A grouting positioning device for a steel pipe wood core filling column and a grouting method thereof

By using a grouting positioning device for steel pipe and wood core filled columns, grouting is performed from bottom to top, and the steel pipe and wood core are positioned using fixing components. This solves the problems of uneven grouting and air bubbles, ensuring the experimental reliability of steel pipe and wood core filled columns.

CN119933364BActive Publication Date: 2025-12-16GUANGZHOU NO 1 CONSTR ENG +2
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202510266126.1
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2025-03-07
Publication Date
2025-12-16
Estimated Expiration
2045-03-07

AI Technical Summary

Technical Problem

During the grouting process of steel pipe wood core filled columns, it is difficult to inject mortar when the wood diameter is large, the vibrator cannot enter the gap for vibration, the wood eccentricity may affect the axial compressive strength test, and the lower gap may not be filled with mortar and may contain air bubbles.

Method used

A grouting positioning device for steel pipe and wood core filled columns is adopted, including a base and a fixing component. The fixing component positions the steel pipe and wood core, and grouting is carried out from bottom to top through the grouting channel to ensure uniform filling of mortar, and air bubbles are removed by gravity.

Benefits of technology

This method achieves uniform filling of the gap between the steel pipe and the wooden core, avoids the influence of air bubbles, and ensures the accuracy and reliability of the experiment.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119933364B_ABST
    Figure CN119933364B_ABST
Patent Text Reader

Abstract

The application relates to the technical field, in particular to a grouting positioning device for a steel pipe wood core filling column and a grouting method thereof, which comprises a base and a fixing assembly. A grouting channel is formed in the base and penetrates through the upper and lower bottom surfaces of the base. A fixing boss is arranged on the inner circumferential wall of the grouting channel. The bottom of the fixing assembly is inserted into the top of the grouting channel, and the fixing assembly is arranged on the top surface of the fixing boss. The fixing assembly comprises an outer circumferential steel pipe fixing mechanism and two wood core fixing mechanisms. The two wood core fixing mechanisms are sequentially and spacedly arranged in the up-down direction. The steel pipe fixing mechanism comprises a plurality of spacedly arranged telescopic rods. The two ends of each telescopic rod are respectively and detachably connected with one wood core fixing mechanism. The wood core fixing mechanism comprises a sleeving part and a clamping part. The sleeving part is detachably connected with the clamping part. The steel pipe and the wood core can be positioned by the application, so that the steel pipe wood core filling column is uniformly filled with mortar through grouting.
Need to check novelty before this filing date? Find Prior Art

Description

TECHNICAL FIELD

[0001] The present application relates to the technical field of steel pipe grouting, in particular to a grouting positioning device for a steel pipe wood core filled column and a grouting method thereof. BACKGROUND

[0002] In order to study the steel pipe wood core filled column, that is, to fill the mortar or concrete between the steel pipe and the wood to replace the steel pipe concrete column, the specific manufacturing steps are as follows: the wood is placed in the center of the steel pipe, the steel pipe and the wood are manually fixed, and then the grouting is carried out from top to bottom, and the vibration is carried out during the pouring process to ensure uniform filling. The wood, a renewable resource, is used to replace natural aggregate.

[0003] However, the following problems are found in the research process:

[0004] 1. If the diameter of the wood is large, the gap between the steel pipe and the wood is very small. On the one hand, it is difficult to fill the mortar into the gap; on the other hand, the gap is too small to put the vibrator into the gap for vibration, so that the mortar cannot completely fill the gap;

[0005] 2. The position of the steel pipe and the wood is manually fixed, which cannot guarantee that the wood is always in the center, and the wood may have a large eccentricity, which has a certain influence on the future axial compression experiment;

[0006] 3. When grouting from top to bottom, the mortar cannot fill the gap between the steel pipe and the wood well, and the lower part of the filled column may not be filled with mortar; or even if the lower part of the component is completely filled with mortar, it cannot be determined whether there are large air bubbles in the mortar in the gap, which affects the later experiment. SUMMARY

[0007] The purpose of the present application is to provide a grouting positioning device for a steel pipe wood core filled column and a grouting method thereof, which solves the problems mentioned in the background art and obtains a steel pipe wood core filled column with uniformly filled mortar or concrete gap.

