Water delivery line dynamic adjustment method and system based on underground powerhouse axis

By adopting a dynamic adjustment method of water transmission line based on the axis of the underground plant in the water transmission and power generation system, the problem of lack of flexibility and depth in the design of water transmission line in the prior art is solved, and the automatic adjustment and design coordination of water transmission line are achieved.

CN120013131AActive Publication Date: 2025-05-16POWERCHINA BEIJING ENG CORP
View PDF 12 Cites 0 Cited by

Patent Information

Application Number
CN202510007944.X
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2025-01-03
Publication Date
2025-05-16
Estimated Expiration
2045-01-03

AI Technical Summary

Technical Problem

The existing water transmission and power generation system circuit design lacks flexibility and depth, and cannot effectively match the adjustment of the underground factory axis, resulting in a lack of coordination and optimization of the water transmission line design.

Method used

The dynamic adjustment method of water transmission line based on the underground factory axis is adopted. By reading the water transmission line parameters and obtaining the factory axis adjustment parameters, appropriate adjustment strategies are selected (such as adjusting the turning section of the pipeline, the relative angle between the branch pipe and the branch pipe at the fork pipe, and the angle between the pipeline and the factory axis) to automatically adjust the water transmission line.

Benefits of technology

The dynamic adjustment of the water transmission line is achieved, the design requirements are met, the efficiency of the factory road coordination is improved, the errors caused by human factors are reduced, and the quality and efficiency of the design is improved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN120013131A_ABST
    Figure CN120013131A_ABST
Patent Text Reader

Abstract

The invention belongs to the technical field of water delivery and power generation systems, and discloses a water delivery line dynamic adjustment method and system based on the axis of an underground powerhouse. Parameters of a water conveying line, building information and plant axis adjusting parameters are obtained and read through the data reading and analyzing module, control points and turning sections are analyzed and generated, a plant angle adjusting strategy is selected and executed through the plant axis angle adjusting module, a plant position adjusting mode is selected and executed through the plant axis position adjusting module, and the control points and the turning sections are adjusted. And finally, dynamically adjusting the water delivery line through a water delivery line dynamic adjustment module according to the adjustment of the factory building axis angle and the factory building axis position. According to the method, the water conveying line can be automatically adjusted according to the selected adjusting strategy and mode, the adjusting result meets the design requirement of the water conveying line, and the factory channel cooperation efficiency can be improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention belongs to the technical field of water transmission and power generation systems, and in particular relates to a method and system for dynamically adjusting a water transmission line based on an axis of an underground plant. Background Art

[0002] At present, the line design of the water transmission and power generation system of pumped storage power stations is mainly based on two-dimensional design of horizontal and longitudinal sections. Some scholars have also explored the three-dimensional design of the line, but the accuracy and depth are insufficient. Basically, the water transmission line is generated based on the layout parameters of the water transmission system, and most of them are typical layouts. There is a lack of research and development of three-dimensional collaborative design methods and procedures for parameterized adjustment of the water transmission line, especially in combination with the axis of the underground plant. After the axis of the underground plant is adjusted, the water transmission system line cannot be matched and adjusted, and the water transmission line can only be regenerated based on the existing plant location, lacking flexibility and the possibility of solution optimization. Summary of the invention

[0003] The present invention aims to address the deficiencies in the prior art and provide a method and system for dynamically adjusting the water transmission line based on the axis of the underground plant building, which can automatically adjust the water transmission line according to a selected adjustment strategy and method, and the adjustment result meets the design requirements of the water transmission line, thereby improving the coordination efficiency of the plant road.

[0004] In order to achieve the above technical objectives, the present invention adopts the following technical solutions:

[0005] A method for dynamically adjusting a water supply line based on an underground powerhouse axis comprises the following steps:

[0006] The following steps are involved:

[0007] S1, read the parameters of the water transmission line, obtain the building information on the water transmission route, generate control points, and process the control points to generate turning sections;

[0008] S2. Obtaining the adjustment parameters of the plant axis;

[0009] S3. When the plant axis adjustment parameter shows that the plant axis angle needs to be adjusted, one of the plant axis angle adjustment strategies 1, 2 and 3 is selected. Strategy 1 is to adjust the turning section of the pipeline of the water transmission line. Strategy 2 is to adjust the relative angle between the branch pipe and the bifurcated branch pipe at the fork of the pipeline of the water transmission line. Strategy 3 is to adjust the angle between the pipeline of the water transmission line and the plant axis.

[0010] When the plant axis adjustment parameter shows that the plant axis position needs to be adjusted, and the plant axis position moves upstream, the length of each flat section of the pipeline of the water transmission line is shortened;

[0011] When the powerhouse axis adjustment parameters show that the powerhouse axis position needs to be adjusted and the powerhouse axis position moves downstream, the tailwater tunnel length is reduced;

[0012] S4. Based on the adjustment of the plant axis angle and the plant axis position, the water supply line is dynamically adjusted.

