Building engineering quantity statistical method and device, electronic equipment and storage medium

By decomposing the architectural model into multiple building units and merging decoration components defined by the same practice, the complex workload problem required to adjust the room space and component location in architectural design is solved, the accuracy and objectivity of the statistical project volume are achieved, and the flexibility of the statistical process is improved.

CN119721945AActive Publication Date: 2025-03-28深圳市斯维尔科技股份有限公司
View PDF 5 Cites 0 Cited by

Patent Information

Application Number
CN202411574130.6
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-11-06
Publication Date
2025-03-28
Estimated Expiration
2044-11-06

AI Technical Summary

Technical Problem

In architectural design, when the room space changes, the workload required to adjust the location and size of the room space and the location and size of the related components is very large. The prior art is difficult to effectively reduce this complexity while ensuring the accuracy and objectivity of statistics.

Method used

By obtaining the building model, it is broken down into multiple building units according to the preset boundary surface, and the decoration components of each building unit are extracted according to the preset model standards. Then, the method definitions of each decoration component are obtained, the decoration components defined by the same practice are merged, and the decoration components in each building unit are counted according to the preset calculation rules to obtain the unit engineering quantity of each building unit.

Benefits of technology

This method effectively reduces the complexity of statistical engineering volume, avoids repeated statistics of the same decoration component in adjacent building units, ensures statistics accuracy and objectivity, and improves the flexibility of the statistical process.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119721945A_ABST
    Figure CN119721945A_ABST
Patent Text Reader

Abstract

The embodiment of the invention provides a building engineering quantity statistical method and device, electronic equipment and a storage medium, and the method comprises the steps: obtaining a building model, and decomposing the building model into a plurality of building units according to a preset boundary surface; according to a preset model standard, extracting a decoration component of each building unit in the building model; obtaining a practice definition of each decoration component, and if the practice definitions of the multiple decoration components on the same boundary surface in the same building unit are the same, combining the decoration components with the same practice definition; according to a preset calculation rule, the decoration components in all the building units are counted in sequence, and the unit engineering quantity of all the building units is obtained; according to the method provided by the embodiment of the invention, the complexity of the statistical engineering quantity can be reduced, and the accuracy and objectivity of the statistical engineering quantity are ensured at the same time.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to but is not limited to the field of engineering statistics technology, and in particular to a construction engineering quantity statistics method, device, electronic equipment and storage medium. Background Art

[0002] In architectural design, the design of a room generally includes three parts: the decoration description in the building description, the decoration material list, and the building floor plan. The decoration description is used to describe the detailed methods of a certain type of decoration, such as the detailed methods of decorating the tile floor. The decoration material list is used to describe the combination of decoration methods used in the room, such as the living room floor is tiled, the wall is painted, etc.

[0003] In the related art, when the room space changes, it is necessary to adjust the spatial position and size of the room, and also adjust the spatial position and size of the corresponding components such as the wall, floor, ceiling, skirting, etc. When the design of the room changes, the workload of adjustment is also very large, and it is necessary to filter out the corresponding decorative components according to the room, and then adjust the corresponding decorative components. Summary of the invention

[0004] The following is a summary of the subject matter described in detail herein. This summary is not intended to limit the scope of the claims.

[0005] The embodiments of the present application provide a method, device, electronic device and storage medium for counting construction project quantities, which can reduce the complexity of counting construction project quantities while ensuring the accuracy and objectivity of counting construction project quantities.

[0006] To achieve the above-mentioned purpose, the first aspect of an embodiment of the present application proposes a method for counting construction project quantities, comprising: obtaining a building model, and decomposing the building model into multiple building units according to a preset boundary surface; extracting the decoration components of each of the building units in the building model according to a preset model standard; obtaining the practice definition of each of the decoration components, and if the practice definitions of multiple decoration components located on the same boundary surface in the same building unit are the same, merging the decoration components with the same practice definitions; and counting the decoration components in each of the building units in turn according to a preset calculation rule to obtain the unit project quantity of each of the building units.

[0007] In one embodiment, the unit engineering quantity includes the wall engineering quantity in the building unit, and the decoration components in each building unit are counted in turn according to a preset calculation rule to obtain the unit engineering quantity of each building unit, including: obtaining the contour plane and wall height range of the building unit; obtaining the top height and bottom height of the decoration component associated with the contour plane, when the top height and the bottom height are both within the wall height range, determining the corresponding decoration component as a wall component; and determining the wall engineering quantity according to the wall component.

