Method and device for determining project change degree of power transmission line

By obtaining and comparing the first geographical information and environmental impact assessment geographic information of transmission line projects, quantifying the degree of change, the problem of acceptance failure caused by changes in transmission line projects is solved, accurate quantification and intelligent early warning are achieved, project risks are reduced, and scientific decision-making is supported.

CN120337466AActive Publication Date: 2025-07-18INNER MONGOLIA ELECTRIC POWER SURVEY & DESIGN INST
View PDF 3 Cites 0 Cited by

Patent Information

Application Number
CN202510418411.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2025-04-03
Publication Date
2025-07-18
Estimated Expiration
2045-04-03

AI Technical Summary

Technical Problem

During the process of increasing the design depth and optimizing the existing transmission line project, the actual construction path and the path plan for the environmental impact assessment stage of the project have undergone major changes, resulting in the project being unable to pass the completed environmental protection acceptance.

Method used

By obtaining the first geographical information of the transmission line project and the geographical information of the environmental impact assessment, the change information is determined, including path length changes, lateral displacement over-limit accumulation, the proportion of new sensitive targets added, and the invasion status of ecologically sensitive areas, quantifying the degree of change, and setting a warning range of 25%-30% to achieve accurate quantification and intelligent early warning of the degree of change.

Benefits of technology

It has achieved accurate quantification of the degree of change in transmission lines, avoided problems found in the acceptance stage, allowed fine adjustments within a reasonable range of technology, reduced unnecessary environmental assessment needs, reduced engineering risks, ensured that the red line of regulations is not crossed, and supported scientific decision-making.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN120337466A_ABST
    Figure CN120337466A_ABST
Patent Text Reader

Abstract

The invention provides a power transmission line project change degree determination method and device, and the method comprises the steps: obtaining first geographic information of a power transmission line project and second geographic information of a power transmission line project environmental assessment; determining change information between the first geographic information and the second geographic information according to the first geographic information and the second geographic information; and determining the project change degree of the power transmission line according to the change information. The power transmission line engineering change degree can be determined, and accurate quantification and intelligent early warning of the power transmission line change degree are achieved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of transmission line engineering, and particularly to a method and device for determining the degree of change of a transmission line project. Background Art

[0002] With the increase in the design depth, design optimization, and other restrictive factors for route selection in existing transmission line projects, the actual construction path plan of the transmission line significantly changes from the path plan in the project environmental impact assessment (EIA) stage, resulting in major changes to the project. During the completion environmental protection acceptance of the project, due to the significant changes in the transmission line plan, the project fails to pass the completion environmental protection acceptance. Summary of the Invention

[0003] The technical problem to be solved by the present invention is to provide a method and device for determining the degree of change of a transmission line project, which can determine the degree of change of the transmission line project and achieve accurate quantification and intelligent early warning of the degree of change of the transmission line.

[0004] To solve the above technical problem, the technical solution of the present invention is as follows:

[0005] A method for determining the degree of change of a transmission line project includes:

[0006] Obtain the first geographical information of the transmission line project and the second geographical information of the transmission line project EIA;

[0007] Determine the change information between the first geographical information and the second geographical information according to the first geographical information and the second geographical information;

[0008] Determine the degree of change of the transmission line project according to the change information.

[0009] Optionally, the obtaining of the first geographical information of the transmission line project includes:

[0010] Obtain the first path coordinates, the names of the first electromagnetic and noise sensitive points, the names of the first nature reserves, scenic spots, and drinking water source protection areas along the line in the construction drawing stage of the transmission line project.

[0011] Optionally, the obtaining of the second geographical information of the transmission line project EIA includes:

[0012] Obtain the second path coordinates, the names of the second electromagnetic and noise sensitive points, the names of the second nature reserves, scenic spots, and drinking water source protection areas along the line in the EIA stage of the transmission line project.

[0013] Optionally, the determining of the change information between the first geographical information and the second geographical information according to the first geographical information and the second geographical information includes:

[0014] Determine the first change range of the increase in the path length in the construction drawing stage compared to the environmental impact assessment stage based on the first path coordinates and the second path coordinates;

[0015] Determine the second change range of the cumulative length of the lateral displacement of the line in the construction drawing stage exceeding the set value compared to the environmental impact assessment stage based on the first path coordinates and the second path coordinates;

[0016] Determine the third change range of the newly added electromagnetic and acoustic environment sensitive targets in the construction drawing stage compared to the environmental impact assessment stage based on the first electromagnetic and noise sensitive point names and the second electromagnetic and noise sensitive point names;

[0017] Determine the fourth change situation of the ecological sensitive areas of nature reserves, scenic spots, and drinking water source protection areas along the line in the construction drawing stage compared to the environmental impact assessment stage based on the first names of ecological sensitive areas of nature reserves, scenic spots, and drinking water source protection areas along the line and the second names of ecological sensitive areas of nature reserves, scenic spots, and drinking water source protection areas along the line;

[0018] Determine the change information based on the relationships between the first change range and the first set interval, the second change range and the second set interval, the third change range and the third set interval, and the fourth change situation and the fourth set situation.

