Bridge construction progress management method and system based on BIM model

By establishing construction progress management methods in the BIM model, including preparing plans, obtaining on-site progress, and establishing a coordination mechanism, the scheduling problems of the BIM model in construction progress management are solved, effective coordination of construction progress and completion of planning are achieved, and construction efficiency and safety are improved.

CN120106492AInactive Publication Date: 2025-06-06SICHUAN ROAD & BRIDGE CONSTRUCTION GROUP CO LTD +1
View PDF 4 Cites 0 Cited by

Patent Information

Application Number
CN202510222984.6
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2025-02-27
Publication Date
2025-06-06
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

The existing BIM model is difficult to achieve reasonable scheduling in construction progress management, resulting in improper coordination of construction progress and affecting construction efficiency and safety.

Method used

By establishing a bridge construction progress management method based on BIM model, including preparing a construction progress plan, obtaining on-site construction progress, comparing the plan with on-site progress, establishing a progress reward mechanism, and establishing a construction progress coordination mechanism for each cycle, clarifying the construction tasks and goals, so as to facilitate the coordination of construction progress in each cycle.

Benefits of technology

Effective coordination of construction progress has been achieved, the construction tasks and goals have been completed in accordance with the plan, the construction efficiency and safety have been improved, and the construction tasks and goals of the total cycle have been completed in accordance with the plan.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN120106492A_ABST
    Figure CN120106492A_ABST
Patent Text Reader

Abstract

The invention relates to a BIM model-based bridge construction progress management method and system, and belongs to the technical field of electric digital data processing, and the method comprises the following steps: 1), building a construction plan; step 2), acquiring the construction progress of the site by taking a period as a unit; 3) comparing the construction plan with the construction progress of the site; step 4): establishing a construction progress coordination mechanism of each period, and determining construction tasks and construction targets of each constructor in the construction progress of each period, thereby facilitating coordination of the construction progress of each period; step 5), comparing whether the time required by the construction plan is the same as the time consumed by on-site construction so as to judge the condition of the on-site construction time and the time required by the construction plan; the method has the beneficial effects that by establishing a construction progress coordination mechanism of each period, the construction task and the construction target of each constructor in the construction progress of each period are determined, and coordination of the construction progress of each period is facilitated.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention belongs to the technical field of electronic digital data processing, and in particular relates to a bridge construction progress management method and system based on a BIM model. Background Art

[0002] BIM model is a comprehensive management system based on digital three-dimensional model. It integrates various relevant information of construction projects into a building model database. It not only includes the geometric information of the building, but also covers non-geometric information such as material properties, component costs, construction progress, operation and maintenance, forming an integrated information resource library, providing a basis for collaborative work for all participants in the entire life cycle of the building.

[0003] The BIM model can simulate various situations of a construction project, such as construction progress simulation and construction site layout simulation, so that construction personnel can understand the construction situation and provide a reliable optimization plan.

[0004] Construction units can use BIM models to manage construction progress, construction quality, and construction safety. For example, by associating the construction progress with the BIM model, the construction progress can be simulated, which can intuitively display the construction process, facilitate the reasonable arrangement of resources, and timely discover progress deviations, thereby improving construction efficiency and safety. Summary of the invention

[0005] The present invention provides a bridge construction progress management method and system based on the BIM model, which is used to solve the technical problem of reasonable scheduling of the BIM model construction progress. The present invention establishes a construction progress coordination mechanism for each period, clarifies the construction tasks and construction goals of each construction personnel in the construction progress of each period, and facilitates the coordination of the construction progress of each period.

[0006] In order to achieve the above object, the present invention is implemented by the following technical solutions:

[0007] The bridge construction progress management method based on the BIM model includes the following steps:

[0008] Step 1): Establish a construction plan; among which, prepare a construction schedule to clarify the specific construction tasks and construction goals of the construction personnel in each period;

[0009] Step 2): Obtain the construction progress on site in cycles; obtain data on the number of construction personnel, technical level of construction personnel, work attitude of construction personnel, and construction quality in each cycle to ensure that the project can be completed according to the predetermined construction tasks and construction goals;

[0010] Step 3): Compare the construction plan with the on-site construction progress; among others, establish a progress reward mechanism based on the comparison results;

[0011] Step 4): Establish a construction progress coordination mechanism for each cycle, clarify the construction tasks and construction goals of each construction personnel in the construction progress of each cycle, and facilitate the coordination of the construction progress of each cycle;

[0012] Step 5): Compare the time required by the construction plan with the time spent on site construction to see if they are the same, so as to determine whether the on-site construction time is consistent with the time required by the construction plan.