[0008] In one embodiment, the unit engineering quantity includes the ground engineering quantity in the building unit, and the decoration components in each building unit are counted in turn according to a preset calculation rule to obtain the unit engineering quantity of each building unit, including: obtaining the ground height range of the building unit, and determining the ground components according to the ground height range; determining the ground engineering quantity according to the projection area of ​​the ground components on the horizontal surface and the vertical plane.

[0009] In one embodiment, the unit engineering quantity includes the skirting engineering quantity in the building unit, and the decoration components in each building unit are counted in turn according to a preset calculation rule to obtain the unit engineering quantity of each building unit, including: obtaining the bottom contour line in the building unit; determining the skirting engineering quantity according to the bottom contour line and a preset skirting height.

[0010] In one embodiment, the unit engineering quantity includes the ceiling engineering quantity in the building unit, and the decoration components in each building unit are counted in turn according to a preset calculation rule to obtain the unit engineering quantity of each building unit, including: obtaining the ground range of the building unit directly above the current building unit; determining the decoration components associated with the bottom of the ground range as ceiling components, and determining the ceiling workload according to the projection area of ​​the ceiling components on the ground range; if the current building unit is connected to the building unit directly above by stairs, obtaining the stairwell within the ground range, and adjusting the ceiling workload using the projection area of ​​the stairwell on the ground range.

[0011] In one embodiment, the method further includes: when there are repeated unit quantities between adjacent building units, deducting the repeated unit quantities in one of the building units; merging the unit quantities based on preset merging rules according to the positions of the building units on the building model and the definition of the practices corresponding to the unit quantities, so as to obtain the target quantity of the building model.

[0012] In one embodiment, the practice definition includes the material, steps, quantity and position of the decoration components. Before the decoration components in each of the building units are counted in turn according to a preset calculation rule to obtain the unit project quantity of each of the building units, the following steps are included: if any one of the material, step, quantity or position is missing in the practice definition of the decoration component, the corresponding decoration component will be eliminated.

[0013] To achieve the above-mentioned purpose, the second aspect of the present application proposes a construction project quantity statistics device, including: an acquisition module, used to acquire a building model, and decompose the building model into multiple building units according to a preset boundary surface; an extraction module, used to extract the decoration components of each of the building units in the building model according to a preset model standard; a merging module, used to acquire the practice definition of each of the decoration components, if the practice definitions of multiple decoration components located on the same boundary surface in the same building unit are the same, the decoration components with the same practice definition are merged; a statistics module, used to count the decoration components in each of the building units in turn according to a preset calculation rule to obtain the unit project quantity of each of the building units.

[0014] To achieve the above-mentioned purpose, the third aspect of an embodiment of the present application proposes an electronic device, which includes a memory and a processor, the memory stores a computer program, and the processor implements the construction project quantity statistics method described in the first aspect when executing the computer program.

[0015] To achieve the above-mentioned purpose, the fourth aspect of an embodiment of the present application proposes a storage medium, which is a computer-readable storage medium, and the storage medium stores a computer program. When the computer program is executed by a processor, it implements the construction project quantity statistics method described in the first aspect above.

[0016] The embodiments of the present application include at least the following beneficial effects: in a building model, most decoration components are associated with boundary surfaces, and the building model is decomposed according to the boundary surfaces. For a complete boundary surface, one side of the boundary surface belongs to one building unit, and the other side of the boundary surface belongs to another building unit. If there are multiple other boundary surfaces intersecting with the current boundary surface on one side, it can also be decomposed again according to these intersecting boundary surfaces, thereby reducing the situation where a complete decoration component is divided into multiple building units, avoiding the same decoration component from being repeatedly counted in adjacent building units, and reducing the complexity of statistical engineering quantities; at the same time, Within a building unit, the construction difficulty varies depending on the position, angle and direction of the boundary surface. Therefore, within a building unit, when there are multiple decoration components with the same definition of practice, the decoration components with the same definition of practice are merged based on the associated boundary surface. This can reduce the complexity of statistical engineering quantities and avoid general statistics of decoration components with different construction difficulties, thereby ensuring the accuracy and objectivity of statistical engineering quantities. After the decorative components associated with the same boundary surface are merged, when the definition of the practice of the decorative components changes, the unit engineering quantity after statistics can be directly modified, which improves the flexibility of the statistical process.

