Urban substation flood control design reliability test method

By comprehensively measuring the monitoring data of heavy rain and flood process and the monitoring data of typical heavy rain and flood process, the reliability of flood control design of the substation network was analyzed, and the problem of failure to effectively consider climate change and lower surface changes in the existing technology was solved, and the accuracy of flood control design inspection results was improved.

CN119918132AActive Publication Date: 2025-05-02URBAN PLANNING & DESIGN INST OF SHENZHEN UPDIS
View PDF 10 Cites 0 Cited by

Patent Information

Application Number
CN202411955143.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-12-27
Publication Date
2025-05-02
Estimated Expiration
2044-12-27

AI Technical Summary

Technical Problem

In the prior art, the reliability inspection method for substation flood control design fails to effectively consider future climate change and urban underlay surface changes, resulting in low accuracy of inspection results.

Method used

By obtaining the measured rainstorm and flood process monitoring data, analyzing the flood control design reliability of the substation network, the first, second and third flood control design reliability analysis results are obtained, and these results are combined to obtain the final flood control design reliability inspection results.

Benefits of technology

The accuracy of the final flood control design reliability inspection results of the substation network is improved, and it can provide a basis for improvement for the flood control design of the substation to consider possible climate changes and urban underlay surface changes in the future.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119918132A_ABST
    Figure CN119918132A_ABST
Patent Text Reader

Abstract

The embodiment of the invention discloses an urban substation flood control design reliability test method, which comprises the following steps of: analyzing the flood control design reliability of a substation network by using actually measured rainstorm flood process monitoring data to obtain a first flood control design reliability analysis result; analyzing the flood control design reliability of the substation network by using the typical rainstorm flood process monitoring data to obtain a second flood control design reliability analysis result, and analyzing the flood control design reliability of the substation network by using the comprehensive rainstorm process monitoring data to obtain a third flood control design reliability analysis result; and integrating the first flood control design reliability analysis result, the second flood control design reliability analysis result and the third flood control design reliability analysis result to obtain a final flood control design reliability test result of the substation network, so that the accuracy of the final flood control design reliability test result of the substation network is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present disclosure relates to the technical field of power risk assessment, and in particular to a reliability inspection method for flood control design of an urban substation. Background Art

[0002] Water ingress into a substation will seriously affect power supply security, so prior inspection of the reliability of the substation's flood control design is crucial to the power supply security of the substation. However, the frequent occurrence of extreme rainstorm disasters and rapid urbanization have made flood disasters more severe. The reliability inspection method for substation flood control design in related technologies does not take into account future climate change and changes in urban underlying surfaces, resulting in low accuracy of the reliability inspection results of substation flood control design. Summary of the invention

[0003] The following is a summary of the subject matter of the detailed description of the present disclosure. This summary is not intended to limit the scope of the claims.

[0004] The disclosed embodiment provides a reliability test method for flood control design of an urban substation, which can improve the accuracy of the reliability test results of the final flood control design of the substation network. The reliability test results of the final flood control design of the substation network can be applied to the flood control design of the substation, and provide a practical and accurate basis for improving the flood control design of the substation.

[0005] An embodiment of the first aspect of the present disclosure provides a reliability inspection method for flood control design of an urban substation, comprising:

[0006] Obtain actual rainstorm and flood process monitoring data;

[0007] Analyzing the flood control design reliability of the substation network using the measured rainstorm and flood process monitoring data, and obtaining a first flood control design reliability analysis result of the substation network under the measured rainstorm and flood process monitoring data;

[0008] Selecting typical rainstorm and flood process monitoring data from the measured rainstorm and flood process monitoring data, using the typical rainstorm and flood process monitoring data to analyze the flood control design reliability of the substation network, and obtaining a second flood control design reliability analysis result of the substation network under the typical rainstorm and flood process monitoring data;

[0009] Comprehensively forming comprehensive rainstorm process monitoring data by integrating the adverse factors in the typical rainstorm and flood process monitoring data, and using the comprehensive rainstorm process monitoring data to analyze the flood control design reliability of the substation network, to obtain a third flood control design reliability analysis result of the substation network under the comprehensive rainstorm process monitoring data;

[0010] The final flood control design reliability test result of the substation network is obtained by combining the first flood control design reliability analysis result, the second flood control design reliability analysis result and the third flood control design reliability analysis result.

[0011] According to certain embodiments of the first aspect of the present disclosure, the flood control design reliability of the substation network includes whether the substation is flooded and failed, the order of the substation flooding and failure, the number of substations in the substation network that are flooded and failed, and the scale of substation failures; the use of the measured rainstorm and flood process monitoring data or the typical rainstorm and flood process monitoring data or the comprehensive rainstorm process monitoring data to analyze the flood control design reliability of the substation network includes:

[0012] Obtaining the topological relationship of the substation network;

[0013] Analyze and determine whether each of the substations in the substation network is flooded and failed according to the measured rainstorm and flood process monitoring data or the typical rainstorm and flood process monitoring data or the comprehensive rainstorm process monitoring data;

[0014] Determine the order of substation flooding failure according to the topological relationship of the substation network and the water inflow direction of the river system in the basin;

[0015] According to the topological relationship of the substation network, the number of substations that are flooded and failed in the substation network and the scale of the substation failures in different time periods are analyzed.

