Atomization equipment, temperature control method of atomization equipment and related device

By introducing a dynamic control method of target temperature curve and critical temperature difference in the atomization equipment, the problem of equipment temperature instability is solved, the function of rapid heating or cooling is realized, and the user experience is improved.

CN119791340APending Publication Date: 2025-04-11SHENZHEN GEEKVAPE TECH CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202510027308.3
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2025-01-07
Publication Date
2025-04-11

AI Technical Summary

Technical Problem

When existing atomization equipment requires a significant change in temperature in a short time, the temperature is unstable, affecting the user's user experience.

Method used

By introducing heating units, storage units, temperature control units and logic units into the atomization equipment, the critical temperature difference value is dynamically changed to achieve accurate control of the temperature of the heating body. The specific method includes determining the target temperature of the heating element according to the target temperature curve, obtaining the actual temperature, and determining whether to calculate the duty cycle to control the heating power based on the critical temperature difference value.

Benefits of technology

It improves the stability of the temperature of the atomization equipment, enhances the flexibility of the equipment, can quickly increase or cool down, and improves the user experience.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119791340A_ABST
    Figure CN119791340A_ABST
Patent Text Reader

Abstract

The invention discloses atomization equipment, a temperature control method of the atomization equipment and a related device, and belongs to the technical field of atomization equipment. The atomization equipment comprises a heating unit which comprises at least one heating body. And the storage unit is used for storing one or more target temperature curves. And the temperature control unit is used for calculating the duty ratio so as to control the heating power of the heating body based on the duty ratio. The logic unit is used for calling the temperature control unit at a certain frequency and determining whether the temperature control unit needs to calculate the duty ratio or not when the temperature control unit is called, that is, the target temperature of the corresponding heating body at the current time point is determined according to the target temperature curve, and the actual temperature of the corresponding heating body at the current time point is obtained; and based on the target temperature, the actual temperature and the first critical temperature difference value of the current time point, whether the temperature control unit needs to calculate the duty ratio is determined. By dynamically changing the critical temperature difference value, the use experience of a user on the atomization equipment can be improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of atomizing equipment, and in particular to an atomizing equipment, a temperature control method of the atomizing equipment and related devices. Background Art

[0002] Temperature control is a crucial part of atomizer equipment. Current atomizer equipment uses a PID controller (Proportional Integration Differentiation) to achieve precise temperature control. However, since various parameter values ​​cannot be changed during the heating process of the atomizer equipment, when the atomizer equipment needs to change the temperature significantly in a short period of time, the temperature of the atomizer equipment may become unstable, seriously affecting the user experience. Summary of the invention

[0003] The present application provides an atomization device, a temperature control method of the atomization device and a related device, which can dynamically change the critical temperature difference value and improve the user experience of the atomization device. The technical solution is as follows:

[0004] In one aspect, an atomization device is provided, the atomization device comprising:

[0005] A heating unit, wherein the heating unit comprises at least one heating element, and when a plurality of heating elements are included, each heating element is driven independently;

[0006] A storage unit, the storage unit is used to store one or more target temperature curves, at least one of the heating elements has a corresponding target temperature curve, the target temperature curve is used to indicate the relationship between the heating time and the temperature of the corresponding heating element;

[0007] a temperature control unit, the temperature control unit being used to calculate a duty cycle so as to control the heating power of the heating element based on the duty cycle;

[0008] A logic unit, the logic unit is used to call the temperature control unit at a certain frequency, and determine whether the temperature control unit needs to calculate the duty cycle when calling the temperature control unit, and the logic unit determines whether the temperature control unit needs to calculate the duty cycle when calling the temperature control unit, including:

[0009] Determine the target temperature of the corresponding heating element at the current time point according to the target temperature curve, and obtain the actual temperature of the corresponding heating element at the current time point; determine whether the temperature control unit needs to calculate the duty cycle based on the target temperature at the current time point, the actual temperature at the current time point, and the first critical temperature difference value; wherein the first critical temperature difference value is the critical temperature difference value corresponding to the current time point, and the first critical temperature difference is determined at the previous time point based on the predicted temperature at the current time point and the target temperature at the current time point; the predicted temperature at the current time point is the temperature at the current time point obtained when the temperature control unit controls the corresponding heating element to generate heat with the heating power at the previous time point starting from the previous time point, and reaches the current time point; the previous time point and the current time point are separated by a preset time period.

[0010] Optionally, the logic unit is specifically used for:

[0011] Calculating the difference between the target temperature at the current time point and the actual temperature at the current time point;

[0012] If the difference between the target temperature at the current time point and the actual temperature at the current time point is greater than the first critical temperature difference, it is determined that the temperature control module does not need to calculate the duty cycle, and the temperature control unit controls the corresponding heating element to output full power for heating, so that the corresponding heating element can heat up quickly.

[0013] Optionally, if the difference between the target temperature at the current time point and the actual temperature at the current time point is not greater than the critical temperature difference value, the logic unit is further configured to:

[0014] Determine whether the difference between the target temperature at the current time point and the actual temperature at the current time point is less than the inverse of the first critical temperature difference value;

[0015] If the difference between the target temperature at the current time point and the actual temperature at the current time point is less than the inverse of the first critical temperature difference value, it is determined that the temperature control module does not need to calculate the duty cycle, and the temperature control unit controls the corresponding heating element not to generate heat, so that the corresponding heating element is cooled down quickly;

[0016] If the difference between the target temperature at the current time point and the actual temperature at the current time point is greater than or equal to the inverse of the first critical temperature difference value, and less than or equal to the first critical temperature difference value, it is determined that the temperature control module needs to calculate the duty cycle, and the temperature control module controls the corresponding heating power of the heating element based on the calculated duty cycle.

