By using a biochar heat exchange system, the heat energy generated during the biochar preparation process is used to warm the greenhouse, which solves the problems of low efficiency and environmental pollution of traditional greenhouse heating methods and achieves a high-efficiency and economical greenhouse heating effect.
Patent Information
- Application Number
- CN202510263249.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2025-03-06
- Publication Date
- 2026-11-17
- Estimated Expiration
- 2045-03-06
AI Technical Summary
Traditional greenhouse heating methods are inefficient in terms of energy use, costly, and pollute the environment. Thermal energy is not effectively utilized during the biochar preparation process.
Design a biochar heat exchange system to use the heat energy from the biochar preparation process to warm the greenhouse. By setting up a dual heat storage chamber and valve assembly, periodic heat exchange between hot mixed gas and cold air is achieved. Combined with PLC and cylinder control of valve switching, the system's stability and automated operation are ensured.
It improves energy efficiency, reduces greenhouse heating costs, and achieves effective utilization of thermal energy in the biochar preparation process, resulting in good economic and environmental benefits.
Smart Images

Figure CN120153889B_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of greenhouse environment control technology. More specifically, this invention relates to a biochar heat exchange system for greenhouse heating. Background Technology
[0002] In agricultural production, greenhouse cultivation is an important method that creates a suitable growing environment for crops, extends their growth cycle, and improves yield and quality. However, temperature control in greenhouses remains a critical and challenging issue. In cold seasons or regions with low temperatures, maintaining a suitable temperature inside the greenhouse requires significant energy consumption. Traditional greenhouse heating methods primarily include coal, oil, and gas heating, but these methods have several problems. First, energy efficiency is low, with a large amount of heat wasted during transmission and use, leading to high energy costs and increasing farmers' production costs. Second, the combustion of these traditional energy sources produces large amounts of pollutants, such as carbon dioxide, sulfur dioxide, and nitrogen oxides, causing serious environmental pollution and failing to meet the requirements of sustainable development. Furthermore, while electric heating is relatively clean, electricity costs are high, and in areas with unstable power supplies, power outages may occur, affecting normal greenhouse operations. Solar heating methods are also available, but they are greatly affected by weather and season; on cloudy days or in winter when sunlight is limited, the heating effect is often unsatisfactory.
[0003] Current technologies in biochar production primarily focus on biochar production itself, while the significant amount of heat energy generated during the process is not fully and effectively utilized. This heat energy is typically emitted into the environment as high-temperature waste gas, resulting not only in energy waste but also potential thermal pollution of the surrounding environment. This application aims to address the challenge of integrating the heat energy generated during biochar production with greenhouse heating requirements to develop an efficient, environmentally friendly, and economical greenhouse heating system. Previous attempts have encountered difficulties in achieving ideal heating effects and energy utilization efficiency due to challenges in matching biochar production equipment with the greenhouse environment, heat exchange efficiency, and system stability. Summary of the Invention
[0004] This invention provides a biochar heat exchange system for greenhouse heating, which can utilize the heat energy from the biochar preparation process to heat the greenhouse, thereby improving energy efficiency and reducing greenhouse heating costs.
[0005] To achieve these objectives and other advantages according to the present invention, a biochar heat exchange system for greenhouse warming is provided, comprising: A pair of biochar preparation devices (1) are set at the front and rear sides of the greenhouse (7); A pair of heat exchange devices (2) are set on both sides of the outside of the greenhouse (7). One heat exchange device (2) is connected to a biochar preparation device (1) on the same side through a set of hot mixed gas pipeline (3) and cold mixed gas pipeline (4). The pair of heat exchange devices (2) are connected through a set of upward air pipeline (5) and downward air pipeline (6). The two sets of hot mixed gas pipeline (3) and cold mixed gas pipeline (4) are set outside the greenhouse (7). The set of upward air pipeline (5) and downward air pipeline (6) passes through the inside of the greenhouse (7). The hot mixed gas of the biochar preparation device (1) enters the heat exchange device (2) through the hot mixed gas pipeline (3). After heat exchange and cooling, it flows back to the biochar preparation device (1) through the cold mixed gas pipeline (4) for purification and recovery. The cold air after passing through the greenhouse (7) enters a heat exchange device (2) through the upward air pipeline (5) or the downward air pipeline (6). After heat exchange and heating, it passes through the greenhouse (7) again through the downward air pipeline (6) or the upward air pipeline (5) and enters another heat exchange device (2).
[0006] Preferably, the heat exchange device (2) comprises: The dual heat storage chamber includes a first heat storage chamber (21) and a second heat storage chamber (25), the first heat storage chamber (21) and the second heat storage chamber (25) being filled with ceramic heat storage body; The valve assembly includes a first valve assembly and a second valve assembly. The valves switch to control the direction of airflow, thereby achieving the switching of cycles of heating the first heat storage chamber (21) with hot mixed gas while cooling the second heat storage chamber (25) with cold air, and cooling the first heat storage chamber (21) with cold air while heating the second heat storage chamber (25).