[0013] Optionally, in step 1), the preparation of the construction schedule adopts the following steps:

[0014] Step a): Expected construction plan: determine in advance whether there is a deviation between the planned construction progress of each period and the actual construction progress of each period. If there is a deviation, the planned construction progress is changed; if there is no deviation, the planned construction progress is not changed;

[0015] Wherein, in step a), when there is a deviation between the planned construction progress of each period and the actual construction progress of each period, the planned construction progress of each period is adjusted according to the deviation analysis result by means of the construction task sequence, construction task time and construction resource allocation;

[0016] Step b): Divide the construction process: According to the sequence of construction tasks, clarify the number of construction workers in each period and the feedback of construction workers in each period on the construction progress.

[0017] Optionally, in step 2), the construction progress of the site is obtained on a weekly, monthly or quarterly basis;

[0018] The construction progress is obtained by setting and selecting the time nodes through the classification time node selection method of the following formula (1):

[0019] (1);

[0020] In formula (1), , and Representing weekly time festival, monthly time festival and quarterly time festival respectively. To distinguish the time section, , and Distinguish the weekly time periods Monthly time festival and quarterly time ;

[0021] Execute command for time section selection, Ability to select weekly time periods Monthly time festival and quarterly time Any time period in

[0022] For weekly time Monthly time festival and quarterly time Set the time of each week. Monthly time festival or quarterly time period Select a time node from any time node in For weekly time Monthly time festival and quarterly time The setting function of A selected time section.

[0023] Furthermore, the target data node method is used to obtain the construction progress data. The data target node method is as follows:

[0024] (2);

[0025] in, , , and They represent the number of construction workers after characterization, the technical level of construction workers after characterization, the work attitude of construction workers after characterization, and the construction quality after characterization respectively; , , and They are the construction personnel quantity target, construction personnel technical level target, construction personnel work attitude target and construction quality target; , , and They are the construction personnel quantity node, construction personnel technical level node, construction personnel work attitude node and construction quality node;

[0026] To collect the number of construction workers, their technical level, their working attitude and construction quality;

[0027] To record the number of construction workers , Technical level of construction personnel , Construction workers' work attitude And construction quality .

[0028] Optionally, in step 3), a progress reward mechanism is established based on the comparison results to reward construction personnel who complete construction tasks on time or ahead of schedule, and to warn construction personnel who delay the construction period.

[0029] Optionally, in step 4), the construction progress coordination mechanism of each cycle is established by the following steps:

[0030] Step I): Determine the construction tasks and construction goals of the construction personnel in each period, so as to understand whether the construction tasks and construction goals of the construction personnel in each period are completed according to the construction plan;

[0031] Step II): If the construction tasks and construction targets of a certain cycle are not completed, the unfinished construction tasks and construction targets in this cycle are coordinated to the previous cycle of this cycle or to the next cycle of this cycle;

[0032] Step III: Based on step II), determine the construction tasks and construction goals of the total period and complete them according to the construction plan.

[0033] Furthermore, in step II, the method for determining whether a construction task or construction target of a certain period has not been completed is the target sequence method, which is the following formula (3):

[0034] (3);

[0035] in, For the The construction tasks and goals of the cycle, To save The construction tasks and objectives of the period; To bring together the construction tasks and construction goals from the first cycle To Construction tasks and construction goals of the cycle ;

[0036] To detect the The construction tasks and goals of the cycle, To detect the construction tasks and construction goals of each cycle; Coordinate operations for data;

[0037] After checking the construction tasks and construction targets of each cycle, coordinate the execution of the unfinished construction tasks and construction targets in a certain cycle; To determine the construction tasks and construction objectives for the overall period.

[0038] Optionally, in step 5), the on-site construction time and the time required by the construction plan are judged. If the on-site construction time is less than or equal to the time required by the construction plan, the entire bridge construction progress is successfully completed. If the on-site construction time is greater than the time required by the construction plan, the entire bridge construction progress is not successfully completed.

[0039] The bridge construction progress management system based on the BIM model includes:

[0040] Construction calculation unit;

[0041] A data acquisition unit, used to acquire the construction progress on site;

[0042] Data evaluation unit for comparing construction plan with construction progress on site;

[0043] Data coordination unit, used to establish the construction progress coordination mechanism for each period, to facilitate the coordination of the construction progress of each period;

[0044] The construction calculation unit and the data acquisition unit circuits are connected to the data evaluation unit, and the data evaluation unit circuit is connected to the data coordination unit.