[0017] Optionally, the logic unit is further used for:

[0018] Determine a target temperature at a next time point according to the target temperature curve, wherein the current time point and the next time point are separated by a preset time period;

[0019] Determine the predicted temperature at the next time point according to the actual temperature at the current time point and the heating power corresponding to the current time point;

[0020] Determining a second critical temperature difference value corresponding to the next time point according to the target temperature at the next time point and the predicted temperature at the next time point;

[0021] When the difference between the target temperature at the next time point and the actual temperature at the next time point is greater than or equal to the inverse of the second critical temperature difference value, and less than or equal to the second critical temperature difference value, the temperature control unit is controlled to calculate the duty cycle to stabilize the temperature of the corresponding heating element.

[0022] Optionally, the temperature control unit is further used for:

[0023] When the corresponding heating element is in a temperature rising state, the product of the first duty cycle and the ratio of the second critical temperature difference value to the first critical temperature difference value is determined as the target duty cycle, wherein the first duty cycle is the duty cycle corresponding to the heating power of the corresponding heating element currently controlled by the temperature control unit to generate heat;

[0024] When the corresponding heating element is not in a temperature rising state, the product of the first duty cycle and the ratio of the first critical temperature difference value to the second critical temperature difference value is determined as the target duty cycle;

[0025] The heating power of the corresponding heating element is controlled based on the target duty cycle.

[0026] Optionally, the storage unit is further used to store a relative change relationship, wherein the relative change relationship is used to indicate a relative change in the resistance of the heating element when the temperature of the heating element changes by one degree Celsius;

[0027] The logic unit is also used to determine the actual temperature of the corresponding heating element at the current time point based on the resistance value of the corresponding heating element at the current time point, the initial resistance value of the corresponding heating element, the relative change relationship and the ambient temperature at the current time point.

[0028] On the other hand, a temperature control method of an atomizing device is provided, wherein the atomizing device comprises a heating unit, a temperature control unit and a logic unit, wherein the heating unit comprises at least one heating element, and at least one of the heating elements has a corresponding target temperature curve, wherein the target temperature curve is used to indicate the relationship between the heating time and the temperature of the corresponding heating element; the method is applied to the logic unit; the method comprises:

[0029] calling the temperature control unit;

[0030] Determine the target temperature of the corresponding heating element at the current time point according to the target temperature curve;

[0031] Obtaining the actual temperature of the corresponding heating element at the current time point;

[0032] Based on the target temperature at the current time point, the actual temperature at the current time point, and a first critical temperature difference value, determine whether the temperature control unit needs to calculate the duty cycle; wherein the first critical temperature difference value is the critical temperature difference value corresponding to the current time point, and the first critical temperature difference value is determined at the previous time point based on the predicted temperature at the current time point and the target temperature at the current time point; the predicted temperature at the current time point is the temperature at the current time point obtained when the temperature control unit controls the corresponding heating element to generate heat with the heating power at the previous time point starting from the previous time point, and reaches the current time point; the previous time point and the current time point are separated by a preset time period.

[0033] On the other hand, a temperature control device for an atomizing device is provided, characterized in that the device comprises:

[0034] A calling module is used to call the temperature control unit;

[0035] A first determination module, used to determine the target temperature of the corresponding heating element at a current time point according to the target temperature curve;

[0036] An acquisition module, used for acquiring the actual temperature of the corresponding heating element at the current time point;

[0037] The second determination module is used to determine whether the temperature control unit needs to calculate the duty cycle based on the target temperature at the current time point, the actual temperature at the current time point, and a first critical temperature difference value; wherein the first critical temperature difference value is the critical temperature difference value corresponding to the current time point, and the first critical temperature difference value is determined at the previous time point based on the predicted temperature at the current time point and the target temperature at the current time point; the predicted temperature at the current time point is the temperature at the current time point obtained when the temperature control unit controls the corresponding heating element to generate heat with the heating power corresponding to the previous time point starting from the previous time point; the previous time point and the current time point are separated by a preset time period.

[0038] On the other hand, a computer-readable storage medium is provided, in which a computer program is stored. The computer program can be executed by a processor to implement the steps of the temperature control method of the atomization device described above.

[0039] On the other hand, a computer program product comprising instructions is provided. When the instructions are executed on a computer, the computer executes the steps of the temperature control method of the atomizing device described above.

[0040] The technical solution provided by this application can at least bring the following beneficial effects:

[0041] The logic unit in the embodiment of the present application can predict in advance the difference between the actual temperature of the heating element in the atomization device and the target temperature, and dynamically determine the corresponding critical temperature difference value based on this, so that the actual temperature of the heating element can be close to the target temperature, thereby stabilizing the atomization device and further improving the user experience of the atomization device; moreover, the logic unit calls the temperature control unit at a certain frequency, and determines whether the temperature control unit needs to calculate the duty cycle when calling the temperature control unit, that is, whether the duty cycle needs to be involved in the calculation, which can improve the flexibility of the atomization device. BRIEF DESCRIPTION OF THE DRAWINGS

[0042] Figure 1 A schematic diagram of the structure of an atomization device provided in an embodiment of the present application;

[0043] Figure 2 A flow chart of a temperature control method for an atomization device provided in an embodiment of the present application;

[0044] Figure 3 A schematic diagram of a temperature control device for an atomization device provided in an embodiment of the present application. DETAILED DESCRIPTION

[0045] The present invention is further described in detail below by specific embodiments in conjunction with the accompanying drawings. Wherein similar elements in different embodiments adopt associated similar element numbers. In the following embodiments, many detailed descriptions are for making the present application better understood. However, those skilled in the art can easily recognize that some features can be omitted in different situations, or can be replaced by other elements, materials, methods. In some cases, some operations related to the present application are not shown or described in the specification, this is to avoid the core part of the present application being overwhelmed by too much description, and for those skilled in the art, it is not necessary to describe these related operations in detail, and they can fully understand the related operations according to the description in the specification and the general technical knowledge in the art.

