Total drawing process database construction method, device and equipment for process design and simulation of bullet train application station and storage medium
By constructing a digital database of EMUs, the long modeling time problem caused by the process simulation of EMUs relying on manual model building is solved, and rapid modeling and intelligent modeling of process simulation are realized, and design efficiency is improved.
Patent Information
- Application Number
- CN202411602617.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-11-11
- Publication Date
- 2025-04-04
AI Technical Summary
The process simulation used by EMUs mainly relies on manual model building, resulting in long modeling time and cannot meet the time requirements of design work.
By obtaining the digital parameters of the simulated model used by the EMU, dividing it into process physical model parameters and process information parameters, and constructing a digital database of the EMU, thereby obtaining the process overall plan layout.
It realizes rapid modeling and intelligent modeling of process simulation, reduces modeling time, provides data support, and assists designers in design solutions.
Smart Images

Figure CN119760951A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of motor vehicle engineering design, and in particular to a method, device, equipment and storage medium for constructing a general drawing process database for process design and simulation of motor vehicle operation. Background Art
[0002] The EMU operation center is a place for the preparation, first and second level repair, temporary repair and storage of EMUs that depart from and arrive at the passenger station, ensuring the safe and stable operation of the EMUs on the line. How to reasonably arrange the facilities in the EMU operation center, improve the operation efficiency of the EMUs, and achieve the effective ability to meet the operational needs is the focus of the design of the EMU operation center; process simulation is a technology that analyzes and optimizes the operation process through models and simulations. It can help designers better understand the operation and preparation process of EMUs by simulating facility layout, operation time, scheduling mode, etc., thereby improving efficiency.
[0003] However, there are relatively few simulation studies on EMU operation sites at home and abroad. The simulation models are mainly built and modified manually, which is labor-intensive and time-consuming, making it difficult to meet the time requirements of design work. The process simulation technology has not been widely used in the design of EMU operation sites. At present, the selection of the overall layout plan of the EMU operation site mainly relies on the experience of designers and auditors for qualitative analysis, and there is no intuitive data for quantitative analysis to assist decision-making.
[0004] Therefore, there is an urgent need to solve the problem that process simulation mainly relies on manual model construction and the modeling time is long.
[0005] The above contents are only used to assist in understanding the technical solution of the present application and do not constitute an admission that the above contents are prior art. Summary of the invention
[0006] The main purpose of this application is to provide a method, device, equipment and storage medium for constructing a general drawing process database for process design and simulation of EMU operation, aiming to solve the technical problem that process simulation mainly relies on manual model construction and the modeling time is long.
[0007] To achieve the above-mentioned purpose, the present application proposes a method for constructing a general drawing process database for process design and simulation of a motor vehicle operation, wherein the method comprises:
[0008] Obtain digital parameters of the simulation model of the EMU operation;
[0009] Based on the digital parameters of the simulation model of the motor vehicle operation, physical model data and process information data are obtained;
[0010] Constructing a digital database of a motor vehicle operation center according to the physical model data and the process information data;
[0011] The overall technical plan layout plan of the EMU operation center is obtained according to the digital database of the EMU operation center.
[0012] In one embodiment, the physical model data and process information data are obtained based on the digital parameters of the simulation model of the motor vehicle operation, including:
[0013] Dividing the digital parameters of the simulation model of the motor vehicle operation into process physical model parameters and process information parameters;
[0014] Obtaining physical model data based on the process physical model parameters;
[0015] Process information data is obtained based on the process information parameters.
[0016] In one embodiment, the step of dividing the digital parameters of the motor vehicle operation simulation model into process physical model parameters and process information parameters includes:
[0017] According to the model information in the two-dimensional drawing and the process information required for simulation, the digital parameters of the simulation model of the motor vehicle operation are divided into process physical model parameters and process information parameters.
[0018] In one embodiment, obtaining physical model data based on the process physical model parameters includes:
[0019] Obtaining physical model data according to the process physical model parameters;
[0020] The physical model data is divided into EMU data, track data, switch data, building data, equipment data, connection data between physical modules and other data.
