Dry-hanging type veneer with hidden leveling keel and preparation and installation process of dry-hanging type veneer

By scraping off residual material during the processing of the wall panel main body, and using expansion bolts and limit nuts to ensure the stability and smoothness of the keel main body, the problem of space and labor and material resources occupied during dry-hanging wall installation is solved, and efficient and safe wall installation is achieved.

CN120095957APending Publication Date: 2025-06-06ZHEJIANG SANFENG CONSTR CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202510116210.5
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2025-01-24
Publication Date
2025-06-06

AI Technical Summary

Technical Problem

Dry-hanging walls occupy a large indoor space during installation and require a lot of manpower and material resources. The smoke and dust generated during construction are harmful to the health of construction workers.

Method used

By scraping off residual material on the side of the initially condensed wall panel body during the processing process of the wall panel body to form an installation notch, the keel assembly can be embedded in the installation notch, avoiding the need to use a drill rig to open the notch during the installation process, and using expansion bolts and limit nuts to ensure the stability and smoothness of the keel body.

Benefits of technology

It realizes the completion of wall installation without occupying additional indoor space, reduces manpower and material consumption, reduces smoke and dust generated by construction, and improves construction safety and efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN120095957A_ABST
    Figure CN120095957A_ABST
Patent Text Reader

Abstract

The invention discloses a dry-hanging type veneer with a hidden leveling keel and a preparation and installation process of the dry-hanging type veneer. The dry-hanging type veneer structurally comprises a wall assembly, a veneer body and a keel body. The wall assembly comprises a plurality of wall plate bodies which are sequentially arranged, and mounting notches are formed in the edges of the corners of the wall plate bodies. The keel assembly is installed in the installation notch, and a clamping part is arranged at the outer end of the keel assembly. And the veneer is clamped and matched with the clamping part. In the machining process of the wallboard main body, excess materials are scraped on the side edge of the wallboard main body which is preliminarily coagulated, and the mounting notch is formed. When the wall surface is assembled, the keel assembly can be installed in the installation notch in an embedded mode, so that indoor space is not additionally occupied during installation of the veneer, and meanwhile the problems that a large amount of manpower and material resources are consumed due to the fact that a drilling machine needs to be used for forming the notch in the installation process, and the body of a constructor is damaged by smoke generated by construction are avoided.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention belongs to the technical field of prefabricated decoration, and in particular relates to a dry-hanging decorative panel with a hidden leveling keel and a preparation and installation process thereof. Background Art

[0002] In the prior art, the construction methods of prefabricated walls are mainly divided into two methods: gluing and dry hanging.

[0003] The gluing is mainly achieved by using clips on both sides of the veneer, and the connection between the veneer and the wall is achieved by using structural glue or other organic foam adhesives. Dry hanging is mainly achieved by dry hanging components. Among them, the gluing method has technical problems such as a long construction process, a high level of professional construction and difficulty in quality control, it is difficult to separate the wall and thus cannot add sockets, and there is organic chemical pollution to the indoor environment.

[0004] Among them, the dry hanging processing method has the following technical problems: 1. Between the dry hanging integrated decorative panels and the lightweight partition walls, leveling keels or clips are required to form a 10-15mm cavity, occupying the indoor use space and thus reducing the net size of the space. For example, the use of leveling modules in residential stairwells to reduce the size of the stairwell affects the minimum size of the fire escape; when the living room, bedroom, dining room and other rooms of affordable housing are small, the use area will be reduced by 5% to 10%. 2. For dry hanging reversible integrated wall panels, when the width of the decorative panel is greater than 600mm, structural adhesives are used for pasting, resulting in the damage of the decorative panel after removal and inability to reinstall. 3. The space between the bathroom and the kitchen is limited. In order to meet the net width, the thickness of the partition wall is reduced to 60mm, which does not meet the length-to-thickness ratio of ≤40 in GB / T15762-2020 "Autoclaved Aerated Concrete Board". 4. In order to meet the separation of pipelines, the socket switch wire pipe and water supply pipe are placed between the decorative panel and the partition wall, occupying 20~35mm of space.