[0016] According to certain embodiments of the first aspect of the present disclosure, analyzing and determining whether each substation in the substation network is flooded and failed according to the measured rainstorm and flood process monitoring data or the typical rainstorm and flood process monitoring data or the comprehensive rainstorm process monitoring data includes:

[0017] Obtain urban terrain and street view data, urban drainage network data, urban river and river terrain data, substation floor elevation data, and substation cable joint elevation data;

[0018] For each of the substations in the substation network, determining a substation flood control standard according to the substation grade;

[0019] According to the measured rainstorm and flood process monitoring data or the typical rainstorm and flood process monitoring data or the comprehensive rainstorm process monitoring data, combined with the substation flood control standard, the urban terrain and streetscape data, the urban drainage network data, the urban rivers and river terrain data, based on the inference formula method in the rainstorm runoff calculation chart, determine the design flood water level under the return period;

[0020] The designed flood water level is compared with the substation floor elevation data and the substation cable joint elevation data to determine whether each substation is flooded and fails.

[0021] According to certain embodiments of the first aspect of the present disclosure, the measured rainstorm and flood process monitoring data or the typical rainstorm and flood process monitoring data or the comprehensive rainstorm process monitoring data, combined with the substation flood control standard, the urban terrain and streetscape data, the urban drainage network data, the urban rivers and river terrain data, based on the inference formula method in the rainstorm runoff calculation chart, determines the design flood water level under the return period, including:

[0022] Determining the return period according to the substation flood control standard;

[0023] According to the measured rainstorm and flood process monitoring data or the typical rainstorm and flood process monitoring data or the comprehensive rainstorm process monitoring data, the rainstorm parameters are determined based on the inference formula method in the rainstorm runoff calculation chart, and the design rainstorm data is calculated based on the rainstorm parameters, the recurrence period, the urban terrain and streetscape data, the urban drainage network data, the urban rivers and river terrain data, and the rainstorm contour map;

[0024] According to the designed rainstorm data, the urban terrain and streetscape data, the urban drainage network data, and the urban rivers and river terrain data, the inference formula method in the rainstorm runoff calculation chart is used to calculate the runoff generation and confluence, and the designed flood process line is obtained based on the runoff generation and confluence;

[0025] The peak flow in the design flood process line is extracted, and the peak flow is substituted into the water level and flow relationship curve to calculate the design flood water level under the recurrence period.

[0026] According to certain embodiments of the first aspect of the present disclosure, the selecting typical rainstorm and flood process monitoring data from the measured rainstorm and flood process monitoring data includes:

[0027] The frequency of the measured rainstorm and flood process monitoring data is calculated based on the measured rainstorm and flood process monitoring data, and the frequency of the measured rainstorm and flood is sorted from high to low, and the measured rainstorm and flood process monitoring data whose frequency of the measured rainstorm and flood is before the preset ranking is used as the typical rainstorm and flood process monitoring data.

[0028] According to certain embodiments of the first aspect of the present disclosure, the calculating the frequency of measured heavy rain and flood according to the measured heavy rain and flood process monitoring data includes:

[0029] The rainstorm and flood level and type of each measured rainstorm and flood are obtained from each of the measured rainstorm and flood process monitoring data, the number of occurrences of the rainstorm and flood level and type of the measured rainstorm and flood within the recurrence period is calculated, the total number of occurrences of the rainstorm and flood levels and types of all the measured rainstorm and floods within the recurrence period is counted, the proportion of the number of occurrences of the rainstorm and flood level and type of the measured rainstorm and flood within the recurrence period in the total number of occurrences is calculated, and the frequency of the measured rainstorm and flood is obtained.

[0030] According to certain embodiments of the first aspect of the present disclosure, the unfavorable factors in the typical rainstorm and flood process monitoring data include a long duration of the rainstorm, a high rainfall intensity of the rainstorm, and a large total precipitation of the rainstorm.

[0031] An embodiment of the second aspect of the present disclosure is an electronic device, which includes a memory and a processor, wherein the memory stores a computer program, and when the processor executes the computer program, it implements the reliability inspection method for flood control design of an urban substation as described above.

[0032] An embodiment of the third aspect of the present disclosure is a storage medium, wherein the storage medium stores a computer program, and when the computer program is executed by a processor, the reliability verification method for flood control design of an urban substation is implemented as described above.