[0021] In one embodiment, the physical model data is divided into EMU data, track data, turnout data, building data, equipment data, connection data between physical modules and other data, including:
[0022] Based on the physical model data, obtain EMU data, track data, turnout data, building data, equipment data and custom data;
[0023] According to the relationship between the EMU data, track data, turnout data, house data and equipment data, connection data between the physical modules are constructed;
[0024] The custom data is regarded as other data.
[0025] In one embodiment, obtaining process information data based on the process information parameters includes:
[0026] According to the process information parameters, process information data is obtained;
[0027] The process information data is divided into process path data, operation procedure data, operation content data, operation time data, EMU running speed data, train receiving and dispatching time data and data associated with the physical model.
[0028] In one embodiment, the process information data is divided into process path data, operation process data, operation content data, operation time data, EMU running speed data, train sending and receiving time data and data associated with the physical model, including:
[0029] Based on the process information data, the process path data, operation procedure data, operation content data, operation time data, EMU running speed data and train receiving and dispatching time data are obtained;
[0030] According to the relationship between the process path data, operation procedure data, operation content data, operation time data, EMU running speed data, train sending and receiving time data and each of the physical models, the associated data with the physical model are constructed.
[0031] In addition, to achieve the above purpose, the present application also proposes a general diagram process database construction device for process design and simulation of a motor vehicle operation, the general diagram process database construction device for process design and simulation of a motor vehicle operation includes:
[0032] An acquisition module is used to acquire digital parameters of the simulation model of the motor vehicle operation;
[0033] A division module is used to obtain physical model data and process information data based on the digital parameters of the simulation model of the motor vehicle operation;
[0034] A construction module, used to construct a digital database of a motor vehicle operation center according to the physical model data and the process information data;
[0035] The output module is used to obtain the overall process plan of the EMU operation center according to the digital database of the EMU operation center.
[0036] In addition, to achieve the above-mentioned purpose, the present application also proposes a device for constructing a general drawing process database for process design and simulation of a motor vehicle operation institute, the device comprising: a memory, a processor, and a computer program stored on the memory and executable on the processor, the computer program being configured to implement the steps of the method for constructing a general drawing process database for process design and simulation of a motor vehicle operation institute as described above.
[0037] In addition, to achieve the above-mentioned purpose, the present application also proposes a storage medium, which is a computer-readable storage medium, and a computer program is stored on the storage medium. When the computer program is executed by the processor, the steps of the method for constructing a general drawing process database for process design and simulation of EMU operation are implemented as described above.
[0038] In addition, to achieve the above-mentioned purpose, the present application also provides a computer program product, which includes a computer program, and when the computer program is executed by a processor, it implements the steps of the method for constructing a general drawing process database for process design and simulation of EMU operation as described above.
[0039] One or more technical solutions proposed in this application have at least the following technical effects:
[0040] By dividing the digital parameters of the EMU operation simulation model into two categories: process physical model parameters and process information parameters, a digital database of the EMU operation center is constructed according to the process physical model parameters and process information parameters, so as to solve the problem that process simulation mainly relies on manual model construction and takes a long time to model. Compared with the existing technology, it provides data support for rapid modeling and intelligent modeling of process simulation, and assists designers in comparing and selecting design schemes for the EMU operation center. BRIEF DESCRIPTION OF THE DRAWINGS
[0041] The accompanying drawings, which are incorporated in and constitute a part of this specification, illustrate embodiments consistent with the present application and, together with the description, serve to explain the principles of the present application.
[0042] In order to more clearly illustrate the embodiments of the present application or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, for ordinary technicians in this field, other drawings can be obtained based on these drawings without paying any creative labor.
[0043] Figure 1 A flow chart of a method for constructing a general drawing process database for process design and simulation of a motor vehicle operation provided in the present application in Embodiment 1;
[0044] Figure 2 It is the overall framework of the master plan process database obtained based on the master plan process database construction method for process design and simulation of motor vehicle operation in the embodiment of the present application;
[0045] Figure 3 This is a process plan diagram of a certain motor vehicle operation center;
[0046] Figure 4 This is a schematic diagram of the module structure of a general diagram process database construction device for process design and simulation of a motor vehicle operation according to an embodiment of the present application;
[0047] Figure 5 This is a schematic diagram of the equipment structure of the hardware operating environment involved in the method for constructing a general drawing process database for process design and simulation of motor vehicle operation in an embodiment of the present application.