[0008] To achieve the above purpose, a grouting positioning device for a steel pipe wood core filled column and a grouting method thereof are adopted, which comprises a base and a fixing assembly.

[0009] A grouting channel penetrating the upper and lower surfaces of the base is formed on the base, and a fixing boss is arranged on the inner peripheral wall of the grouting channel.

[0010] The bottom of the fixing assembly is matched and inserted into the top of the grouting channel, and the fixing assembly is arranged on the top surface of the fixing boss. The fixing assembly comprises a peripheral steel pipe fixing mechanism and two wood core fixing mechanisms. The two wood core fixing mechanisms are sequentially and spacedly arranged in the up-down direction. The steel pipe fixing mechanism comprises a plurality of spacedly arranged telescopic rods. The two ends of the telescopic rod are respectively and detachably connected with one wood core fixing mechanism. The wood core fixing mechanism comprises a sleeving part and a clamping part. The sleeving part is detachably connected with the clamping part. The sleeving part comprises a plurality of sleeves and a plurality of fixing cylinders. The two ends of the sleeve are respectively and slidably connected with one fixing cylinder. The fixing cylinder is matched and inserted into the top of the grouting channel and is slidably connected with the top surface of the fixing boss. The telescopic rod is detachably connected with the fixing cylinder. The clamping part comprises a fixing block, a plurality of cross rods and a plurality of limiting pieces. The plurality of cross rods are spacedly arranged on the outer periphery of the fixing block. One end of the cross rod is slidably connected with the fixing block. The cross rod can slide along the radial direction of the fixing block. The other end of the cross rod is detachably connected with the fixing cylinder. The plurality of limiting pieces are one-to-one correspondingly arranged on the plurality of cross rods. The limiting piece is partially protruded from the surface of the cross rod and can rotate along the axial direction of the cross rod.

[0011] As a preferred technical solution, the two ends of the telescopic rod are provided with first clamping grooves. The telescopic rod is clamped with the fixing cylinder through the first clamping grooves. The other end of the cross rod is provided with a second clamping groove. The cross rod is clamped with the fixing cylinder through the second clamping groove.

[0012] As a preferred technical solution, the limiting piece is a baffle.

[0013] As a preferred technical solution, an observation hole is arranged on the fixing block. The observation hole is located at the middle of the fixing block.

[0014] As a preferred technical solution, a plurality of locking bolts are arranged. The plurality of locking bolts are respectively used for locking the telescopic rod and the cross rod.

[0015] As a preferred technical solution, the base comprises a connecting part and a supporting part. The bottom end of the supporting part is slidably connected with the top end of the connecting part. The fixing boss is arranged on the inner peripheral wall of the supporting part.

[0016] The application also provides a grouting method of a steel pipe and wood core filling column, which comprises the following steps:

[0017] The wood core, the first wood core fixing mechanism, the second wood core fixing mechanism and the steel pipe fixing mechanism are waxed, the wood core is placed on the first wood core fixing mechanism, the center of the wood core is aligned with the center of the fixing block on the wood core fixing mechanism, the crossbar on the wood core fixing mechanism is slid so that the baffle on the crossbar is aligned with the outer peripheral wall of the wood core, the baffle is rotated so that the baffle is arranged upwards and is attached to the outer peripheral wall of the wood core, the steel pipe is placed on the wood core fixing mechanism, the outer peripheral size of the sleeve joint part on the wood core fixing mechanism is adjusted so that the outer peripheral wall of the steel pipe is attached to the inner peripheral wall of the sleeve joint part, the end of the crossbar away from the fixing block is detachably connected with the sleeve joint part, the steel pipe fixing mechanisms are installed on the sleeve joint part at intervals, the height of the steel pipe fixing mechanism is adjusted so that the top surface of the steel pipe fixing mechanism is flush with the top surface of the steel pipe and the inner wall of the steel pipe fixing mechanism is attached to the outer peripheral wall of the steel pipe, the second wood core fixing mechanism is detachably connected to the end of the steel pipe fixing mechanism away from the sleeve joint part, the sleeve joint part, the crossbar and the baffle on the second wood core fixing mechanism are adjusted so that the bottom surface of the second wood core fixing mechanism is attached to the top surface of the steel pipe and the wood core respectively, the installed steel pipe fixing assembly, the first wood core fixing mechanism, the second wood core fixing mechanism, the steel pipe and the wood core are placed on the base, the base is provided with a grouting channel penetrating through the upper and lower bottom surfaces thereof, the fixing boss is arranged along the inner peripheral wall of the grouting channel, the bottom of the first wood core fixing mechanism is inserted into the top of the grouting channel and the first wood core fixing mechanism is located on the top surface of the fixing boss, and the base is connected with the pumping pipe of the grouting machine.