[0019] Optionally, the determining the change information based on the relationships between the first change range and the first set interval, the second change range and the second set interval, the third change range and the third set interval, and the fourth change situation and the fourth set situation includes:

[0020] If any one of the conditions that the first change range exceeds the first set interval, the second change range exceeds the second set interval, the third change range exceeds the third set interval, and the fourth change situation meets the fourth set situation is satisfied, determine that the change information is a major change;

[0021] If any one of the conditions that the first change range meets the first set interval, the second change range meets the second set interval, and the third change range meets the third set interval is satisfied, determine that the change information is a major change warning;

[0022] If the three conditions that the first change range is less than the first set interval, the second change range is less than the second set interval, and the third change range is less than the third set interval are satisfied, determine that the change information is an allowable change.

[0023] Optionally, the first change range is the proportion of the increase in the path length in the construction drawing stage compared to the environmental impact assessment stage to the path length in the environmental impact assessment stage;

[0024] The second change range is the ratio of the cumulative length by which the lateral displacement of the line in the construction drawing stage exceeds the set value compared to the path length in the environmental impact assessment stage, to the path length in the environmental impact assessment stage;

[0025] The third change range is the ratio of the newly added electromagnetic and acoustic environment sensitive targets in the construction drawing stage compared to the environmental impact assessment stage, to the number of electromagnetic and acoustic environment sensitive targets in the environmental impact assessment stage;

[0026] The fourth change situation is whether there are newly added ecological sensitive areas such as nature reserves, scenic spots, and drinking water source protection areas along the line in the construction drawing stage compared to the environmental impact assessment stage.

[0027] Optionally, determining the degree of change of the transmission line project according to the change information includes:

[0028] Determining that the degree of change of the transmission line project is a major change, a major change warning, or a permitted change according to the change information.

[0029] The present invention also provides a device for determining the degree of change of a transmission line project, including:

[0030] An acquisition module, configured to acquire the first geographic information of the transmission line project and the second geographic information of the environmental impact assessment of the transmission line project;

[0031] A processing module, configured to establish a three-dimensional real scene model according to the first geographic information and the second geographic information; determine the change information between the first geographic information and the second geographic information according to the three-dimensional real scene model; and determine the degree of change of the transmission line project according to the change information.

[0032] The present invention also provides a computing device, including: a processor and a memory storing a computer program, and when the computer program is run by the processor, the method described above is executed.

[0033] The present invention also provides a computer-readable storage medium, storing instructions, and when the instructions are run on a computer, the computer is made to execute the method described above.

[0034] The above solution of the present invention has at least the following beneficial effects:

[0035] In the above solution of the present invention, the present invention comprehensively quantifies the degree of change through four-dimensional indicators of the path length change rate, the cumulative proportion of transverse displacement exceeding the limit, the new proportion of sensitive targets, and the intrusion status of the ecological sensitive area. The post-completion inspection is advanced to the construction drawing stage to avoid problems being discovered only at the acceptance stage. A warning range of 25%-30% is set to allow fine-tuning of the path within a reasonable technical range, reducing the unnecessary need for environmental impact assessment changes. The direct triggering of a major change warning for a newly added ecological sensitive area ensures that the legal red line cannot be crossed. Shifting from passive rectification to active optimization significantly reduces project risks. The combination of quantitative indicators and elastic thresholds supports scientific decision-making and reduces human misjudgment. The automated process of warning → optimization → release realizes an efficient closed-loop for change control. BRIEF DESCRIPTION OF THE DRAWINGS

[0036] Figure 1 is a flowchart of a method for determining the degree of change in a transmission line project of the present invention;

[0037] Figure 2 is a specific implementation process diagram of a method for determining the degree of change in a transmission line project of the present invention;

[0038] Figure 3 is a schematic diagram of the modules of a device for determining the degree of change in a transmission line project of the present invention. DETAILED DESCRIPTION OF THE EMBODIMENTS

[0039] Hereinafter, exemplary embodiments of the present invention will be described in more detail with reference to the accompanying drawings. Although the exemplary embodiments of the present invention are shown in the drawings, it should be understood that the present invention can be implemented in various forms and should not be limited by the embodiments set forth herein. On the contrary, these embodiments are provided so that the present invention can be more thoroughly understood and the scope of the present invention can be fully conveyed to those skilled in the art.