[0033] The disclosed embodiments include at least the following beneficial effects: obtaining measured rainstorm and flood process monitoring data; using the measured rainstorm and flood process monitoring data to analyze the flood control design reliability of the substation network, and obtaining a first flood control design reliability analysis result of the substation network under the measured rainstorm and flood process monitoring data; selecting typical rainstorm and flood process monitoring data from the measured rainstorm and flood process monitoring data, and using the typical rainstorm and flood process monitoring data to analyze the flood control design reliability of the substation network, and obtaining a second flood control design reliability analysis result of the substation network under the typical rainstorm and flood process monitoring data; comprehensively forming comprehensive rainstorm process monitoring data by integrating adverse factors in each typical rainstorm and flood process monitoring data, and using the comprehensive rainstorm process monitoring data to analyze the flood control design reliability of the substation network, and obtaining a third flood control design reliability analysis result of the substation network under the comprehensive rainstorm process monitoring data; comprehensively integrating the first flood control design reliability analysis result, the second flood control design reliability analysis result, and the third flood control design reliability analysis result, and obtaining a final flood control design reliability test result of the substation network. The reliability of flood control design of substation network is analyzed based on the monitoring data of typical rainstorm and flood processes that have occurred in the city, which is in line with the situation of extreme rainstorm and flood and rapid change of urban underlying surface under the current changing environment, and improves the accuracy of the final flood control design reliability test results of substation network. And the adverse factors of the monitoring data of typical rainstorm and flood processes that have occurred in the city are integrated to form the comprehensive rainstorm process monitoring data that has occurred in the basin and may occur in the future. The reliability of flood control design of substation network is analyzed based on this comprehensive rainstorm process monitoring data, taking into account the possible climate change in the future, and improving the accuracy of the final flood control design reliability test results of substation network. And the final flood control design reliability test results of substation network can be applied to the flood control design of substation, which can provide a basis for improving flood control design for substation effectively and accurately.

[0034] Other features and advantages of the present disclosure will be set forth in the following description, and in part will be apparent from the description, or may be learned by practicing the present disclosure. BRIEF DESCRIPTION OF THE DRAWINGS

[0035] The accompanying drawings are used to provide further understanding of the technical solution of the present disclosure and constitute a part of the specification. Together with the embodiments of the present disclosure, they are used to explain the technical solution of the present disclosure and do not constitute a limitation on the technical solution of the present disclosure.

[0036] Figure 1 An optional flow chart of a reliability inspection method for flood control design of an urban substation provided by an embodiment of the present disclosure;

[0037] Figure 2 An optional flow chart for analyzing the reliability of flood control design of a substation network provided in an embodiment of the present disclosure;

[0038] Figure 3 The embodiments of the present disclosure provide Figure 2 An optional flowchart of step 202;

[0039] Figure 4 The embodiments of the present disclosure provide Figure 3 An optional flowchart of step 303 in FIG. DETAILED DESCRIPTION

[0040] In order to make the purpose, technical solution and advantages of the present disclosure more clear, the present disclosure is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present disclosure and are not used to limit the present disclosure.

[0041] In the embodiments of the present disclosure, the term "module" or "unit" refers to a computer program or a part of a computer program with a predetermined function, and works together with other related parts to achieve a predetermined goal, and can be implemented in whole or in part by using software, hardware (such as processing circuits or memories) or a combination thereof. Similarly, a processor (or multiple processors or memories) can be used to implement one or more modules or units. In addition, each module or unit can be part of an overall module or unit that includes the function of the module or unit.

[0042] Unless otherwise defined, all technical and scientific terms used herein have the same meaning as those commonly understood by those skilled in the art to which the present disclosure belongs. The terms used herein are only for the purpose of describing the embodiments of the present disclosure and are not intended to limit the present disclosure.

[0043] The embodiments of the present disclosure are further described below in conjunction with the accompanying drawings.

[0044] Reference Figure 1 As shown, Figure 1 An optional flow chart of a reliability test method for flood control design of a city substation provided in an embodiment of the present disclosure, the reliability test method for flood control design of a city substation includes but is not limited to steps 101 to 105, and each step is introduced in turn below.

[0045] Step 101: Obtain actual rainstorm and flood process monitoring data.

[0046] Specifically, a rainstorm flood is a flood caused by heavy rainfall, which causes a rapid increase in the amount of water in rivers and a sharp rise in water levels. It is the most common and most threatening flood. It can be simply understood that a rainstorm flood refers to a flood caused by heavy rain.

[0047] Step 102: Analyze the flood control design reliability of the substation network using the measured rainstorm and flood process monitoring data to obtain a first flood control design reliability analysis result of the substation network under the measured rainstorm and flood process monitoring data.

[0048] Specifically, the flood control design reliability of the substation network is analyzed using the measured rainstorm and flood process monitoring data, and the first flood control design reliability analysis result of the substation network under the measured rainstorm and flood process monitoring data is obtained. The analysis of the flood control design reliability of the substation network based on the measured rainstorm and flood process monitoring data that have occurred in the city conforms to the actual situation of the substation network in the city, can improve the accuracy of the first flood control design reliability analysis result of the substation network, and improve the accuracy of the final flood control design reliability test result of the substation network.

[0049] Step 103: Select typical rainstorm and flood process monitoring data from the measured rainstorm and flood process monitoring data, use the typical rainstorm and flood process monitoring data to analyze the flood control design reliability of the substation network, and obtain the second flood control design reliability analysis result of the substation network under the typical rainstorm and flood process monitoring data.

