Heat-preservation and energy-saving type fabricated floor slab and manufacturing method thereof
By opening injection hole groups and laying steel cages at both ends of the floor slab body, combining locking parts positioning and moving grouting machines, the problems of high altitude operation difficulty and uneven distribution of the insulation layer in traditional construction are solved, uniform filling and structural stability of the insulation layer are achieved, and construction efficiency and insulation performance are improved.
Patent Information
- Application Number
- CN202510862620.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2025-06-25
- Publication Date
- 2025-08-15
- Estimated Expiration
- 2045-06-25
AI Technical Summary
In the construction of traditional insulation prefabricated floor slabs, high altitude back operation is difficult, positioning accuracy is difficult to ensure, the insulation layer is unevenly distributed, and the construction period is long.
The injecting hole set is set at both ends of the floor main body, the first and second steel cages are arranged, and the formwork is reserved to form an insulation cavity. The insulating mortar is filled from the injecting hole set with a mobile grouting device, and the insulating mortar is vibrated with a vibrating rod.
The uniform filling and stable connection of the insulation layer are achieved, the construction efficiency and strength of the insulation layer are improved, the operation process is simplified, and the insulation performance and structural durability are ensured.
Smart Images

Figure CN120486642A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of prefabricated floor slabs, and in particular to a heat-insulating and energy-saving prefabricated floor slab and a manufacturing method thereof. Background Art
[0002] As an integral component of building industrialization, prefabricated floor slabs have been widely adopted in the construction industry. Traditionally, the construction of insulated prefabricated floor slabs employs the following process: First, the prefabricated floor slabs are hoisted onto supporting walls, and concrete is poured on top to form the structural layer. Subsequently, scaffolding is erected at the bottom of the floor slab to support the lower formwork. A grouting machine is connected to the floor slab to inject insulation slurry through pre-set grouting ports in the lower formwork, ultimately filling the space between the floor slab and the lower formwork to form the lower insulation layer.
[0003] However, this kind of thermal insulation assembled floor has the following shortcomings:
[0004] 1. After the floor slab is hoisted, the lower formwork and scaffolding support system need to be set up again. The operators need to look up to position the formwork and connect it with the grouting pipe. The high-altitude upward operation is difficult and the positioning accuracy is difficult to guarantee, which significantly prolongs the construction period.
[0005] 2. When the slurry is filled in a closed space, its fluidity is limited, and uneven distribution is likely to occur. At the same time, due to the constraints of the working space, it is impossible to implement an effective vibration process, which leads to residual pores or voids inside the insulation layer, reducing the insulation performance and structural durability. Summary of the Invention
[0006] In view of the deficiencies in the prior art, the present invention provides a thermal insulation and energy-saving assembled floor slab, which solves the problems mentioned in the background art.
[0007] To achieve the above objectives, the present invention is implemented through the following technical solutions:
[0008] The heat-insulating and energy-saving assembled floor slab comprises a floor slab body, both ends of which are mounted on the top of the supporting wall, and a group of injection holes are opened at both ends of the surface;
[0009] The first steel cages are arranged transversely and at equal intervals longitudinally on the surface of the floor slab body, with the injection hole group being located between two groups of the first steel cages; the surface of the floor slab body is filled with an upper mortar layer, and the first steel cages are located in the upper mortar layer;
[0010] A first locking member is mounted on the surface of the floor slab body and is positioned between the two sets of first reinforcement cages. The bottom of the first locking member extends downwardly outward from the floor slab body, and both ends of the first locking member are respectively pressed on one set of first reinforcement cages to position the first reinforcement cages.
[0011] The lower formwork is spaced apart at the bottom of the main floor slab and between the two sets of supporting walls. The lower insulation layer is filled between the top of the lower formwork and the main floor slab. The injection hole group serves as an inlet and outlet channel for the mobile grouting device to fill the insulation mortar. The injection hole group also serves as the connection area between the upper mortar layer and the lower insulation layer.
[0012] A second reinforcement cage is arranged transversely and at equal intervals longitudinally on the surface of the lower formwork, the second reinforcement cage being positioned below the middle portion between the two groups of first reinforcement cages;
[0013] The second locking member is installed on the lower template. The top of the second locking member is connected to the bottom extension structure of the first locking member. The second locking member passes through the second steel cage longitudinally. The second locking member is placed at both ends of a group of second steel cages. The second locking member is used to hoist and position the second steel cage and the lower template.
[0014] Furthermore, the first steel cage includes a first rod body, a second rod body and a first oblique rod body. The side walls of the first rod body are symmetrically provided with first oblique rod bodies extending downward. The first oblique rod bodies are arranged at intervals laterally. The bottom ends of the two groups of first oblique rod bodies are each provided with a second rod body. The first rod body and the two groups of second rod bodies form an isosceles triangle. The two groups of second rod bodies are placed on the surface of the floor main body.
[0015] Furthermore, the first locking member includes a pressure rod, a first locking screw, and an arc plate. Two groups of arc plates are provided at both ends of the pressure rod, and the two groups of arc plates at one end are respectively pressed on two second rod bodies of a group of first steel cages; symmetrical through-holes are opened in the middle of the pressure rod, and the first locking screw passes through the inside of the through-holes. The first locking screw is located on the inner side of the arc plate, and a first through-hole for the first locking screw to pass through is opened on the surface of the floor main body. The first locking screw passes through the first through-hole downward, and the outer wall of the first locking screw is threadedly connected to the first locking nut. The first locking nut contacts the bottom surface of the floor main body to fix the first locking member on the floor main body.
