A protective earthen embankment and its deformation control method

By interlacing unidirectional and bidirectional geogrids in the protective earthen embankment, and combining them with anti-sliding nets and soil bag reverse wrapping design, the problem of insufficient connection strength of geogrids was solved, enabling stability and deformation detection of the earthen embankment and extending its service life.

CN120649424BActive Publication Date: 2026-01-06BOSTD GEOSYNTHETICS QINGDAO LTD
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202511156313.0
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2025-08-19
Publication Date
2026-01-06
Estimated Expiration
2045-08-19

AI Technical Summary

Technical Problem

Traditional protective earthen embankments suffer from structural deficiencies due to insufficient interlayer bonding strength of geogrids during long-term use. This makes it impossible to detect and address embankment deformation in a timely manner, affecting the protective effect and service life.

Method used

The method involves interleaving unidirectional geogrids and top-layer bidirectional geogrids, combined with anti-slip netting and soil bag reverse wrapping design. Stable connection and timely detection of the geogrids are achieved through connection structures and deformation detection components, and deformation is repaired by grouting reinforcement method.

Benefits of technology

It enhances the overall structural stability of the protective earthen embankment, enables timely detection and repair of geogrid deformation, and extends the service life and protective effect of the earthen embankment.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN120649424B_ABST
    Figure CN120649424B_ABST
Patent Text Reader

Abstract

This invention relates to the field of protective embankment technology and discloses a protective embankment and its deformation control method, comprising a foundation and several layers of unidirectional geogrids. A layer of unidirectional geogrid is laid on the surface of the foundation, and the several layers of unidirectional geogrids are laid sequentially from bottom to top, with a filling layer between adjacent unidirectional geogrids. A top layer of bidirectional geogrid is laid on the top of the embankment, and a filling layer is filled between the top bidirectional geogrid and the unidirectional geogrid below it. Soil bags are provided on both sides of the filling layer along the width of the embankment, and multiple soil bags are stacked vertically to form a unit bag. This protective embankment and its deformation control method, through the reverse-wrapping design of the unidirectional geogrids and soil bags, and the reverse-wrapping design between the anti-slip net and the soil bags, can effectively fix the sides of the geogrid, enhance the connection between the geogrid and the soil bags and the anti-slip net, thereby improving the overall structural stability of the protective embankment.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of protective earthen embankment technology, specifically to a protective earthen embankment and its deformation control method. Background Technology

[0002] Protective earthen dikes are dike-like structures constructed primarily of earth, with protective functions, often used to resist disasters such as floods, waves, and explosive impacts.

[0003] Traditional protective earthen embankments often experience deformation and decreased stability during long-term use due to soil pressure and external environmental factors. For example, as an important component of protective earthen embankments, insufficient interlayer bonding strength of geogrids can lead to insufficient overall structural stability, affecting the embankment's robustness. Furthermore, deformation of geogrids in existing protective earthen embankments is not readily detectable, making it difficult to identify problems promptly and take timely measures, thus impacting the embankment's service life and protective effectiveness. Summary of the Invention

[0004] To address the problems existing in the above background technology, the present invention is implemented through the following technical solution: a protective earthen embankment and its deformation control method, comprising a foundation and several layers of unidirectional geogrids, wherein a layer of unidirectional geogrids is laid on the surface of the foundation, and several layers of unidirectional geogrids are laid sequentially from bottom to top, with a filling layer filling between adjacent unidirectional geogrids; a top layer of bidirectional geogrids is laid on the top of the earthen embankment, and a filling layer filling between the top layer of bidirectional geogrids and the unidirectional geogrids below it.

[0005] The filling layer is provided with soil bags on both sides along the width of the embankment. Multiple soil bags are stacked on top of each other to form a unit bag. The unidirectional geogrid wraps around the unit bag from the outside to the top along both sides along the width of the embankment and extends from the upper surface of the unit bag into the interior of the embankment. The outer surface of the stacked unit bags is covered with anti-slip netting, and the upper and lower sides of the anti-slip netting extend into the interior of the embankment.

[0006] The unidirectional geogrid has connecting structures on both sides in the width direction and on both sides of the anti-slip net.

