Bridge construction safety device and system and implementation method

By designing a combined tensile bridge construction hanging basket and an integrated monitoring system, the problems of fixing and lack of safety monitoring of traditional hanging basket structures are solved, and the flexibility, safety and efficiency of bridge construction are achieved.

CN119900219APending Publication Date: 2025-04-29SICHUAN ROAD & BRIDGE CONSTRUCTION GROUP CO LTD
View PDF 6 Cites 0 Cited by

Patent Information

Application Number
CN202411933528.4
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-12-26
Publication Date
2025-04-29

AI Technical Summary

Technical Problem

During the bridge construction process, the traditional hanging basket structure is fixed, which is difficult to adapt to the construction needs of bridges of different widths. The lifting stability is insufficient, which poses safety hazards. At the same time, there is a lack of effective safety monitoring means, making it difficult to monitor changes in bridge structure in real time.

Method used

A combined bridge construction hanging basket is designed, which adopts a stretched structure, consisting of an outer hanging basket, a middle hanging basket and an inner hanging basket. The horizontal length is adjusted through sliding design, and it is equipped with a mobile walking vehicle and a steel rope retracting and unwinding mechanism to ensure the stable lifting and lowering of the hanging basket. At the same time, a bridge detection system integrating an anemometer, inclination meter, strain gauge and static level is used to monitor changes in bridge structure in real time.

Benefits of technology

The device can flexibly adapt to bridge construction needs of different widths, improve construction efficiency and safety, ensure the stability of the hanging basket and the stability of lifting, and timely detect potential safety hazards by monitoring the bridge structure in real time, and ensure the safety of construction personnel and bridges.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119900219A_ABST
    Figure CN119900219A_ABST
Patent Text Reader

Abstract

The invention discloses a bridge construction safety device and system and an implementation method. The device comprises two sets of moving walking vehicles located on a bridge panel, the two sets of moving walking vehicles are located on the two edges of the bridge panel respectively, the device comprises a combined type bridge construction hanging basket, and the combined type bridge construction hanging basket is formed by butt joint of two sets of hanging basket bodies of a stretching type structure. Each set of hanging basket bodies of the stretching type structure is connected with the corresponding movable walking vehicle through a steel rope, and the movable walking vehicles drive the hanging basket bodies of the stretching type structure to ascend and descend to the bridge construction position below the bridge face plate from the ground. According to the stretching type structure of the combined type bridge construction hanging basket, through ingenious combination and sliding design of the outer hanging basket body, the middle hanging basket body and the inner hanging basket body, the horizontal length can be conveniently adjusted. Therefore, the construction requirements of bridges with different widths can be easily met, a special hanging basket does not need to be customized for each bridge specification, the equipment preparation and replacement time is remarkably shortened, and the construction efficiency is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of bridge construction safety, and in particular to a bridge construction safety device, system and implementation method. Background Art

[0002] As an important part of transportation infrastructure, bridge construction faces many safety challenges and technical difficulties during the construction process. As the scale of bridges continues to expand and the structure becomes increasingly complex, ensuring construction safety and efficiency has become a key task.

[0003] During the construction of a bridge, construction workers need to perform a variety of operations under the bridge, such as painting, repairing, and installing ancillary facilities on the bottom of the bridge. Traditional construction hanging baskets often have fixed structures and are difficult to adapt to the construction needs of bridges of different widths, which limits construction efficiency and flexibility. In addition, they lack stability during the lifting process, which can easily lead to safety accidents. In addition, there is a lack of comprehensive and effective safety monitoring methods during bridge construction, making it difficult to accurately grasp the state changes of the bridge structure during the construction process in real time. For example, factors such as wind, temperature, humidity, and construction loads will affect bridge columns and bridge panels, which may cause structural deformation, tilt, or even damage. If they are not monitored in time and appropriate measures are not taken, the lives of construction workers and the overall quality and service life of the bridge will be seriously threatened.

[0004] Therefore, there is an urgent need for a bridge construction safety device and system that can adapt to different construction environments, ensure the safety of construction workers and effectively monitor the bridge structure, so as to fill the gap in the existing technology and meet the high standards of bridge construction safety and quality control. Summary of the invention

[0005] Therefore, in order to solve the above-mentioned shortcomings, the present invention provides a bridge construction safety device, system and implementation method. The tensile structure of the combined bridge construction hanging basket can conveniently adjust the horizontal length through the ingenious combination and sliding design of the outer hanging basket body, the middle hanging basket body and the inner hanging basket body. This makes it easy to adapt to the construction needs of bridges of different widths, without the need to customize a special hanging basket for each bridge specification, significantly reducing equipment preparation and replacement time and improving construction efficiency.