[0017] Other features and advantages of the present application will be described in the following description, and partly become apparent from the description, or understood by practicing the present application. The purpose and other advantages of the present application can be realized and obtained by the structures specifically pointed out in the description, claims and drawings. BRIEF DESCRIPTION OF THE DRAWINGS

[0018] The accompanying drawings are used to provide further understanding of the technical solution of the present application and constitute a part of the specification. Together with the embodiments of the present application, they are used to explain the technical solution of the present application and do not constitute a limitation on the technical solution of the present application.

[0019] Figure 1 An optional flow chart of a construction engineering quantity statistics method provided in an embodiment of the present application; Figure 2 An optional flow chart of counting wall surface engineering quantities provided in an embodiment of the present application; Figure 3 An optional schematic diagram of a process for counting ground engineering quantities provided in an embodiment of the present application; Figure 4 An optional flow chart of counting the amount of skirting works provided in an embodiment of the present application; Figure 5 An optional flow chart of counting ceiling engineering quantities provided in an embodiment of the present application; Figure 6An optional specific flow diagram of the engineering quantity merging provided in the embodiment of the present application; Figure 7 An optional structural schematic diagram of a construction engineering quantity statistics device provided in this embodiment; Figure 8 A schematic diagram of an optional hardware structure of an electronic device provided in an embodiment of the present application. DETAILED DESCRIPTION

[0020] In order to make the purpose, technical solution and advantages of the present application more clearly understood, the present application is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present application and are not used to limit the present application.

[0021] In the description of this application, “several” means one or more, “more” means more than two, “greater than”, “less than”, “exceed”, etc. are understood to exclude the number, and “above”, “below”, “within”, etc. are understood to include the number.

[0022] It should be noted that, although the functional modules are divided in the device schematic diagram and the logical order is shown in the flowchart, in some cases, the steps shown or described may be performed in a different order than the module division in the device or the order in the flowchart. The terms "first", "second", etc. in the specification, claims or the above drawings are used to distinguish similar objects, and are not necessarily used to describe a specific order or sequence.

[0023] To facilitate understanding of the technical solutions provided in the embodiments of the present application, some key terms used in the embodiments of the present application are explained here: Construction project quantity statistics refers to the process of quantifying the various resources, work content and engineering results involved in the project before, during or after the construction of the construction project. This includes the systematic calculation and statistics of building materials, components, labor, mechanical equipment use and various workloads during the construction process. The purpose of construction project quantity statistics is to ensure the smooth progress of the project, control costs, and evaluate the economic benefits of the project. Construction project quantity statistics is an important part of project management, which helps project managers to allocate resources, control costs, plan schedules and ensure quality. Through accurate engineering quantity statistics, we can effectively avoid waste of resources, improve engineering efficiency and ensure that the project is completed as planned and on budget.

[0024] In the related art, when the room space changes, it is necessary to adjust the spatial position and size of the room, and also adjust the spatial position and size of the corresponding components such as the wall, floor, ceiling, skirting, etc. When the design of the room changes, the workload of adjustment is also very large, and it is necessary to filter out the corresponding decorative components according to the room, and then adjust the corresponding decorative components.

[0025] Based on this, the embodiments of the present application provide a method, device, electronic device and storage medium for counting construction project quantities, which can reduce the complexity of counting construction project quantities while ensuring the accuracy and objectivity of counting construction project quantities.

[0026] The construction project quantity statistics method, device, electronic device and storage medium provided in the embodiments of the present application are specifically explained through the following embodiments. First, the construction project quantity statistics method in the embodiments of the present application is described.

[0027] The construction quantity statistics method provided in the embodiment of the present application relates to the field of computer technology. The construction quantity statistics method provided in the embodiment of the present application can be applied to a terminal, can be applied to a server side, or can be software running in a terminal or a server side. In some embodiments, the terminal can be a smart phone, a tablet computer, a laptop computer, a desktop computer, etc.; the server side can be configured as an independent physical server, or can be configured as a server cluster or a distributed system composed of multiple physical servers, and can also be configured as a cloud server that provides basic cloud computing services such as cloud services, cloud databases, cloud computing, cloud functions, cloud storage, network services, cloud communications, middleware services, domain name services, security services, CDN, and big data and artificial intelligence platforms; the software can be an application that implements the construction quantity statistics method, etc., but is not limited to the above forms.

[0028] The present application can be used in many general or special computer system environments or configurations. For example: personal computers, server computers, handheld or portable devices, tablet devices, multiprocessor systems, microprocessor-based systems, set-top boxes, programmable consumer electronics, network PCs, minicomputers, mainframe computers, distributed computing environments including any of the above systems or devices, etc. The present application can be described in the general context of computer-executable instructions executed by a computer, such as program modules. Generally, program modules include routines, programs, objects, components, data structures, etc. that perform specific tasks or implement specific abstract data types. The present application can also be practiced in distributed computing environments, in which tasks are performed by remote processing devices connected through a communication network. In a distributed computing environment, program modules can be located in local and remote computer storage media including storage devices.