[0046] In addition, the features, operations or characteristics described in the specification can be combined in any appropriate manner to form various implementations. At the same time, the steps or actions in the method description can also be interchanged or adjusted in a manner that is obvious to those skilled in the art. Therefore, the various sequences in the specification and the drawings are only for the purpose of clearly describing a certain embodiment and are not meant to be a required sequence, unless otherwise specified that a certain sequence must be followed.

[0047] The serial numbers of the components in this document, such as "first", "second", etc., are only used to distinguish the objects described and do not have any order or technical meaning. The "connection" and "coupling" mentioned in this application, unless otherwise specified, include direct and indirect connections (couplings).

[0048] Before explaining in detail the atomization device and the temperature control method of the atomization device provided in the present application, the application scenarios involved in the embodiments of the present application are first introduced.

[0049] The current atomizer equipment uses a PID controller to achieve precise temperature control, that is, the PID controller is used to change the heating power of the atomizer equipment so that the actual temperature of the atomizer equipment is stabilized at the target temperature. However, during the heating operation of the atomizer equipment, the values ​​of various parameters such as P (proportional coefficient), I (integral time), and D (differential time) cannot be changed, and the temperature difference critical value is pre-set and cannot be changed. Therefore, the heating rate or cooling rate of the atomizer equipment during use cannot be changed, thereby reducing the heating rate or cooling rate of the atomizer equipment. Moreover, when the atomizer equipment needs to change the temperature significantly in a short period of time, the temperature of the atomizer equipment may be unstable, which seriously affects the user experience.

[0050] Based on this, an embodiment of the present application provides an atomization device, which can predict in advance the difference between the actual temperature of the heating element in the atomization device and the target temperature, and dynamically determine the corresponding critical temperature difference value based on this, so as to reduce the difference between the actual temperature of the heating element and the target temperature; in addition, it can also flexibly determine whether the temperature control unit is needed to calculate the duty cycle, thereby enabling the atomization device to quickly heat up when it needs to heat up, and quickly cool down when it needs to cool down.

[0051] Next, the atomization equipment provided in the embodiment of the present application is introduced in detail.

[0052] Please refer to Figure 1 , Figure 1It is a structural schematic diagram of an atomization device provided in an embodiment of the present application. The atomization device includes: a heating unit 1, the heating unit 1 includes at least one heating element 11, when multiple heating elements 11 are included, each heating element 11 is driven independently; the heating element 11 is used to generate heat so that the atomization device works. A storage unit 2, the storage unit 2 is used to store one or more target temperature curves, each of the at least one heating element 11 has a corresponding target temperature curve, and the target temperature curve is used to indicate the relationship between the heating time and the temperature of the corresponding heating element 11. A temperature control unit 3, the temperature control unit 3 is used to calculate the duty cycle to control the heating power of the heating element 11 based on the duty cycle. The logic unit 4 is used to call the temperature control unit 3 at a certain frequency, and determine whether the temperature control unit 3 needs to calculate the duty cycle when calling the temperature control unit 3. The specific process is: determine the target temperature of the corresponding heating element 11 at the current time point according to the target temperature curve, and obtain the actual temperature of the corresponding heating element 11 at the current time point; based on the target temperature at the current time point, the actual temperature at the current time point, and the first critical temperature difference value, determine whether the temperature control unit 3 needs to calculate the duty cycle; wherein the first critical temperature difference value is the critical temperature difference value corresponding to the current time point, and the first critical temperature difference value is determined at the previous time point based on the predicted temperature at the current time point and the target temperature at the current time point; the predicted temperature at the current time point is the temperature at the current time point obtained from the previous time point when the temperature control unit 3 controls the corresponding heating element 11 to generate heat with the heating power at the previous time point, and the previous time point and the current time point are separated by a preset time period.

[0053] That is, the number of target temperature curves stored in the storage unit 2 corresponds to the at least one heating element 11 included in the heating unit 1, that is, each of the at least one heating element 11 has a corresponding target temperature curve. For example, if the heating unit includes two heating elements, namely, heating element X and heating element Y, and heating element X has a target temperature curve X, and heating element Y has a target temperature curve Y, then two target temperature curves, namely, target temperature curve X and target temperature curve Y, are stored in the storage unit 2.

[0054] And in the case where the heating unit 1 includes multiple heating elements 11, each of the multiple heating elements 11 is driven independently, that is, whether each heating element 11 performs heating work and the temperature to be reached may be the same or different, so it can be seen that the target temperature curves corresponding to the multiple heating elements 11 may be the same or different. As an example, the heating unit 1 is divided into an upper section and a lower section, that is, it has two heating elements 11, and the upper section and the lower section have different corresponding temperatures at different heating time points, so it can be seen that the target temperature curve of the upper section is different from the target temperature curve corresponding to the lower section.

[0055] In some embodiments, at least one target temperature curve in the storage unit 2 is pre-set in the storage unit 2 by a technician before the atomization device leaves the factory, so that in subsequent processes, relevant operations can be performed directly according to the stored target temperature curve.