[0007] Preferably, the first heat storage chamber (21) has a first vent (211) and a second vent (212). The second heat storage chamber (25) has a third vent (251) and a fourth vent (252); The first valve assembly includes a first inner chamber (22) and a first outer chamber (23) arranged coaxially. The first inner chamber (22) is provided with a first valve stem (24). The first valve stem (24) is provided with a first valve stem end plate (241), a first valve plate (242), a second valve plate (243), and a third valve plate (244) in sequence along the valve stem travel direction, dividing the first inner chamber (22) into independent first space (221), second space (222), third space (223), and fourth space (224). Along the valve stem travel direction, there are sequentially provided a first through hole (225), a cold air inlet (226), a first inner chamber ventilation port (227), a cold mixed gas outlet (228), and a second through hole (229). The first through hole (225) and the second through hole (229) are connected to the first outer chamber (23). The first inner chamber ventilation port (227) is connected to the first ventilation port (211). The first outer chamber (23) is provided with a first outer chamber ventilation port (231). The first outer chamber ventilation port (231) is connected to the fourth ventilation port (252). The second valve assembly includes a second inner chamber (26) and a second outer chamber (27) arranged coaxially. A second valve stem (28) is disposed inside the second inner chamber (26). Along the valve stem's travel direction, a second valve stem end plate (281), a fourth valve plate (282), a fifth valve plate (283), and a sixth valve plate (284) are sequentially disposed on the second valve stem (28), dividing the second inner chamber (26) into independent fifth space (261), sixth space (262), seventh space (263), and eighth space (264). Along the valve stem travel direction, there are sequentially provided a third through hole (265), a hot air inlet (266), a second inner chamber ventilation port (267), a hot air outlet (268), and a fourth through hole (269). The third through hole (265) and the fourth through hole (269) are connected to the second outer chamber (27). The second inner chamber ventilation port (267) is connected to the second ventilation port (212). The second outer chamber (27) is provided with a second outer chamber ventilation port (271). The first outer chamber ventilation port (231) is connected to the third ventilation port (251). When the valve is switched to the first state, that is, when the hot mixed gas heats the first heat storage chamber (21) while the cold air cools the second heat storage chamber (25), the first valve stem (24) retracts to the first position and the second valve stem (28) moves to the third position. The first through hole (225) and the cold air inlet (226) are located in the second space (222), the first inner chamber air exchange port (227) and the cold mixed gas outlet (228) are located in the third space (223), the second through hole (229) is located in the fourth space (224), the third through hole (265) is located in the fifth space (261), the hot mixed gas inlet (266) and the second inner chamber air exchange port (267) are located in the sixth space (262), and the hot air outlet (268) and the fourth through hole (269) are located in the seventh space (263). When the valve is switched to the second state, that is, when the cold air cools the first heat storage chamber (21) and the hot mixed gas heats the second heat storage chamber (25), the first valve stem (24) moves to the second position and the second valve stem (28) retracts to the fourth position. The first through hole (225) is located in the first space (221), the cold air inlet (226) and the first inner chamber ventilation port (227) are located in the second space (222), the cold mixed gas outlet (228) and the second through hole (229) are located in the third space (223), the third through hole (265) and the hot mixed gas inlet (266) are located in the sixth space (262), the second inner chamber ventilation port (267) and the hot air outlet (268) are located in the seventh space (263), and the fourth through hole (269) is located in the eighth space (264).
[0008] Preferably, the heat exchange device (2) further includes a purging system that uses inert gas to purge the dual heat storage chambers.
[0009] Preferably, the heat exchange device (2) further includes a PLC, which uses a cylinder to synchronously control the forward and backward movements of the first valve stem (24) and the second valve stem (28). When the valve is switched to the first state, the first valve stem (24) is backward to the first position and the second valve stem (28) is forward to the third position. When the valve is switched to the second state, the first valve stem (24) is forward to the second position and the second valve stem (28) is backward to the fourth position.
[0010] Preferably, the PLC sets a switching time and a purging time. The first heat storage chamber (21) is in a heating state and the second heat storage chamber (25) is in a cooling state. When the set switching time is reached, the PLC controls the valve assembly to stop the air intake. The PLC controls the purging of inert gas. When the set purging time is reached, the PLC controls the purging system to stop running and complete the purging process. The PLC controls the valve assembly to switch valves and control the airflow direction so that the first heat storage chamber (21) is in a cooling state and the second heat storage chamber (25) is in a heating state.
[0011] The present invention has at least the following beneficial effects: First, the present invention, through the setting of two sets of hot mixed gas pipelines (3) and cold mixed gas pipelines (4) and a set of air pipelines, allows the hot mixed gas of the biochar preparation device (1) to enter the heat exchange device (2) through the hot mixed gas pipeline (3) and be cooled down, and then be returned for purification and recovery through the cold mixed gas pipeline (4). The cold air of the greenhouse (7) enters the heat exchange device (2) through the air pipeline, is heated up and then passes through the greenhouse (7) again. The heat energy in the biochar preparation process is used to heat up the greenhouse (7), so that the heat of the hot mixed gas is transferred to the cold air in the greenhouse (7), which improves the energy utilization efficiency, reduces the cost of heating the greenhouse (7), and realizes the effective utilization of heat energy in the biochar preparation process, which has good economic and environmental benefits.
[0012] Secondly, this invention employs a dual-heat storage chamber and valve assembly design to achieve periodic heat exchange between the hot mixed gas and the cold air. The ceramic heat storage body can efficiently store and release heat, improving heat exchange efficiency. By switching valves, the hot mixed gas and the cold air can be alternately heated and cooled in different heat storage chambers, ensuring continuous and stable operation of the system.
[0013] Third, by controlling the position of the valve stem, this invention enables the connection and isolation of different spaces, ensuring that the hot mixed gas and cold air can flow and exchange heat accurately under different working conditions, thus guaranteeing the reliability and stability of the system and improving the heat exchange effect.
[0014] Fourth, the present invention adopts a purging system design, which can effectively solve the problem of gas residue in the dual heat storage chamber. Using inert gas for purging can prevent the mixing of different gases and ensure environmental protection and no pollution. Fifth, this invention uses PLC and cylinders to synchronously control the forward and backward movements of the valve stem, which improves the accuracy and stability of valve switching. The automated control method reduces the error and labor intensity of manual operation, enabling the system to operate more accurately according to the set state, thereby improving the system's operating efficiency and reliability.
[0015] Sixth, this invention enables automatic valve switching and purging operations by setting switching and purging times via PLC, ensuring the continuity and stability of the heat exchange process, allowing the system to operate more precisely according to the set state, and improving the system's automation level.
