Nuclear power station overhaul work order preparation management method
By automatically preparing and implementing the overhaul work order preparation plan, priority is given to overhaul work orders that need to be carefully prepared, and automatic data statistics and reminders are implemented, which solves the problem of difficult and inefficient quality of overhaul work order preparation in the existing technology, and improves the overall efficiency of overhaul work order preparation work.
Patent Information
- Application Number
- CN202411239435.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-05
- Publication Date
- 2025-06-06
AI Technical Summary
In the preparation management of overhaul work orders for existing nuclear power plants, overhaul work orders that need to be carefully prepared are often completed in the later stage of overhaul, which cannot guarantee the quality of preparation, and frequent statistics on the completion rate of preparation leads to inefficiency.
By automatically preparing a work order preparation plan for overhaul work orders, priority will be given to overhaul work orders that need to be carefully prepared, and automatic data statistics and reminders will be realized to ensure that each responsible team completes the preparation work on time.
It ensures the quality of preparation of overhaul work orders that need to be prepared carefully, avoids problems during the preparation process that will affect the entire overhaul preparation work, and improves the efficiency of overhaul work order preparation.
Smart Images

Figure CN120106333A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of nuclear power plant overhaul preparation management, and in particular to a nuclear power plant overhaul work order preparation management method, device, computer equipment and computer-readable storage medium. Background Art
[0002] Preparation of overhaul work orders is one of the core elements of nuclear power plant overhaul preparation. Material procurement, manpower allocation, planning and all on-site work implementation of the overhaul rely on the overhaul work order. Therefore, the preparation progress and quality of the overhaul work order are crucial to the overall overhaul preparation control.
[0003] According to the requirements of the overhaul preparation management procedure, the responsible team of the overhaul work order needs to freely select a certain proportion of overhaul work orders to complete the preparation work before the overhaul. This operation mode has the following problems:
[0004] 1. Because only a certain percentage of the preparation work for overhaul work orders is required to be completed, the responsible team is very likely to tend to complete the overhaul work orders that are easier to prepare first, and put off some overhaul work orders that require careful preparation for completion in the later stages. However, there is not enough time to ensure the preparation quality of these overhaul work orders in the later stages of the overhaul. If problems arise during the preparation of these overhaul work orders, it will have a greater impact on the entire overhaul preparation work.
[0005] 2. Overhaul work order preparation managers need to frequently count the completion rate of overhaul work order preparation and urge each responsible team to complete the overhaul work order preparation work. The overhaul work order preparation efficiency is very low. Summary of the invention
[0006] One of the purposes of the present invention is to provide a method, device, computer equipment and storage medium for preparation management of overhaul work orders for nuclear power plants, so as to solve the problem that the preparation work of overhaul work orders that need to be carefully prepared must be completed later, and the preparation quality of overhaul work orders that need to be carefully prepared cannot be guaranteed. If problems arise during the preparation process of overhaul work orders that need to be carefully prepared, the entire overhaul preparation work will be impacted. The present invention realizes automatic preparation of overhaul work order preparation plans for nuclear power plants, gives priority to the preparation work of overhaul work orders that need to be carefully prepared, guarantees the preparation quality of overhaul work orders that need to be carefully prepared, and avoids the impact of problems during the preparation process of overhaul work orders that need to be carefully prepared on the entire overhaul preparation work.
[0007] The second purpose of the present invention is to provide a method, device, computer equipment and storage medium for nuclear power plant overhaul work order preparation management, so as to solve the problem that the overhaul work order preparation completion rate needs to be frequently counted in the existing nuclear power plant overhaul work order preparation management work, and each responsible team is urged to complete the overhaul work order preparation work, and the overhaul work order preparation efficiency is very low. The method realizes automatic statistics of the execution data of the nuclear power plant overhaul work order preparation plan, automatically reminds each responsible team to complete the overhaul work order preparation work, and improves the overhaul work order preparation efficiency.
[0008] In order to solve the above problems, the present invention provides a method for preparing and managing a nuclear power plant overhaul work order, comprising the following steps:
[0009] S101. Obtain all overhaul work orders;
[0010] S102, grouping and sorting all overhaul work orders;
[0011] S103, setting up a preparation plan for all overhaul work orders;
[0012] S104. Promote the execution of preparation plans for all overhaul work orders.
[0013] As one of the achievable methods, the overhaul work order includes the following field information: work order task number, work order overhaul number, work order creation time, equipment level, maintenance level, scheduling group, responsible team, material reservation status and work order task status;
[0014] Among them, the "Material Reservation Status" field information of the overhaul work order includes "Material Obstacles" and "No Material Obstacles";
[0015] The "Schedule Group" field information of the overhaul work order includes "Mainline Plan" and "Non-Mainline Plan";
[0016] The "Equipment Level" field information of the overhaul work order includes "S", "A", "B" and "C";
[0017] The "Maintenance Level" field information of the overhaul work order includes "M1", "M2", "M3" and "Others";
[0018] The "Work Order Task Number" field information of the overhaul work order contains numbers generated in ascending order according to the creation time of the overhaul work order;
[0019] The "Work Order Task Status" field information of the overhaul work order includes "Preparation Not Started", "Preparation Started" and "Preparation Completed".