[0018] S2, starting the grouting machine to start grouting, and closing the grouting machine when mortar overflows from the top end of the steel pipe;

[0019] S3, separating the base from the pumping pipe by using a steel sheet, removing and curing, and then sequentially removing the base, the second wood core fixing mechanism, the steel pipe fixing assembly, the first wood core fixing mechanism, the steel pipe and the wood core to obtain the steel pipe wood core filled column.

[0020] As a preferred technical solution, the base comprises a connecting part and a supporting part, the bottom end of the supporting part is slidably connected with the top end of the connecting part, and the fixing boss is arranged on the inner peripheral wall of the supporting part.

[0021] The step of separating the base from the pumping pipe by using a steel sheet specifically comprises: penetrating the steel sheet into the connection between the supporting part and the connecting part so that the base and the pumping pipe are separated.

[0022] Compared with the prior art, the grouting positioning device for the steel pipe wood core filled column and the grouting method thereof have the following beneficial effects:

[0023] 1、The base is connected with the pumping pipe of the grouting machine, and the mortar is grouted from bottom to top, so that the gap between the steel pipe and the wood core is filled with mortar, and due to the action of gravity, there are no large air bubbles in the mortar in the gap, which avoids affecting the later experiment;

[0024] 2、The fixed assembly is arranged to position the steel pipe and the wood core, so that the steel pipe and the wood core do not move during the grouting process, and the gap between the steel pipe and the wood core remains unchanged during the grouting process, which is beneficial to fill the gap with mortar and avoids affecting the later experiment. BRIEF DESCRIPTION OF DRAWINGS

[0025] The present application will be further described in detail in conjunction with the drawings and preferred embodiments, but those skilled in the art will appreciate that the drawings are only drawn for the purpose of explaining the preferred embodiments, and therefore should not be regarded as limiting the scope of the present application. In addition, unless specifically indicated, the drawings are only intended to conceptually represent the composition or structure of the described object and may include exaggerated display, and the drawings are not necessarily drawn to scale.

[0026] Figure 1 is a structural schematic view of the present application;

[0027] Figure 2 is a structural schematic view of the fixed assembly of the present application;

[0028] Figure 3 is a structural schematic view of the base of the present application;

[0029] Figure 4 is a structural schematic view of the clamping part of the present application;

[0030] Figure 5 is a structural schematic view of the sleeve part of the present application;

[0031] Wherein: 1, base; 11, connecting part; 12, supporting part; 121, fixed boss; 13, grouting channel; 2, fixed assembly; 21, steel pipe fixing mechanism; 211, telescopic rod; 2110, first clamping groove; 22, wood core fixing mechanism; 221, sleeve part; 2211, sleeve; 2212, fixed cylinder; 222, clamping part; 2220, fixed block; 2221, cross bar; 2222, limiting piece; 2223, observation hole; 2224, second clamping groove; 3, locking bolt. DETAILED DESCRIPTION

[0032] The embodiments of the present application are described in detail below, and examples of the embodiments are shown in the drawings, wherein the same or similar reference signs represent the same or similar elements or elements having the same or similar functions throughout. The embodiments described below by reference to the drawings are exemplary and are intended to explain the present application, and cannot be understood as limiting the present application.