[0040] As Figure 1 shown, an embodiment of the present invention provides a method for determining the degree of change in a transmission line project, including:

[0041] Step 11, obtaining the first geographic information of the transmission line project and the second geographic information of the environmental impact assessment of the transmission line project;

[0042] Step 12, determining the change information between the first geographic information and the second geographic information according to the first geographic information and the second geographic information;

[0043] Step 13, determining the degree of change in the transmission line project according to the change information.

[0044] By comparing the first geographic information and the second geographic information, the present invention determines the degree of change in the transmission line project, realizes the accurate quantification and intelligent warning of the degree of change in the transmission line, and significantly improves the project compliance and economy.

[0045] Specifically, in step 11, the obtaining of the first geographical information of the transmission line project includes:

[0046] Obtaining the first path coordinates, the names of the first electromagnetic and noise sensitive points, the names of the first nature reserves, scenic spots, and ecological sensitive areas of drinking water source protection areas along the line during the construction drawing stage of the transmission line project.

[0047] In step 11, the obtaining of the second geographical information of the environmental impact assessment of the transmission line project includes:

[0048] Obtaining the second path coordinates, the names of the second electromagnetic and noise sensitive points, the names of the second nature reserves, scenic spots, and ecological sensitive areas of drinking water source protection areas along the line during the environmental impact assessment stage of the transmission line project.

[0049] In an optional embodiment of the present invention, in step 12, the determining of the change information between the first geographical information and the second geographical information according to the first geographical information and the second geographical information includes:

[0050] Step 121, determining the first change amplitude of the path length in the construction drawing stage compared with that in the environmental impact assessment stage according to the first path coordinates and the second path coordinates;

[0051] Step 122, determining the second change amplitude of the cumulative length of the lateral displacement of the line in the construction drawing stage exceeding the set value compared with that in the environmental impact assessment stage according to the first path coordinates and the second path coordinates;

[0052] Step 123, determining the third change amplitude of the newly added electromagnetic and acoustic environment sensitive targets in the construction drawing stage compared with that in the environmental impact assessment stage according to the names of the first electromagnetic and noise sensitive points and the names of the second electromagnetic and noise sensitive points;

[0053] Step 124, determining the fourth change situation of the ecological sensitive areas of nature reserves, scenic spots, and drinking water source protection areas along the line in the construction drawing stage compared with that in the environmental impact assessment stage according to the names of the first ecological sensitive areas of nature reserves, scenic spots, and drinking water source protection areas along the line and the names of the second ecological sensitive areas of nature reserves, scenic spots, and drinking water source protection areas along the line;

[0054] Step 125, determining the change information according to the relationships between the first change amplitude and the first set interval, the second change amplitude and the second set interval, the third change amplitude and the third set interval, and the fourth change situation and the fourth set situation.

[0055] In this embodiment, by quantifying the increase in path length (the first change range), the impact degree of the change in project scale on the environment can be intuitively reflected. The analysis of the cumulative length of lateral displacement (the second change range) can accurately identify the key sections where the construction line deviates from the environmental impact assessment design. The identification of newly added sensitive targets (the third change range) realizes the dynamic tracking of electromagnetic / noise sensitive points, and can timely discover the problems missed in the environmental impact assessment. The analysis of the changes in ecological sensitive areas (the fourth change situation) ensures the synchronous update of protection measures for special areas such as nature reserves, and avoids ecological damage. Through multi-dimensional data fusion analysis, the quantitative evaluation and intelligent determination of engineering design changes are realized.

[0056] In an alternative embodiment of the present invention, in step 125, the determining of the change information according to the relationships between the first change range and the first set interval, the second change range and the second set interval, the third change range and the third set interval, and the fourth change situation and the fourth set situation includes:

[0057] Step 1251, if any one of the conditions that the first change range exceeds the first set interval, the second change range exceeds the second set interval, the third change range exceeds the third set interval, and the fourth change situation conforms to the fourth set situation is satisfied, determine that the change information is a major change;

[0058] Step 1252, if any one of the conditions that the first change range conforms to the first set interval, the second change range conforms to the second set interval, and the third change range conforms to the third set interval is satisfied, determine that the change information is a major change warning;

[0059] Step 1253, if the three conditions that the first change range is less than the first set interval, the second change range is less than the second set interval, and the third change range is less than the third set interval are satisfied, determine that the change information is an allowable change.

[0060] Specifically, the first change range is the ratio of the increase in the path length in the construction drawing stage compared to the path length in the environmental impact assessment stage to the path length in the environmental impact assessment stage;

[0061] The second change range is the ratio of the cumulative length of the lateral displacement of the line in the construction drawing stage exceeding the set value compared to the path length in the environmental impact assessment stage to the path length in the environmental impact assessment stage;

[0062] The third change range is the ratio of the newly added electromagnetic and acoustic environment sensitive targets in the construction drawing stage compared to the environmental impact assessment stage to the number of electromagnetic and acoustic environment sensitive targets in the environmental impact assessment stage;

[0063] The fourth change situation is whether there are newly added ecological sensitive areas such as nature reserves, scenic spots, and drinking water source protection areas along the line in the construction drawing stage compared to the environmental impact assessment stage.

