Fabricated composite shear wall for high-rise building and construction method

By setting an alignment block at the communication groove at the bottom of the shear wall and setting a sliding column at the limit seat, and using positioning ropes to pass through specific slots and sliding columns, the problem of additional installation of the positioning components in the prior art is solved, and the rapid alignment of the shear wall and the foundation is achieved, and the installation efficiency and construction speed are improved.

CN119801163AInactive Publication Date: 2025-04-11浙江恒昌建设有限公司
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202510055906.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2025-01-14
Publication Date
2025-04-11
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

In the prior art, the positioning assembly requires additional installation, resulting in no significant improvement in the installation rate of the shear wall.

Method used

Quick alignment of the shear wall and the base is achieved by providing alignment blocks at the communication groove at the bottom of the shear wall, sliding columns at the limit seat, and positioning ropes through the through hole grooves, through grooves and sliding columns.

Benefits of technology

It simplifies the operation process, improves installation efficiency, shortens construction time, and speeds up the overall construction progress of high-rise buildings.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119801163A_ABST
    Figure CN119801163A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of fabricated buildings, and discloses a high-rise building fabricated combined shear wall and a construction method.The high-rise building fabricated combined shear wall comprises a foundation base, the foundation base is used for leveling and supporting a wall body, a containing groove is formed in the top of the foundation base and used for containing the wall body, two first I-shaped grooves are formed in the bottom of the inner wall of the containing groove, and two second I-shaped grooves are formed in the bottom of the inner wall of the containing groove; and the shear wall is installed at the bottom of the inner wall of the containing groove, the shear wall is a structural member used for resisting lateral force, grouting grooves are formed in the left side and the right side of the shear wall correspondingly, communicating grooves are formed in the top and the bottom of the shear wall correspondingly, and an alignment block is fixedly connected to the top of the inner wall of the communicating groove in the bottom. The alignment block is arranged in the communicating groove in the bottom of the shear wall, the sliding column is arranged on the limiting seat, the positioning rope penetrates through the through hole groove, the penetrating groove and the sliding column to achieve rapid alignment of the shear wall and the foundation base, and compared with the mode that a complex positioning assembly needs to be additionally installed, the operation process is simplified, and the installation efficiency is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of prefabricated buildings, and in particular to a high-rise building prefabricated composite shear wall and a construction method thereof. Background Art

[0002] Shear wall, also known as wind-resistant wall, earthquake-resistant wall or structural wall, is a wall in a house or structure that mainly bears horizontal and vertical loads caused by wind loads or earthquakes to prevent structural shear damage. It is also called earthquake-resistant wall and is generally made of reinforced concrete. Prefabricated shear wall is a shear wall formed by prefabricating part or all of the components of the shear wall structure in the factory and then transporting them to the construction site for assembly and connection. This construction method is different from the traditional cast-in-place shear wall. It emphasizes the factory prefabrication of components and efficient assembly on site.

[0003] After searching, the publication number CN222206853U discloses a prefabricated shear wall structure for green buildings, which includes a connecting sleeve embedded in the shear wall and a connecting steel bar embedded in the wall and passed through the connecting sleeve. The bottom wall of the connecting sleeve is penetrated with a through hole for the pre-embedded steel bar to slide through. The outer surface of the connecting sleeve at the lower end is provided with a grouting hole, and the outer surface of the connecting sleeve at the upper end is provided with a grouting hole. The connecting sleeve is provided with a positioning assembly for positioning the pre-embedded steel bar. The positioning assembly includes a connecting rope for connecting to the pre-embedded steel bar and a pulling member for pulling the connecting rope. The upper end of the connecting rope is provided with a through hole and a grouting hole, and the pulling member is arranged outside the shear wall. The present application has the beneficial effect of reducing the time spent on aligning the connecting sleeve with the embedded steel bar below, thereby increasing the installation rate of the prefabricated shear wall.

[0004] The shear walls in the above application need to use positioning components when docking to align the relative positions of the embedded steel bars, and additional components are required to assist in the alignment. Although the alignment time is reduced, the positioning components still need to be installed additionally, and their use does not speed up the installation rate of the shear walls much. Summary of the invention

[0005] In view of the deficiencies in the prior art, the present invention provides a high-rise building assembled composite shear wall and a construction method, which solves the problem that positioning components need to be additionally installed and the use thereof does not speed up the installation rate of the shear wall much.