[0033] In the description of this application, it should be understood that the terms "front," "rear," "top," "bottom," "inner," and "outer," etc., indicating orientation or positional relationships based on the orientation or positional relationships shown in the accompanying drawings, are used only for the convenience of describing the invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, or be constructed and operated in a specific orientation, and therefore should not be construed as a limitation of this application. Furthermore, in the description of this invention, "a plurality of" means two or more, unless otherwise explicitly specified.

[0034] Please see Figures 1-5 The grouting positioning device for a steel pipe wood core filled column provided in this application embodiment includes: a base 1 and a fixing component 2;

[0035] The base 1 has a grouting channel 13 that runs through its upper and lower bottom surfaces, and a fixing boss 121 is provided along the inner peripheral wall of the grouting channel 13.

[0036] The bottom of the fixing component 2 is inserted into the top of the grouting channel 13, and the fixing component 2 is located on the top surface of the fixing boss 121. The fixing component 2 includes an outer steel pipe fixing mechanism 21 and two wooden core fixing mechanisms 22. The two wooden core fixing mechanisms 22 are arranged alternately in the vertical direction. The steel pipe fixing mechanism 21 includes multiple spaced telescopic rods 211. The two ends of the telescopic rods 211 are detachably connected to one of the wooden core fixing mechanisms 22. The wooden core fixing mechanism 22 includes a sleeve part 221 and a snap-fit ​​part 222. The sleeve part 221 and the snap-fit ​​part 222 are detachably connected. The sleeve part 221 includes multiple sleeves 2211 and multiple fixing cylinders 2212. The two ends of the sleeves 2211 are slidably connected to one of the fixing cylinders 2212. The fixing cylinders 2212 are inserted into the fixing mechanism. At the top of the grouting channel 13, the fixed cylinder 2212 is slidably connected to the top surface of the fixed boss 121, the telescopic rod 211 is detachably connected to the fixed cylinder 2212, the snap-fit ​​part 222 includes a fixed block 2220, multiple crossbars 2221 and multiple limiting members 2222, the multiple crossbars 2221 are spaced apart on the outer periphery of the fixed block 2220, one end of the crossbar 2221 is slidably connected to the fixed block 2220, the crossbar 2221 can slide along the radial direction of the fixed block 2220, and the other end is detachably connected to the fixed cylinder 2212, the multiple limiting members 2222 are rotatably disposed on the multiple crossbars 2221 one by one, the limiting members 2222 are partially protruding from the surface of the crossbar 2221, and the limiting members 2222 can rotate along the axial direction of the crossbar 2221.

[0037] In the embodiment, the steel pipe and the wood core are positioned by the fixing assembly 2. When fixing, first, the wood core is positioned at the center of the fixing block 2220, the limiting piece 2222 is tightly fitted with the outer circumferential wall of the wood core by adjusting the clamping part 222, the wood core is clamped and positioned, then the length of the telescopic rod 211 is adjusted and the circumference of the sleeve part 221 is changed, so that the inner circumferential wall of the telescopic rod 211 and the sleeve part 221 are tightly fitted with the outer circumferential wall of the steel pipe, the steel pipe is clamped and positioned. After fixing, the bottom of the fixing assembly 2 is inserted into the top of the grouting channel 13, and the fixing assembly 2 is located on the top surface of the fixing boss 121, the base 1 is connected with the pumping pipe, the grouting machine is started, the mortar enters the base 1 through the pumping pipe and enters the gap between the steel pipe and the wood core, until the mortar overflows from the top of the steel pipe, which indicates that the gap between the steel pipe and the wood core is filled with mortar, and the grouting machine is turned off. The pumping pipe is removed, the base 1 and the fixing assembly 2 filled with mortar are maintained, and after maintenance, the base 1, the fixing assembly 2, the steel pipe and the wood core are removed in sequence, and the excess solidified mortar is knocked off, so that the steel pipe wood core filling column with uniform pouring and no internal bubbles is obtained.

