a three-dimensional diagram of the rotating structure of the present invention; Figure 5 A top view of the transmission structure of the present invention; Figure 6 It is a flow chart of blasting construction of the present invention.

[0028] In the figure: 1. walking device; 2. cab; 3. transmission structure; 30. bracket; 31. servo motor; 32. first conveyor belt; 33. support ear; 34. front shovel; 35. second conveyor belt; 36. baffle; 37. limit block; 4. slag removal rotation structure; 40. mounting frame; 41. motor; 42. rotating part; 43. lifting plate; 44. connecting part; 45. connecting rod; 46. first hydraulic cylinder; 47. second hydraulic cylinder; 48. first rotating rod; 49. second rotating rod; 410. impact drill; 411. third hydraulic cylinder; 412. bucket; 413. drilling machine; 414. fourth hydraulic cylinder; 415. dust suppression part. DETAILED DESCRIPTION

[0029] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0030] See also Figure 1-6 The present invention provides an embodiment: a slag scraper for tunnel blasting and a blasting construction method, comprising: A walking device 1, the walking device 1 is composed of a crawler and a mounting seat, wherein the walking device 1 can move on different terrains through the crawler and can also improve stability; A cab 2, wherein the cab 2 is arranged on a mounting seat of the traveling device 1, and a construction worker can control the traveling device 1 through the cab 2; The transmission structure 3 is arranged on the mounting seat of the traveling device 1, and the transmission structure 3 is controlled by the cab 2 so that the transmission structure 3 can clean up the gravel; The slag scraping rotating structure 4 is arranged on the transmission structure 3 and is composed of a slag scraping hole opening structure and a rotating structure. The slag scraping rotating structure 4 is provided with an impact drill 410, a bucket 412 and a drilling machine 413. The slag scraping rotating structure 4 is controlled by the cab 2. The bucket 412 can be used to clean up the gravel, and the impact drill 410 can be used to crush the gravel with a large volume. At the same time, the drilling machine 413 can be used to open holes for explosions on the mountain; The construction workers control the walking device 1, the transmission structure 3 and the scraper rotating structure 4 through the cab 2. In the process of cleaning the gravel, the smaller gravel is cleaned through the scraper rotating structure 4 and the transmission structure 3. When encountering larger gravel, it is cleaned through the impact drill 410. After the gravel is cleaned, the mountain is drilled with the drilling machine 413 on the scraper rotating structure 4. The operation is convenient and the construction workers do not need to set up a drilling platform.

[0031] In this embodiment, the transmission structure 3 includes a bracket 30, one end of both sides of the bracket 30 is equipped with a servo motor 31, a first conveyor belt 32 is installed inside the bracket 30, the other end of both sides of the bracket 30 is equipped with a support ear 33, the other end of the bracket 30 is equipped with a front shovel 34, the front shovel 34 is equipped with a second conveyor belt 35, both sides of the other end of the front shovel 34 are rotatably installed, and a limit block 37 is installed at one end of the front shovel 34 close to the baffle 36. After the gravel enters the front shovel 34, it is moved to the bracket 30 by the second conveyor belt 35, and then the gravel is sent to the transport vehicle through the first conveyor belt 32. In this process, the baffle 36 can be used to prevent the gravel from sliding off the transmission structure 3.

[0032] In this embodiment, the servo motor 31 is connected to the first conveyor belt 32, and the first conveyor belt 32 can move on the bracket 30, and the second conveyor belt 35 can move on the front shovel 34. A power source is provided at the bottom of the front shovel 34, and drives the second conveyor belt 35 to move. The first conveyor belt 32 and the second conveyor belt 35 are moved by the servo motor 31 and the power source at the bottom of the front shovel 34 respectively.

[0033] In this embodiment, connecting blocks are provided on both sides of the other end of the front shovel 34. The front shovel 34 is rotatably connected to the baffle 36 through the connecting blocks. The front shovel 34 limits the rotation angle of the baffle 36 through the limit block 37. When the gravel enters the front shovel 34, the baffle 36 moves toward the direction of the first conveyor belt 32. After the gravel enters the front shovel 34, the baffle 36 returns to its original position due to gravity, and the limit block 37 blocks the rotation range of the baffle 36, so that the baffle 36 can block the feeding position of the front shovel 34.