[0020] As one of the achievable methods, S102, grouping and sorting all overhaul work orders includes the following steps:
[0021] S1021. All overhaul work orders are divided into all overhaul work orders generated outside 12 months before the start of the overhaul and all overhaul work orders generated within 12 months before the start of the overhaul according to the "work order creation time" field information;
[0022] S1022. Group and sort all overhaul work orders generated outside 12 months before the start of the overhaul, and sort all overhaul work orders generated within 12 months before the start of the overhaul.
[0023] As one of the feasible methods, in S1021, the "Work Order Creation Time" field information is all overhaul work orders generated outside 12 months before the start of the overhaul, and the "Work Order Creation Time" field information is all overhaul work orders generated within 12 months before the start of the overhaul, and the "Work Order Creation Time" field information is all overhaul work orders generated within 12 months before the start of the overhaul.
[0024] As one of the achievable methods, S1022, grouping and sorting all overhaul work orders generated outside 12 months before the start of the overhaul, including the following steps:
[0025] S10221. Sort all overhaul work orders generated outside the 12 months before the start of the overhaul according to the following steps:
[0026] S102211. Sort all overhaul work orders generated outside the 12 months before the start of the overhaul according to the "Scheduling Group" field information. The overhaul work orders with the "Scheduling Group" field information of "Main Line Plan" are sorted first, and the overhaul work orders with the "Scheduling Group" field information of "Non-Main Line Plan" are sorted last;
[0027] S102212. Sort all overhaul work orders with the same “Scheduling Group” field information in S102211 according to the “Equipment Level” field information. The overhaul work order with “S” in the “Equipment Level” field information is ranked first, the overhaul work order with “A” in the “Equipment Level” field information is ranked second, the overhaul work order with “B” in the “Equipment Level” field information is ranked third, and the overhaul work order with “C” in the “Equipment Level” field information is ranked fourth;
[0028] S102213. Sort all overhaul work orders with the same “scheduling group” and “equipment level” field information in S102212 according to the “maintenance level” field information, with the overhaul work order with the “maintenance level” field information of “M1” being ranked first, the overhaul work order with the “maintenance level” field information of “M2” being ranked second, the overhaul work order with the “maintenance level” field information of “M3” being ranked third, and the overhaul work order with the “maintenance level” field information of “other” being ranked fourth;
[0029] S102214, sorting all overhaul work orders having the same “scheduling group”, “equipment level” and “maintenance level” field information in S102213 in ascending order according to the numbers in the “work order task number” field information;
[0030] S10222. For all the overhaul work orders sorted by S10221, they are divided into overhaul work orders with material obstacles and overhaul work orders without material obstacles according to the information in the "Material Reservation Status" field. Overhaul work orders with material obstacles are overhaul work orders with the "Material Reservation Status" field information as "with material obstacles", and overhaul work orders without material reservation obstacles are overhaul work orders with the "Material Reservation Status" field information as "without material obstacles".
[0031] As one of the achievable methods, S1022, sorting all overhaul work orders generated within 12 months before the start of the overhaul, includes the following steps:
[0032] Sort all overhaul work orders generated within 12 months before the start of the overhaul in ascending order according to the time in the "Work Order Creation Time" field information;
[0033] Sort all overhaul work orders with the same "Work Order Creation Time" field information in the above steps in ascending order according to the numbers in the "Work Order Task Number" field information.
[0034] As one of the achievable methods, S103, setting a preparation plan for all overhaul work orders, including setting a planned completion preparation date for all overhaul work orders;
[0035] Set the planned completion date for all overhaul work orders, including setting the planned completion date for all overhaul work orders generated outside 12 months before the start of the overhaul and without material obstacles, setting the planned completion date for all overhaul work orders generated outside 12 months before the start of the overhaul and with material obstacles, and setting the planned completion date for all overhaul work orders generated within 12 months before the start of the overhaul.
[0036] As one of the feasible ways, setting the planned completion date for all overhaul work orders generated outside 12 months before the start of the overhaul and without material obstacles includes the following steps:
[0037] During the period from 12 months before the start of the overhaul to 6 months before the start of the overhaul, all overhaul work orders generated outside the 12 months before the start of the overhaul and without material obstacles are sorted, and the "Work Order Task Status" field information of one overhaul work order data is planned to be advanced to "Completion Preparation" every Friday.