[0050] Specifically, typical rainstorm and flood refer to measured rainstorm and flood that are representative and more likely to occur. Typical rainstorm and flood process monitoring data are selected from the measured rainstorm and flood process monitoring data, and the flood control design reliability of the substation network is analyzed using the typical rainstorm and flood process monitoring data to obtain the second flood control design reliability analysis results of the substation network under the typical rainstorm and flood process monitoring data. The flood control design reliability of the substation network is analyzed based on the typical rainstorm and flood process monitoring data that have occurred in the city, which conforms to the current changing environment of extreme rainstorms and floods and the rapid changes in the underlying surface of the city, and can improve the accuracy of the second flood control design reliability analysis results of the substation network, and improve the accuracy of the final flood control design reliability test results of the substation network.

[0051] In some embodiments, typical rainstorm and flood process monitoring data are selected from the measured rainstorm and flood process monitoring data, including: calculating the frequency of measured rainstorm and floods based on the measured rainstorm and flood process monitoring data, and sorting the frequency of measured rainstorm and floods from high to low, and taking the measured rainstorm and flood process monitoring data whose frequency of measured rainstorm and floods is before a preset ranking as typical rainstorm and flood process monitoring data.

[0052] It can be understood that by calculating the frequency of measured rainstorms and floods, sorting the frequencies of measured rainstorms and floods from high to low, and selecting the measured rainstorm and flood process monitoring data corresponding to the measured rainstorms and floods with high frequencies as the typical rainstorm and flood process monitoring data, the measured rainstorms and floods with higher frequencies are more representative and more likely to occur in the future, which can more accurately predict the possible rainstorm and flood events in the future, and improve the accuracy of the reliability analysis results of the second flood control design of the substation network. The measured rainstorm and flood process monitoring data corresponding to the measured rainstorm and floods with higher frequencies are more in line with the extreme rainstorms and floods and the rapid changes in the urban underlying surface under the current changing environment, and improve the accuracy of the reliability analysis results of the second flood control design of the substation network.

[0053] In some embodiments, the frequency of measured rainstorms and floods is calculated based on measured rainstorm and flood process monitoring data, including: obtaining the rainstorm and flood level and type of each measured rainstorm and flood from each measured rainstorm and flood process monitoring data, calculating the number of occurrences of the rainstorm and flood level and type of the measured rainstorm and flood within the recurrence period, counting the total number of occurrences of the rainstorm and flood levels and types of all measured rainstorm and floods within the recurrence period, calculating the proportion of the number of occurrences of the rainstorm and flood level and type of the measured rainstorm and flood within the recurrence period in the total number of occurrences, and obtaining the frequency of the measured rainstorm and flood.

[0054] It is understandable that the level and type of rainstorm floods can directly reflect the intensity and characteristics of rainfall, and comprehensive consideration of the level and type of rainstorm floods can more accurately predict possible rainstorm flood events in the future. The frequency of measured rainstorm floods is calculated based on the level and type of rainstorm floods of the measured rainstorm floods. The calculated frequency of measured rainstorm floods is more representative for accurately predicting possible rainstorm flood events in the future, and can improve the accuracy of the reliability analysis results of the second flood control design of the substation network.

[0055] Step 104: Integrate the adverse factors in the typical rainstorm and flood process monitoring data to form comprehensive rainstorm process monitoring data, use the comprehensive rainstorm process monitoring data to analyze the flood control design reliability of the substation network, and obtain the third flood control design reliability analysis result of the substation network under the comprehensive rainstorm process monitoring data.

[0056] In some embodiments, unfavorable factors in typical rainstorm flood process monitoring data include long duration of the rainstorm, high rainfall intensity of the rainstorm, and large total precipitation of the rainstorm.

[0057] It can be understood that the adverse factors of the monitoring data of various typical rainstorm and flood processes that have occurred in the city are integrated to form the comprehensive rainstorm process monitoring data that has occurred in the basin and may occur in the future. Based on this comprehensive rainstorm process monitoring data, the flood control design reliability of the substation network is analyzed, and the possible climate change in the future is taken into account, which improves the accuracy of the third flood control design reliability analysis results of the substation network, and improves the accuracy of the final flood control design reliability test results of the substation network.

[0058] In some embodiments, the flood prevention design reliability of the substation network includes whether the substation fails due to flooding, the order of substation failure due to flooding, the number of substations in the substation network that fail due to flooding, and the scale of substation failure. Figure 2 As shown, Figure 2 An optional flow chart for analyzing the flood control design reliability of a substation network provided in an embodiment of the present disclosure uses measured rainstorm and flood process monitoring data or typical rainstorm and flood process monitoring data or comprehensive rainstorm process monitoring data to analyze the flood control design reliability of a substation network, including but not limited to the following steps 201 to 204.

[0059] Step 201: Obtain the topological relationship of the substation network.

[0060] Step 202: Analyze and determine whether each substation in the substation network is flooded and ineffective based on the measured rainstorm and flood process monitoring data or the typical rainstorm and flood process monitoring data or the comprehensive rainstorm process monitoring data.

[0061] Step 203: Determine the order of substation flooding failure according to the topological relationship of the substation network and the water inflow direction of the river system in the basin.

[0062] Step 204: Analyze the number of substations that are flooded and failed in the substation network and the scale of substation failures in different time periods according to the topological relationship of the substation network.

