Air dome basic construction structure and air membrane structure construction method
By adopting a combined structure of dome side support beams, bracket components and spiral piles in the construction of air domes, the problem of ground excavation is solved in the traditional air dome construction method, and the effect of simplicity of construction and cost reduction is achieved.
Patent Information
- Application Number
- CN202510133426.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2025-02-06
- Publication Date
- 2025-04-11
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
The traditional air dome construction method requires the construction of steel or concrete foundations, resulting in problems such as ground excavation, large workload and high cost.
Dome side support beams, bracket components, water transport piles and woven mesh are used to avoid ground excavation through spiral piles, build an air dome foundation, and relies on the structure of the beam to complete the installation and setting of the entrance and computer room.
It greatly saves time and capital investment required for civil engineering construction, significantly reduces the manufacturing cost of air domes, and improves the stability of the structure and simplicity of construction.
Smart Images

Figure CN119801315A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the field of air dome structures, in particular to a basic construction structure of an air dome and an air membrane structure construction method. Background Art
[0002] An air dome is a type of building that uses air pressure to support its structure. It is usually made of a special architectural membrane as its outer shell and is equipped with an intelligent operation control system to provide air pressure inside, allowing the main body of the building to be supported by the pressure difference between the inside and the outside. Its working principle is based on the compressibility of air and the pressure difference. Air is continuously filled into the space between the membrane and the ground or the foundation structure through equipment such as blowers, forming an air pressure higher than the external environment, thereby causing the membrane to generate outward tension, which is balanced with the internal air pressure, thereby supporting the entire dome structure, enabling it to maintain a stable shape and sufficient strength to resist external loads.
[0003] The traditional way of constructing an air dome requires building a steel or concrete foundation, excavating the ground first, using excavation equipment, and spending a lot of time, effort, and money on placing steel bars and pouring concrete.
[0004] Therefore, those skilled in the art have proposed a basic construction structure of an air dome and a construction method of an air membrane structure to solve the problems raised by the background technology. Summary of the invention
[0005] In order to solve the above technical problems, the present invention provides a basic construction structure of an air dome and an air membrane structure construction method to solve the problems in the prior art that the traditional air dome construction method needs to build a steel or concrete foundation, the ground must be excavated first, and the workload is large.
[0006] A basic construction structure of an air dome, comprising:
[0007] Dome side support beams, two groups of dome side support beams are arranged in parallel, the dome side support beams include a first support beam and a second support beam, and the first support beam and the second support beam are both "H"-shaped plate structures;
[0008] A support assembly, which is installed at both ends of the dome side support beam and includes an extension beam, an inner membrane support beam and an outer membrane support beam;
[0009] The water delivery pile is in a "U"-shaped structure, and the first support beam and the second support beam are installed at both ends of the water delivery pile;
[0010] A woven mesh is covered on the dome side support beams and the bracket assembly to form an air dome.
[0011] Preferably, extension beams are horizontally installed at both ends of the two groups of dome side support beams, vertical outer membrane support beams are installed between the two groups of extension beams, and two groups of inner membrane support beams are vertically installed between the two groups of dome side support beams, and the two groups of inner membrane support beams are respectively located at both ends of the dome side support beams.
[0012] Preferably, woven mesh fixings are installed on the inner surfaces of the first support beam and the second support beam, and a plurality of hangers are arrayed on the outer surfaces of the first support beam and the second support beam, metal wires are pressed between two groups of symmetrically arranged woven mesh fixings, and metal wires are also connected between two groups of symmetrically arranged hangers, and the woven mesh covers the metal wires.
[0013] Preferably, a plurality of reinforcing ribs are installed between the first support beam and the second support beam.
[0014] Preferably, a plurality of through holes are provided between the first support beam, the second support beam and the water delivery pile, and fixing bolts and nuts are installed at the through holes.
[0015] Preferably, a plurality of clamping bolts are threadedly engaged at the outer walls of the first support beam and the second support beam, and the positions of the clamping bolts are adapted to the woven mesh fixing pieces.
