Novel construction method for hoisting irregular component through hoisting beam

By installing the hoist at the corresponding position on the hoist beam, combining a single crane and multiple hoists, the installation problem of large and large special-shaped components in confined spaces due to mismatch in space angles is solved, and rapid positioning is achieved and installation accuracy and safety is improved.

CN120004126APending Publication Date: 2025-05-16CHINA MCC20 GRP CORP LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202510278264.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2025-03-10
Publication Date
2025-05-16

AI Technical Summary

Technical Problem

In confined spaces, especially in mixed air chamber factories, when installing large special-shaped components such as S-shaped pipe elbows, installation problems are caused by mismatch in space angles. Traditional lifting methods are time-consuming and labor-intensive and have safety risks.

Method used

A new type of lifting beam device is adopted. By installing a winch on the lifting beam, the position of the winch corresponds one by one to the lifting lug position on the lifting member. A single crane and multiple winches are used to adjust the spatial angle of the components and realize the positioning.

Benefits of technology

It realizes rapid in-place installation of large special-shaped components in confined space, solves the difficulty in positioning of irregular components such as S-shaped pipe elbows, improves installation efficiency and accuracy, reduces construction costs, and reduces safety risks.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN120004126A_ABST
    Figure CN120004126A_ABST
Patent Text Reader

Abstract

The invention discloses a novel construction method for hoisting an irregular component by using a hoisting beam, which comprises the following steps of: mounting winches on the hoisting beam, and enabling the positions of the winches to be in one-to-one correspondence with the positions of hoisting lugs on the hoisted component in the vertical direction; and a winch is correspondingly connected with the lifting lug, and a crane is connected with the lifting beam. And the hoisted component is lifted, and the space angle of the hoisted component is adjusted, so that the hoisted component reaches the specified position and is located at the set space angle. And the hoisted component is fixed. The hoisting beam is hoisted through a single crane, space angle adjustment and hoisting in-place of the hoisted component are carried out through the four winches on the hoisting beam, the installation problem caused by the space angle of the large special-shaped component in the limited space is solved, and rapid in-place installation of the large special-shaped component in the limited space is achieved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the field of equipment installation engineering, and in particular to a construction method for hoisting irregular components with a novel hoisting beam. Background Art

[0002] The construction site often encounters difficulties in installing components and equipment in the factory under space-constrained environments, especially when the components are in place with a certain spatial angle, which brings certain difficulties to the installation and adjustment. The construction space of the air mixing chamber factory in this project is small, involving more cross-operations, and there are many oversized special-shaped pipe fittings. Most of the special-shaped pipe fittings need to be adjusted and installed using hand winches. It is time-consuming and labor-intensive. The S-shaped pipe elbow is particularly difficult to place. The S-shaped pipe elbow weighs 20 tons. Since it is difficult to cast the internal refractory materials after it is in place, the refractory materials must be completed before lifting, and the total weight reaches 41 tons. Due to the small construction space and complex structure of the air mixing chamber, it is impossible to use the double crane lifting method for lifting. The traditional lifting method is to use 4 sets of hand winches in conjunction with the crane for lifting. Moreover, it is inconvenient to use the manual winch after lifting. It is difficult to adjust the construction at high places, which is time-consuming and labor-intensive, and the effect is poor. In addition, high-altitude operations bring great safety risks. The above methods are not only time-consuming and labor-intensive, but also difficult to ensure quality, and there are potential safety issues. Summary of the invention

[0003] The invention provides a construction method for hoisting irregular components with a novel hanging beam, which can solve the installation problem of large-scale special-shaped components in a confined space caused by spatial angles.

[0004] The embodiment of the present invention provides a construction method for hoisting irregular components with a new type of lifting beam, comprising the following steps: installing a winch on the lifting beam so that the position of the winch corresponds to the position of the lifting lug on the hoisted component in the vertical direction. Connecting the winch to the lifting lug accordingly, and connecting the crane to the lifting beam. Lifting the hoisted component, and adjusting the spatial angle of the hoisted component so that the hoisted component reaches a specified position and is at a set spatial angle. Fixing the hoisted component.