[0056] It should be noted that the above description is based on the assumption that the at least one temperature curve is pre-set by a technician, or, in application, the target temperature curve may also be determined by other methods, which is not limited in the embodiments of the present application.

[0057] In addition, in some embodiments, the temperature control unit 3 may be a PID controller. The PID controller is composed of a proportional unit (P), an integral unit (I) and a differential unit (D), which can calculate the duty cycle and control the heating power of the heating element 11 based on the calculated duty cycle, so that the heating element 11 can achieve the effect of heating, cooling or stabilizing the temperature.

[0058] It should be noted that the above description is based on the temperature control unit 3 being a PID controller, or, in application, the temperature control unit 3 may also be other devices capable of controlling temperature, which is not limited in the embodiments of the present application.

[0059] The logic unit 4 can call the temperature control unit 3 at a certain frequency, for example, the logic unit 4 calls the temperature control unit 3 once every 100 milliseconds. And each time the temperature control unit 3 is called, it is determined whether the temperature control unit 3 needs to calculate the duty cycle, so as to quickly heat up or cool down the heating element 11.

[0060] Based on the above description, it can be known that the target temperature curve is used to indicate the relationship between the time and temperature of the corresponding heating element 11. Therefore, the logic unit can determine the target temperature of the corresponding heating element 11 at the current time point according to the target temperature curve. For example, the heating element 11 has been heated for a total of 25 seconds from the beginning of heating to the present, that is, the current time point is 25 seconds. Therefore, the logic unit 4 can search the target temperature corresponding to the heating time of 25 seconds in the target temperature curve.

[0061] It should be noted that the heating time may be timed by a timer included in the atomization device, or by the logic unit 4, which is not limited in the embodiment of the present application.

[0062] Continuing with the above description, the logic unit 4 can also obtain the actual temperature of the corresponding heating element 11 at the current time point, so that in the subsequent process, according to the target temperature at the current time point, the actual temperature at the current time point and the first critical temperature difference value, it is determined whether the temperature control unit 2 needs to calculate the duty cycle for the temperature control unit 3 this time.

[0063] Among them, the first critical temperature difference value is determined at the previous time point based on the predicted temperature at the current time point and the target temperature at the current time point, and the predicted temperature at the current time point is the temperature at the current time point obtained when the temperature control unit 3 controls the corresponding heating element 11 to generate heat with the heating power at the previous time point from the previous time point to the current time point. It can be seen that the actual temperature at the current time point can be predicted in advance at the previous time point based on the actual temperature and heating power at the previous time point, and the first critical temperature difference value corresponding to the current time point is determined at the previous time point based on the predicted temperature at the current time point (i.e., the predicted temperature at the current time point) and the target temperature at the current time point, so that when the heating time of the corresponding heating element 11 is from the previous time point to the current time point, the actual temperature at the current time point can be close to the target temperature at the current time point.

[0064] Moreover, the previous time point and the current time point are separated by a preset time period. For example, assuming that the preset time period is 3 seconds, the previous time point can be (t-3) seconds, and the current time point can be t seconds. For example, the previous time point is 22 seconds, and the current time point is 25 seconds.

[0065] Continuing with the above example, assuming that the heating time is (t-3) seconds, and the heating power at (t-3) seconds is V, and the temperature of the heating element is A, the logic unit 4 can predict the actual temperature of the heating element at t seconds based on the heating power V and the temperature A at (t-3) seconds, and then obtain the target temperature of the heating element at t seconds according to the target temperature curve, so as to determine the critical temperature difference corresponding to t seconds based on the predicted actual temperature and target temperature at t seconds, so as to ensure that during the heating process of the heating element, when the heating time point is t seconds, the actual temperature of the heating element can be close to the target temperature, thereby improving the user experience of the atomization device.

[0066] In some embodiments, the logic unit 4 can also calculate the difference between the target temperature at the current time point and the actual temperature at the current time point; if the difference between the target temperature at the current time point and the actual temperature at the current time point is greater than the first critical temperature difference, it is determined that the temperature control module 3 does not need to calculate the duty cycle, and the temperature control unit 3 controls the corresponding heating element 11 to output full power for heating, so that the corresponding heating element 11 can heat up quickly.

[0067] After obtaining the target temperature at the current time point and the actual temperature at the current time point, the logic unit 4 can also determine the difference between the target temperature and the actual temperature, and determine whether the temperature control module 3 needs to calculate the duty cycle based on the determined difference and the first critical temperature difference.

[0068] That is to say, if the difference between the target temperature at the current time point and the actual temperature at the current time point is greater than the first critical temperature difference, it means that the actual temperature at the current time point is far from the target temperature at the current time point, and the corresponding heating element 11 needs to be heated at full power so that the actual temperature of the heating element 11 can be quickly raised to the target temperature in the subsequent process. In the above case, the temperature control module 3 does not need to calculate the duty cycle, but only needs to control the corresponding heating element 11 to output heating at full power, so that the corresponding heating element 11 can quickly heat up.

[0069] In addition, in some embodiments, if the difference between the target temperature at the current time point and the actual temperature at the current time point is not greater than the critical temperature difference value, the logic unit 4 can also determine whether the difference between the target temperature at the current time point and the actual temperature at the current time point is less than the inverse of the first critical temperature difference value; if the difference between the target temperature at the current time point and the actual temperature at the current time point is less than the inverse of the first critical temperature difference value, it is determined that the temperature control module 3 does not need to calculate the duty cycle, and the temperature control unit 3 controls the corresponding heating element 11 not to generate heat, so that the corresponding heating element 11 can be cooled down quickly; if the difference between the target temperature at the current time point and the actual temperature at the current time point is greater than or equal to the inverse of the first critical temperature difference value, and is less than or equal to the first critical temperature difference value, it is determined that the temperature control module 3 needs to calculate the duty cycle, and the temperature control module 3 controls the heating power of the corresponding heating element 11 based on the calculated duty cycle.

