Slag basin for cooling high titanium slag and using method thereof
By adopting a double-layer structure slag basin and a central hanging lump design, the problems of short service life and low release reliability of slag basin in high-titanium slag cooling and demolding technology are solved, and efficient and stable high-titanium slag cooling and removal process are achieved.
Patent Information
- Application Number
- CN202510280432.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2025-03-11
- Publication Date
- 2025-05-30
AI Technical Summary
The existing high-titanium slag cooling and demolding technology has the problems of short service life of slag basins and low demolding reliability, resulting in low production efficiency.
A slag basin with a double-layer structure includes an inner layer made of heavy refractory bricks and an outer layer composed of structural steel welded parts. A hanging lump is set up in the center and a protective coating is coated on the surface of the hanging lump.
Effectively reduce thermal shock, extend the service life of slag basins, improve the reliability of mold release, simplify the operation process, reduce production costs, and improve the production efficiency of high-titanium slag cooling and removal links.
Smart Images

Figure CN120062995A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of metallurgical technology, and particularly to a slag basin for cooling high-titanium slag and a method for using the same. Background Art
[0002] In the process of producing titanium dioxide by the chlorination method using ilmenite as a raw material, high-titanium slag, as an important intermediate product, its cooling process has an important impact on subsequent production processes. By rapidly cooling the molten high-titanium slag, the content of rutile phase in the high-titanium slag can be effectively reduced, thereby improving the acidolysis rate of the titanium slag and further enhancing the efficiency of the entire production process. However, there are some problems to be solved urgently in the existing high-titanium slag cooling and demoulding technologies.
[0003] First of all, the slag basin, as a commonly used device for cooling high-titanium slag, is usually a casting or a welded part. When the molten high-titanium slag enters the slag basin, it will cause a strong thermal shock to the slag basin. This thermal shock will cause the temperature of the slag basin to rise rapidly, and then cause the deformation or cracking of the slag basin. Although laying a layer of high-titanium slag at the bottom of the slag basin in advance can slow down the thermal shock to a certain extent, this measure cannot effectively inhibit the deformation and cracking of the slag basin fundamentally. At present, the service life of the slag basin is short. Frequent replacement of the slag basin not only increases the production cost, but also affects the continuity of production.
[0004] Secondly, in the process of removing the high-titanium slag from the slag basin, the commonly used method at present is to place a pair of metal wedges at the edge of the slag basin to form wedge holes during the condensation of the molten high-titanium slag. Subsequently, a lifting fixture is placed at the wedge holes to lift the solidified high-titanium slag out of the slag basin. However, during the lifting process, the high-titanium slag near the wedge holes needs to bear a large stress, which makes the high-titanium slag prone to breakage or loss at the wedge holes. Once the wedge holes are damaged, the high-titanium slag needs to be broken before it can be removed from the slag basin, which not only increases the complexity of the operation, but also greatly reduces the production efficiency. It can be seen that the existing method of setting wedge holes for demoulding has low reliability and is prone to cause breakage of high-titanium slag and a decrease in production efficiency.
[0005] The problems of short service life of the slag basin and low demoulding reliability in the prior art seriously affect the production efficiency of the high-titanium slag cooling and removal links.
[0006] In view of this, the present invention is specifically proposed. Summary of the Invention
[0007] One of the purposes of the present invention is to provide a slag basin for cooling high-titanium slag, aiming to solve at least one of the above technical problems in the prior art.
[0008] Another purpose of the present invention is to provide a method for using a slag basin for cooling high-titanium slag.
[0009] To achieve the above object of the present invention, the following technical solutions are specifically adopted:
[0010] A slag basin for cooling high-titanium slag according to a first aspect of the present invention includes a slag hopper and a hanging weight.
[0011] The slag hopper is in the shape of an ark with a large top and a small bottom, and the slag hopper has a double-layer structure; the hanging weight is arranged at the central position of the slag hopper.
[0012] A protective coating is provided on the surface of the hanging weight.
[0013] Further, the double-layer structure includes an inner layer and an outer layer.
[0014] The inner layer is made of heavy refractory bricks stacked, and the outer layer is composed of structural steel welded parts.
[0015] Further, lifting hooks and reinforcing ribs are provided on the outer wall of the structural steel welded parts.
