Through real-time data feedback and abnormal detection systems, combined with coded handover and Internet of Things sensors, the problem of untimely and insufficient effectiveness of SO spare parts recognition in nuclear power plants is solved, and the rapid and accurate identification and efficient management of spare parts information is achieved, and the production management level of nuclear power plants is improved.
Patent Information
- Application Number
- CN202411644369.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-11-18
- Publication Date
- 2025-04-29
AI Technical Summary
During the identification process of SO spare parts for the nuclear power plant in batch handover, there are problems such as untimely identification and insufficient effectiveness, which leads to the inability to hand over and receive spare parts normally as planned, increasing the risk of on-site maintenance.
Through real-time data feedback mechanism and abnormal detection system, we can quickly identify and correct information inconsistencies, and optimize the overall spare parts management process through coded handover and real-time tracking of IoT sensors.
It ensures the rapid and accurate identification of SO spare parts, improves the traceability of spare parts information, reduces the processing time of sudden problems, and improves the safety, reliability and economicality of nuclear power plant production management.
Smart Images

Figure CN119904176A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of industrial automation and monitoring technology, and in particular to a management method and system for effectively identifying spare parts transferred in batches for an engineering project. Background Art
[0002] During the production preparation process of a nuclear power plant, staff need to spend a lot of time in a short period of time to sort out and identify the spare parts information transferred in large quantities by the project, and classify and organize the data according to certain rules. After identification and coding, they are finally entered into the spare parts database.
[0003] Spare parts handed over by the project are spare parts for the operation period purchased by the nuclear power plant engineering company along with the equipment, hereinafter referred to as SO spare parts, which are estimated to be about 20,000 pieces. As an important part of the initial inventory after the commercial operation of the nuclear power plant, they are used to ensure the effective operation of the routine and first overhaul maintenance activities of the two cycles of the unit. If the identification is not timely or the identification effectiveness is insufficient, the spare parts cannot be handed over and received normally as planned, resulting in the risk of no spare parts available or unavailable spare parts during on-site maintenance.
[0004] At present, domestic power plants lack mature and efficient methods when accepting SO spare parts for project handover. There are many problems such as inconsistent handover, missing handover information, and handover efficiency.
[0005] The present invention establishes a set of management methods for the identification of SO spare parts transferred in batches in nuclear power plant projects to ensure the consistency and rapid and accurate identification of reviewed SO spare parts and transferred SO spare parts, support nuclear power plant spare parts identification, supplementary spare parts demand submission, spare parts inventory management, equipment maintenance and other production operations, and improve the safety, reliability and economy of nuclear power plant production management. Summary of the invention
[0006] In view of the above existing problems, the present invention is proposed.
[0007] Therefore, the present invention provides a management method for effectively identifying spare parts transferred in batches of projects. In the process of spare parts procurement, identification, transfer and use, the present invention can quickly identify and correct information inconsistencies through a real-time data feedback mechanism and anomaly detection system. When problems occur, the traceability of spare parts information is improved by establishing a comprehensive record and backtracking path, ensuring that sudden problems can be quickly handled.
[0008] In order to solve the above technical problems, the present invention provides the following technical solutions, a management method for effectively identifying spare parts handed over in batches of projects, comprising: in the SO spare parts review and confirmation stage, the integrity of the SO spare parts information is confirmed and encoded; in the spare parts batch coding stage, the spare parts are encoded in detail and the management attributes are confirmed based on the technical documents of the production department; in the SO spare parts handover and identification stage, the spare parts are quickly identified and accepted through coded handover, thereby optimizing the overall spare parts management process.
[0009] As a preferred solution of the management method for effectively identifying spare parts for batch transfer of projects described in the present invention, the SO spare parts information includes accurately recording the information of SO spare parts, including model, specification, quantity and purpose, during the SO spare parts review and confirmation stage, and generating a specific SO spare parts serial code in the form of email or document to ensure the uniqueness of each spare part.
[0010] As a preferred solution of the management method for effectively identifying the spare parts transferred in batches of an engineering project described in the present invention, the specific SO spare parts serial code includes a specific format of a combination of the unit number and the LOT package number followed by the SO identification header and a four-digit serial code, which identifies the source and batch of the spare parts. For each spare part, multiple verifications are performed on the production standards and certificates of conformity. Only when the conditions are met, the spare parts transaction information will be legally confirmed and recorded to ensure the authenticity of the source;
[0011] Once the spare parts are shipped, the dynamic status will be tracked in real time through IoT sensors, the data will be updated in real time and associated with the serial code.