[0029] The embodiments of the present application are further described below in conjunction with the accompanying drawings.

[0030] like Figure 1 As shown, Figure 1An optional flow chart of a construction quantity statistics method provided in an embodiment of the present application, the construction quantity statistics method can be executed by a server, or can also be executed by a terminal, or can also be executed by a server in conjunction with a terminal, and the construction quantity statistics method includes but is not limited to the following steps S110 to S140: Step S110, obtaining a building model, and decomposing the building model into a plurality of building units according to a preset boundary surface; Step S120, extracting the decoration components of each building unit in the building model according to a preset model standard; Step S130, obtaining the method definition of each decoration component, if the method definition of multiple decoration components located on the same boundary surface in the same building unit is the same, merging the decoration components with the same method definition; Step S140, counting the decoration components in each building unit in turn according to a preset calculation rule to obtain the unit engineering quantity of each building unit.

[0031] It is understandable that in the building model, most of the decoration components are associated with the boundary surfaces. The building model is decomposed according to the boundary surfaces. For a complete boundary surface, one side of the boundary surface belongs to one building unit, and the other side of the boundary surface belongs to another building unit. If there are multiple other boundary surfaces intersecting with it on one side of the current boundary surface, it can also be decomposed again according to these intersecting boundary surfaces, thereby reducing the situation where the complete decoration components are divided into multiple building units, avoiding the same decoration components from being repeatedly counted in adjacent building units, and reducing the complexity of statistical engineering quantities; at the same time, in the building unit The construction difficulty varies according to the position, angle and direction of the boundary surface. Therefore, in a building unit, when there are multiple decoration components with the same definition of practice, the decoration components with the same definition of practice are merged based on the associated boundary surface. This can reduce the complexity of statistical engineering quantity and avoid general statistics of decoration components with different construction difficulties, thereby ensuring the accuracy and objectivity of statistical engineering quantity. After the decorative components associated with the same boundary surface are merged, when the definition of the practice of the decorative components changes, the unit engineering quantity after statistics can be directly modified, which improves the flexibility of the statistical process.

[0032] Specifically, the building unit may be a single room, a corridor, a balcony, or other multiple spaces separated by walls.

[0033] In addition, before the decoration components in each building unit are counted in turn according to the preset calculation rules to obtain the unit project quantity of each building unit, if any of the materials, steps, quantities or positions in the definition of the decoration component is missing, the decoration component will not be included in the statistics of the unit project quantity.

[0034] In addition, refer to Figure 2 As shown, the unit engineering quantity includes the wall engineering quantity within the building unit. Figure 1 Step S140 in the embodiment includes but is not limited to the following steps S210 to S220: Step S210, obtaining the outline plane and wall height range of the building unit; Step S220, obtaining the top height and bottom height of the decoration component associated with the contour plane, and when both the top height and the bottom height are within the wall height range, determining the corresponding decoration component as a wall component; Step S230, determining the wall construction quantity according to the wall components.

[0035] Specifically, a building unit is surrounded by the ground, the ceiling and multiple walls. The wall height range represents the height of the plane where the wall and the ceiling meet, and the range formed by the height of the plane where the wall and the ground meet. The contour plane represents the plane formed by the contour line between the wall and the ground, and the contour line between the wall and the ceiling. In a building unit that is connected to the outside world only through doors and windows, the contour plane can also be simply understood as the inner surface of the wall in the building unit.

[0036] In a specific embodiment, the wall component includes the painting work of the entire wall, and the project quantity corresponding to the painting work of the wall is recorded as the wall painting area. When the painting materials, painting procedures and painting thickness of each wall in the building unit are the same, the painting work of each wall will be included in the same project quantity; if the painting materials, painting procedures or painting thicknesses on different walls are different, the wall painting area will be counted according to the specific categories of painting materials, painting procedures and painting thickness.

[0037] In a specific implementation, the wall components also include attached wall columns, room beams, wall buttresses and chimneys. The attached wall columns, room beams, wall buttresses and chimneys are projected onto the wall surface connected to themselves, and the projection areas of the attached wall columns, room beams, wall buttresses and chimneys on the wall surface are calculated, and this part of the projection area is included in the wall surface engineering quantity.