[0013] Preferably, in step S1, the water transmission route parameters include multiple three-dimensional multi-segment lines, pipeline parameters of each segment of the line, main pipe parameters of the pipeline, branch pipe parameters, bifurcated pipe parameters of the pipeline, branch pipe parameters at the bifurcated pipe, bifurcated branch pipe parameters, the starting point, end point and line length of the line, the horizontal length of each flat section of the pipeline of the water transmission line, and the horizontal length of the tailwater tunnel of the water transmission line; the building information includes the location, spacing, direction, water supply form and number of units of the building, and the number of main pipes and branches of the water transmission line are determined based on the water supply form and the number of units.

[0014] Preferably, in step S1, the control points include a water diversion system control point and a tailwater system control point;

[0015] The control points of the water diversion system include: the water diversion pressure regulating well is the control point J, the center point of the water diversion branch pipe is the control point K, the intersection point of the water diversion branch pipe axis and the powerhouse axis is the control point P, and the intersection point of the center line of the line turning section is the control point H;

[0016] The control points of the tailwater system include: the center point of the unit is the control point C, the center point of the tailwater branch pipe is the control point K', the bottom tunnel of the tailwater chamber is the control point L, the tailwater surge chamber is the control point M, and the intersection point of the center line of the line turning section is the control point H;

[0017] The control points are arranged in order according to the main pipe of the water transmission line, the branch pipe of the water transmission line and the direction of water flow.

[0018] Preferably, in step S1, the spacing includes the spacing of the water diversion system and the spacing of the tailwater system;

[0019] The spacing of the water diversion system includes: the spacing between the water diversion and pressure regulating wells LJ, the spacing between the center points of the branch pipes LK, and the spacing between the intersection points of the water diversion branch pipe axis and the powerhouse axis LP;

[0020] The tailwater system spacing includes: unit center spacing LC, tailwater branch pipe center spacing LK', tailwater lock chamber bottom tunnel spacing LL, tailwater surge chamber spacing LM;

[0021] Determine the location of the control points based on the number of main pipes, the number of branch pipes and the spacing between them, and connect the control points in sequence.

[0022] Preferably, in step S1, generating a turning segment specifically includes:

[0023] Control points are connected to form multiple lines, corner control points are screened, and adjacent corner control points are detected and screened out from the corner control points, and the adjacent corner control points are processed to generate turning sections.

[0024] Preferably, in step S2, the plant axis adjustment parameters include: plant axis angle adjustment information and plant axis position adjustment information.

[0025] Preferably, in step S3, strategy 1 specifically includes:

[0026] Adjust the line direction of the water transmission line pipeline and the corresponding parameters of the turning section of the pipeline, keep the angle between the water diversion branch pipe and the plant axis unchanged, and match the angle adjustment information of the plant axis: according to the angle formed by the direction of the plant axis after adjustment and the direction of the plant axis before adjustment, keep the relative relationship between the center control point K of the water diversion branch pipe and the intersection control point P of the water diversion branch pipe axis and the plant axis unchanged, adjust the position of the turning section H of the pipeline, adjust the radius and angle of the turning section to meet the design limit requirements of the turning radius and the design limit requirements of the turning angle; the adjustment strategy of the tailwater system is the same as that of the water diversion system.

[0027] Preferably, in step S3, strategy 2 specifically includes:

[0028] Adjust the relative angles α and β between the water diversion bifurcated pipe and the water diversion bifurcated pipe to match the angle adjustment information of the plant axis: keep the route of the pipeline unchanged, the turning radius and turning angle of the turning section of the pipeline also remain unchanged, and the angle θ of the bifurcation angle between the water diversion bifurcated pipes remains unchanged. According to the angle formed by the direction after the adjustment of the plant axis and the direction before the adjustment of the plant axis, adjust the relative angles α and β between the water diversion bifurcated pipe and the water diversion bifurcated pipe, and the angle of the bifurcation angle between the water diversion bifurcated pipe + the relative angle between the water diversion bifurcated pipe and the water diversion bifurcated pipe = 360°, α+β+θ=360°, the relationship between the control point P of the intersection of the water diversion branch pipe axis and the plant axis changes; the adjustment strategy 2 of the tailwater system is the same as that of the water diversion system.

[0029] Preferably, in step S3, strategy three specifically includes:

[0030] Adjust the angle between the axis of the water diversion branch pipe and the axis of the powerhouse to match the angle adjustment information of the powerhouse axis: keep the route of the pipeline unchanged, keep the turning radius and turning angle of the turning section of the pipeline unchanged, and keep the relative angles α and β between the water diversion branch pipe and the water diversion branch pipe, and the angle θ of the bifurcation angle between the water diversion branch pipes unchanged; adjust the angle γ between the axis of the water diversion branch pipe and the axis of the powerhouse according to the angle formed by the direction after the adjustment of the powerhouse axis and the direction before the adjustment of the powerhouse axis, and at the same time ensure that the angle between the axis of the water diversion branch pipe and the axis of the powerhouse is greater than 60° and less than 180°; the adjustment strategy three of the tailwater system is the same as that of the water diversion system.