[0016] Preferably, it also includes a spiral pile, which includes a cylindrical pile, a spiral blade and a locking piece; the spiral blade is formed on the circumference of the cylindrical pile, the locking piece is fixed at the end of the cylindrical pile, and the locking piece is pressed onto one side of the dome side support beam.
[0017] Preferably, a plurality of reinforcing wires are fixedly connected between the two groups of inner membrane support beams, an organic room is formed between the inner membrane support beams and the outer membrane support beams, and an entrance is provided at the outer membrane support beams.
[0018] A basic construction structure of an air dome and a construction method of an air membrane structure include the following steps:
[0019] S1. Determine the construction location of the air dome and install water delivery piles at the construction location;
[0020] S2. Install the dome side support beams. Install the first support beam and the second support beam at both ends of the water delivery pile with fixing bolts and nuts, and tighten and fix them with screw piles to ensure a firm connection. During the installation process, pay attention to the parallelism and horizontality of the first support beam and the second support beam, and use measuring instruments for precise measurement and adjustment;
[0021] Install reinforcing ribs between the first support beam and the second support beam; the installation position and quantity of the reinforcing ribs shall comply with the structural design specifications to enhance the overall strength of the dome side support beam;
[0022] S3. Install the bracket assembly. Install the extension beams horizontally at both ends of the two sets of dome side support beams to ensure that the extension beams are firmly connected to the dome side support beams and the horizontality meets the requirements; install the outer membrane support beams vertically between the two sets of extension beams. The verticality and position of the outer membrane support beams should be accurate to ensure that they can effectively support the external woven mesh and work in coordination with other structural components;
[0023] Two groups of inner membrane support beams are vertically installed between the two groups of dome side support beams. The inner membrane support beams are located at both ends of the dome side support beams. During the installation process, attention should be paid to the verticality of the inner membrane support beams and the firmness of the connection with the dome side support beams;
[0024] S4, installing the braided mesh, installing braided mesh fixings on the inner surfaces of the first support beam and the second support beam, and installing hangers on their outer surfaces to connect metal wires; connecting the metal wires between the symmetrically arranged braided mesh fixings and the hangers to form a metal wire support for fixing the braided mesh;
[0025] Cover the braided mesh on the metal wire and fix the braided mesh to the braided mesh fixing part with the clamping bolts; the tightening degree of the clamping bolts should be moderate to ensure that the braided mesh is firmly fixed without damaging the braided mesh;
[0026] S5. Fixedly connect a number of reinforcing wires between the two groups of inner membrane support beams; set an entrance at the outer membrane support beam, and install a machine room between the inner membrane support beam and the outer membrane support beam.
[0027] Compared with the prior art, the present invention has the following beneficial effects:
[0028] The present invention constructs the foundation of the air dome by arranging dome side support beams and bracket components, and avoids ground excavation operations with the help of screw piles, thereby greatly saving the time and capital investment required for civil engineering construction; water pipes can be constructed according to the actual situation on site, and it has a wide range of uses. It can serve as a counterweight to resist strong winds such as typhoons and enhance the overall stability of the air dome, and can also be used as a part of the foundation and frame. The installation and setting of facilities such as entrances and machine rooms can be completed by relying solely on the beam structure. This structure is not only simple to construct, but also can significantly reduce the manufacturing cost of the air dome. BRIEF DESCRIPTION OF THE DRAWINGS
[0029] Figure 1 It is a schematic diagram of the overall structure of the present invention;
[0030] Figure 2 This is a schematic diagram of the explosion structure of the dome side support beam;
[0031] Figure 3 It is a structural schematic diagram of the connection between the dome side support beam and the water pipe;
[0032] Figure 4 It is a schematic diagram of the cross-sectional structure of the present invention;
[0033] Figure 5 It is a schematic diagram of the three-dimensional structure of the air-covered membrane structure of the present invention;
[0034] Figure 6 A partial schematic diagram of the dome side support beams connected to the air membrane structure.