[0063] Specifically, based on the measured rainstorm and flood process monitoring data or typical rainstorm and flood process monitoring data or comprehensive rainstorm process monitoring data, analyze and determine whether each substation in the substation network is flooded and failed. After determining whether each substation is flooded and failed, determine the order of substation flooding and failure based on whether each substation is flooded and failed, combined with the topological relationship of the substation network and the direction of water inflow of the river system in the basin. Based on whether each substation is flooded and failed, combined with the topological relationship of the substation network, analyze the number of substations that are flooded and failed in the substation network and the scale of substation failures in different time periods.

[0064] It can be understood that, firstly, based on the measured rainstorm and flood process monitoring data or the typical rainstorm and flood process monitoring data or the comprehensive rainstorm process monitoring data, it is analyzed and determined whether each substation in the substation network is flooded and failed, and then the flood control design reliability of the substation network is further analyzed, thus realizing the transition from the flood control design reliability analysis of a single substation site to the flood control design reliability analysis of the substation network. The analysis is more comprehensive, and the final flood control design reliability test results of the substation network are more accurate.

[0065] In some embodiments, reference Figure 3 As shown, Figure 3 The embodiments of the present disclosure provide Figure 2 An optional flowchart of step 202, based on measured rainstorm and flood process monitoring data or typical rainstorm and flood process monitoring data or comprehensive rainstorm process monitoring data, analyzes and determines whether each substation in the substation network is flooded and failed, including but not limited to the following steps 301 to 304.

[0066] Step 301: Acquire urban terrain and street view data, urban drainage network data, urban river and river terrain data, substation floor elevation data, and substation cable joint elevation data.

[0067] Step 302: For each substation in the substation network, determine the substation flood control standard according to the substation level.

[0068] Step 303: According to the measured rainstorm and flood process monitoring data or the typical rainstorm and flood process monitoring data or the comprehensive rainstorm process monitoring data, combined with the substation flood control standards, urban terrain and streetscape data, urban drainage network data, urban rivers and river terrain data, based on the inference formula method in the rainstorm runoff calculation chart, determine the design flood water level under the recurrence period.

[0069] Step 304: Compare the designed flood water level with the substation floor elevation data and the substation cable joint elevation data to determine whether each substation is flooded and fails.

[0070] Specifically, the design flood refers to the flood that is likely to occur in a local area and is planned for the design of flood control projects and meets the specified flood control design standards. The design flood is the maximum flood that flood control planning and flood control projects are expected to prevent.

[0071] It is understandable that the cable joint, as an important part of the substation, can accurately judge and determine whether each substation is submerged and failed by comparing the design flood water level with the substation cable joint elevation data. By comparing the design flood water level with the substation floor elevation data, it is determined whether each substation is submerged and failed, and then the final flood control design reliability test results of the substation network are obtained based on whether each substation is submerged and failed. The final flood control design reliability test results of the substation network are applied to the flood control design of the substation. The substation floor is raised according to the final flood control design reliability test results of the substation network. The final flood control design reliability test results of the substation network can effectively and accurately provide a basis for improving the flood control design of the substation. In addition, the design flood water level is comprehensively compared with the substation floor elevation data and the substation cable joint elevation data to determine whether each substation is submerged and failed, which improves the accuracy of the final flood control design reliability test results of the substation network.

[0072] In some embodiments, reference Figure 4 As shown, Figure 4 The embodiments of the present disclosure provide Figure 3 An optional flow chart of step 303, based on measured rainstorm and flood process monitoring data or typical rainstorm and flood process monitoring data or comprehensive rainstorm process monitoring data, combined with substation flood control standards, urban terrain and streetscape data, urban drainage network data, urban rivers and river terrain data, based on the inference formula method in the rainstorm runoff calculation chart, determines the design flood water level under the recurrence period, including but not limited to the following steps 401 to 404.

[0073] Step 401: Determine the recurrence period according to the substation flood control standard.

[0074] Step 402: Determine the rainstorm parameters based on the inference formula method in the rainstorm runoff calculation chart according to the measured rainstorm and flood process monitoring data or the typical rainstorm and flood process monitoring data or the comprehensive rainstorm process monitoring data, and calculate the designed rainstorm data according to the rainstorm parameters, recurrence period, urban terrain and streetscape data, urban drainage network data, urban river and river terrain data, and rainstorm contour map.

[0075] Step 403: Calculate the runoff and confluence using the inference formula method in the storm runoff calculation chart based on the designed storm data, urban topography and streetscape data, urban drainage network data, and urban rivers and river terrain data, and obtain the designed flood process line based on the runoff and confluence.

[0076] Step 404: extract the peak flow in the design flood process line, substitute the peak flow into the water level and flow relationship curve to calculate the design flood water level under the recurrence period.

[0077] Specifically, design rainstorm refers to the rainstorm that is planned for the design of flood control projects, meets the specified design standards, and is likely to occur locally. Design rainstorm is used to derive the design flood.

[0078] It can be understood that the design flood water level is calculated based on the measured rainstorm and flood process monitoring data or the typical rainstorm and flood process monitoring data or the comprehensive rainstorm process monitoring data, combined with the urban terrain and streetscape data, urban drainage network data, urban rivers and river terrain data. In addition to considering the rainfall intensity in the city, the design flood water level also takes into account the city’s topography and drainage conditions, which is in line with the actual situation and improves the accuracy of the calculated design flood water level.