[0005] In addition, some workers use a drill to drill slots on the wall after the wall installation is completed for the installation of the keel, thereby reducing the occupied indoor space and increasing the net size of the indoor space. However, this method will consume a lot of manpower and material resources. At the same time, a large amount of smoke and dust will be generated during the opening of the slot, which will cause damage to the health of the construction workers. Summary of the invention

[0006] In order to make up for the deficiencies of the prior art, the present invention provides a dry-hanging decorative panel with hidden leveling keels and a preparation and installation process thereof, so as to solve the technical problems that the dry-hanging wall panels occupy a large indoor space during installation and the solution requires a lot of manpower and material resources.

[0007] To achieve the above purpose, the specific technical solutions of the present invention are as follows: In the first aspect, a preparation and installation process of a dry-hanging decorative panel with a hidden leveling keel, the specific steps are as follows: S1, frame construction, according to the size of each partition board to be constructed, the steel mesh sheets of corresponding sizes are manually tied, and multiple inserted thousand rods are detachably fixed on the corresponding steel mesh sheets through clamps.

[0008] S2, pouring, pouring the concrete slurry automatically mixed by the autoclaved aerated concrete raw materials into the constructed mold.

[0009] S3, inserting the skeleton, inserting multiple steel mesh sheets into the mold after casting through an inserting machine, and after insertion, transporting them together with the mold to a curing room for gasification and initial solidification to form a blank body.

[0010] S4, pull out the plug rod inserted into the blank body.

[0011] S5, demoulding, the blank body after resting is transferred to the cutting area. The flip demoulding mechanism flips the blank body and places it on the trolley. After it is placed stably, the flip demoulding mechanism grabs the mold of the blank body except the bottom surface and disassembles and separates it.

[0012] S6, segmentation, the blank body is driven by the trolley to pass through the vertical cutting device and the horizontal cutting device in sequence to perform the cutting process. Through the cutting, the blank body is sequentially segmented into a plurality of segmented blanks with the same thickness as the required wallboard body.

[0013] S7, side notching, the divided and stacked split blanks are conveyed by a conveyor belt through a notching device, and the notching device is provided with a notching knife at the dividing surface of each stacked split blank. When the stacked split blanks pass the position of the notching knife under the conveyor belt, the excess material on the side of the split blanks is scraped off to form the required installation notches on the wall panel body.

[0014] S8, high temperature steam curing, the refined blank is turned over by the turning table, returned to the trolley, and transported by the trolley to the autoclave for autoclave treatment to form the required wall panel body.

[0015] S9, splicing and placing, arranging the main bodies of the formed wall panels in sequence.

[0016] S10, installing the keel, placing the keel body in the corresponding installation slot, and driving the expansion bolts into the keel body to achieve a fixed connection between the keel body and the wall panel body.

[0017] S11, keel leveling, rotating the limit nut on the expansion bolt, controlling the length of the expansion bolt extending into the wall panel body, so that each keel body to be installed subsequently is on the same vertical plane.

[0018] S12, installing the decorative panel, engaging the decorative panel with the corresponding snap-in parts on the keel body to achieve installation and fixation of a single decorative panel.

[0019] S13, repeating steps S10 to S12 to complete the installation of each decorative panel on the entire wall.

[0020] Furthermore, the blade head of the slotting knife in step S7 is a stepped arrangement blade head, so that when the stacked split blanks pass the position of the slotting knife under the conveyor belt, the slotting knife will gradually penetrate into the side of the split blanks, and finally scrape off the residual material of 5 cm long and 1.0~2.0 cm deep.

[0021] Furthermore, in step S1, the steel mesh sheet is installed at the center of the casting mold so that the steel mesh sheet is located on the middle layer of the finally formed wall panel body.

[0022] Furthermore, in step S10, the formed wall panel bodies are arranged in sequence along the horizontal direction, and the installation notches on the wall panel bodies are perpendicular to the ground. The installation notches between the left and right adjacent wall panel bodies are spliced ​​to form a joint groove that matches the keel assembly.

[0023] Furthermore, during the installation of the decorative panel in step S13, the clamping groove on one side of the decorative panel is preferentially engaged with the clamping portion on the corresponding keel body. After the fixing of one side of the decorative panel is completed, another keel body is installed in the adjacent joint groove. The clamping portion on the keel body is inserted into the clamping groove on the other side of the decorative panel during the installation process, thereby completing the installation and fixing of the entire decorative panel.

[0024] Furthermore, in step S10, the formed wallboard bodies are arranged in sequence along the vertical direction, and the joint seams of the wallboard bodies of two adjacent layers are staggered in the vertical direction. The installation notches between the two adjacent wallboard bodies are spliced ​​to form a joint groove that matches the keel assembly.