[0016] Furthermore, the third rod, the fourth rod and the second oblique rod of the second steel cage, the side wall of the third rod is symmetrically provided with the second oblique rod extending upward, the second oblique rods are arranged at intervals horizontally, and the tops of the two groups of second oblique rods are each provided with a fourth rod, the third rod and the two groups of fourth rods form an isosceles triangle, the two groups of fourth rods are placed on the surface of the floor main body, and the third rod is placed on the surface of the lower formwork.
[0017] Furthermore, the second locking member includes a supporting rod, a threaded sleeve and a second locking screw. The supporting rod is provided with a second through hole at a position opposite to the first through hole. The supporting rod is sleeved on the bottom of the two groups of first locking screws. The bottom of the first locking screw extends outward from the second through hole. The portion of the first locking screw extending outward from the second through hole is threadedly connected to the second locking nut. The supporting rod passes between adjacent second oblique rod bodies and is placed at the bottom of the two groups of fourth rod bodies. Threaded sleeves are symmetrically provided at both ends of the bottom surface of the supporting rod. The second locking screw passes through the lower template from bottom to top and is screwed into the threaded sleeve.
[0018] During the floor slab production phase, the second locking screw is screwed into the threaded sleeve to position the lower formwork;
[0019] When the floor is in use, the second locking screw can be unscrewed and the threaded sleeve can be used as a reserved opening for the ceiling.
[0020] Furthermore, compensation blocks are provided at both ends of the surface of the support rod, the second through hole is located on the inner side of the compensation block, and the compensation block contacts the bottom surface of the floor slab body.
[0021] Furthermore, the injection hole group includes a first grouting hole and a second grouting hole, and the first grouting hole and the second grouting hole are respectively placed at both ends of the floor slab body;
[0022] An upper constraint groove is provided on the bottom surface of the floor slab body, and a lower constraint groove is provided on the surface of the lower formwork. The lower constraint groove is relatively located directly below the upper constraint groove; both ends of the upper constraint groove are connected to the first grouting hole and the second grouting hole respectively;
[0023] A traction part is reserved inside the insulation cavity, which includes a rope body, a first buckle and a second buckle. The two ends of the rope body are connected to the first buckle and the second buckle. The rope body is placed at the bottom of the floor main body and the two ends extend outward to the first grouting hole and the second grouting hole respectively. The first buckle and the second buckle are respectively buckled at the two ends of the adjacent first steel cage.
[0024] A method for manufacturing a heat-insulating and energy-saving assembled floor slab, the method comprising the following steps:
[0025] S1. Hoist and connect the thermal insulation and energy-saving assembled floor slab to the supporting wall;
[0026] S2, filling of lower insulation layer:
[0027] S2.1. Undo the first and second buckles connected to the first reinforcement cage, and connect the second buckle to the mobile grouting device;
[0028] S2.2. Connect the mobile grouting device to the grouting pipe, and then place the mobile grouting device into the insulation chamber through the second grouting hole;
[0029] S2.3. Pull the first buckle outward to move the mobile grouting device along the insulation cavity to evenly fill the insulation cavity with insulation mortar;
[0030] S2.4. Pull out the grouting pipe to move the mobile grouting device in the opposite direction along the insulation cavity to fill and compact the insulation mortar for the second time;
[0031] S2.5. After one group of grouting holes is filled, the mobile grouting device is moved to the next group of grouting holes to complete the filling of the lower insulation layer;
[0032] S3, filling the upper mortar layer:
[0033] The grouting pipe is filled with mortar above the main body of the floor slab to form an upper mortar layer, and the upper mortar layer is connected to the lower insulation layer at the injection hole group.
[0034] Furthermore, the mobile grouting device includes a front end plate, a rear end plate, a central tube, a discharge pipe and a vibrating rod, the front end of the central tube is fixedly connected to the front end plate, and the rear end is fixedly connected to the rear end plate, a connecting ring connected to the second buckle is provided in the middle of the outer wall of the front end plate, and a docking joint is provided in the middle of the rear end plate, the docking joint is communicated with the central tube, and the docking joint is connected to the grouting pipe;
[0035] An upper guard plate is provided on the top of the center tube and a lower guard plate is provided on the bottom. The two ends of the upper guard plate are flush connected to the front end plate and the rear end plate. The two ends of the lower guard plate are flush connected to the front end plate and the rear end plate. The surface of the upper guard plate is provided with an upper guide block that fits in the upper constraint groove. The bottom surface of the lower guard plate is provided with a lower guide block that fits in the lower constraint groove.
[0036] The two ends of the side wall of the central tube are symmetrically connected with discharge pipes, and multiple groups of vibrating rods are symmetrically arranged in the middle of the side wall of the central tube; side sealing plates are symmetrically installed between the upper guard plate and the lower guard plate for sliding, and the side sealing plates are symmetrically placed on both sides of the central tube, and the side sealing plates are slidably fitted on the outer walls of the discharge pipe and the vibrating rods;
[0037] In the discharge state, the two sets of side sealing plates move outwards, the discharge pipe opens to discharge materials, and the vibrating rod retracts into the inner side sealing plate;
[0038] In the vibrating state, the two sets of side sealing plates move inward to close the discharge pipe and expose the vibrating rods, and multiple sets of vibrating rods work to compact the mortar.