[0006] The present invention is implemented in this way, constructing a bridge construction safety device, characterized in that: the device includes two groups of mobile traveling vehicles located on the bridge panel, the two groups of mobile traveling vehicles are respectively located at the two edges of the bridge panel, the device includes a combined bridge construction hanging basket, the combined bridge construction hanging basket includes two groups of hanging basket bodies with tensile structures connected to each other, each group of hanging basket bodies with tensile structures is connected to the corresponding mobile traveling vehicle by a steel cable, and the mobile traveling vehicle drives the hanging basket body with tensile structure to be lifted from the ground to the bridge construction position below the bridge panel.

[0007] A bridge construction safety device according to the present invention is characterized in that: the composition of the tensile structured hanging basket body includes three parts: an outer hanging basket body, a middle hanging basket body in the middle, and an innermost inner hanging basket body; the inner sides and bottoms of the outer hanging basket body and the middle hanging basket body are respectively provided with grooves, and the outer sides and bottoms of the middle hanging basket body and the inner hanging basket body are respectively provided with transverse protrusions, the middle hanging basket body in the middle is placed in the grooves on the inner side and bottom of the outer hanging basket body through the transverse protrusions on the outer side and bottom, and the middle hanging basket body can slide along the outer hanging basket body, the inner hanging basket body is placed in the grooves of the adjacent middle hanging basket body through the transverse protrusions on the outer side and bottom, and the inner hanging basket body can slide along the inner side, so that the hanging basket body realizes a tensile structure, thereby achieving the purpose of adjusting the horizontal length of the combined bridge construction hanging basket.

[0008] A bridge construction safety device according to the present invention is characterized in that: the bottoms of the outer hanging basket body, the middle hanging basket body and the inner hanging basket body are separately opened with corresponding pins or bolt holes, and the outer hanging basket body and the middle hanging basket body, as well as the middle hanging basket body and the inner hanging basket body can be positioned by pins or bolts, that is, the middle hanging basket body and the inner hanging basket body can be positioned by pins or bolts after being stretched into place.

[0009] A bridge construction safety device according to the present invention is characterized in that the inner hanging basket bodies of the two groups of hanging basket bodies are connected by a pin shaft.

[0010] A bridge construction safety device according to the present invention is characterized in that the two groups of mobile walking vehicles respectively have a steel rope reeling and unreeling mechanism, and the side also has a steel rope support roller that can lean against the edge of the bridge panel, which is used to pull the steel rope out of the corresponding edge of the bridge panel, increase the steel rope support and thus reduce the friction of the steel rope.

[0011] A bridge construction safety system, characterized by comprising a bridge construction safety device and a bridge detection system; The bridge detection system includes an anemometer, an inclinometer, and a strain gauge A installed on the upper part of the bridge column, and a static level and a strain gauge B installed on the lower part; The anemometer is used to measure wind speed and wind direction; The inclinometer is used to measure the inclination angle of the bridge column relative to the horizontal plane; The strain gauge is used to measure the strain of bridge columns and bridge decks, which refers to the shape change of bridge columns and bridge decks when an object is subjected to external forces, temperature changes, humidity changes, etc.; The static level is used to measure the vertical displacement between bridge columns.