[0070] That is to say, if the difference between the target temperature at the current time point and the actual temperature at the current time point is not greater than the critical temperature difference value, the logic unit 4 also needs to determine whether the temperature difference between the target temperature at the current time point and the actual temperature at the current time point is less than the inverse of the first critical temperature difference value, so as to determine whether the actual temperature at the current time point exceeds the target temperature at the current time point by too much, so as to determine whether the corresponding heating element 11 needs to be cooled down quickly.

[0071] If the difference between the target temperature at the current time point and the actual temperature at the current time point is less than the inverse of the first critical temperature difference value, it means that the actual temperature at the current time point exceeds the target temperature at the current time point by too much, and the corresponding heating element needs to be stopped from generating heat, that is, zero power output, so that the actual temperature of the heating element 11 can be quickly reduced to the target temperature in the subsequent process. In the above case, the temperature control module 3 does not need to calculate the duty cycle, but only needs to control the corresponding heating element 11 to stop generating heat, so that the corresponding heating element 11 can be quickly cooled down.

[0072] If the difference between the target temperature at the current time point and the actual temperature at the current time point is greater than or equal to the inverse of the first critical temperature difference value, and is less than or equal to the first critical temperature difference value, that is, the difference between the actual temperature at the current time point and the target temperature at the current time point is not less than the inverse of the first critical temperature difference value, and is not greater than the first critical temperature difference value, it means that the current temperature control unit 3 can intervene in the calculation, so that the actual temperature of the heating element 11 is stabilized at the target temperature. That is to say, in the above case, the logic unit 4 determines that the temperature control module 3 needs to calculate the duty cycle, and after the temperature control module 3 calculates the duty cycle, the corresponding heating power of the heating element 11 is controlled based on the duty cycle, so as to stabilize the actual temperature of the heating element 11.

[0073] In some embodiments, the logic unit 4 can also determine the target temperature at the next time point based on the target temperature curve, and the current time point is separated from the next time point by a preset time period; determine the predicted temperature at the next time point based on the actual temperature at the current time point and the heating power corresponding to the current time point; and determine the second critical temperature difference value corresponding to the next time point based on the target temperature at the next time point and the predicted temperature at the next time point; when the difference between the target temperature at the next time point and the actual temperature at the next time point is greater than or equal to the inverse of the second critical temperature difference value, and is less than or equal to the second critical temperature difference value, the temperature control unit 3 is controlled to calculate the duty cycle to stabilize the temperature of the heating element 11.

[0074] That is to say, the logic unit 4 can also predict the actual temperature at the next time point based on the actual temperature and heating power at the current time point. That is, starting from the current time point, the temperature control unit controls the corresponding heating element to generate heat based on the actual temperature at the current time point and the heating power corresponding to the current time point, and when it reaches the next time point, the predicted temperature at the next time point is determined.

[0075] Then, the current time point determines the second critical temperature difference value corresponding to the next time point based on the predicted temperature at the next time point and the target temperature at the next time point, so that when the heating time of the corresponding heating element 11 is from the current time point to the next time point, the actual temperature at the next time point can be close to the target temperature at the next time point.

[0076] Moreover, the current time point and the next time point are separated by a preset time period. For example, assuming that the preset time period is 3 seconds, the current time point may be t seconds, and the next time point may be (t+3) seconds. For example, the current time point is 25 seconds, and the next time point is 28 seconds.

[0077] Continuing with the above example, assuming that the heating time is t seconds, and the heating power at t seconds is U, and the temperature of the heating element is B, the logic unit 4 can predict the actual temperature of the heating element at (t+3) seconds based on the heating power U and the temperature B at t seconds, and obtain the target temperature of the heating element at (t+3) seconds according to the target temperature curve, so as to determine the critical temperature difference corresponding to (t+3) seconds based on the actual temperature and target temperature predicted at (t+3) seconds, so as to ensure that during the heating process of the heating element, when the heating time point is (t+3) seconds, the actual temperature of the heating element can be close to the target temperature, thereby improving the user experience of the atomization device.

[0078] Continuing with the above description, at the next time point, the logic unit 3 can also determine that the temperature control unit 3 needs to calculate the duty cycle when the difference between the target temperature at the next time point and the actual temperature at the next time point is greater than or equal to the inverse of the second critical temperature difference value, and less than or equal to the second critical temperature difference value. In other words, the temperature control unit 3 can intervene in the calculation, that is, the temperature control unit 3 needs to calculate the duty cycle, and after calculating the duty cycle, control the heating power of the corresponding heating element 11 based on the duty cycle, so that the actual temperature of the heating element 11 is stabilized at the target temperature.

[0079] In some embodiments, when the logic unit 4 determines that the temperature control unit 3 needs to calculate the duty cycle, the temperature control unit 3 can also determine the target duty cycle by multiplying the first duty cycle by the ratio of the second critical temperature difference value to the first critical temperature difference value when the corresponding heating element 11 is in a heating state, wherein the first duty cycle is the duty cycle corresponding to the heating power of the corresponding heating element 11 currently controlled by the temperature control unit 3 to generate heat; when the heating element 11 is not in a heating state, the target duty cycle is determined by multiplying the first duty cycle by the ratio of the first critical temperature difference value to the second critical temperature difference value; and the heating power of the corresponding heating element 11 is controlled based on the target duty cycle.