[0079] In some embodiments, for each substation in the substation network, the substation flood control standard is determined according to the substation level, and the recurrence period is determined according to the substation flood control standard, wherein one substation corresponds to one recurrence period, and multiple different recurrence periods are obtained. According to the measured rainstorm flood process monitoring data or typical rainstorm flood process monitoring data or comprehensive rainstorm process monitoring data, the rainstorm parameters are determined based on the inference formula method in the rainstorm runoff calculation chart, and the design rainstorm data is calculated according to the rainstorm parameters, multiple different recurrence periods, urban terrain and streetscape data, urban drainage network data, urban rivers and river terrain data, and rainstorm contour map; according to the design rainstorm data, urban terrain and streetscape data, urban drainage network data, urban rivers and river terrain data, the inference formula method in the rainstorm runoff calculation chart is used to calculate the runoff and confluence, and the design flood process line is calculated according to the runoff and confluence; the peak flow in the design flood process line is extracted, and the peak flow is substituted into the water level and flow relationship curve to calculate the design flood water level under multiple different recurrence periods. By comparing the design flood water levels under multiple different return periods with the substation floor elevation data and substation cable joint elevation data, it is determined whether each substation will be flooded and fail under different return periods, and the final flood control design reliability test results of the substation network under multiple different return periods are obtained.

[0080] Step 105: The first flood control design reliability analysis result, the second flood control design reliability analysis result, and the third flood control design reliability analysis result are integrated to obtain a final flood control design reliability test result of the substation network.

[0081] It can be seen that the measured rainstorm and flood process monitoring data are obtained; the measured rainstorm and flood process monitoring data are used to analyze the flood control design reliability of the substation network, and the first flood control design reliability analysis result of the substation network under the measured rainstorm and flood process monitoring data is obtained; typical rainstorm and flood process monitoring data are selected from the measured rainstorm and flood process monitoring data, and the flood control design reliability of the substation network is analyzed using the typical rainstorm and flood process monitoring data, and the second flood control design reliability analysis result of the substation network under the typical rainstorm and flood process monitoring data is obtained; the adverse factors in the typical rainstorm and flood process monitoring data are integrated to form comprehensive rainstorm process monitoring data, and the flood control design reliability of the substation network is analyzed using the comprehensive rainstorm process monitoring data, and the third flood control design reliability analysis result of the substation network under the comprehensive rainstorm process monitoring data is obtained; the first flood control design reliability analysis result, the second flood control design reliability analysis result, and the third flood control design reliability analysis result are integrated to obtain the final flood control design reliability test result of the substation network. The reliability of flood control design of substation network is analyzed based on the monitoring data of typical rainstorm and flood processes that have occurred in the city, which is in line with the situation of extreme rainstorm and flood and rapid change of urban underlying surface under the current changing environment, and improves the accuracy of the final flood control design reliability test results of substation network. And the adverse factors of the monitoring data of typical rainstorm and flood processes that have occurred in the city are integrated to form the comprehensive rainstorm process monitoring data that has occurred in the basin and may occur in the future. The reliability of flood control design of substation network is analyzed based on this comprehensive rainstorm process monitoring data, taking into account the possible climate change in the future, and improving the accuracy of the final flood control design reliability test results of substation network. And the final flood control design reliability test results of substation network can be applied to the flood control design of substation, which can provide a basis for improving flood control design for substation effectively and accurately.

[0082] In some embodiments, measured rainstorm and flood process monitoring data, urban terrain and street view data, urban drainage network data, urban river and river terrain data, substation floor elevation data, substation cable joint elevation data, and substation network topological relationships are obtained. The measured rainstorm and flood process monitoring data are used to analyze the flood control design reliability of the substation network, and the first flood control design reliability analysis result of the substation network under the measured rainstorm and flood process monitoring data is obtained; according to the frequency of measured rainstorm and flood, typical rainstorm and flood process monitoring data are selected from the measured rainstorm and flood process monitoring data, and the flood control design reliability of the substation network is analyzed using the typical rainstorm and flood process monitoring data, and the second flood control design reliability analysis result of the substation network under the typical rainstorm and flood process monitoring data is obtained; the unfavorable factors in the typical rainstorm and flood process monitoring data include long duration of rainstorm, high rainfall intensity of rainstorm and large total precipitation of rainstorm, and the unfavorable factors in the typical rainstorm and flood process monitoring data are integrated to form comprehensive rainstorm process monitoring data, and the flood control design reliability of the substation network is analyzed using the comprehensive rainstorm process monitoring data, and the third flood control design reliability analysis result of the substation network under the comprehensive rainstorm process monitoring data is obtained; the first flood control design reliability analysis result, the second flood control design reliability analysis result and the third flood control design reliability analysis result are integrated to obtain the final flood control design reliability test result of the substation network.

[0083] Among them, the reliability of flood control design of substation network is analyzed using measured rainstorm and flood process monitoring data or typical rainstorm and flood process monitoring data or comprehensive rainstorm process monitoring data, including: analyzing and determining whether each substation in the substation network is flooded and failed according to the measured rainstorm and flood process monitoring data or typical rainstorm and flood process monitoring data or comprehensive rainstorm process monitoring data; determining the order of substation flooding and failure according to the topological relationship of the substation network and the direction of water inflow of the basin water system; analyzing the number of substations flooded and failed in the substation network and the scale of substation failures in different time periods according to the topological relationship of the substation network.