[0006] To achieve the above objectives, the present invention is implemented through the following technical solutions: A high-rise building assembled shear wall, comprising: A foundation, the foundation is used for leveling and supporting the wall, a placement groove is provided on the top of the foundation, the placement groove is used for placing the wall, and two first I-shaped grooves are provided on the bottom of the inner wall of the placement groove; A shear wall, which is installed at the bottom of the inner wall of the placement groove. The shear wall is a structural member used to resist lateral force. Grouting grooves are opened on both sides of the shear wall. A connecting groove is opened on the top and bottom of the shear wall. An alignment block is fixedly connected to the top of the inner wall of the connecting groove at the bottom, and a through groove is opened on the front side of the alignment block; A limiting mechanism, the limiting mechanism is used to limit the position of the shear wall, the limiting mechanism comprises a limiting seat, and a sliding column is fixedly connected to the inner wall of the limiting seat; A column mechanism is used to connect the foundation seat with the shear wall. The column mechanism includes two first I-shaped grooves and two second I-shaped grooves. An I-shaped column is arranged between the first I-shaped grooves and the second I-shaped grooves adjacent to each other in upper and lower directions.

[0007] Preferably, the shear wall further comprises reinforcing steel bars, which are arranged in the grouting grooves and are fixedly connected to the grouting grooves. The reinforcing steel bars are used to enhance the connection strength when cement is poured into the grouting grooves.

[0008] Preferably, a filling cavity is opened at the center of the inner wall of the shear wall, and the filling cavity is used to fill functional materials. The filling cavity is filled with a polyester fiber sound insulation board.

[0009] Preferably, the placement groove is located at the bottom of the inner wall of the limiting seat, and the placement groove is fixedly connected to the limiting seat.

[0010] Preferably, the two first I-shaped grooves are located between the two connecting grooves, the two first I-shaped grooves are both opened on the shear wall, and the two second I-shaped grooves are opened at the bottom of the inner wall of the placement groove.

[0011] Preferably, the I-shaped column passes through the top connecting groove, the first I-shaped groove, the bottom connecting groove and the second I-shaped groove in sequence.

[0012] Preferably, a through hole groove is opened on the surface of the shear wall, and the through hole groove is used to observe the docking of the shear wall.

[0013] A method for constructing a high-rise building assembled composite shear wall, the method comprising the following steps: Step 1, production of precast concrete wall panels: precast concrete foundation and shear wall are manufactured according to demand, and a first I-shaped groove, a connecting groove, and a second I-shaped groove are reserved on the foundation and the shear wall, and a filling cavity is set in the shear wall; Step 2, on-site installation: transport the precast concrete foundation and shear wall to the construction site, level the ground, lift the foundation first and put it in place by crane equipment, then lift the shear wall by crane equipment, and then use the positioning rope to pass through the through-hole groove, and pass the rope through the through-hole groove, and further pull the rope downward until the rope passes through the sliding column, and then the rope comes out from the through-hole groove again. As the crane equipment descends, the shear wall is limited, and the foundation and shear wall can be aligned by just pulling the rope; Step 3: Then pull out the rope to complete the docking work of a shear wall, then pass the I-shaped column through the top connecting groove in sequence and enter the first I-shaped groove, then the I-shaped column enters the bottom connecting groove until it passes through the second I-shaped groove on the foundation, completing the connection between the foundation and the shear wall, repeat the above steps 2-3 to complete the assembly of the shear wall; Step 4: Pour concrete into the grouting grooves in the shear wall. The concrete flows along the grouting grooves and gradually fills the two connecting grooves and the two grouting grooves. After solidification, the reinforcement steel bars can be used to strengthen the connection between the two shear walls. Preferably, in step 4, when pouring concrete, a vibration device is used to vibrate the concrete so that the concrete is poured evenly in the shear wall, and the concrete is observed through the through-hole groove.

[0014] The present invention provides a high-rise building assembled combined shear wall and a construction method. It has the following beneficial effects: 1. The present invention realizes the rapid alignment of the shear wall and the foundation seat by arranging an alignment block in the connecting groove at the bottom of the shear wall, arranging a sliding column in the limit seat, and using a positioning rope to pass through the through-hole groove, the through-groove and the sliding column. Compared with the method of additionally installing complex positioning components, the operation process is simplified and the installation efficiency is improved.

[0015] 2. The present invention adopts the method of penetrating the connecting groove, the first I-shaped groove and the second I-shaped groove and nailing them into the ground, which enhances the connection strength between the foundation and the shear wall. The connection method is easy to operate, can effectively shorten the construction time, and speed up the overall construction progress of the high-rise building.