[0045] Beneficial effects of the present invention:

[0046] 1. After establishing a construction plan, the present invention obtains the on-site construction progress in units of cycles, compares the construction plan with the on-site construction progress, establishes a construction progress coordination mechanism for each cycle, clarifies the construction tasks and construction goals of each construction personnel in the construction progress of each cycle, facilitates the coordination of the construction progress of each cycle, and compares whether the time required for the construction plan and the time consumed by the on-site construction are the same. By establishing a construction progress coordination mechanism for each cycle, the unfinished construction tasks and construction goals of a certain cycle are coordinated to the previous cycle of the current cycle or to the next cycle of the current cycle, and the construction tasks and construction goals of the total cycle are completed according to the construction plan.

[0047] 2. The establishment of the construction progress coordination mechanism for each cycle of the present invention is that after the construction personnel have determined the construction tasks and construction goals of each cycle, they will understand whether the construction tasks and construction goals of the construction personnel in each cycle are completed according to the construction plan. If the construction tasks and construction goals of a certain cycle are not completed, the unfinished construction tasks and construction goals in this cycle will be coordinated to the previous cycle of this cycle or to the next cycle of this cycle. The construction tasks and construction goals of the total cycle are completed according to the construction plan, and the construction tasks and construction goals of the total cycle remain unchanged. BRIEF DESCRIPTION OF THE DRAWINGS

[0048] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0049] Figure 1 It is a schematic diagram of the system structure of the present invention;

[0050] Figure 2 It is a work flow chart of the present invention;

[0051] Figure 3 It is the construction progress coordination principle diagram of the present invention. DETAILED DESCRIPTION

[0052] The embodiments of the present application are described in detail below with reference to the accompanying drawings.

[0053] Example 1

[0054] like Figure 1 As shown, this embodiment provides a bridge construction progress management system based on a BIM model, including:

[0055] Construction calculation unit, used to prepare construction schedule;

[0056] A data acquisition unit, used to acquire the construction progress on site;

[0057] Data evaluation unit for comparing construction plan with construction progress on site;

[0058] Data coordination unit, used to establish the construction progress coordination mechanism for each period, to facilitate the coordination of the construction progress of each period;

[0059] The data comparison unit is used to compare whether the time required by the construction plan and the time consumed by the on-site construction are the same.

[0060] The construction calculation unit and the data acquisition unit are connected to the data evaluation unit by circuits, the data evaluation unit is connected to the data coordination unit by circuits, and the data coordination unit is further connected to the data comparison unit by circuits.

[0061] The construction progress plan compiled in the construction calculation unit and the on-site construction progress in the data acquisition unit are transmitted to the data evaluation unit for comparison. The data evaluation unit then compares whether the construction plan is consistent with the on-site construction progress. If they are inconsistent, they are coordinated through the data coordination unit. Finally, the data comparison unit compares whether the total time required for the construction plan and the total time consumed for the on-site construction are the same, so as to determine whether the entire bridge construction progress is successfully completed within the planned time. If the on-site construction time is less than or equal to the time required by the construction plan, the entire bridge construction progress is successfully completed. If the on-site construction time is greater than the time required by the construction plan, the entire bridge construction progress is not successfully completed.

[0062] In addition, the respective operating procedures within the construction calculation unit, data acquisition unit, data evaluation unit, data coordination unit and data comparison unit are set according to the situation.

[0063] Example 2

[0064] Based on Example 1, Figure 2 The present embodiment provides a bridge construction progress management method based on a BIM model, comprising the following steps:

[0065] Step 1): Establish a construction plan; among them, prepare a construction schedule to clarify the specific construction tasks and construction goals of the construction personnel in each cycle (one week, one month or one quarter);

[0066] Step 2): Obtain the construction progress on site in cycles; obtain data on the number of construction personnel, technical level of construction personnel, work attitude of construction personnel, and construction quality in each cycle to ensure that the project can be completed according to the predetermined construction tasks and construction goals;

[0067] Step 3): Compare the construction plan and the on-site construction progress; wherein, according to the comparison, establish a progress reward mechanism; wherein, in step 3), according to the comparison, establish a progress reward mechanism, reward the construction personnel who complete the construction task on time or ahead of schedule, and warn the construction personnel who delay the construction period. The comparison of step 3) can be set according to the program inside the data evaluation module;

[0068] Step 4): Establish a construction progress coordination mechanism for each cycle, clarify the construction tasks and construction goals of each construction personnel in the construction progress of each cycle, and facilitate the coordination of the construction progress of each cycle;

[0069] Step 5): Compare the time required by the construction plan (i.e. the total cycle time required by the construction plan) and the time consumed by the on-site construction (i.e. the total cycle time required for the on-site construction) to see if they are the same, so as to determine whether the on-site construction time is consistent with the time required by the construction plan.