[0007] Furthermore, the side of the unidirectional geogrid passes upward through the unidirectional geogrid above it or the top bidirectional geogrid, and then passes downward back through the filling layer, thereby forming an "O" shaped cavity on the side of the unidirectional geogrid. The connecting structure on the side of the unidirectional geogrid is a second connecting rod, which is inserted into the "O" shaped cavity.

[0008] Furthermore, the anti-slip net has a "C" shaped structure, and the sides of two adjacent anti-slip nets are connected by a connecting structure, which is a connector. The connector fixes the sides of the two anti-slip nets together with the unidirectional geogrid and / or the top bidirectional geogrid superimposed on the anti-slip nets.

[0009] Furthermore, the connector is composed of an L-shaped upper connector and a lower connector. The lower surface of the upper connector is provided with several inserts, and the lower end of each insert is provided with a hemispherical plug. The surface of the lower connector is provided with an elastic slot that is adapted to the hemispherical plug.

[0010] Furthermore, T-shaped fixing steel bars are installed between the anti-slip net and the soil bag;

[0011] A fastener is installed in the middle of each layer of the unidirectional geogrid.

[0012] Furthermore, a control layer is laid on the surface of the anti-slip net, and a deformation detection component is installed in the control layer to detect whether the unidirectional geogrid is deformed.

[0013] Furthermore, several sets of the deformation detection components are vertically arranged on the side of the anti-slip net and pre-embedded in the control layer;

[0014] The deformation detection component includes a jacking pipe and multiple unit pipes, which are arranged sequentially from top to bottom. The upper end of the jacking pipe is provided with a port.

[0015] The unit tube includes a detection tube, a detection hose, and a connecting tube. The side surface of the detection tube has a side hole. The upper end of the detection hose is fixedly installed on the bottom end of the top tube or the previous detection tube, and the lower end is inverted "T" shape and sealed in the next detection tube. The side of the detection hose is connected to the corresponding unidirectional geogrid.

[0016] The connecting tube is located inside the detection tube. The lower end of the connecting tube is slidably and sealed in the detection hose at the bottom of the detection tube. The interior of the connecting tube is a through channel. A plug is fixedly provided on the outer surface of the connecting tube. The plug corresponds to the side hole. A connecting rod is provided between the bottom end of the connecting tube and the detection hose on its upper side.

[0017] Furthermore, the upper end of the internal channel of the connecting pipe is a spherical opening.

[0018] Furthermore, the deformation control method specifically includes:

[0019] Add liquid to the jacking pipe and observe whether liquid flows out from the side hole of the deformation detection component. If no liquid flows out, it is determined that the unidirectional geogrid is not deformed. If liquid flows out, it is determined that the corresponding unidirectional geogrid is deformed.

[0020] If the uniaxial geogrid is deformed, grouting reinforcement is used to fill and reinforce the corresponding layer of uniaxial geogrid until the deformation of that layer of uniaxial geogrid is restored.

[0021] Compared with the prior art, the present invention has the following beneficial effects:

[0022] 1. The protective earthen embankment and its deformation control method, through the reverse wrapping design of unidirectional geogrid and soil bags, as well as the reverse wrapping design between anti-slip net and soil bags, can effectively fix the sides of the geogrid, enhance the connection between the geogrid, soil bags and anti-slip net, thereby improving the overall stability of the protective earthen embankment structure.

[0023] 2. The protective embankment and its deformation control method utilize the design of a jacking pipe and multiple unit pipes in the deformation detection component. The side of the detection hose in the unit pipe is connected to the corresponding unidirectional geogrid. When the unidirectional geogrid deforms, the side hole is opened, and liquid is added to the jacking pipe. If liquid flows out of the side hole, it can be determined that the corresponding unidirectional geogrid has deformed. This detection method is simple to operate, provides accurate detection results, and can promptly detect the deformation of the unidirectional geogrid. Attached Figure Description

[0024] Figure 1 This is a schematic diagram of the cross-sectional structure of the earthen embankment of the present invention. Figure 1 ;

[0025] Figure 2 This is a schematic diagram of the cross-sectional structure of the earthen embankment of the present invention. Figure 2 ;

[0026] Figure 3 This is a three-dimensional schematic diagram of the cross-sectional structure of the earthen embankment of the present invention. Figure 1 ;

[0027] Figure 4 This is a schematic diagram of the cross-sectional structure of the earthen embankment of the present invention. Figure 1 ;

[0028] Figure 5 This is a three-dimensional schematic diagram of the cross-sectional structure of the earthen embankment of the present invention. Figure 2 ;