[0038] Further, the two ends of the telescopic rod 211 are provided with first clamping grooves 2110, the telescopic rod 211 is clamped with the fixing cylinder 2212 through the first clamping grooves 2110, the other end of the cross rod 2221 is provided with a second clamping groove 2224, and the cross rod 2221 is clamped with the fixing cylinder 2212 through the second clamping groove 2224. The telescopic rod 211 and the fixing cylinder 2212 and the cross rod 2221 and the fixing cylinder 2212 are detachably connected in a clamping manner, which is convenient to install and convenient to disassemble later.

[0039] In addition, the application preferably uses a baffle as the limiting piece 2222, the baffle is rotatably arranged on the cross rod 2221, before installing the wood core, the baffle is rotated to the first position, so that the baffle is accommodated in the side of the cross rod 2221, then the cross rod 2221 is slid to make the baffle flush with the outer side wall of the wood core, and then the baffle is rotated to the second position, so that the baffle is tightly fitted with the outer side wall of the wood core, and the wood core is positioned.

[0040] Further, the fixing block 2220 is provided with an observation hole 2223, and the observation hole 2223 is located at the center of the fixing block 2220. During the installation of the wood core, whether the center of the wood core coincides with the center of the fixing block 2220 can be observed through the observation hole 2223, so that the wood core is ensured not to deviate during positioning, and adverse effects on subsequent tests caused by deviation of the wood core are avoided.

[0041] Further, a plurality of locking bolts 3 are further included, and each of the plurality of locking bolts 3 is used for locking the telescopic rod 211 and the horizontal rod 2221. The locking of the telescopic rod 211 and the horizontal rod 2221 is achieved by the bolt fixing mode in the application, which is simple and easy to adjust, and also facilitates the disassembly of the device after maintenance.

[0042] Further, the base 1 includes a connecting portion 11 and a supporting portion 12, the bottom end of the supporting portion 12 is in sliding connection with the top end of the connecting portion 11, and the fixed boss 121 is arranged on the inner circumferential wall of the supporting portion 12. The base 1 is combined by the connecting portion 11 and the supporting portion 12, which facilitates the separation of the base 1 from the fixing assembly 2 after grouting, and the connecting portion 11 does not need to be detached from the pumping pipe, and the next steel pipe wood core filling column can be manufactured by replacing the supporting portion 12.

[0043] The application further provides a grouting method of a steel pipe wood core filling column, which comprises the following steps:

[0044] Waxing the wood core, the first wood core fixing mechanism 22, the second wood core fixing mechanism 22 and the steel pipe fixing mechanism 21, placing the wood core on the first wood core fixing mechanism 22 with the center of the wood core aligned with the center of the fixing block 2220 on the wood core fixing mechanism 22, sliding the crossbar 2221 on the wood core fixing mechanism 22 so that the flapper on the crossbar 2221 is aligned with the outer peripheral wall of the wood core, rotating the flapper so that the flapper is arranged upward and fits the outer peripheral wall of the wood core, placing the steel pipe on the wood core fixing mechanism 22, adjusting the outer peripheral size of the sleeve joint 221 on the wood core fixing mechanism 22 so that the outer peripheral wall of the steel pipe fits the inner peripheral wall of the sleeve joint 221, detachably connecting the end of the crossbar 2221 away from the fixing block 2220 with the sleeve joint 221, spacing the steel pipe fixing mechanism 21 on the sleeve joint 221, adjusting the height of the steel pipe fixing mechanism 21 so that the top surface of the steel pipe fixing mechanism 21 is flush with the top surface of the steel pipe and the inner wall of the steel pipe fixing mechanism 21 fits the outer peripheral wall of the steel pipe, detachably connecting the second wood core fixing mechanism 22 at the end of the steel pipe fixing mechanism 21 away from the sleeve joint 221, adjusting the sleeve joint 221, the crossbar 2221 and the flapper on the second wood core fixing mechanism 22 so that the bottom surface of the second wood core fixing mechanism 22 respectively fits the top surface of the steel pipe and the wood core, placing the installed steel pipe fixing assembly 2, the first wood core fixing mechanism 22, the second wood core fixing mechanism 22, the steel pipe and the wood core on the base 1, the base 1 being provided with a grouting channel 13 penetrating through the upper and lower bottom surfaces thereof, the inner peripheral wall of the grouting channel 13 being provided with a fixing boss 121, the bottom of the first wood core fixing mechanism 22 being inserted into the top of the grouting channel 13 with the first wood core fixing mechanism 22 located on the top surface of the fixing boss 121, connecting the base 1 with the pumping pipe of a grouting machine;