[0070] Among them, in step 5), the on-site construction time and the time required by the construction plan are judged. If the on-site construction time is less than or equal to the time required by the construction plan, the entire bridge construction progress is successfully completed. If the on-site construction time is greater than the time required by the construction plan, the entire bridge construction progress is not successfully completed.

[0071] Example 3

[0072] Based on Example 2, in step 1), the preparation of the construction schedule adopts the following steps:

[0073] Step a): Anticipated construction plan: Determine in advance whether there is a deviation between the planned construction progress of each period and the actual construction progress of each period. If there is a deviation (such as insufficient construction resources or affected by weather), the planned construction progress will be changed. If there is no deviation, the planned construction progress will not be changed.

[0074] Wherein, in step a), when there is a deviation between the planned construction progress of each period and the actual construction progress of each period, the planned construction progress of each period is adjusted according to the deviation analysis result by means of the construction task sequence, construction task time and construction resource allocation;

[0075] Step b): Divide the construction process: According to the sequence of construction tasks, clarify the number of construction workers in each period and the feedback of construction workers in each period on the construction progress.

[0076] Example 4

[0077] Based on Example 2, in step 2), the construction progress of the site is obtained on a weekly, monthly or quarterly basis;

[0078] The construction progress is obtained by setting and selecting the time nodes through the classification time node selection method of the following formula (1):

[0079] (1);

[0080] In formula (1), , and They represent weekly time periods (i.e. how many days a week there are), monthly time periods (i.e. how many days a month there are), and quarterly time periods (i.e. how many days a quarter there are). To distinguish the time section, , and Distinguish the weekly time periods Monthly time festival and quarterly time , that is, to distinguish between weekly time festivals Monthly time festival and quarterly time ;

[0081] Execute command for time section selection, Ability to select weekly time periods Monthly time festival and quarterly time Any time period in

[0082] For weekly time Monthly time festival and quarterly time Set the time of each session (i.e. set the specific number of days per week, set the specific number of days per month, and set the specific number of days per quarter), and then select the specific number of days per week from the weekly time session. Monthly time festival or quarterly time period Select a time node from any time node in For weekly time Monthly time festival and quarterly time The setting function of A selected time section.

[0083] From formula (1), it can be known that the construction progress can be intelligently obtained at a certain time node in a weekly, monthly or quarterly period by setting a weekly, monthly or quarterly time. For example, the construction progress can be obtained on a weekly, monthly or quarterly basis.

[0084] Furthermore, the target data node method is used to obtain the construction progress data. The data target node method is as follows:

[0085] (2);

[0086] in, , , and They represent the number of construction workers after characterization, the technical level of construction workers after characterization, the work attitude of construction workers after characterization, and the construction quality after characterization respectively; , , and They are the construction personnel quantity target (the specific number of construction personnel), the construction personnel technical level target (the evaluation criteria for the construction personnel technical level), the construction personnel work attitude target (the evaluation criteria for the construction personnel work attitude) and the construction quality target (the evaluation criteria for the construction quality); , , and They are the construction personnel quantity node (adjustment of the construction personnel quantity), the construction personnel technical level node (modification of the evaluation criteria for the construction personnel technical level), the construction personnel work attitude node (modification of the evaluation criteria for the construction personnel work attitude) and the construction quality node (modification of the evaluation criteria for the construction quality);

[0087] To collect the number of construction workers, their technical level, their working attitude and construction quality; is the function for aggregating data;

[0088] To record the number of construction workers , Technical level of construction personnel , Construction workers' work attitude And construction quality .

[0089] in, To determine the target number of construction personnel based on the number of construction personnel node, and obtain the number of construction personnel after characterization; To determine the technical level target of construction personnel based on the technical level node of construction personnel and obtain the technical level of construction personnel after characterization; In order to determine the construction workers' work attitude targets based on the construction workers' work attitude nodes and obtain the construction workers' work attitude after characterization, To obtain the construction quality after characterization based on the construction quality node and the construction quality node target, Formula (3) uses the target data node method to intelligently obtain the construction progress data at a certain time node in each week, month or quarter.