[0038] As one of the feasible ways, setting the planned completion date for all overhaul work orders with material obstacles generated outside 12 months before the start of the overhaul includes the following steps:
[0039] During the period from 5 months to 2 months before the start of the overhaul, all overhaul work orders with material obstacles generated outside the 12 months before the start of the overhaul will be sorted, and it is planned that the "Work Order Task Status" field information of one overhaul work order data will be advanced to "Completion Preparation" every Friday.
[0040] As one possible approach, set a planned completion date for all overhaul work orders generated within 12 months before the start of the overhaul, including the following steps:
[0041] Within 60% of the time between the creation date of the first overhaul work order generated within 12 months before the start of the overhaul and the start date of the overhaul, all overhaul work orders generated within 12 months before the start of the overhaul are sorted, and the "Work Order Task Status" field information of one overhaul work order data is planned to be advanced to "Completion Preparation" every Friday;
[0042] 60% of the time between the creation date of the first overhaul work order generated within 12 months before the start of the overhaul and the start date of the overhaul that is less than five days will be calculated as five days.
[0043] As one of the achievable methods, S104, promoting the execution of the preparation plan of all overhaul work orders, includes the following steps:
[0044] According to the information in the "Responsible Team" field, the execution data of the overhaul work order preparation plan of each responsible team is classified and displayed;
[0045] Send the overhaul work order preparation plan execution data of each responsible team via email.
[0046] As one of the achievable methods, the overhaul work order preparation plan execution data includes field information: responsible team, planned completion preparation time, actual completion preparation time, preparation plan execution status and remarks;
[0047] Statistics on the execution data of the overhaul work order preparation plan include the following steps:
[0048] Get the "Work Order Task Status" field information of the overhaul work order and advance it to the planned time of "Completion Preparation", and get the "Planned Completion Preparation Time" field information of the overhaul work order;
[0049] Get the actual time when the "Work Order Task Status" field information of the overhaul work order is advanced to "Completion Preparation", and get the "Actual Completion Preparation Time" field information of the overhaul work order;
[0050] The "Preparation Plan Execution Status" field information of the overhaul work order is generated according to the "Planned Preparation Completion Time" and "Actual Preparation Completion Time" field information of the overhaul work order; the "Preparation Plan Execution Status" field information of the overhaul work order includes "Preparation completed as planned" and "Preparation not completed as planned"; if the time in the "Actual Preparation Completion Time" field information of the overhaul work order is later than the time in the "Planned Preparation Completion Time" field information, the "Preparation Plan Execution Status" field information of the overhaul work order is "Preparation not completed as planned", otherwise, the "Preparation Plan Execution Status" field information of the overhaul work order is "Preparation completed as planned";
[0051] The "Remarks" field information of the overhaul work order whose "Preparation Plan Execution" field information is "Preparation not completed as planned" is obtained; the "Remarks" field information of the overhaul work order includes the reason why the preparation was not completed as planned.
[0052] In order to solve the above problems, the present invention also provides a nuclear power plant overhaul work order preparation management device, comprising:
[0053] Acquisition module, used to obtain all overhaul work orders;
[0054] The first calculation module is used to group and sort all overhaul work orders;
[0055] The second calculation module is used to set the preparation plan for all overhaul work orders;
[0056] The third calculation module is used to promote the execution of the preparation plan of all overhaul work orders.
[0057] In order to solve the above technical problems, the present invention provides a computer device, including a memory and a processor, wherein the memory stores computer-readable instructions, and when the processor executes the computer-readable instructions, the steps of the above-mentioned nuclear power plant overhaul work order preparation management method are implemented.
[0058] In order to solve the above technical problems, the present invention provides a computer-readable storage medium, on which computer-readable instructions are stored. When the computer-readable instructions are executed, the steps of the above-mentioned nuclear power plant overhaul work order preparation management method are implemented.
[0059] Beneficial technical effects of the present invention:
[0060] The nuclear power plant overhaul work order preparation management method, device, computer equipment and storage medium of the present invention realize the automatic preparation of the nuclear power plant overhaul work order preparation plan, give priority to the overhaul work orders that need to be carefully prepared for preparation work, ensure the preparation quality of the overhaul work orders that need to be carefully prepared, and avoid the impact of problems in the preparation process of the overhaul work orders that need to be carefully prepared on the entire overhaul preparation work; realize the statistics of the execution data of the nuclear power plant overhaul work order preparation plan, automatically remind each responsible team to complete the overhaul work order preparation work, and improve the overhaul work order preparation efficiency. BRIEF DESCRIPTION OF THE DRAWINGS
[0061] Figure 1 A flowchart of an embodiment of a method for managing a nuclear power plant overhaul work order preparation according to the present invention;
[0062] Figure 2 A schematic structural view of an embodiment of a nuclear power plant overhaul work order preparation management device of the present invention.