[0048] The purpose, features and advantages of this application will be further described in conjunction with the embodiments and with reference to the accompanying drawings. DETAILED DESCRIPTION
[0049] It should be understood that the specific embodiments described herein are only used to explain the technical solutions of the present application and are not used to limit the present application.
[0050] In order to better understand the technical solution of the present application, a detailed description will be given below in conjunction with the accompanying drawings and specific implementation methods.
[0051] The main solution of the embodiment of the present application is: to obtain the digital parameters of the simulation model of the EMU operation center; to obtain the physical model data and process information data based on the digital parameters of the simulation model of the EMU operation center; to construct a digital database of the EMU operation center according to the physical model data and the process information data; and to obtain the overall process plan of the EMU operation center according to the digital database of the EMU operation center.
[0052] At present, due to the time-consuming process simulation and other reasons, the overall process plan design of the EMU operation center mainly relies on the experience of designers and reviewers, and does not use simulation methods for quantitative analysis, making it difficult to determine the effective capacity of the designed EMU facilities.
[0053] The present application provides a solution, which divides the digital parameters of the EMU operation simulation model into two categories: process physical model parameters and process information parameters, and constructs a digital database of the EMU operation based on the process physical model parameters and process information parameters, thereby solving the problem that process simulation mainly relies on manual model building and the modeling time is long. Compared with the existing technology, it provides data support for rapid modeling and intelligent modeling of process simulation, and assists designers in comparing and selecting design plans for the EMU operation.
[0054] It should be noted that the execution subject of this embodiment can be a computing service device with data processing, network communication and program running functions, such as a tablet computer, a personal computer, a mobile phone, etc., or an electronic device capable of realizing the above functions, etc. The following takes a personal computer as an example to illustrate this embodiment and the following embodiments.
[0055] Based on this, the embodiment of the present application provides a method for constructing a general diagram process database for process design and simulation of a motor vehicle operation, referring to Figure 1 , Figure 1This is a flow chart of the first embodiment of the method for constructing a general drawing process database for process design and simulation of motor vehicle operation in this application.
[0056] In this embodiment, the method for constructing a general drawing process database for process design and simulation of a motor vehicle operation includes steps S10 to S40:
[0057] Step S10, obtaining digital parameters of the simulation model of the motor vehicle operation;
[0058] It should be noted that the digital parameters of the EMU operation simulation model include two categories: process physical model parameters and process information parameters. These parameters need to accurately simulate the actual operating environment of the EMU operation center in order to facilitate effective simulation analysis and research.
[0059] It is understandable that, since it is necessary to use it for rapid modeling in secondary development of simulation software, step S10 can simulate the actual operating environment of the EMU operation site, thereby ensuring the effectiveness and reliability of the overall process layout plan of the EMU operation site.
[0060] Step S20, obtaining physical model data and process information data based on the digital parameters of the simulation model of the motor vehicle operation;
[0061] It should be noted that the physical model data includes EMU data, track data, turnout data, building data, equipment data, and connection data between physical modules; the process information data includes process path data, operation procedure data, operation content data, operation time data, EMU running speed data, train sending and receiving time data, etc.
[0062] For example, to help understand the division of the database, please refer to 2, Figure 2 The invention provides an overall framework of a general drawing process database obtained based on a method for constructing a general drawing process database for process design and simulation of a motor vehicle operation station.
[0063] It can be understood that since the digital parameters of the simulation model of the EMU operation need to be divided into two parts, one part is the physical model data, and the other part is the process information data, step S20 is performed to avoid data mixing and difficulty in management, thereby more effectively organizing and managing the various data required in the simulation process, while ensuring the accuracy and practicality of the simulation model.