[0080] For example, when the corresponding heating element 11 is in a temperature rising state, the target duty cycle can be determined according to the following formula (1):

[0081]

[0082] Wherein, A1 represents the target duty cycle, A0 represents the first duty cycle, T1 represents the first temperature difference critical value, and T2 represents the second critical temperature difference value.

[0083] As another example, when the corresponding heating element 11 is in a cooling state, the target duty cycle can be determined according to the following formula (2):

[0084]

[0085] It should be noted that the above-mentioned method for determining the target duty cycle is for illustration only. In application, the target duty cycle may also be determined by other methods, which is not limited in the embodiments of the present application.

[0086] In some embodiments, the logic unit 4 can determine whether the corresponding heating element 11 is in a heating state or a cooling state based on the size relationship between the target temperature at the current time point and the target temperature at the previous time point, and send the determined state to the temperature control unit 3, so that the temperature control unit 3 obtains the current state of the heating element 11 and determines the target duty cycle based on the state. Alternatively, the temperature control unit 3 can determine whether the corresponding heating element 11 is in a heating state or a cooling state based on the size relationship of the duty cycle calculated each time. This embodiment of the application is not limited to this.

[0087] In some embodiments, the storage unit 2 is also used to store a relative change relationship, which is used to indicate the relative change of the temperature of the heating element 11 and its resistance when it changes by one degree Celsius; the logic unit 4 is also used to determine the actual temperature of the corresponding heating element 11 at the current time point based on the resistance of the corresponding heating element 11 at the current time point, the initial resistance of the corresponding heating element 11, the relative change relationship and the current ambient temperature.

[0088] In addition, in some embodiments, the relative change relationship is TCR. TCR represents the relative change of the resistance of the heating element 11 when the temperature of the heating element 11 changes by 1°C, and its unit is ppm / °C.

[0089] As an example, the actual temperature at the current time point may be determined according to the following formula (3):

[0090]

[0091] Wherein, T represents the actual temperature at the current time point, R1 represents the resistance value of the corresponding heating element 11 at the current time point, R0 represents the initial resistance value of the corresponding heating element 11, TCR represents the relative change relationship, T S Indicates the ambient temperature at the current time.

[0092] It should be noted that the above is explained by determining the actual temperature of the corresponding heating element 11 at the current time point based on the resistance value of the corresponding heating element 11 at the current time point, the initial resistance value of the corresponding heating element 11, the relative change relationship and the current ambient temperature. Alternatively, in application, the actual temperature of the corresponding heating element 11 at the current time point can also be directly measured by a temperature sensor or other methods can be used to obtain the actual temperature of the corresponding heating element 11 at the current time point.

[0093] In addition, in some embodiments, the logic unit 4 can also obtain the resistance value of the corresponding heating element 11 at the current time point by collecting the ADC (Analog to Digital Converter) value and performing calculations based on the ADC value, or the logic unit 4 can also determine the resistance value at the current time point by other means; the initial resistance value can be set by a technician, so that the logic unit 4 can directly obtain the initial resistance value when needed; the ambient temperature at the current time point can be measured by the temperature sensor included in the atomization device, or it can be determined by other means. The embodiments of the present application are not limited to this.

[0094] The logic unit in the embodiment of the present application can predict the difference between the actual temperature of the heating element in the atomization device and the target temperature in advance, and based on this, dynamically determine the corresponding critical temperature difference, so that the actual temperature of the heating element is close to the target temperature, thereby stabilizing the stability of the atomization device, and then improving the user's experience of the atomization device; moreover, the logic unit calls the temperature control unit at a certain frequency, and determines whether the temperature control unit needs to calculate the duty cycle when calling the temperature control unit, that is, whether the duty cycle needs to intervene in the calculation, which can improve the flexibility of the atomization device. Moreover, when the difference between the target temperature and the actual temperature at the current time point is greater than the first critical temperature difference, the logic unit determines that the temperature control unit does not need to calculate the duty cycle, and makes the temperature control unit control the corresponding heating element to output at full power, so that the temperature can be quickly heated up when the atomization device needs to be heated up; when the difference between the target temperature and the actual temperature at the current time point is less than the opposite number of the first critical temperature difference, it is determined that the temperature control module does not need to calculate the duty cycle, and makes the temperature control unit control the corresponding heating element not to generate heat, so that the temperature can be quickly cooled down when the atomization device needs to be cooled down.

[0095] Next, the temperature control method of the atomization device provided in the embodiment of the present application is explained in detail.

[0096] Figure 2 It is a flow chart of a method for controlling an atomizing device provided in an embodiment of the present application. The atomizing device includes a heating unit, a temperature control unit and a logic unit. The heating unit includes at least one heating element. The at least one heating element has a corresponding target temperature curve. The target temperature curve is used to indicate the relationship between the heating time and the temperature of the corresponding heating element. The method is applied to the logic unit. The method includes:

[0097] Step 201: Call the temperature control unit.

[0098] Step 202: Determine the target temperature of the corresponding heating element at the current time point according to the target temperature curve.

[0099] The process of the above step 202 has been described in detail above. Please refer to the relevant content above and will not be repeated here.

[0100] Step 203: Obtain the actual temperature of the corresponding heating element at the current time point.

[0101] The process of the above step 203 has been described in detail above. Please refer to the above related content and will not be repeated here.