[0016] Other advantages, objectives and features of the present invention will become apparent in part from the following description, and in part from those skilled in the art through study and practice of the invention. Attached Figure Description
[0017] Figure 1 This is a schematic diagram of the structure of one technical solution of the present invention; Figure 2 This is a schematic diagram of the heat exchange device when switching the valve to the first state according to a technical solution of the present invention; Figure 3 This is a schematic diagram of the heat exchange device when switching the valve to the second state according to a technical solution of the present invention. Detailed Implementation
[0018] The present invention will now be described in further detail with reference to the accompanying drawings, so that those skilled in the art can implement it based on the description.
[0019] It should be understood that terms such as “having,” “comprising,” and “including” as used herein do not exclude the presence or addition of one or more other elements or combinations thereof.
[0020] It should be noted that, unless otherwise specified, the experimental methods described in the following embodiments are conventional methods, and the reagents and materials mentioned are commercially available. In the description of this invention, it should be noted that, unless otherwise explicitly specified and limited, the terms "installation," "connection," and "setting" should be interpreted broadly. For example, they can refer to fixed connection or setting, detachable connection or setting, or integral connection or setting. Those skilled in the art can understand the specific meaning of the above terms in this invention based on the specific circumstances. The terms "lateral," "longitudinal," "upper," "lower," "front," "rear," "left," "right," "vertical," "horizontal," "top," "bottom," "inner," and "outer," etc., indicate the orientation or positional relationship based on the orientation or positional relationship shown in the accompanying drawings, and are only for the convenience of describing this invention and simplifying the description. They do not indicate or imply that the device or element referred to must have a specific orientation, or be constructed and operated in a specific orientation, and therefore should not be construed as a limitation of this invention.
[0021] like Figure 1 As shown, the present invention provides a biochar heat exchange system for greenhouse heating, comprising: A pair of biochar preparation devices (1) are set at the front and rear sides of the greenhouse (7); A pair of heat exchange devices (2) are set on both sides of the outside of the greenhouse (7). One heat exchange device (2) is connected to a biochar preparation device (1) on the same side through a set of hot mixed gas pipeline (3) and cold mixed gas pipeline (4). The pair of heat exchange devices (2) are connected through a set of upward air pipeline (5) and downward air pipeline (6). The two sets of hot mixed gas pipeline (3) and cold mixed gas pipeline (4) are set outside the greenhouse (7). The set of upward air pipeline (5) and downward air pipeline (6) passes through the inside of the greenhouse (7). The hot mixed gas of the biochar preparation device (1) enters the heat exchange device (2) through the hot mixed gas pipeline (3). After heat exchange and cooling, it flows back to the biochar preparation device (1) through the cold mixed gas pipeline (4) for purification and recovery. The cold air after passing through the greenhouse (7) enters a heat exchange device (2) through the upward air pipeline (5) or the downward air pipeline (6). After heat exchange and heating, it passes through the greenhouse (7) again through the downward air pipeline (6) or the upward air pipeline (5) and enters another heat exchange device (2).
[0022] In the above technical solution, by setting up two sets of hot mixed gas pipelines (3) and cold mixed gas pipelines (4) and a set of air pipelines, the hot mixed gas of the biochar preparation device (1) enters the heat exchange device (2) through the hot mixed gas pipeline (3) and is cooled down, and then is returned for purification and recovery by the cold mixed gas pipeline (4). The cold air of the greenhouse (7) enters the heat exchange device (2) through the air pipeline, is heated up and then passes through the greenhouse (7) again. The heat energy in the biochar preparation process is used to heat up the greenhouse (7), so that the heat of the hot mixed gas is transferred to the cold air in the greenhouse (7), which improves the energy utilization efficiency, reduces the cost of heating the greenhouse (7), and realizes the effective utilization of heat energy in the biochar preparation process, which has good economic and environmental benefits.
[0023] In practical applications, a pair of biochar preparation devices (1) and a pair of heat exchange devices (2) are first installed on both sides of the greenhouse (7). The biochar preparation device (1) can be a common biomass pyrolysis device, such as a fixed-bed pyrolysis furnace or a fluidized-bed pyrolysis furnace. Taking a fixed-bed pyrolysis furnace as an example, biomass raw materials (such as straw, sawdust, etc.) are loaded into the furnace and pyrolyzed under oxygen-deficient or oxygen-limited conditions to produce biochar and hot mixed gas. The hot mixed gas pipeline (3) and the cold mixed gas pipeline (4) are made of high-temperature resistant and corrosion-resistant metal pipes, such as stainless steel pipes, and the pipes are wrapped with insulation materials, such as rock wool or glass wool, to reduce heat loss during transmission. The air pipeline is made of a material with a certain strength, such as double-layer hollow PVC pipes, to ensure smooth airflow. When the biochar preparation device (1) starts working, the temperature of the generated hot mixed gas is usually between 300-800℃, and it enters the heat exchange device (2) through the hot mixed gas pipeline (3). In the heat exchanger (2), the hot mixed gas exchanges heat with the cold air. After the temperature drops, it flows back to the biochar preparation device (1) through the cold mixed gas pipeline (4) for purification and recovery. The cold air in the greenhouse (7) enters a heat exchanger (2) through the upward air pipeline (5) or the downward air pipeline (6). After being heated in the heat exchanger (2), it passes through the greenhouse (7) again through the downward air pipeline (6) or the upward air pipeline (5) to provide heat to the greenhouse (7). During the installation process, it is necessary to ensure that the pipeline connection is tight. Welding or flange connection can be used, and sealant should be used to seal it to prevent air leakage. At the same time, the biochar preparation device (1) and the heat exchanger (2) should be inspected and maintained regularly, such as checking whether the furnace lining of the pyrolysis furnace is damaged or whether the pipeline is corroded, to ensure the normal operation of the system.