[0063] Figure 3 The figure is a schematic structural view of a computer device according to an embodiment of the present invention. DETAILED DESCRIPTION
[0064] Unless otherwise defined, all technical and scientific terms used herein have the same meaning as commonly understood by technicians in the technical field to which this application belongs; the terms used in the specification of the application are only for the purpose of describing specific embodiments and are not intended to limit this application; the terms "including" and "having" and any variations thereof in the specification and claims of this application and the above-mentioned figure descriptions are intended to cover non-exclusive inclusions.
[0065] Reference to "embodiments" herein means that a particular feature, structure, or characteristic described in conjunction with the embodiments may be included in at least one embodiment of the present application. The appearance of the phrase in various locations in the specification does not necessarily refer to the same embodiment, nor is it an independent or alternative embodiment that is mutually exclusive with other embodiments. It is explicitly and implicitly understood by those skilled in the art that the embodiments described herein may be combined with other embodiments.
[0066] The technical solution of the present invention is clearly and completely described below in conjunction with the accompanying drawings and specific embodiments.
[0067] refer to Figure 1 , shows a flow chart of an embodiment of a method for preparing and managing a nuclear power plant overhaul work order, the method for preparing and managing a nuclear power plant overhaul work order comprising the following steps:
[0068] S101. Obtain all overhaul work orders;
[0069] S102, grouping and sorting all overhaul work orders;
[0070] S103, setting up a preparation plan for all overhaul work orders;
[0071] S104. Promote the execution of preparation plans for all overhaul work orders.
[0072] In this embodiment, as one of the achievable methods, the overhaul work order includes the following field information: work order task number, work order overhaul number, work order creation time, equipment level, maintenance level, scheduling group, responsible team, material reservation status and work order task status;
[0073] Among them, the "Material Reservation Status" field information of the overhaul work order includes "Material Obstacles" and "No Material Obstacles";
[0074] The "Schedule Group" field information of the overhaul work order includes "Mainline Plan" and "Non-Mainline Plan";
[0075] The "Equipment Level" field information of the overhaul work order includes "S", "A", "B" and "C";
[0076] The "Maintenance Level" field information of the overhaul work order includes "M1", "M2", "M3" and "Others";
[0077] The "Work Order Task Number" field information of the overhaul work order contains numbers generated in ascending order according to the creation time of the overhaul work order;
[0078] The "Work Order Task Status" field information of the overhaul work order includes "Preparation Not Started", "Preparation Started" and "Preparation Completed".
[0079] In this embodiment, as one of the achievable methods, S102, grouping and sorting all overhaul work orders, includes the following steps:
[0080] S1021. All overhaul work orders are divided into all overhaul work orders generated outside 12 months before the start of the overhaul and all overhaul work orders generated within 12 months before the start of the overhaul according to the "work order creation time" field information;
[0081] S1022. Group and sort all overhaul work orders generated outside 12 months before the start of the overhaul, and sort all overhaul work orders generated within 12 months before the start of the overhaul.
[0082] In this embodiment, as one of the achievable methods, in S1021, the "Work Order Creation Time" field information is all overhaul work orders generated outside 12 months before the start of the overhaul, and the "Work Order Creation Time" field information is all overhaul work orders generated within 12 months before the start of the overhaul, and the "Work Order Creation Time" field information is all overhaul work orders generated within 12 months before the start of the overhaul.
[0083] In this embodiment, as one of the achievable methods, S1022, grouping and sorting all overhaul work orders generated outside 12 months before the start of the overhaul, includes the following steps:
[0084] S10221. Sort all overhaul work orders generated outside the 12 months before the start of the overhaul according to the following steps:
[0085] S102211. Sort all overhaul work orders generated outside the 12 months before the start of the overhaul according to the "Scheduling Group" field information. The overhaul work orders with the "Scheduling Group" field information of "Main Line Plan" are sorted first, and the overhaul work orders with the "Scheduling Group" field information of "Non-Main Line Plan" are sorted last;
[0086] S102212. Sort all overhaul work orders with the same “Scheduling Group” field information in S102211 according to the “Equipment Level” field information. The overhaul work order with “S” in the “Equipment Level” field information is ranked first, the overhaul work order with “A” in the “Equipment Level” field information is ranked second, the overhaul work order with “B” in the “Equipment Level” field information is ranked third, and the overhaul work order with “C” in the “Equipment Level” field information is ranked fourth;
[0087] S102213. Sort all overhaul work orders with the same “scheduling group” and “equipment level” field information in S102212 according to the “maintenance level” field information, with the overhaul work order with the “maintenance level” field information of “M1” being ranked first, the overhaul work order with the “maintenance level” field information of “M2” being ranked second, the overhaul work order with the “maintenance level” field information of “M3” being ranked third, and the overhaul work order with the “maintenance level” field information of “other” being ranked fourth;
[0088] S102214, sorting all overhaul work orders having the same “scheduling group”, “equipment level” and “maintenance level” field information in S102213 in ascending order according to the numbers in the “work order task number” field information;
[0089] S10222. For all the overhaul work orders sorted by S10221, they are divided into overhaul work orders with material obstacles and overhaul work orders without material obstacles according to the information in the "Material Reservation Status" field. Overhaul work orders with material obstacles are overhaul work orders with the "Material Reservation Status" field information as "with material obstacles", and overhaul work orders without material reservation obstacles are overhaul work orders with the "Material Reservation Status" field information as "without material obstacles".