[0029] Figure 6 This is a schematic diagram of the cross-sectional structure of the earthen embankment of the present invention. Figure 2 ;

[0030] Figure 7 These are three views of the connector structure of the present invention;

[0031] Figure 8 For the present invention Figure 7 Schematic diagram of the closed and unfolded structure at point A in the middle;

[0032] Figure 9 This is a structural layout diagram of the connector of the present invention;

[0033] Figure 10 The three views of the fixed steel reinforcement structure of this invention;

[0034] Figure 11 This is a schematic diagram showing the distribution of the deformation detection components of the present invention;

[0035] Figure 12 This is a three-dimensional view of the deformation detection component structure of the present invention;

[0036] Figure 13 For the present invention Figure 12 Enlarged structural diagram at point B;

[0037] Figure 14 This is a schematic diagram of the connection structure between the unidirectional geogrid and the testing hose of the present invention.

[0038] In the diagram: 1. Foundation; 2. Bottom layer bidirectional geogrid; 3. Unidirectional geogrid; 4. Soil bag; 5. Fixing component; 6. Connecting structure; 61. Connecting component; 62. Connecting rod II; 7. Anti-slip net; 8. Top layer bidirectional geogrid; 9. Control layer; 10. Jacking pipe; 11. Unit pipe; 111. Detection pipe; 1111. Side hole; 112. Detection hose; 113. Connecting pipe; 1131. Block; 1132. Spherical opening; 114. Connecting rod; 12. Fixing reinforcement. Detailed Implementation

[0039] The technical solutions of the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of the present invention, and not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of the present invention.

[0040] An example of the protective earthen embankment and its deformation control method is as follows:

[0041] Please see Figures 1-14A protective earthen embankment and its deformation control method are disclosed. The protective earthen embankment includes a foundation 1 and several layers of unidirectional geogrids 3. A bottom layer of bidirectional geogrids 2 is laid inside the embankment. Crushed stone is filled below the bottom layer of bidirectional geogrids 2. A filling layer is formed between the bottom layer of bidirectional geogrids 2 and the unidirectional geogrids 3 above it. A layer of unidirectional geogrids 3 is laid on the surface of the foundation 1. Several layers of unidirectional geogrids 3 are laid sequentially from bottom to top. A filling layer is filled between adjacent unidirectional geogrids 3. A fixing member 5 is installed in the middle of each layer of unidirectional geogrids 3. Each layer of unidirectional geogrids 3 is composed of two unidirectional geogrids 3 spliced ​​together from left to right. The two unidirectional geogrids 3 in the same layer are connected by the fixing member 5, which is a connecting rod. The side of one unidirectional geogrid 3 passes upward through the other unidirectional geogrid 3 and then downward, so that the connection between the two unidirectional geogrids 3 forms an "O" shaped cavity. The connecting rod is inserted into the "O" shaped cavity.

[0042] The top of the embankment is covered with a top layer of bidirectional geogrid 8, and a filling layer is placed between the top layer of bidirectional geogrid 8 and the unidirectional geogrid 3 below it. The filling layer and subgrade material are laid on top of the top layer of bidirectional geogrid 8.

[0043] Soil bags 4 are set on both sides of the filling layer along the width of the embankment. Multiple soil bags 4 are stacked one on top of the other to form a unit bag. The unidirectional geogrid 3 wraps around the unit bag from the outside to the top along both sides of the width of the embankment and extends from the upper surface of the unit bag into the interior of the embankment. That is, every four layers of soil bags 4 wrap one layer of unidirectional geogrid 3. The outer surface of several stacked unit bags is covered with anti-slip net 7. The anti-slip net 7 is a three-dimensional mesh structure composed of bidirectional geogrid and three layers of folded net. The upper and lower sides of the anti-slip net 7 extend into the interior of the embankment, that is, the slope structure of the anti-slip net 7 wrapping. The unidirectional geogrid 3 and the anti-slip net 7 are provided with connecting structures 6 on both sides of the width direction and the upper and lower sides of the anti-slip net 7. T-shaped fixing steel bars 12 are installed between the anti-slip net 7 and the soil bags 4.