[0005] In some of the embodiments, the winch is installed on the hanging beam, and the position of the winch is made to correspond vertically to the position of the lifting ear on the hoisted component, including: the winch is slidably installed on the hanging beam, and then the position of the winch is adjusted by sliding the winch, so that the position of the winch is made to correspond vertically to the position of the lifting ear on the hoisted component.

[0006] In some of the embodiments, after the position of the winch is adjusted, the position of the winch is fixed.

[0007] In some of the embodiments, lifting the suspended component includes: using a winch to lift the suspended component to a preset height, and checking whether there is any abnormality in the connection status between the winch and the suspended component. If there is any abnormality, stopping lifting the suspended component and making adjustments. If there is no abnormality, continuing to lift the suspended component.

[0008] In some of the embodiments, checking whether there is any abnormality in the connection state between the hoist and the hoisted component includes: checking whether the center of gravity of the hoisted component is always kept within the control range of the hoisting point of the hoisting beam.

[0009] In some of the embodiments, adjusting the spatial angle of the hoisted component includes: controlling each winch disposed on the left side of the hoisted component to lift or lower the hoisted component, and / or controlling each winch disposed on the right side of the hoisted component to lower or lift the hoisted component, thereby adjusting the rightward rolling angle or the leftward rolling angle of the hoisted component.

[0010] In some of the embodiments, adjusting the spatial angle of the hoisted component includes: controlling each winch disposed on the front side of the hoisted component to lift or lower the hoisted component, and / or controlling each winch disposed on the rear side of the hoisted component to lower or lift the hoisted component, thereby adjusting the front upward angle or the front downward angle of the hoisted component.

[0011] In some of the embodiments, adjusting the spatial angle of the hoisted component includes: fine-tuning the steering of a main hook on the crane that is connected to the hoisting beam.

[0012] In some embodiments, the embodiments of the present invention further provide a beam hanging device using the above construction method, comprising a beam hanging device and a winch. The beam hanging device is used to connect to a crane. The winches include a plurality of winches, each of which is installed on the beam hanging device, and the position of each winch corresponds to the position of each lifting lug on the hoisted component in the vertical direction, and each winch is used to connect to each lifting lug.

[0013] In some of these embodiments, each winch may be slidably mounted on the hanging beam.

[0014] According to an embodiment of the present invention, a new type of construction method for hoisting irregular components with a hanging beam is provided, comprising the following steps: installing a winch on the hanging beam so that the position of the winch corresponds to the position of the lifting lug on the hoisted component in the vertical direction. Connecting the winch to the lifting lug accordingly, and connecting the crane to the hanging beam. Lifting the hoisted component, and adjusting the spatial angle of the hoisted component so that the hoisted component reaches a specified position and is at a set spatial angle. Fixing the hoisted component. The present invention lifts the hanging beam by a single crane, and adjusts the spatial angle of the hoisted component and hoists it into place by four winches on the hanging beam, thereby solving the installation problem of large special-shaped components in a confined space due to the spatial angle, and realizing the rapid installation of large special-shaped components in a confined space, especially solving the installation problem of the difficult installation of the S-shaped pipe elbow connecting the drying rotary kiln and the roasting rotary kiln under the conditions of complex structure, compact layout and narrow space in the air mixing chamber plant, and realizing the rapid installation and rapid butt welding of the S-shaped pipe elbow. BRIEF DESCRIPTION OF THE DRAWINGS

[0015] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For those skilled in the art, other drawings can be obtained based on these drawings without paying any creative work.

[0016] Figure 1 A top view of a hanging beam device in an embodiment of the present invention;

[0017] Figure 2 It is a front view of the hanging beam device in the embodiment of the present invention;

[0018] Figure 3 A side view of a hanging beam device in an embodiment of the present invention;

[0019] Figure 4 Schematic diagram of the structure of the hanging beam device at a first angle in an embodiment of the present invention;

[0020] Figure 5 Schematic diagram of the structure of the hanging beam device at a second angle in an embodiment of the present invention;

[0021] Figure 6 for Figure 5 A magnified schematic diagram of center A. DETAILED DESCRIPTION

[0022] In order to make the purpose, technical solution and advantages of the present invention more clearly understood, the present invention is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present invention and are not intended to limit the present invention.