[0064] The first set interval is 25%-30%, the second set interval is 25%-30%, the third set interval is 25%-30%, and the fourth set condition is that there are newly added ecological sensitive areas such as natural protection areas, scenic spots, and drinking water source protection areas along the line during the construction drawing stage compared with the environmental impact assessment stage.

[0065] In this embodiment, if any change index exceeds the limit (the path length exceeds 30%, the cumulative horizontal displacement exceeds 30%, the number of newly added sensitive points exceeds 30%, or a new ecological sensitive area is added), it is determined as a major change. This avoids the situation where a single index fails to meet the standard but other indicators seriously exceed the standard being missed. The addition of a new ecological sensitive area directly triggers a major change to ensure that the legal red line cannot be crossed. When any change index is between 25% and 30%, a warning is triggered. The design unit is allowed to fine-tune the path within a reasonable technical range to avoid unnecessary optimization costs caused by a "one-size-fits-all" approach. If all change indicators are less than 25% and there are no newly added sensitive areas, it is determined as an allowable change. This quickly releases low-risk projects and shortens the approval cycle.

[0066] Specifically, determining the proportion (the second change amplitude) of the cumulative length of the horizontal displacement of the line in the construction drawing stage compared with the environmental impact assessment stage that exceeds the set value includes:

[0067] According to Determine the horizontal displacement of the line in the construction drawing stage compared with the line in the environmental impact assessment stage,

[0068] where L i is the horizontal displacement between the line in the construction drawing stage and the line in the environmental impact assessment stage, (x i , y i ) are the coordinates of each point on the line in the construction drawing stage, (m i , n i ) are the coordinates of each point on the line in the environmental impact assessment stage, and i is the index value of each point, i = 1, 2, 3,..., n;

[0069] According to Determine the cumulative length of the horizontal displacement of the line in the construction drawing stage compared with the line in the environmental impact assessment stage that exceeds the set value,

[0070] where ∑L 超 is the cumulative length of the horizontal displacement of the line in the construction drawing stage compared with the line in the environmental impact assessment stage that exceeds the set value, L i is the horizontal displacement between the line in the construction drawing stage and the line in the environmental impact assessment stage, L 阈 is the set value (specifically, 500m can be taken), and i is the index value of each point, i = 1, 2, 3,..., n;

[0071] According to Determine the proportion (the second change range) of the cumulative length of the lateral displacement of the line in the construction drawing stage exceeding the set value to the path length in the environmental impact assessment stage,

[0072] where P is the proportion (the second change range) of the cumulative length of the lateral displacement of the line in the construction drawing stage exceeding the set value to the path length in the environmental impact assessment stage, and ∑L 超 is the cumulative length of the lateral displacement of the line in the construction drawing stage exceeding the set value compared to the line in the environmental impact assessment stage, and L 环总长 is the path length in the environmental impact assessment stage.

[0073] In this embodiment, the second change range provides a scientific and efficient environmental compliance assessment tool for the transmission line project by quantifying the cumulative impact of excessive lateral displacement. Its synergistic effect with other indicators.

[0074] In an optional embodiment of the present invention, in step 13, the determining the degree of change of the transmission line project according to the change information includes:

[0075] Step 131, determine that the degree of change of the transmission line project is a major change, a major change warning, or an allowable change according to the change information.

[0076] When the degree of change of the transmission line project is a major change, a warning shall be given to the construction drawing path plan. The construction unit shall feedback the result to the design unit, and the design unit shall optimize the line path in the construction drawing design stage and conduct a comprehensive study with the construction unit from aspects such as technology, environmental protection, economy, and restrictive factors to determine the final construction path plan.

[0077] When the degree of change of the transmission line project is a major change warning, a pre-warning shall be given to the construction drawing path plan. The construction unit shall feedback the result to the design unit, and the design unit shall optimize and adjust the line path in the construction drawing design stage to adjust the construction drawing path plan within the warning line to prevent a major change in the final construction path plan.

[0078] When the degree of change of the transmission line project is an allowable change, the path plan passes.

[0079] In this embodiment, it changes from passive rectification after completion to active optimization in the construction drawing stage, greatly reducing the project risk. Through quantitative indicators and elastic thresholds, it supports scientific decision-making and reduces human misjudgment. The automated process of pre-warning → optimization → release realizes an efficient closed-loop for change control.