[0064] In a feasible implementation, step S10 may include steps A11 to A13:
[0065] Step A11, dividing the digital parameters of the simulation model of the motor vehicle operation into process physical model parameters and process information parameters according to the model information in the two-dimensional drawing and the process information required for the simulation;
[0066] It should be noted that the two-dimensional drawings are important documents that describe the design of each component and system of the EMU in detail. The process physical model parameters can be determined based on the model information. The process information required for simulation is the key data to ensure that the simulation model can accurately reflect the actual running and operating conditions of the EMU.
[0067] Step A12, obtaining physical model data based on the process physical model parameters;
[0068] The physical model data is divided into EMU data, track data, turnout data, building data, equipment data, connection data between physical modules and other data.
[0069] It should be noted that the EMU data mainly includes the EMU composition, number, and length; the track data mainly includes the track number, track name, track length, curve radius, track type, and whether it is meshed; the turnout data mainly includes the turnout number and turnout type; the house data mainly includes the house name, house size, EMU entry direction, EMU exit direction, and the track number contained in the house; the equipment data mainly includes the equipment name, the house name, and the equipment model; the connection data between the physical modules mainly describes how the above-mentioned independent physical models are connected; other categories provide storage functions for custom data, mainly including facility names, parameter names, and parameter values.
[0070] Step A13, obtaining process information data based on the process information parameters.
[0071] The process information data is divided into process path information data, operation procedure data, operation content data, operation time data, EMU running speed data, train receiving and dispatching time data and data associated with the physical model.
[0072] It should be noted that the process path information data includes the numbers of the physical models that the EMU passes through when it is dispatched in the EMU depot; the operation procedure data includes the sequence of work steps when the EMU moves along the process path; the operation content data describes the operation content information of a certain work step; the operation time data describes the time required to complete a certain operation content; the EMU running speed data describes the speed of the EMU passing through a certain physical model; the sending and receiving time data counts the time when the EMU enters or leaves the EMU depot; and the data associated with the physical model stores the process information numbers contained in each physical model.
[0073] In this embodiment, detailed division of physical model data and process information data is helpful for organizing and managing various required data.
[0074] The above is only a feasible implementation of step S20 provided in this embodiment, and this embodiment does not specifically limit the specific implementation of step S20.
[0075] Step S30, constructing a digital database of a motor vehicle operation center according to the physical model data and the process information data;
[0076] It should be noted that the digital database of the EMU operation center includes process physical model data and process information data, which is used to store the physical facility information and process information contained in the EMU operation center plan.
[0077] It is understandable that, since information resources need to be integrated, step S30 is performed to improve data consistency, and the database can integrate the scattered physical model data and process information data into a unified platform for easy management and access.
[0078] Step S40, obtaining the overall technical plan layout plan of the EMU operation center according to the EMU operation center digital database.
[0079] It should be noted that the overall layout plan of the EMU depot is a complex design process, which needs to consider many factors, including but not limited to the functional positioning, scale design and process flow of the EMU depot.
[0080] For example, Figure 3 , Figure 3 The following is a schematic diagram of the process plan of a certain motor vehicle operation center. The database constructed by this method can store the physical facility information and process information contained in the process general plan.
[0081] It is understandable that since it is inefficient to manually obtain the overall process layout plan of the EMU operation center, performing step S40 can avoid errors that may be caused by humans, thereby ensuring the scientificity, rationality and practicality of the design plan, while improving the efficiency and quality of design and operation.
[0082] The present embodiment provides a method for constructing a general drawing process database for process design and simulation of a motor vehicle operation center. By dividing the digital parameters of the simulation model of the motor vehicle operation center into two categories: process physical model parameters and process information parameters, a digital database of the motor vehicle operation center is constructed according to the process physical model parameters and the process information parameters, thereby solving the problem that process simulation mainly relies on manual model building and the modeling time is long. Compared with the existing technology, it provides data support for rapid modeling and intelligent modeling of process simulation, and assists designers in comparing and selecting design plans for the motor vehicle operation center.