[0090] In this embodiment, as one of the feasible methods, the "Material Reservation Status" field information of the overhaul work order is "Material Obstacles", indicating that the materials of the overhaul work order have not been successfully reserved, and it is an overhaul work order with material obstacles; the "Material Reservation Status" field information of the overhaul work order is "No Material Obstacles", indicating that the overhaul work order has no material requirements or the materials have been successfully reserved, and it is a work order without material obstacles.
[0091] In this embodiment, as one of the achievable methods, S1022, sorting all overhaul work orders generated within 12 months before the start of the overhaul, includes the following steps:
[0092] Sort all overhaul work orders generated within 12 months before the start of the overhaul in ascending order according to the time in the "Work Order Creation Time" field information;
[0093] Sort all overhaul work orders with the same "Work Order Creation Time" field information in the above steps in ascending order according to the numbers in the "Work Order Task Number" field information.
[0094] In this embodiment, as one of the achievable methods, S103, setting a preparation plan for all overhaul work orders, including setting a planned completion preparation date for all overhaul work orders;
[0095] Set the planned completion date for all overhaul work orders, including setting the planned completion date for all overhaul work orders generated outside 12 months before the start of the overhaul and without material obstacles, setting the planned completion date for all overhaul work orders generated outside 12 months before the start of the overhaul and with material obstacles, and setting the planned completion date for all overhaul work orders generated within 12 months before the start of the overhaul.
[0096] In this embodiment, as one of the achievable methods, setting the planned completion preparation date of all overhaul work orders generated outside 12 months before the start of the overhaul and without material obstacles includes the following steps:
[0097] During the period from 12 months before the start of the overhaul to 6 months before the start of the overhaul, all overhaul work orders generated outside the 12 months before the start of the overhaul and without material obstacles are sorted, and the "Work Order Task Status" field information of one overhaul work order data is planned to be advanced to "Completion Preparation" every Friday.
[0098] In this embodiment, as one of the achievable methods, setting the planned completion preparation date of all overhaul work orders generated outside 12 months before the start of the overhaul and with material obstacles includes the following steps:
[0099] During the period from 5 months to 2 months before the start of the overhaul, all overhaul work orders with material obstacles generated outside the 12 months before the start of the overhaul will be sorted, and it is planned that the "Work Order Task Status" field information of one overhaul work order data will be advanced to "Completion Preparation" every Friday.
[0100] In this embodiment, as one of the achievable methods, setting the planned completion preparation date of all overhaul work orders generated within 12 months before the start of the overhaul includes the following steps:
[0101] Within 60% of the time between the creation date of the first overhaul work order generated within 12 months before the start of the overhaul and the start date of the overhaul, all overhaul work orders generated within 12 months before the start of the overhaul are sorted, and the "Work Order Task Status" field information of one overhaul work order data is planned to be advanced to "Completion Preparation" every Friday;
[0102] 60% of the time between the creation date of the first overhaul work order generated within 12 months before the start of the overhaul and the start date of the overhaul that is less than five days will be calculated as five days.
[0103] In this embodiment, as one of the achievable methods, S104, advancing the execution of the preparation plan of all overhaul work orders, includes the following steps:
[0104] According to the information in the "Responsible Team" field, the execution data of the overhaul work order preparation plan of each responsible team is classified and displayed;
[0105] Send the overhaul work order preparation plan execution data of each responsible team via email;
[0106] Regular offline overhaul preparation meetings are held to inform each responsible team of the execution data of the overhaul work order preparation plan and conduct assessments.
[0107] In this embodiment, as one of the achievable methods, the overhaul work order preparation plan execution data includes field information: responsible team, planned preparation completion time, actual preparation completion time, preparation plan execution status and remarks;
[0108] Statistics on the execution data of the overhaul work order preparation plan include the following steps:
[0109] Get the "Work Order Task Status" field information of the overhaul work order and advance it to the planned time of "Completion Preparation", and get the "Planned Completion Preparation Time" field information of the overhaul work order;
[0110] Get the actual time when the "Work Order Task Status" field information of the overhaul work order is advanced to "Completion Preparation", and get the "Actual Completion Preparation Time" field information of the overhaul work order;
[0111] The "Preparation Plan Execution Status" field information of the overhaul work order is generated according to the "Planned Preparation Completion Time" and "Actual Preparation Completion Time" field information of the overhaul work order; the "Preparation Plan Execution Status" field information of the overhaul work order includes "Preparation completed as planned" and "Preparation not completed as planned"; if the time in the "Actual Preparation Completion Time" field information of the overhaul work order is later than the time in the "Planned Preparation Completion Time" field information, the "Preparation Plan Execution Status" field information of the overhaul work order is "Preparation not completed as planned", otherwise, the "Preparation Plan Execution Status" field information of the overhaul work order is "Preparation completed as planned";
[0112] The "Remarks" field information of the overhaul work order whose "Preparation Plan Execution" field information is "Preparation not completed as planned" is obtained; the "Remarks" field information of the overhaul work order includes the reason why the preparation was not completed as planned.