[0034] In the present embodiment, the rotating structure in the slag scraping rotating structure 4 includes a mounting frame 40, motors 41 are provided at both ends of the top of the mounting frame 40, a rotating member 42 is rotatably installed in the middle position of the top of the mounting frame 40, a lifting plate 43 is rotatably installed on the top of the rotating member 42, a connecting member 44 is installed in the middle position of the top of the lifting plate 43, a fourth hydraulic cylinder 414 is provided inside the rotating member 42, a dust suppression member 415 is provided inside the mounting frame 40, and the rotating member 42 in the rotating structure is rotated by the output end of the motor 41, thereby adjusting the direction of the slag scraping opening structure on the slag scraping rotating structure 4, and the fourth hydraulic cylinder 414 can drive the slag scraping opening structure on the lifting plate 43 to rise and fall, thereby assisting in adjusting the direction of the slag scraping opening structure.

[0035] In this embodiment, the mounting frame 40 is installed on the support 30 through the support ear 33, the output end of the fourth hydraulic cylinder 414 is connected to the lifting plate 43, both ends of the dust suppression member 415 pass through the side wall of the mounting frame 40 and extend to the outside, a rotating opening is opened on the top of the mounting frame 40, and the rotating member 42 is rotatably connected to the mounting frame 40 through the rotating opening. The rotating structure is stably and firmly installed on the support 30 through the support ear 33, and the construction personnel inject clean water into the dust suppression member 415, and then the clean water flows out through the dust suppression member 415 and sprays on the gravel to prevent the smoke and dust on the gravel from being raised during the transmission process.

[0036] In this embodiment, teeth are provided at the bottom of the outer surface of the rotating member 42, and bevel teeth are provided at the output end of the motor 41. The output end of the motor 41 is meshed with the teeth on the rotating member 42 through the bevel teeth. Movable grooves are provided at both ends of the top of the lifting plate 43. The motor 41 drives the rotating member 42 to rotate through the cooperation between the bevel teeth and the teeth, and the movable grooves on the lifting plate 43 can assist in the use of the slag removal hole opening structure.

[0037] In this embodiment, the slag removal hole opening structure in the slag removal rotating structure 4 includes a connecting rod 45, both ends of the connecting member 44 are rotatably provided with connecting rods 45, the end of the bottom of the connecting rod 45 away from the connecting member 44 is rotatably installed with a first hydraulic cylinder 46, and the top of the connecting rod 45 is rotatably provided with a second hydraulic cylinder 47, and the ends of the two connecting rods 45 away from the connecting member 44 are rotatably installed with a first rotating rod 48 and a second rotating rod 49, respectively, and the end of the first rotating rod 48 away from the connecting member 44 is installed with an impact drill 410, and the bottom of the first rotating rod 48 is rotatably installed There is a bucket 412, and a third hydraulic cylinder 411 is installed at one end of the first rotating rod 48 close to the connecting piece 44, and a drilling machine 413 is rotatably installed at the bottom of the second rotating rod 49. The slag removal and hole opening structure drives the bucket 412 and the drilling machine 413 to move through the assistance of multiple hydraulic cylinders, so that the bucket 412 can send the gravel into the transmission structure. When encountering larger gravel, the gravel can be broken by the impact drill 410 to facilitate the cleaning of the gravel. When it is necessary to open a hole in the mountain, the construction personnel can use the drilling machine 413 to open a hole in the mountain.

[0038] In this embodiment, the two ends of the first hydraulic cylinder 46 are rotatably connected to the lifting plate 43 and the connecting rod 45 respectively, the output end of the second hydraulic cylinder 47 is connected to the first rotating rod 48 or the second rotating rod 49, and the output end of the third hydraulic cylinder 411 is connected to the bucket 412. The construction personnel drive the connecting rod 45 to rotate on the lifting plate 43 through the first hydraulic cylinder 46, and the second hydraulic cylinder 47 can drive the first rotating rod 48 or the second rotating rod 49 to rotate on the connecting rod 45, and the third hydraulic cylinder 411 can drive the bucket 412 to rotate on the first rotating rod 48.

[0039] A tunnel blasting construction method, characterized in that it comprises the following steps: S1: Survey and set out, test soil samples to determine rock grade, and plan blasting plans; S2: The drilling platform is in place, and the construction workers build the drilling platform in front of the mountain; S3: Drilling: construction workers use drilling platforms to open holes for blasting on the mountain; S4: Hole cleaning: construction workers clean the holes used for blasting; S5: Loading, networking, detonation. Construction workers place explosives into the holes, connect the fuses of the explosives together, and then detonate them simultaneously; S6: Ventilation and exhaust of smoke (dust). Construction workers use ventilation devices to remove the smoke and dust generated by blasting; S7: Risk elimination: construction personnel conduct risk elimination on the tunnels created by blasting; S8: Slag removal, using a slag scraper to clean up the gravel in the tunnel; S9: enter the next cycle; When entering the next cycle, the construction workers no longer need to set up a drilling platform, and can directly drill holes in the mountain through the drilling machine 413 on the slag removal and drilling structure. The operation is convenient and fast, and the construction efficiency is improved.