[0102] Step 204: Determine whether the temperature control unit needs to calculate the duty cycle based on the target temperature at the current time point, the actual temperature at the current time point, and the first critical temperature difference value; wherein the first critical temperature difference value is the critical temperature difference value corresponding to the current time point, and the first critical temperature difference value is determined at the previous time point based on the predicted temperature at the current time point and the target temperature at the current time point; the predicted temperature at the current time point is the temperature at the current time point obtained from the previous time point when the temperature control unit controls the corresponding heating element to generate heat with the heating power corresponding to the previous time point to the current time point; the previous time point and the current time point are separated by a preset time period.

[0103] The process of the above step 204 has been described in detail above. Please refer to the above related content and will not be repeated here.

[0104] The embodiment of the present application can predict in advance the difference between the actual temperature of the heating element in the atomization device and the target temperature, and based on this, dynamically determine the corresponding critical temperature difference value, so that the actual temperature of the heating element can be close to the target temperature, thereby stabilizing the atomization device and further improving the user experience of the atomization device; and when calling the temperature control unit, determine whether the temperature control unit needs to calculate the duty cycle, that is, whether the duty cycle needs to be involved in the calculation, which can improve the flexibility of the atomization device.

[0105] Figure 3 is a schematic diagram of a temperature control device for an atomizing device provided in an embodiment of the present application, see Figure 3 The control device includes: a calling module 301, a first determining module 302, an acquiring module 303, and a second determining module 304.

[0106] A calling module 301 is used to call a temperature control unit;

[0107] A first determination module 302 is used to determine the target temperature of the corresponding heating element at the current time point according to the target temperature curve;

[0108] The acquisition module 303 is used to acquire the actual temperature of the corresponding heating element at the current time point;

[0109] The second determination module 304 is used to determine whether the temperature control unit needs to calculate the duty cycle based on the target temperature at the current time point, the actual temperature at the current time point, and the first critical temperature difference value; wherein the first critical temperature difference value is the critical temperature difference value corresponding to the current time point, and the first critical temperature difference value is determined at the previous time point based on the predicted temperature at the current time point and the target temperature at the current time point; the predicted temperature at the current time point is the temperature at the current time point obtained from the previous time point when the temperature control unit controls the corresponding heating element to generate heat with the heating power corresponding to the previous time point to the current time point; the previous time point and the current time point are separated by a preset time period.

[0110] The embodiment of the present application can predict in advance the difference between the actual temperature of the heating element in the atomization device and the target temperature, and based on this, dynamically determine the corresponding critical temperature difference value, so that the actual temperature of the heating element can be close to the target temperature, thereby stabilizing the atomization device and further improving the user experience of the atomization device; and when calling the temperature control unit, determine whether the temperature control unit needs to calculate the duty cycle, that is, whether the duty cycle needs to be involved in the calculation, which can improve the flexibility of the atomization device.

[0111] It should be noted that the temperature control device provided in the above embodiment only uses the division of the above functional modules as an example when controlling the temperature of the atomizing device. In practical applications, the above functional distribution can be completed by different functional modules as needed, that is, the internal structure of the temperature control device is divided into different functional modules to complete all or part of the functions described above. In addition, the temperature control device of the atomizing device provided in the above embodiment belongs to the same concept as the above atomizing device embodiment. The specific implementation process is detailed in the atomizing device embodiment, which will not be repeated here.

[0112] Those skilled in the art will appreciate that all or part of the functions of the various methods in the above-mentioned embodiments can be implemented by hardware or by computer programs. When all or part of the functions in the above-mentioned embodiments are implemented by computer programs, the program can be stored in a computer-readable storage medium, and the storage medium can include: read-only memory, random access memory, disk, optical disk, hard disk, etc., and the program is executed by a computer to implement the above-mentioned functions. For example, the program is stored in the memory of the device, and when the program in the memory is executed by the processor, all or part of the above-mentioned functions can be implemented. In addition, when all or part of the functions in the above-mentioned embodiments are implemented by computer programs, the program can also be stored in a storage medium such as a server, another computer, disk, optical disk, flash disk or mobile hard disk, and can be downloaded or copied and saved in the memory of the local device, or the system of the local device is updated, and when the program in the memory is executed by the processor, all or part of the functions in the above-mentioned embodiments can be implemented.

[0113] The above specific examples are used to illustrate the present invention, which is only used to help understand the present invention and is not intended to limit the present invention. For those skilled in the art, according to the concept of the present invention, some simple deductions, modifications or substitutions can be made.

Claims

1. An atomization device, characterized in that: The atomization device comprises: A heating unit, wherein the heating unit comprises at least one heating element, and when a plurality of heating elements are included, each heating element is driven independently; A storage unit, the storage unit is used to store one or more target temperature curves, at least one of the heating elements has a corresponding target temperature curve, the target temperature curve is used to indicate the relationship between the heating time and the temperature of the corresponding heating element; a temperature control unit, the temperature control unit being used to calculate a duty cycle so as to control the heating power of the heating element based on the duty cycle; A logic unit, the logic unit is used to call the temperature control unit at a certain frequency, and determine whether the temperature control unit needs to calculate the duty cycle when calling the temperature control unit, and the logic unit determines whether the temperature control unit needs to calculate the duty cycle when calling the temperature control unit, including: Determine the target temperature of the corresponding heating element at the current time point according to the target temperature curve, and obtain the actual temperature of the corresponding heating element at the current time point; determine whether the temperature control unit needs to calculate the duty cycle based on the target temperature at the current time point, the actual temperature at the current time point, and the first critical temperature difference value; wherein the first critical temperature difference value is the critical temperature difference value corresponding to the current time point, and the first critical temperature difference value is determined at the previous time point based on the predicted temperature at the current time point and the target temperature at the current time point; the predicted temperature at the current time point is the temperature at the current time point obtained when the temperature control unit controls the corresponding heating element to generate heat with the heating power at the previous time point starting from the previous time point, and reaches the current time point; the previous time point and the current time point are separated by a preset time period.