[0080] The present invention comprehensively quantifies the degree of change through four-dimensional indicators, namely, the path length change rate, the cumulative proportion of excessive lateral displacement, the new proportion of sensitive targets, and the intrusion status of ecological sensitive areas. The post-completion inspection is advanced to the construction drawing stage to avoid problems being discovered only at the acceptance stage. A warning range of 25%-30% is set to allow fine-tuning of the path within a reasonable technical range, reducing the need for unnecessary environmental impact assessment changes. The addition of an ecological sensitive area directly triggers a major change warning to ensure that the legal red line cannot be crossed. Shifting from passive rectification to active optimization significantly reduces project risks. The combination of quantitative indicators and flexible thresholds supports scientific decision-making and reduces human misjudgment. The automated process of warning → optimization → release realizes an efficient closed-loop for change control.

[0081] As Figure 2 shown, a specific implementation process of the present invention is as follows:

[0082] First, the construction unit collects the first path coordinates, the names of the first electromagnetic and noise sensitive points, and the names of ecological sensitive areas such as nature reserves, scenic spots, and drinking water source protection areas along the first line (the first geographical information) in the construction drawing stage of this transmission line, and imports them into the map software, naming it the construction drawing path of the XXX project.

[0083] Second, the construction unit collects the second path coordinates, the names of the second electromagnetic and noise sensitive points, and the names of ecological sensitive areas such as nature reserves, scenic spots, and drinking water source protection areas along the second line (the second geographical information) in the environmental impact assessment stage of the transmission line, and imports them into the map software, naming it the environmental impact assessment path of the XXX project.

[0084] Start the major change judgment program for the transmission line. After that, the software will judge whether there is a major change in the construction drawing transmission line path plan according to the pre-set major change judgment conditions for the transmission line.

[0085] 1. If there is no major change in the transmission line path or the path change does not reach the warning threshold, the path plan passes, and the system prompts that the path plan is feasible.

[0086] 2. If the path change of the transmission line has reached the warning standard for major changes, that is, when comparing the plan in the construction drawing stage with the plan in the environmental impact assessment stage, the changes in the construction drawing stage compared with the environmental impact assessment stage meet the following conditions:

[0087] (1) The path length in the construction drawing stage increases by more than 25%-30% of the path length of the environmental impact assessment path plan.

[0088] (2) The cumulative length of the lateral displacement of the construction drawing line exceeding 500 meters exceeds 25%-30% of the path length of the environmental impact assessment path plan.

[0089] 3. Due to changes in the route of the construction drawing, the number of newly added electromagnetic and acoustic environment sensitive targets exceeds 25% - 30% of the number of the environmental impact assessment (EIA) route plan.

[0090] Then a warning is issued for the construction drawing route plan, indicating that a major change in the construction drawing route plan is about to occur. The construction unit should feedback the result to the design unit, and the design unit should optimize and adjust the route of the construction drawing design stage to bring the construction drawing route plan within the warning line to prevent major changes in the final construction route plan.

[0091] If the change in the transmission line route already meets the conditions for major changes, that is, compared with the EIA plan in the construction drawing stage, the following conditions are met for the changes in the construction drawing stage compared with the EIA plan:

[0092] 1. The increase in the route length in the construction drawing stage exceeds 30% of the route length of the EIA route plan.

[0093] 2. The cumulative length of the lateral displacement of the construction drawing line exceeding 500 meters exceeds 30% of the route length of the EIA route plan.

[0094] 3. Due to changes in the route of the construction drawing line, the number of newly added electromagnetic and acoustic environment sensitive targets exceeds 30% of the number of the EIA route plan.

[0095] 4. Due to changes in the route plan of the construction drawing line, it leads to entering new ecological sensitive areas such as nature reserves, scenic spots, and drinking water source protection areas.

[0096] Then a warning is issued for the construction drawing route plan, indicating that a major change has occurred in the construction drawing line route plan. The construction unit should feedback the result to the design unit, and the design unit should optimize the route of the construction drawing design stage and conduct a comprehensive review with the construction unit from aspects such as technology, environmental protection, economy, and restrictive factors to determine the final construction route plan. If, after route optimization, the route plan no longer belongs to a major change, then the construction unit should carry out construction work based on the optimized construction drawing. If, after the route plan is adjusted, it still belongs to a major change, but it is considered more reasonable after a comprehensive review from multiple aspects such as technology, environmental protection, economy, and restrictive factors. Then the construction unit starts the preparation work for the changed EIA in synchronization with the optimized route plan of the construction drawing to prevent the acceptance work.

[0097] The present invention realizes the automatic judgment of major changes in transmission lines, replaces manual measurement and judgment, etc., realizes high-precision and automatic judgment, and reduces the possibility of misjudgment caused by human operation. It saves project investment and shortens the project completion time. The present invention realizes the early intervention of major change judgment, prevents and reduces the occurrence of major changes in transmission line projects, and achieves the purpose of optimizing the line path by the construction unit, saving project investment and shortening the project acceptance period. The present invention realizes that if there are major changes in the line path, the change environmental impact assessment work can be carried out synchronously according to the final construction path at the construction drawing stage, without affecting the subsequent project completion environmental protection acceptance and the work of the second-phase project.