[0025] Furthermore, in step S13, a hanging piece that matches the clamping part of the keel body is preferentially installed on the back of the veneer. When the veneer is attached to the wallboard body, the hanging piece on the veneer extends into the keel body through the clearance slot. The veneer is moved in the length direction of the keel body so that the hanging piece on the veneer can be clamped with the clamping part of the keel body during the movement.

[0026] In a second aspect, a dry-hanging decorative panel with a hidden leveling keel comprises a wall assembly, a decorative panel and a keel body. The wall assembly comprises a plurality of wall panel bodies arranged in sequence, each of which has an installation slot on its corner edge. The keel assembly is installed in the installation slot, and a clamping portion is provided at the outer end. The decorative panel is clamped and matched with the clamping portion.

[0027] Furthermore, the keel body is in a "J" shape, and is divided into a mounting portion at the inner end and transition portions arranged on both sides of the mounting portion. The mounting portion is fixed in the mounting notch by bolts. A clearance space is formed between the transition portions on both sides, and the clamping portion is arranged at the outer end of the transition portion. The edges of both sides of the decorative panel are provided with clamping grooves that match the clamping portion. The clamping grooves on the decorative panel are clamped and matched with the clamping portion.

[0028] Furthermore, each of the wall panel bodies is arranged in sequence along the vertical direction, and the installation notches on the side are parallel to the horizontal plane. The keel body includes an inner installation portion and an upwardly bent clamping portion. A hanging piece that matches the clamping portion is fixed on the inner side of the decorative panel. The hanging piece is clamped and matched with the clamping portion.

[0029] Compared with the prior art, the present invention has the following advantages: 1. The present invention forms installation notches by scraping off excess material from the side of the initially solidified wallboard body during the processing of the wallboard body. The keel assembly can be embedded in the installation notches during wall assembly, so that the installation of the decorative panel does not occupy additional indoor space, and avoids the need to use a drill to open the notch during the installation process, which consumes a lot of manpower and material resources, and the smoke and dust generated during the construction cause harm to the health of the construction workers.

[0030] 2. The keel body of the present invention is installed by using expansion bolts to ensure the stability of the installation. At the same time, by setting a limit nut on the inner side of the expansion bolt, the length of the expansion bolt extending into the wall panel body is controlled by rotating the limit nut, so that the keel bodies in each keel assembly are on the same vertical plane, thereby ensuring the flatness of each part of the decorative panel installed on the keel body. BRIEF DESCRIPTION OF THE DRAWINGS

[0031] Figure 1 This is a schematic diagram of the overall structure of Example 1 of the present invention; Figure 2 It is a structural schematic diagram of the keel body and the leveling and fixing assembly in Example 1 of the present invention; Figure 3 This is a schematic diagram of the overall structure of Example 2 of the present invention; Figure 4 It is a schematic structural diagram of the keel body and the leveling fixing assembly in Example 2 of the present invention.

[0032] Figure numerals: 1. wall panel body; 2. decorative panel; 3. keel assembly; 4. installation notch; 5. slot; 6. keel body; 6-1. installation part; 6-2. transition part; 6-3. clamping part; 7. leveling and fixing assembly; 7-1. expansion bolt; 7-2. limit nut; 8. hanging part. DETAILED DESCRIPTION

[0033] In the description of the present invention, it is necessary to understand that the terms "one end", "the other end", "outside", "upper", "inside", "horizontal", "coaxial", "center", "end", "length", "outer end" and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present invention.

[0034] The present invention will be further described below in conjunction with the accompanying drawings.

[0035] Example 1

[0036] like Figure 1 and 2 As shown, a dry-hanging decorative panel with a hidden leveling keel includes a wall assembly, a decorative panel 2 and a keel assembly 3. The wall assembly includes a plurality of wall panel bodies 1 arranged in a horizontal direction. An installation slot 4 is provided on the corner edge of each wall panel body 1. The keel assembly 3 is installed in the installation slot 4, and a clamping portion 6-3 is provided on the outer end. A clamping slot 5 matching the clamping portion 6-3 is provided on both side edges of the decorative panel 2. The clamping slot 5 on the decorative panel 2 is clamped with the clamping portion 6-3, so that the decorative panel 2 can be fixed on the wall panel body 1 without occupying additional indoor space.