[0035] In the figure:
[0036] 110. dome side support beam; 111. first support beam; 112. second support beam;
[0037] 111a, lower flange; 111b, upper flange; 111c, through hole; 111d, fixing bolt; 111e, nut; 113, reinforcing rib;
[0038] 120, extension beam;
[0039] 130, inner membrane support beam;
[0040] 140, outer membrane support beam;
[0041] 150. Water delivery pile;
[0042] 160. Screw pile; 161. Cylindrical pile; 162. Screw blade; 163. Locking piece;
[0043] 170, braided mesh; 171, braided mesh fixing piece; 172, clamping bolt;
[0044] 180, metal wire; 181, pendant; 190, reinforcement wire;
[0045] 201, computer room; 200, entrance; G, underground; W, water body. DETAILED DESCRIPTION
[0046] The following embodiments of the present invention are described in further detail in conjunction with the accompanying drawings and examples. The following examples are used to illustrate the present invention, but are not intended to limit the scope of the present invention.
[0047] Embodiment 1: The present invention provides a basic construction structure of an air dome, including: a dome side support beam 110, a bracket assembly, a water delivery pile 150, a woven mesh 170 and a screw pile 160;
[0048] As attached Figure 1 To Attachment Figure 2 As shown: two groups of dome side support beams 110 are arranged in parallel, and the dome side support beams 110 include a first support beam 111 and a second support beam 112, and the first support beam 111 and the second support beam 112 are both "H"-shaped plate structures;
[0049] As attached Figure 1 and attached Figure 5 As shown: the bracket assembly is erected at both ends of the dome side support beam 110, which includes an extension beam 120, an inner membrane support beam 130 and an outer membrane support beam 140. The dome side support beam 110, the inner membrane support beam 130, the outer membrane support beam 140 and the extension beam 120 are all H-shaped beams. The portion corresponding to the central transverse reinforcement of the H-shaped steel is called the web, and the vertical reinforcements at both sides of the transverse reinforcement that are at right angles to the transverse reinforcement are called flanges. The lower portion centered on the horizontal rod is called the lower flange 111a, and the flange at the top is called the upper flange 111b. The beam of the "H"-shaped structure has good mechanical properties. Its web can withstand shear force, and the flange can effectively resist bending moment, thereby providing stable lateral support for the entire air dome.
[0050] As attached Figure 3 As shown: the water delivery pile 150 is in a "U"-shaped structure, and the first support beam 111 and the second support beam 112 are installed at both ends of the water delivery pile 150;
[0051] As attached Figure 4 , Attachment Figure 5 and attached Figure 6 As shown, the woven mesh 170 covers the dome side support beams 110 and the bracket assembly to form an air dome.
[0052] As attached Figure 3 and attached Figure 4 As shown: the spiral pile 160 includes a cylindrical pile 161, a spiral blade 162 and a locking piece 163; the spiral blade 162 is formed on the circumference of the cylindrical pile 161, the locking piece 163 is fixed at the end of the cylindrical pile 161, and the locking piece 163 is pressed onto one side of the dome side support beam 110. The spiral blade 162 facilitates the pile body to be screwed into the ground, thereby increasing the friction between the pile and the soil. The locking piece 163 is fixed at the end of the cylindrical pile 161 and pressed onto one side of the dome side support beam 110, thereby further fixing the dome side support beam to prevent it from being blown up by external forces such as wind.
[0053] Extension beams 120 are horizontally installed at both ends of the two groups of dome side support beams 110, and vertical outer membrane support beams 140 are installed between the two groups of extension beams 120. Two groups of inner membrane support beams 130 are vertically installed between the two groups of dome side support beams 110. The two groups of inner membrane support beams 130 are respectively located at both ends of the dome side support beams 110. A number of reinforcement lines 190 are fixedly connected between the two groups of inner membrane support beams 130. An engine room 201 is formed between the inner membrane support beams 130 and the outer membrane support beams 140, and an entrance 200 is provided at the outer membrane support beam 140.