[0098] As Figure 3 shown, in an embodiment of the present invention, a device 30 for determining the degree of change in a transmission line project includes:

[0099] An acquisition module 31, configured to acquire the first geographic information of the transmission line project and the second geographic information of the environmental impact assessment of the transmission line project;

[0100] A processing module 32, configured to determine the change information between the first geographic information and the second geographic information according to the first geographic information and the second geographic information; and determine the degree of change in the transmission line project according to the change information.

[0101] Optionally, the acquisition of the first geographic information of the transmission line project includes:

[0102] Acquiring the first path coordinates, the names of the first electromagnetic and noise sensitive points, the names of the first nature reserves, scenic spots, and ecological sensitive areas of drinking water source protection areas along the line in the construction drawing stage of the transmission line project.

[0103] Optionally, the acquisition of the second geographic information of the environmental impact assessment of the transmission line project includes:

[0104] Acquiring the second path coordinates, the names of the second electromagnetic and noise sensitive points, the names of the second nature reserves, scenic spots, and ecological sensitive areas of drinking water source protection areas along the line in the environmental impact assessment stage of the transmission line project.

[0105] Optionally, the determination of the change information between the first geographic information and the second geographic information according to the first geographic information and the second geographic information includes:

[0106] Determining a first change amplitude of the increase in the path length in the construction drawing stage compared to the environmental impact assessment stage according to the first path coordinates and the second path coordinates;

[0107] Determining a second change amplitude of the cumulative length of the lateral displacement of the line in the construction drawing stage exceeding a set value compared to the environmental impact assessment stage according to the first path coordinates and the second path coordinates;

[0108] Determine the third change range of the electromagnetic and acoustic environment sensitive targets newly added in the construction drawing stage compared with the environmental impact assessment stage according to the names of the first electromagnetic and noise sensitive points and the second electromagnetic and noise sensitive points;

[0109] Determine the fourth change situation of the ecological sensitive areas of nature reserves, scenic spots, and drinking water source protection areas along the line in the construction drawing stage compared with the environmental impact assessment stage according to the names of the ecological sensitive areas of nature reserves, scenic spots, and drinking water source protection areas along the first line and the ecological sensitive areas of nature reserves, scenic spots, and drinking water source protection areas along the second line;

[0110] Determine the change information according to the relationships between the first change range and the first set interval, the second change range and the second set interval, the third change range and the third set interval, and the fourth change situation and the fourth set situation.

[0111] Optionally, the determining the change information according to the relationships between the first change range and the first set interval, the second change range and the second set interval, the third change range and the third set interval, and the fourth change situation and the fourth set situation includes:

[0112] If any one of the conditions that the first change range exceeds the first set interval, the second change range exceeds the second set interval, the third change range exceeds the third set interval, and the fourth change situation meets the fourth set situation is satisfied, determine that the change information is a major change;

[0113] If any one of the conditions that the first change range meets the first set interval, the second change range meets the second set interval, and the third change range meets the third set interval is satisfied, determine that the change information is a major change warning;

[0114] If the three conditions that the first change range is less than the first set interval, the second change range is less than the second set interval, and the third change range is less than the third set interval are satisfied, determine that the change information is an allowable change.

[0115] Optionally, the first change range is the ratio of the increase in the path length in the construction drawing stage compared with the environmental impact assessment stage to the path length in the environmental impact assessment stage;

[0116] The second change range is the ratio of the cumulative length of the lateral displacement of the line in the construction drawing stage exceeding the set value compared with the environmental impact assessment stage to the path length in the environmental impact assessment stage;

[0117] The third change range is the ratio of the newly added electromagnetic and acoustic environment sensitive targets in the construction drawing stage compared with the environmental impact assessment stage to the number of electromagnetic and acoustic environment sensitive targets in the environmental impact assessment stage;

[0118] The fourth change situation is whether there are newly added ecological sensitive areas such as nature reserves, scenic spots, and drinking water source protection areas along the line during the construction drawing stage compared with the environmental impact assessment stage.

[0119] Optionally, determining the degree of change of the transmission line project according to the change information includes:

[0120] Determining that the degree of change of the transmission line project according to the change information is a major change, a major change warning, or an allowable change.

[0121] It should be noted that this device corresponds to the above method, and all implementation manners in the above method embodiments are applicable to the embodiments of this device and can also achieve the same technical effects.

[0122] An embodiment of the present invention also provides a computing device, including: a processor and a memory storing a computer program. When the computer program is run by the processor, it executes the method described in the above embodiments. All implementation manners in the above method embodiments are applicable to this embodiment and can also achieve the same technical effects.