[0040] Embodiment 1, as Figure 2-4 As shown, the rotating member 42 in the rotating structure is rotated by the output end of the motor 41, so as to adjust the direction of the slag removal opening structure on the slag removal rotating structure 4, and the fourth hydraulic cylinder 414 can drive the slag removal opening structure on the lifting plate 43 to lift and lower, and assist in adjusting the direction of the slag removal opening structure; the rotating structure is stably and firmly installed on the bracket 30 through the support ear 33, and the construction personnel inject clean water into the dust removal member 415, and then the clean water flows out through the dust removal member 415 and sprays on the gravel to prevent the smoke and dust on the gravel from being raised during the transmission process; the motor 41 is driven by the bevel teeth and the teeth The cooperation drives the rotating part 42 to rotate, and the movable groove on the lifting plate 43 can assist the use of the slag removal and hole opening structure. The slag removal and hole opening structure drives the bucket 412 and the drilling machine 413 to move through the assistance of multiple hydraulic cylinders, so that the bucket 412 can deliver the gravel into the transmission structure. When encountering larger gravel, the gravel can be broken up by the impact drill 410 to facilitate the cleaning of the gravel. When it is necessary to open a hole in the mountain, the construction personnel can use the drilling machine 413 to open a hole in the mountain, and the first rotating rod 48 and the second rotating rod 49 can be replaced by a hydraulic telescopic rod.

[0041] Embodiment 2, as Figure 5As shown, the first conveyor belt 32 and the second conveyor belt 35 are moved by the servo motor 31 and the power source at the bottom of the front shovel 34 respectively. After the crushed stone enters the front shovel 34, it is moved to the bracket 30 by the second conveyor belt 35, and then the crushed stone is sent to the transport vehicle through the first conveyor belt 32. In this process, the baffle 36 can be used to prevent the crushed stone from sliding off the conveying structure 3. When the crushed stone enters the front shovel 34, the baffle 36 moves in the direction of the first conveyor belt 32. After the crushed stone enters the front shovel 34, the baffle 36 returns to its original position due to gravity, and then the limit block 37 blocks the rotation range of the baffle 36, and enables the baffle 36 to block the feeding position of the front shovel 34.

[0042] Working principle: construction workers control the walking device 1, transmission structure 3 and scraper rotating structure 4 through the cab 2. In the process of cleaning gravel, smaller gravel is cleaned through the scraper rotating structure 4 and the transmission structure 3. When encountering larger gravel, it is cleaned through the impact drill 410. After the gravel is cleaned, the mountain is drilled through the drilling machine 413 on the scraper rotating structure 4. The operation is convenient and the construction workers do not need to set up a drilling platform.

[0043] For those skilled in the art, the present invention is not limited to the details of the above exemplary embodiments, and the present invention can be implemented in other specific forms without departing from the spirit or scope of the present invention. Therefore, the embodiments of the present invention are exemplary and non-restrictive. The scope of the present invention is defined by the appended claims rather than the above description, and it is intended that all changes falling within the meaning and scope of the equivalent elements of the claims are included in the present invention. Any reference numerals in the claims should not be regarded as limiting the claims involved.

Claims

1. A slag scraper for tunnel blasting, characterized in that: include: A walking device (1), the walking device (1) comprising a crawler track and a mounting seat, wherein the walking device (1) can move on different terrains via the crawler track and can also improve stability; A cab (2), wherein the cab (2) is arranged on a mounting seat of the traveling device (1), and construction personnel can control the traveling device (1) through the cab (2); A transmission structure (3), wherein the transmission structure (3) is arranged on a mounting seat of the walking device (1), and the transmission structure (3) is controlled by the cab (2) so that the transmission structure (3) can clean up gravel; The slag scraping rotating structure (4) is arranged on the transmission structure (3) and is composed of a slag scraping hole opening structure and a rotating structure. The slag scraping rotating structure (4) is provided with an impact drill (410), a bucket (412) and a drilling machine (413). The slag scraping rotating structure (4) is controlled by the cab (2) and can clean up the gravel through the bucket (412), and can also crush large gravel through the impact drill (410), and can also open holes for explosion on the mountain through the drilling machine (413).