[0054] A woven mesh fixing part 171 is installed on the inner surface of the first support beam 111 and the second support beam 112, and a plurality of hangers 181 are arrayed on the outer surface of the first support beam 111 and the second support beam 112. A metal wire 180 is pressed between two groups of symmetrically arranged woven mesh fixing parts 171, and a metal wire 180 is also connected between the two groups of symmetrically arranged hangers 181, and the woven mesh 170 covers the metal wire 180.
[0055] A plurality of reinforcing ribs 113 are installed between the first support beam 111 and the second support beam 112 .
[0056] A plurality of through holes 111c are provided between the first support beam 111, the second support beam 112 and the water delivery pile 150, and fixing bolts 111d and nuts 111e are installed at the through holes 111c;
[0057] In order to enhance the stability of the air dome, the dome side support beam 110 can be installed on the water delivery pile 150, i.e., the platform feather, to play a counterweight role. In this case, the weight of the water delivery pile 150 and its underground part, plus the weight of the water filled in the water delivery pile 150, will form a larger load, thereby ensuring that the air dome of the present invention can be stably supported even in strong winds.
[0058] At this time, in order to firmly fix the dome side support beam 110 on the water delivery pile 150, the lower flange 111a of the dome side support beam 110 needs to be placed on the water delivery pile 150 and fixedly connected by bolts 111d and nuts 111e.
[0059] The outer wall of the first support beam 111 and the second support beam 112 is threaded with a plurality of clamping bolts 172, and the position of the clamping bolts 172 is adapted to the braided mesh fixing piece 171; by screwing in the clamping bolts 172, the braided mesh fixing piece 171 can be closely fitted with the braided mesh 170. It is more ideal to fix the braided mesh 170 to the inner side of the upper flange 111b of the H-shaped steel beam; the braided mesh 170 is covered at the metal wire 180, and the braided mesh 170 is fixed to the dome side support beam 110 by the metal wire 180, so that the braided mesh 170 can be closely fitted on the support structure to form an airtight air dome, and by screwing in the clamping bolts 172, the braided mesh fixing piece 171 can be closely fitted with the braided mesh 170, further ensuring the fixing effect of the braided mesh.
[0060] Embodiment 2: The inner membrane support beam 130 and the outer membrane support beam 140 are preferably circular in shape. In the air dome structure, since it is significantly affected by wind force, a streamlined structure is adopted to minimize the influence of wind.
[0061] Therefore, it is ideal that the inner membrane support beam 130 supporting the inner membrane and the outer membrane support beam 140 supporting the outer membrane have a hemispherical or arc-shaped curvature; for the extension beam 120, its structure is used to support the outer membrane support beam 140 so as to construct a machine room 201 or an entrance 200 outside the inner membrane support beam 130, and it is also expected to have a hemispherical or arc-shaped curvature.
[0062] At this time, the radius of curvature of the inner membrane support beam 130 is greater than the circular diameter of the outer membrane support beam 140, because the outer membrane support beam 140, as a structure supporting the outer membrane, needs to form an inlet 200.
[0063] The woven net 170 is constructed by connecting two sets of inner membrane support beams 130 with reinforcing wires 190, which can effectively prevent the woven net 170 from sagging. When there is a power outage, a blower failure, or when the blowing stops when replacing the woven net 170, the internal pressure of the air film will decrease, and the woven net 170 may sag due to its own weight, thereby causing damage to the covered crops; to avoid such situations, whether it is a power outage or a failure such as strong wind, this structure is extremely critical to prevent the woven net 170 from sagging above the crops.