[0016] Further, in the inner cavity of the slag hopper, the bottom size is 2000 - 3000 mm in length, 1000 - 2000 mm in width, and 800 - 1000 mm in height.
[0017] In the inner cavity of the slag hopper, the top size is 3500 - 4500 mm in length and 3000 - 4000 mm in width.
[0018] Further, the hanging weight is a metal casting and is composed of a lifting ring and a square platform.
[0019] The lifting ring is arranged above the square platform, and the square platform is in the shape of a truncated pyramid with a small top and a large bottom.
[0020] The top length of the square platform is 200 - 300 mm, the width is 150 - 200 mm, and the height is 600 - 800 mm.
[0021] The bottom length of the square platform is 600 - 800 mm and the width is 500 - 600 mm.
[0022] Further, the hanging weight is a metal casting and is composed of a lifting ring and a frustum of a cone.
[0023] The lifting ring is arranged above the frustum of the cone, and the frustum of the cone is in the shape of an inverted mushroom with a small top and a large bottom.
[0024] The lower diameter of the frustum of the cone is 600 - 800 mm, the upper diameter is 200 - 300 mm, and the height is 600 - 800 mm.
[0025] Further, the protective coating contains first high-titanium slag.
[0026] And / or, a second high-titanium slag layer is provided on the inner surface of the slag hopper.
[0027] And / or, the thickness of the second high-titanium slag layer is 100 - 300 mm.
[0028] Furthermore, the particle size of the first high-titanium slag is less than 100 mesh.
[0029] Furthermore, the particle size of the second high-titanium slag in the second high-titanium slag layer is less than 2 mesh.
[0030] In the second aspect of the present invention, a method for using the slag basin is provided. Molten third high-titanium slag is poured into the slag basin. After the upper surface layer of the third high-titanium slag solidifies, cooling water is poured from the hanging weight to accelerate cooling. After the third high-titanium slag is completely solidified, the third high-titanium slag is lifted from the hanging weight and broken, and then the hanging weight is removed.
[0031] Compared with the prior art, the present invention has at least the following beneficial effects:
[0032] The slag basin for cooling high-titanium slag provided by the present invention adopts a double-layer structure, which can effectively reduce the thermal impact force generated when the molten high-titanium slag enters, and avoid deformation or cracking caused by local stress concentration. At the same time, the hanging weight arranged in the center of the slag hopper enhances the overall structural stability, and the protective coating on its surface further provides heat insulation, corrosion resistance and wear resistance protection, significantly extending the service life of the slag basin. In addition, the design of the hanging weight abandons the traditional wedge-hole demoulding method, enabling the high-titanium slag to naturally form a stable connection structure during the condensation process, with uniform stress during lifting, reducing the risk of breakage and improving the reliability of demoulding. While extending the service life of the slag basin, the present invention significantly improves the reliability of high-titanium slag demoulding, providing a more efficient and stable solution for the cooling and removal of high-titanium slag.
[0033] The method for using the slag basin of the present invention accelerates the cooling process by pouring cooling water from the hanging weight after the upper surface layer of the high-titanium slag solidifies, significantly shortening the time for the high-titanium slag to change from the molten state to the completely solidified state and improving production efficiency. At the same time, this method uses the hanging weight for hoisting and removing the high-titanium slag, simplifies the demoulding operation, reduces the risk of high-titanium slag breakage caused by damage to the wedge hole, and reduces the manual operation intensity and production cost. The optimized cooling and demoulding methods not only improve the safety and reliability of demoulding, but also reduce the risk of equipment damage and production interruption, significantly improving the overall production efficiency of the high-titanium slag cooling and removal process, and providing efficient and stable technical support for titanium dioxide production. BRIEF DESCRIPTION OF THE DRAWINGS
[0034] To more clearly illustrate the specific embodiments of the present invention or the technical solutions in the prior art, the following will briefly introduce the drawings required for the description of the specific embodiments or the prior art. Obviously, the drawings in the following description are some embodiments of the present invention. For those of ordinary skill in the art, without creative efforts, other drawings can also be obtained based on these drawings.
[0035] Figure 1 Schematic structural diagram of the slag basin provided for Example 1;
[0036] Figure 2 Schematic structural diagram of the slag basin provided for Example 2;
[0037] Figure 3 Schematic structural diagram of the slag basin provided for Example 3.
