Curtain wall keel and curtain wall construction method

By constructing a curtain wall design model and conducting on-site calibration, and by adopting a "互"-shaped structure and chemical bolt connections, the problem of the top curtain wall keel damaging the insulation layer was solved, achieving efficient and stable keel fixing and reducing costs.

CN119843808BActive Publication Date: 2025-12-12CHINA MCC22 GROUP CORP LTD +1
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202510197652.7
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2025-02-21
Publication Date
2025-12-12
Estimated Expiration
2045-02-21

AI Technical Summary

Technical Problem

The existing top-floor curtain wall keel is prone to damaging the insulation layer structure when connected to the building's exterior wall, and its large self-weight leads to deformation and increased costs.

Method used

By constructing a curtain wall design model, conducting on-site measurements and calibrations, and pre-welding the main and secondary keels according to the codes set in the model, the main keels are hoisted to the corresponding positions on the exterior wall of the building. The top main keel, which adopts a "互"-shaped structure, is fixed to the concrete beams and floor slabs using chemical bolts to avoid damaging the insulation layer.

Benefits of technology

It achieves efficient and accurate structured splicing and fixing, avoids damage to the thermal insulation layer structure of the building's exterior wall by the top curtain wall keel, improves fixing strength and stability, and reduces costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119843808B_ABST
    Figure CN119843808B_ABST
Patent Text Reader

Abstract

The present application relates to the technical field of curtain wall construction, in particular to a curtain wall keel and a curtain wall construction method. The present application constructs a curtain wall design model, and measures and calibrates in the field to ensure the accuracy of the curtain wall design model. According to the coding set in the curtain wall design model, the corresponding main keel and secondary keel are welded in advance and hoisted to the corresponding position of the building outer wall to realize structured splicing and fixing. The splicing efficiency is higher and more accurate. The original shape of the curtain wall keel is changed, the top of the top layer curtain wall keel is fixed with the bottom of the building top layer concrete beam, and the bottom is fixed with the lower structure of the top layer main keel, so as to avoid the destruction of the thermal insulation layer structure of the building outer wall during the fixing construction process of the top layer curtain wall keel.
Need to check novelty before this filing date? Find Prior Art

Description

TECHNICAL FIELD

[0001] The present application relates to the technical field of curtain wall construction, in particular to a curtain wall keel and a curtain wall construction method. BACKGROUND

[0002] The building curtain wall refers to the load-bearing outer wall of the building, which is usually composed of panels (glass, metal plate, stone plate, ceramic plate, etc.) and the supporting structure behind it. The existing low-rise buildings mostly adopt the design method of combining glass curtain walls and panel curtain walls. The fixed glass curtain wall between floors and the panel curtain wall installed on the outer wall of the floor can be both beautiful and practical. The panel curtain wall needs to be fixed on the building outer wall through the curtain wall keel. The traditional curtain wall keel is mostly clamped on the outer wall of the floor, and the top of the top layer curtain wall keel is mostly connected to the upper part of the building structure through anchor bars. The anchor bars are easy to damage the insulation layer structure, affecting the building insulation effect. If the top layer curtain wall keel is directly fixed to the top of the building, the self-weight of the keel is large, which is easy to deform, and the bearing capacity of the embedded part is higher, and the cost is higher. SUMMARY

[0003] The technical problem to be solved by the present application is that the existing top layer curtain wall keel is easy to damage the insulation layer structure when connected to the building outer wall.

[0004] To solve the problem, the present application provides a construction method that can improve the fixing strength of the curtain wall keel without damaging the insulation layer structure of the building outer wall. The specific scheme is as follows:

[0005] A curtain wall keel and a curtain wall construction method, comprising the following steps:

[0006] Step one, determine the positions of the main keel and the secondary keel of the curtain wall according to the building design drawings, and build a curtain wall design model according to the building structure, the main keel, the secondary keel and the curtain wall.

[0007] Step two, calibrate the curtain wall design model by on-site measurement.

[0008] Step three, encode each curtain wall, main keel and secondary keel in the curtain wall design model, precast the curtain wall according to the curtain wall design model, and manufacture the main keel and the secondary keel on site.