[0044] Every four layers of soil bags 4 are wrapped with a layer of unidirectional geogrid 3. After the unidirectional geogrid 3 is tightened, it is fixed to the ground with U-shaped nails. The remaining part is filled with soil and compacted. The side fold-back part of the unidirectional geogrid 3 is connected to the adjacent unidirectional geogrid 3 with connecting rod 2 62. Every length L (L is determined according to the longitudinal and transverse tensile strength of the anti-slip net 7 and the soil cover depth, not less than 1000mm and not more than 4000mm) a layer of anti-slip net 7 is wrapped. The bottom of the anti-slip net 7 is buried with a length M (M is not less than twice the width of the wrapped soil bag 4). The effective fold-back length of the top of the anti-slip net 7 is M. The anti-slip net 7 is fixed with fixing steel bars 12. The top of the fixing steel bars 12 is a horizontal 100mm*10mm*10mm steel bar, and the longitudinal part is a φ8 threaded steel bar. The steel bars are fixed to the steel bars by welding. The fixed reinforcing bars 12 are arranged with a transverse spacing of S and a longitudinal spacing of N (N is an integer multiple of the geogrid pitch). The arrangement pattern is a plum blossom pile, and the anti-slip net 7 and the transverse ribs of the unidirectional geogrid 3 are tied together with steel wire rope.

[0045] Example 1: The longitudinal and transverse tensile strength of the anti-slip net 7 is 6kN / m, the width of the soil bag 4 is 500mm, the pitch of the unidirectional geogrid 3 is 420mm, and the soil covering depth of the anti-slip net 7 is 100mm. Every four layers of soil bags 4 are wrapped around a layer of unidirectional geogrid 3. After the unidirectional geogrid 3 is tightened, it is fixed to the ground with U-shaped nails. The remaining part is filled with soil and compacted. The folded-back portion of the unidirectional geogrid 3 is connected to the adjacent layer of unidirectional geogrid 3 with connecting rod 62. Every 3000mm, a layer of anti-slip net 7 is wrapped around the net. The bottom of the anti-slip net 7 is buried for 1000mm, and the effective folded-back length of the top of the anti-slip net 7 is 1000mm. The anti-slip net 7 is fixed with fixing steel bars 12. The top of the fixing steel bars 12 is a horizontal 100mm*10mm*10mm steel bar, and the longitudinal part is a φ8 threaded steel bar. The steel bars are welded to the steel bars. The fixed reinforcing bars 12 are arranged with a horizontal spacing of 500mm and a vertical spacing of 420mm, in a plum blossom pile pattern, and the anti-slip net 7 and the transverse ribs of the unidirectional geogrid 3 are tied together with steel wire rope.

[0046] Example 2: The longitudinal and transverse tensile strength of the anti-slip net 7 is 4kN / m, the width of the soil bag 4 is 600mm, the pitch of the unidirectional geogrid 3 is 320mm, and the soil covering depth of the anti-slip net 7 is 50mm. Every four layers of soil bags 4 are wrapped around a layer of unidirectional geogrid 3. After the unidirectional geogrid 3 is tightened, it is fixed to the ground with U-shaped nails. The remaining part is filled with soil and compacted. The folded-back portion of the unidirectional geogrid 3 is connected to the adjacent layer of unidirectional geogrid 3 with connecting rod 62. Every 4000mm, a layer of anti-slip net 7 is wrapped around the net. The bottom of the anti-slip net 7 is buried for 1200mm, and the effective folded-back length of the top of the anti-slip net 7 is 1200mm. The anti-slip net 7 is fixed with fixing steel bars 12. The top of the fixing steel bars 12 is a horizontal 100mm*10mm*10mm steel bar, and the longitudinal part is a φ8 threaded steel bar. The steel bars are welded to the steel bars. The fixed reinforcing bars 12 are arranged with a horizontal spacing of 500mm and a vertical spacing of 320mm, in a plum blossom pile pattern, and the anti-slip net 7 and the transverse ribs of the unidirectional geogrid 3 are tied together with steel wire rope.

[0047] It should be noted that the side of the unidirectional geogrid 3 passes upward through the unidirectional geogrid 3 above it or the top bidirectional geogrid 8, and then passes downward back through the filling layer, thus forming an "O" shaped cavity on the side of the unidirectional geogrid 3. The connecting structure 6 on the side of the unidirectional geogrid 3 is a connecting rod 62, which is inserted into the "O" shaped cavity.