[0038] Main element symbol description: 10 - slag hopper; 11 - outer welded member; 111 - lifting hook; 112 - reinforcing rib; 12 - inner layer of hard refractory brick; 20 - hanging weight; 21 - lifting ring; 22 - square platform; 23 - frustum; 30 - protective coating; 40 - form the second high-titanium slag layer. Specific embodiments
[0039] To make the objectives, technical solutions, and advantages of the present invention clearer, the following will clearly and completely describe the technical solutions in the embodiments of the present invention with reference to the drawings in the embodiments of the present invention. Obviously, the described embodiments are only some embodiments of the present invention, rather than all embodiments.
[0040] In the following text, the terms "including", "having", and their cognates that can be used in various embodiments of the present invention are only intended to represent specific features, numbers, steps, operations, elements, components, or combinations of the foregoing items, and should not be construed as first excluding the existence of one or more other features, numbers, steps, operations, elements, components, or combinations of the foregoing items or increasing the possibility of one or more features, numbers, steps, operations, elements, components, or combinations of the foregoing items.
[0041] The first aspect of the present invention provides a slag basin for cooling high-titanium slag, including a slag hopper 10 and a hanging weight 20. The slag hopper 10 is in the shape of an ark with a large top and a small bottom, and the hanging weight 20 is arranged at the central position of the slag hopper 10. A protective coating 30 is provided on the surface of the hanging weight 20.
[0042] The slag pot for cooling high-titanium slag provided by the present invention adopts the structure of an ark-shaped slag hopper 10 with a larger upper part and a smaller lower part, which can effectively slow down the thermal impact force generated when the molten high-titanium slag enters, and avoid deformation or cracking caused by local stress concentration. At the same time, the hanging weight 20 arranged in the center of the slag hopper 10 enhances the overall structural stability, and the protective coating 30 on its surface further provides heat insulation, corrosion resistance and wear resistance protection, significantly extending the service life of the slag pot. In addition, the design of the hanging weight 20 abandons the traditional wedge-hole demoulding method, enabling the high-titanium slag to naturally form a stable connection structure during the condensation process. When lifted out, the force is evenly distributed, reducing the risk of breakage and improving the reliability of demoulding. The present invention not only extends the service life of the slag pot, but also significantly improves the reliability of high-titanium slag demoulding, providing a more efficient and stable solution for the cooling and removal of high-titanium slag.
[0043] The slag pot of the present invention adopts the structure of an ark-shaped slag hopper 10 with a larger upper part and a smaller lower part, and this design can effectively slow down the thermal impact force generated when the molten high-titanium slag enters the slag pot. Compared with the traditional slag pot, it avoids the problems of deformation or cracking caused by local stress concentration. In addition, the protective coating 30 arranged on the surface of the hanging weight 20 not only provides heat insulation protection, but also enhances the corrosion resistance and wear resistance of the hanging weight. These improvement measures work together to significantly extend the service life of the slag pot and reduce the frequent replacement and maintenance costs caused by slag pot damage.
[0044] The slag pot design of the present invention abandons the traditional demoulding method of setting wedge holes at the edge of the slag pot, and realizes the removal of high-titanium slag through the hanging weight 20. The hanging weight 20 is located in the center of the slag hopper 10, and its structural design enables the high-titanium slag to naturally form a stable connection structure during the condensation process, avoiding the problem of high-titanium slag breakage caused by stress concentration at the traditional wedge holes. During the lifting process, the force on the high-titanium slag is more evenly distributed, reducing the risk of breakage caused by excessive stress. In addition, the protective coating 30 on the surface of the hanging weight 20 further reduces the adhesion between the high-titanium slag and the hanging weight 20, making the demoulding process smoother, improving the reliability of demoulding, and reducing the decline in production efficiency caused by demoulding failure.
[0045] Furthermore, the slag hopper 10 has a double-layer structure; the double-layer structure includes an inner layer and an outer layer.