[0113] refer to Figure 2 As an implementation of the above method, the present invention provides an embodiment of a nuclear power plant overhaul work order preparation management device. The device embodiment corresponds to the embodiment of the above nuclear power plant overhaul work order preparation management method. The device can be specifically applied to various electronic devices.
[0114] The nuclear power plant overhaul work order preparation management device described in this embodiment includes:
[0115] Acquisition module 201, used to acquire all overhaul work orders;
[0116] The first calculation module 202 is used to group and sort all overhaul work orders;
[0117] The second calculation module 203 is used to set the preparation plan of all overhaul work orders;
[0118] The third calculation module 204 is used to promote the execution of the preparation plan of all overhaul work orders;
[0119] The acquisition module 201 , the first calculation module 202 , the second calculation module 203 and the third calculation module 204 are connected with each other.
[0120] As an implementation of the above method, the present invention provides an embodiment of a computer device, and the computer device embodiment corresponds to the embodiment of the above-mentioned nuclear power plant overhaul work order preparation management method.
[0121] The computer device described in this embodiment includes a memory 301, a processor 302 and a network interface 303 that are interconnected and communicated through a system bus. It should be noted that the figure only shows a computer device with components 301-303, but it should be understood that it is not required to implement all the components shown, and more or fewer components can be implemented instead. Among them, those skilled in the art can understand that the computer device here is a device that can automatically perform numerical calculations and / or information processing according to pre-set or stored instructions, and its hardware includes but is not limited to microprocessors, application-specific integrated circuits, programmable gate arrays, digital processors, embedded devices, etc.
[0122] The computer device may be a computing device such as a desktop computer, a notebook, a PDA, a cloud server, etc. The computer device may interact with a user through a keyboard, a mouse, a remote controller, a touch pad, or a voice control device.
[0123] The memory 301 includes at least one type of readable storage medium, and the readable storage medium includes flash memory, hard disk, multimedia card, card-type memory, random access memory, static random access memory, read-only memory, electrically erasable programmable read-only memory, programmable read-only memory, magnetic memory, disk, optical disk, etc. In some embodiments, the memory 301 can be an internal storage unit of the computer device, such as a hard disk or memory of the computer device. In other embodiments, the memory 301 can also be an external storage device of the computer device, such as a plug-in hard disk, smart memory card, secure digital card, flash memory card, etc. equipped on the computer device. Of course, the memory 301 can also include both the internal storage unit of the computer device and its external storage device. In this embodiment, the memory 301 is generally used to store the operating system and various application software installed on the computer device, such as the computer-readable instructions of the above-mentioned nuclear power plant overhaul work order preparation management method. In addition, the memory 301 can also be used to temporarily store various types of data that have been output or are to be output.
[0124] The processor 302 may be a central processing unit, a controller, a microcontroller, a microprocessor, or other data processing chip in some embodiments. The processor 302 is generally used to control the overall operation of the computer device. In this embodiment, the processor 302 is used to run the computer-readable instructions stored in the memory 301 or process data, such as running the computer-readable instructions of the above-mentioned nuclear power plant overhaul work order preparation management method.
[0125] The network interface 303 may include a wireless network interface or a wired network interface. The network interface 303 is generally used to establish a communication connection between the computer device and other electronic devices.
[0126] As an implementation of the above method, the present invention provides an embodiment of a computer-readable storage medium, and the embodiment of the computer-readable storage medium corresponds to the embodiment of the above-mentioned nuclear power plant overhaul work order preparation management method.
[0127] The computer-readable storage medium described in this embodiment stores computer-readable instructions, and the computer-readable instructions can be executed by at least one processor to enable the at least one processor to perform the steps of the above-mentioned nuclear power plant overhaul work order preparation management method.
[0128] The nuclear power plant overhaul work order preparation management method, device, computer equipment and storage medium of the present embodiment realize the automatic preparation of the nuclear power plant overhaul work order preparation plan, give priority to the preparation work of the overhaul work orders that need to be carefully prepared, ensure the preparation quality of the overhaul work orders that need to be carefully prepared, and avoid the impact of problems in the preparation process of the overhaul work orders that need to be carefully prepared on the entire overhaul preparation work; realize the statistics of the execution data of the nuclear power plant overhaul work order preparation plan, automatically remind each responsible team to complete the overhaul work order preparation work, and improve the overhaul work order preparation efficiency.