[0012] A method for implementing a bridge construction safety system, characterized in that: it is carried out according to the following process; 1. Preliminary preparation: Material and component procurement: According to the design requirements, purchase high-quality steel for the production of mobile walking vehicles, hanging baskets and other structural components to ensure that their strength and durability meet the safety standards for bridge construction; at the same time, purchase accurate anemometers, inclinometers, strain gauges, static levels and other monitoring equipment, as well as supporting steel ropes, pins, bolts, rollers and other accessories; Construction site planning: At the bridge construction site, a special area is planned for the assembly of mobile traveling vehicles and modular bridge construction hanging baskets; the site should be flat and open to facilitate construction operations and equipment storage, and close to the edges of the bridge deck for subsequent installation; 2. Installation of the mobile trolley: hoist the two sets of mobile trolleys to the predetermined positions on both edges of the bridge deck respectively; use professional anchoring devices to firmly fix the mobile trolleys on the bridge deck to ensure that they will not move or shake during operation; install the steel rope retracting and unwinding mechanism on the mobile trolley, and debug its operating performance to ensure that the steel rope can be smoothly retracted and released; install the steel rope support roller on the side of the mobile trolley to make it close to the edge of the bridge deck, and adjust the height and angle of the roller to achieve effective support for the steel rope and reduce friction; 3. Assembly of the combined bridge construction hanging basket: assemble the outer hanging basket body, the middle hanging basket body and the inner hanging basket body respectively; slide the middle hanging basket body in the middle into the grooves on the inner side and bottom of the outer hanging basket body through the transverse protrusions on the outer side and the bottom, so that the middle hanging basket body can slide smoothly along the outer hanging basket body; then, place the inner hanging basket body into the groove of the adjacent middle hanging basket body through the transverse protrusions on the outer side and the bottom, ensuring that the inner hanging basket body can also slide flexibly, thereby realizing the stretching structure of the hanging basket body; according to the actual width requirements of the bridge, adjust the stretching length of the middle hanging basket body and the inner hanging basket body to achieve a suitable horizontal length; after being stretched into place, insert the pin shaft or tighten the bolt to fix it through the corresponding pin shaft or bolt hole between the outer hanging basket body and the middle hanging basket body, and between the middle hanging basket body and the inner hanging basket body to ensure the stability of the hanging basket body structure; finally, use the pin shaft to connect the inner hanging basket bodies of the two groups of hanging basket bodies to form a complete combined bridge construction hanging basket; 4. Connect the mobile vehicle and the hanging basket: Fix one end of the steel rope to each set of the hanging basket with a tensile structure, and connect the other end to the steel rope retracting and unreeling mechanism of the corresponding mobile vehicle; carefully check the connection of the steel rope to ensure that the connection is firm and reliable, without the risk of loosening or slipping; 5. Bridge detection system installation: Select a suitable location on the top of the bridge column to install anemometer, inclinometer and strain gauge A; use professional mounting brackets to fix these devices on the bridge column and perform precise calibration and debugging to ensure that they can accurately measure wind speed, wind direction, inclination angle and strain data of the bridge column; Install a static level and strain gauge B at the corresponding position below the bridge column, and also firmly install and accurately debug them so that they can effectively measure the vertical displacement and strain between the bridge columns; 6. System debugging and trial operation: Test the wire rope reeling and unwinding mechanism of the mobile vehicle, operate its rising, falling and stopping actions, check whether the lifting and lowering of the hanging basket is stable and smooth, whether the wire rope support roller plays an effective role in reducing friction, and observe whether there are abnormal noises, vibrations or jams in the operation of the entire device; start the bridge detection system, conduct data acquisition tests on the anemometer, inclinometer, strain gauge and static level, check whether each monitoring equipment can work normally, whether the collected data is accurate and stable, and compare and analyze the test data with the actual environmental parameters or standard data. If there is any deviation, adjust and calibrate it in time; during the trial operation, arrange professionals to conduct a comprehensive inspection of the entire bridge construction safety device and system, including the connection tightness of each component, the operating status of the equipment, the stability of data transmission, etc., to ensure that the system is in the best working condition before it is officially put into use; 7. Formal use and maintenance: During the bridge construction process, the operator controls the steel rope reeling and unreeling mechanism of the mobile traveling vehicle according to the construction requirements to lift the combined bridge construction hanging basket to the designated construction position under the bridge deck, and the construction personnel carry out various construction operations on the bottom surface of the bridge in the hanging basket; The bridge detection system monitors various parameters of bridge columns and bridge panels in real time, such as wind speed, wind direction, inclination angle, strain and vertical displacement, and transmits the data to the monitoring center at the construction site or the mobile terminal devices of relevant technicians; arranges regular maintenance work, lubricates, inspects and tightens the mechanical parts of the mobile traveling vehicle at regular intervals, conducts appearance inspection and structural integrity assessment of the hanging basket body, performs precision calibration and data storage cleaning on the monitoring equipment, and replaces damaged or aging parts and equipment in time to ensure that the bridge construction safety devices and systems operate continuously, stably and efficiently throughout the entire bridge construction cycle, providing reliable protection for bridge construction safety.

[0013] The present invention has the following advantages: 1. Improved construction convenience and efficiency: Flexible adaptation to various bridge widths: The tensile structure of the combined bridge construction basket can easily adjust the horizontal length through the ingenious combination and sliding design of the outer basket body, the middle basket body and the inner basket body. This makes it easy to adapt to the construction needs of bridges of different widths, without the need to customize a special basket for each bridge specification, significantly reducing equipment preparation and replacement time and improving construction efficiency.

[0014] Convenient lifting operation: Two sets of mobile traveling vehicles located at the edge of the bridge deck are equipped with a steel rope reeling and unreeling mechanism, which can accurately control the lifting and lowering of the combined hanging basket. Operators can quickly lift the hanging basket from the ground to the working position under the bridge deck according to the construction progress and location requirements, or lower it smoothly after the construction is completed. The operation is simple and efficient, which greatly shortens the time for construction workers to go up and down the working surface and improves the overall construction rhythm.