[0064] A pair of air film side support beams 110 are arranged at a predetermined interval, and the pair of dome side support beams 110 are connected by means of reinforcing ribs 113 and arranged in parallel; an extension beam 120 horizontal to the ground is connected to the two ends of each outer beam of a pair of dome side support beams 110, and the two ends of each inner beam in a pair of beams are connected to the inner membrane support beam 130 perpendicular to the ground, and then the outer membrane support beam 140 is connected to the two ends of the extension beam 120 and made perpendicular to the ground. This step is to ensure that the side support beam 110 is fixed by the screw pile 160 to prevent it from being blown up by external forces such as wind.
[0065] Embodiment 3: According to the planned position, the water delivery pile 150 is driven into the ground to ensure that its depth and verticality meet the design requirements. During the driving process, the depth and inclination of the pile body are monitored in real time, and timely adjustments are made if there are deviations.
[0066] The first support beam 111 and the second support beam 112 are butt-jointed with the two ends of the water delivery pile 150 through the through hole 111c, and the fixing bolts 111d and nuts 111e are installed and tightened with a torque wrench according to the specified torque to ensure a firm connection.
[0067] Reinforcing ribs 113 are installed between the first support beam 111 and the second support beam 112. The spacing between the reinforcing ribs is determined according to structural design calculations. The ribs are connected by welding to ensure uniform weld quality without defects such as pores and cracks.
[0068] Use measuring instruments (such as levels and theodolites) to accurately measure the parallelism and horizontality of the first support beam and the second support beam, and control the error within a very small range. If there is any deviation, correct it by adjusting bolts or placing shims under the beams.
[0069] The extension beams 120 are installed horizontally at both ends of the two sets of dome side support beams 110, and are connected by welding or high-strength bolts to ensure that the extension beams are tightly connected to the dome side support beams 110 and the levelness meets the requirements, and the levelness deviation does not exceed the specified value.
[0070] The outer membrane support beam 140 is vertically installed between the two groups of extension beams 120, and the outer membrane support beam 140 is lifted by a crane or other equipment. After adjusting the verticality, it is welded or bolted to the extension beam 120, and the verticality error is controlled within the design allowable range.
[0071] Two groups of inner membrane support beams 130 are vertically installed between the two groups of dome side support beams 110. The inner membrane support beams are respectively located at both ends of the dome side support beams. The same precise installation method is used to ensure the verticality of the inner membrane support beams and the firmness of the connection with the dome side support beams. The connection parts are reinforced to prevent loosening.
[0072] The braided mesh fixing parts 171 are installed on the inner surface of the first support beam 111 and the second support beam 112, and are fixed by rivets or bolts to ensure that the fixing parts are firmly installed and the spacing is uniform. The hanging parts 181 are installed on the outer surface, and the layout of the hanging parts is carried out according to the design requirements to ensure that the braided mesh can be evenly supported.
[0073] The metal wire 180 is connected between the symmetrically arranged woven mesh fixings 171 and the hangers 181 to form a support network of the metal wire 180. The tension of the metal wire is moderate to ensure sufficient support for the woven mesh without damaging the woven mesh or the fixings due to excessive tension.
[0074] The braided mesh 170 is covered on the metal wire 180, and gradually spread out from one end of the dome to cover the entire frame. The braided mesh should be laid flat without wrinkles or damage. Then the braided mesh 170 is fixed to the braided mesh fixing part 171 by the clamping bolt 172. The tightening degree of the clamping bolt 172 is gradually adjusted to ensure that the braided mesh is firmly fixed and fits tightly with the fixing part to avoid gaps that may cause air leakage.
[0075] A number of reinforcing wires 190 are fixedly connected between the two groups of inner membrane support beams 130. The reinforcing wires are made of high-strength materials, and the spacing between them is determined according to the span and stress conditions of the woven mesh. The connection method is firm and reliable to prevent the woven mesh from sagging.
[0076] An entrance 200 is provided at the outer membrane support beam 140, and the structural design of the entrance should facilitate the entry and exit of personnel and equipment while ensuring air tightness. Special sealing materials and connection methods are used to ensure that there is no air leakage at the entrance.