2. The atomizing device according to claim 1, characterized in that The logic unit is specifically used for: Calculating the difference between the target temperature at the current time point and the actual temperature at the current time point; If the difference between the target temperature at the current time point and the actual temperature at the current time point is greater than the first critical temperature difference, it is determined that the temperature control module does not need to calculate the duty cycle, and the temperature control unit controls the corresponding heating element to output full power for heating, so that the corresponding heating element can heat up quickly.

3. The atomizing device according to claim 2, characterized in that: If the difference between the target temperature at the current time point and the actual temperature at the current time point is not greater than the critical temperature difference value, the logic unit is further configured to: Determine whether the difference between the target temperature at the current time point and the actual temperature at the current time point is less than the inverse of the first critical temperature difference value; If the difference between the target temperature at the current time point and the actual temperature at the current time point is less than the inverse of the first critical temperature difference value, it is determined that the temperature control module does not need to calculate the duty cycle, and the temperature control unit controls the corresponding heating element not to generate heat, so that the corresponding heating element is cooled down quickly; If the difference between the target temperature at the current time point and the actual temperature at the current time point is greater than or equal to the inverse of the first critical temperature difference value, and less than or equal to the first critical temperature difference value, it is determined that the temperature control module needs to calculate the duty cycle, and the temperature control module controls the corresponding heating power of the heating element based on the calculated duty cycle.

4. The atomizing device according to any one of claims 1 to 3, characterized in that: The logic unit is also used for: Determine a target temperature at a next time point according to the target temperature curve, wherein the current time point and the next time point are separated by a preset time period; Determine the predicted temperature at the next time point according to the actual temperature at the current time point and the heating power corresponding to the current time point; Determining a second critical temperature difference value corresponding to the next time point according to the target temperature at the next time point and the predicted temperature at the next time point; When the difference between the target temperature at the next time point and the actual temperature at the next time point is greater than or equal to the inverse of the second critical temperature difference value, and less than or equal to the second critical temperature difference value, the temperature control unit is controlled to calculate the duty cycle to stabilize the temperature of the corresponding heating element.

5. The atomizing device according to claim 4, characterized in that: The temperature control unit is also used for: When the corresponding heating element is in a temperature rising state, the product of the first duty cycle and the ratio of the second critical temperature difference value to the first critical temperature difference value is determined as the target duty cycle, wherein the first duty cycle is the duty cycle corresponding to the heating power of the corresponding heating element currently controlled by the temperature control unit to generate heat; When the corresponding heating element is not in a temperature rising state, the product of the first duty cycle and the ratio of the first critical temperature difference value to the second critical temperature difference value is determined as the target duty cycle; The heating power of the corresponding heating element is controlled based on the target duty cycle.

6. The atomizing device according to claim 1, characterized in that: The storage unit is also used to store a relative change relationship, wherein the relative change relationship is used to indicate a relative change in the resistance of the heating element when the temperature of the heating element changes by one degree Celsius; The logic unit is also used to determine the actual temperature of the corresponding heating element at the current time point based on the resistance value of the corresponding heating element at the current time point, the initial resistance value of the corresponding heating element, the relative change relationship and the ambient temperature at the current time point.

7. A temperature control method for atomizing equipment, characterized in that: The atomization device includes a heating unit, a temperature control unit and a logic unit, the heating unit includes at least one heating element, at least one heating element has a corresponding target temperature curve, and the target temperature curve is used to indicate the relationship between the heating time and the temperature of the corresponding heating element; The method is applied to the logic unit; the method comprises: calling the temperature control unit; Determine the target temperature of the corresponding heating element at the current time point according to the target temperature curve; Obtaining the actual temperature of the corresponding heating element at the current time point; Based on the target temperature at the current time point, the actual temperature at the current time point, and a first critical temperature difference value, determine whether the temperature control unit needs to calculate the duty cycle; wherein the first critical temperature difference value is the critical temperature difference value corresponding to the current time point, and the first critical temperature difference value is determined at the previous time point based on the predicted temperature at the current time point and the target temperature at the current time point; the predicted temperature at the current time point is the temperature at the current time point obtained when the temperature control unit controls the corresponding heating element to generate heat with the heating power at the previous time point starting from the previous time point, and reaches the current time point; the previous time point and the current time point are separated by a preset time period.

8. A temperature control device for atomizing equipment, characterized in that: The device comprises: A calling module is used to call the temperature control unit; A first determination module, used to determine the target temperature of the corresponding heating element at a current time point according to the target temperature curve; An acquisition module, used for acquiring the actual temperature of the corresponding heating element at the current time point; The second determination module is used to determine whether the temperature control unit needs to calculate the duty cycle based on the target temperature at the current time point, the actual temperature at the current time point, and a first critical temperature difference value; wherein the first critical temperature difference value is the critical temperature difference value corresponding to the current time point, and the first critical temperature difference value is determined at the previous time point based on the predicted temperature at the current time point and the target temperature at the current time point; the predicted temperature at the current time point is the temperature at the current time point obtained when the temperature control unit controls the corresponding heating element to generate heat with the heating power corresponding to the previous time point starting from the previous time point; the previous time point and the current time point are separated by a preset time period.

9. A computer-readable storage medium, characterized in that: The medium stores a computer program, which can be executed by a processor to implement the method according to claim 7.

10. A computer program product comprising a computer program and / or instructions, characterized in that: When the computer program and / or the instructions are executed by a processor, the method according to claim 7 is implemented.