[0039] Furthermore, the side walls of the side sealing plates are symmetrically provided with moving blocks, which are slidably embedded in the front end plate and the rear end plate respectively. The front end plate and the rear end plate are built with double-headed threaded rods for driving the side sealing plates to move, and the double-headed threaded rods are threadedly connected to the moving blocks; a first notch is provided at a position where the side sealing plate is relative to the discharge pipe, and a second notch is provided at a position where the side sealing plate is relative to the vibrating rod;
[0040] A self-rotating sealing plate is rotatably installed in the middle of the inner part of the discharge pipe, and a rotating shaft is provided in the middle of the two ends of the self-rotating sealing plate. The rotating shaft rotates and extends outward to the discharge pipe, and a torsion spring is installed at the rotating connection. A driven gear is provided at the outer end of the rotating shaft; a third notch is opened on the inner side of the first notch to avoid the driven gear, and a horizontally arranged rack is provided on the inner wall of the third notch, and the rack is meshed and placed below the driven gear.
[0041] The present invention provides a heat-insulating and energy-saving assembled floor slab and a method for manufacturing the same. Compared with the prior art, the present invention has the following advantages:
[0042] 1. A lower formwork is reserved at the bottom of the main body of the floor slab, and an insulation cavity is left between the lower formwork and the main body of the floor slab, so that the lower formwork can also be laid out when the main body of the floor slab is overlapped;
[0043] 2. A group of injection holes is opened on the surface of the floor slab. When filling the insulation mortar into the insulation cavity, the grouting pipe can be inserted from the injection hole group. Workers can complete the filling and grouting of the insulation cavity while standing on the floor slab. The grouting is more uniform and the operation is easier. When filling the floor slab with concrete, the upper mortar layer is connected to the lower insulation layer in the insulation cavity through the injection hole group, forming an integrated structure from top to bottom, and the lower insulation layer is more stable.
[0044] 3. Laying the first steel cage on the main body of the floor slab can improve the strength of the upper mortar layer, and laying the second steel cage on the surface of the lower formwork can improve the strength of the lower insulation layer;
[0045] 4. The first locking member can be assembled on the main body of the floor slab, so that it can press down and position the first reinforcement cages on both sides, and also serve as a positioning reserved structure for the second reinforcement cage and the lower formwork;
[0046] 5. The second locking piece can lift the second steel cage so that the second steel cage fits on the bottom surface of the floor main body. Then the second locking piece is connected to the first locking piece to realize the positioning of the second locking piece and the second steel cage. Finally, the lower template is installed at the bottom of the second locking piece to realize the positioning of the lower template. BRIEF DESCRIPTION OF THE DRAWINGS
[0047] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the following briefly introduces the drawings required for use in the embodiments or the description of the prior art. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying any creative work.
[0048] Figure 1 A schematic diagram of the heat-insulating and energy-saving assembled floor structure of the present invention is shown;
[0049] Figure 2A schematic diagram of the bottom-up structure of the assembled floor slab of the present invention is shown;
[0050] Figure 3 A schematic diagram of the connection structure between the first reinforcement cage and the second reinforcement cage of the present invention is shown;
[0051] Figure 4 Shown Figure 1 A schematic diagram of the enlarged structure at point A;
[0052] Figure 5 Shown Figure 1 A schematic diagram of the enlarged structure at point B;
[0053] Figure 6 Shows a schematic diagram of the second steel cage structure of the present invention;
[0054] Figure 7 A schematic diagram of the connection structure between the first locking member and the second locking member of the present invention is shown;
[0055] Figure 8 A schematic diagram of the separate structure of the first locking member and the second locking member of the present invention is shown;
[0056] Figure 9 It shows a schematic diagram of the cross-sectional structure of the prefabricated floor slab of the present invention;
[0057] Figure 10 Shown Figure 9 Schematic diagram of the enlarged structure at C;
[0058] Figure 11 A schematic diagram of a top cross-sectional structure of a mobile grouting device according to the present invention is shown;
[0059] Figure 12 A schematic diagram of the side cross-section structure of the mobile grouting device of the present invention is shown;
[0060] Figure 13 It shows a front view structural diagram of the connection between the discharge pipe and the side sealing plate of the present invention;
[0061] As shown in the figure:
[0062] 100, floor slab body, 110, first grouting hole, 120, second grouting hole, 130, first through hole, 140, upper restraining groove;
[0063] 200, first steel cage, 210, first rod, 220, first oblique rod, 230, second rod;
[0064] 300, first locking member, 310, pressure rod, 311, through hole, 320, first locking screw, 330, first locking nut, 340, arc plate;
[0065] 400, lower template, 410, lower constraint groove;
[0066] 500, supporting wall;
[0067] 600, second steel cage, 610, third rod, 620, second oblique rod, 630, fourth rod;
[0068] 700, second locking member, 710, support rod, 711, compensation block, 712, second through hole, 720, threaded sleeve, 730, second locking screw, 740, second locking nut;
[0069] 800, traction member, 810, rope body, 820, first buckle, 830, second buckle;
[0070] 900. Mobile grouting device, 910. Front end plate, 911. Connecting ring, 920. Rear end plate, 921. Butt joint, 922. Grouting pipe, 930. Upper guard plate, 931. Upper guide block, 940. Lower guard plate, 941. Lower guide block, 950. Center pipe, 960. Side sealing plate, 961. First notch, 962. Second notch, 963. Third notch, 964. Rack, 965. Moving block, 970. Discharge pipe, 971. Rotating sealing plate, 972. Rotating shaft, 973. Driven gear, 980. Double-headed threaded rod, 990. Vibrating rod. DETAILED DESCRIPTION
[0071] To make the objectives, technical solutions, and advantages of the embodiments of the present invention more clear, the technical solutions in the embodiments of the present invention are clearly and completely described. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of them. All other embodiments derived by persons of ordinary skill in the art based on the embodiments of the present invention without inventive effort are within the scope of protection of the present invention.