[0016] 3. The present invention reserves various slots and holes and sets filling cavities when prefabricating concrete foundations and shear walls. These are all manufactured in accordance with precise design and process requirements during the factory production process, which can effectively ensure the dimensional accuracy and quality stability of the components, reduce on-site construction errors, and provide a strong guarantee for the quality of high-rise buildings. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] Figure 1 A three-dimensional diagram of an assembled composite shear wall of a high-rise building according to the present invention; Figure 2It is a schematic diagram of a limiting mechanism of a high-rise building assembled combined shear wall according to the present invention; Figure 3 A schematic cross-sectional view of a shear wall of an assembled composite shear wall of a high-rise building according to the present invention; Figure 4 It is a schematic cross-sectional view of a foundation and a shear wall of an assembled composite shear wall of a high-rise building according to the present invention; Figure 5 The present invention is a schematic diagram of the process of constructing a method for assembled composite shear walls of a high-rise building.

[0018] Among them, 1. foundation seat; 2. through hole groove; 3. shear wall; 4. I-shaped column; 5. reinforcing steel bar; 6. first I-shaped groove; 7. placement groove; 8. sliding column; 9. limit seat; 10. connecting groove; 11. second I-shaped groove; 12. grouting groove; 13. filling cavity; 14. alignment block; 15. through groove. DETAILED DESCRIPTION

[0019] The technical solution of the present invention will be described clearly and completely below in conjunction with the accompanying drawings of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0020] Embodiment 1: Please see attached Figure 1 -Attached Figure 4 The embodiment of the present invention provides a high-rise building assembled composite shear wall, comprising: A foundation 1 is used for leveling and supporting the wall. A placement groove 7 is provided on the top of the foundation 1. The placement groove 7 is used for placing the wall. Two first I-shaped grooves 6 are provided on the bottom of the inner wall of the placement groove 7. Shear wall 3, the shear wall 3 is installed at the bottom of the inner wall of the placement groove 7, the shear wall 3 is used as a structural member to resist lateral force, the left and right sides of the shear wall 3 are provided with grouting grooves 12, the top and bottom of the shear wall 3 are provided with connecting grooves 10, the top of the inner wall of the bottom connecting groove 10 is fixedly connected with an alignment block 14, and the front side of the alignment block 14 is provided with a through groove 15; A limiting mechanism, which is used to limit the position of the shear wall 3, comprises a limiting seat 9, and a sliding column 8 is fixedly connected to the inner wall of the limiting seat 9; The column mechanism is used to connect the foundation 1 with the shear wall 3. The column mechanism includes two first I-shaped grooves 6 and two second I-shaped grooves 11. An I-shaped column 4 is arranged between the upper and lower adjacent first I-shaped grooves 6 and second I-shaped grooves 11.

[0021] The foundation 1 is the basic part of the assembled combined shear wall, and its main function is to level and support the wall. The placement groove 7 on the top is used to place the shear wall 3, and the two first I-shaped grooves 6 opened at the bottom of the inner wall of the placement groove 7 cooperate with the column mechanism to achieve a stable connection between the foundation 1 and the shear wall 3, thereby enhancing the stability of the entire structure; The shear wall 3 is a key structural member for resisting lateral force. The grouting grooves 12 on the left and right sides and the reinforcing steel bars 5 arranged inside can effectively enhance the connection strength between the shear walls after grouting. When the concrete is poured into the grouting grooves 12, it forms a whole with the reinforcing steel bars 5 and bears the force together, thereby improving the shear resistance of the wall and further enhancing the seismic performance of the entire structure. The filling cavity 13 at the center of the inner wall is filled with a polyester fiber sound insulation board, which not only does not affect the strength of the wall structure, but also has a good sound insulation effect. The principle is that there are a large number of tiny pores inside the polyester fiber sound insulation board, which can effectively absorb and reflect sound, reduce sound propagation, and provide a quieter environment inside the building; The connecting grooves 10 at the top and bottom and the alignment block 14 and the through grooves 15 at the top of the inner wall of the bottom connecting groove 10 facilitate alignment and connection with other components during construction and installation, thereby improving construction efficiency and installation accuracy. The through-hole grooves 2 on the surface facilitate construction workers to observe the docking condition of the shear wall and ensure construction quality. The sliding column 8 on the inner wall of the limiting seat 9 in the limiting mechanism is used in conjunction with the positioning rope and the through hole groove 2 and the through groove 15 to limit the position of the shear wall 3 when it is installed. By passing the rope through these parts and interacting with the sliding column 8, during the descent of the crane equipment, the foundation 1 and the shear wall 3 can be quickly and accurately aligned by simply pulling the rope, which effectively reduces errors during the installation process.

[0022] Compared with the method that requires additional installation of complex positioning components, the operation process is simplified and the installation efficiency is improved. In addition, this connection method is easy to operate, which can effectively shorten the construction time and speed up the overall construction progress of high-rise buildings.