[0048] It should also be noted that the anti-slip net 7 has a "C" shaped structure. The sides of two adjacent anti-slip nets 7 are connected by a connecting structure 6. The connecting structure 6 is a connector 61, which fixes the sides of the two anti-slip nets 7 together with the unidirectional geogrid 3 and / or the top bidirectional geogrid 8 superimposed on the anti-slip nets 7.

[0049] The connector 61 consists of an L-shaped upper connector and a lower connector. The lower surface of the upper connector is provided with several inserts, and the lower end of each insert is provided with a hemispherical plug. The surface of the lower connector is provided with a flexible slot that is compatible with the hemispherical plug. The lower end of one side of the upper connector is provided with a spherical body, and one side surface of the lower connector is provided with a spherical notch.

[0050] That is, connector 61 consists of two parts: a plate with gourd-shaped and mushroom-shaped grooves (lower connector) and a plate with gourd-shaped and mushroom-shaped protrusions (upper connector). The upper connector can be snapped into the lower connector like a buckle. The gourd and mushroom shapes ensure that the protrusions can easily fit into the grooves and will not easily pull out. Each mushroom-shaped protrusion has two buckles, which, together with the gourd-shaped protrusions, can accommodate the thickness variation between the geogrid and the anti-slip net 7. The gourd-shaped protrusions and the small notch at one end of the lower connector ensure that after one side of the gourd-shaped protrusion of the upper connector is snapped in, the other side can rotate. This way, when the anti-slip net 7 and the unidirectional geogrid 3 are placed between the two plates, it is not necessary to specifically align the grooves.

[0051] Based on this, a control layer 9 is laid on the surface of the anti-slip net 7, and a deformation detection component is installed in the control layer 9 to detect whether the unidirectional geogrid 3 is deformed.

[0052] It should be noted that several sets of deformation detection components are vertically arranged on the side of the anti-slip net 7 and pre-embedded in the control layer 9; the deformation detection components include a jacking pipe 10 and multiple unit pipes 11, which are distributed from top to bottom. Each unit pipe 11 corresponds to a layer of unidirectional geogrid 3. The upper end of the jacking pipe 10 is provided with a port, and a cap is installed in the port. After the cap is opened, liquid can be added to the jacking pipe 10.

[0053] Unit pipe 11 includes detection pipe 111, detection hose 112, and connecting pipe 113. The side surface of detection pipe 111 has a side hole 1111. The upper end of detection hose 112 is fixedly installed on the bottom end of the top pipe 10 or the previous detection pipe 111, and the lower end is inverted "T" shape and sealed in the next detection pipe 111. The side of detection hose 112 is connected to the corresponding unidirectional geogrid 3. Anti-slip net 7 has a mesh structure. The side of unidirectional geogrid 3 corresponding to detection hose 112 is connected by a rigid connecting rod. The rigid connecting rod passes through the mesh of the anti-slip net 7 and is connected to the detection hose 112. One end of the rigid connecting rod is installed on the surface of unidirectional geogrid 3, and the other end can fit against the surface of detection hose 112. The rigid connecting rod and detection hose 112 can be connected together by binding with a strap.

[0054] The connecting pipe 113 is located inside the detection pipe 111. The lower end of the connecting pipe 113 is slidably and sealed in the detection hose 112 at the bottom of the detection pipe 111. The interior of the connecting pipe 113 is a through channel. A plug 1131 is fixedly provided on the outer surface of the connecting pipe 113. The plug 1131 corresponds to the side hole 1111. A connecting rod 114 is provided between the bottom end of the connecting pipe 113 and the detection hose 112 above it.

[0055] When the uniaxial geogrid 3 deforms, it will cause the corresponding detection hose 112 to move. The detection hose 112 drives the connecting pipe 113 to move through the connecting rod 114. The connecting pipe 113 drives the block 1131 to move, thereby opening the side hole 1111. When liquid is added to the top pipe 10, the liquid will flow into the space outside the connecting pipe 113 in the detection pipe 111 when it flows through the unit pipe 11, and then flow out from the side hole 1111. By observing whether liquid flows out from the side hole 1111, it can be determined whether the uniaxial geogrid 3 has deformed. At the same time, the liquid will enter the lower unit pipe 11 through the channel in the connecting pipe 113. Therefore, the deformation of all uniaxial geogrids 3 can be detected.