[0031] Preferably, in step S3, reducing the length of each flat section of the pipeline of the water transmission line specifically includes:

[0032] When the plant axis needs to move upstream, the length of each flat section of the water supply line pipeline is shortened according to the plant axis position adjustment information, the length of the tailwater tunnel is increased accordingly, and the sum of the lengths of each flat section is made equal to the length of the tailwater tunnel.

[0033] Preferably, in step S3, reducing the length of the tailwater tunnel specifically includes:

[0034] When the plant axis needs to move downstream, the length of the tailwater tunnel is shortened according to the plant axis position adjustment information, the lengths of the various flat sections of the pipeline of the corresponding water transmission line are shortened, and the sum of the lengths of the various flat sections is made equal to the length of the tailwater tunnel.

[0035] The present invention also provides a system for dynamically adjusting a water transmission line using the above-mentioned method for dynamically adjusting a water transmission line based on an underground powerhouse axis, comprising a data reading and analysis module, a powerhouse axis adjustment module and a water transmission line dynamic adjustment module;

[0036] The data reading and analysis module is used to obtain and read the parameters of the water transmission line, building information, and plant axis adjustment parameters, and analyze and generate control points and turning sections;

[0037] The plant axis adjustment module is used to select and execute the plant angle adjustment strategy, select and execute the length of each flat section of the pipeline of the water transmission line or the length of the tailwater tunnel;

[0038] The water supply line dynamic adjustment module is used to dynamically adjust the water supply line according to the adjustment of the plant axis angle and the plant axis position.

[0039] Compared with the prior art, the beneficial effects of the present invention are:

[0040] By adjusting the angle and position of the plant axis, selecting the adjustment strategy and method, and then adjusting the control points, the intersection control points of the water diversion branch pipe axis and the plant axis, the turning sections of the pipeline, the lengths of each flat section and the length of the tailwater tunnel, the corresponding water transmission line will be automatically adjusted according to the selected adjustment strategy. The adjustment result meets the design requirements of the water transmission line, improves the efficiency of plant-road coordination, and effectively reduces the problems of errors and omissions caused by human factors, thereby improving the quality and efficiency of plant-road collaborative design. BRIEF DESCRIPTION OF THE DRAWINGS

[0041] Figure 1 This is a flow chart of a method for dynamically adjusting a water delivery line based on an underground powerhouse axis according to an embodiment of the present invention;

[0042] Figure 2 This is an example diagram of a plant axis angle adjustment strategy according to an embodiment of the present invention;

[0043] Figure 3This is an example diagram of a second plant axis angle adjustment strategy according to an embodiment of the present invention;

[0044] Figure 4 3. It is a diagram showing three examples of the plant axis angle adjustment strategy according to an embodiment of the present invention;

[0045] Figure 5 This is an example diagram of adjusting the upstream movement of the plant axis in an embodiment of the present invention;

[0046] Figure 6 This is an example diagram of the adjustment of the plant axis moving downstream according to an embodiment of the present invention. DETAILED DESCRIPTION

[0047] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0048] Example 1

[0049] Combination Figure 1 As shown, an embodiment of the present invention provides a method for dynamically adjusting a water transmission line based on an axis of an underground powerhouse, comprising the following steps:

[0050] S1, read the parameters of the water transmission line, obtain the building information on the water transmission route, generate control points, and process the control points to generate turning sections;

[0051] S2. Obtaining the adjustment parameters of the plant axis;

[0052] S3. When the plant axis adjustment parameter shows that the plant axis angle needs to be adjusted, one of the plant axis angle adjustment strategies 1, 2 and 3 is selected. Strategy 1 is to adjust the turning section of the pipeline of the water transmission line. Strategy 2 is to adjust the relative angle between the branch pipe and the bifurcated branch pipe at the fork of the pipeline of the water transmission line. Strategy 3 is to adjust the angle between the pipeline of the water transmission line and the plant axis.

[0053] Specifically, the decision of which strategy to choose, one, two, or three, can be made based on the designer’s previous experience;

[0054] When the plant axis adjustment parameter shows that the plant axis position needs to be adjusted, and the plant axis position moves upstream, the length of each flat section of the pipeline of the water transmission line is shortened;

[0055] When the powerhouse axis adjustment parameters show that the powerhouse axis position needs to be adjusted and the powerhouse axis position moves downstream, the tailwater tunnel length is reduced;

[0056] S4. Based on the adjustment of the plant axis angle and the plant axis position, the water supply line is dynamically adjusted.