[0038] In a specific embodiment, the wall components also include wall skirts, door frame holes, window frame holes, and holes. Similarly, the wall skirts, door frame holes, and window frame holes are projected onto the wall associated with themselves, and the projection areas of the wall skirts, door frame holes, and window frame holes on the wall are calculated. When there are holes on the wall, if the diameter of a single hole is greater than 0.3 meters, it will be deducted from the wall engineering quantity. If the diameter of a single hole is less than or equal to 0.3 meters, it will not be deducted from the wall engineering quantity.

[0039] It should be noted that the side wall and top surface areas of both door frame openings and window frame openings are not included in the wall construction volume.

[0040] In addition, refer to Figure 3 As shown, in one embodiment of the present application, the unit engineering quantity includes the ground engineering quantity within the building unit. Figure 1 Step S140 in the embodiment includes but is not limited to the following steps S310 to S320: Step S310, obtaining the ground height range of the building unit, and determining the ground component according to the ground height range; Step S320, determining the ground engineering quantity according to the projection areas of the ground components on the horizontal surface and the vertical plane.

[0041] Specifically, the ground height range represents a range formed by the ground height line of the current building unit and the ceiling height line of the building unit located directly below; the decoration components located within the ground height range are obtained to determine the ground components.

[0042] In a specific embodiment, the ground component includes the painting work of the ground within the building unit, and the engineering quantity corresponding to the painting work of the ground is recorded as the ground painting area. When the ground within the building unit is divided into multiple areas, the painting work between different areas includes different painting materials, painting procedures and painting thicknesses, then the painting area is counted according to the specific categories of the painting materials, painting procedures and painting thicknesses of each area.

[0043] In a specific embodiment, when there are partition walls, wall buttresses, wall columns, wall-attached chimneys and pipes arranged on the ground in a building unit, the projected areas of the partition walls, wall buttresses, wall columns, wall-attached chimneys and pipes arranged on the ground on the ground are not deducted.

[0044] In addition, refer to Figure 4 As shown, the unit works include the skirting works within the building unit. Figure 1 Step S140 in the embodiment includes but is not limited to the following steps S410 to S420: Step S410, obtaining the bottom contour line within the building unit; Step S420, determining the skirting work quantity according to the bottom contour line and the preset skirting height.

[0045] Specifically, the bottom contour line is the line formed by the wall and the ground. When there are partition walls or wall columns in the building unit, the partition walls and wall columns are projected onto the plane where the ground is located, and the side length of the projected shape is included in the bottom contour line.

[0046] Then, obtain the preset skirting height and determine the skirting work quantity based on the product of the total length of the bottom contour line and the skirting height.

[0047] In addition, refer to Figure 5 As shown, the unit engineering quantity includes the ceiling engineering quantity within the building unit. Figure 1 Step S140 in the embodiment includes but is not limited to the following steps S510 to S530: Step S510, obtaining the ground range of the building unit located directly above the current building unit; Step S520, determining the decoration components associated with the bottom of the ground range as ceiling components, and determining the ceiling workload according to the projection area of ​​the ceiling components on the ground range; Step S530: If the current building unit is connected to the building unit directly above by stairs, obtain the stairwell within the ground range, and adjust the ceiling workload using the projection area of ​​the stairwell on the ground range.

[0048] Specifically, the ceiling components include the ceiling painting work within the building unit, and the engineering quantity corresponding to the ceiling painting work is recorded as the ceiling painting area. When the ceiling within the building unit is divided into multiple areas, the painting work between different areas includes different painting materials, painting procedures and painting thicknesses, then the painting area is counted according to the specific categories of the painting materials, painting procedures and painting thicknesses of each area.

[0049] In a specific implementation, if the current building unit is connected to the building unit directly above by a staircase, and the projected area of ​​the stairwell on the ceiling is greater than 500 square millimeters, the projected area of ​​the stairwell is deducted from the ceiling engineering quantity.

[0050] In a specific implementation, when the stairs are connected to the ground of the building unit directly above, the area of ​​the inner edge of the stair opening beam is included in the ceiling engineering quantity. If the stairs do not have a stair opening beam, 300 mm is added to the edge of the top step of the stairs and included in the ceiling engineering quantity.

[0051] In a specific implementation, if the stairs are plank stairs, the painted area of ​​the stair floor is calculated as the inclined area and included in the ceiling project quantity; if the stairs are zigzag stair floors, it is calculated as the surface area of ​​the bottom of the stairs and included in the ceiling project quantity.