[0072] Example 1
[0073] In order to solve the technical problems in the background technology, the following thermal insulation and energy-saving prefabricated floor slab is provided:
[0074] Combine Figures 1-10 As shown, the heat-insulating and energy-saving assembled floor provided by the present invention includes a floor body 100, both ends of which are mounted on the top of a supporting wall 500, and a group of injection holes are opened at both ends of the surface;
[0075] The first steel cages 200 extend transversely and are arranged at equal intervals longitudinally on the surface of the floor slab body 100, with the injection hole group being located between two groups of the first steel cages 200; the surface of the floor slab body 100 is filled with an upper mortar layer, and the first steel cages 200 are placed in the upper mortar layer;
[0076] The first locking member 300 is installed on the surface of the floor slab body 100 and is placed between the two sets of first reinforcement cages 200. The bottom of the first locking member 300 extends downward and outward from the floor slab body 100. The two ends of the first locking member 300 are respectively pressed on one set of first reinforcement cages 200 to position the first reinforcement cages 200.
[0077] The lower formwork 400 is spaced apart at the bottom of the floor slab 100 and between the two sets of supporting walls 500. The lower insulation layer is filled between the top of the lower formwork and the floor slab 100. The injection hole group serves as an inlet and outlet channel for the mobile grouting device 900 to fill the insulation mortar. The injection hole group also serves as the connection area between the upper mortar layer and the lower insulation layer.
[0078] The second steel cage 600 extends transversely and is arranged at equal intervals longitudinally on the surface of the lower template 400. The second steel cage 600 is placed below the middle between the two groups of first steel cages 200.
[0079] The second locking member 700 is installed on the lower template 400. The top of the second locking member 700 is connected to the bottom extension structure of the first locking member 300. The second locking member 700 longitudinally passes through the second steel cage 600. The second locking member 700 is placed at both ends of a group of second steel cages 600. The second locking member 700 is used to hoist and position the second steel cage 600 and the lower template 400.
[0080] In the above scheme:
[0081] 1. A lower template 400 is reserved at the bottom of the floor slab body 100. An insulation cavity is left between the lower template 400 and the floor slab body 100. In this way, the lower template 400 can also be laid out when the floor slab body 100 is overlapped;
[0082] 2. A group of injection holes is provided on the surface of the floor slab body 100. When filling the insulation mortar into the insulation cavity, the grouting pipe 922 can be inserted through the injection hole group. Workers can complete the filling and grouting of the insulation cavity while standing on the floor slab body 100. The grouting is more uniform and the operation is easier. When filling the floor slab body 100 with concrete, the upper mortar layer is connected to the lower insulation layer in the insulation cavity through the injection hole group, forming an integrated structure from top to bottom, and the lower insulation layer is more stable.
[0083] 3. A first steel cage 200 is arranged on the floor slab body 100 to improve the strength of the upper mortar layer, and a second steel cage 600 is arranged on the surface of the lower formwork 400 to improve the strength of the lower insulation layer;
[0084] 4. The first locking member 300 can be assembled on the floor slab body 100, so that it can press down and position the first reinforcement cage 200 on both sides, and also serve as a positioning reserved structure for the second reinforcement cage 600 and the lower formwork 400;
[0085] 5. The second locking member 700 can lift the second steel cage 600 so that the second steel cage 600 fits on the bottom surface of the floor slab body 100. Then the second locking member 700 is connected to the first locking member 300 to achieve the positioning of the second locking member 700 and the second steel cage 600. Finally, the lower template 400 is installed at the bottom of the second locking member 700 to achieve the positioning of the lower template 400.
[0086] In this embodiment, the first steel cage 200 includes a first rod body 210, a second rod body 230 and a first oblique rod body 220. The side walls of the first rod body 210 are symmetrically provided with first oblique rod bodies 220 extending downward. The first oblique rod bodies 220 are arranged at intervals in the horizontal direction. The bottom ends of the two groups of first oblique rod bodies 220 are each provided with a second rod body 230. The first rod body 210 and the two groups of second rod bodies 230 form an isosceles triangle. The two groups of second rod bodies 230 are placed on the surface of the floor slab body 100. The second steel cage 600 includes a third rod 610, a fourth rod 630 and a second oblique rod 620. The side walls of the third rod 610 are symmetrically provided with second oblique rods 620 extending upward. The second oblique rods 620 are arranged at intervals in the horizontal direction. The tops of the two groups of second oblique rods 620 are each provided with a fourth rod 630. The third rod 610 and the two groups of fourth rods 630 form an isosceles triangle. The two groups of fourth rods 630 are placed on the surface of the floor slab body 100, and the third rod 610 is placed on the surface of the lower formwork 400.
[0087] In this embodiment, the first locking member 300 includes a pressure rod 310, a first locking screw 320, and an arc plate 340. Two groups of arc plates 340 are provided at both ends of the pressure rod 310. The two groups of arc plates 340 at one end are respectively pressed on two second rod bodies 230 of a group of first steel cages 200; a through-hole 311 is symmetrically opened in the middle of the pressure rod 310, and the first locking screw 320 passes through the inside of the through-hole 311. The first locking screw 320 is located on the inner side of the arc plate 340, and a first through-hole 130 for the first locking screw 320 to pass through is opened on the surface of the floor slab body 100. The first locking screw 320 passes through the first through-hole 130 downwardly, and the outer wall of the first locking screw 320 is threadedly connected to the first locking nut 330. The first locking nut 330 contacts the bottom surface of the floor slab body 100 to fix the first locking member 300 on the floor slab body 100.
[0088] In the above scheme: the first locking screw 320 can fix the pressure rod 310 on the floor slab body 100; the two ends of the pressure rod 310 extend to the first steel cage 200 on both sides, so that the pressure rod 310 can press down to position the first steel cage 200; the design of the arc plate 340 can increase the contact surface of the pressure rod 310, making the downward pressure stability of the pressure rod 310 higher.