[0057] Example 2

[0058] Combination Figure 1 As shown, an embodiment of the present invention provides a method for dynamically adjusting a water transmission line based on an axis of an underground powerhouse, comprising the following steps:

[0059] S1, read the parameters of the water transmission line, obtain the building information on the water transmission route, generate control points, and process the control points to generate turning sections;

[0060] S2. Obtaining the adjustment parameters of the plant axis;

[0061] S3. When the plant axis adjustment parameter shows that the plant axis angle needs to be adjusted, one of the plant axis angle adjustment strategies 1, 2 and 3 is selected. Strategy 1 is to adjust the turning section of the pipeline of the water transmission line. Strategy 2 is to adjust the relative angle between the branch pipe and the bifurcated branch pipe at the fork of the pipeline of the water transmission line. Strategy 3 is to adjust the angle between the pipeline of the water transmission line and the plant axis.

[0062] Specifically, the decision of which strategy to choose, one, two, or three, can be made based on the designer’s previous experience;

[0063] When the plant axis adjustment parameter shows that the plant axis position needs to be adjusted, and the plant axis position moves upstream, the length of each flat section of the pipeline of the water transmission line is shortened;

[0064] When the powerhouse axis adjustment parameters show that the powerhouse axis position needs to be adjusted and the powerhouse axis position moves downstream, the tailwater tunnel length is reduced;

[0065] S4. Dynamically adjust the water delivery line based on the adjustment of the plant axis angle and the plant axis position;

[0066] On this basis, in this embodiment, the water transmission route parameters include multiple three-dimensional multi-segment routes, pipeline parameters of each segment of the route, main pipe parameters, branch pipe parameters, bifurcated pipe parameters, branch pipe parameters at the bifurcated pipe, bifurcated branch pipe parameters, the starting point, end point and line length of the route, the length of each flat section of the pipeline of the water transmission route, and the length of the tailwater tunnel of the water transmission route; the building information includes the location, spacing, direction, water supply form and number of units of the building, and the number of main pipes and branches of the water transmission route is determined based on the water supply form and the number of units;

[0067] Further, the control points include a water diversion system control point and a tailwater system control point;

[0068] The control points of the water diversion system include: the water diversion pressure regulating well is the control point J, the center point of the water diversion branch pipe is the control point K, the intersection point of the water diversion branch pipe axis and the powerhouse axis is the control point P, and the intersection point of the center line of the line turning section is the control point H;

[0069] The control points of the tailwater system include: the center point of the unit is the control point C, the center point of the tailwater branch pipe is the control point K', the bottom tunnel of the tailwater chamber is the control point L, the tailwater surge chamber is the control point M, and the intersection point of the center line of the line turning section is the control point H;

[0070] Sort the control points in order according to the main pipe of the water transmission line, the branch pipe of the water transmission line and the direction of water flow;

[0071] Further, the spacing includes the spacing of the diversion system and the spacing of the tailwater system;

[0072] The spacing of the water diversion system includes: the spacing between the water diversion and pressure regulating wells LJ, the spacing between the center points of the branch pipes LK, and the spacing between the intersection points of the water diversion branch pipe axis and the powerhouse axis LP;

[0073] The tailwater system spacing includes: unit center spacing LC, tailwater branch pipe center spacing LK', tailwater lock chamber bottom tunnel spacing LL, tailwater surge chamber spacing LM;

[0074] Determine the location of the control points according to the number of main pipes and branch pipes of the water transmission line and their spacing, and connect the control points in sequence;

[0075] Directions are defined as "east", represented by E; "south", represented by S; "west", represented by W; "north", represented by N; "southeast", represented by SE; "southwest", represented by SW; "northwest", represented by NW; "northeast", represented by NE.

[0076] Furthermore, the process of generating a turning segment specifically includes:

[0077] Connect control points to form multiple lines, select corner control points, detect and select adjacent corner control points from the corner control points, perform corner processing on the adjacent corner control points, and generate turning sections;

[0078] Furthermore, the factory building axis adjustment parameters include: factory building axis angle adjustment information and factory building axis position adjustment information.

[0079] By adjusting the angle and position of the plant axis, selecting the adjustment strategy and method, and then adjusting the control points, the intersection control points of the water diversion branch pipe axis and the plant axis, the turning sections of the pipeline, the lengths of each flat section and the length of the tailwater tunnel, the corresponding water transmission line will automatically adjust the water transmission line according to the selected adjustment strategy, thereby realizing dynamic adjustment of the entire water transmission line.