[0012] As a preferred solution of the management method for effective identification of spare parts for batch transfer of projects described in the present invention, the SO spare parts review and confirmation includes that the SO spare parts review and confirmation form is circulated step by step between the production, business and business departments of the power plant and the engineering company, and the spare parts information is reviewed and confirmed by all relevant departments to form a systematic data record to avoid information omission.
[0013] As a preferred solution of the management method for effective identification of spare parts transferred in batches of projects described in the present invention, the batch coding stage of spare parts includes the production department comprehensively registering the core data of various spare parts according to the electronic operation and maintenance manual and assembly drawings to ensure the clarity of the quality assurance level, core supervision attributes and sensitivity management characteristics required for each spare part;
[0014] After completing the collection of spare parts information, the production department should conduct a detailed comparison with the SO spare parts data to establish a relationship between the two. The similarity threshold T is set to determine whether to establish a relationship. When the spare parts number similarity S(BID,SOID)≥T, the relationship is established.
[0015] In the case where the association is not established, a problem flag is generated, a feedback mechanism is used to backtrack the data, and the association model is updated.
[0016] As a preferred solution of the management method for effectively identifying spare parts for batch transfer of projects described in the present invention, the SO spare parts transfer identification includes scanning the barcode or QR code of the physical spare parts through full verification of the registered spare parts information, quickly confirming the accuracy of the model, specification and quantity of the spare parts on site, and improving the efficiency of the warehousing operation.
[0017] As a preferred solution of the management method for effective identification of spare parts transferred in batches of projects described in the present invention, the rapid identification and acceptance of spare parts includes that the identification technology used has a real-time data feedback function. When inconsistent information is found, it is quickly traced back to the problem link for processing. Each alarm event will generate a unique event ID and record context information to form a detailed event log. The backtracking path is based on the event ID. The system quickly retrieves all historical records of the spare parts through the backtracking function, including information on procurement, warehousing, and use, to form a complete tracking chain. The backtracking function R (EID) is expressed as:
[0018]
[0019] Among them, D ac (EID) means obtaining the actual recorded data through the event ID. ex (EID) means obtaining the expected data or history through the event ID. ti (EID) indicates the time when the acquisition event occurs, and M(EID) indicates the related transaction record;
[0020] The information records formed should be incorporated into the overall spare parts management system of the power plant, closely linked with other business links, to promote information sharing and decision support, and enhance the transparency of the entire management process.
[0021] Another object of the present invention is to provide a management system for effectively identifying spare parts for batch transfer of projects, which can improve the accuracy and response speed of spare parts management and support high-reliability nuclear power plant operation.
[0022] As a preferred solution of the management system for effective identification of spare parts transferred in batches of projects described in the present invention, it includes: information encoding module, review and circulation module, data verification module, tracking and identification module, and system integration module;
[0023] The information encoding module is responsible for collecting, encoding and generating serial codes of spare parts information to ensure the integrity of the information and the uniqueness of the spare parts;
[0024] The review circulation module processes the circulation of spare parts review confirmation sheets, ensures the review and confirmation of spare parts information among various departments, and forms system records;
[0025] The data verification module codes spare parts in detail, registers core data, and compares it with SO spare parts data to establish association;
[0026] The tracking and identification module uses IoT sensors to track the status of spare parts and realizes rapid identification and acceptance of spare parts through barcode or QR code scanning;
[0027] The system integration module handles problems in the identification process, records event logs, implements data backtracking, and integrates all information into the spare parts management system to improve transparency and decision support.
[0028] A computer device includes a memory and a processor, wherein the memory stores a computer program, and is characterized in that when the processor executes the computer program, it implements the steps of a management method for effectively identifying spare parts transferred in batches of projects.
[0029] A computer-readable storage medium stores a computer program thereon, characterized in that when the computer program is executed by a processor, the steps of a management method for effectively identifying spare parts transferred in batches for an engineering project are implemented.
[0030] Beneficial effects of the present invention: This method provides a management method for identifying SO spare parts for batch transfer of nuclear power plant projects, and realizes the whole process of project procurement stage through SO spare parts serial code, so that the power plant can efficiently and accurately identify SO spare parts after SO spare parts arrive. After this management method is solidified, it can be passed on to new bases through experience sharing, which is conducive to the standardized management of nuclear power spare parts of the group. BRIEF DESCRIPTION OF THE DRAWINGS
[0031] In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the following briefly introduces the drawings required for describing the embodiments. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work. Among them:
[0032] Figure 1 A flowchart of a management method for effectively identifying spare parts for batch transfer of an engineering project is provided in accordance with an embodiment of the present invention.