[0015] 2. Enhanced structural stability: Stable hanging basket connection design: The outer hanging basket, middle hanging basket and inner hanging basket are fixed by the cooperation of pins or bolt holes and pins or bolts, and the inner hanging baskets of the two sets of hanging baskets are also connected by pins. This multiple connection method forms a stable structural system, which effectively prevents the hanging basket from deformation, shaking or falling apart due to uneven force or external interference during construction, and provides a safe and reliable working platform for construction personnel.

[0016] Reliable steel rope support and friction reduction: The steel rope support rollers on the side of the mobile trolley are against the edge of the bridge deck, providing an additional support point for the steel rope. This not only enhances the stability of the steel rope during the lifting process, avoiding the smooth operation of the hanging basket due to the shaking of the steel rope, but also extends the service life of the steel rope by reducing the friction between the steel rope and the edge of the bridge, reducing the risk of safety accidents caused by steel rope failure, and further ensuring construction safety and continuity.

[0017] 3. Bridge structure monitoring and safety assurance: Comprehensive monitoring parameter coverage: The bridge inspection system integrates a variety of advanced monitoring equipment such as anemometers, inclinometers, strain gauges and static levels. The anemometer can monitor the wind speed and direction in the construction area in real time, providing data basis for dealing with the impact of strong winds on bridge construction; the inclinometer can accurately measure the inclination angle of the bridge column relative to the horizontal plane, and promptly discover the problem of bridge foundation settlement or structural tilt; the strain gauge can measure the strain of bridge columns and bridge panels under various loads and environmental factors, reflecting the stress state of the structure; the static level focuses on measuring the vertical displacement between bridge columns to assist in judging the stability of the overall bridge structure. Through comprehensive monitoring of these key parameters, all-round control of the structural safety status during bridge construction is achieved.

[0018] Real-time safety warning and decision support: The data collected by the monitoring system can be transmitted in real time to the monitoring center at the construction site or the terminal equipment of relevant technicians. Once the monitoring data exceeds the preset safety threshold, the system can immediately issue a warning signal to remind the construction personnel to take corresponding protective measures or adjust the construction plan. At the same time, these accurate data also provide a scientific decision-making basis for bridge engineers and technicians, helping them to timely analyze the causes and extent of structural safety hazards, formulate reasonable repair or reinforcement strategies, ensure that bridge construction is always carried out within a safe and controllable range, effectively prevent the occurrence of major safety accidents, and ensure the construction quality and long-term service life of the bridge. BRIEF DESCRIPTION OF THE DRAWINGS

[0019] Figure 1 It is a schematic diagram of the implementation of the bridge construction safety device of this application; Figure 2 Schematic diagram of the hanging basket assembly in this application; Figure 3-Figure 4 It is a schematic diagram of the hanging basket body in and outside the present application; Figure 5-Figure 6 It is a schematic diagram of the middle hanging basket body in this application; Figure 7 It is a schematic diagram of the inner hanging basket body in this application; Figure 8 It is a schematic diagram of the layout of the bridge detection system in this application. DETAILED DESCRIPTION

[0020] The following will be combined with the attached Figure 1-Figure 8 The present invention is described in detail, and the technical solutions in the embodiments of the present invention are clearly and completely described. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0021] The present invention provides a bridge construction safety device, such as Figure 1-Figure 7 As shown, it can be implemented in the following manner. The device includes two groups of mobile walking vehicles 2 located on the bridge panel 1, and the two groups of mobile walking vehicles 2 are respectively located at the two edges of the bridge panel 1. The device includes a combined bridge construction hanging basket 3. The combined bridge construction hanging basket 3 includes two groups of hanging basket bodies 4 with tensile structures connected to each other. Each group of hanging basket bodies 4 with tensile structures is connected to the corresponding mobile walking vehicle 2 through a steel cable. The mobile walking vehicle 2 drives the hanging basket body 4 with tensile structures to be lifted from the ground to the bridge construction position under the bridge panel 1.