[0080] Example 3

[0081] Combination Figure 1 As shown, an embodiment of the present invention provides a method for dynamically adjusting a water transmission line based on an axis of an underground powerhouse, comprising the following steps:

[0082] S1, read the parameters of the water transmission line, obtain the building information on the water transmission route, generate control points, and process the control points to generate turning sections;

[0083] S2. Obtaining the adjustment parameters of the plant axis;

[0084] S3. When the plant axis adjustment parameter shows that the plant axis angle needs to be adjusted, one of the plant axis angle adjustment strategies 1, 2 and 3 is selected. Strategy 1 is to adjust the turning section of the pipeline of the water transmission line. Strategy 2 is to adjust the relative angle between the branch pipe and the bifurcated branch pipe at the fork of the pipeline of the water transmission line. Strategy 3 is to adjust the angle between the pipeline of the water transmission line and the plant axis.

[0085] Specifically, the decision of which strategy to choose, one, two, or three, can be made based on the designer’s previous experience;

[0086] When the plant axis adjustment parameter shows that the plant axis position needs to be adjusted, and the plant axis position moves upstream, the length of each flat section of the pipeline of the water transmission line is shortened;

[0087] When the powerhouse axis adjustment parameters show that the powerhouse axis position needs to be adjusted and the powerhouse axis position moves downstream, the tailwater tunnel length is reduced;

[0088] S4. Dynamically adjust the water delivery line based on the adjustment of the plant axis angle and the plant axis position;

[0089] Further, the control points include water diversion system control points and tailwater system control points;

[0090] Further, the spacing includes the spacing of the diversion system and the spacing of the tailwater system;

[0091] Furthermore, the process of generating a turning segment specifically includes:

[0092] Connect control points to form multiple lines, select corner control points, detect and select adjacent corner control points from the corner control points, perform corner processing on the adjacent corner control points, and generate turning sections;

[0093] Further, the plant axis adjustment parameters include: plant axis angle adjustment information, plant axis position adjustment information;

[0094] On this basis, in this embodiment, in step S3, strategy 1 specifically includes:

[0095] like Figure 2 As shown, adjust the line direction of the pipeline of the water transmission line and the corresponding parameters of the turning section of the pipeline, keep the angle between the water diversion branch pipe and the powerhouse axis unchanged, and match the angle adjustment information of the powerhouse axis: according to the angle formed by the direction after the adjustment of the powerhouse axis and the direction before the adjustment of the powerhouse axis, keep the relative relationship between the center control point K of the water diversion branch pipe and the intersection control point P of the water diversion branch pipe axis and the powerhouse axis unchanged, adjust the turning section H position of the pipeline, adjust the turning section radius and the turning section angle to meet the design limit values ​​of the turning radius and the turning angle requirements; the adjustment strategy of the tailwater system is the same as that of the water diversion system;

[0096] Furthermore, Strategy 2 specifically includes:

[0097] like Figure 3 As shown, the relative angles α and β between the water diversion bifurcated pipe branch and the water diversion bifurcated pipe branch are adjusted to match the angle adjustment information of the plant axis: the pipeline route is kept unchanged, the turning radius and turning angle of the turning section of the pipeline are also kept unchanged, and the angle θ of the bifurcation angle between the water diversion bifurcated pipe branch is kept unchanged. According to the angle formed by the direction after the adjustment of the plant axis and the direction before the adjustment of the plant axis, the relative angles α and β between the water diversion bifurcated pipe branch and the water diversion bifurcated pipe branch are adjusted, and the angle of the bifurcation angle between the water diversion bifurcated pipe branch + the relative angle between the water diversion bifurcated pipe branch and the water diversion bifurcated pipe branch = 360°, α+β+θ=360°, and the relationship between the control point P of the intersection of the water diversion branch axis and the plant axis changes; the adjustment strategy 2 of the tailwater system is the same as that of the water diversion system;

[0098] Furthermore, Strategy 3 specifically includes:

[0099] like Figure 4 As shown, the angle between the axis of the water diversion branch pipe and the axis of the powerhouse is adjusted to match the angle adjustment information of the powerhouse axis: keep the route of the pipeline unchanged, keep the turning radius and turning angle of the turning section of the pipeline unchanged, and keep the relative angles α and β between the water diversion branch pipe and the water diversion branch pipe, and the angle θ of the bifurcation angle between the water diversion branch pipes unchanged; according to the angle formed by the direction of the powerhouse axis after adjustment and the direction of the powerhouse axis before adjustment, adjust the angle γ between the axis of the water diversion branch pipe and the powerhouse axis, and at the same time ensure that the angle between the axis of the water diversion branch pipe and the powerhouse axis is greater than 60° and less than 180°; the adjustment strategy three of the tailwater system is the same as that of the water diversion system.

[0100] Example 4

[0101] Combination Figure 1 As shown, an embodiment of the present invention provides a method for dynamically adjusting a water transmission line based on an axis of an underground powerhouse, comprising the following steps:

[0102] S1, read the parameters of the water transmission line, obtain the building information on the water transmission route, generate control points, and process the control points to generate turning sections;

[0103] S2. Obtaining the adjustment parameters of the plant axis;

[0104] S3. When the plant axis adjustment parameter shows that the plant axis angle needs to be adjusted, one of the plant axis angle adjustment strategies 1, 2 and 3 is selected. Strategy 1 is to adjust the turning section of the pipeline of the water transmission line. Strategy 2 is to adjust the relative angle between the branch pipe and the bifurcated branch pipe at the fork of the pipeline of the water transmission line. Strategy 3 is to adjust the angle between the pipeline of the water transmission line and the plant axis.