[0129] The above-mentioned embodiments only express several implementation methods of the present invention, and the description thereof is relatively specific and detailed, but it cannot be understood as limiting the scope of the patent of the present invention. It should be pointed out that, for ordinary technicians in this field, several variations and improvements can be made without departing from the concept of the present invention, which all belong to the protection scope of the present invention. Therefore, the protection scope of the patent of the present invention shall be subject to the attached claims.
Claims
1. A method for preparing and managing work orders for nuclear power plant overhaul, characterized in that: The following steps are involved: S101. Obtain all overhaul work orders; S102, grouping and sorting all overhaul work orders; S103, setting up a preparation plan for all overhaul work orders; S104. Promote the execution of preparation plans for all overhaul work orders.
2. The method for preparing and managing nuclear power plant overhaul work orders according to claim 1, characterized in that: The overhaul work order includes the following fields: work order task number, work order overhaul number, work order creation time, equipment level, maintenance level, scheduling group, responsible team, material reservation status and work order task status; Among them, the "Material Reservation Status" field information of the overhaul work order includes "Material Obstacle" and "No Material Obstacle"; The Schedule Group field information of the overhaul work order includes Main Line Plan and Non-Main Line Plan. The "Equipment Level" field information of the overhaul work order includes "S", "A", "B" and "C"; The "Maintenance Level" field information of the overhaul work order includes "M1", "M2", "M3" and "Others"; The "Work Order Task Number" field of the overhaul work order contains numbers generated in ascending order according to the creation time of the overhaul work order; The Work Order Task Status field of an overhaul work order includes Preparation Not Started, Preparation Started, and Preparation Completed.
3. The method for preparing and managing nuclear power plant overhaul work orders according to claim 2, characterized in that: Step 102, grouping and sorting all overhaul work orders, includes the following steps: Step 1021: All overhaul work orders are divided into all overhaul work orders generated outside 12 months before the start of the overhaul and all overhaul work orders generated within 12 months before the start of the overhaul according to the "work order creation time" field information; Step 1022: group and sort all overhaul work orders generated outside 12 months before the start of the overhaul, and sort all overhaul work orders generated within 12 months before the start of the overhaul.
4. The method for preparing and managing nuclear power plant overhaul work orders according to claim 3, characterized in that: Step 1022, grouping and sorting all overhaul work orders generated outside the 12 months before the start of the overhaul, includes the following steps: Step 10221: sort all overhaul work orders generated outside the 12 months before the start of the overhaul according to the following steps: Step 102211, sort all overhaul work orders generated outside 12 months before the start of the overhaul according to the "Scheduling Group" field information, and sort the overhaul work orders whose "Scheduling Group" field information is "Main Line Plan" at the front, and the overhaul work orders whose "Scheduling Group" field information is "Non-Main Line Plan" at the back; Step 102212, sort all the overhaul work orders with the same "Schedule Group" field information in step 102211 according to the "Equipment Level" field information, the overhaul work order with "Equipment Level" field information "S" is sorted first, the overhaul work order with "Equipment Level" field information "A" is sorted second, the overhaul work order with "Equipment Level" field information "B" is sorted third, and the overhaul work order with "Equipment Level" field information "C" is sorted fourth; Step 102213, sort all the overhaul work orders with the same "Scheduling Group" and "Equipment Level" field information in step 102212 according to the "Maintenance Level" field information, the overhaul work order with the "Maintenance Level" field information of "M1" is sorted first, the overhaul work order with the "Maintenance Level" field information of "M2" is sorted second, the overhaul work order with the "Maintenance Level" field information of "M3" is sorted third, and the overhaul work order with the "Maintenance Level" field information of "Other" is sorted fourth; Step 102214, sort all overhaul work orders having the same "Scheduling Group", "Equipment Level" and "Maintenance Level" field information in step 102213 in ascending order according to the numbers in the "Work Order Task Number" field information; Step 10222. For all the overhaul work orders sorted in step 10221, they are divided into overhaul work orders with material obstacles and overhaul work orders without material obstacles according to the "Material Reservation Status" field information. Overhaul work orders with material obstacles are overhaul work orders with "Material Reservation Status" field information as "With Material Obstacles", and overhaul work orders without material reservation obstacles are overhaul work orders with "Material Reservation Status" field information as "Without Material Obstacles".
5. The method for preparing and managing nuclear power plant overhaul work orders according to claim 3, characterized in that: Step 1022, sorting all overhaul work orders generated within 12 months before the start of the overhaul, including the following steps: Sort all overhaul work orders generated within 12 months before the start of the overhaul in ascending order according to the time in the Work Order Creation Time field information; Sort all overhaul work orders with the same "Work Order Creation Time" field information in the above steps in ascending order according to the numbers in the "Work Order Task Number" field information.