[0083] It should be noted that the above examples are only used to understand the present application and do not constitute a limitation on the method of constructing a general drawing process database for process design and simulation of EMU operation in the present application. More simple transformations based on this technical concept are all within the scope of protection of the present application.
[0084] This application also provides a general diagram process database construction device for process design and simulation of motor vehicle operation, please refer to Figure 4 The general drawing process database construction device for process design and simulation of motor vehicle operation includes:
[0085] The acquisition module 10 is used to obtain digital parameters of the simulation model of the motor vehicle operation.
[0086] The division module 20 is used to obtain physical model data and process information data based on the digital parameters of the simulation model of the motor vehicle operation.
[0087] The construction module 30 is used to construct a digital database of the EMU operation center according to the physical model data and the process information data.
[0088] The output module 40 is used to obtain the overall process plan of the EMU operation center according to the digital database of the EMU operation center.
[0089] The general diagram process database construction device for process design and simulation of a motor vehicle operation center provided by the present application adopts the general diagram process database construction method for process design and simulation of a motor vehicle operation center in the above-mentioned embodiment, which can solve the technical problem of the construction of the general diagram process database for process design and simulation of a motor vehicle operation center. Compared with the prior art, the beneficial effects of the general diagram process database construction device for process design and simulation of a motor vehicle operation center provided by the present application are the same as the beneficial effects of the general diagram process database construction method for process design and simulation of a motor vehicle operation center provided by the above-mentioned embodiment, and the other technical features in the general diagram process database construction device for process design and simulation of a motor vehicle operation center are the same as the features disclosed in the above-mentioned embodiment method, which will not be repeated here.
[0090] In one embodiment, the division module 20 is further used to divide the digital parameters of the EMU operation simulation model into process physical model parameters and process information parameters; obtain physical model data based on the process physical model parameters; and obtain process information data based on the process information parameters.
[0091] In one embodiment, the division module 20 is further used to divide the digital parameters of the simulation model of the motor vehicle operation into process physical model parameters and process information parameters according to the model information in the two-dimensional drawing and the process information required for simulation.
[0092] In one embodiment, the division module 20 is also used to obtain physical model data based on the process physical model parameters; and divide the physical model data into EMU data, track data, turnout data, building data, equipment data, connection data between physical modules and other data.
[0093] In one embodiment, the construction module 30 is also used to obtain EMU data, track data, turnout data, house data, equipment data and custom data based on the physical model data; construct connection data between each physical module according to the relationship between the EMU data, track data, turnout data, house data and equipment data; and use the custom data as other data.
[0094] In one embodiment, the division module 20 is also used to obtain process information data based on process information parameters; divide the process information data into process path data, operation procedure data, operation content data, operation time data, EMU running speed data, train sending and receiving time data and data associated with the physical model.
[0095] In one embodiment, the construction module 30 is also used to obtain process path data, operation procedure data, operation content data, operation time data, EMU running speed data and train sending and receiving time data based on process information data; and construct associated data with the physical model according to the relationship between the process path data, operation procedure data, operation content data, operation time data, EMU running speed data, train sending and receiving time data and each of the physical models.
[0096] The present application provides a device for constructing a general drawing process database for process design and simulation of a motor vehicle operation center. The device for constructing a general drawing process database for process design and simulation of a motor vehicle operation center comprises: at least one processor; and a memory communicatively connected to the at least one processor; wherein the memory stores instructions executable by the at least one processor, and the instructions are executed by the at least one processor so that the at least one processor can execute the method for constructing a general drawing process database for process design and simulation of a motor vehicle operation center in the above-mentioned embodiment one.
[0097] Reference below Figure 5 , which shows a schematic diagram of the structure of a general diagram process database construction device for process design and simulation of a motor vehicle operation institute suitable for implementing the embodiment of the present application. The general diagram process database construction device for process design and simulation of a motor vehicle operation institute in the embodiment of the present application may include but is not limited to mobile terminals such as mobile phones, laptop computers, digital broadcast receivers, PDAs (Personal Digital Assistants), PADs (Portable Application Descriptions), PMPs (Portable Media Players), vehicle-mounted terminals (such as vehicle-mounted navigation terminals), etc., and fixed terminals such as digital TVs, desktop computers, etc. Figure 5The general diagram process database construction device used for process design and simulation of EMU operation is only an example and should not bring any limitation to the functions and scope of use of the embodiments of the present application.