[0009] Step four, according to the set code in the curtain wall design model, pre-weld and fix each main keel and the corresponding secondary keel on the ground.

[0010] Step five, hoist the main keel and the secondary keel of the top layer to the corresponding positions on the top of the building outer wall, and fix the top of each main keel of the top layer to the bottom of the top layer concrete beam, and fix the bottom of each main keel of the top layer to the lower structure of the top layer main keel.

[0011] Step six, weld and fix the adjacent secondary keels of the top layer.

[0012] Step seven, the main keel and the secondary keel of the remaining layers are hoisted to the corresponding positions of the building outer wall in sequence, and the adjacent secondary keels of the same layer are welded and fixed;

[0013] Step eight, according to the code set in the curtain wall design model, the curtain wall is installed on the corresponding secondary keel.

[0014] The application adopting the technical scheme has the beneficial effects compared with the prior art:

[0015] The application constructs the curtain wall design model and measures and calibrates in the field to ensure the accuracy of the curtain wall design model, the corresponding main keel and secondary keel are welded in advance according to the code set in the curtain wall design model and are hoisted to the corresponding positions of the building outer wall to realize the structured splicing and fixing, the splicing efficiency is higher and more accurate, the original curtain wall keel shape is changed, the top of the top layer curtain wall keel is fixed with the bottom of the top layer concrete beam, the bottom is fixed with the lower structure of the top layer main keel, and the anchor bar of the top layer curtain wall keel avoids damaging the insulation layer structure of the building outer wall.

[0016] As a preferred, the further technical scheme of the application is:

[0017] The main keel of the top layer is formed by two L-shaped support rods in positive and reverse buckling, and the top and bottom of the main keel of the top layer are fixed to the bottom of the top layer concrete beam and the lower structure of the top layer main keel through the rear-mounted embedded parts. The two L-shaped support rods, the top layer concrete beam and the lower structure of the top layer main keel form the main keel of the top layer in the shape of a similar "H" character, so that the top of the main keel of the top layer can be fixed to the bottom of the top layer concrete beam, and at the same time, the bottom of the main keel of the top layer can be fixed to the lower structure of the top layer main keel, and the main keel structure in the shape of the "H" character is more stable.

[0018] The rear-mounted embedded parts include chemical bolts, which are used to be inserted into the bottom of the top layer concrete beam and the outer side of the top layer concrete floor. The chemical bolts are used to connect the main keel of the top layer and the concrete structure, so that the fixed structure of the main keel of the top layer is more stable.

[0019] According to the curtain wall design model, the curtain wall is prefabricated, and the main keel and the secondary keel are made on site, specifically: the size and shape information of the main keel, the secondary keel and the curtain wall in the curtain wall design model is obtained, the size and shape information of the curtain wall is sent to the factory, the curtain wall is made in the factory, the main keel and the secondary keel are made according to the size and shape information of the main keel and the secondary keel on the construction site, and the main keel and the secondary keel are made of square steel pipes. BRIEF DESCRIPTION OF DRAWINGS

[0020] Figure 1 is a schematic view of the curtain wall and the curtain wall keel structure of the embodiment of the application;

[0021] Figure 2 is a side view of the connection between the top curtain wall keel and the building structure of the embodiment of the present application;

[0022] Figure 3 is Figure 2 is a partial enlarged view of A in the middle.

[0023] In the figure: 1, top concrete beam; 2, main keel; 3, top concrete floor; 4, secondary keel; 5, connecting plate; 6, screw rod; 7, chemical glue pipe. DETAILED DESCRIPTION

[0024] The present application will be further described in conjunction with the embodiments, and the purpose is only to better understand the content of the present application, therefore, the examples do not limit the protection scope of the present application.