[0023] The shear wall 3 further includes reinforcing steel bars 5 , which are arranged in the grouting grooves 12 . The reinforcing steel bars 5 are fixedly connected to the grouting grooves 12 . The reinforcing steel bars 5 are used to enhance the connection strength when cement is poured into the grouting grooves 12 .

[0024] A filling cavity 13 is opened at the center of the inner wall of the shear wall 3 . The filling cavity 13 is used to fill functional materials. The filling cavity 13 is filled with a polyester fiber sound insulation board.

[0025] The placement groove 7 is located at the bottom of the inner wall of the limiting seat 9, and the placement groove 7 is fixedly connected to the limiting seat 9.

[0026] The two first I-shaped grooves 6 are located between the two connecting grooves 10 . The two first I-shaped grooves 6 are both opened on the shear wall 3 . The two second I-shaped grooves 11 are opened at the bottom of the inner wall of the placement groove 7 .

[0027] The I-shaped column 4 passes through the top connecting groove 10 , the first I-shaped groove 6 , the bottom connecting groove 10 and the second I-shaped groove 11 in sequence.

[0028] The installation of the I-shaped column 4 is an important link in strengthening the structural connection. It passes through each connecting groove and the I-shaped groove in turn until it is nailed into the ground, completing the connection between the foundation 1 and the shear wall 3, further improving the stability and integrity of the entire structure, enabling each part to work together to resist the various loads borne by the high-rise building. The principle is to form a stable spatial force system, effectively transfer and distribute the load, and ensure the safety and reliability of the building.

[0029] A through hole groove 2 is provided on the surface of the shear wall 3 , and the through hole groove 2 is used to observe the butt joint of the shear wall 3 .

[0030] Please see attached Figure 5 A method for constructing a high-rise building assembled composite shear wall comprises the following steps: Step 1, production of precast concrete wall panels: precast concrete foundation 1 and shear wall 3 are manufactured according to requirements, and a first I-shaped groove 6, a connecting groove 10, and a second I-shaped groove 11 are reserved on the foundation 1 and the shear wall 3, and a filling cavity 13 is set in the shear wall 3; Step 2, on-site installation: transport the precast concrete foundation 1 and the shear wall 3 to the construction site, level the ground, first lift the foundation 1 and put it in place by the crane equipment, then lift the shear wall 3 by the crane equipment, and then use the positioning rope to pass through the through-hole groove 2, and pass the rope through the through-hole groove 15, and further pull the rope downward until the rope passes through the sliding column 8, and then the rope comes out from the through-hole groove 2 again. As the crane equipment descends, the shear wall 3 is limited, and the foundation 1 and the shear wall 3 can be aligned by just pulling the rope; Step 3: Then, pull out the rope to complete the docking work of a shear wall 3, and then insert the I-shaped column 4 through the top connecting groove 10 in sequence and enter the first I-shaped groove 6, and then the I-shaped column 4 enters the bottom connecting groove 10 until it passes through the second I-shaped groove 11 on the foundation 1, completing the connection between the foundation 1 and the shear wall 3, and repeat the above steps 2-3 to complete the assembly of the shear wall 3; Step 4, pour concrete into the grouting groove 12 in the shear wall 3, the concrete flows along the grouting groove 12, and the concrete gradually fills the two connecting grooves 10 and the two grouting grooves 12. After waiting for solidification, the reinforcing steel bars 5 can be used to strengthen the connection between the two shear walls 3.

[0031] In step 4, when pouring concrete, a vibration device is used to vibrate the concrete so that the concrete is poured evenly in the shear wall 3, and the concrete is observed through the through hole groove 2.

[0032] Embodiment 2: The present embodiment differs from the above-mentioned embodiment in that the present embodiment can also be used in the construction of low-rise housing. The I-shaped columns (4) are sequentially passed through the connecting groove (10) at the top and then enter the first I-shaped groove (6). Then, the I-shaped columns (4) enter the connecting groove (10) at the bottom until they pass through the second I-shaped groove (11) on the foundation (1). The I-shaped columns (4) are continuously nailed downward into the ground, thereby completing the connection between the foundation (1), the shear wall (3) and the ground.

[0033] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.