[0089] In this embodiment, the second locking member 700 includes a support rod 710, a threaded sleeve 720 and a second locking screw 730. The support rod 710 is provided with a second through hole 712 at a position relative to the first through hole 130. The support rod 710 is sleeved on the bottom of the two sets of first locking screws 320. The bottom of the first locking screw 320 extends outward from the second through hole 712. The portion of the first locking screw 320 extending outward from the second through hole 712 is threadedly connected to the second locking nut 740. Passing through between adjacent second oblique rods 620 and placed at the bottom of the two groups of fourth rods 630, threaded sleeves 720 are symmetrically provided at both ends of the bottom surface of the support rod 710, and the second locking screw 730 passes through the lower template 400 from bottom to top and is screwed into the threaded sleeve 720; during the floor production stage, the second locking screw 730 is screwed into the threaded sleeve 720 to position the lower template 400; during the floor use stage, the second locking screw 730 can be unscrewed, and the threaded sleeve 720 can be used as a reserved opening for the ceiling.
[0090] In the above scheme: the support rod 710 can lift and position the second steel cage 600; the support rod 710 can be fixed to the first locking screw 320 using the second locking nut 740; the second locking screw 730 can be connected to the reserved threaded sleeve 720, thereby achieving the positioning of the lower template 400.
[0091] In this embodiment, compensation blocks 711 are provided at both ends of the surface of the support rod 710. The second through hole 712 is located on the inner side of the compensation block 711, and the compensation block 711 contacts the bottom surface of the floor slab body 100. The compensation block 711 can fill the gap between the support rod 710 and the floor slab body 100 when the support rod 710 is lifted and positioned. The compensation block 711 contacts the floor slab body 100, which facilitates the screwing and positioning of the second locking nut 740.
[0092] In this embodiment, the injection hole group includes a first grouting hole 110 and a second grouting hole 120, and the first grouting hole 110 and the second grouting hole 120 are respectively disposed at both ends of the floor slab body 100;
[0093] An upper restraining groove 140 is formed on the bottom surface of the floor slab body 100, and a lower restraining groove 410 is formed on the surface of the lower formwork 400. The lower restraining groove 410 is located directly below the upper restraining groove 140. The two ends of the upper restraining groove 140 are respectively connected to the first grouting hole 110 and the second grouting hole 120.
[0094] A traction member 800 is reserved inside the insulation cavity. The traction member 800 includes a rope body 810, a first buckle 820 and a second buckle 830. The two ends of the rope body 810 are connected to the first buckle 820 and the second buckle 830. The rope body 810 is placed at the bottom of the floor main body 100 and the two ends extend outward to the first grouting hole 110 and the second grouting hole 120 respectively. The first buckle 820 and the second buckle 830 are respectively buckled at the two ends of the adjacent first steel cage 200.
[0095] In the above scheme: the traction part 800 reserved on the floor slab main body 100 can be easily connected to the mobile grouting device 900 on site. By pulling the first buckle 820, the mobile grouting device 900 can be driven to move through the rope body 810 and the second buckle 830, so that the mobile grouting device 900 can move and evenly fill the insulation slurry into the insulation cavity; the upper constraint groove 140 and the lower constraint groove 410 are set to constrain the movement process of the mobile grouting device 900, so that the translation of the mobile grouting device 900 is smoother and will not deviate.
[0096] The assembly method of the thermal insulation and energy-saving prefabricated floor is as follows:
[0097] Place the first reinforcement cages 200 on the floor slab body 100 at intervals, install the compression rods 310 on the floor slab body 100 using the first locking screws 320, tighten the first locking nuts 330, and press down the second rods 230 of the first reinforcement cages 200 on both sides with the ends of the compression rods 310. The arc plates 340 press down and position the second rods 230.
[0098] The rope body 810 of the traction member 800 passes through the first grouting hole 110 and the second grouting hole 120, and the first buckle 820 and the second buckle 830 are connected to the first oblique rod body 220 of the first reinforcement cage 200;
[0099] Turn the floor slab body 100 over so that the protruding portion of the first locking screw 320 faces upward, then lay out the second reinforcement cage 600, insert the support rod 710 through the second reinforcement cage 600, so that the support rod 710 contacts the two sets of fourth rod bodies 630, and insert the protruding portion of the first locking screw 320 through the second through hole 712. Then, tighten the second locking nut 740 to achieve the positioning of the support rod 710 and the second reinforcement cage 600.
[0100] Finally, the upper and lower templates 400 are covered, and the second locking screw 730 is passed through the lower template 400 and screwed into the threaded sleeve 720 to achieve the positioning of the lower template 400.
[0101] Example 2
[0102] A method for manufacturing a heat-insulating and energy-saving assembled floor slab, the method comprising the following steps:
[0103] S1. Hoist the floor slab of Example 1 and connect it to the supporting wall 500;
[0104] S2, filling of lower insulation layer:
[0105] S2.1. Undo the first buckle 820 and the second buckle 830 connected to the first reinforcing cage 200, and connect the second buckle 830 to the mobile grouting device 900;
[0106] S2.2. Connect the mobile grouting device 900 to the grouting pipe 922, and then place the mobile grouting device 900 into the heat preservation chamber through the second grouting hole 120;
[0107] S2.3. Pull out the first buckle 820 to move the mobile grouting device 900 along the insulation cavity to evenly fill the insulation cavity with insulation mortar;
[0108] S2.4. Pull out the grouting pipe 922, causing the mobile grouting device 900 to move in the opposite direction within the insulation cavity to refill and compact the insulation mortar.