[0123] An embodiment of the present invention also provides a computer-readable storage medium storing instructions. When the instructions are run on a computer, the computer is caused to execute the method described in the above embodiments. All implementation manners in the above method embodiments are applicable to this embodiment and can also achieve the same technical effects.

[0124] Those of ordinary skill in the art can realize that the units and algorithm steps of each example described in combination with the embodiments disclosed herein can be implemented by electronic hardware, or a combination of computer software and electronic hardware. Whether these functions are executed in a hardware or software manner depends on the specific application and design constraint conditions of the technical solution. Professional technicians can use different methods to implement the described functions for each specific application, but such implementation should not be considered to exceed the scope of the present invention.

[0125] Those skilled in the art can clearly understand that for the convenience and brevity of description, the specific working processes of the systems, devices, and units described above can refer to the corresponding processes in the foregoing method embodiments and will not be elaborated herein.

[0126] In the embodiments provided by the present invention, it should be understood that the disclosed devices and methods can be implemented in other ways. For example, the device embodiments described above are merely illustrative. For example, the division of the units is only a logical function division. In actual implementation, there may be other division methods. For example, multiple units or components can be combined or integrated into another system, or some features can be ignored or not executed. Another point is that the displayed or discussed coupling, direct coupling, or communication connection between each other can be through some interfaces. The indirect coupling or communication connection of the devices or units can be in electrical, mechanical, or other forms.

[0127] The units described as separate components may or may not be physically separated. The components displayed as units may or may not be physical units, that is, they can be located in one place or distributed to multiple network units. Some or all of the units can be selected according to actual needs to achieve the purpose of the solution of this embodiment.

[0128] In addition, in each embodiment of the present invention, the functional units can be integrated in a processing unit, or each unit can exist physically alone, or two or more units can be integrated in one unit.

[0129] If the functions are implemented in the form of software function units and sold or used as independent products, they can be stored in a computer-readable storage medium. Based on this understanding, the technical solution of the present invention, in essence, or the part that contributes to the prior art, or this part of the technical solution, can be embodied in the form of a software product. This computer software product is stored in a storage medium and includes several instructions to enable a computer device (which can be a personal computer, a server, or a network device, etc.) to execute all or part of the steps of the methods described in each embodiment of the present invention. The foregoing storage medium includes: various media such as USB flash drives, mobile hard disks, ROM, RAM, magnetic disks, or optical discs that can store program codes.

[0130] In addition, it should be noted that in the device and method of the present invention, obviously, each component or each step can be decomposed and / or recombined. These decompositions and / or recombinations shall be regarded as equivalent solutions of the present invention. Moreover, the steps of performing the above series of processes can naturally be executed in chronological order according to the described order, but it is not necessary to execute them in chronological order. Some steps can be executed in parallel or independently of each other. For those of ordinary skill in the art, it is understandable that all or any steps or components of the method and device of the present invention can be implemented in any computing device (including processors, storage media, etc.) or a network of computing devices in the form of hardware, firmware, software, or a combination thereof, which can be achieved by those of ordinary skill in the art using their basic programming skills after reading the description of the present invention.

[0131] Therefore, the object of the present invention can also be achieved by running a program or a set of programs on any computing device. The computing device can be a well-known general-purpose device. Therefore, the object of the present invention can also be achieved only by providing a program product containing program code for implementing the method or device. That is to say, such a program product also constitutes the present invention, and a storage medium storing such a program product also constitutes the present invention. Obviously, the storage medium can be any well-known storage medium or any storage medium developed in the future. It should also be noted that in the device and method of the present invention, obviously, each component or each step can be decomposed and / or recombined. These decompositions and / or recombinations shall be regarded as equivalent solutions of the present invention. Moreover, the steps of performing the above series of processes can naturally be executed in chronological order according to the described order, but it is not necessary to execute them in chronological order. Some steps can be executed in parallel or independently of each other.

[0132] The above is the preferred embodiment of the present invention. It should be pointed out that for those of ordinary skill in the art, without departing from the principle of the present invention, several improvements and refinements can be made, and these improvements and refinements should also be regarded as the protection scope of the present invention.

Claims

1. A method for determining the degree of change in a transmission line project, characterized in that, Including: Obtaining the first geographic information of the transmission line project and the second geographic information of the environmental impact assessment of the transmission line project; Determining the change information between the first geographic information and the second geographic information according to the first geographic information and the second geographic information; Determining the change degree of the transmission line project according to the change information.

2. The method for determining the degree of change of a transmission line project according to claim 1, characterized in that The obtaining of the first geographic information of the transmission line project includes: Obtaining the first path coordinates, the names of the first electromagnetic and noise sensitive points, the names of the first natural reserves, scenic spots and ecological sensitive areas of drinking water source protection areas along the line in the construction drawing stage of the transmission line project.

