Mounting and fixing device and mounting method for prefabricated bay window

By pre-embedding the sleeves and connecting the pull-up rings in the prefabricated bay window and the prefabricated laminated plate, the problem of prefabricated bay window lifting is solved, precise positioning and rapid installation are achieved, and construction risks and costs are reduced.

CN120331608APending Publication Date: 2025-07-18CHINA CONSTR TECH GRP SOUTH CHINA CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202510702155.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2025-05-28
Publication Date
2025-07-18

AI Technical Summary

Technical Problem

In the prior art, prefabricated bay windows are prone to deviate during lifting, resulting in inaccurate installation, increasing construction risks and later repair costs, and it is impossible to avoid overturning of prefabricated bay windows.

Method used

Using an installation fixing device including a first embedded sleeve, a second embedded sleeve and an adjustable length pull rod, precise positioning and fixing are achieved by embedding the sleeve in the prefabricated bay window and the prefabricated stacking plate and connecting the pull ring.

Benefits of technology

The precise positioning and rapid installation of prefabricated bay windows is achieved, which reduces the risk of position deviation, improves the convenience and firmness of the connection, avoids the risk of overturning, and reduces the later repair work and costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN120331608A_ABST
    Figure CN120331608A_ABST
Patent Text Reader

Abstract

The invention discloses a mounting and fixing device and a mounting method for a prefabricated bay window. The mounting and fixing device comprises a first pre-embedded sleeve, a second pre-embedded sleeve and a length-adjustable pull rod, the first pre-buried sleeve is pre-buried in the prefabricated bay window, the second pre-buried sleeve is pre-buried in the prefabricated laminated slab, pull rings are fixed to the first pre-buried sleeve and the second pre-buried sleeve through connecting bolts respectively, the two ends of the pull rod are connected with the pull rings at the two ends through pin shafts respectively, and the pull rings at the two ends are connected with the first pre-buried sleeve and the second pre-buried sleeve respectively. When the device is used for installing the prefabricated bay-window, the position of the prefabricated bay-window can be adjusted through the pull rod when the axis of the prefabricated bay-window is positioned, so that precise positioning is guaranteed, the phenomenon of deviation is not prone to occurring after fixing, rapid installation can be achieved, the convenience and firmness of connection are improved, and the quality of the prefabricated bay-window after installation is guaranteed; the prefabricated bay window is prevented from overturning after being hoisted and before concrete is poured, and the safety risk of site construction is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of prefabricated building construction, and particularly relates to an installation and fixing device and an installation method for a precast bay window. Background Technique

[0002] At present, in prefabricated buildings, precast bay windows are generally connected and fixed by embedded pull rings. Since the pull rings are extremely prone to displacement during the concrete pouring process, it is impossible to ensure reasonable pull nodes after the precast bay window is hoisted. When tying steel bars and performing other construction operations on the precast bay window, it is extremely easy to cause the precast bay window to shake, resulting in displacement and the risk of overturning of the precast bay window. Pouring the concrete of the upper floor slab will also cause disturbance to the precast bay window. At this time, the precast bay window cannot be adjusted again, and only the precast bay window can be chiseled and repaired later, which will consume huge repair costs, and the chiseling also affects the integrity of the precast bay window structure. Summary of the Invention

[0003] The purpose of the invention is to provide an installation and fixing device and an installation method for a precast bay window, which can connect and fix the precast bay window after hoisting, and the positioning is accurate without deviation; avoid the workload of secondary cutting of the embedded pull rings in the later stage, greatly reduce the risk of overturning of the precast bay window, and ensure the installation quality of the precast bay window.

[0004] To achieve the above invention purpose, the invention provides an installation and fixing device for a precast bay window, including a first embedded sleeve, a second embedded sleeve and a pull rod that can adjust its own length; the first embedded sleeve is embedded in the precast bay window, the second embedded sleeve is embedded in the precast composite slab, a first pull ring is connected to the first embedded sleeve, a second pull ring is connected to the second embedded sleeve, and both ends of the pull rod are respectively connected to the first pull ring and the second pull ring through pin shafts.

[0005] In some implementation manners, the pull rod includes a diagonal bracing member, a first internal thread sleeve and a second internal thread sleeve. External threads are provided at both ends of the diagonal bracing member, and one end of the first internal thread sleeve and one end of the second internal thread sleeve are respectively threadedly connected to both ends of the diagonal bracing member; the other end of the first internal thread sleeve and the other end of the second internal thread sleeve are respectively connected to the first pull ring and the second pull ring through pin shafts.

[0006] In some implementation manners, both the first pull ring and the second pull ring are double-ear pull rings.