Claims

1. A high-rise building assembled composite shear wall, characterized in that: include: A foundation (1), the foundation (1) being used for leveling and supporting a wall, a placement groove (7) being provided on the top of the foundation (1), the placement groove (7) being used for placing a wall, and two first I-shaped grooves (6) being provided on the bottom of the inner wall of the placement groove (7); A shear wall (3), the shear wall (3) being installed at the bottom of the inner wall of the placement groove (7), the shear wall (3) being a structural member used to resist lateral force, the left and right sides of the shear wall (3) being provided with grouting grooves (12), the top and bottom of the shear wall (3) being provided with connecting grooves (10), the top of the inner wall of the connecting groove (10) at the bottom being fixedly connected with an alignment block (14), the front side of the alignment block (14) being provided with a through groove (15); A limiting mechanism, the limiting mechanism being used to limit the position of the shear wall (3), the limiting mechanism comprising a limiting seat (9), the inner wall of the limiting seat (9) being fixedly connected to a sliding column (8); A column mechanism, the column mechanism being used to connect the foundation (1) with the shear wall (3), the column mechanism comprising two first I-shaped grooves (6) and two second I-shaped grooves (11), an I-shaped column (4) being arranged between the first I-shaped grooves (6) and the second I-shaped grooves (11) adjacent to each other in upper and lower directions.

2. The high-rise building assembled composite shear wall according to claim 1, characterized in that: The shear wall (3) further comprises reinforcing steel bars (5), the reinforcing steel bars (5) being arranged in the grouting groove (12), the reinforcing steel bars (5) being fixedly connected to the grouting groove (12), and the reinforcing steel bars (5) being used to enhance the connection strength when cement is poured into the grouting groove (12).

3. The high-rise building assembled composite shear wall according to claim 1, characterized in that: A filling cavity (13) is provided at the center of the inner wall of the shear wall (3), and the filling cavity (13) is used to fill functional materials. The filling cavity (13) is filled with a polyester fiber sound insulation board.

4. The high-rise building assembled composite shear wall according to claim 1, characterized in that: The placement groove (7) is located at the bottom of the inner wall of the limiting seat (9), and the placement groove (7) is fixedly connected to the limiting seat (9).

5. The high-rise building assembled composite shear wall according to claim 1, characterized in that: The two first I-shaped grooves (6) are located between the two connecting grooves (10), the two first I-shaped grooves (6) are both opened on the shear wall (3), and the two second I-shaped grooves (11) are opened at the bottom of the inner wall of the placement groove (7).

6. The high-rise building assembled composite shear wall according to claim 1, characterized in that: The I-shaped column (4) sequentially passes through the top connecting groove (10), the first I-shaped groove (6), the bottom connecting groove (10) and the second I-shaped groove (11).

7. The high-rise building assembled composite shear wall according to claim 1, characterized in that: A through hole groove (2) is provided on the surface of the shear wall (3), and the through hole groove (2) is used to observe the butt joint of the shear wall (3).

8. A method for constructing assembled composite shear walls of high-rise buildings, characterized in that: For a high-rise building assembled composite shear wall as claimed in any one of claims 1 to 7, the construction method comprises the following steps: Step 1, production of precast concrete wall panels: precast concrete foundation (1) and shear wall (3) are manufactured according to requirements, and a first I-shaped groove (6), a connecting groove (10), and a second I-shaped groove (11) are reserved on the foundation (1) and the shear wall (3), and a filling cavity (13) is provided in the shear wall (3); Step 2, on-site installation: transport the prefabricated concrete foundation (1) and the shear wall (3) to the construction site, level the ground, and then use a crane to first lift the foundation (1) and put it in place, and then use the crane to lift the shear wall (3), and then use a positioning rope to pass through the through-hole groove (2), and pass the rope through the through-hole groove (15), and then further pull the rope downward until the rope passes through the sliding column (8), and then the rope is passed out from the through-hole groove (2) again. As the crane descends, the shear wall (3) is limited, and the base (1) and the shear wall (3) can be aligned by simply pulling the rope; Step 3, then the rope is pulled out to complete the docking work of a shear wall (3), and then the I-shaped column (4) is passed through the top connecting groove (10) in sequence and then enters the first I-shaped groove (6), and then the I-shaped column (4) enters the bottom connecting groove (10) until it passes through the second I-shaped groove (11) on the foundation (1), completing the connection between the foundation (1) and the shear wall (3), and repeating the above steps 2-3 to complete the assembly of the shear wall (3); Step 4: concrete is poured into the grouting groove (12) in the shear wall (3). The concrete flows along the grouting groove (12) and gradually fills the two connecting grooves (10) and the two grouting grooves (12). After solidification, the reinforcing steel bars (5) are added to strengthen the connection between the two shear walls (3).

9. A method for constructing a high-rise building assembled shear wall according to claim 8, characterized in that: In the fourth step, when pouring concrete, a vibration device is used to vibrate the concrete so that the concrete is poured evenly in the shear wall (3), and the concrete is observed through the through hole groove (2).