[0025] Referring to the accompanying Figures 1-3 , the embodiment of the present application discloses a curtain wall keel and a curtain wall construction method, comprising the following steps:

[0026] Step one, determine the position and shape of the curtain wall main keel 2 and the secondary keel 4 according to the building design drawing, specifically, the building design drawing is provided by the building contractor, based on the building design drawing, modeling is carried out in Revit software, the building foundation model is obtained, and then the drawing model is positioned; based on the positioning result, design the curtain wall and the keel, generate the curtain wall and keel design drawing, build the curtain wall and the keel into the building foundation model, and obtain the curtain wall design model;

[0027] Step two, the construction personnel measure the size of the building curtain wall position on site, and calibrate the curtain wall design model;

[0028] Step three, encode each curtain wall, main keel 2 and secondary keel 4 in the curtain wall design model, such as curtain wall I-I, curtain wall I-II, curtain wall I-III, main keel II-I, main keel II-II, main keel II-III, secondary keel IV-I, secondary keel IV-II, secondary keel IV-III, etc., the encoding of the secondary keel 4 and the main keel 2 one-to-one corresponds, in order to facilitate the construction personnel to find and install, send the curtain wall design model to the factory, the factory personnel make the curtain wall according to the curtain wall design model, and make the main keel 2 and the secondary keel 4 on site according to the curtain wall design model;

[0029] Step four, according to the curtain wall design model of the main keel 2, the secondary keel 4 and the curtain wall set code, the ground in advance each main keel 2 and the corresponding secondary keel 4 is welded and fixed, the main keel 2 and the secondary keel 4 are made of square steel pipe, according to the size and shape of the main keel 2 and the secondary keel 4 in the curtain wall design model, the square steel pipe is heated and bent on site, the curtain wall is made of aluminum plate in advance in the factory, wherein the main keel 2 of the top layer is formed by two supporting rods positive and negative buckling, the two supporting rods are welded and fixed by square steel pipe, the two L-shaped square steel pipes and the top layer concrete beam are in the shape of “X” with the top layer concrete floor 3, and the adjacent two main keels 2 are welded and fixed;

[0030] Step five, the main keel 2 and the secondary keel 4 of the top layer are hoisted to the corresponding position of the building outer wall top, specifically, the top of each main keel 2 of the top layer is vertically fixed at the bottom of the outer side of the building top layer concrete beam 1, which does not contact with the thermal insulation layer of the building outer wall, the bottom of each main keel 2 of the top layer is fixed on the lower structure of the main keel 2 of the top layer, that is, on the outer side of the top layer concrete floor 3 below the building top layer concrete beam 1;

[0031] Step six, after the installation of the main keel 2 and the secondary keel 4 of the top layer, the secondary keels 4 between the top layer are welded and fixed;

[0032] Step seven, the main keel 2 and the secondary keel 4 of the remaining layers are hoisted to the corresponding position of the building outer wall according to the set position and code in the curtain wall design model, and the adjacent secondary keels 4 of the same layer are welded and fixed;

[0033] Step eight, according to the code set in the curtain wall design model, each curtain wall is installed on the corresponding secondary keel 4, the curtain wall is made of aluminum plate in advance in the factory, the curtain wall and the column and beam of the secondary keel 4 are fixed by self-tapping screws, and then the gap between the adjacent aluminum plates is checked to ensure that the horizontal and vertical are straight, and protective tape is pasted on both sides of the gap.

[0034] In this embodiment, the top and bottom of the main keel 2 of the top layer are fixed on the bottom of the top layer concrete beam 1 and the outer side of the top layer concrete floor 3 respectively through the rear embedded parts. Through the “X” shaped structure of the main keel 2 of the top layer, the top of the main keel 2 of the top layer can be fixed on the bottom of the top layer concrete beam 1, at the same time, the bottom of the main keel 2 of the top layer can be fixed on the outer side of the top layer concrete floor 3, and the main keel 2 of the “X” shaped structure is more firm.

[0035] In the embodiment, the rear embedded part includes a chemical bolt, the chemical bolt includes a screw rod 6 and a chemical glue pipe 7, and during construction, the top of the top layer main keel 2 is firstly constructed, specifically, the top of the top layer main keel 2 is fixedly connected with a connecting plate 5, bolt holes are formed around the connecting plate 5, holes are drilled at the outer side position of the bottom of the top layer concrete beam 1, and the chemical glue pipe 7 of the chemical bolt is placed into the concrete hole, then the screw rod 6 of the chemical bolt is screwed into the concrete hole with the chemical glue pipe 7, the connecting plate 5 is fixedly connected with the concrete structure through the chemical bolt by rotating the nut, and after the chemical glue pipe 7 melts and solidifies, the connecting plate 5 is fixedly connected with the concrete structure through the chemical bolt; during construction of the bottom of the top layer main keel 2, two connecting pipes are firstly vertically welded and fixed at the bottom of the top layer main keel 2, the distal end of the connecting pipe is fixedly connected with the connecting plate 5, and the connecting plate 5 is fixedly connected with the top layer concrete floor 3 outside the top layer concrete floor 3 below the building top layer concrete beam 1 through the chemical bolt, so that the fixed structure of the top layer main keel 2 is more stable.