[0077] The machine room 201 is installed between the inner membrane support beam 130 and the outer membrane support beam 140. The frame of the machine room is firmly connected to the support beam. The walls and roof are installed with suitable building materials to ensure the sealing and heat insulation of the machine room, providing a good operating environment for the internal equipment.
[0078] After the dome side support beam 110 is installed, screw piles 160 are installed at appropriate positions on both sides thereof. The cylindrical pile 161 is screwed into the ground through the spiral blade 162. After reaching the designed depth, the locking piece 163 is fixed to the end of the cylindrical pile 161 and pressed onto one side of the dome side support beam 110, and is further fixed by bolts or welding to enhance the wind resistance of the entire structure.
[0079] After the installation is completed, the entire air dome is fully debugged. First, the inflation equipment is started to inflate the dome, the air pressure changes are monitored, and the air tightness of the woven mesh is checked to ensure that there is no obvious leakage under the specified air pressure.
[0080] Check whether each connection point is firm, including between beams, between beams and piles, between woven mesh and fixings, etc. If there is any looseness, reinforce it in time.
[0081] Simulated wind load and snow load tests are carried out to detect the stability and deformation of the structure by applying corresponding loads on the dome surface. According to the test results, necessary optimization and adjustments are made to the structure to ensure that the air dome can operate safely under various severe weather conditions.
[0082] The embodiments of the present invention are provided for the purpose of illustration and description. Although the embodiments of the present invention have been shown and described above, it can be understood that the above embodiments are exemplary and cannot be understood as limitations of the present invention. Ordinary technicians in this field can change, modify, replace and deform the above embodiments within the scope of the present invention.
[0083] In the description of the present invention, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Therefore, the features defined as "first" and "second" may explicitly or implicitly include one or more of the features. "Multiple" means two or more, unless otherwise clearly and specifically defined.
[0084] In the present invention, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", "fixed" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0085] In the present invention, unless otherwise clearly specified and limited, a first feature being "above" or "below" a second feature may mean that the first and second features are in direct contact, or the first and second features are in indirect contact through an intermediate medium. Moreover, a first feature being "above", "above" or "above" a second feature may mean that the first feature is directly above or obliquely above the second feature, or simply means that the first feature is higher in level than the second feature. A first feature being "below", "below" or "below" a second feature may mean that the first feature is directly below or obliquely below the second feature, or simply means that the first feature is lower in level than the second feature.
[0086] In the description of this specification, the description with reference to the terms "one embodiment", "some embodiments", "examples", "specific examples" or "some examples" etc. means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present invention. In this specification, the schematic representations of the above terms do not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described may be combined in any one or more embodiments or examples in a suitable manner. In addition, those skilled in the art may combine and combine different embodiments or examples described in this specification and the features of different embodiments or examples, unless they are contradictory.
[0087] In the drawings of the embodiments disclosed in the present invention, only the structures involved in the embodiments disclosed in the present invention are involved, and other structures can refer to the general design. In the absence of conflict, the same embodiment and different embodiments of the present invention can be combined with each other.
[0088] Although the present invention has been described in detail with reference to the aforementioned embodiments, it is still possible for those skilled in the art to modify the technical solutions described in the aforementioned embodiments, or to make equivalent substitutions for some of the technical features therein. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.
Claims
1. A basic construction structure of an air dome, characterized in that: include: Dome side support beams (110), two groups of the dome side support beams (110) are arranged in parallel, the dome side support beams (110) include a first support beam (111) and a second support beam (112), and the first support beam (111) and the second support beam (112) are both "H"-shaped plate structures; A support assembly, the support assembly being mounted at both ends of the dome side support beam (110), and comprising an extension beam (120), an inner membrane support beam (130) and an outer membrane support beam (140); A water delivery pile (150), wherein the water delivery pile (150) is in a "U"-shaped structure, and the first support beam (111) and the second support beam (112) are installed at two ends of the water delivery pile (150); A woven net (170) is provided, wherein the woven net (170) covers the dome side support beam (110) and the bracket assembly to form an air dome.