[0024] Traditional greenhouse (7) heating methods are inefficient in energy use, costly, and pollute the environment, while the heat energy in the biochar preparation process is not effectively utilized. The system constructed by the above technical solution combines the biochar preparation device (1) with the greenhouse (7) heating, thereby achieving efficient utilization of heat energy, reducing the heating cost of the greenhouse (7), and reducing environmental pollution.
[0025] In another technical solution, the heat exchange device (2) includes: The dual heat storage chamber includes a first heat storage chamber (21) and a second heat storage chamber (25), the first heat storage chamber (21) and the second heat storage chamber (25) being filled with ceramic heat storage body; The valve assembly includes a first valve assembly and a second valve assembly. The valves switch to control the direction of airflow, thereby achieving the switching of cycles of heating the first heat storage chamber (21) with hot mixed gas while cooling the second heat storage chamber (25) with cold air, and cooling the first heat storage chamber (21) with cold air while heating the second heat storage chamber (25).
[0026] The above technical solution employs a dual-cell heat storage system and valve assembly design to achieve periodic heat exchange between the hot mixed gas and the cold air. The ceramic heat storage medium can efficiently store and release heat, improving heat exchange efficiency. By switching valves, the hot mixed gas and the cold air can be alternately heated and cooled in different heat storage chambers, ensuring continuous and stable operation of the system.
[0027] For the dual heat storage chambers in the heat exchange device (2), high-temperature resistant and heat storage-efficient ceramic heat storage bodies are selected to fill the first heat storage chamber (21) and the second heat storage chamber (25). The ceramic heat storage bodies can be made into honeycomb or spherical shapes to increase the contact area with the gas and improve the heat storage and heat exchange efficiency. The valve assembly materials should be made of high-temperature resistant and wear-resistant metals, such as chromium-molybdenum alloy steel. After installation, debugging is required to ensure that the switching valve can accurately control the flow direction of the airflow and realize the switching cycle of heating the first heat storage chamber (21) with hot mixed gas while cooling the second heat storage chamber (25) with cold air, and cooling the first heat storage chamber (21) with cold air while heating the second heat storage chamber (25). The accuracy of valve switching and the heat exchange effect can be verified by installing pressure sensors and temperature sensors in the pipeline to monitor the pressure and temperature changes of the airflow in real time.
[0028] Based on the integration of the biochar preparation device (1) and the greenhouse (7) for heating, a high-efficiency heat exchange device (2) is needed to complete the heat exchange process. The above technical solution improves heat exchange efficiency by setting up a dual heat storage chamber and valve assembly to achieve periodic heat exchange between hot mixed gas and cold air.
[0029] like Figure 2-3 As shown, in another technical solution, The first heat storage chamber (21) has a first vent (211) and a second vent (212); The second heat storage chamber (25) has a third vent (251) and a fourth vent (252); The first valve assembly includes a first inner chamber (22) and a first outer chamber (23) arranged coaxially. The first inner chamber (22) is provided with a first valve stem (24). The first valve stem (24) is provided with a first valve stem end plate (241), a first valve plate (242), a second valve plate (243), and a third valve plate (244) in sequence along the valve stem travel direction, dividing the first inner chamber (22) into independent first space (221), second space (222), third space (223), and fourth space (224). Along the valve stem travel direction, there are sequentially provided a first through hole (225), a cold air inlet (226), a first inner chamber ventilation port (227), a cold mixed gas outlet (228), and a second through hole (229). The first through hole (225) and the second through hole (229) are connected to the first outer chamber (23). The first inner chamber ventilation port (227) is connected to the first ventilation port (211). The first outer chamber (23) is provided with a first outer chamber ventilation port (231). The first outer chamber ventilation port (231) is connected to the fourth ventilation port (252). The second valve assembly includes a second inner chamber (26) and a second outer chamber (27) arranged coaxially. A second valve stem (28) is disposed inside the second inner chamber (26). Along the valve stem's travel direction, a second valve stem end plate (281), a fourth valve plate (282), a fifth valve plate (283), and a sixth valve plate (284) are sequentially disposed on the second valve stem (28), dividing the second inner chamber (26) into independent fifth space (261), sixth space (262), seventh space (263), and eighth space (264). Along the valve stem travel direction, there are sequentially provided a third through hole (265), a hot air inlet (266), a second inner chamber ventilation port (267), a hot air outlet (268), and a fourth through hole (269). The third through hole (265) and the fourth through hole (269) are connected to the second outer chamber (27). The second inner chamber ventilation port (267) is connected to the second ventilation port (212). The second outer chamber (27) is provided with a second outer chamber ventilation port (271). The first outer chamber ventilation port (231) is connected to the third ventilation port (251). When the valve is switched to the first state, that is, when the hot mixed gas heats the first heat storage chamber (21) while the cold air cools the second heat storage chamber (25), the first valve stem (24) retracts to the first position and the second valve stem (28) moves to the third position. The first through hole (225) and the cold air inlet (226) are located in the second space (222), the first inner chamber air exchange port (227) and the cold mixed gas outlet (228) are located in the third space (223), the second through hole (229) is located in the fourth space (224), the third through hole (265) is located in the fifth space (261), the hot mixed gas inlet (266) and the second inner chamber air exchange port (267) are located in the sixth space (262), and the hot air outlet (268) and the fourth through hole (269) are located in the seventh space (263). When the valve is switched to the second state, that is, when the cold air cools the first heat storage chamber (21) and the hot mixed gas heats the second heat storage chamber (25), the first valve stem (24) moves to the second position and the second valve stem (28) retracts to the fourth position. The first through hole (225) is located in the first space (221), the cold air inlet (226) and the first inner chamber ventilation port (227) are located in the second space (222), the cold mixed gas outlet (228) and the second through hole (229) are located in the third space (223), the third through hole (265) and the hot mixed gas inlet (266) are located in the sixth space (262), the second inner chamber ventilation port (267) and the hot air outlet (268) are located in the seventh space (263), and the fourth through hole (269) is located in the eighth space (264).