2. A slag scraper for tunnel blasting according to claim 1, characterized in that: The transmission structure (3) comprises a bracket (30), one end of both sides of the bracket (30) is mounted with a servo motor (31), a first conveyor belt (32) is mounted inside the bracket (30), the other end of both sides of the bracket (30) is mounted with a support ear (33), a front shovel (34) is mounted on the other end of the bracket (30), a second conveyor belt (35) is mounted on the front shovel (34), baffles (36) are rotatably mounted on both sides of the other end of the front shovel (34), and a limit block (37) is mounted on one end of the front shovel (34) close to the baffle (36).

3. A slag scraper for tunnel blasting according to claim 2, characterized in that: The servo motor (31) is connected to the first conveyor belt (32), and the first conveyor belt (32) can move on the bracket (30), and the second conveyor belt (35) can move on the front shovel (34). A power source is provided at the bottom of the front shovel (34) to drive the second conveyor belt (35) to move.

4. A slag scraper for tunnel blasting according to claim 3, characterized in that: Connecting blocks are provided on both sides of the other end of the front shovel (34), and the front shovel (34) is rotatably connected to the baffle (36) via the connecting blocks. The front shovel (34) limits the rotation angle of the baffle (36) via a limiting block (37).

5. The slag scraper for tunnel blasting according to claim 4, characterized in that: The rotating structure in the scraping rotating structure (4) comprises a mounting frame (40), motors (41) are arranged at both ends of the top of the mounting frame (40), a rotating member (42) is rotatably mounted in the middle position of the top of the mounting frame (40), a lifting plate (43) is rotatably mounted on the top of the rotating member (42), a connecting member (44) is installed in the middle position of the top of the lifting plate (43), a fourth hydraulic cylinder (414) is arranged inside the rotating member (42), and a dust suppression member (415) is arranged inside the mounting frame (40).

6. A slag scraper for tunnel blasting according to claim 5, characterized in that: The mounting frame (40) is mounted on the bracket (30) via a support ear (33); the output end of the fourth hydraulic cylinder (414) is connected to the lifting plate (43); both ends of the dust suppression member (415) penetrate the side wall of the mounting frame (40) and extend to the outside; a rotating opening is provided at the top of the mounting frame (40); and the rotating member (42) is rotatably connected to the mounting frame (40) via the rotating opening.

7. The slag scraper for tunnel blasting according to claim 6, characterized in that: The bottom of the outer surface of the rotating member (42) is provided with teeth, the output end of the motor (41) is provided with bevel teeth, the output end of the motor (41) is meshed with the teeth on the rotating member (42) through the bevel teeth, and movable grooves are provided at both ends of the top of the lifting plate (43).

8. The slag scraper for tunnel blasting according to claim 5, characterized in that: The slag removal hole opening structure in the slag removal rotating structure (4) comprises a connecting rod (45), both ends of the connecting member (44) are rotatably provided with a connecting rod (45), a first hydraulic cylinder (46) is rotatably mounted on the end of the bottom of the connecting rod (45) away from the connecting member (44), a second hydraulic cylinder (47) is rotatably mounted on the top of the connecting rod (45), a first rotating rod (48) and a second rotating rod (49) are rotatably mounted on the ends of the two connecting rods (45) away from the connecting member (44), an impact drill (410) is mounted on the end of the first rotating rod (48) away from the connecting member (44), a bucket (412) is rotatably mounted on the bottom of the first rotating rod (48), a third hydraulic cylinder (411) is mounted on the end of the first rotating rod (48) close to the connecting member (44), and a drilling machine (413) is rotatably mounted on the bottom of the second rotating rod (49).

9. The slag scraper for tunnel blasting according to claim 8, characterized in that: The two ends of the first hydraulic cylinder (46) are rotatably connected to the lifting plate (43) and the connecting rod (45), respectively; the output end of the second hydraulic cylinder (47) is connected to the first rotating rod (48) or the second rotating rod (49); and the output end of the third hydraulic cylinder (411) is connected to the bucket (412).

10. A tunnel blasting construction method, characterized in that: The following steps are involved: S1: Survey and stake out, test soil samples to determine rock grade, and plan blasting plans; S2: The drilling platform is in place, and the construction workers build the drilling platform in front of the mountain; S3: Drilling: construction workers use drilling platforms to open holes for blasting on the mountain; S4: Hole cleaning: construction workers clean the holes used for blasting; S5: Loading, networking, detonation. Construction workers place explosives into the holes, connect the fuses of the explosives together, and then detonate them simultaneously; S6: Ventilation and exhaust of smoke (dust). Construction workers use ventilation devices to remove the smoke and dust generated by blasting; S7: Risk elimination: construction personnel conduct risk elimination on the tunnels created by blasting; S8: Slag removal, using a slag scraper to clean up the gravel in the tunnel; S9: Enter the next cycle.