[0084] Among them, according to the measured rainstorm and flood process monitoring data or the typical rainstorm and flood process monitoring data or the comprehensive rainstorm process monitoring data, analyze and determine whether each substation in the substation network is flooded and invalid, including: for each substation in the substation network, determine the substation flood control standard according to the substation level, and determine the recurrence period according to the substation flood control standard; according to the measured rainstorm and flood process monitoring data or the typical rainstorm and flood process monitoring data or the comprehensive rainstorm process monitoring data, combined with the substation flood control standard, urban terrain and streetscape data, urban drainage network data, urban rivers and river terrain data, based on the inference formula method in the rainstorm runoff calculation chart, determine the design flood water level under the recurrence period; compare the design flood water level with the substation floor elevation data and the substation cable joint elevation data to determine whether each substation is flooded and invalid.

[0085] The disclosed embodiment also provides an electronic device, the electronic device includes a memory and a processor, the memory stores a computer program, and the processor implements the above-mentioned reliability inspection method for flood control design of urban substation when executing the computer program. The electronic device can be any intelligent terminal including a computer.

[0086] The embodiment of the present disclosure further provides a storage medium storing a computer program, which implements the above-mentioned reliability inspection method for flood control design of a city substation when the computer program is executed by a processor.

[0087] The terms "first", "second", "third", "fourth", etc. (if any) in the specification of the present disclosure and the above-mentioned drawings are used to distinguish similar objects, and are not necessarily used to describe a specific order or sequence. It should be understood that the data used in this way can be interchanged where appropriate to describe the embodiments of the present disclosure, such as being able to be implemented in an order other than those illustrated or described herein. In addition, the terms "including" and "having" and any variations thereof are intended to cover non-exclusive inclusions, for example, a process, method, system, product or device that includes a series of steps or units is not necessarily limited to those steps or units clearly listed, but may include other steps or units that are not clearly listed or inherent to these processes, methods, products or devices.

[0088] It should be understood that in the present disclosure, "at least one (item)" means one or more, and "plurality" means two or more. "And / or" is used to describe the association relationship of associated objects, indicating that three relationships may exist. For example, "A and / or B" can mean: only A exists, only B exists, and A and B exist at the same time, where A and B can be singular or plural. The character " / " generally indicates that the objects associated before and after are in an "or" relationship. "At least one of the following" or similar expressions refers to any combination of these items, including any combination of single or plural items. For example, at least one of a, b or c can mean: a, b, c, "a and b", "a and c", "b and c", or "a and b and c", where a, b, c can be single or multiple.

[0089] It should be understood that in the description of the embodiments of the present disclosure, the meaning of multiple (or multiple items) is more than two, greater than, less than, exceed, etc. are understood to not include the number, and above, below, within, etc. are understood to include the number.

[0090] It should also be understood that the various implementations provided in the embodiments of the present disclosure can be combined arbitrarily to achieve different technical effects.

[0091] The above is a specific description of the preferred implementation of the present disclosure, but the present disclosure is not limited to the above-mentioned implementation mode. Technical personnel familiar with the field can also make various equivalent deformations or substitutions under the shared conditions without violating the spirit of the present disclosure. These equivalent deformations or substitutions are all included in the scope defined by the claims of the present disclosure.

Claims

1. A reliability test method for flood control design of urban substation, characterized in that: include: Obtain actual rainstorm and flood process monitoring data; Analyzing the flood control design reliability of the substation network using the measured rainstorm and flood process monitoring data, and obtaining a first flood control design reliability analysis result of the substation network under the measured rainstorm and flood process monitoring data; Selecting typical rainstorm and flood process monitoring data from the measured rainstorm and flood process monitoring data, using the typical rainstorm and flood process monitoring data to analyze the flood control design reliability of the substation network, and obtaining a second flood control design reliability analysis result of the substation network under the typical rainstorm and flood process monitoring data; Comprehensively forming comprehensive rainstorm process monitoring data by integrating the adverse factors in the typical rainstorm and flood process monitoring data, and using the comprehensive rainstorm process monitoring data to analyze the flood control design reliability of the substation network, to obtain a third flood control design reliability analysis result of the substation network under the comprehensive rainstorm process monitoring data; The final flood control design reliability test result of the substation network is obtained by combining the first flood control design reliability analysis result, the second flood control design reliability analysis result and the third flood control design reliability analysis result.

2. A reliability inspection method for flood control design of urban substation according to claim 1, characterized in that: The flood control design reliability of the substation network includes whether the substation fails due to flooding, the order of the substation failure due to flooding, the number of substations that fail due to flooding in the substation network, and the scale of substation failures; the use of the measured rainstorm and flood process monitoring data or the typical rainstorm and flood process monitoring data or the comprehensive rainstorm process monitoring data to analyze the flood control design reliability of the substation network includes: Obtaining the topological relationship of the substation network; Analyze and determine whether each of the substations in the substation network is flooded and failed according to the measured rainstorm and flood process monitoring data or the typical rainstorm and flood process monitoring data or the comprehensive rainstorm process monitoring data; Determine the order of substation flooding failure according to the topological relationship of the substation network and the water inflow direction of the river system in the basin; According to the topological relationship of the substation network, the number of substations that are flooded and failed in the substation network and the scale of the substation failures in different time periods are analyzed.