[0090] Example 5

[0091] Based on Example 2, in step 4), the establishment of the construction progress coordination mechanism of each cycle adopts the following steps:

[0092] Step I): Determine the construction tasks and construction goals of the construction personnel in each period, so as to understand whether the construction tasks and construction goals of the construction personnel in each period are completed according to the construction plan;

[0093] Step II): If the construction tasks and construction targets of a certain cycle are not completed, the unfinished construction tasks and construction targets in this cycle are coordinated to the previous cycle of this cycle or to the next cycle of this cycle;

[0094] Step III: Based on step II), determine the construction tasks and construction goals of the total period and complete them according to the construction plan.

[0095] Furthermore, in step II, the method for determining whether a construction task or construction target of a certain period has not been completed is the target sequence method, which is the following formula (3):

[0096] (3);

[0097] in, For the construction tasks and construction goals of the first cycle, To preserve the construction tasks and construction goals of the first cycle, For the The construction tasks and goals of the cycle, To save The construction tasks and goals of the cycle, For the The construction tasks and goals of the cycle, To save The construction tasks and objectives of the period; To bring together the construction tasks and construction goals from the first cycle To Construction tasks and construction goals of the cycle ;

[0098] For the detected The construction tasks and goals of the cycle, For the detected The construction tasks and construction goals of the cycle are judged. To detect and judge the construction tasks and construction targets of each cycle, the construction tasks and construction targets from the first cycle are detected. To Construction tasks and construction goals of the cycle After determining the construction tasks and construction goals of each period, we can then determine the construction tasks and construction goals of each period. To detect the construction tasks and construction targets from the first cycle in a sequence To Construction tasks and construction goals of the cycle or in another order, Construction tasks and construction goals of the cycle Construction tasks and goals until the first cycle , is the detection order; Coordinate operations for data;

[0099] After testing the construction tasks and construction targets of each cycle, data coordination operations are carried out , coordinate the unfinished construction tasks and construction goals in a certain cycle; To determine the construction tasks and construction goals for the total cycle (because the unfinished construction tasks and construction goals in a certain cycle are allocated to other cycles, the construction tasks and construction goals for the total cycle remain unchanged).

[0100] Specific data coordination operations, such as Figure 3 As shown, the first Construction tasks and construction goals of the cycle After (actually that is , only the detected The construction tasks and construction goals of the cycle are achieved through make a judgment) The planned Periodic construction tasks and construction target data Whether the construction is completed according to the plan, if Periodic construction tasks and construction target data If the construction plan is not completed, The unfinished construction plan is coordinated to or middle.

[0101] The above is only a specific embodiment of the present invention, but the protection scope of the present invention is not limited thereto. Any person skilled in the art can easily think of changes or substitutions within the technical scope of the present invention, which should be included in the protection scope of the present invention. Therefore, the protection scope of the present invention should be based on the protection scope of the claims.

Claims

1. The bridge construction progress management method based on BIM model is characterized by: The steps include: Step 1): Establish a construction plan; among which, prepare a construction schedule to clarify the specific construction tasks and construction goals of the construction personnel in each period; Step 2): Obtain the construction progress on site in cycles; obtain data on the number of construction personnel, technical level of construction personnel, work attitude of construction personnel, and construction quality in each cycle to ensure that the project can be completed according to the predetermined construction tasks and construction goals; Step 3): Compare the construction plan with the on-site construction progress; among others, establish a progress reward mechanism based on the comparison results; Step 4): Establish a construction progress coordination mechanism for each cycle, clarify the construction tasks and construction goals of each construction personnel in the construction progress of each cycle, and facilitate the coordination of the construction progress of each cycle; Step 5): Compare the time required by the construction plan with the time spent on site construction to see if they are the same, so as to determine whether the on-site construction time is consistent with the time required by the construction plan.

2. The bridge construction progress management method based on the BIM model according to claim 1 is characterized in that: In step 1), the preparation of the construction schedule adopts the following steps: Step a): Expected construction plan: pre-determine whether there is a deviation between the planned construction progress of each period and the actual construction progress of each period, and if there is a deviation, change the planned construction progress; if there is no deviation, do not change the planned construction progress; Wherein, in the step a), when there is a deviation between the planned construction progress of each period and the actual construction progress of each period, the planned construction progress of each period is adjusted according to the deviation analysis result by the construction task sequence, construction task time and construction resource allocation; Step b): Divide the construction process: According to the sequence of construction tasks, clarify the number of construction workers in each period and the feedback of construction workers in each period on the construction progress.