[0105] Specifically, the decision of which strategy to choose, one, two, or three, can be made based on the designer’s previous experience;

[0106] When the plant axis adjustment parameter shows that the plant axis position needs to be adjusted, and the plant axis position moves upstream, the length of each flat section of the pipeline of the water transmission line is shortened;

[0107] When the powerhouse axis adjustment parameters show that the powerhouse axis position needs to be adjusted and the powerhouse axis position moves downstream, the tailwater tunnel length is reduced;

[0108] S4. Dynamically adjust the water delivery line based on the adjustment of the plant axis angle and the plant axis position;

[0109] Further, the control points include water diversion system control points and tailwater system control points;

[0110] Further, the spacing includes the spacing of the diversion system and the spacing of the tailwater system;

[0111] Furthermore, the process of generating a turning segment specifically includes:

[0112] Connect control points to form multiple lines, select corner control points, detect and select adjacent corner control points from the corner control points, perform corner processing on the adjacent corner control points, and generate turning sections;

[0113] Further, the plant axis adjustment parameters include: plant axis angle adjustment information, plant axis position adjustment information;

[0114] On this basis, in this embodiment, in step S3, there are two ways to adjust the position of the plant axis. One is to reduce the length of each flat section of the pipeline of the water transmission line, and the other is to reduce the length of the tailwater tunnel. Among them, reducing the length of each flat section of the pipeline of the water transmission line specifically includes:

[0115] When the powerhouse axis needs to be moved upstream, the length of each flat section of the water transmission line pipeline is shortened according to the powerhouse axis position adjustment information, the length of the tailwater tunnel is increased accordingly, and the sum of the lengths of each flat section is equal to the length of the tailwater tunnel;

[0116] like Figure 5 As shown, each flat section of the pipeline of the water transmission line is divided into an upper flat section, a middle flat section and a lower flat section. The length of the upper flat section is Lpy1, the length of the middle flat section is Lpy2, the length of the lower flat section is Lpy3, and the length of the tailwater tunnel is Lw. When the axis of the powerhouse needs to move upstream, according to the position adjustment information of the axis of the powerhouse, that is, the length of the axis of the powerhouse moving upstream, the length of each flat section of the pipeline of the water transmission line is correspondingly reduced, that is, the length of the upper flat section Lpy1, the length of the middle flat section Lpy2, and the length of the lower flat section Lpy3 are adjusted, and the length of the tailwater tunnel Lw is correspondingly increased, and Lw=Lpy1+Lpy2+Lpy3 is satisfied at the same time; in actual application, if the pressure pipeline is in the form of a single vertical shaft or a single inclined shaft, there are only the upper flat section Lpy1 and the lower flat section Lpy3, and there is no middle flat section Lpy2, and Lw=Lpy1+Lpy3 needs to be satisfied accordingly;

[0117] Furthermore, reducing the length of the tailwater tunnel specifically includes:

[0118] When the powerhouse axis needs to be moved downstream, the length of the tailwater tunnel is shortened according to the powerhouse axis position adjustment information, and the lengths of the respective flat sections of the pipeline of the corresponding water transmission line are adjusted, and the sum of the lengths of the respective flat sections is made equal to the length of the tailwater tunnel;

[0119] like Figure 6 As shown, when the plant axis needs to move downstream, the length of the tailwater tunnel Lw is correspondingly reduced according to the plant axis position adjustment information, that is, the length of the plant axis moved downstream, and the length of the upper flat section Lpy1, the length of the middle flat section Lpy2, and the length of the lower flat section Lpy3 are increased, and Lw=Lpy1+Lpy2+Lpy3 is satisfied at the same time; similarly, in actual application, if the pressure pipeline is in the form of a single vertical shaft or a single inclined shaft, there are only an upper flat section Lpy1 and a lower flat section Lpy3, and there is no middle flat section Lpy2, and Lw=Lpy1+Lpy3 needs to be satisfied accordingly.

[0120] It should be noted that the horizontal length mentioned above is not the actual length. The actual length needs to be calculated based on the horizontal length, each flat section and the slope of the tailwater tunnel.