3. The method for determining the degree of change of a transmission line project according to claim 2, wherein The obtaining of the second geographic information of the environmental impact assessment of the transmission line project includes: Obtaining the second path coordinates, the names of the second electromagnetic and noise sensitive points, the names of the second natural reserves, scenic spots and ecological sensitive areas of drinking water source protection areas along the line in the environmental impact assessment stage of the transmission line project.

4. The method for determining the degree of change of a transmission line project according to claim 3, wherein The determining of the change information between the first geographic information and the second geographic information according to the first geographic information and the second geographic information includes: Determining the first change amplitude of the increase in the path length in the construction drawing stage compared with the environmental impact assessment stage according to the first path coordinates and the second path coordinates; Determining the second change amplitude of the cumulative length of the lateral displacement of the line in the construction drawing stage exceeding the set value compared with the environmental impact assessment stage according to the first path coordinates and the second path coordinates; Determining the third change amplitude of the newly added electromagnetic and acoustic environment sensitive targets in the construction drawing stage compared with the environmental impact assessment stage according to the names of the first electromagnetic and noise sensitive points and the names of the second electromagnetic and noise sensitive points; Determining the fourth change situation of the ecological sensitive areas of natural reserves, scenic spots and drinking water source protection areas along the line in the construction drawing stage compared with the environmental impact assessment stage according to the names of the ecological sensitive areas of natural reserves, scenic spots and drinking water source protection areas along the first line and the names of the ecological sensitive areas of natural reserves, scenic spots and drinking water source protection areas along the second line; Determining the change information according to the relationships between the first change amplitude and the first set interval, the second change amplitude and the second set interval, the third change amplitude and the third set interval, and the fourth change situation and the fourth set situation.

5. The method for determining the degree of change of a transmission line project according to claim 4, wherein, The determining of the change information according to the relationships between the first change amplitude and the first set interval, the second change amplitude and the second set interval, the third change amplitude and the third set interval, and the fourth change situation and the fourth set situation includes: If any of the conditions that the first change amplitude exceeds the first set interval, the second change amplitude exceeds the second set interval, the third change amplitude exceeds the third set interval, and the fourth change situation meets the fourth set situation is satisfied, determining that the change information is a major change; If any of the conditions that the first change amplitude meets the first set interval, the second change amplitude meets the second set interval, and the third change amplitude meets the third set interval is satisfied, determining that the change information is a major change warning; If the three conditions that the first change amplitude is less than the first set interval, the second change amplitude is less than the second set interval, and the third change amplitude is less than the third set interval are satisfied, determining that the change information is an allowable change.

6. The method for determining the degree of change of a transmission line project according to claim 5, wherein The first change range is the proportion of the increase in the path length in the construction drawing stage compared to the path length in the environmental impact assessment stage to the path length in the environmental impact assessment stage; The second change range is the proportion of the cumulative length of the lateral displacement of the line in the construction drawing stage exceeding the set value compared to the path length in the environmental impact assessment stage to the path length in the environmental impact assessment stage; The third change range is the proportion of the newly added electromagnetic and acoustic environment sensitive targets in the construction drawing stage compared to the environmental impact assessment stage to the number of electromagnetic and acoustic environment sensitive targets in the environmental impact assessment stage; The fourth change situation is whether there are newly added ecological sensitive areas such as nature reserves, scenic spots, and drinking water source protection areas along the line in the construction drawing stage compared to the environmental impact assessment stage.

7. The method for determining the degree of change of a transmission line project according to claim 5, wherein Determining the degree of change of the transmission line project according to the change information includes: Determining that the degree of change of the transmission line project according to the change information is a major change, a major change warning, or an allowable change.

8. A device for determining the degree of change in a transmission line project, characterized in that, Including: An acquisition module for acquiring the first geographic information of the transmission line project and the second geographic information of the environmental impact assessment of the transmission line project; A processing module for establishing a three-dimensional real-scene model according to the first geographic information and the second geographic information; Determining the change information between the first geographic information and the second geographic information according to the three-dimensional real-scene model; Determining the degree of change of the transmission line project according to the change information.

9. A computing device, characterized in that, Including: A processor and a memory storing a computer program, and when the computer program is run by the processor, it executes the method according to any one of claims 1 to 7.

10. A computer-readable storage medium, characterized in that, Storing an instruction, and when the instruction runs on a computer, it causes the computer to execute the method according to any one of claims 1 to 7.

Citation Information

Patent Citations

  • Noise map drawing method applied to urban planning and construction project environmental impact assessment

    CN108871551A

  • GIS-based power transmission and transformation project environmental protection detection system and method

    CN113806423A

  • Power grid project environmental protection water conservation major change monitoring method, system, equipment and medium

    CN118521541A