[0030] In the above technical solution, the connection and isolation of different spaces are realized by controlling the position of the valve stem, ensuring that the hot mixed gas and cold air can flow and exchange heat accurately under different working conditions, thus guaranteeing the reliability and stability of the system and improving the heat exchange effect.
[0031] When constructing the specific structure of the dual heat storage chambers and valve assembly, the positions of the vents in the first heat storage chamber (21) and the second heat storage chamber (25) need to be determined based on the optimal effect of gas flow and heat exchange. For example, the first vent (211) and the second vent (212) should be respectively located on opposite sides of the first heat storage chamber (21), close to the bottom and top, and the third vent (251) and the fourth vent (252) should be respectively located on opposite sides of the second heat storage chamber (25), close to the bottom and top, to promote sufficient gas flow within the chamber. During the processing of each component of the first valve assembly and the second valve assembly, dimensional accuracy must be ensured. During the assembly process, the valve plates on the first valve stem (24) and the second valve stem (28) should be installed sequentially according to the design requirements, and it should be ensured that they can move smoothly within the first inner chamber (22) and the second inner chamber (26), and that the sealing effect with the first inner chamber (22) and the second inner chamber (26) is guaranteed. The first valve stem end plate (241) and the second valve stem end plate (281) are the power ends. By pushing the first valve stem end plate (241) and the second valve stem end plate (281), the first valve stem (24) and the second valve stem (28) are moved forward. By pulling the first valve stem end plate (241) and the second valve stem end plate (281), the first valve stem (24) and the second valve stem (28) are moved back.
[0032] When the first valve stem (24) is in the first position, the first through hole (225) and the cold air inlet (226) are located in the second space (222). The cold air enters the first inner chamber (22) through the cold air inlet (226), enters the first outer chamber (23) through the first through hole (225), and enters the second heat storage chamber (25) through the first outer chamber air exchange port (231). That is, the cold air enters the second heat storage chamber (25). The first inner chamber air exchange port (227) and the cold mixed gas outlet (228) are located in the third space (223). The cold mixed gas enters the first inner chamber (22) through the first inner chamber air exchange port (227) from the first heat storage chamber (21), and is discharged and returned to the biochar preparation device (1) through the cold mixed gas outlet (228). That is, the cold mixed gas of the first heat storage chamber (21) is returned to the biochar preparation device (1). Meanwhile, when the second valve stem (28) is in the third position, the hot mixed gas inlet (266) and the second inner chamber ventilation port (267) are located in the sixth space (262). The hot mixed gas enters the second inner chamber (26) through the hot mixed gas inlet (266) and enters the first heat storage chamber (21) through the second inner chamber ventilation port (267), that is, the hot mixed gas enters the first heat storage chamber (21). The hot air outlet (268) and the fourth through hole (269) are located in the seventh space (263). The hot air enters the second outer chamber (27) through the second outer chamber ventilation port (271) from the second heat storage chamber (25), enters the second inner chamber (26) through the fourth through hole (269), and is discharged from the hot air outlet (268) to the upward air duct (5) or the downward air duct (6) to enter the greenhouse (7), that is, the hot air enters the greenhouse (7). When the valve is in the first state, the first valve stem (24) is in the first position and the second valve stem (28) is in the third position, so that the hot mixed gas heats the first heat storage chamber (21) while the cold air cools the second heat storage chamber (25).
[0033] When the first valve stem (24) is in the second position, the cold air inlet (226) and the first inner chamber ventilation port (227) are located in the second space (222). The cold air enters the first heat storage chamber through the cold air inlet (226) and the first inner chamber ventilation port (227), that is, the cold air enters the first heat storage chamber (21). The cold mixed gas outlet (228) and the second through hole (229) are located in the third space (223). The cold mixed gas enters the outer inner chamber through the first outer chamber ventilation port from the second heat storage chamber (25), enters the first inner chamber (22) through the second through hole (229), and is discharged from the cold mixed gas outlet (228) and returned to the biochar preparation device (1), that is, the cold mixed gas of the second heat storage chamber (25) is returned to the biochar preparation device (1). Meanwhile, when the second valve stem (28) is in the fourth position, the hot mixed gas inlet (266) and the third through hole (265) are located in the sixth space (262). The hot mixed gas enters the second inner chamber (26) through the hot mixed gas inlet (266), enters the second outer chamber (27) through the third through hole (265), and enters the second heat storage chamber (25) through the second outer chamber ventilation port (271). That is, the hot mixed gas enters the second heat storage chamber (25). The second inner chamber ventilation port (267) and the hot air outlet (268) are located in the seventh space (263). The hot air enters the second inner chamber (26) from the first heat storage chamber (21) through the second inner chamber ventilation port (267), and is discharged through the hot air outlet (268) to the upward air duct (5) or the downward air duct (6) to enter the greenhouse (7). That is, the hot air enters the greenhouse (7). When the valve is in the second state, the first valve stem (24) is in the second position and the second valve stem (28) is in the fourth position, so that the cold air cools the first heat storage chamber (21) and the hot mixed gas heats the second heat storage chamber (25).
[0034] After installation, the valve assembly is debugged. The process of switching the valve to the first and second states is simulated manually or with the aid of control equipment to check whether the connectivity of each space meets the design requirements. Simultaneously, tracer gas is used to test the flow path of gas in the heat storage chamber and valve assembly under different states to verify its consistency with the theoretical design. Any deviations are adjusted promptly. The above technical solution further clarifies the specific structure and operating state of the dual heat storage chamber and valve assembly, ensuring that the hot mixed gas and cold air can accurately flow and exchange heat in the heat storage chamber under different states, guaranteeing the stable operation of the system.