[0046] The inner layer is made of heavy refractory bricks stacked, and the outer layer is composed of structural steel welded parts. The inner refractory bricks have excellent high-temperature resistance and heat insulation performance, can withstand the high-temperature impact of molten high-titanium slag and slow down the heat conduction to the outside, protecting the outer structural steel components from the influence of high temperature; the outer structural steel components provide high-strength support for the slag hopper 10 to ensure its structural integrity when bearing the weight and stress of high-titanium slag during the cooling process. This double-layer structure gives full play to the advantages of refractory bricks and structural steel, effectively reducing the risk of deformation and damage caused by thermal shock, and significantly improving the service life and reliability of the slag hopper 10.
[0047] On the one hand, the heavy-duty refractory brick has good heat insulation performance, which can effectively slow down the thermal shock borne by the outer metal weldment; on the other hand, it has excellent erosion resistance and can resist the erosion of molten high-titanium slag, thus significantly improving the erosion resistance of the slag basin.
[0048] Furthermore, a lifting hook 111 and a reinforcing rib 112 are provided on the outer wall of the structural steel weldment. The lifting hook 111 provides a convenient connection for the hoisting and movement of the slag bucket. By performing the hoisting operation at the lifting lug 20, the solidified high-titanium slag can be quickly and stably lifted out of the slag bucket, while avoiding direct contact with the internal structure of the slag bucket and possible damage. This design not only improves the efficiency and safety of demoulding, but also reduces the risk of high-titanium slag breakage caused by improper hoisting.
[0049] The setting of the reinforcing rib 112 can significantly enhance the structural strength and stability of the outer wall of the slag basin. When the slag basin bears the high-temperature impact of molten high-titanium slag and the stress generated during the cooling process, the reinforcing rib 112 can effectively disperse the stress and prevent the outer wall from deforming or cracking. In addition, the reinforcing rib 112 can also improve the overall rigidity of the slag bucket, extend its service life, and ensure the reliability and stability of the slag bucket during long-term use.
[0050] The combination of the lifting hook 111 and the reinforcing rib 112 not only improves the hoisting and operating performance of the slag bucket, but also enhances its structural strength and durability. This design enables the slag basin to operate stably under complex working conditions of high temperature and high stress, while simplifying the operation process, reducing production costs, and improving production efficiency.
[0051] Furthermore, in the inner cavity of the slag bucket 10, the bottom size is 2000 - 3000 mm in length, 1000 - 2000 mm in width, and 800 - 1000 mm in height.
[0052] In the inner cavity of the slag bucket 10, the top size is 3500 - 4500 mm in length and 3000 - 4000 mm in width.
[0053] Furthermore, the lifting lug 20 is a metal casting and is composed of a lifting ring 21 and a square platform 22.
[0054] The lifting ring 21 is arranged above the square platform 22, and the square platform 22 is a frustum-shaped structure with a smaller top and a larger bottom. The lifting lug 20 adopts the frustum-shaped structure of the square platform 22. When the molten high-titanium slag solidifies, a connection structure matching the structure of the square platform 22 will be formed. During hoisting, the connection structure is in close contact with the lifting lug 20, and the solidified high-titanium slag can be stably lifted out of the slag bucket, thus significantly improving the reliability of demoulding.
[0055] The top length of the square platform 22 is 200 - 300 mm, the width is 150 - 200 mm, and the height is 600 - 800 mm.
[0056] The bottom length of the square platform 22 is 600 - 800 mm, and the width is 500 - 600 mm.
[0057] Further, the hanging weight 20 is a metal casting, composed of a lifting ring 21 and a frustum 23. The lifting ring 21 is arranged above the frustum 23. The frustum 23 has an inverted mushroom-like structure with a smaller upper part and a larger lower part. The lower diameter of the frustum 23 is 600 - 800 mm, the upper diameter is 200 - 300 mm, and the height is 600 - 800 mm.
[0058] Further, the protective coating 30 contains first high-titanium slag. Coating the surface of the hanging weight 20 with the protective coating 30 can effectively extend the service life of the hanging weight 20. At the same time, using an organic binder and first high-titanium slag to manufacture the protective coating 30 avoids the infiltration of metal ions, thereby preventing pollution to the high-titanium slag.
[0059] In the specific implementation process, the organic binder uses starch. Add starch to water and stir evenly to obtain a colloid. At the same time, crush the first high-titanium slag into a powder with a particle size less than 100 mesh. Mix the above colloid and high-titanium slag powder evenly to obtain a plastic dough. Coat the plastic dough evenly on the surface of the hanging weight 20 and dry it to obtain the protective coating 30.