[0037] In some embodiments, the installation notches 4 between the two adjacent wall panel bodies 1 can be spliced ​​to form a joint groove that matches the keel assembly 3. The keel assembly 3 is arranged in the joint groove. The joint groove increases the installation space of the keel assembly 3, which facilitates the adaptive adjustment and clamping of the keel assembly 3.

[0038] Specific structure such as Figure 2 As shown, the keel assembly 3 includes a keel body 6 and a leveling and fixing assembly 7. The keel body 6 is in a "F"-shaped structure, and is divided into a mounting portion 6-1 at the inner end and transition portions 6-2 arranged on both sides of the mounting portion 6-1. The mounting portion 6-1 is fixed in the joint groove by the leveling and fixing assembly 7. A clearance space is formed between the transition portions 6-2 on both sides, and the clamping portion 6-3 is arranged at the outer end of the transition portion 6-2. During the installation process, the clamping portions 6-3 on the adjacent sides of two adjacent keel bodies 6 are inserted into the clamping grooves 5 on both sides of the correspondingly installed decorative panels 2, thereby realizing the installation and fixing of the decorative panels 2. When the decorative panels 2 need to be removed, the leveling and fixing assembly 7 on the mounting portion 6-1 is removed, and an outward force is applied to the decorative panels 2. The transition portions 6-2 on the keel bodies 6 on both sides are deformed toward the side of the clearance space, so that the clamping portion 6-3 can smoothly detach from the clamping grooves 5 on the decorative panels 2, thereby realizing the disassembly and separation of the decorative panels 2.

[0039] Furthermore, a filler strip in a ladder-shaped structure is provided in the clearance space. After the installation and connection of the leveling and fixing assembly 7 is completed, the filler strip is embedded in the clearance space, thereby achieving the beauty of the connection between two adjacent wall panel bodies 1.

[0040] like Figure 2 As shown, the leveling fixing assembly 7 includes a fixing part and a limiting nut 7-2. Among them, the fixing part is an expansion bolt 7-1. A mounting through hole matching the expansion bolt 7-1 is provided on the keel body 6. The expansion bolt 7-1 passes through the mounting through hole and is fixed to the wall panel body 1. The limiting nut 7-2 is threadedly connected to the inner side of the expansion bolt 7-1, and the length of the expansion bolt 7-1 extending into the wall panel body 1 can be controlled by rotating and adjusting the limiting nut 7-2, so that the keel bodies 6 in each keel assembly 3 are on the same vertical plane, thereby ensuring the flatness of each part of the decorative panel 2 installed on the keel body 6.

[0041] Furthermore, a connection bracket is pre-buried at the installation slot 4 of one of the two adjacent wall panel bodies 1. The connection bracket adopts a square pipe fitting. During the installation process, the inner end of the expansion bolt 7-1 is fixedly connected to the square pipe fitting, which effectively avoids the problem of cracking of the wall surface during the installation process of drilling holes on the wall panel body 1.

[0042] In some embodiments, mortar cement or foam glue is filled between two adjacent wall panel bodies 1 to achieve a fixed connection between the wall panel bodies 1 .

[0043] The specific preparation and installation process of the dry-hanging decorative panel 2 in this embodiment has the following specific steps: S1, skeleton construction, according to the size of each partition board to be constructed, manually tie the steel mesh sheets of corresponding size, and install the steel mesh sheets in the center of the casting mold, so that the steel mesh sheets are located on the middle layer of the final wall panel body 1, thereby ensuring the strength of the wall panel body 1. Multiple plug rods are detachably fixed on the corresponding steel mesh sheets through clamps.

[0044] S2, pouring, pouring the concrete slurry automatically mixed by the autoclaved aerated concrete raw materials into the constructed mold.

[0045] S3, insert the skeleton, insert multiple steel mesh sheets into the mold after pouring through the inserter, and transport them together with the mold to the curing room for gasification and initial solidification to form a blank. The temperature in the curing room is 40~45℃, and the static time is 180~240min. At this time, the blank is in a state of initial solidification.

[0046] S4, pull out the plug rod inserted into the blank body.

[0047] S5, demoulding, the blank body after resting is transferred to the cutting area. The flip demoulding mechanism flips the blank body 90 degrees and places it on the trolley. After it is placed stably, the flip demoulding mechanism grabs the mold of the blank body except the bottom surface and disassembles and separates it.