[0035] In another technical solution, the heat exchange device (2) further includes a purging system that uses inert gas to purge the dual heat regenerators. During the operation of the dual heat regenerators, issues such as residual gas may arise, affecting the heat exchange effect and system stability. The above technical solution solves this problem by setting up a purging system and using inert gas to purge the dual heat regenerators. Using inert gas for purging also prevents the mixing of different gases, ensuring environmental friendliness and zero pollution.
[0036] In another technical solution, the heat exchange device (2) further includes a PLC, which uses a cylinder to synchronously control the forward and backward movements of the first valve stem (24) and the second valve stem (28). When switching the valve to the first state, the first valve stem (24) retracts to the first position and the second valve stem (28) moves to the third position. When switching the valve to the second state, the first valve stem (24) moves to the second position and the second valve stem (28) retracts to the fourth position. In order to achieve accurate switching of the valve assembly, a reliable control method is required. The above technical solution uses a PLC and a cylinder to synchronously control the forward and backward movements of the valve stem, ensuring the accuracy and stability of valve switching. The automated control method reduces the error and labor intensity of manual operation, enabling the system to operate more accurately according to the set state, thereby improving the system's operating efficiency and reliability.
[0037] In another technical solution, the PLC sets the switching time and purging time. The first heat storage chamber (21) is in a heating state and the second heat storage chamber (25) is in a cooling state. When the set switching time is reached, the PLC controls the valve assembly to stop the air intake. The PLC controls the purging of inert gas. When the set purging time is reached, the PLC controls the purging system to stop running, completing the purging process. The PLC controls the valve assembly to switch valves and control the airflow direction, so that the first heat storage chamber (21) is in a cooling state and the second heat storage chamber (25) is in a heating state. In order for the system to operate automatically and orderly, the switching time and purging time need to be set reasonably. The above technical solution sets the switching time and purging time by the PLC, which can automatically perform valve switching and purging operations according to the set time, ensuring the continuity and stability of the heat exchange process, enabling the system to operate more accurately according to the set state, and improving the automation level and operating efficiency of the system.
[0038] Another technical solution also includes: Pressure sensors are arranged in the first heat storage chamber (21) and the second heat storage chamber (25) to collect the pressure in the heat storage chamber in real time. It is necessary to ensure that the installation position of the sensors will not affect the normal flow of gas and can accurately reflect the pressure change in the heat storage chamber. At least three temperature sensors are also evenly arranged along the height direction of the heat storage material, for example, every 0.5 m, to collect temperature data at different height positions in real time and calculate the temperature gradient value. The PLC continuously analyzes the collected temperature and pressure data. When the temperature gradient between adjacent temperature sensors changes by more than 5°C / m within 10 minutes, and the pressure sensor detects a pressure change in the heat storage chamber exceeding ±500 Pa within 5 minutes, the PLC determines that there may be a local blockage or gas leak in the heat storage material. At this point, the PLC immediately issues an audible and visual warning to the operator and automatically switches the heat exchange system to standby mode. In standby mode, the flow rate is reduced to 50% of the normal flow rate by adjusting the flow control valve on the intake pipe to reduce the system load, prevent further escalation of the fault, and initiate a fault diagnosis procedure, sequentially closing the valves of each intake branch, monitoring pressure and temperature changes, and locating the fault. By monitoring the temperature and pressure changes in the heat storage chamber in real time, potential problems such as local blockage or gas leaks in the heat storage material can be detected promptly, and warnings can be issued quickly to prevent further deterioration of the fault, ensuring the safety of operators and the stable operation of the equipment. Automatically switching to standby mode and reducing the intake flow rate after a fault is detected reduces the system load, prevents the fault from escalating, and reduces maintenance costs and production losses. At the same time, the troubleshooting procedure can quickly locate the fault and shorten the repair time.
[0039] In another technical solution, the PLC has dynamic switching time and purging time optimization functions: No fewer than 5 temperature sensors are installed in the greenhouse (7) to collect the greenhouse temperature in real time and calculate the rate of change of greenhouse temperature. When the average temperature of the greenhouse (7) drops by T within 1 hour a The temperature exceeds 2°C, and the average temperature T of the first heat storage chamber (21) or the second heat storage chamber (25) is T. b The value is higher than the set threshold T of the heat storage chamber. o At that time, the PLC automatically shortens the heating time t of the first heat storage chamber (21) and the second heat storage chamber (25). 减少 The following formula is used to calculate the temperature drop rate and the thermal storage capacity of biochar: t 减少 (min) = (T) a -2℃) × 10 + (T b -T o )×2 By dynamically adjusting the heating duration based on real-time data of greenhouse and heat storage chamber temperatures, overheating can be avoided, and heat energy can be applied more precisely to greenhouse warming, thereby improving energy utilization efficiency.
[0040] Gas sensors are installed in the first heat storage chamber (21) and the second heat storage chamber (25). Thermal conductivity gas sensors with an accuracy of ±5% are used. The gas sensors are connected to a gas composition analyzer, which can detect major components such as CO2, O2, and N2 with an accuracy of ±1%. If the amount of residual gas exceeds 20% of the amount vented during normal operation, and the content of harmful gas (CO) exceeds the safety threshold, the PLC will automatically extend the purging time by 5-10 minutes to ensure the purging effect while avoiding energy waste caused by over-purging. The purging time is automatically adjusted according to the gas composition detection results, which can ensure that the residual gas and harmful gas in the heat storage chamber are effectively removed, ensuring the normal operation of the system and environmental safety, while avoiding energy waste caused by over-purging.
[0041] Furthermore, a fuzzy control algorithm is introduced. The PLC takes multiple variables as inputs, including the greenhouse temperature change rate, the heat storage chamber temperature change curve (temperature data is collected and fitted at 10-minute intervals), the air intake flow rate (monitored in real time by a mass flow meter with an accuracy of ±1%), and the pressure (monitored in real time by a pressure transmitter with an accuracy of ±0.5%). Fuzzy linguistic variables are set, such as "fast," "medium," and "slow" for the greenhouse temperature change rate, and "rapid rise," "stable," and "rapid fall" for the heat storage chamber temperature change curve. Through a pre-established rule base containing no fewer than 20 fuzzy inference rules, such as when the greenhouse temperature change rate is "fast" and the heat storage chamber temperature change curve is "stable," the switching time is appropriately shortened to dynamically determine the optimal switching time and purging time. The PLC updates the fuzzy inference calculation every 15 minutes based on the latest collected data, ensuring that the system always operates at high efficiency.