2. The basic construction structure of an air dome as claimed in claim 1, characterized in that: Extension beams (120) are horizontally installed at both ends of the two groups of dome side support beams (110), and vertical outer membrane support beams (140) are installed between the two groups of extension beams (120). Two groups of inner membrane support beams (130) are vertically installed between the two groups of dome side support beams (110), and the two groups of inner membrane support beams (130) are respectively located at both ends of the dome side support beams (110).
3. The basic construction structure of an air dome as claimed in claim 2, characterized in that: A woven mesh fixing part (171) is installed on the inner surface of the first support beam (111) and the second support beam (112), and a plurality of hangers (181) are arrayed on the outer surface of the first support beam (111) and the second support beam (112), a metal wire (180) is pressed between two groups of symmetrically arranged woven mesh fixing parts (171), and a metal wire (180) is also connected between the two groups of symmetrically arranged hangers (181), and the woven mesh (170) covers the metal wire (180).
4. The basic construction structure of an air dome as claimed in claim 3, characterized in that: A plurality of reinforcing ribs (113) are installed between the first support beam (111) and the second support beam (112).
5. The basic construction structure of an air dome as claimed in claim 4, characterized in that: A plurality of through holes (111c) are provided between the first support beam (111), the second support beam (112) and the water delivery pile (150), and fixing bolts (111d) and nuts (111e) are installed at the through holes (111c).
6. The basic construction structure of an air dome as claimed in claim 5, characterized in that: A plurality of clamping bolts (172) are threadedly engaged at the outer walls of the first support beam (111) and the second support beam (112), and the positions of the clamping bolts (172) are adapted to the braided mesh fixing member (171).
7. An air dome basic construction structure as claimed in claim 1 or 6, characterized in that: It also includes a spiral pile (160), which includes a cylindrical pile (161), a spiral blade (162) and a locking piece (163); the spiral blade (162) is formed on the circumference of the cylindrical pile (161), the locking piece (163) is fixed at the end of the cylindrical pile (161), and the locking piece (163) is pressed onto one side of the dome side support beam (110).
8. The basic construction structure of an air dome as claimed in claim 2, characterized in that: A plurality of reinforcing wires (190) are fixedly connected between the two groups of inner membrane support beams (130), an engine room (201) is formed between the inner membrane support beams (130) and the outer membrane support beams (140), and an entrance (200) is provided at the outer membrane support beams (140).
9. An air dome basic construction structure and an air membrane structure construction method, used in conjunction with any one of the air dome basic construction structures of claims 1 to 8, characterized in that: The following steps are involved: S1, determining the construction location of the air dome, and installing water delivery piles (150) at the construction location; S2, installing the dome side support beam (110), installing the first support beam (111) and the second support beam (112) at both ends of the water delivery pile (150) through fixing bolts (111d) and nuts (111e), and tightening and fixing them through screw piles (160); installing reinforcing ribs (113) between the first support beam (111) and the second support beam (112); S3, installing the support assembly, horizontally installing the extension beams (120) at both ends of the two groups of dome side support beams (110), vertically installing the outer membrane support beams (140) between the two groups of extension beams (120), and vertically installing the two groups of inner membrane support beams (130) between the two groups of dome side support beams (110); S4, installing the braided mesh (170), installing the braided mesh fixing piece (171) on the inner surface of the first support beam (111) and the second support beam (112), installing the hanging piece (181) on the outer surface thereof, and connecting the metal wire (180); covering the braided mesh (170) on the metal wire (180), and fixing the braided mesh (170) on the braided mesh fixing piece (171) by means of a tightening bolt (172); S5. A plurality of reinforcing wires (190) are fixedly connected between two groups of inner membrane support beams (130); an entrance (200) is provided at the outer membrane support beam (140), and a machine room (201) is installed between the inner membrane support beam (130) and the outer membrane support beam (140).