[0056] It should be noted that the upper end of the internal channel of the connecting pipe 113 is a spherical opening 1132. By designing the spherical opening 1132, it is easy for liquid to enter the outer space of the connecting pipe 113, and when the side hole 1111 is opened, it is easy for liquid to flow out.

[0057] The specific methods for controlling the deformation of protective earthen embankments include:

[0058] Add liquid to the jacking pipe 10 and observe whether liquid flows out at the side hole 1111 in the deformation detection component. If not, it is determined that the unidirectional geogrid 3 is not deformed. If it is, it is determined that the corresponding unidirectional geogrid 3 is deformed.

[0059] If the uniaxial geogrid 3 deforms, grouting reinforcement is used to fill and reinforce the corresponding layer of uniaxial geogrid 3 until the deformation of the uniaxial geogrid 3 in that layer is restored.

[0060] The construction steps for the protective earthen embankment slope are as follows:

[0061] S1. Excavation from base course to bottom bidirectional geogrid 2 elevation: Remove debris, excavate and level the base according to bottom bidirectional geogrid 2 elevation, and inspect the foundation bearing layer.

[0062] S2. Laying the first layer of anti-slip netting 7: Cut the anti-slip netting 7 as required, lay it in the specified position, and reserve the length required for the anti-slip netting 7 to wrap around itself. Fix the anti-slip netting 7 and tighten it, using fixing steel bars 12 for securement. Before nailing in the fixing steel bars 12, tie them with wire ropes. After nailing in, use wire ropes to tie the anti-slip netting 7 and the transverse ribs of the unidirectional geogrid 3 together.

[0063] S3. Laying the first layer of unidirectional geogrid 3: Cut out the unidirectional geogrid 3 as required, lay it in the specified position, and reserve the length required for the unidirectional geogrid 3 to wrap around. Unfold the unidirectional geogrid 3 smoothly, tighten it to avoid wrinkles, and fix it to the ground with U-shaped nails every 1.5m-2m.

[0064] S4. Layered compaction of backfill soil: A certain amount of soil is laid on the uniaxial geogrid 3 and behind the soil bag 4. The other free end of the geogrid is pulled into the geogrid by a tension beam and pressed on with backfill soil. Soil is laid on the reinforcement to the specified thickness, and compacted in layers until the next main reinforcement layer is reached.

[0065] S5. Wrap the unidirectional geogrid 3 around the soil bag 4 and lay it on the backfill.

[0066] S6. Cut and position the unidirectional geogrid 3 as required, and use connecting rod 262 to connect this layer of unidirectional geogrid 3 to the reverse-wrapped unidirectional geogrid 3.

[0067] S7. Repeat steps S3-S6. When the length L is reached, use the anti-slip net 7 to wrap around the slope. After tightening, use the fixing steel bar 12 to fix the slope. Use the connector 61 to fix the unidirectional geogrid 3 and the anti-slip net 7 at the wrapping point.

[0068] S8. Repeat the above steps until the slope construction is completed.

[0069] S9. Lay a control layer 9 on the slope of the embankment. The control layer 9 consists of planting soil and planting turf. Before laying the control layer 9, install the deformation detection component on the surface of the anti-slip net 7, connect the unidirectional geogrid 3 to the corresponding detection hose 112, and then lay the control layer 9 and bury the deformation detection component in the control layer 9.

[0070] Although embodiments of the invention have been shown and described, it will be understood by those skilled in the art that various changes, modifications, substitutions and alterations can be made to these embodiments without departing from the principles and spirit of the invention, the scope of which is defined by the appended claims and their equivalents.