[0033] Figure 2 A schematic diagram of the working principle of a management method for effectively identifying spare parts for batch transfer of projects provided by an embodiment of the present invention.
[0034] Figure 3A schematic diagram of working modules of a management system for effectively identifying spare parts for batch transfer of projects provided by an embodiment of the present invention. DETAILED DESCRIPTION
[0035] In order to make the above-mentioned purposes, features and advantages of the present invention more obvious and easy to understand, the specific implementation methods of the present invention are described in detail below in conjunction with the drawings of the specification. Obviously, the described embodiments are part of the embodiments of the present invention, but not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary persons in the art without creative work should fall within the scope of protection of the present invention.
[0036] In the following description, many specific details are set forth to facilitate a full understanding of the present invention, but the present invention may also be implemented in other ways different from those described herein, and those skilled in the art may make similar generalizations without violating the connotation of the present invention. Therefore, the present invention is not limited to the specific embodiments disclosed below.
[0037] Secondly, the term "one embodiment" or "embodiment" as used herein refers to a specific feature, structure, or characteristic that may be included in at least one implementation of the present invention. The term "in one embodiment" that appears in different places in this specification does not necessarily refer to the same embodiment, nor is it a separate or selective embodiment that is mutually exclusive with other embodiments.
[0038] The present invention is described in detail with reference to schematic diagrams. When describing the embodiments of the present invention, for the sake of convenience, the cross-sectional diagrams showing the device structure will not be partially enlarged according to the general scale, and the schematic diagrams are only examples, which should not limit the scope of protection of the present invention. In addition, in actual production, the three-dimensional dimensions of length, width and depth should be included.
[0039] At the same time, in the description of the present invention, it should be noted that the directions or positional relationships indicated by the terms "upper, lower, inner and outer" are based on the directions or positional relationships shown in the drawings, which are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific direction, be constructed and operated in a specific direction, and therefore cannot be understood as limiting the present invention. In addition, the terms "first, second or third" are only used for descriptive purposes and cannot be understood as indicating or implying relative importance.
[0040] In the present invention, unless otherwise clearly specified and limited, the terms "install, connect, connect" should be understood in a broad sense, for example: it can be a fixed connection, a detachable connection or an integral connection; it can also be a mechanical connection, an electrical connection or a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0041] Example 1, reference Figure 1 and Figure 2 , which is the first embodiment of the present invention, provides a management method for effectively identifying spare parts transferred in batches of projects, including:
[0042] S1: During the SO spare parts review and confirmation phase, the integrity of the SO spare parts information is confirmed and coded.
[0043] Furthermore, after the initial SO review confirmation form contains complete information on each SO spare part and has clear procurement requirements, the SO spare part serial number is compiled item by item. The compilation rule of the SO spare part serial number is unit number + SO + LOT package number + 4-digit serial number, such as HNSO002A0001, which is the first SO spare part of the LOT002A deaerator equipment. The review confirmation form containing the SO spare part serial number will be circulated from the power plant production department, business department, engineering company business department, and all the way to the various departments of the manufacturer. The corresponding SO serial number will be printed on the outer packaging label when the spare parts leave the factory, so that the SO spare part serial number can be realized in the whole process of the engineering procurement stage, so as to ensure the consistency of the model and specifications of the SO spare parts in the pre-purchase review list and the actual SO spare parts handed over on site, and avoid the inconsistency of model specifications and quantity that is currently common in domestic power plants when handing over SO spare parts.
[0044] During the SO spare parts review and confirmation phase, the SO spare parts information, including model, specification, quantity and purpose, must be accurately recorded, and a specific SO spare parts serial number must be generated via email or in document form to ensure the uniqueness of each spare part.
[0045] It should also be noted that the specific format is a combination of the unit number and the LOT package number followed by the SO identifier header and a four-digit serial number to identify the source and batch of spare parts. For each spare part, multiple verifications are conducted on the production standards and certificates of conformity. Only when the conditions are met will the spare parts transaction information be legally confirmed and recorded to ensure the authenticity of the source;
[0046] Once the spare parts are shipped, the dynamic status will be tracked in real time through IoT sensors, the data will be updated in real time and associated with the serial code.