[0098] like Figure 5 As shown, the equipment for constructing a general drawing process database for process design and simulation of a motor vehicle operation institute may include a processing device 1001 (such as a central processing unit, a graphics processing unit, etc.), which can perform various appropriate actions and processes according to a program stored in a read-only memory (ROM: Read Only Memory) 1002 or a program loaded from a storage device 1003 to a random access memory (RAM: Random Access Memory) 1004. Various programs and data required for the operation of the equipment for constructing a general drawing process database for process design and simulation of a motor vehicle operation institute are also stored in RAM1004. The processing device 1001, ROM1002 and RAM1004 are connected to each other via a bus 1005. An input / output (I / O) interface 1006 is also connected to the bus. Typically, the following systems can be connected to the I / O interface 1006: input devices 1007 including, for example, a touch screen, a touchpad, a keyboard, a mouse, an image sensor, a microphone, an accelerometer, a gyroscope, etc.; output devices 1008 including, for example, a liquid crystal display (LCD), a speaker, a vibrator, etc.; storage devices 1003 including, for example, a magnetic tape, a hard disk, etc.; and communication devices 1009. The communication device 1009 can allow the general drawing process database construction device for process design and simulation of the motor vehicle operation institute to communicate wirelessly or wired with other devices to exchange data. Although the figure shows a general drawing process database construction device for process design and simulation of the motor vehicle operation institute with various systems, it should be understood that it is not required to implement or have all the systems shown. More or fewer systems may be implemented or have instead.
[0099] In particular, according to the embodiments disclosed in the present application, the process described above with reference to the flowchart can be implemented as a computer software program. For example, the embodiments disclosed in the present application include a computer program product, which includes a computer program carried on a computer-readable medium, and the computer program includes a program code for executing the method shown in the flowchart. In such an embodiment, the computer program can be downloaded and installed from a network through a communication device, or installed from a storage device 1003, or installed from a ROM 1002. When the computer program is executed by the processing device 1001, the above-mentioned functions defined in the method of the embodiment disclosed in the present application are executed.
[0100] The equipment for constructing a master diagram process database for process design and simulation of a motor vehicle operation center provided by the present application adopts the method for constructing a master diagram process database for process design and simulation of a motor vehicle operation center in the above-mentioned embodiment, and can solve the technical problem of constructing a master diagram process database for process design and simulation of a motor vehicle operation center. Compared with the prior art, the beneficial effects of the equipment for constructing a master diagram process database for process design and simulation of a motor vehicle operation center provided by the present application are the same as the beneficial effects of the method for constructing a master diagram process database for process design and simulation of a motor vehicle operation center provided by the above-mentioned embodiment, and the other technical features in the equipment for constructing a master diagram process database for process design and simulation of a motor vehicle operation center are the same as the features disclosed in the method of the previous embodiment, and will not be repeated here.
[0101] It should be understood that the various parts disclosed in this application can be implemented by hardware, software, firmware or a combination thereof. In the description of the above embodiments, specific features, structures, materials or characteristics can be combined in any one or more embodiments or examples in a suitable manner.
[0102] The above is only a specific implementation of the present application, but the protection scope of the present application is not limited thereto. Any person skilled in the art who is familiar with the present technical field can easily think of changes or substitutions within the technical scope disclosed in the present application, which should be included in the protection scope of the present application. Therefore, the protection scope of the present application should be based on the protection scope of the claims.
[0103] The present application provides a computer-readable storage medium having computer-readable program instructions (i.e., computer programs) stored thereon, and the computer-readable program instructions are used to execute the method for constructing a general drawing process database for process design and simulation of a motor vehicle operation center in the above-mentioned embodiment.