[0052] In a specific implementation, if there are beams on the ceiling, the areas on both sides of the beams are increased and included in the ceiling engineering quantity.

[0053] In addition, refer to Figure 6 As shown, the construction engineering quantity statistics method proposed in the embodiment of the present application also includes the following steps S610 to S620: Step S610, when there are repeated unit engineering quantities between adjacent building units, deduction processing is performed on the repeated unit engineering quantities in one of the building units; Step S620, according to the position of the building unit on the building model and the definition of the method corresponding to the unit engineering quantity, the unit engineering quantities are merged based on the preset merging rules to obtain the target engineering quantity of the building model.

[0054] In a specific implementation, when adjacent building units are connected via door frames or window frames, and the quantities related to the door frames and window frames are included in the adjacent building units, the repeatedly calculated quantities are deducted from the unit quantities of one of the building units.

[0055] In addition, when adjacent building units are connected by stairs or patios, and the engineering quantities related to the stairs and patios are included in the adjacent building units, the attribution of the engineering quantities related to the stairs and patios is determined according to the preset rules, and the repeatedly calculated engineering quantities are attributed to the unit engineering quantities of the affiliated building units, and the corresponding engineering quantities are deducted from the other building units.

[0056] In addition, the embodiment of the present application also provides a construction engineering quantity statistics device 700, including: An acquisition module 701 is used to acquire a building model and decompose the building model into a plurality of building units according to a preset boundary surface; Extraction module 702, used to extract the decoration components of each building unit in the building model according to a preset model standard; A merging module 703 is used to obtain the method definition of each decoration component, and if the method definitions of multiple decoration components located on the same boundary surface in the same building unit are the same, the decoration components with the same method definition are merged; The statistical module 704 is used to count the decoration components in each building unit in turn according to a preset calculation rule to obtain the unit engineering quantity of each building unit.

[0057] The above-mentioned construction engineering quantity counting device 700 and the construction engineering quantity counting method are based on the same inventive concept, which will not be described in detail here.

[0058] In addition, refer to Figure 8 , Figure 8 The hardware structure of an electronic device of another embodiment is illustrated, and the electronic device includes: The processor 801 may be implemented by a general-purpose CPU (Central Processing Unit), a microprocessor, an application-specific integrated circuit (ASIC), or one or more integrated circuits, and is used to execute relevant programs to implement the technical solutions provided in the embodiments of the present application; The memory 802 can be implemented in the form of a read-only memory (ROM), a static storage device, a dynamic storage device, or a random access memory (RAM). The memory 802 can store an operating system and other application programs. When the technical solution provided in the embodiment of this specification is implemented by software or firmware, the relevant program code is stored in the memory 802, and the processor 801 calls and executes the construction engineering quantity statistics method of the embodiment of the present application, for example, executing the above-described Figure 1 Steps S110 to S140 of the method, Figure 2 Steps S210 to S23 of the method, Figure 3 Steps S310 to S320 of the method, Figure 4 Steps S410 to S420 of the method, Figure 5 Steps S510 to S530 of the method, Figure 6 Steps S610 to S620 of the method; Input / output interface 803, used to implement information input and output; The communication interface 804 is used to realize the communication interaction between the device and other devices. The communication can be realized through wired means (such as USB, network cable, etc.) or wireless means (such as mobile network, WIFI, Bluetooth, etc.); A bus 805 that transmits information between various components of the device (e.g., the processor 801, the memory 802, the input / output interface 803, and the communication interface 804); The processor 801 , the memory 802 , the input / output interface 803 and the communication interface 804 are connected to each other in communication within the device via a bus 805 .

[0059] The present application also provides a storage medium, which is a computer-readable storage medium for computer-readable storage. The storage medium stores one or more programs, and the one or more programs can be executed by one or more processors to implement the above-mentioned construction engineering quantity statistics method, for example, to execute the above-described Figure 1 Steps S110 to S140 of the method, Figure 2 Steps S210 to S23 of the method, Figure 3 Steps S310 to S320 of the method, Figure 4 Steps S410 to S420 of the method, Figure 5 Steps S510 to S530 of the method, Figure 6 Method steps S610 to S620.

[0060] The memory, as a non-transient computer-readable storage medium, can be used to store non-transient software programs and non-transient computer executable programs. In addition, the memory may include a high-speed random access memory, and may also include a non-transient memory, such as at least one disk storage device, a flash memory device, or other non-transient solid-state storage device. In some embodiments, the memory may optionally include a memory remotely disposed relative to the processor, and these remote memories may be connected to the processor via a network. Examples of the above-mentioned network include, but are not limited to, the Internet, an intranet, a local area network, a mobile communication network, and combinations thereof.