[0036] In the embodiment, the curtain wall is prefabricated according to the curtain wall design model, and the main keel 2 and the secondary keel 4 are manufactured on site, specifically, the size and shape information of the curtain wall in the curtain wall design model is acquired, the size and shape information of the curtain wall is sent to the factory, and the curtain wall is prefabricated in the factory; the size and shape information of the main keel 2 and the secondary keel 4 in the curtain wall design model is acquired, a two-dimensional drawing is generated, the size and shape of the main keel 2 and the secondary keel 4 are marked on the drawing, for example, the arc length, radius, distance and other information of the main keel 2 or the secondary keel 4, and the main keel 2 and the secondary keel 4 are correspondingly manufactured on site using square steel pipes.

[0037] The application guarantees the accuracy of the curtain wall design model by constructing the curtain wall design model and measuring and calibrating on site, the corresponding main keel 2 and secondary keel 4 are welded in advance according to the coding set in the curtain wall design model and hoisted to the corresponding position of the building outer wall, the structured splicing and fixing are realized, the splicing efficiency is higher and more accurate, the original curtain wall keel shape is changed, the top of the top layer curtain wall keel is fixed with the bottom of the building top layer concrete beam 1, and the bottom is fixed with the top layer concrete floor 3, so that the top layer curtain wall keel does not damage the insulation layer structure of the building outer wall during construction.

[0038] The above merely describes the preferred embodiments of the application, but the application is not limited to the above, and any equivalent changes made according to the content of the specification and drawings of the application are included in the scope of the application.

Claims

1. A construction method for a curtain wall, characterized in that, Includes the following steps: Step 1: Determine the positions of the main and secondary keels of the curtain wall according to the architectural design drawings, and construct a curtain wall design model based on the building structure, main keels, secondary keels and curtain wall. Step 2: On-site measurement and calibration of the curtain wall design model; Step 3: Code each curtain wall, main keel and secondary keel in the curtain wall design model, prefabricate the curtain wall according to the curtain wall design model, and fabricate the main keel and secondary keel on site; Step 4: According to the set codes in the curtain wall design model, pre-weld and fix each main keel to the corresponding secondary keel on the ground; Step 5: Hoist the main keel and secondary keel of the top floor to the corresponding positions on the top of the building's exterior wall, and fix the top of each top floor main keel to the bottom of the top floor concrete beam, and fix the bottom of each top floor main keel to the lower structure of the top floor main keel. Step 6: Weld and fix the adjacent secondary keels on the top layer; Step 7: Hoist the main and secondary keels of the remaining floors to the corresponding positions on the exterior wall of the building in sequence, and weld and fix the adjacent secondary keels on the same floor. Step 8: Install each curtain wall onto the corresponding secondary keel according to the code set in the curtain wall design model; The top layer main keel is formed by two L-shaped support rods interlocking in opposite directions. The top and bottom of the top layer main keel are fixed to the bottom of the top layer concrete beam and the lower structure of the top layer main keel respectively by post-installed embedded parts.

2. The construction method for the curtain wall according to claim 1, characterized in that: The post-installed components include chemical bolts, which are used to insert into the bottom of the top concrete beam and the outside of the top concrete floor slab.

3. The construction method for the curtain wall according to claim 1, characterized in that, The curtain wall is prefabricated according to the curtain wall design model, and the main keel and secondary keel are made on site. Specifically, the size and shape information of the main keel, secondary keel and curtain wall in the curtain wall design model are obtained, and the size and shape information of the curtain wall is sent to the factory. The factory manufactures the curtain wall, and the main keel and secondary keel are made on site according to the size and shape information of the main keel and secondary keel. The main keel and secondary keel are made of square steel pipe.