[0023] It is difficult to hoist irregular components in a confined space. Usually, irregular components are hoisted by two cranes. The working space of the air mixing chamber of some projects is small and cannot accommodate the standing space of two cranes. Therefore, the traditional hoisting method is used to hoist large irregular components, using a hand chain hoist to adjust the components and install them in place. This traditional hoisting solution is difficult to operate the hand chain hoist after lifting, has poor installation accuracy and low efficiency. For the above situation, please refer to Figure 1-6 An embodiment of the present invention provides a beam hanging device, including a beam hanging 1 and a winch 2.

[0024] The hanging beam 1 is a frame-type structure. The upper part of the hanging beam 1 is provided with a top hanging lug 11, which is used to connect with the main hook of the crane. There are four top hanging lugs 11, two of which are welded on one side of the hanging beam 1, and the other two are welded on the other side of the hanging beam 1, so as to ensure sufficient force and safety during the lifting process.

[0025] The upper part of the suspension beam 1 has a slide rail 12 extending in the left-right direction, and a slidable support 13 is installed on the upper part of the slide rail 12. The support 13 is used for the installation of the winch 2, so as to adjust the position of the winch 2 on the suspension beam 1. There are two slide rails 12, and the two slide rails 12 are arranged in parallel along the front-to-back direction. Both slide rails 12 include two track monomers, and both track monomers extend in the left-to-right direction, and the two track monomers are arranged in parallel along the front-to-back direction. There are four supports 13, and every two supports 13 are slidably installed on the same slide rail 12. Both ends of each slide rail 12 have a limit stop 14 to prevent the support 13 from detaching from the slide rail 12 when sliding. The limit stop 14 is arranged on the front and rear sides of each slide rail 12. The side of each slide rail 12 has a plurality of first positioning pin holes 121 evenly spaced in the left-right direction, and the side of the support 13 has a second positioning pin hole 131, so that after the position of the winch 2 on the suspension beam 1 is adjusted, a positioning pin is inserted to fix the position of the winch 2. There are two second positioning pin holes 131, which are respectively arranged on the left and right sides of the support 13.

[0026] There are multiple winches 2, such as four winches 2, namely winches 1# 21, winches 2# 22, winches 3# 23, and winches 4# 24. Each winch 2 is installed on the upper part of each support 13. The position of each winch 2 corresponds to the position of each lifting lug on the hoisted component in the vertical direction. Each winch 2 has a hook 25, which is used to connect with the lifting lug. The hoisted component includes a special-shaped component or equipment such as an S-shaped pipe elbow.

[0027] The traditional hoisting method uses a crane in conjunction with a hand winch for hoisting, which is not only time-consuming, but also inconvenient to operate with a manual winch after hoisting, difficult to adjust at high altitudes, time-consuming and labor-intensive, and ineffective, and high-altitude operations bring great safety risks. After the lifting beam 1 of the present invention is lifted, the spatial angle of the hoisted component can be adjusted by the winch 2, which can be applied to the construction of irregular components and solve the problem that irregular components such as S-shaped pipe elbows are difficult to hoist and difficult to weld. Moreover, when the lifting operation surface is met, different lifting beams 1 can be welded according to the weight of the hoisted component, and different winches 2 can be selected. The present invention makes the lifting operation simpler and can be retained after use for continued use in production hoisting.

[0028] The embodiment of the present invention provides a construction method for hoisting an irregular component using a novel hanging beam. The construction method adopts the above-mentioned hanging beam device and comprises the following steps:

[0029] (1) The hoist 2 is installed on the lifting beam 1 so that the position of the hoist 2 corresponds to the position of the lifting lug on the hoisted component in the vertical direction.

[0030] Before starting the above steps, design and manufacture the hanging beam 1 according to the weight and dimensions of the hoisted component; select the winch 2 and the crane; calculate the total weight of the hoisted component, the hanging beam 1 and the components on the hanging beam 1, and require that the total weight is ≤ the lifting capacity of the crane.