[0047] Furthermore, the SO spare parts review confirmation form is circulated step by step between the production, business and engineering company business departments of the power plant. Through the review and confirmation of spare parts information by all relevant departments, a systematic data record is formed to avoid information omissions.
[0048] S2: During the spare parts batch coding stage, the spare parts are coded in detail and the management attributes are confirmed based on the technical documents of the production department.
[0049] Going further, it is the stage of batch coding of spare parts. The batch coding stage is the full range of spare parts coding work carried out by the production department according to the manufacturer's operation and maintenance manual (EOMM manual) and various drawings such as assembly drawings. At this stage, the production department can collect more detailed and complete spare parts information than SO spare parts, and can determine the management attributes such as quality assurance level, core regulatory spare parts, and key sensitive spare parts based on this; on this basis, by comparing with the SO spare parts information, the serial code of the batch coding can be associated with the serial code of the SO spare parts. After the formal coding is completed, the association between the formal coding and the serial code of the SO spare parts can be established. In order to facilitate the production department to accurately carry out the sorting and review of the corresponding supplementary spare parts procurement needs based on the SO spare parts procurement quantity, effectively avoid the problems of duplicate procurement, procurement omissions or inventory backlogs.
[0050] Furthermore, the production department comprehensively registers the core data of various spare parts based on the electronic operation and maintenance manual and assembly drawings to ensure the clarity of the required quality assurance level, core regulatory attributes and sensitivity management characteristics of each spare part;
[0051] After completing the collection of spare parts information, the production department should conduct a detailed comparison with the SO spare parts data to establish a relationship between the two. The similarity threshold T is set to determine whether to establish a relationship. When the spare parts number similarity S(BID,SOID)≥T, the relationship is established:
[0052]
[0053] Among them, C(BID,SOID) indicates whether the association is established (1 for establishment, 0 for non-establishment);
[0054] In the case where the association is not established, a problem flag is generated, a feedback mechanism is used to backtrack the data, and the association model is updated.
[0055]
[0056] Among them, n represents the amount of information collected. The feedback result will affect the weight setting of the similarity function and realize dynamic adjustment. For example, if it is found that the proportion of a specific attribute significantly improves the recognition rate, the weight of the attribute can be increased accordingly.
[0057] S3: During the SO spare parts handover and identification phase, the overall spare parts management process is optimized through rapid identification and acceptance of spare parts through coded handover.
[0058] Furthermore, by fully verifying the registered spare parts information and scanning the barcode or QR code of the physical spare parts, the accuracy of the model, specification and quantity of the spare parts on site can be quickly confirmed, and the efficiency of the warehousing operation can be improved.
[0059] The rapid identification and acceptance of spare parts includes the identification technology used with real-time data feedback function. When inconsistent information is found, it can quickly trace back to the problem link for processing. Each alarm event will generate a unique event ID and record context information to form a detailed event log. The backtracking path is based on the event ID. The system quickly retrieves all historical records of the spare parts through the backtracking function, including information on procurement, warehousing, and use, forming a complete tracking chain. The backtracking function R (EID) is expressed as:
[0060]
[0061] Among them, D ac (EID) means obtaining the actual recorded data through the event ID. ex (EID) means obtaining the expected data or history through the event ID. ti (EID) indicates the time when the acquisition event occurred, and M(EID) indicates the relevant transaction record; once it is determined that data recovery is required, the recovery function FF is used to adjust the data and restore data consistency. The recovery function F is designed as follows:
[0062]
[0063] If D is detected ac (EID) and D ex (EID) is inconsistent, the actual record D ac (EID) is replaced with the expected record D ex (EID), if they are consistent, the system will continue to monitor the data point to ensure the accuracy of subsequent information.
[0064] It should be noted that after recovery, the system will automatically update the data in the master database, including updating the timestamp of the data record, generating a new data status report, and recording the recovery process. The recovered data will be fed back to other business systems to ensure information synchronization.
[0065] The information records formed should be incorporated into the overall spare parts management system of the power plant, closely linked with other business links, promote information sharing and decision support, and enhance the transparency of the entire management process.
[0066] Through the comparison and correlation work in the first two stages, the physical SO spare parts can be handed over with codes. On this basis, it is only necessary to carry out identification and acceptance with the physical objects handed over on site to quickly complete the handover and storage of spare parts, thus avoiding the problem of low identification efficiency that is more common in domestic power plants when handing over SO spare parts.