[0045] S2, starting the grouting machine to start grouting, and stopping the grouting machine when mortar overflows from the top end of the steel pipe;

[0046] S3, separating the base 1 from the pumping pipe with a steel sheet, removing for maintenance, and sequentially removing the base 1, the second wood core fixing mechanism 22, the steel pipe fixing assembly 2, the first wood core fixing mechanism 22, the steel pipe and the wood core after maintenance to obtain a steel pipe wood core filled column.

[0047] As a preferred technical solution, the base 1 comprises a connecting part 11 and a supporting part 12, the bottom end of the supporting part 12 being slidably connected with the top end of the connecting part 11, and the fixing boss 121 being arranged on the inner peripheral wall of the supporting part 12;

[0048] The separating the base 1 from the pumping pipe by the steel sheet specifically includes: penetrating the steel sheet into the joint of the supporting part 12 and the connecting part 11, so that the two are separated.

[0049] In the embodiment, the steel pipe wood core filling column obtained by the grouting method has uniform internal mortar filling, no air bubbles and good performance, and is beneficial to subsequent performance tests.

[0050] In summary, the grouting positioning device and the grouting method of the steel pipe wood core filling column can accurately position the steel pipe and the wood core, and obtain the steel pipe wood core filling column with uniform mortar filling. The positioning device has a simple structure, and the pouring steps are convenient and easy to operate.

[0051] This specification discloses the present application with reference to the accompanying drawings, and also enables those skilled in the art to implement the present application, including manufacturing and using any device or system, using appropriate materials, and using any combined method. The scope of the present application is defined by the claimed technical solutions, and includes other examples thought by those skilled in the art. As long as such other examples include structural elements not different from the literal language of the claimed technical solutions, or such other examples contain equivalent structural elements not substantially different from the literal language of the claimed technical solutions, such other examples should be considered to be within the protection scope determined by the claimed technical solutions of the present application.

Claims

1. A grouting positioning device for a steel pipe and wood core filled column, used for positioning the steel pipe and wood core, characterized in that, include: Base and mounting components; The base has a grouting channel that runs through its upper and lower bottom surfaces, and a fixing boss is provided along the inner peripheral wall of the grouting channel. The bottom of the fixing component is inserted into the top of the grouting channel, and the fixing component is located on the top surface of the fixing boss. The fixing component includes a steel pipe fixing mechanism and two wooden core fixing mechanisms arranged on the outer periphery. The two wooden core fixing mechanisms are arranged alternately in the vertical direction, with the lower one being the first wooden core fixing mechanism and the upper one being the second wooden core fixing mechanism. The steel pipe fixing mechanism includes multiple telescopic rods arranged at intervals, and the two ends of each telescopic rod are detachably connected to one of the wooden core fixing mechanisms. The wooden core fixing mechanism includes a sleeve part and a snap-fit ​​part, and the sleeve part and the snap-fit ​​part are detachably connected. The sleeve part includes multiple sleeves and multiple fixing cylinders. Both ends of the cylinder are slidably connected to a fixed cylinder, which is inserted into the top of the grouting channel and slidably connected to the top surface of the fixed boss. The telescopic rod is detachably connected to the fixed cylinder. The locking part includes a fixed block, multiple crossbars and multiple limiting members. The multiple crossbars are spaced apart on the outer periphery of the fixed block. One end of the crossbar is slidably connected to the fixed block and can slide along the radial direction of the fixed block. The other end is detachably connected to the fixed cylinder. The multiple limiting members are rotatably mounted on the multiple crossbars. The limiting members protrude from the surface of the crossbars and can rotate along the axial direction of the crossbars. The telescopic rod has a first slot at both ends, and the telescopic rod is engaged with the fixed cylinder through the first slot. The crossbar has a second slot at the other end, and the crossbar is engaged with the fixed cylinder through the second slot.