[0022] In the bridge construction safety device described in the present application; the composition of the hanging basket body 4 of the tensile structure includes three parts: an outer hanging basket body 5, a middle hanging basket body 6 in the middle, and an innermost inner hanging basket body 7; the inner sides and bottoms of the outer hanging basket body 5 and the middle hanging basket body 6 are respectively provided with grooves 8, and the outer sides and bottoms of the middle hanging basket body 6 and the inner hanging basket body 7 are respectively provided with transverse protrusions 9, and the middle hanging basket body 6 in the middle is placed in the grooves 8 on the inner side and bottom of the outer hanging basket body 5 through the transverse protrusions 9 on the outer side and the bottom, and the middle hanging basket body 6 can slide along the inner side of the outer hanging basket body 5, and the inner hanging basket body 7 is placed in the grooves 8 of the adjacent middle hanging basket body 6 through the transverse protrusions 9 on the outer side and the bottom, and the inner hanging basket body 7 can slide along the inner side, so that the hanging basket body 4 realizes a tensile structure, and the purpose of adjusting the horizontal length of the combined bridge construction hanging basket 3 is achieved.

[0023] In the bridge construction safety device described in the present application; the bottoms of the outer basket body 5, the middle basket body 6 and the inner basket body 7 are separately opened with corresponding pins or bolt holes 10, and the outer basket body 5 and the middle basket body 6, as well as the middle basket body 6 and the inner basket body 7 can be positioned by pins or bolts, that is, the middle basket body 6 and the inner basket body 7 can be positioned by pins or bolts after being stretched into place.

[0024] In the bridge construction safety device described in the present application, the inner basket bodies 7 of the two sets of basket bodies 4 are connected by a pin shaft 11.

[0025] In the bridge construction safety device described in the present application; the two groups of mobile walking vehicles 2 respectively have a steel rope reeling and unreeling mechanism, and the side also has a steel rope support roller 12 that can lean against the edge of the bridge panel 1, which is used to pull the steel rope out of the corresponding edge of the bridge panel 1, increase the steel rope support and thereby reduce the friction of the steel rope.

[0026] A bridge construction safety system includes a bridge construction safety device and a bridge detection system; the bridge construction safety device is implemented according to the above scheme, that is, Figure 1-Figure 7 As shown in the implementation. Figure 8 As shown, the bridge detection system includes an anemometer 14, an inclinometer 15, a strain gauge A16 installed on the upper part of the bridge column 13, and a static level 17 and a strain gauge B18 installed on the lower part; The anemometer 14 is used to measure wind speed and wind direction; The inclinometer 15 is used to measure the inclination angle of the bridge column 13 relative to the horizontal plane; The strain gauge is used to measure the strain of bridge columns and bridge decks, which refers to the shape change of bridge columns and bridge decks when an object is subjected to external forces, temperature changes, humidity changes, etc.; The static level 17 is used to measure the vertical displacement between bridge columns; The implementation process of an operation method of a bridge construction safety system is described in detail; 1. Preliminary preparation: Material and component procurement: According to the design requirements, high-quality steel is purchased for the production of mobile traveling vehicles, hanging baskets and other structural components to ensure that their strength and durability meet the safety standards for bridge construction. At the same time, accurate monitoring equipment such as anemometers, inclinometers, strain gauges, static levels, and supporting accessories such as steel ropes, pins, bolts, rollers, etc. are purchased.

[0027] Construction site planning: At the bridge construction site, a special area is planned for the assembly of mobile traveling vehicles and combined bridge construction hanging baskets. Ensure that the site is flat and open to facilitate construction operations and equipment storage, and close to the edges of the bridge deck for subsequent installation.

[0028] 2. Installation of the mobile trolley: Lift the two sets of mobile trolleys to the predetermined positions on both edges of the bridge deck. Use professional anchoring devices to firmly fix the mobile trolleys on the bridge deck to ensure that they will not move or shake during operation. Install the steel rope retracting and unwinding mechanism on the mobile trolley, and debug its operating performance to ensure that the steel rope can be smoothly retracted and released. Install the steel rope support roller on the side of the mobile trolley so that it is close to the edge of the bridge deck, and adjust the height and angle of the roller to achieve effective support for the steel rope and reduce friction.

[0029] 3. Assembly of the combined bridge construction hanging basket: Assemble the outer hanging basket body, the middle hanging basket body and the inner hanging basket body respectively. Slide the middle hanging basket body into the grooves on the inner side and bottom of the outer hanging basket body through the transverse protrusions on the outside and bottom, so that the middle hanging basket body can slide smoothly along the outer hanging basket body. Then, place the inner hanging basket body into the groove of the adjacent middle hanging basket body through the transverse protrusions on the outside and bottom, ensuring that the inner hanging basket body can also slide flexibly, thereby realizing the stretching structure of the hanging basket body. According to the actual width requirements of the bridge, adjust the stretching length of the middle hanging basket body and the inner hanging basket body to reach the appropriate horizontal length. After stretching in place, insert the pin or tighten the bolt through the corresponding pin or bolt hole between the outer hanging basket body and the middle hanging basket body, and between the middle hanging basket body and the inner hanging basket body to fix the position and ensure the stability of the hanging basket body structure. Finally, use the pin to connect the inner hanging basket bodies of the two groups of hanging basket bodies to form a complete combined bridge construction hanging basket.