[0061] The embodiments described in the embodiments of the present application are intended to more clearly illustrate the technical solutions of the embodiments of the present application and do not constitute a limitation on the technical solutions provided in the embodiments of the present application. Those skilled in the art will appreciate that with the evolution of technology and the emergence of new application scenarios, the technical solutions provided in the embodiments of the present application are also applicable to similar technical problems.

[0062] It can be understood by those skilled in the art that Figures 1 to 6 The technical solutions shown in the figure do not constitute a limitation on the embodiments of the present application, and may include more or fewer steps than those shown in the figure, or a combination of certain steps, or different steps.

[0063] The device embodiments described above are merely illustrative, and the units described as separate components may or may not be physically separated, that is, they may be located in one place or distributed on multiple network units. Some or all of the modules may be selected according to actual needs to achieve the purpose of the solution of this embodiment.

[0064] Those skilled in the art will appreciate that all or some of the steps in the methods disclosed above, and the functional modules / units in the systems and devices may be implemented as software, firmware, hardware, or a suitable combination thereof.

[0065] The terms "first", "second", "third", "fourth", etc. (if any) in the specification of the present application and the above-mentioned drawings are used to distinguish similar objects, and are not necessarily used to describe a specific order or sequence. It should be understood that the data used in this way can be interchangeable where appropriate, so that the embodiments of the present application described herein can be implemented in an order other than those illustrated or described herein. In addition, the terms "including" and "having" and any of their variations are intended to cover non-exclusive inclusions, for example, a process, method, system, product or device comprising a series of steps or units is not necessarily limited to those steps or units clearly listed, but may include other steps or units that are not clearly listed or inherent to these processes, methods, products or devices.

[0066] It should be understood that in the present application, "at least one (item)" means one or more, and "plurality" means two or more. "And / or" is used to describe the association relationship of associated objects, indicating that three relationships may exist. For example, "A and / or B" can mean: only A exists, only B exists, and A and B exist at the same time, where A and B can be singular or plural. The character " / " generally indicates that the objects associated before and after are in an "or" relationship. "At least one of the following" or similar expressions refers to any combination of these items, including any combination of single or plural items. For example, at least one of a, b or c can mean: a, b, c, "a and b", "a and c", "b and c", or "a and b and c", where a, b, c can be single or multiple.

[0067] In the several embodiments provided in the present application, it should be understood that the disclosed devices and methods can be implemented in other ways. For example, the device embodiments described above are only schematic. For example, the division of the above units is only a logical function division. There may be other division methods in actual implementation, such as multiple units or components can be combined or integrated into another system, or some features can be ignored or not executed. Another point is that the mutual coupling or direct coupling or communication connection shown or discussed can be through some interfaces, indirect coupling or communication connection of devices or units, which can be electrical, mechanical or other forms.

[0068] The units described above as separate components may or may not be physically separated, and the components shown as units may or may not be physical units, that is, they may be located in one place or distributed on multiple network units. Some or all of the units may be selected according to actual needs to achieve the purpose of the solution of this embodiment.

[0069] In addition, each functional unit in each embodiment of the present application may be integrated into one processing unit, or each unit may exist physically separately, or two or more units may be integrated into one unit. The above-mentioned integrated unit may be implemented in the form of hardware or in the form of software functional units.

[0070] If the integrated unit is implemented in the form of a software functional unit and sold or used as an independent product, it can be stored in a computer-readable storage medium. Based on this understanding, the technical solution of the present application, or the part that contributes to the prior art, or all or part of the technical solution can be embodied in the form of a software product, which is stored in a storage medium and includes multiple instructions for a computer device (which can be a personal computer, a server, or a network device, etc.) to execute all or part of the steps of the methods of various embodiments of the present application. The aforementioned storage medium includes: U disk, mobile hard disk, read-only memory (ROM), random access memory (RAM), disk or optical disk, and other media that can store programs.

[0071] The preferred embodiments of the present invention are described above with reference to the accompanying drawings, but the scope of the rights of the present invention is not limited thereto. Any modification, equivalent substitution and improvement made by a person skilled in the art without departing from the scope and essence of the present invention should be within the scope of the rights of the present invention.