[0121] Example 5

[0122] The embodiment of the present invention further provides a system for dynamically adjusting a water transmission line based on the above-mentioned method for dynamically adjusting a water transmission line based on an underground powerhouse axis, comprising a data reading and analysis module, a powerhouse axis adjustment module and a water transmission line dynamic adjustment module;

[0123] The data reading and analysis module is used to obtain and read the parameters of the water transmission line, building information, and plant axis adjustment parameters, and analyze and generate control points and turning sections;

[0124] The plant axis adjustment module is used to select and execute the plant angle adjustment strategy, select and execute the length of each flat section of the pipeline of the water transmission line or the length of the tailwater tunnel;

[0125] The water supply line dynamic adjustment module is used to dynamically adjust the water supply line according to the adjustment of the plant axis angle and the plant axis position.

[0126] The above description is only an embodiment of the present invention and is not intended to limit the present invention. Any modification, equivalent replacement and improvement made within the application scope of the present invention shall be included in the protection scope of the present invention.

Claims

1. A method for dynamically adjusting a water supply line based on an underground powerhouse axis, characterized in that: The following steps are involved: S1, read the parameters of the water transmission line, obtain the building information on the water transmission route, generate control points, and process the control points to generate turning sections; S2. Obtaining the adjustment parameters of the plant axis; S3. When the plant axis adjustment parameter shows that the plant axis angle needs to be adjusted, one of the plant axis angle adjustment strategies 1, 2 and 3 is selected. Strategy 1 is to adjust the turning section of the pipeline of the water transmission line. Strategy 2 is to adjust the relative angle between the branch pipe and the bifurcated branch pipe at the fork of the pipeline of the water transmission line. Strategy 3 is to adjust the angle between the pipeline of the water transmission line and the plant axis. When the plant axis adjustment parameter shows that the plant axis position needs to be adjusted, and the plant axis position moves upstream, the length of each flat section of the pipeline of the water transmission line is shortened; When the powerhouse axis adjustment parameters show that the powerhouse axis position needs to be adjusted and the powerhouse axis position moves downstream, the tailwater tunnel length is reduced; S4. Based on the adjustment of the plant axis angle and the plant axis position, the water supply line is dynamically adjusted.

2. The method for dynamic adjustment of water supply lines based on the axis of underground powerhouse according to claim 1, characterized in that: In step S1, the water delivery route parameters include multiple three-dimensional multi-segment routes, pipeline parameters of each segment of the route, main pipe parameters, branch pipe parameters, bifurcated pipe parameters, branch pipe parameters at the bifurcated pipe, bifurcated branch pipe parameters, the starting point, end point and route length of the route, the horizontal length of each flat section of the pipeline of the water delivery route, and the horizontal length of the tailwater tunnel of the water delivery route; The building information includes the location, spacing, direction, water supply form and number of units of the building. The number of main pipes and branch pipes of the water transmission line is determined based on the water supply form and the number of units.

3. The method for dynamic adjustment of water supply lines based on the axis of underground powerhouse according to claim 2, characterized in that: In step S1, the control points include the water diversion system control points and the tailwater system control points; The control points of the water diversion system include: the water diversion pressure regulating well is the control point J, the center point of the water diversion branch pipe is the control point K, the intersection point of the water diversion branch pipe axis and the powerhouse axis is the control point P, and the intersection point of the center line of the line turning section is the control point H; The control points of the tailwater system include: the center point of the unit is the control point C, the center point of the tailwater branch pipe is the control point K', the bottom tunnel of the tailwater chamber is the control point L, the tailwater surge chamber is the control point M, and the intersection point of the center line of the line turning section is the control point H; The control points are arranged in order according to the main pipe of the water transmission line, the branch pipe of the water transmission line and the direction of water flow.

4. The method for dynamic adjustment of water supply lines based on the axis of underground powerhouse according to claim 3, characterized in that: In step S1, the spacing includes the water diversion system spacing and the tailwater system spacing; The spacing of the water diversion system includes: the spacing between the water diversion and surge tanks LJ, the spacing between the center points of the branch pipes LK, and the spacing between the intersection points of the water diversion branch pipe axis and the powerhouse axis LP; The tailwater system spacing includes: unit center spacing LC, tailwater branch pipe center spacing LK', tailwater lock chamber bottom tunnel spacing LL, tailwater surge chamber spacing LM; Determine the location of the control points based on the number of main pipes, the number of branch pipes and the spacing between them, and connect the control points in sequence.

5. The method for dynamic adjustment of water supply lines based on the axis of underground powerhouse according to claim 4, characterized in that: In step S1, generating a turning segment specifically includes: Control points are connected to form multiple lines, corner control points are screened, and adjacent corner control points are detected and screened out from the corner control points, and the adjacent corner control points are processed to generate turning sections.

6. The method for dynamic adjustment of water supply lines based on the axis of underground powerhouse according to claim 5, characterized in that: In step S2, the factory axis adjustment parameters include: factory axis angle adjustment information and factory axis position adjustment information.