[0007] In some implementation manners, the first embedded sleeve is fixedly connected to the first pull ring through a first connection assembly. The first connection assembly includes a first connection bolt, a first baffle, a first U-shaped connecting piece, and a first fixing piece. The open end of the first U-shaped connecting piece is fixed on the first baffle. The first connection bolt passes through the first baffle and is threadedly connected to the first embedded sleeve, thereby fixing the first baffle on the precast bay window. The first fixing piece is clamped between the head of the first connection bolt and the first baffle.

[0008] In some implementation manners, the second embedded sleeve is fixedly connected to the second pull ring through a second connection assembly. The second connection assembly includes a second connection bolt, a second baffle, a second U-shaped connecting piece, and a second fixing piece. The open end of the second U-shaped connecting piece is fixed on the second baffle. The second connection bolt passes through the second baffle and is threadedly connected to the second embedded sleeve, thereby fixing the second baffle on the precast bay window. The second fixing piece is clamped between the head of the second connection bolt and the second baffle.

[0009] In some implementation manners, the second embedded sleeve is fixedly connected to the additional steel bars in the precast composite slab.

[0010] To achieve the above-mentioned invention purpose, the present invention also provides a method for installing and fixing a precast bay window by using the above-mentioned installation and fixing device. The method includes the following steps:

[0011] Through the deepening of the design drawings, the embedded positions of the first embedded sleeve and the second embedded sleeve are respectively marked in the precast bay window component drawings and the precast composite slab component drawings. The precast processing factory manufactures the precast bay window and the precast composite slab according to the deepened design drawings.

[0012] Transport the precast components of the standard floor to the construction site. After the hoisting of the precast composite slab and the casting of the shear wall on the current floor are completed and the concrete curing reaches the required strength, hoist the precast bay window on the current floor.

[0013] First, adjust the elevation and check the installation position. Subsequently, install and fix the precast bay window. Connect one end of the pull rod to the first embedded sleeve buried in the precast bay window, and connect the other end of the pull rod to the second embedded sleeve buried in the precast composite slab.

[0014] Then, tighten the pull rod by adjusting the pull rod to firmly tie the precast bay window and the precast composite slab into a whole, thus completing the installation and fixing of the precast bay window.

[0015] Compared with the prior art, the beneficial effects of the present invention are as follows:

[0016] By using the installation and fixing device and installation method provided by the present invention, it is possible to adjust the position of the precast bay window during the axis positioning by using a pull rod with adjustable length to ensure the fine decoration positioning, and it is not easy to deviate after fixation, which can achieve rapid installation, improve the convenience and firmness of connection, and ensure the quality of the precast bay window after installation; it avoids the overturning of the precast bay window before pouring concrete after hoisting, reducing the on-site construction safety risk. Moreover, both the pull rod and the pull ring can be disassembled and reused after the construction of this layer is completed, reducing the cost of fixing the precast bay window and greatly reducing the workload of manually cutting off the embedded pull ring in the later stage. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] Figure 1 FIG. 6 is a schematic structural diagram of a precast bay window embedded with an embedded sleeve provided by an embodiment of the present invention;

[0018] Figure 2 FIG. 10 is a schematic structural diagram of a precast composite slab embedded with an embedded sleeve provided by an embodiment of the present invention;

[0019] Figure 3 FIG. 14 is Figure 2 a cross-sectional view of the position where the embedded sleeve is embedded in the precast composite slab shown in FIG. 15;

[0020] Figure 4 FIG. 20 is a schematic structural diagram of the precast bay window after installation provided by an embodiment of the present invention;

[0021] Figure 5 FIG. 24 is a schematic connection structural diagram of a pull rod, a connection component and a pull ring provided by an embodiment of the present invention;

[0022] Figure 6 FIG. 28 is a schematic diagram of installing a precast bay window by using the installation and fixing device provided by an embodiment of the present invention.

[0023] ILLUSTRATION DESCRIPTION:

[0024] The first embedded sleeve 10, the second embedded sleeve 20, the pull rod 30, the diagonal bracing member 31, the first internal thread sleeve 32, the second internal thread sleeve 33, the first pull ring 41, the second pull ring 42, the pin shaft 50, the first connecting bolt 51, the first baffle 52, the first U-shaped connecting member 53, the first fixing piece 54, the precast bay window 100, the precast composite slab 200, the additional steel bar 201. DETAILED DESCRIPTION OF THE EMBODIMENTS

[0025] In order to make the objectives, features, and advantages of the present invention more obvious and understandable, the following will clearly and completely describe the technical solutions in the embodiments of the present invention in conjunction with the accompanying drawings in the embodiments of the present invention. Obviously, the embodiments described below are only a part of the embodiments of the present invention, rather than all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those of ordinary skill in the art without creative efforts shall fall within the protection scope of the present invention.