6. The method for preparing and managing nuclear power plant overhaul work orders according to claim 2, characterized in that: Step 103, setting a preparation plan for all overhaul work orders, including setting a planned completion date for all overhaul work orders; Set the planned completion date for all overhaul work orders, including setting the planned completion date for all overhaul work orders generated outside 12 months before the start of the overhaul and without material obstacles, setting the planned completion date for all overhaul work orders generated outside 12 months before the start of the overhaul and with material obstacles, and setting the planned completion date for all overhaul work orders generated within 12 months before the start of the overhaul.
7. The method for preparing and managing nuclear power plant overhaul work orders according to claim 6, characterized in that: Set the planned completion date for all overhaul work orders generated outside 12 months before the start of the overhaul and without material obstacles, including the following steps: During the period from 12 months to 6 months before the start of the overhaul, all overhaul work orders generated outside the 12 months before the start of the overhaul and without material obstacles are sorted, and the "Work Order Task Status" field information of one overhaul work order data is planned to be advanced to "Completion Preparation" every Friday; Set the planned completion date for all overhaul work orders with material obstacles that were generated outside 12 months before the start of the overhaul, including the following steps: During the period from 5 months to 2 months before the start of the overhaul, all overhaul work orders with material obstacles generated outside the 12 months before the start of the overhaul are sorted, and the "Work Order Task Status" field information of one overhaul work order data is planned to be advanced to "Completion Preparation" every Friday; Set the planned completion date for all overhaul work orders generated within 12 months before the start of the overhaul, including the following steps: Within 60% of the time between the creation date of the first overhaul work order generated within 12 months before the start of the overhaul and the start date of the overhaul, all overhaul work orders generated within 12 months before the start of the overhaul are sorted, and the "Work Order Task Status" field information of one overhaul work order data is planned to be advanced to "Completion Preparation" every Friday; 60% of the time between the creation date of the first overhaul work order generated within 12 months before the start of the overhaul and the start date of the overhaul that is less than five days will be calculated as five days.
8. The method for preparing and managing nuclear power plant overhaul work orders according to claim 2, characterized in that: Step 104, promoting the execution of the preparation plan for all overhaul work orders, includes the following steps: According to the information in the "Responsible Team" field, the execution data of the overhaul work order preparation plan of each responsible team is classified and counted and displayed; Send the overhaul work order preparation plan execution data of each responsible team via email.
9. The method for preparing and managing nuclear power plant overhaul work orders according to claim 8, characterized in that: The overhaul work order preparation plan execution data includes field information: responsible team, planned preparation completion time, actual preparation completion time, preparation plan execution status and remarks; Statistics on the execution data of the overhaul work order preparation plan include the following steps: Get the Work Order Task Status field information of the overhaul work order and advance it to the planned time of Completion Preparation to obtain the Planned Completion Preparation Time field information of the overhaul work order; Get the actual time when the Work Order Task Status field information of the overhaul work order is advanced to Completion Preparation, and obtain the Actual Completion Preparation Time field information of the overhaul work order; Generate the "Preparation Plan Execution Status" field information of the overhaul work order based on the "Planned Preparation Completion Time" and "Actual Preparation Completion Time" field information of the overhaul work order; the "Preparation Plan Execution Status" field information of the overhaul work order includes "Preparation completed as planned" and "Preparation not completed as planned"; if the time in the "Actual Preparation Completion Time" field information of the overhaul work order is later than the time in the "Planned Preparation Completion Time" field information, the "Preparation Plan Execution Status" field information of the overhaul work order is "Preparation not completed as planned", otherwise, the "Preparation Plan Execution Status" field information of the overhaul work order is "Preparation completed as planned"; Get the "Remarks" field information of the overhaul work order whose "Preparation Plan Execution" field information is "Preparation not completed as planned". The "Remarks" field information of the overhaul work order includes the reason why the preparation was not completed as planned.
10. A nuclear power plant overhaul work order preparation management device, characterized in that: include: The acquisition module (201) is used to acquire all overhaul work orders; A first calculation module (202) is used to group and sort all overhaul work orders; A second calculation module (202) is used to set a preparation plan for all overhaul work orders; The third calculation module (203) is used to promote the execution of the preparation plan of all overhaul work orders.
11. A computer device comprising a memory and a processor, wherein the memory stores computer-readable instructions, characterized in that: When the processor executes the computer-readable instructions, the steps of the nuclear power plant overhaul work order preparation management method as described in any one of claims 1-9 are implemented.
12. A computer-readable storage medium having computer-readable instructions stored thereon, characterized in that: When the computer-readable instructions are executed, the steps of the nuclear power plant overhaul work order preparation management method as described in any one of claims 1-9 are implemented.