7. The method for dynamically adjusting the water supply line based on the axis of the underground powerhouse according to claim 6, characterized in that: In step S3, strategy 1 specifically includes: Adjust the line direction of the water transmission line pipeline and the corresponding parameters of the turning section of the pipeline, keep the angle between the water diversion branch pipe and the plant axis unchanged, and match the angle adjustment information of the plant axis: according to the angle formed by the direction of the plant axis after adjustment and the direction of the plant axis before adjustment, keep the relative relationship between the center control point K of the water diversion branch pipe and the intersection control point P of the water diversion branch pipe axis and the plant axis unchanged, adjust the position of the turning section H of the pipeline, adjust the radius and angle of the turning section to meet the design limit requirements of the turning radius and the design limit requirements of the turning angle; the adjustment strategy of the tailwater system is the same as that of the water diversion system.

8. The method for dynamic adjustment of water supply lines based on the axis of underground powerhouse according to claim 6, characterized in that: In step S3, strategy 2 specifically includes: Adjust the relative angles α and β between the water diversion bifurcated pipe and the water diversion bifurcated pipe to match the angle adjustment information of the plant axis: keep the route of the pipeline unchanged, the turning radius and turning angle of the turning section of the pipeline also remain unchanged, and the angle θ of the bifurcation angle between the water diversion bifurcated pipes remains unchanged. According to the angle formed by the direction after the adjustment of the plant axis and the direction before the adjustment of the plant axis, adjust the relative angles α and β between the water diversion bifurcated pipe and the water diversion bifurcated pipe, and the angle of the bifurcation angle between the water diversion bifurcated pipe + the relative angle between the water diversion bifurcated pipe and the water diversion bifurcated pipe = 360°, α+β+θ=360°, the relationship between the control point P of the intersection of the water diversion branch pipe axis and the plant axis changes; the adjustment strategy 2 of the tailwater system is the same as that of the water diversion system.

9. The method for dynamically adjusting the water supply line based on the axis of the underground powerhouse according to claim 6, characterized in that: In step S3, strategy three specifically includes: Adjust the angle between the axis of the water diversion branch pipe and the axis of the powerhouse to match the angle adjustment information of the powerhouse axis: keep the route of the pipeline unchanged, keep the turning radius and turning angle of the turning section of the pipeline unchanged, and keep the relative angles α and β between the water diversion branch pipe and the water diversion branch pipe, and the angle θ of the bifurcation angle between the water diversion branch pipes unchanged; adjust the angle γ between the axis of the water diversion branch pipe and the axis of the powerhouse according to the angle formed by the direction after the adjustment of the powerhouse axis and the direction before the adjustment of the powerhouse axis, and at the same time ensure that the angle between the axis of the water diversion branch pipe and the axis of the powerhouse is greater than 60° and less than 180°; the adjustment strategy three of the tailwater system is the same as that of the water diversion system.

10. The method for dynamic adjustment of water supply lines based on the axis of underground powerhouse according to claim 6, characterized in that: In step S3, reducing the length of each flat section of the pipeline of the water transmission line specifically includes: When the plant axis needs to move upstream, the length of each flat section of the water supply line pipeline is shortened according to the plant axis position adjustment information, the length of the tailwater tunnel is increased accordingly, and the sum of the lengths of each flat section is made equal to the length of the tailwater tunnel.

11. The method for dynamically adjusting the water supply line based on the axis of the underground powerhouse according to claim 6, characterized in that: In step S3, reducing the length of the tailwater tunnel specifically includes: When the plant axis needs to move downstream, the length of the tailwater tunnel is shortened according to the plant axis position adjustment information, the lengths of the various flat sections of the pipeline of the corresponding water transmission line are shortened, and the sum of the lengths of the various flat sections is made equal to the length of the tailwater tunnel.

12. A system for dynamically adjusting a water delivery line using the method for dynamically adjusting a water delivery line based on an underground powerhouse axis as claimed in any one of claims 1 to 11, characterized in that: It includes data reading and analysis module, plant axis adjustment module and water transmission line dynamic adjustment module; The data reading and analysis module is used to obtain and read the parameters of the water transmission line, building information, and plant axis adjustment parameters, and analyze and generate control points and turning sections; The plant axis adjustment module is used to select and execute the plant angle adjustment strategy, select and execute the length of each flat section of the pipeline of the water transmission line or the length of the tailwater tunnel; The water supply line dynamic adjustment module is used to dynamically adjust the water supply line according to the adjustment of the plant axis angle and the plant axis position.

Citation Information

Patent Citations

  • main coolant pump, ESPECIALLY FOR PRESSURE WATER NUCLEAR POWER PLANTS, WITH A SAFETY DEVICE

    AT322985B

  • Method for deicing energized electrical transmission lines

    CA2499131A1

  • Underground cavity longitudinal axis arrangement method under leading effect of high ground stress factors

    CN110747832A

  • Method and system for measuring flow of special-shaped water conveying pipe culvert

    CN112857491A

  • Construction method for continuous underneath passing of large-diameter water delivery pipeline in shield section

    CN114737979A