[0060] In another implementation process, the organic binder is carboxymethyl cellulose. Dissolve carboxymethyl cellulose in water to obtain an adhesive. Subsequently, add first high-titanium slag powder with a particle size less than 100 mesh, mix evenly to obtain a plastic dough. Coat the plastic dough evenly on the surface of the hanging weight 20 and dry it to obtain the protective coating 30.
[0061] And / or, the inner surface of the slag bucket 10 is provided with a second high-titanium slag layer, which can not only further reduce the thermal shock borne by the slag bucket, but also enhance its erosion resistance, ensuring that the slag bucket has a long service life.
[0062] And / or, the thickness of the second high-titanium slag layer is 100 - 300 mm. In the specific implementation process, in order to further extend the service life of the slag bucket, lay granular second high-titanium slag with a thickness of 200 - 300 mm at the bottom of the slag bucket 10, and lay second high-titanium slag with a thickness of 100 - 200 mm on the wall of the slag bucket 10 to form the second high-titanium slag layer 40.
[0063] Further, the particle size of the first high-titanium slag is less than 100 mesh.
[0064] Further, the particle size of the second high-titanium slag is less than 2 mesh.
[0065] In the second aspect of the present invention, a method for using the slag pot is provided. Molten third high-titanium slag is poured into the slag pot. After the upper surface layer of the third high-titanium slag solidifies, cooling water is poured from the lifting weight 20 to accelerate cooling. After the third high-titanium slag is completely solidified, the third high-titanium slag is lifted from the lifting weight 20 and can be removed outside the slag bucket.
[0066] The method for using the slag pot of the present invention significantly shortens the time for the high-titanium slag to change from the molten state to complete solidification and improves production efficiency by pouring cooling water from the lifting weight 20 after the upper surface layer of the high-titanium slag solidifies, thereby accelerating the cooling process. At the same time, this method uses the lifting weight 20 for hoisting and removing the high-titanium slag, simplifies the demolding operation, reduces the risk of high-titanium slag breakage caused by damage to the wedge holes, and reduces the manual operation intensity and production cost. The optimized cooling and demolding methods not only improve the safety and reliability of demolding, but also reduce the risk of equipment damage and production interruption, significantly enhancing the overall production efficiency of the high-titanium slag cooling and removal processes, and providing efficient and stable technical support for titanium dioxide production.
[0067] Specifically, after the upper surface layer of the third high-titanium slag of the present invention solidifies, cooling water is poured from the lifting weight 20. This cooling method can quickly reduce the temperature of the high-titanium slag, enabling the internal heat to be rapidly conducted and dissipated. Compared with traditional natural cooling or single air cooling, the direct contact with cooling water significantly increases the cooling rate, shortens the time for the high-titanium slag to change from the molten state to complete solidification, and thus improves production efficiency.
[0068] After the high-titanium slag is completely solidified, the high-titanium slag is lifted and removed from the slag pot through the lifting weight 20. Since the lifting weight 20 is located at the center of the slag bucket 10 and the structure of the slag pot is optimized, the high-titanium slag can shrink uniformly during the condensation process, reducing adhesion to the inner wall of the slag bucket. The design of the lifting weight 20 enables the high-titanium slag to be evenly stressed when lifted out, further improving the safety and reliability of demolding and reducing the risk of high-titanium slag breakage or slag pot damage caused by improper demolding. Pouring water for cooling from the lifting weight 20 can not only quickly reduce the temperature of the high-titanium slag, but also cool the lifting weight 20 at the same time. Since the lifting weight 20 is a metal part with better heat conduction performance than the high-titanium slag, by virtue of the heat transfer effect of the lifting weight 20, the cooling process of the high-titanium slag can be accelerated, thereby shortening the cooling time and improving production efficiency. In addition, the cooling water can also penetrate downward through the protective coating 30 or the high-titanium slag laid on the four walls of the slag bucket 10 to cool the inside or the surroundings of the high-titanium slag, further shortening the cooling time and enhancing production efficiency.