[0109] S2.5. After one group of grouting holes is filled, the mobile grouting device 900 is moved to the next group of grouting holes to complete the filling of the lower insulation layer;
[0110] S3, filling the upper mortar layer:
[0111] The grouting pipe 922 fills mortar above the floor slab body 100 to form an upper mortar layer, and the upper mortar layer is connected to the lower insulation layer at the injection hole group.
[0112] In the above scheme:
[0113] 1. Through the reserved traction piece 800, it can be docked with the mobile grouting device 900. Based on the first grouting hole 110 and the second grouting hole 120 reserved on the floor slab body 100, the mobile grouting device 900 can be placed from the second grouting hole 120 and pulled from the first grouting hole 110. This can make the mobile grouting device 900 move and fill between the floor slab body 100 and the lower formwork, making the filling more uniform and solving the problem that the grouting operation cannot be extended to the center position;
[0114] 2. The mobile grouting device 900 can complete uniform grouting and vibrate the slurry to improve the distribution uniformity and density of the slurry.
[0115] 3. After processing is completed, the second locking screw can be unscrewed, the template can be removed, and the lower insulation layer can be placed on the roof. The threaded sleeve can be used as a reserved part for the suspended ceiling.
[0116] like Figure 11-13As shown, in this embodiment, the mobile grouting device 900 includes a front end plate 910, a rear end plate 920, a central tube 950, a discharge pipe 970 and a vibrating rod 990. The front end of the central tube 950 is fixedly connected to the front end plate 910, and the rear end is fixedly connected to the rear end plate 920. A connecting ring 911 connected to the second buckle 830 is provided in the middle of the outer wall of the front end plate 910, and a docking joint 921 is provided in the middle of the rear end plate 920. The docking joint 921 is communicated with the central tube 950, and the docking joint 921 is connected to the grouting pipe 922.
[0117] An upper guard plate 930 is provided on the top of the central tube 950, and a lower guard plate 940 is provided on the bottom. The ends of the upper guard plate 930 are flushly connected to the front plate 910 and the rear plate 920. The ends of the lower guard plate 940 are flushly connected to the front plate 910 and the rear plate 920. The surface of the upper guard plate 930 is provided with an upper guide block 931 that fits and fits in the upper constraint groove 140. The bottom surface of the lower guard plate 940 is provided with a lower guide block 941 that fits and fits in the lower constraint groove 410.
[0118] The two ends of the side wall of the central tube 950 are symmetrically connected to the discharge pipe 970, and a plurality of groups of vibrating rods 990 are symmetrically provided in the middle of the side wall of the central tube 950; side sealing plates 960 are symmetrically slidably installed between the upper guard plate 930 and the lower guard plate 940, and the side sealing plates 960 are symmetrically placed on both sides of the central tube 950. The side sealing plates 960 are slidably fitted on the outer walls of the discharge pipe 970 and the vibrating rods 990;
[0119] In the discharge state, the two sets of side sealing plates 960 move outward, the discharge pipe 970 opens to discharge the material, and the vibrating rod 990 retracts into the inner side sealing plate 960;
[0120] In the vibrating state, the two sets of side sealing plates 960 move inward to close the discharge pipe 970 and expose the vibrating rods 990, and the multiple sets of vibrating rods 990 work to compact the mortar.
[0121] In the above solution, when the mobile grouting device 900 is placed in the filling cavity, the upper guide block 931 can be aligned with the upper constraint groove 140 and the lower guide block 941 can be aligned with the lower constraint groove 410 to ensure the stability of subsequent movement.
[0122] Discharge pipes 970 and vibrating rods 990 are arranged on both sides of the central pipe 950. The slurry input from the grouting pipe 922 can be discharged to both sides through the docking joint 921, the central pipe 950, and the discharge pipes 970, realizing multi-point output and filling of concrete; the vibrating rods 990 can vibrate the concrete;
[0123] The upper guard plate 930, the lower guard plate 940, the front end plate 910, the rear end plate 920 and the side sealing plates 960 on both sides can form a complete shell, and the side sealing plates 960 are movable structures;
[0124] During discharge, the side sealing plate 960 moves outward, thus forming a complete shell, thereby reducing walking resistance and making concrete output smoother; after discharge, when the vibrating rod 990 needs to vibrate, the side sealing plate 960 moves outward, thus exposing the vibrating rod 990 and allowing the vibrating rod 990 to vibrate the concrete.
[0125] In this embodiment, the side wall of the side sealing plate 960 is symmetrically provided with a moving block 965, and the moving block 965 is slidably embedded in the front end plate 910 and the rear end plate 920 respectively. The front end plate 910 and the rear end plate 920 are built with a double-headed threaded rod 980 for driving the side sealing plate 960 to move, and the double-headed threaded rod 980 is threadedly connected to the moving block 965; a first notch 961 is provided at the relative position of the side sealing plate 960 and the discharge pipe 970, and a second notch is provided at the relative position of the side sealing plate 960 and the vibration rod 990 962; a self-rotating sealing plate 971 is rotatably installed in the middle of the inner part of the discharge pipe 970, and a rotating shaft 972 is provided in the middle of both ends of the self-rotating sealing plate 971. The rotating shaft 972 rotates and extends the discharge pipe 970, and a torsion spring is installed at the rotating connection. A driven gear 973 is provided at the outer end of the rotating shaft 972; a third notch 963 is provided on the inner side of the first notch 961 to avoid the driven gear 973, and a horizontally arranged rack 964 is provided on the inner wall of the third notch 963, and the rack 964 is meshed and placed below the driven gear 973.