[0031] In the above steps, the hoist 2 is slidably mounted on the hanging beam 1, and then the position of the hoist 2 is adjusted by sliding the hoist 2, so that the position of the hoist 2 corresponds to the position of the lifting lug on the hoisted component in the vertical direction. Optionally, four hoists 2 are respectively mounted on four supports 13, and then the positions of the four hoists 2 are adjusted by sliding the four hoists 2 respectively, so that the positions of the four hoists 2 correspond to the positions of the four lifting lugs on the hoisted component in the vertical direction. The above process is to ensure that the hanging beam 1 and the hoist 2 reach a balanced state after lifting. Further, after adjusting the position of the hoist 2, the position of the hoist 2 is fixed. Optionally, the position of the hoist 2 is fixed by inserting the locating pin into the second locating pin hole 131 and the first locating pin hole 121. The above process is to ensure that the hanging beam 1 and the hoist 2 reach a balanced state after lifting.

[0032] (2) Connect the winch 2 to the lifting lugs accordingly, and connect the crane to the lifting beam 1.

[0033] In the above steps, the winch 2 is connected with the lifting hook 25 and the lifting eye.

[0034] (3) Lift the hoisted component and adjust the spatial angle of the hoisted component so that the hoisted component reaches the specified position and is at the set spatial angle.

[0035] In the above steps, the hoisted component is lifted by controlling the crane and the hoisting machine 2. The spatial angle of the hoisted component is adjusted by controlling the hoisting machine 2.

[0036] Lifting the hoisted component includes: using the winch 2 to lift the hoisted component to a preset height, and checking whether there is any abnormality in the connection status between the winch 2 and the hoisted component. If there is an abnormality, stop lifting the hoisted component and make adjustments. If there is no abnormality, continue lifting the hoisted component. Wherein, slowly lift the hoisted component to a preset height. The preset height is 100-200mm. Further, check whether there is any abnormality in the connection status between the winch 2 and the hoisted component, including: check whether the center of gravity of the hoisted component is always kept within the control range of the lifting point of the lifting beam 1.

[0037] Adjusting the spatial angle of the suspended component includes: controlling each winch 2 disposed on the left side of the suspended component to lift or lower the suspended component, and / or controlling each winch 2 disposed on the right side of the suspended component to lower or lift the suspended component, thereby adjusting the rightward roll angle or the leftward roll angle of the suspended component. In other words, the roll angle of the suspended component is adjusted by controlling the winches 2 on the left and right sides. Optionally, by controlling the 1# winch 21 and the 3# winch 23 to lift the suspended component, and the 2# winch 22 and the 4# winch 24 to lower the suspended component, the suspended component rolls to the right, and the rightward roll angle of the suspended component is adjusted. The opposite operation causes the suspended component to roll to the left, and the leftward roll angle of the suspended component is adjusted.

[0038] Adjusting the spatial angle of the hoisted component also includes: controlling each winch 2 disposed on the front side of the hoisted component to lift or lower the hoisted component, and / or controlling each winch 2 disposed on the rear side of the hoisted component to lower or lift the hoisted component, thereby adjusting the front side pitch angle or front side pitch angle of the hoisted component. In other words, the pitch angle of the hoisted component is adjusted by controlling the winches 2 on both sides. Optionally, the hoisted component is lifted by controlling the 1# winch 21 and the 2# winch 22, and the hoisted component is lowered by controlling the 3# winch 23 and the 4# winch 24, so that the front side of the hoisted component pitches downward, and the front side pitch angle of the hoisted component is adjusted. The opposite operation causes the front side of the hoisted component to pitch upward, and the front side pitch angle of the hoisted component is adjusted.

[0039] Adjusting the spatial angle of the hoisted component also includes: fine-tuning the steering of a main hook on the crane connected to the hoisting beam 1 .

[0040] The above adjustment of the spatial angle of the hoisted component can be achieved by observing from the ground and the high-altitude platform, and by remotely controlling the lifting and lowering of the hooks on the four winches 2.

[0041] (4) Fix the components to be hoisted.

[0042] After the above steps are completed, the hook on the hoist 2 is disengaged from the lifting lug on the hoisted component, and then the hanging beam 1 and the components on the hanging beam 1 are hoisted to the lifting position for subsequent construction use.