[0026] In the description of the present invention, it should be noted that the orientation or positional relationship indicated by the terms "center", "upper", "lower", "left", "right", "front", "rear", "vertical", "horizontal", "inner", "outer", etc. is based on the orientation or positional relationship shown in the accompanying drawings. It is only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and thus should not be construed as a limitation to the present invention; the terms "first", "second", "third" are only used for descriptive purposes and cannot be understood as indicating or implying relative importance; in addition, unless otherwise clearly defined and limited, the terms "installed", "connected", "connected" should be understood in a broad sense. For example, it can be a fixed connection, a detachable connection, or an integral connection; it can be directly connected, or indirectly connected through an intermediate medium, and it can be the communication inside two components. For those of ordinary skill in the art, the specific meanings of the above terms in the present invention can be understood according to specific situations.

[0027] The following further illustrates the technical solutions of the present invention in conjunction with the accompanying drawings and through specific implementation manners.

[0028] Please refer to Figures 1 to 4 , this embodiment provides an installation and fixing device for a precast bay window, including a first embedded sleeve 10, a second embedded sleeve 20, and a pull rod 30 that can adjust its own length; the first embedded sleeve 10 is embedded in the precast bay window 100, the second embedded sleeve 20 is embedded in the precast composite slab 200, a first pull ring 41 is fixedly connected to the first embedded sleeve 10, a second pull ring 42 is fixedly connected to the second embedded sleeve 20, and both ends of the pull rod 30 are respectively connected to the first pull ring 41 and the second pull ring 42 through a pin shaft 50.

[0029] Specifically, please refer to Figure 5 , the pull rod 30 of this embodiment includes a diagonal strut member 31, a first internal thread sleeve 32, and a second internal thread sleeve 33. External threads are provided at both ends of the diagonal strut member 31, and one end of the first internal thread sleeve 32 and one end of the second internal thread sleeve 33 are respectively threadedly connected to both ends of the diagonal strut member 31; the other end of the first internal thread sleeve 32 and the other end of the second internal thread sleeve 33 are respectively connected to the first pull ring 41 and the second pull ring 42 through a pin shaft 50.

[0030] In this embodiment, both the first pull ring 41 and the second pull ring 42 are double-ear pull rings.

[0031] Furthermore, the first embedded sleeve 10 of this embodiment is fixedly connected to the first pull ring 41 through a first connection assembly, and the second embedded sleeve 20 is fixedly connected to the second pull ring 42 through a second connection assembly. Preferably, the first connection assembly of this embodiment includes a first connection bolt 51, a first baffle 52, a first U-shaped connecting piece 53, and a first fixing piece 54; the open end of the first U-shaped connecting piece 53 is fixed on the first baffle 52, the first connection bolt 51 passes through the first baffle 52 and is threadedly connected to the first embedded sleeve 10, thereby fixing the first baffle 52 on the precast bay window 100, the first fixing piece 54 is clamped between the head of the first connection bolt 51 and the first baffle 52, and the first pull ring 41 is buckled into the inner ring of the first U-shaped connecting piece 53 to achieve detachable connection. Similarly, the second connection assembly includes a second connection bolt 55, a second baffle, a second U-shaped connecting piece, and a second fixing piece; the open end of the second U-shaped connecting piece is fixed on the second baffle, the second connection bolt 55 passes through the second baffle and is threadedly connected to the second embedded sleeve, thereby fixing the second baffle on the precast bay window, the second fixing piece is clamped between the head of the second connection bolt 55 and the second baffle, and the second pull ring 42 is buckled into the inner ring of the second U-shaped connecting piece to achieve detachable connection.

[0032] Furthermore, in order to strengthen the connection strength between the second embedded sleeve 20 and the precast composite slab 200, the second embedded sleeve 20 of this embodiment is fixedly connected to the additional steel bar 201 in the precast composite slab 200.

[0033] Please refer to Figure 6 , based on the above installation and fixing device, this embodiment provides a method for installing a precast bay window, and this method includes the following steps:

[0034] Through the deepening of the design drawings, mark the embedded positions of the first embedded sleeve 10 and the second embedded sleeve 20 in the precast bay window component drawings and the precast composite slab component drawings respectively, and the precast processing factory manufactures the precast bay window 100 and the precast composite slab 200 according to the deepened design drawings;

[0035] Transport the precast components of the standard floor to the construction site. After the precast composite slab 200 of the current floor is hoisted and the shear wall is poured, and the concrete curing reaches the required strength, hoist the precast bay window 100 of the current floor;

[0036] First, adjust the elevation and check the installation position, and then install and fix the precast bay window 100. Connect one end of the pull rod 30 to the first embedded sleeve 10 buried in the precast bay window 100, and connect the other end of the pull rod 30 to the second embedded sleeve 20 buried in the precast composite slab 200;

[0037] Then, by adjusting the pull rod 30 and tightening the pull rod 30, the precast bay window 100 and the precast composite slab 200 are firmly tied together as a whole, that is, the installation and fixation of the precast bay window 100 are completed.