[0104] The computer-readable storage medium provided in the present application may be, for example, a USB flash drive, but is not limited to electrical, magnetic, optical, electromagnetic, infrared, or semiconductor systems, systems or devices, or any combination of the above. More specific examples of computer-readable storage media may include, but are not limited to: an electrical connection with one or more wires, a portable computer disk, a hard disk, a random access memory (RAM), a read-only memory (ROM), an erasable programmable read-only memory (EPROM or flash memory), an optical fiber, a portable compact disk read-only memory (CD-ROM), an optical storage device, a magnetic storage device, or any suitable combination of the above. In this embodiment, the computer-readable storage medium may be any tangible medium containing or storing a program that can be used by or in combination with an instruction execution system, system or device. The program code contained on the computer-readable storage medium may be transmitted using any appropriate medium, including but not limited to: wires, optical cables, RF (Radio Frequency), etc., or any suitable combination of the above.
[0105] The above-mentioned computer-readable storage medium may be included in the equipment for constructing the general drawing process database for process design and simulation of motor vehicle operation; or it may exist independently without being assembled into the equipment.
[0106] The above-mentioned computer-readable storage medium carries one or more programs. When the above-mentioned one or more programs are executed by a device for constructing a general drawing process database for process design and simulation of a motor vehicle operation center, the device for constructing a general drawing process database for process design and simulation of a motor vehicle operation center: obtains digital parameters of a simulation model of a motor vehicle operation center; obtains physical model data and process information data based on the digital parameters of the simulation model of the motor vehicle operation center; constructs a digital database of the motor vehicle operation center according to the physical model data and the process information data; and obtains a general plan layout plan of the process of the motor vehicle operation center according to the digital database of the motor vehicle operation center.
[0107] Computer program code for performing the operations of the present application may be written in one or more programming languages or a combination thereof, including object-oriented programming languages such as Java, Smalltalk, C++, and conventional procedural programming languages such as "C" or similar programming languages. The program code may be executed entirely on the user's computer, partially on the user's computer, as a separate software package, partially on the user's computer and partially on a remote computer, or entirely on a remote computer or server. In the case of a remote computer, the remote computer may be connected to the user's computer through any type of network, including a local area network (LAN) or a wide area network (WAN), or may be connected to an external computer (e.g., via the Internet using an Internet service provider).
[0108] The flow chart and block diagram in the accompanying drawings illustrate the possible architecture, function and operation of the system, method and computer program product according to various embodiments of the present application. In this regard, each square box in the flow chart or block diagram can represent a module, a program segment or a part of a code, and the module, the program segment or a part of the code contains one or more executable instructions for realizing the specified logical function. It should also be noted that in some alternative implementations, the functions marked in the square box can also occur in a sequence different from that marked in the accompanying drawings. For example, two square boxes represented in succession can actually be executed substantially in parallel, and they can sometimes be executed in the opposite order, depending on the functions involved. It should also be noted that each square box in the block diagram and / or flow chart, and the combination of the square boxes in the block diagram and / or flow chart can be implemented with a dedicated hardware-based system that performs a specified function or operation, or can be implemented with a combination of dedicated hardware and computer instructions.
[0109] The modules involved in the embodiments described in this application may be implemented by software or hardware, wherein the name of the module does not constitute a limitation on the unit itself in some cases.
[0110] The readable storage medium provided by the present application is a computer-readable storage medium, which stores computer-readable program instructions (i.e., computer programs) for executing the above-mentioned method for constructing a master diagram process database for process design and simulation of a motor vehicle operation institute, and can solve the technical problem of constructing a master diagram process database for process design and simulation of a motor vehicle operation institute. Compared with the prior art, the beneficial effects of the computer-readable storage medium provided by the present application are the same as the beneficial effects of the method for constructing a master diagram process database for process design and simulation of a motor vehicle operation institute provided by the above-mentioned embodiment, and will not be repeated here.
[0111] The present application also provides a computer program product, including a computer program, which, when executed by a processor, implements the steps of the method for constructing a general drawing process database for process design and simulation of a motor vehicle operation as described above.
[0112] The computer program product provided by the present application can solve the technical problem of constructing a general diagram process database for process design and simulation of a motor vehicle operation. Compared with the prior art, the beneficial effects of the computer program product provided by the present application are the same as the beneficial effects of the method for constructing a general diagram process database for process design and simulation of a motor vehicle operation provided by the above embodiment, and will not be repeated here.