3. The bridge construction progress management method based on the BIM model according to claim 1 is characterized in that: In the step 2), the construction progress on site is obtained on a weekly, monthly or quarterly basis; The construction progress is obtained by setting and selecting the time nodes through the classification time node selection method of the following formula (1): (1); In formula (1), , and Representing weekly time festival, monthly time festival and quarterly time festival respectively. To distinguish the time section, , and Distinguish the weekly time periods Monthly time festival and quarterly time ; Execute command for time section selection, Ability to select weekly time periods Monthly time festival and quarterly time Any time period in For weekly time Monthly time festival and quarterly time Set the time of each week. Monthly time festival or quarterly time Select a time node from any time node in For weekly time Monthly time festival and quarterly time The setting function of A selected time section.

4. The bridge construction progress management method based on the BIM model according to claim 3 is characterized in that: The target data node method is used to obtain the construction progress data. The data target node method is as follows: (2); in, , , and They represent the number of construction workers after characterization, the technical level of construction workers after characterization, the work attitude of construction workers after characterization, and the construction quality after characterization respectively; , , and They are the construction personnel quantity target, construction personnel technical level target, construction personnel work attitude target and construction quality target; , , and They are the construction personnel quantity node, construction personnel technical level node, construction personnel work attitude node and construction quality node; To collect the number of construction workers, their technical level, their working attitude and construction quality; To record the number of construction workers , Technical level of construction personnel , Construction workers' work attitude And construction quality .

5. The bridge construction progress management method based on the BIM model according to claim 1 is characterized in that: In step 3), a progress reward mechanism is established based on the comparison results, rewarding construction personnel who complete construction tasks on time or ahead of schedule, and warning construction personnel who delay the construction period.

6. The bridge construction progress management method based on the BIM model according to claim 1 is characterized in that: In step 4), the construction progress coordination mechanism of each cycle is established by the following steps: Step I): Determine the construction tasks and construction goals of the construction personnel in each period, so as to understand whether the construction tasks and construction goals of the construction personnel in each period are completed according to the construction plan; Step II): If the construction tasks and construction targets of a certain cycle are not completed, the unfinished construction tasks and construction targets in this cycle are coordinated to the previous cycle of this cycle or to the next cycle of this cycle; Step III: Based on step II), determine the construction tasks and construction goals of the total period and complete them according to the construction plan.

7. The bridge construction progress management method based on the BIM model according to claim 6 is characterized in that: In step II, the method for determining whether the construction tasks and construction targets of a certain period have not been completed is the target sequence method, which is the following formula (3): (3); in, For the The construction tasks and goals of the cycle, To save Construction tasks and construction goals of the cycle; To bring together the construction tasks and construction goals from the first cycle To Construction tasks and construction goals of the cycle ; To detect the The construction tasks and goals of the cycle, To detect the construction tasks and construction goals of each cycle; Coordinate operations for data; After checking the construction tasks and construction targets of each cycle, coordinate the execution of the unfinished construction tasks and construction targets in a certain cycle; To determine the construction tasks and construction objectives for the overall period.

8. The bridge construction progress management method based on the BIM model according to claim 1 is characterized in that: In step 5), the on-site construction time and the time required by the construction plan are judged. If the on-site construction time is less than or equal to the time required by the construction plan, the entire bridge construction progress is successfully completed. If the on-site construction time is greater than the time required by the construction plan, the entire bridge construction progress is not successfully completed.

9. A bridge construction progress management system based on a BIM model, used to implement a bridge construction progress management method based on a BIM model according to any one of claims 1 to 8, characterized in that: include: Construction calculation unit; A data acquisition unit, used to acquire the construction progress on site; Data evaluation unit for comparing construction plan with construction progress on site; Data coordination unit, used to establish the construction progress coordination mechanism for each period, to facilitate the coordination of the construction progress of each period; The construction calculation unit and the data acquisition unit circuit are connected to the data evaluation unit, and the data evaluation unit circuit is connected to the data coordination unit.

Citation Information

Patent Citations

  • Construction progress informatization management method

    CN111340458A

  • Engineering project construction progress management method and device, equipment and storage medium

    CN113822654A

  • Construction management method based on BIM

    CN115048699A

  • Construction progress management method and system based on BIM

    CN118521161A