[0067] Embodiment 2, the second embodiment of the present invention, is different from the previous embodiment in that:
[0068] If the functions are implemented in the form of software functional units and sold or used as independent products, they can be stored in a computer-readable storage medium. Based on this understanding, the technical solution of the present invention, or the part that contributes to the prior art or the part of the technical solution, can be embodied in the form of a software product. The computer software product is stored in a storage medium, including several instructions for a computer device (which can be a personal computer, a server, or a network device, etc.) to perform all or part of the steps of the methods described in each embodiment of the present invention. The aforementioned storage medium includes: U disk, mobile hard disk, read-only memory (ROM, Read-Only Memory), random access memory (RAM, Random Access Memory), disk or optical disk, etc., which can store program codes.
[0069] The logic and / or steps represented in the flowchart or otherwise described herein, for example, can be considered as an ordered list of executable instructions for implementing logical functions, and can be embodied in any computer-readable medium for use by an instruction execution system, device or apparatus (such as a computer-based system, a system including a processor, or other system that can fetch instructions from an instruction execution system, device or apparatus and execute instructions), or in conjunction with such instruction execution systems, devices or apparatuses. For the purposes of this specification, "computer-readable medium" can be any device that can contain, store, communicate, propagate or transmit a program for use by an instruction execution system, device or apparatus, or in conjunction with such instruction execution systems, devices or apparatuses.
[0070] More specific examples of computer-readable media (a non-exhaustive list) include the following: an electrical connection with one or more wires (electronic device), a portable computer disk case (magnetic device), a random access memory (RAM), a read-only memory (ROM), an erasable and programmable read-only memory (EPROM or flash memory), an optical fiber device, and a portable compact disk read-only memory (CDROM). In addition, the computer-readable medium may even be a paper or other suitable medium on which the program is printed, since the program may be obtained electronically, for example, by optically scanning the paper or other medium, followed by editing, deciphering or, if necessary, processing in another suitable manner, and then stored in a computer memory.
[0071] It should be understood that the various parts of the present invention can be implemented by hardware, software, firmware or a combination thereof. In the above-mentioned embodiments, a plurality of steps or methods can be implemented by software or firmware stored in a memory and executed by a suitable instruction execution system. For example, if implemented by hardware, as in another embodiment, it can be implemented by any one of the following technologies known in the art or their combination: a discrete logic circuit having a logic gate circuit for implementing a logic function for a data signal, a dedicated integrated circuit having a suitable combination of logic gate circuits, a programmable gate array (PGA), a field programmable gate array (FPGA), etc.
[0072] Example 3, reference Figure 3 , which is an embodiment of the present invention, provides a management system for effective identification of spare parts transferred in batches of projects, characterized by: comprising an information encoding module 1, an examination and circulation module 2, a data checking module 3, a tracking and identification module 4, and a system integration module 5;
[0073] Information encoding module 1 is responsible for the collection, encoding and serial code generation of spare parts information to ensure the integrity of the information and the uniqueness of the spare parts;
[0074] Review circulation module 2, handles the circulation of spare parts review confirmation forms, ensures the review and confirmation of spare parts information among various departments, and forms system records;
[0075] Data verification module 3, detailed coding of spare parts, registration of core data, and comparison with SO spare parts data to establish association;
[0076] Tracking and identification module 4, using IoT sensors to track spare parts status and quickly identify and accept spare parts through barcode or QR code scanning;
[0077] System Integration Module 5 handles problems during the identification process, records event logs, enables data backtracking, and integrates all information into the spare parts management system to improve transparency and decision support.
[0078] It should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention and are not intended to limit the present invention. Although the present invention has been described in detail with reference to the preferred embodiments, those skilled in the art should understand that the technical solutions of the present invention may be modified or replaced by equivalents without departing from the spirit and scope of the technical solutions of the present invention, which should all be included in the scope of the claims of the present invention.
Claims
1. A management method for effectively identifying spare parts transferred in batches during an engineering project, characterized in that: include, During the SO spare parts review and confirmation phase, the integrity of the SO spare parts information is confirmed and coded; In the spare parts batch coding stage, the spare parts are coded in detail and the management attributes are confirmed based on the technical documents of the production department; During the SO spare parts handover and identification phase, the overall spare parts management process is optimized through rapid identification and acceptance of spare parts through coded handover.