[0069] The usage method of the present invention abandons the complex demolding method of setting wedge holes at the edge of the slag basin, and directly uses the lifting weight 20 for hoisting and removal. This design simplifies the operation process, reduces the cumbersome steps of crushing high-titanium slag due to damage to the wedge holes, reduces the manual operation intensity and production cost, and at the same time improves the continuity and stability of production.
[0070] By accelerating cooling and simplifying the demolding operation, the present invention not only shortens the cooling and removal time of high-titanium slag, but also reduces production interruptions caused by equipment damage or operation errors. This optimized usage method can significantly improve the overall production efficiency of the high-titanium slag cooling and demolding links, and provides more efficient and stable technical support for the industrial production of titanium dioxide by the chloride process.
[0071] Example 1
[0072] This example provides a slag basin with a structure as Figure 1 shown: The slag basin is composed of a slag hopper 10, a lifting weight 20 and a protective coating 30.
[0073] Among them: The slag hopper 10 adopts a double-layer structure, including an outer welded member 11 and an inner hard refractory brick 12. Four lifting hooks 111 and stiffeners 112 are arranged on the outer welded member 11 for hoisting operations and enhancing the structural strength. The inner cavity dimensions of the slag hopper 10: bottom dimensions: length 2000 mm, width 1000 mm; height: 800 mm; inner cavity top dimensions: length 3500 mm, width 3000 mm.
[0074] The lifting weight 20 is located in the middle of the slag hopper 10 and is composed of a lifting eye 21 and a square platform 22. The lifting eye 21 is arranged above the square platform 22 for hoisting operations. The dimensions of the square platform 22 are as follows: lower dimensions: length 600 mm, width 500 mm; upper dimensions: length 200 mm, width 150 mm; height: 600 mm. The lifting weight 20 is cast and formed using ZG25 material.
[0075] The protective coating 30 is evenly coated on the outer surface of the lifting weight 20 with a thickness of 20 mm to protect the lifting weight 20 from high-temperature erosion and mechanical impact.
[0076] Add starch to water, stir and heat it to form a colloid. Subsequently, crush the first high-titanium slag to a particle size of less than 100 mesh and mix it evenly with the above colloid to form a plastic dough. Coat the surface of the lifting weight 20 evenly with this plastic dough with a coating thickness of 20 mm, and then dry it at 80 °C to obtain the protective coating 30.
[0077] Example 2
[0078] This example provides another slag basin with a structure as Figure 2As shown: The slag basin consists of a slag hopper 10, a hanging weight 20, and a protective coating 30.
[0079] Among them: The slag hopper 10 adopts a double-layer structure, including an outer welded member 11 and an inner hard refractory brick 12. Four lifting hooks 111 and reinforcing ribs 112 are arranged on the outer welded member 11 for lifting operations and enhancing the structural strength. The inner cavity dimensions of the slag hopper 10 are as follows: The bottom dimension of the inner cavity: length 3000 mm, width 2000 mm; the height of the inner cavity: 1000 mm; the top dimension of the inner cavity: length 4500 mm, width 4000 mm.
[0080] A granular high-titanium slag layer with a thickness of 250 mm is laid at the bottom of the slag hopper 10 to form a second high-titanium slag layer 40, and a granular high-titanium slag layer with a thickness of 150 mm is laid on the inner wall of the slag hopper 10 to form a second high-titanium slag layer 40. The particle size of the granular high-titanium slag is less than 2 mesh.
[0081] The hanging weight 20 is located at the central position of the slag hopper 10 and consists of a lifting ring 21 and a square platform 22. The lifting ring 21 is arranged above the square platform 22 for lifting operations. The dimensions of the square platform 22 are as follows: The lower part dimension: length 700 mm, width 600 mm; the upper part dimension: length 300 mm, width 200 mm; height: 800 mm. The hanging weight 20 is cast and formed using ZG25 material.
[0082] The protective coating 30 is evenly coated on the outer surface of the hanging weight 20 with a thickness of 20 mm to protect the hanging weight 20 from high-temperature erosion and mechanical impact.
[0083] Starch is added to water and stirred and heated to form a colloid. Subsequently, the first high-titanium slag is crushed to a particle size of less than 100 mesh and mixed evenly with the above colloid to form a plastic dough. The plastic dough is evenly coated on the surface of the hanging weight 20 with a coating thickness of 20 mm, and then dried at 80 °C to obtain the protective coating 30.