[0030] 4. Connect the mobile traveling vehicle and the hanging basket body: fix one end of the steel rope on each set of the hanging basket body of the tensile structure, and connect the other end to the steel rope retracting and unreeling mechanism of the corresponding mobile traveling vehicle.

[0031] Carefully check the connection of the steel rope to ensure that the connection is firm and reliable without any risk of loosening or slipping.

[0032] 5. Bridge detection system installation: Select a suitable location on the top of the bridge column to install anemometer, inclinometer and strain gauge A. Use professional mounting brackets to fix these devices on the bridge column and perform precise calibration and debugging to ensure that they can accurately measure wind speed, wind direction, inclination angle and strain data of the bridge column.

[0033] A static level and strain gauge B are installed at the corresponding position at the bottom of the bridge column. They are also firmly installed and precisely debugged so that they can effectively measure the vertical displacement and strain between the bridge columns.

[0034] 6. System debugging and trial operation: Test the wire rope reeling and unwinding mechanism of the mobile vehicle, operate its rising, falling and stopping actions, check whether the lifting and lowering of the hanging basket is stable and smooth, whether the wire rope support roller plays an effective role in reducing friction, and observe whether there are abnormal noises, vibrations or jams in the operation of the entire device. Start the bridge detection system, conduct data acquisition tests on the anemometer, inclinometer, strain gauge and static level, check whether each monitoring equipment can work normally, whether the collected data is accurate and stable, and compare and analyze the test data with the actual environmental parameters or standard data. If there is any deviation, adjust and calibrate it in time. During the trial operation, arrange professionals to conduct a comprehensive inspection of the entire bridge construction safety device and system, including the connection tightness of each component, the operating status of the equipment, the stability of data transmission, etc., to ensure that the system is in the best working condition before it is officially put into use.

[0035] 7. Formal commissioning and maintenance: During the bridge construction process, the operator controls the steel rope reeling and unreeling mechanism of the mobile traveling vehicle according to construction needs to raise and lower the combined bridge construction hanging basket to the designated construction position under the bridge deck, and the construction personnel carry out various construction operations on the bottom surface of the bridge in the hanging basket.

[0036] The bridge detection system monitors various parameters of bridge columns and bridge panels in real time, such as wind speed, wind direction, tilt angle, strain and vertical displacement, and transmits the data to the monitoring center at the construction site or the mobile terminal device of relevant technicians. Regular maintenance work is arranged to lubricate, inspect and tighten the mechanical parts of the mobile traveling vehicle at regular intervals, conduct appearance inspection and structural integrity assessment of the hanging basket, calibrate the accuracy of monitoring equipment and clean up data storage, and replace damaged or aging parts and equipment in time to ensure that the bridge construction safety devices and systems operate continuously, stably and efficiently throughout the entire bridge construction period, providing reliable protection for bridge construction safety.

[0037] The present application has the following advantages through implementation: The construction hanging basket has strong adaptability: The combined bridge construction hanging basket adopts a stretching structure, which consists of an outer hanging basket body, a middle hanging basket body and an inner hanging basket body. The horizontal length can be adjusted by sliding, and it can flexibly adapt to the construction needs of bridges of different widths, greatly improving the versatility and practicality of the device and reducing construction costs. The connection is stable and reliable: The outer hanging basket body, the middle hanging basket body and the inner hanging basket body are connected by pins or bolt holes, and the inner hanging basket bodies of the two groups of hanging basket bodies are also connected by pins, which ensures the structural stability of the hanging basket during use and guarantees the safety of construction workers.

[0038] Efficient and smooth lifting: The mobile traveling vehicle is equipped with a steel rope reeling and winding mechanism and steel rope support rollers, which not only enables convenient lifting and lowering of the hanging basket from the ground to the bridge construction location, but also the steel rope support rollers effectively reduce the friction of the steel rope, making the lifting process smoother and more stable, reducing the safety risks caused by lifting failures.

[0039] Comprehensive and accurate bridge monitoring: The bridge detection system integrates a variety of monitoring equipment such as anemometers, inclinometers, strain gauges and static levels. It can fully and real-time monitor the state changes of bridge columns and bridge panels during the construction process caused by factors such as wind, external force, temperature, humidity, etc., such as wind speed and direction, tilt angle, strain and vertical displacement, etc., providing accurate data support for timely discovery of potential safety hazards and taking effective response measures, effectively ensuring the quality of bridge construction and structural safety, and helping to extend the service life of bridges.