[0038] By using the installation and fixation device and the installation method provided in this embodiment, the position of the precast bay window 100 can be adjusted by the pull rod 30 with adjustable length during the axis positioning of the precast bay window 100 to ensure fine decoration positioning. Moreover, after fixation, it is not easy to deviate, and rapid installation can be realized, improving the convenience and firmness of connection, and ensuring the quality of the precast bay window 100 after installation; the overturning of the precast bay window 100 before pouring concrete after hoisting is avoided, reducing the on-site construction safety risk. In addition, both the pull rod and the pull ring can be disassembled and recycled after the construction of this layer is completed, reducing the cost of fixing the precast bay window 100 and greatly reducing the workload of manually cutting off the embedded pull ring in the later stage.

[0039] The above are only the preferred embodiments of the present invention and are not intended to limit the present invention. Any modifications, equivalent replacements, improvements, etc. made within the spirit and principle of the present invention shall be included within the protection scope of the present invention.

Claims

1. An installation and fixing device for a prefabricated bay window, characterized in that, It includes a first embedded sleeve, a second embedded sleeve and a tie rod whose length can be adjusted by itself; the first embedded sleeve is embedded in the precast bay window, the second embedded sleeve is embedded in the precast composite slab, a first pull ring is connected to the first embedded sleeve, a second pull ring is connected to the second embedded sleeve, and both ends of the tie rod are respectively connected to the first pull ring and the second pull ring through pin shafts.

2. The installation and fixing device according to claim 1, characterized in that, The tie rod includes a diagonal bracing member, a first internal thread sleeve and a second internal thread sleeve. External threads are provided at both ends of the diagonal bracing member. One end of the first internal thread sleeve and one end of the second internal thread sleeve are respectively threadedly connected to both ends of the diagonal bracing member; the other end of the first internal thread sleeve and the other end of the second internal thread sleeve are respectively connected to the first pull ring and the second pull ring through pin shafts.

3. The installation and fixing device according to claim 1, characterized in that Both the first pull ring and the second pull ring are double-ear pull rings.

4. The mounting and fixing device according to claim 2, characterized in that The first embedded sleeve is fixedly connected to the first pull ring through a first connection assembly. The first connection assembly includes a first connection bolt, a first baffle, a first U-shaped connecting piece and a first fixing piece; the open end of the first U-shaped connecting piece is fixed on the first baffle, the first connection bolt passes through the first baffle and is threadedly connected to the first embedded sleeve, thereby fixing the first baffle on the precast bay window, and the first fixing piece is clamped between the head of the first connection bolt and the first baffle.

5. The installation and fixing device according to claim 4, wherein The second embedded sleeve is fixedly connected to the second pull ring through a second connection assembly. The second connection assembly includes a second connection bolt, a second baffle, a second U-shaped connecting piece and a second fixing piece; the open end of the second U-shaped connecting piece is fixed on the second baffle, the second connection bolt passes through the second baffle and is threadedly connected to the second embedded sleeve, thereby fixing the second baffle on the precast bay window, and the second fixing piece is clamped between the head of the second connection bolt and the second baffle.

6. The mounting and fixing device according to claim 1, characterized in that, The second embedded sleeve is fixedly connected to the additional steel bars in the precast composite slab.

7. A method for installing a prefabricated bay window using the installation and fixing device according to any one of claims 1 to 6, characterized in that, The method includes the following steps: Through the deepening of the design drawings, mark the embedded positions of the first embedded sleeve and the second embedded sleeve in the precast bay window component drawing and the precast composite slab component drawing respectively. The precast processing factory manufactures the precast bay window and the precast composite slab according to the deepened design drawings. Transport the precast components of the standard floor to the construction site. After the hoisting of the precast composite slab and the casting of the shear wall on the current floor are completed and the concrete curing reaches the required strength, hoist the precast bay window on the current floor. First adjust the elevation and check the installation position, and then install and fix the precast bay window. Connect and fix one end of the tie rod to the first embedded sleeve buried in the precast bay window, and connect and fix the other end of the tie rod to the second embedded sleeve buried in the precast composite slab. Then, by adjusting the tie rod, tighten the tie rod to firmly connect the precast bay window and the precast composite slab into a whole, that is, complete the installation and fixation of the precast bay window.