[0048] S6, segmentation, the blank body is driven by the trolley to pass through the vertical cutting device and the horizontal cutting device in turn, and performs vertical and horizontal cutting processes. Through the vertical cutting process, the excess waste on both sides of the blank body in the length direction is cut off. Through the horizontal cutting process, the blank body will be cut into a plurality of segmented blanks with the same thickness as the required wall panel body 1 in turn.

[0049] S7, side slotting, the split and stacked split blanks are further transported and passed through the slotting device, where slotting knives are arranged at the split surfaces of each stacked split blank. The slotting knives have step-by-step arrangement of knife heads, so that when the stacked split blanks pass through the slotting knife positions under the conveyor belt, the residual material of 5 cm long and 1.0-2.0 cm deep on the side of the split blanks will be gradually scraped off to form the required installation slots 4 on the wall panel body 1.

[0050] S8, high temperature steam curing, the finely trimmed blank is turned over by the turning table, returned to the trolley, and transported to the autoclave for autoclave treatment. During the autoclave process, the temperature in the autoclave is 150-200°C and the pressure is 8-13 standard atmospheres. The entire autoclave takes 8-12 hours to form the required wallboard body 1.

[0051] S9, splicing and placing, arranging the formed wall panel bodies 1 in sequence along the horizontal direction, and the installation notches 4 on the wall panel bodies 1 are perpendicular to the ground. The installation notches 4 between the two adjacent wall panel bodies 1 on the left and right are spliced ​​to form a joint groove that matches the keel assembly 3. At the same time, during the arrangement process, mortar cement or foam glue is filled between the two adjacent wall panel bodies 1.

[0052] S10, keel installation, install expansion bolts 7-1 into the installation through holes on the keel body 6, and install limit nuts 7-2 at the outer ends of the expansion bolts 7-1. Set the keel body 6 in the corresponding joint groove, and connect the expansion bolts 7-1 to the square steel pipes pre-buried in the wall panel body 1, so as to achieve the installation and fixation of the keel body 6.

[0053] S11, keel leveling, turn the limit nut 7-2 on the expansion bolt 7-1, control the length of the expansion bolt 7-1 extending into the wall panel body 1, so that each keel body 6 installed subsequently is on the same vertical plane, thereby ensuring the flatness of each part of the decorative panel 2 installed on the keel body 6.

[0054] S12, the veneer 2 is installed, and the slot 5 on one side edge of the veneer 2 is engaged with the corresponding engaging portion 6-3 on the keel body 6. After the fixing of one side of the veneer 2 is completed, another keel body 6 is installed in the adjacent joint groove. The engaging portion 6-3 on the keel body 6 is inserted into the slot 5 on the other side edge of the veneer 2 during the installation process, thereby completing the installation and fixing of the entire veneer 2.

[0055] S13, repeating steps S11 to S13 to complete the installation of each decorative panel 2 on the entire wall surface.

[0056] Example 2

[0057] like Figure 3 and 4 As shown, a dry-hanging decorative panel with hidden leveling keel includes a wall assembly, a decorative panel 2 and a keel assembly 3. Among them, the wall assembly includes a plurality of wall panel bodies 1 arranged in sequence along the vertical direction. In the vertical direction, the joint seams of the wall panel bodies 1 of two adjacent layers are staggered, which effectively avoids the reduction of the firmness of the connection between each wall panel body 1 due to the excessive length of the joint seam. Installation notches 4 are provided at the edges of the top and bottom of the wall panel body 1. The installation notches 4 of the upper and lower adjacent wall panel bodies 1 are spliced ​​to form a joint groove that matches the keel assembly 3. The keel assembly 3 is installed in the joint groove, and a clamping portion 6-3 is provided at the outer end. A hanging member 8 that matches the clamping portion 6-3 is fixed on the inner side of the decorative panel 2. Through the clamping cooperation of the hanging member 8 and the clamping portion 6-3, the decorative panel 2 and the wall panel body 1 are fixedly connected.

[0058] Specific structure such as Figure 4 As shown, the keel assembly 3 includes a keel body 6 and a leveling and fixing assembly 7. The keel body 6 includes an inner mounting portion 6-1 and an upwardly bent clamping portion 6-3. During installation, the keel body 6 is embedded in the joint groove. The mounting portion 6-1 in the keel body 6 is fixed to the wall panel body 1 through the leveling and fixing assembly 7.