[0040] The above description of the disclosed embodiments enables one skilled in the art to implement or use the present invention. Various modifications to these embodiments will be apparent to one skilled in the art, and the general principles defined herein may be implemented in other embodiments without departing from the spirit or scope of the present invention. Therefore, the present invention will not be limited to the embodiments shown herein, but rather to the widest scope consistent with the principles and novel features disclosed herein.

Claims

1. A bridge construction safety device, characterized in that; The device includes two groups of mobile traveling vehicles located on the bridge panel, and the two groups of mobile traveling vehicles are respectively located at the two edges of the bridge panel. The device includes a combined bridge construction hanging basket, and the combined bridge construction hanging basket includes two groups of hanging basket bodies with tensile structures connected to each other. Each group of hanging basket bodies with tensile structures is connected to the corresponding mobile traveling vehicle through a steel rope, and the mobile traveling vehicle drives the hanging basket body with tensile structure to be lifted from the ground to the bridge construction position under the bridge panel.

2. A bridge construction safety device according to claim 1, characterized in that; The basket body of the stretching structure comprises an outer basket body, a middle basket body in the middle and an innermost inner basket body; the inner sides and bottoms of the outer basket body and the middle basket body are respectively provided with grooves, and the outer sides and bottoms of the middle basket body and the inner basket body are respectively provided with transverse protrusions, the middle basket body in the middle is placed in the grooves on the inner side and bottom of the outer basket body through the transverse protrusions on the outer side and bottom, and the middle basket body can slide along the outer basket body, the inner basket body is placed in the grooves of the adjacent middle basket body through the transverse protrusions on the outer side and bottom, and the inner basket body can slide along the inner side, so that the basket body realizes a stretching structure, and achieves the purpose of adjusting the horizontal length of the combined bridge construction basket.

3. A bridge construction safety device according to claim 1, characterized in that; The bottoms of the outer hanging basket body, the middle hanging basket body and the inner hanging basket body are separately provided with corresponding pins or bolt holes, and the outer hanging basket body and the middle hanging basket body, as well as the middle hanging basket body and the inner hanging basket body can be positioned by pins or bolts, that is, the middle hanging basket body and the inner hanging basket body can be positioned by pins or bolts after being stretched into place.

4. A bridge construction safety device according to claim 1, characterized in that: The inner hanging basket bodies of the two groups of hanging basket bodies are connected through pin shafts.

5. A bridge construction safety device according to claim 1, characterized in that; The two groups of mobile traveling vehicles respectively have a steel rope reeling and unreeling mechanism, and the side also has a steel rope support roller that can lean against the edge of the bridge panel 1, which is used to pull the steel rope out of the corresponding edge of the bridge panel, increase the steel rope support and thus reduce the friction of the steel rope.

6. A bridge construction safety system, characterized in that; Includes bridge construction safety devices and bridge inspection systems; The bridge detection system includes an anemometer, an inclinometer, and a strain gauge A installed on the upper part of the bridge column, and a static level and a strain gauge B installed on the lower part; The anemometer is used to measure wind speed and wind direction; The inclinometer is used to measure the inclination angle of the bridge column relative to the horizontal plane; The strain gauge is used to measure the strain of bridge columns and bridge decks, which refers to the shape change of bridge columns and bridge decks when an object is subjected to external forces, temperature changes, humidity changes, etc.; The static level is used to measure the vertical displacement between bridge columns.