[0084] Example 3
[0085] This example provides a first type of slag basin, with a structure as Figure 3 shown. Different from Example 2, the inner surface of the slag hopper 10 is not laid to form a second high-titanium slag layer 40. The hanging weight 20 consists of a lifting ring 21 and a frustum 23, where the frustum 23 has an inverted mushroom-like structure with a smaller upper part and a larger lower part. The specific dimensions are as follows: The lower diameter of the frustum 23 is 800 mm, the upper diameter is 300 mm, and the height is 800 mm. The lifting ring 21 is arranged above the frustum 23 for lifting operations. The hanging weight 20 is cast and formed using ZG25 material, and its outer surface is coated with a protective coating 30 with a coating thickness of 20 mm.
[0086] Finally, it should be noted that the above-described embodiments are only specific embodiments of the present invention, used to illustrate the technical solutions of the present invention, rather than limiting it. The protection scope of the present invention is not limited thereto. Although the present invention has been described in detail with reference to the foregoing embodiments, those of ordinary skill in the art should understand that any technician familiar with the technical field of the present invention can still modify the technical solutions described in the foregoing embodiments, or can easily think of changes, or perform equivalent replacements for some of the technical features; and these modifications, changes or replacements do not make the essence of the corresponding technical solutions deviate from the spirit and scope of the technical solutions of the embodiments of the present invention, and should all be covered within the protection scope of the present invention. Therefore, the protection scope of the present invention should be subject to the protection scope of the claims.
Claims
1. A slag basin for cooling high-titanium slag, characterized in that: Including slag bucket and hanging pile; The slag bucket is in the shape of a ark with a large top and a small bottom, and has a double-layer structure; the hanging ball is arranged at the center of the slag bucket; The surface of the hanging ball is provided with a protective coating.
2. The slag basin according to claim 1, characterized in that: The double-layer structure comprises an inner layer and an outer layer; The inner layer is formed by stacking heavy refractory bricks, and the outer layer is formed by structural steel welded parts.
3. The slag basin according to claim 2, characterized in that: The outer wall of the structural steel welded part is provided with a lifting hook and reinforcing ribs.
4. The slag basin according to claim 1, characterized in that: The bottom dimensions of the inner cavity of the slag bucket are 2000-3000 mm long, 1000-2000 mm wide, and 800-1000 mm high; The top dimension of the inner cavity of the slag bucket is 3500-4500 mm in length and 3000-4000 mm in width.
5. The slag basin according to claim 1, characterized in that: The lifting block is a metal casting, which is composed of a lifting ring and a square platform; The lifting ring is arranged above the square platform, and the square platform is a platform-like structure with a small top and a large bottom; The top length of the square platform is 200-300 mm, the width is 150-200 mm, and the height is 600-800 mm; The bottom length of the square platform is 600-800 mm and the width is 500-600 mm.
6. The slag basin according to claim 1, characterized in that: The lifting block is a metal casting, which is composed of a lifting ring and a round table; The lifting ring is arranged above the truncated platform, and the truncated platform is an inverted mushroom-shaped structure with a small top and a large bottom; The bottom diameter of the truncated cone is 600-800 mm, the top diameter is 200-300 mm, and the height is 600-800 mm.
7. The slag basin according to any one of claims 1 to 6, characterized in that: The protective coating comprises a first high-titanium slag; and / or, the inner surface of the slag hopper is provided with a second high-titanium slag layer; And / or, the thickness of the second high-titanium slag layer is 100-300 mm.
8. The slag basin according to claim 7, characterized in that: The particle size of the first high-titanium slag is less than 100 mesh.
9. The slag basin according to claim 7, characterized in that: The particle size of the second high-titanium slag in the second high-titanium slag layer is less than 2 meshes.
10. A method for using the slag basin according to any one of claims 1 to 9, characterized in that: Pour the molten third high-titanium slag into the slag basin, and after the upper surface layer of the third high-titanium slag solidifies, pour cooling water from the hanging lump to accelerate cooling; after the third high-titanium slag is completely solidified, lift the third high-titanium slag from the hanging lump, crush the third high-titanium slag, and then take out the hanging lump.