[0059] After the installation of the keel body 6 is completed, when the decorative panel 2 is attached to one side of the wall panel body 1, the decorative panel 2 to be installed is lifted upward so that the hanging piece 8 on the decorative panel 2 can smoothly enter the joint groove. When the hanging piece 8 completely enters the joint groove, by moving the decorative panel 2 downward, the hanging piece 8 can be engaged with the clamping part 6-3 of the keel body 6 during the movement of the decorative panel 2, thereby achieving the fixing of the decorative panel 2 on the wall panel body 1.

[0060] like Figure 4As shown, the leveling fixing assembly 7 includes a fixing part and a limiting nut 7-2. Among them, the fixing part is an expansion bolt 7-1. A mounting through hole matching the expansion bolt 7-1 is provided on the keel body 6. The expansion bolt 7-1 passes through the mounting through hole and is fixed to the wall panel body 1. The limiting nut 7-2 is threadedly connected to the inner side of the expansion bolt 7-1, and the length of the expansion bolt 7-1 extending into the wall panel body 1 can be controlled by rotating and adjusting the limiting nut 7-2, so that the keel bodies 6 in each keel assembly 3 are on the same vertical plane, thereby ensuring the flatness of each part of the decorative panel 2 installed on the keel body 6.

[0061] Furthermore, a connection bracket is pre-buried at the installation slot 4 of one of the two adjacent wall panel bodies 1. The connection bracket adopts a square pipe fitting. During the installation process, the inner end of the expansion bolt 7-1 is fixedly connected to the square pipe fitting, which effectively avoids the problem of cracking of the wall surface during the installation process of drilling holes on the wall panel body 1.

[0062] The specific preparation and installation process of the dry-hanging decorative panel 2 in this embodiment has the following specific steps: S1, skeleton construction, according to the size of each partition board to be constructed, manually tie the steel mesh sheets of corresponding size, and install the steel mesh sheets in the center of the casting mold, so that the steel mesh sheets are on the middle layer of the final wall panel body 1, thereby ensuring the strength of the wall panel body 1. Multiple plug rods are detachably fixed on the corresponding steel mesh sheets through clamps.

[0063] S2, pouring, pouring the concrete slurry automatically mixed by the autoclaved aerated concrete raw materials into the constructed mold.

[0064] S3, insert the skeleton, insert multiple steel mesh sheets into the mold after pouring through the inserter, and transport them together with the mold to the curing room for gasification and initial solidification to form a blank. The temperature in the curing room is 40~45℃, and the static time is 180~240min. At this time, the blank is in a state of initial solidification.

[0065] S4, pull out the plug rod inserted into the blank body.

[0066] S5, demoulding, the blank body after resting is transferred to the cutting area. The flip demoulding mechanism flips the blank body 90 degrees and places it on the trolley. After it is placed stably, the flip demoulding mechanism grabs the mold of the blank body except the bottom surface and disassembles and separates it.

[0067] S6, segmentation, the blank body is driven by the trolley to pass through the vertical cutting device and the horizontal cutting device in turn, and performs vertical and horizontal cutting processes. Through the vertical cutting process, the excess waste on both sides of the blank body in the length direction is cut off. Through the horizontal cutting process, the blank body will be sequentially segmented into a plurality of segmented blanks with the same thickness as the required wall panel body 1.

[0068] S7, side notching, the split and stacked split blanks are conveyed by the conveyor belt through the notching device, and the notching device is provided with a notching knife at the split surface of each stacked split blank. The knife head of the notching knife is a step-by-step arrangement knife head, so that when the stacked split blanks pass the position of the notching knife under the conveyor belt, the residual material of 5 cm deep on the side of the split blanks will be gradually scraped off to form the required installation notch 4 on the wall panel body 1.

[0069] S8, high temperature steam curing, the finely trimmed blank is turned over by the turning table, returned to the trolley, and transported to the autoclave for autoclave treatment. During the autoclave process, the temperature in the autoclave is 150-200°C and the pressure is 8-13 standard atmospheres. The entire autoclave takes 8-12 hours to form the required wallboard body 1.

[0070] S9, splicing and placing, arranging the formed wall panel bodies 1 in sequence along the vertical direction, and the splicing seams of the wall panel bodies 1 of two adjacent layers are staggered in the vertical direction. The installation notches 4 between the two adjacent wall panel bodies 1 are spliced ​​to form a joint groove that matches the keel assembly 3. At the same time, during the arrangement process, mortar cement or foam glue is filled between each wall panel body 1.