[0043] In summary, the present invention uses a single crane to lift the hanging beam 1, and uses four winches 2 on the hanging beam 1 to adjust the spatial angle of the hoisted components and hoist them into place, which solves the installation problem of large special-shaped components in a confined space due to the spatial angle, and realizes the rapid installation of large special-shaped components in a confined space. In particular, it solves the installation problem of the S-shaped pipe elbow connecting the drying rotary kiln and the roasting rotary kiln under the conditions of complex structure, compact layout and narrow space in the mixing chamber factory, and realizes the rapid installation and rapid butt welding of the S-shaped pipe elbow. In addition, the present invention not only speeds up the installation speed of the hoisted components, but also saves the crane required for installation, improves the installation accuracy, and the hanging beam device can be reused, with high efficiency, reducing construction costs.

[0044] The same or similar numbers in the drawings of this embodiment correspond to the same or similar parts; in the description of the present invention, it should be understood that if the terms "upper", "lower", "left", "right" and the like indicate directions or positional relationships based on the directions or positional relationships shown in the drawings, it is only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific direction, be constructed and operated in a specific direction. Therefore, the terms describing the positional relationship in the drawings are only used for illustrative purposes and cannot be understood as limitations on this patent. For ordinary technicians in this field, the specific meanings of the above terms can be understood according to specific circumstances.

[0045] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present invention should be included in the protection scope of the present invention.

Claims

1. A new type of construction method for hoisting irregular components with a hanging beam, characterized in that: The following steps are involved: Install the hoist on the hanging beam so that the position of the hoist corresponds to the position of the lifting lug on the hoisted component in the vertical direction; Connect the hoist to the lifting lugs accordingly, and connect the crane to the lifting beam; Lifting the hoisted component and adjusting the spatial angle of the hoisted component so that the hoisted component reaches a specified position and is at a set spatial angle; The hoisted component is fixed.

2. The construction method according to claim 1, characterized in that: The hoist is installed on the hanging beam, and the position of the hoist corresponds to the position of the lifting lug on the hoisted component in a vertical direction, including: The hoist is slidably mounted on the suspension beam, and then the position of the hoist is adjusted by sliding the hoist, so that the position of the hoist corresponds to the position of the lifting lug on the hoisted component in a vertical direction.

3. The construction method according to claim 2, characterized in that: After adjusting the position of the hoist, the position of the hoist is fixed.

4. The construction method according to claim 1, characterized in that: Lifting the hoisted component comprises: The hoist is used to lift the hoisted component to a preset height, and the connection status between the hoist and the hoisted component is checked for abnormalities. If there are any abnormalities, the lifting of the hoisted component is stopped and adjustments are made. If there are no abnormalities, the lifting of the hoisted component continues.

5. The construction method according to claim 4, characterized in that: Checking whether there is any abnormality in the connection between the hoist and the hoisted component includes: Check whether the center of gravity of the hoisted component is always kept within the control range of the hoisting point of the hoisting beam.

6. The construction method according to claim 1, characterized in that: Adjusting the spatial angle of the hoisted component includes: The hoisting angle to the right or to the left of the hoisted component is adjusted by controlling the hoisting machines on the left side of the hoisted component to lift or lower the hoisted component, and / or controlling the hoisting machines on the right side of the hoisted component to lower or lift the hoisted component.

7. The construction method according to claim 1, characterized in that: Adjusting the spatial angle of the hoisted component includes: The hoisting machines arranged at the front side of the hoisted component are controlled to lift or lower the hoisted component, and / or the hoisting machines arranged at the rear side of the hoisted component are controlled to lower or lift the hoisted component, thereby adjusting the front upward angle or the front downward angle of the hoisted component.

8. The construction method according to claim 1, characterized in that: Adjusting the spatial angle of the hoisted component comprises: The main hook on the crane connected to the hanging beam is subjected to fine steering adjustment.

9. A beam hanging device using the construction method according to any one of claims 1 to 8, characterized in that: include: A hanging beam, used for connection with a crane; The winches include a plurality of winches, each of which is installed on the suspension beam, and the position of each winch corresponds vertically to the position of each lifting lug on the suspended component, and each winch is used to be connected to the corresponding lifting lug.

10. The beam suspension device according to claim 9, characterized in that: Each of the hoists can be slidably mounted on the suspension beam.