[0126] In the above scheme:
[0127] When the two sets of side sealing plates 960 need to be moved outward, the double-headed threaded rod 980 rotates, and the double-headed threaded rod 980 drives the moving block 965 to move outward, and the moving block 965 drives the side sealing plates 960 to move outward. In this way, a complete shell structure can be formed. When the side sealing plates 960 move outward, the rack 964 passes under the driven gear 973 and drives the driven gear 973 to rotate, so that the self-rotating sealing plate 971 rotates to a horizontal open state and the torsion spring is compressed;
[0128] When the two sets of side sealing plates 960 need to move inward, the double-headed threaded rod 980 reverses, causing the two sets of moving blocks 965 to move inward, and the two sets of side sealing plates 960 move inward synchronously. The vibrating rod 990 extends relatively outward from the second notch 962, and the discharge pipe 970 extends relatively outward from the first notch 961. The rack 964 drives the driven gear 973 to reverse, causing the rotating sealing plate 971 to rotate and block the discharge pipe 970 until the vibrating rod 990 is exposed.
[0129] It should be noted that, in this document, relational terms such as first and second, etc., are used only to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply the existence of any such actual relationship or order between these entities or operations. Moreover, the terms "comprises," "comprising," or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article, or device comprising a series of elements includes not only those elements, but also other elements not explicitly listed, or elements inherent to such process, method, article, or device. In the absence of further limitations, an element defined by the phrase "comprising a ..." does not exclude the presence of other identical elements in the process, method, article, or device comprising the element.
[0130] The above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit the same. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or make equivalent replacements for some of the technical features therein. However, these modifications or replacements do not deviate the essence of the corresponding technical solutions from the spirit and scope of the technical solutions of the various embodiments of the present invention.
Claims
1. Thermal insulation and energy-saving assembled floor slab, characterized by: include: The main body of the floor slab is erected on the top of the supporting wall at both ends, and a group of injection holes are opened at both ends of its surface; The first steel cages are arranged transversely and at equal intervals longitudinally on the surface of the floor slab body, with the injection hole group being located between two groups of the first steel cages; the surface of the floor slab body is filled with an upper mortar layer, and the first steel cages are located in the upper mortar layer; A first locking member is mounted on the surface of the floor slab body and is positioned between the two sets of first reinforcement cages. The bottom of the first locking member extends downwardly outward from the floor slab body, and both ends of the first locking member are respectively pressed on one set of first reinforcement cages to position the first reinforcement cages. The lower formwork is spaced apart at the bottom of the main floor slab and between the two sets of supporting walls. The lower insulation layer is filled between the top of the lower formwork and the main floor slab. The injection hole group serves as an inlet and outlet channel for the mobile grouting device to fill the insulation mortar. The injection hole group also serves as the connection area between the upper mortar layer and the lower insulation layer. A second reinforcement cage is arranged transversely and at equal intervals longitudinally on the surface of the lower formwork, the second reinforcement cage being positioned below the middle portion between the two groups of first reinforcement cages; The second locking member is installed on the lower template. The top of the second locking member is connected to the bottom extension structure of the first locking member. The second locking member passes through the second steel cage longitudinally. The second locking member is placed at both ends of a group of second steel cages. The second locking member is used to hoist and position the second steel cage and the lower template.
2. The heat-insulating and energy-saving assembled floor slab according to claim 1, characterized in that: The first steel cage includes a first rod body, a second rod body and a first oblique rod body. The side walls of the first rod body are symmetrically provided with first oblique rod bodies extending downward. The first oblique rod bodies are arranged at intervals laterally. The bottom ends of the two groups of first oblique rod bodies are each provided with a second rod body. The first rod body and the two groups of second rod bodies form an isosceles triangle. The two groups of second rod bodies are placed on the surface of the floor main body.
3. The heat-insulating and energy-saving assembled floor slab according to claim 2, characterized in that: The first locking member includes a pressure rod, a first locking screw, and an arc plate. Two groups of arc plates are provided at both ends of the pressure rod. The two groups of arc plates at one end are respectively pressed on two second rod bodies of a group of first steel cages; symmetrical through-holes are opened in the middle of the pressure rod, and the first locking screw passes through the inside of the through-holes. The first locking screw is located on the inner side of the arc plate, and a first through-hole for the first locking screw to pass through is opened on the surface of the floor main body. The first locking screw passes through the first through-hole downward, and the outer wall of the first locking screw is threadedly connected to the first locking nut. The first locking nut contacts the bottom surface of the floor main body to fix the first locking member on the floor main body.
4. The heat-insulating and energy-saving assembled floor slab according to claim 3 is characterized in that: The second steel cage comprises a third rod, a fourth rod and a second oblique rod, and the side walls of the third rod are symmetrically provided with second oblique rods extending upward, the second oblique rods are arranged at intervals horizontally, and the tops of the two groups of second oblique rods are each provided with a fourth rod. The third rod and the two groups of fourth rods form an isosceles triangle, the two groups of fourth rods are placed on the surface of the floor main body, and the third rod is placed on the surface of the lower formwork.
5. The heat-insulating and energy-saving assembled floor slab according to claim 4 is characterized in that: The second locking member includes a supporting rod, a threaded sleeve and a second locking screw. The supporting rod is provided with a second through hole at a position relative to the first through hole. The supporting rod is sleeved on the bottom of the two groups of first locking screws. The bottom of the first locking screw extends outward from the second through hole. The portion of the first locking screw extending outward from the second through hole is threadedly connected to the second locking nut; the supporting rod passes between adjacent second oblique rod bodies and is placed at the bottom of the two groups of fourth rod bodies. Threaded sleeves are symmetrically provided at both ends of the bottom surface of the supporting rod. The second locking screw passes through the lower template from bottom to top and is screwed into the threaded sleeve; During the floor slab production phase, the second locking screw is screwed into the threaded sleeve to position the lower formwork; When the floor is in use, the second locking screw can be unscrewed and the threaded sleeve can be used as a reserved opening for the ceiling.