[0071] S10, keel installation, install expansion bolts 7-1 into the installation through holes on the keel body 6, and install limit nuts 7-2 at the outer ends of the expansion bolts 7-1. Set the keel body 6 in the corresponding joint groove, and connect the expansion bolts 7-1 to the square steel pipes pre-buried in the wall panel body 1, so as to achieve the installation and fixation of the keel body 6.

[0072] S11, keel leveling, turn the limit nut 7-2 on the expansion bolt 7-1, control the length of the expansion bolt 7-1 extending into the wall panel body 1, ensure that the subsequently installed keel bodies 6 are on the same vertical plane, and further ensure the flatness of each part of the decorative panel 2 installed on the keel body 6.

[0073] S12, the veneer panel 2 is installed. When the veneer panel 2 is attached to one side of the wall panel body 1, the veneer panel 2 to be installed is lifted upward so that the hanging piece 8 on the veneer panel 2 can smoothly enter the joint groove. When the hanging piece 8 completely enters the joint groove, the veneer panel 2 is moved downward, and the hanging piece 8 can be engaged with the clamping part 6-3 of the keel body 6 during the movement of the veneer panel 2, thereby fixing the veneer panel 2 on the wall panel body 1.

[0074] S13, repeating steps S10 to S12 to complete the installation of each decorative panel 2 on the entire wall surface.

[0075] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit it. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or replace some or all of the technical features therein with equivalents. However, these modifications or replacements do not cause the essence of the corresponding technical solutions to deviate from the scope of the technical solutions of the embodiments of the present invention.

Claims

1. A preparation and installation process of a dry-hanging decorative panel with a hidden leveling keel, characterized in that: The specific steps are as follows: S1, skeleton construction, according to the size of each partition board to be constructed, the steel mesh sheets of corresponding sizes are manually tied, and multiple insertion rods are detachably fixed on the corresponding steel mesh sheets through clamps; S2, pouring, pouring the concrete slurry automatically mixed by the autoclaved aerated concrete raw materials into the constructed mold; S3, inserting the skeleton, inserting a plurality of steel mesh sheets into the mold after casting through an inserting machine, and transporting them together with the mold to a curing room for gasification and initial solidification to form a blank body; S4, pulling out the plugging rod inserted into the blank body; S5, demoulding, transferring the blank body after resting to the cutting area; the flip demoulding mechanism flips the blank body and places it on the trolley; after it is placed stably, the flip demoulding mechanism grabs the mold of the blank body except the bottom surface and disassembles and separates it; S6, segmentation, the blank body is driven by the trolley to pass through the vertical cutting device and the horizontal cutting device in sequence to perform cutting processing; through cutting, the blank body is sequentially segmented into a plurality of segmented blanks having the same thickness as the required wall panel body (1); S7, side notching, the divided and stacked split blanks are conveyed by a conveyor belt through a notching device, the notching device being provided with a notching knife at the dividing surface of each stacked split blank; when the stacked split blanks are conveyed by the conveyor belt and pass through the position where the notching knife is located, the excess material on the side of the split blanks is scraped off to form the required installation notches (4) on the wall panel body (1); S8, high temperature steam curing, the refined green body is turned over by the turning table, returned to the trolley, and transported by the trolley to the autoclave for autoclave treatment to form the required wallboard body (1); S9, splicing and placing, arranging the formed wall panel bodies (1) in sequence; S10, keel installation, placing the keel body (6) in the corresponding installation slot (4), and driving the expansion bolt (7-1) into place to achieve a fixed connection between the keel body (6) and the wall panel body (1); S11, keel leveling, rotating the limit nut (7-2) on the expansion bolt (7-1), controlling the length of the expansion bolt (7-1) extending into the wall panel body (1), so that each keel body (6) to be installed subsequently is on the same vertical plane; S12, installing the decorative panel (2), engaging the decorative panel (2) with the corresponding engaging portion (6-3) on the keel body (6), so as to achieve installation and fixation of a single decorative panel (2); S13, repeating steps S10 to S12 to complete the installation of each decorative panel (2) on the entire wall surface.