2. The grouting positioning device for steel pipe and wood core filled columns as described in claim 1, characterized in that, The limiting component is a baffle.

3. The grouting positioning device for steel pipe and wood core filled columns as described in claim 2, characterized in that, An observation hole is provided on the fixing block, and the observation hole is located at the center of the fixing block.

4. The grouting positioning device for steel pipe and wood core filled columns as described in claim 3, characterized in that, It also includes multiple locking bolts, which are used to lock the telescopic rod and the crossbar respectively.

5. The grouting positioning device for steel pipe and wood core filled columns as described in claim 1, characterized in that, The base includes a connecting part and a supporting part. The bottom end of the supporting part is slidably connected to the top end of the connecting part, and the fixing boss is provided on the inner peripheral wall of the supporting part.

6. A grouting method for steel-tube wood-core filled columns, using the grouting positioning device for steel-tube wood-core filled columns as described in any one of claims 1-5, characterized in that, include: S1. Install steel pipes and wooden cores. The wood core, the first wood core fixing mechanism, the second wood core fixing mechanism, and the steel pipe fixing mechanism are waxed. The wood core is placed on the first wood core fixing mechanism, with the center of the wood core aligned with the center of the fixing block on the first wood core fixing mechanism. The crossbar on the first wood core fixing mechanism is slid so that the baffle on the crossbar is aligned with the outer peripheral wall of the wood core. The baffle is rotated so that it faces upward and fits against the outer peripheral wall of the wood core. The steel pipe is placed on the first wood core fixing mechanism. The outer peripheral size of the sleeve on the first wood core fixing mechanism is adjusted so that the outer peripheral wall of the steel pipe fits against the inner peripheral wall of the sleeve. The end of the crossbar away from the fixing block is detachably connected to the sleeve. The steel pipe fixing mechanisms are installed at intervals on the sleeve. The height of the steel pipe fixing mechanisms is adjusted so that the top surface of the steel pipe fixing mechanism... The steel pipe fixing mechanism is flush with the top surface of the steel pipe, and the inner wall of the steel pipe fixing mechanism is in contact with the outer peripheral wall of the steel pipe. A second wood core fixing mechanism is detachably connected to the end of the steel pipe fixing mechanism away from the sleeve part. The sleeve part, crossbar and baffle on the second wood core fixing mechanism are adjusted so that the bottom surface of the second wood core fixing mechanism is in contact with the top surface of the steel pipe and the wood core respectively. The installed steel pipe fixing mechanism, the first wood core fixing mechanism, the second wood core fixing mechanism, the steel pipe and the wood core are placed on the base. The base has a grouting channel that runs through its upper and lower bottom surfaces. A fixing boss is provided along the inner peripheral wall of the grouting channel. The bottom of the first wood core fixing mechanism is inserted into the top of the grouting channel, and the first wood core fixing mechanism is located on the top surface of the fixing boss. The base is connected to the pumping pipe of the grouting machine. S2. Start the grouting machine to begin grouting. When grout overflows from the top of the steel pipe, turn off the grouting machine. S3. Use steel sheets to separate the base from the pumping pipe, remove it for maintenance, and after maintenance, dismantle the base, the second wood core fixing mechanism, the steel pipe fixing mechanism, the first wood core fixing mechanism, the steel pipe and the wood core in sequence to obtain a steel pipe wood core filled column.

7. The grouting method for steel pipe and wood core filled columns as described in claim 6, characterized in that, The base includes a connecting part and a supporting part. The bottom end of the supporting part is slidably connected to the top end of the connecting part. The fixing boss is provided on the inner peripheral wall of the supporting part. The step of separating the base from the pumping pipe with a steel sheet specifically includes: inserting a steel sheet into the connection between the support part and the connecting part to separate the two.

Citation Information

Patent Citations

  • Lightweight wood-concrete filled combined concrete-filled steel tube column and manufacturing method thereof

    CN117988507A

  • Concrete filled steel tubular column reinforcing device

    CN220504625U