7. A method for implementing a bridge construction safety system, characterized in that; Follow the process below; 1. Preliminary preparation: Material and component procurement: According to the design requirements, purchase high-quality steel for the production of mobile walking vehicles, hanging baskets and other structural components to ensure that their strength and durability meet the safety standards for bridge construction; at the same time, purchase accurate anemometers, inclinometers, strain gauges, static levels and other monitoring equipment, as well as supporting steel ropes, pins, bolts, rollers and other accessories; Construction site planning: At the bridge construction site, a special area is planned for the assembly of mobile traveling vehicles and modular bridge construction hanging baskets; the site should be flat and open to facilitate construction operations and equipment storage, and close to the edges of the bridge deck for subsequent installation; 2. Installation of the mobile trolley: hoist the two sets of mobile trolleys to the predetermined positions on both edges of the bridge deck respectively; use professional anchoring devices to firmly fix the mobile trolleys on the bridge deck to ensure that they will not move or shake during operation; install the steel rope retracting and unwinding mechanism on the mobile trolley, and debug its operating performance to ensure that the steel rope can be smoothly retracted and released; install the steel rope support roller on the side of the mobile trolley to make it close to the edge of the bridge deck, and adjust the height and angle of the roller to achieve effective support for the steel rope and reduce friction; 3. Assembly of the combined bridge construction hanging basket: assemble the outer hanging basket body, the middle hanging basket body and the inner hanging basket body respectively; slide the middle hanging basket body in the middle into the grooves on the inner side and bottom of the outer hanging basket body through the transverse protrusions on the outer side and the bottom, so that the middle hanging basket body can slide smoothly along the outer hanging basket body; then, place the inner hanging basket body into the groove of the adjacent middle hanging basket body through the transverse protrusions on the outer side and the bottom, ensuring that the inner hanging basket body can also slide flexibly, thereby realizing the stretching structure of the hanging basket body; according to the actual width requirements of the bridge, adjust the stretching length of the middle hanging basket body and the inner hanging basket body to achieve a suitable horizontal length; after being stretched into place, insert the pin shaft or tighten the bolt to fix it through the corresponding pin shaft or bolt hole between the outer hanging basket body and the middle hanging basket body, and between the middle hanging basket body and the inner hanging basket body to ensure the stability of the hanging basket body structure; finally, use the pin shaft to connect the inner hanging basket bodies of the two groups of hanging basket bodies to form a complete combined bridge construction hanging basket; 4. Connect the mobile vehicle and the hanging basket: Fix one end of the steel rope to each set of the hanging basket with a tensile structure, and connect the other end to the steel rope retracting and unreeling mechanism of the corresponding mobile vehicle; carefully check the connection of the steel rope to ensure that the connection is firm and reliable, without the risk of loosening or slipping; 5. Bridge detection system installation: Select a suitable location on the top of the bridge column to install anemometer, inclinometer and strain gauge A; use professional mounting brackets to fix these devices on the bridge column and perform precise calibration and debugging to ensure that they can accurately measure wind speed, wind direction, inclination angle and strain data of the bridge column; Install a static level and strain gauge B at the corresponding position below the bridge column, and also firmly install and accurately debug them so that they can effectively measure the vertical displacement and strain between the bridge columns; 6. System debugging and trial operation: Test the wire rope reeling and unreeling mechanism of the mobile walking vehicle, operate its rising, falling and stopping actions, check whether the lifting and lowering of the hanging basket is stable and smooth, whether the wire rope support roller plays an effective role in reducing friction, and observe whether there is any abnormal noise, vibration or jamming during the operation of the entire device; Start the bridge inspection system, conduct data collection tests on the anemometer, inclinometer, strain gauge and static level, check whether each monitoring device can work normally, whether the collected data is accurate and stable, and compare and analyze the test data with the actual environmental parameters or standard data. If there is any deviation, make timely adjustments and calibrations; During the trial operation, professionals were arranged to conduct a comprehensive inspection of the entire bridge construction safety device and system, including the connection tightness of each component, the operating status of the equipment, the stability of data transmission, etc., to ensure that the system is in the best working condition before it is officially put into use; 7. Formal use and maintenance: During the bridge construction process, the operator controls the steel rope reeling and unreeling mechanism of the mobile traveling vehicle according to the construction requirements to lift the combined bridge construction hanging basket to the designated construction position under the bridge deck, and the construction personnel carry out various construction operations on the bottom surface of the bridge in the hanging basket; The bridge detection system monitors various parameters of bridge columns and bridge panels in real time, such as wind speed, wind direction, inclination angle, strain and vertical displacement, and transmits the data to the monitoring center at the construction site or the mobile terminal devices of relevant technicians; arranges regular maintenance work, lubricates, inspects and tightens the mechanical parts of the mobile traveling vehicle at regular intervals, conducts appearance inspection and structural integrity assessment of the hanging basket body, performs precision calibration and data storage cleaning on the monitoring equipment, and replaces damaged or aging parts and equipment in time to ensure that the bridge construction safety devices and systems operate continuously, stably and efficiently throughout the entire bridge construction cycle, providing reliable protection for bridge construction safety.

Citation Information

Patent Citations

  • Bridge construction hanging basket

    CN117604927A

  • Car is examined to bridge with adjustable self -control

    CN206477248U

  • Construction platform for trimming prefabricated segmental bridge body

    CN209722727U

  • Bridge repairing device for municipal engineering

    CN212582415U

  • Steel structure bridge installation and maintenance car

    CN219527364U