Claims

1. A protective earth embankment comprising a foundation (1), a number of layers of unidirectional geogrids (3), characterised in that: The surface of the foundation (1) is paved with a layer of unidirectional geogrid (3), a plurality of layers of unidirectional geogrid (3) are sequentially paved from bottom to top, and the adjacent unidirectional geogrid (3) is filled with a filling layer, and the top of the embankment is paved with a top layer of bidirectional geogrid (8), and the top layer of bidirectional geogrid (8) and the unidirectional geogrid (3) below it are filled with a filling layer; The filling layer is provided with a soil bag (4) on both sides along the width direction of the embankment, a plurality of soil bags (4) are stacked one above the other to form a unit bag, the unidirectional geogrid (3) is wrapped from the outside to the top along the two side edges of the embankment in the width direction, and extends from the upper surface of the unit bag to the inside of the embankment, and the outer surface of a plurality of stacked unit bags is paved with an anti-skid net (7), and the upper and lower side edges of the anti-skid net (7) extend to the inside of the embankment; The two side edges of the unidirectional geogrid (3) in the width direction and the upper and lower side edges of the anti-skid net (7) are provided with a connecting structure (6); The surface of the anti-skid net (7) is paved with a control layer (9), and a deformation detection assembly is installed in the control layer (9), and the deformation detection assembly is used to detect whether the unidirectional geogrid (3) deforms; A plurality of groups of deformation detection assemblies are vertically arranged on the side surface of the anti-skid net (7) and are pre-buried in the control layer (9); The deformation detection assembly comprises a top pipe (10) and a plurality of unit pipes (11), the top pipe (10) and the plurality of unit pipes (11) are sequentially distributed from top to bottom, and the upper end of the top pipe (10) is provided with a port; The unit pipe (11) comprises a detection pipe (111), a detection hose (112) and a communication pipe (113), a side hole (1111) is formed in the side surface of the detection pipe (111), the upper end of the detection hose (112) is fixedly installed in the top pipe (10) or the bottom end of the upper detection pipe (111), the lower end is inverted "T" shaped and is sealingly installed in the next detection pipe (111), and the side surface of the detection hose (112) is connected with the corresponding unidirectional geogrid (3); The communication pipe (113) is located in the detection pipe (111), the lower end of the communication pipe (113) is sealingly and slidingly installed in the detection hose (112) at the bottom end of the detection pipe (111), the inside of the communication pipe (113) is a through channel, a plug (1131) is fixedly arranged on the outer surface of the communication pipe (113), the plug (1131) corresponds to the side hole (1111), and a connecting rod (114) is arranged between the communication pipe (113) and the bottom end of the detection hose (112) above it.

2. The protective earth berm of claim 1, wherein: The side edge of the unidirectional geogrid (3) passes through the unidirectional geogrid (3) or the top layer of bidirectional geogrid (8) above it upwards, and then passes back into the filling layer, thereby forming an "O" cavity on the side edge of the unidirectional geogrid (3), and the connecting structure (6) of the side edge of the unidirectional geogrid (3) is a connecting rod two (62), and the connecting rod two (62) is inserted and installed in the "O" cavity.

3. The protective earth berm of claim 1, wherein: The anti-skid net (7) is in a "C" shape structure, and the side edges of two adjacent anti-skid nets (7) are connected by a connecting structure (6), the connecting structure (6) is a connecting piece (61), and the connecting piece (61) fixes the side edges of the two anti-skid nets (7) and the unidirectional geogrid (3) and / or the top bidirectional geogrid (8) stacked above and below the anti-skid nets (7) together.

4. The protective earth berm of claim 3, wherein: The connecting piece (61) is composed of an upper connecting body and a lower connecting body, the lower surface of the upper connecting body is provided with a plurality of insertion rods, the lower end of the insertion rod is provided with a hemispherical plug, and the surface of the lower connecting body is provided with an elastic insertion slot matched with the hemispherical plug.

5. The protective earth berm of claim 1, wherein: A T-shaped fixing steel bar (12) is arranged between the anti-skid net (7) and the soil bag (4). A fixing piece (5) is arranged in the middle of the unidirectional geogrid (3) of each layer.

6. The protective earth berm of claim 1, wherein: The upper end of the internal passage of the communication pipe (113) is a spherical port (1132).

7. A method for controlling the deformation of an earth protection embankment, using an earth protection embankment according to claim 6, characterized in that: The deformation control method is specifically: Liquid is added to the top pipe (10), and whether liquid flows out at the side hole (1111) of the deformation detection assembly is observed, if not, it is determined that the unidirectional geogrid (3) has not deformed, if yes, it is determined that the corresponding unidirectional geogrid (3) has deformed; If the unidirectional geogrid (3) deforms, a grouting reinforcement method is used to grout and fill and reinforce the position of the unidirectional geogrid (3) of the corresponding layer until the unidirectional geogrid (3) of the layer deforms and recovers.

Citation Information

Patent Citations

  • Shallowlayer and deeplayer integrated flexible protection facility for improving mechanical property of reinforced soil structure

    CN213625615U