[0113] The above descriptions are only some embodiments of the present application, and are not intended to limit the patent scope of the present application. All equivalent structural changes made using the contents of the present application specification and drawings under the technical concept of the present application, or direct / indirect applications in other related technical fields are included in the patent protection scope of the present application.
Claims
1. A method for constructing a general drawing process database for process design and simulation of a motor vehicle operation, characterized in that: The method includes: Obtain digital parameters of the simulation model of the EMU operation; Based on the digital parameters of the simulation model of the motor vehicle operation, physical model data and process information data are obtained; Constructing a digital database of a motor vehicle operation center according to the physical model data and the process information data; The overall technical plan layout plan of the EMU operation center is obtained according to the digital database of the EMU operation center.
2. The method according to claim 1, characterized in that The physical model data and process information data are obtained based on the digital parameters of the simulation model of the motor vehicle operation, including: Dividing the digital parameters of the simulation model of the motor vehicle operation into process physical model parameters and process information parameters; Obtaining physical model data based on the process physical model parameters; Process information data is obtained based on the process information parameters.
3. The method according to claim 2, characterized in that The step of dividing the digital parameters of the simulation model of the motor vehicle operation into process physical model parameters and process information parameters includes: According to the model information in the two-dimensional drawing and the process information required for simulation, the digital parameters of the simulation model of the motor vehicle operation are divided into process physical model parameters and process information parameters.
4. The method according to claim 2, characterized in that The obtaining of physical model data based on the process physical model parameters includes: Obtaining physical model data according to the process physical model parameters; The physical model data is divided into EMU data, track data, switch data, building data, equipment data, connection data between physical modules and other data.
5. The method according to claim 4, characterized in that The physical model data is divided into EMU data, track data, turnout data, building data, equipment data, connection data between physical modules and other data, including: Based on the physical model data, obtain EMU data, track data, turnout data, building data, equipment data and custom data; According to the relationship between the EMU data, track data, turnout data, house data and equipment data, connection data between the physical modules are constructed; The custom data is regarded as other data.
6. The method according to claim 2, characterized in that The obtaining of process information data based on the process information parameters includes: According to the process information parameters, process information data is obtained; The process information data is divided into process path data, operation procedure data, operation content data, operation time data, EMU running speed data, train receiving and dispatching time data and data associated with the physical model.
7. The method according to claim 6, characterized in that The process information data is divided into process path data, operation process data, operation content data, operation time data, train speed data, train dispatching and receiving time data and data associated with the physical model, including: Based on the process information data, the process path data, operation procedure data, operation content data, operation time data, EMU running speed data and train receiving and dispatching time data are obtained; According to the relationship between the process path data, operation procedure data, operation content data, operation time data, EMU running speed data, train sending and receiving time data and each of the physical models, the associated data with the physical model are constructed.
8. A general drawing process database construction device for process design and simulation of motor vehicle operation, characterized in that: The device comprises: An acquisition module is used to acquire digital parameters of the simulation model of the motor vehicle operation; A division module is used to obtain physical model data and process information data based on the digital parameters of the simulation model of the motor vehicle operation; A construction module, used to construct a digital database of a motor vehicle operation center according to the physical model data and the process information data; The output module is used to obtain the overall process plan of the EMU operation center according to the digital database of the EMU operation center.
9. A general diagram process database construction device for process design and simulation of motor vehicle operation, characterized in that: The device includes: a memory, a processor, and a computer program stored in the memory and executable on the processor, wherein the computer program is configured to implement the steps of a method for constructing a general drawing process database for process design and simulation of a motor vehicle operation center as described in any one of claims 1 to 7.
10. A storage medium, characterized in that: The storage medium is a computer-readable storage medium, and a computer program is stored on the storage medium. When the computer program is executed by a processor, the steps of the method for constructing a general drawing process database for process design and simulation of a motor vehicle operation center as described in any one of claims 1 to 7 are implemented.