3. A reliability inspection method for flood control design of urban substation according to claim 2, characterized in that: The analyzing and determining whether each substation in the substation network is flooded and failed according to the measured rainstorm and flood process monitoring data or the typical rainstorm and flood process monitoring data or the comprehensive rainstorm process monitoring data comprises: Obtain urban terrain and street view data, urban drainage network data, urban river and river terrain data, substation floor elevation data, and substation cable joint elevation data; For each of the substations in the substation network, determining a substation flood control standard according to the substation grade; According to the measured rainstorm and flood process monitoring data or the typical rainstorm and flood process monitoring data or the comprehensive rainstorm process monitoring data, combined with the substation flood control standard, the urban terrain and streetscape data, the urban drainage network data, the urban rivers and river terrain data, based on the inference formula method in the rainstorm runoff calculation chart, determine the design flood water level under the return period; The designed flood water level is compared with the substation floor elevation data and the substation cable joint elevation data to determine whether each substation is flooded and fails.

4. A reliability inspection method for flood control design of urban substation according to claim 3, characterized in that: The method of determining the design flood level under the return period based on the measured rainstorm and flood process monitoring data or the typical rainstorm and flood process monitoring data or the comprehensive rainstorm process monitoring data, in combination with the substation flood control standard, the urban terrain and streetscape data, the urban drainage network data, the urban rivers and river terrain data, and based on the inference formula method in the rainstorm runoff calculation chart, includes: Determining the return period according to the substation flood control standard; According to the measured rainstorm and flood process monitoring data or the typical rainstorm and flood process monitoring data or the comprehensive rainstorm process monitoring data, the rainstorm parameters are determined based on the inference formula method in the rainstorm runoff calculation chart, and the design rainstorm data is calculated based on the rainstorm parameters, the recurrence period, the urban terrain and streetscape data, the urban drainage network data, the urban rivers and river terrain data, and the rainstorm contour map; According to the designed rainstorm data, the urban terrain and streetscape data, the urban drainage network data, and the urban rivers and river terrain data, the inference formula method in the rainstorm runoff calculation chart is used to calculate the runoff generation and confluence, and the designed flood process line is obtained based on the runoff generation and confluence; The peak flow in the design flood process line is extracted, and the peak flow is substituted into the water level and flow relationship curve to calculate the design flood water level under the recurrence period.

5. A reliability inspection method for flood control design of urban substation according to claim 1, characterized in that: The selecting of typical rainstorm and flood process monitoring data from the measured rainstorm and flood process monitoring data comprises: The frequency of the measured rainstorm and flood process monitoring data is calculated based on the measured rainstorm and flood process monitoring data, and the frequency of the measured rainstorm and flood is sorted from high to low, and the measured rainstorm and flood process monitoring data whose frequency of the measured rainstorm and flood is before the preset ranking is used as the typical rainstorm and flood process monitoring data.

6. A reliability inspection method for flood control design of urban substation according to claim 5, characterized in that: The method of calculating the frequency of measured rainstorm and flood according to the measured rainstorm and flood process monitoring data comprises: The rainstorm and flood level and type of each measured rainstorm and flood are obtained from each of the measured rainstorm and flood process monitoring data, the number of occurrences of the rainstorm and flood level and type of the measured rainstorm and flood within the recurrence period is calculated, the total number of occurrences of the rainstorm and flood levels and types of all the measured rainstorm and floods within the recurrence period is counted, the proportion of the number of occurrences of the rainstorm and flood level and type of the measured rainstorm and flood within the recurrence period in the total number of occurrences is calculated, and the frequency of the measured rainstorm and flood is obtained.

7. A reliability inspection method for flood control design of urban substation according to claim 1, characterized in that: The unfavorable factors in the typical rainstorm and flood process monitoring data include long duration of the rainstorm, high rainfall intensity of the rainstorm, and large total precipitation of the rainstorm.

8. An electronic device, characterized in that: The electronic device includes a memory and a processor, the memory stores a computer program, and the processor implements the reliability inspection method for flood control design of an urban substation as described in any one of claims 1 to 7 when executing the computer program.

9. A storage medium storing a computer program, characterized in that: When the computer program is executed by a processor, a reliability inspection method for flood control design of an urban substation according to any one of claims 1 to 7 is implemented.

Citation Information

Patent Citations

  • Method for designing rainstorm-flood frequency assumption test under changing environment

    CN108280792A

  • Typhoon rainstorm flood disaster full life cycle monitoring method and system

    CN110009158A

  • Transformer substation ponding submerging calculation method based on high-precision DEM

    CN113762756A

  • Substation flood inundation risk early warning method and system based on different influence types

    CN115186858A

  • Transformer substation rainfall flood risk assessment model construction method based on simulation

    CN116739341A