[0042] 1. Determine the input and output variables. Input variables: Greenhouse temperature change rate: denoted as V The unit is ℃ / h, which reflects the rate of temperature change in the greenhouse.
[0043] Characteristics of the temperature change curve in the heat storage chamber: denoted as K The temperature change trend of the heat storage chamber was characterized by fitting and analyzing temperature data collected at 10-minute intervals.
[0044] Intake flow deviation: denoted as Δ F The difference between the actual intake airflow and the set intake airflow is expressed in m³ / h, reflecting the stability of the intake airflow.
[0045] Output variables: Switching time adjustment amount: denoted as Δ t The unit is min, and it is used to adjust the switching time between the first and second heat storage chambers.
[0046] 2. Define fuzzy linguistic variables and membership functions. Greenhouse temperature change rate: Slow (S): The membership function adopts a trapezoidal distribution. For example, when it is less than or equal to 1℃ / h, the membership degree is 1; it decreases linearly to 0 between 1-2℃ / h.
[0047] M: The membership function is triangularly distributed, ranging from 1 to 3℃ / h, with a membership of 1 at the middle point of 2℃ / h, and gradually decreasing to 0 at both ends.
[0048] Fast (F): The membership function adopts a trapezoidal distribution. When the temperature is greater than or equal to 3℃ / h, the membership degree is 1; it increases linearly to 1 between 2-3℃ / h.
[0049] Characteristics of the temperature change curve in the heat storage chamber: Rapid Rise (RU): Based on the slope of the curve fitting, when the slope is greater than a certain set value (such as 0.5℃ / 10min), the membership degree is 1; within a certain range (such as 0.3-0.5℃ / 10min), it linearly decreases to 0.
[0050] Stationary (S): The slope is between (-0.1) and 0.1℃ / 10min, and the membership degree is 1; outside this range, it decreases linearly to 0.
[0051] Rapid Decrease (RD): When the slope is less than a certain set value (e.g., -0.5℃ / 10min), the membership degree is 1; within a certain range (e.g., (-0.5) - (-0.3)℃ / 10min), it linearly increases to 1.
[0052] Intake flow deviation: Negative Large (NB): When the flow deviation is less than -10 m³ / h, the membership degree is 1; it decreases linearly to 0 between (-10) and (-5) m³ / h.
[0053] Negative small (NS): Between (-5) and 0 m³ / h, the membership function is triangularly distributed, with a membership of 1 at -2.5 m³ / h, decreasing to 0 at both ends.
[0054] Zero (Z): The flow deviation is between (-1)-1 m³ / h, and the membership degree is 1; it decreases linearly to 0 outside this range.
[0055] Positive small (PS): Between 0 and 5 m³ / h, the membership function has a triangular distribution, with a membership of 1 at 2.5 m³ / h, decreasing to 0 at both ends.
[0056] PB: When the flow deviation is greater than 10 m³ / h, the membership degree is 1; it increases linearly to 1 between 5 and 10 m³ / h.
[0057] Switching time adjustment amount: Significantly shortened (SS): when the adjustment is less than -10 min, the membership degree is 1; it decreases linearly to 0 between (-10) and (-5) min.
[0058] Shortening (S): Between (-5) and 0 min, the membership function is triangularly distributed, with a membership of 1 at -2.5 min, decreasing to 0 at both ends.
[0059] Unchanged (Z): The adjustment amount is between (-1) and 1 min, and the membership degree is 1; if it exceeds this range, it decreases linearly to 0.
[0060] Extension (L): Between 0 and 5 min, the membership function is triangularly distributed, with a membership of 1 at 2.5 min, decreasing to 0 at both ends.
[0061] Significantly extended (LL): When the adjustment is greater than 10 min, the membership degree is 1; it increases linearly to 1 between 5 and 10 min.
[0062] 3. Establish a fuzzy reasoning rule base. Based on system operation experience and actual needs, establish no fewer than 20 fuzzy inference rules, for example: If it is fast (F), stable (S), and zero (Z), then it is significantly shortened (SS).
[0063] If it is medium (M), fast rising (RU), and positive small (PS), then it is shortening (S).
[0064] If it is slow (S), decreases rapidly (RD), and is negative (NB), then it is greatly extended (LL).
[0065] By introducing fuzzy control algorithms and comprehensively considering multiple variables for dynamic reasoning and calculation, the system can automatically adjust switching time and purging time according to actual operating conditions, always maintaining a high-efficiency operating state, thus improving the system's intelligence level and adaptability.
[0066] The number of devices and processing scale described herein are for the purpose of simplifying the description of the invention. Applications, modifications, and variations of the invention will be readily apparent to those skilled in the art.
[0067] Although embodiments of the present invention have been disclosed above, they are not limited to the applications listed in the specification and embodiments. They can be applied to various fields suitable for the present invention. For those skilled in the art, other modifications can be easily made. Therefore, without departing from the general concept defined by the claims and their equivalents, the present invention is not limited to the specific details and illustrations shown and described herein.