2. The preparation and installation process of a dry-hanging decorative panel with hidden leveling keel according to claim 1 is characterized in that: The blade head of the slotting knife in step S7 is a stepped blade head, so that when the stacked split blanks pass the position of the slotting knife under the conveyor belt, the slotting knife will gradually penetrate into the side of the split blanks, and finally scrape off 5 cm long and 1.0~2.0 cm deep residual material.

3. The preparation and installation process of a dry-hanging decorative panel with hidden leveling keel according to claim 1 is characterized in that: In step S1, the steel mesh sheet is installed at the center of the casting mold, so that the steel mesh sheet is located on the middle layer of the finally formed wall panel body (1).

4. The preparation and installation process of a dry-hanging decorative panel with hidden leveling keel according to claim 1, characterized in that: In step S10, the formed wall panel bodies (1) are arranged in sequence along the horizontal direction, and the installation notches (4) on the wall panel bodies (1) are perpendicular to the ground; the installation notches (4) between the two adjacent wall panel bodies (1) on the left and right are spliced ​​to form a joint groove that matches the keel assembly (3).

5. The preparation and installation process of the dry-hanging decorative panel with hidden leveling keel according to claim 4 is characterized in that: During the installation of the decorative panel (2) in step S13, the slot (5) on one side edge of the decorative panel (2) is preferentially engaged with the engaging portion (6-3) on the corresponding keel body (6); after the fixing of one side of the decorative panel (2) is completed, another keel body (6) is installed in the adjacent joint groove; during the installation process, the engaging portion (6-3) on the keel body (6) is inserted into the slot (5) on the other side edge of the decorative panel (2), thereby completing the installation and fixing of the entire decorative panel (2).

6. The preparation and installation process of the dry-hanging decorative panel with hidden leveling keel according to claim 1 is characterized in that: In step S10, the formed wall panel bodies (1) are arranged in sequence along the vertical direction, and the joint seams of the wall panel bodies (1) of two adjacent layers are staggered in the vertical direction; the installation notches (4) between the two upper and lower adjacent wall panel bodies (1) are spliced ​​to form a joint groove that matches the keel assembly (3).

7. The preparation and installation process of the dry-hanging decorative panel with hidden leveling keel according to claim 6, characterized in that: In the step S13, a hanging piece (8) that matches the snap-on portion (6-3) of the keel body (6) is preferentially installed on the back of the decorative panel (2); when the decorative panel (2) is attached to one side of the wall panel body (1), the hanging piece (8) on the decorative panel (2) extends into the keel body (6) through the clearance groove; and the decorative panel (2) is moved in the length direction of the keel body (6) so that the hanging piece (8) on the decorative panel (2) can snap-on with the snap-on portion (6-3) of the keel body (6) during the movement.

8. A dry-hanging decorative panel with hidden leveling keel, characterized in that: The preparation and installation process as claimed in claim 1 comprises a wall assembly, a decorative panel (2) and a keel body (6); the wall assembly comprises a plurality of wall panel bodies (1) arranged in sequence, each of which has an installation slot (4) on its corner edge; the keel assembly (3) is installed in the installation slot (4), and a clamping portion (6-3) is provided at the outer end; the decorative panel (2) is clamped and matched with the clamping portion (6-3).

9. The dry-hanging decorative panel with hidden leveling keel according to claim 8, characterized in that: The keel body (6) is in a "J"-shaped structure, and is divided into a mounting portion (6-1) at the inner end and transition portions (6-2) arranged on both sides of the mounting portion (6-1); the mounting portion (6-1) is fixed in the mounting slot (4) by bolts; a clearance space is formed between the transition portions (6-2) on both sides, and the clamping portion (6-3) is arranged at the outer end of the transition portion (6-2); the edges of both sides of the veneer panel (2) are provided with clamping grooves (5) that match the clamping portion (6-3); the clamping grooves (5) on the veneer panel (2) are clamped and matched with the clamping portion (6-3).

10. The dry-hanging decorative panel with hidden leveling keel according to claim 8, characterized in that: The wall panel bodies (1) are arranged in sequence along the vertical direction, and the side mounting notches (4) are parallel to the horizontal plane; the keel body (6) comprises an inner mounting portion (6-1) and an upwardly bent clamping portion (6-3); a hanging member (8) matching the clamping portion (6-3) is fixed on the inner side surface of the decorative panel (2); and the hanging member (8) is clamped and matched with the clamping portion (6-3).