6. The heat-insulating and energy-saving assembled floor slab according to claim 5, characterized in that: Compensation blocks are provided at both ends of the surface of the support rod, the second through hole is located on the inner side of the compensation block, and the compensation block contacts the bottom surface of the floor slab body.
7. The heat-insulating and energy-saving assembled floor slab according to claim 5, characterized in that: The injection hole group includes a first grouting hole and a second grouting hole, and the first grouting hole and the second grouting hole are respectively placed at both ends of the floor slab body; An upper constraint groove is provided on the bottom surface of the floor slab body, and a lower constraint groove is provided on the surface of the lower formwork. The lower constraint groove is relatively located directly below the upper constraint groove; both ends of the upper constraint groove are connected to the first grouting hole and the second grouting hole respectively; A traction part is reserved inside the insulation cavity, which includes a rope body, a first buckle and a second buckle. The two ends of the rope body are connected to the first buckle and the second buckle. The rope body is placed at the bottom of the floor main body and the two ends extend outward to the first grouting hole and the second grouting hole respectively. The first buckle and the second buckle are respectively buckled at the two ends of the adjacent first steel cage.
8. A method for manufacturing a heat-insulating and energy-saving assembled floor slab, characterized by: The production method comprises the following steps: S1. Hoist and overlap the heat-insulating and energy-saving assembled floor slab described in claim 7 on the supporting wall; S2, filling of lower insulation layer: S2.
1. Undo the first and second buckles connected to the first reinforcement cage, and connect the second buckle to the mobile grouting device; S2.
2. Connect the mobile grouting device to the grouting pipe, and then place the mobile grouting device into the insulation chamber through the second grouting hole; S2.
3. Pull the first buckle outward to move the mobile grouting device along the insulation cavity to evenly fill the insulation cavity with insulation mortar; S2.
4. Pull out the grouting pipe to move the mobile grouting device in the opposite direction along the insulation cavity to fill and compact the insulation mortar for the second time; S2.
5. After one group of grouting holes is filled, the mobile grouting device is moved to the next group of grouting holes to complete the filling of the lower insulation layer; S3, filling the upper mortar layer: The grouting pipe is filled with mortar above the main body of the floor slab to form an upper mortar layer, and the upper mortar layer is connected to the lower insulation layer at the injection hole group.
9. The method for manufacturing a heat-insulating and energy-saving assembled floor slab according to claim 8, characterized in that: The mobile grouting device includes a front end plate, a rear end plate, a central tube, a discharge pipe and a vibrating rod. The front end of the central tube is fixedly connected to the front end plate, and the rear end is fixedly connected to the rear end plate. A connecting ring connected to the second buckle is provided in the middle of the outer wall of the front end plate. A docking joint is provided in the middle of the rear end plate. The docking joint is communicated with the central tube, and the docking joint is connected to the grouting pipe. An upper guard plate is provided on the top of the center tube and a lower guard plate is provided on the bottom. The two ends of the upper guard plate are flush connected to the front end plate and the rear end plate. The two ends of the lower guard plate are flush connected to the front end plate and the rear end plate. The surface of the upper guard plate is provided with an upper guide block that fits in the upper constraint groove. The bottom surface of the lower guard plate is provided with a lower guide block that fits in the lower constraint groove. The two ends of the side wall of the central tube are symmetrically connected with discharge pipes, and multiple groups of vibrating rods are symmetrically arranged in the middle of the side wall of the central tube; side sealing plates are symmetrically installed between the upper guard plate and the lower guard plate for sliding, and the side sealing plates are symmetrically placed on both sides of the central tube, and the side sealing plates are slidably fitted on the outer walls of the discharge pipe and the vibrating rods; In the discharge state, the two sets of side sealing plates move outwards, the discharge pipe opens to discharge materials, and the vibrating rod retracts into the inner side sealing plate; In the vibrating state, the two sets of side sealing plates move inward to close the discharge pipe and expose the vibrating rods, and multiple sets of vibrating rods work to compact the mortar.
10. The method for manufacturing a heat-insulating and energy-saving assembled floor slab according to claim 9, characterized in that: The side walls of the side sealing plates are symmetrically provided with moving blocks, which are slidably embedded in the front end plate and the rear end plate respectively. The front end plate and the rear end plate are built with double-headed threaded rods for driving the side sealing plates to move, and the double-headed threaded rods are threadedly connected to the moving blocks; a first notch is provided at a position where the side sealing plate is relative to the discharge pipe, and a second notch is provided at a position where the side sealing plate is relative to the vibrating rod; A self-rotating sealing plate is rotatably installed in the middle of the inner part of the discharge pipe, and a rotating shaft is provided in the middle of the two ends of the self-rotating sealing plate. The rotating shaft rotates and extends outward to the discharge pipe, and a torsion spring is installed at the rotating connection. A driven gear is provided at the outer end of the rotating shaft; a third notch is opened on the inner side of the first notch to avoid the driven gear, and a horizontally arranged rack is provided on the inner wall of the third notch, and the rack is meshed and placed below the driven gear.
Citation Information
Patent Citations
Fabricated disassembly-free heat preservation bottom die reinforcement cage floor support plate
CN119860054A
Prefabrication method for layered wall that can integrate tile and heat insulation layer without breakage
JP2025074075A