Claims
1. A biochar heat exchange system for greenhouse heating, characterized in that, include: A pair of biochar preparation devices (1) are set at the front and rear sides of the greenhouse (7); A pair of heat exchange devices (2) are set on both sides of the outside of the greenhouse (7). One heat exchange device (2) is connected to a biochar preparation device (1) on the same side through a set of hot mixed gas pipeline (3) and cold mixed gas pipeline (4). The pair of heat exchange devices (2) are connected through a set of upward air pipeline (5) and downward air pipeline (6). The two sets of hot mixed gas pipeline (3) and cold mixed gas pipeline (4) are set outside the greenhouse (7). The set of upward air pipeline (5) and downward air pipeline (6) passes through the inside of the greenhouse (7). The hot mixed gas of the biochar preparation device (1) enters the heat exchange device (2) through the hot mixed gas pipeline (3), and after being cooled by heat exchange, it flows back to the biochar preparation device (1) through the cold mixed gas pipeline (4) for purification and recovery. The cold air after passing through the greenhouse (7) enters a heat exchange device (2) through the upward air pipeline (5), and after being heated by heat exchange, it passes through the greenhouse (7) again through the downward air pipeline (6) and enters another heat exchange device (2). Alternatively, the cold air after passing through the greenhouse (7) enters a heat exchange device (2) through the downward air pipeline (6), and after being heated by heat exchange, it passes through the greenhouse (7) again through the upward air pipeline (5) and enters another heat exchange device (2). The heat exchange device (2) includes: The dual heat storage chamber includes a first heat storage chamber (21) and a second heat storage chamber (25), the first heat storage chamber (21) and the second heat storage chamber (25) being filled with ceramic heat storage body; The valve assembly includes a first valve assembly and a second valve assembly. The valves switch to control the flow direction of the airflow, thereby achieving the switching of cycles of heating the first heat storage chamber (21) with hot mixed gas while cooling the second heat storage chamber (25) with cold air, and cooling the first heat storage chamber (21) with cold air while heating the second heat storage chamber (25). The first heat storage chamber (21) has a first vent (211) and a second vent (212); The second heat storage chamber (25) has a third vent (251) and a fourth vent (252); The purging system uses inert gas to purge the dual regenerators; Pressure sensors are arranged in the first heat storage chamber (21) and the second heat storage chamber (25) to collect the pressure in the heat storage chamber in real time. At least three temperature sensors are also evenly arranged along the height direction of the ceramic heat storage body to collect temperature data at different height positions in real time and calculate the temperature gradient value. No fewer than 5 temperature sensors are installed in the greenhouse (7) to collect the greenhouse temperature in real time and calculate the rate of change of greenhouse temperature. Gas sensors are arranged in the first heat storage chamber (21) and the second heat storage chamber (25), and the gas sensors are connected to a gas composition analyzer.
2. The biochar heat exchange system for greenhouse heating as described in claim 1, characterized in that, The first valve assembly includes a first inner chamber (22) and a first outer chamber (23) arranged coaxially. The first inner chamber (22) is provided with a first valve stem (24). The first valve stem (24) is provided with a first valve stem end plate (241), a first valve plate (242), a second valve plate (243), and a third valve plate (244) in sequence along the valve stem travel direction, dividing the first inner chamber (22) into independent first space (221), second space (222), third space (223), and fourth space (224). Along the valve stem travel direction, there are sequentially provided a first through hole (225), a cold air inlet (226), a first inner chamber ventilation port (227), a cold mixed gas outlet (228), and a second through hole (229). The first through hole (225) and the second through hole (229) are connected to the first outer chamber (23). The first inner chamber ventilation port (227) is connected to the first ventilation port (211). The first outer chamber (23) is provided with a first outer chamber ventilation port (231). The first outer chamber ventilation port (231) is connected to the fourth ventilation port (252). The second valve assembly includes a second inner chamber (26) and a second outer chamber (27) arranged coaxially. A second valve stem (28) is disposed inside the second inner chamber (26). Along the valve stem's travel direction, a second valve stem end plate (281), a fourth valve plate (282), a fifth valve plate (283), and a sixth valve plate (284) are sequentially disposed on the second valve stem (28), dividing the second inner chamber (26) into independent fifth space (261), sixth space (262), seventh space (263), and eighth space (264). Along the valve stem travel direction, there are sequentially provided a third through hole (265), a hot air inlet (266), a second inner chamber ventilation port (267), a hot air outlet (268), and a fourth through hole (269). The third through hole (265) and the fourth through hole (269) are connected to the second outer chamber (27). The second inner chamber ventilation port (267) is connected to the second ventilation port (212). The second outer chamber (27) is provided with a second outer chamber ventilation port (271). The second outer chamber ventilation port (271) is connected to the third ventilation port (251). When the valve is switched to the first state, that is, when the hot mixed gas heats the first heat storage chamber (21) while the cold air cools the second heat storage chamber (25), the first valve stem (24) retracts to the first position and the second valve stem (28) moves to the third position. The first through hole (225) and the cold air inlet (226) are located in the second space (222), the first inner chamber air exchange port (227) and the cold mixed gas outlet (228) are located in the third space (223), the second through hole (229) is located in the fourth space (224), the third through hole (265) is located in the fifth space (261), the hot mixed gas inlet (266) and the second inner chamber air exchange port (267) are located in the sixth space (262), and the hot air outlet (268) and the fourth through hole (269) are located in the seventh space (263). When the valve is switched to the second state, that is, when the cold air cools the first heat storage chamber (21) and the hot mixed gas heats the second heat storage chamber (25), the first valve stem (24) moves to the second position and the second valve stem (28) retracts to the fourth position. The first through hole (225) is located in the first space, the cold air inlet (226) and the first inner chamber ventilation port (227) are located in the second space, the cold mixed gas outlet (228) and the second through hole (229) are located in the third space, the third through hole (265) and the hot mixed gas inlet (266) are located in the sixth space (262), the second inner chamber ventilation port (267) and the hot air outlet (268) are located in the seventh space (263), and the fourth through hole (269) is located in the eighth space (264).
Citation Information
Patent Citations
Automatic fuel gas heating device using air as carrier
CN203692069U
Environment-friendly and energy-saving type heat preservation and temperature compensation seedbed
CN218302528U