2. A management method for effective identification of spare parts transferred in batches during an engineering project as claimed in claim 1, characterized in that: The SO spare parts information includes, during the SO spare parts review and confirmation stage, accurately recording the information of the SO spare parts, including model, specification, quantity and purpose, and generating a specific SO spare parts serial number in the form of email or document to ensure the uniqueness of each spare part.
3. A management method for effective identification of spare parts transferred in batches during an engineering project as claimed in claim 2, characterized in that: The specific SO spare parts serial code includes a specific format of a combination of the unit number and the SO identification header followed by the LOT package number and a four-digit serial code, which identifies the source and batch of the spare parts. For each spare part, multiple verifications are performed on the production standards and certificates of conformity. Only when the conditions are met, the spare parts transaction information will be legally confirmed and recorded to ensure the authenticity of the source; Once the spare parts are shipped, the dynamic status will be tracked in real time through IoT sensors, the data will be updated in real time and associated with the serial code.
4. A management method for effective identification of spare parts transferred in batches during an engineering project as claimed in claim 3, characterized in that: The SO spare parts review and confirmation includes that the SO spare parts review and confirmation form is circulated step by step between the production, business and engineering company business departments of the power plant, and through the review and confirmation of spare parts information by all relevant departments, a systematic data record is formed to avoid information omission.
5. A management method for effective identification of spare parts transferred in batches during an engineering project as claimed in claim 4, characterized in that: The spare parts batch coding stage includes the production department comprehensively registering the core data of various spare parts based on the electronic operation and maintenance manual and assembly drawings to ensure the clarity of the quality assurance level, core regulatory attributes and sensitivity management characteristics required for each spare part; After completing the collection of spare parts information, the production department should conduct a detailed comparison with the SO spare parts data to establish a relationship between the two. The similarity threshold T is set to determine whether to establish a relationship. When the spare parts number similarity S(BID,SOID)≥T, the relationship is established. In the case where the association is not established, a problem flag is generated, a feedback mechanism is used to backtrack the data, and the association model is updated.
6. A management method for effective identification of spare parts transferred in batches during an engineering project as claimed in claim 5, characterized in that: The SO spare parts handover identification includes, through full verification of the registered spare parts information, scanning of the barcode or QR code of the physical spare parts, quickly confirming the accuracy of the model, specification and quantity of the spare parts on site, and improving the efficiency of the warehousing operation.
7. A management method for effective identification of spare parts transferred in batches during an engineering project as claimed in claim 6, characterized in that: The rapid identification and acceptance of spare parts includes that the identification technology used has a real-time data feedback function. When inconsistent information is found, it is quickly traced back to the problem link for processing. Each alarm event will generate a unique event ID and record context information to form a detailed event log. The backtracking path is based on the event ID. The system quickly retrieves all historical records of the spare parts through the backtracking function, including information on procurement, warehousing, and use, to form a complete tracking chain. The backtracking function R (EID) is expressed as: Among them, D ac (EID) means obtaining the actual recorded data through the event ID. ex (EID) means obtaining the expected data or history through the event ID. ti (EID) indicates the time when the acquisition event occurs, and M(EID) indicates the related transaction record; The information records formed should be incorporated into the overall spare parts management system of the power plant, closely linked with other business links, promote information sharing and decision support, and enhance the transparency of the entire management process.
8. A system using a management method for effective identification of spare parts transferred in batches of projects as claimed in any one of claims 1 to 7, characterized in that: It includes information coding module, review and circulation module, data verification module, tracking and identification module, and system integration module; The information encoding module is responsible for collecting, encoding and generating serial codes of spare parts information to ensure the integrity of the information and the uniqueness of the spare parts; The review circulation module processes the circulation of spare parts review confirmation sheets, ensures the review and confirmation of spare parts information among various departments, and forms system records; The data verification module codes spare parts in detail, registers core data, and compares it with SO spare parts data to establish association; The tracking and identification module uses IoT sensors to track the status of spare parts and realizes rapid identification and acceptance of spare parts through barcode or QR code scanning; The system integration module handles problems in the identification process, records event logs, implements data backtracking, and integrates all information into the spare parts management system to improve transparency and decision support.
9. A computer device comprising a memory and a processor, wherein the memory stores a computer program, wherein: When the processor executes the computer program, the steps of the method according to any one of claims 1 to 7 are implemented.