Claims

1. A construction engineering quantity statistics method, characterized in that: include: Acquire a building model, and decompose the building model into a plurality of building units according to a preset boundary surface; Extracting the decoration components of each of the building units in the building model according to a preset model standard; Obtaining the working method definition of each of the decoration components, if the working method definitions of multiple decoration components located on the same boundary surface in the same building unit are the same, merging the decoration components with the same working method definition; The decoration components in each of the building units are counted in turn according to a preset calculation rule to obtain the unit engineering quantity of each of the building units.

2. The construction engineering quantity statistics method according to claim 1, characterized in that: The unit engineering quantity includes the wall engineering quantity in the building unit. The decoration components in each building unit are counted in turn according to the preset calculation rules to obtain the unit engineering quantity of each building unit, including: Obtaining the outline plane and wall height range of the building unit; Acquire the top height and the bottom height of the decoration component associated with the contour plane, and when the top height and the bottom height are both within the wall height range, determine the corresponding decoration component as a wall component; The wall construction quantity is determined according to the wall components.

3. The construction engineering quantity statistics method according to claim 1, characterized in that: The unit engineering quantity includes the ground engineering quantity in the building unit. The decoration components in each building unit are counted in turn according to the preset calculation rules to obtain the unit engineering quantity of each building unit, including: Acquire the ground height range of the building unit, and determine the ground component according to the ground height range; The ground engineering quantity is determined according to the projection area of ​​the ground components on the horizontal surface and the vertical plane.

4. The construction engineering quantity statistics method according to claim 1, characterized in that: The unit engineering quantity includes the skirting engineering quantity in the building unit. The decoration components in each building unit are counted in turn according to the preset calculation rules to obtain the unit engineering quantity of each building unit, including: Obtaining a bottom contour line within the building unit; The skirting work quantity is determined according to the bottom contour line and the preset skirting height.

5. The construction engineering quantity statistics method according to claim 1, characterized in that: The unit engineering quantity includes the ceiling engineering quantity in the building unit. The decoration components in each building unit are counted in turn according to the preset calculation rules to obtain the unit engineering quantity of each building unit, including: Obtaining the ground range of the building unit located directly above the current building unit; Determine the decoration component associated with the bottom of the ground range as a ceiling component, and determine the ceiling workload according to the projection area of ​​the ceiling component on the ground range; If the current building unit is connected to the building unit located directly above by stairs, the stairwell located within the ground range is obtained, and the ceiling workload is adjusted using the projection area of ​​the stairwell on the ground range.

6. The construction engineering quantity statistics method according to claim 1, characterized in that: The construction engineering quantity statistical method also includes: When there are repeated unit engineering quantities between adjacent building units, the repeated unit engineering quantities in one of the building units are deducted; According to the position of the building unit on the building model and the definition of the method corresponding to the unit engineering quantity, the unit engineering quantities are merged based on a preset merging rule to obtain the target engineering quantity of the building model.

7. The construction engineering quantity statistics method according to claim 1, characterized in that: The method definition includes the materials, steps, quantity and location of the decoration components. Before the decoration components in each building unit are counted in sequence according to the preset calculation rules to obtain the unit engineering quantity of each building unit, the construction engineering quantity statistical method includes: If any of the materials, steps, quantities or positions is missing in the manufacturing method definition of the decoration component, the corresponding decoration component will be discarded.

8. A construction engineering quantity statistics device, characterized in that: include: An acquisition module, used for acquiring a building model, and decomposing the building model into a plurality of building units according to a preset boundary surface; An extraction module, used for extracting the decoration components of each of the building units in the building model according to a preset model standard; a merging module, configured to obtain the definition of the method of each of the decoration components, and if the method definitions of multiple decoration components located on the same boundary surface in the same building unit are the same, merge the decoration components with the same method definitions; The statistical module is used to count the decoration components in each of the building units in turn according to a preset calculation rule to obtain the unit engineering quantity of each of the building units.

9. An electronic device, characterized in that: The electronic device includes a memory and a processor, the memory stores a computer program, and the processor implements the construction project quantity statistics method described in any one of claims 1 to 7 when executing the computer program.

10. A storage medium storing a computer program, characterized in that: When the computer program is executed by a processor, the construction engineering quantity statistics method described in any one of claims 1 to 7 is implemented.

Citation Information

Patent Citations

  • Engineering quantity calculation method and device for to-be-decorated space

    CN111985038A

  • Engineering quantity calculation method and device and electronic equipment

    CN113886924A

  • Method and device for determining wall information, computer equipment and storage medium

    CN117592167A

  • Virtual hardcover fast calculation method and system based on Revit scheme model

    CN117668984A

  • Skirting information determination method and device, computer equipment and storage medium

    CN117830579A