Treatment construction process for floor settlement position of fabricated building body

By connecting the precast groove bottom with the cast-in-place structure, the problem of inconsistent support in the floor settlement area was solved, achieving stable fixation and improved space utilization.

CN120946100AActive Publication Date: 2025-11-14CHINA WATER CONSERVANCY & HYDROPOWER NO 9 ENG BUREAU CO LTD +1
View PDF 10 Cites 0 Cited by

Patent Information

Application Number
CN202511125296.4
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2025-08-12
Publication Date
2025-11-14
Estimated Expiration
2045-08-12

AI Technical Summary

Technical Problem

The grooves in the settlement area of ​​the existing building cause inconsistent heights of the steel formwork supporting the floor slab, resulting in the occupation of space below.

Method used

The prefabricated groove bottom and the cast-in-place body are connected by a combination of positioning steel plates, inner steel molds, reinforcing hangers and through bolts, which achieves a fixed connection between the prefabricated groove bottom and the cast-in-place body and avoids the need for multiple square timber supports at the bottom.

Benefits of technology

This method achieves stable fixation of the floor settlement groove, avoids space occupation caused by multiple square timber supports for the bottom formwork in the groove area, and improves construction efficiency and space utilization.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN120946100A_ABST
    Figure CN120946100A_ABST
Patent Text Reader

Abstract

The invention discloses a treatment construction process for a floor settlement position of a fabricated building body. The treatment construction process comprises a treatment construction process for constructing a trepanning construction structure at the floor settlement position. The vertical section of the cast-in-place body is poured through a pouring space formed by the inner steel die, the vertical section of the bottom steel die and the prefabricated groove bottom body, the top of the prefabricated groove bottom body is connected and limited with the horizontal section of the bottom steel die through the inner steel die and a reinforcing suspender, and the bottom of the prefabricated groove bottom body is connected and limited with the vertical section of the bottom steel die through a positioning steel plate. The weight of the prefabricated groove bottom body is transmitted to the bottom steel die, so that the bottom of the prefabricated groove bottom body does not need to be supported by a plurality of square timbers, and the problem that the descending space is further occupied due to the fact that the groove area bottom die is supported by a plurality of square timbers is solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to a construction structure for floor settlement without opening holes, belonging to the field of building construction technology. Background Technology

[0002] In a building structure, the recessed area that sinks downward will occupy the space below, resulting in inconsistent heights of the support rods that support the bottom steel formwork of the floor slab.

[0003] The existing building structure support technology for recessed areas, as described in Chinese Patent Publication No. CN217811195U, uses multiple square timbers to support the bottom formwork, which further occupies the space for the recessed area to descend. Summary of the Invention

[0004] To address the aforementioned technical problems, this invention provides a construction process for treating settlement at the floor level of prefabricated buildings.

[0005] The present invention is achieved through the following technical solutions.

[0006] The present invention provides a construction process for treating settlement at the floor level of a prefabricated building, comprising: a construction process for constructing an opening structure at the settlement point of the floor level.

[0007] The aforementioned construction process includes: a bottom steel formwork supported by support rods; a reinforcing hanger connected to the horizontal section of the bottom steel formwork via through bolt assemblies; an inner steel formwork connected to the reinforcing hanger; and positioning steel plates of the precast groove bottom body fixed at both ends to the bottom steel formwork and the inner steel formwork, so that the precast groove bottom body receives the fixed connection and force from the bottom steel formwork and the inner steel formwork, and the bottom of the precast groove bottom body does not require support. Concrete is poured into the pouring space formed by the inner steel formwork, the vertical section of the bottom steel formwork, and the precast groove bottom body to form a cast-in-place body. At this time, the cast-in-place body and the precast groove bottom body are connected and assembled by connecting bars, and the vertical section of the cast-in-place body and the precast groove bottom body form a floor settlement groove.

[0008] The construction structure for opening holes at the floor settlement location includes: A prefabricated groove bottom body with positioning steel plates embedded at both ends; The positioning steel plates at both ends of the precast groove bottom are fixed in accordance with the bottom steel mold and the inner steel mold.

[0009] The precast groove bottom with positioning steel plate has L-shaped cast-in-place bodies at both ends, and the vertical section of the cast-in-place body and the precast groove bottom form a floor settlement groove.

[0010] The precast groove bottom is pre-embedded with connecting ribs that extend into the cast-in-place body, and the precast groove bottom and the cast-in-place body are connected by the connecting ribs.

[0011] The bottom of the horizontal section of the bottom steel formwork has a support rod that provides support; the top of the inner steel formwork is fixedly connected to a reinforcing rod, the bottom surfaces of both ends of the reinforcing rod can contact the cast-in-place body, and the two ends of the reinforcing rod are fixedly connected to the horizontal section of the bottom steel formwork by through bolt assemblies.

[0012] An opening sleeve is pre-embedded in the cast-in-place body corresponding to the through bolt assembly, and the opening sleeve forms an opening for the bolt body of the through bolt assembly to pass through.

[0013] The beneficial effects of this invention are as follows: the vertical section of the cast-in-place body is poured through a casting space formed by the inner steel mold, the vertical section of the bottom steel mold, and the precast groove bottom body. The top of the precast groove bottom body is connected and limited to the horizontal section of the bottom steel mold through the inner steel mold and the reinforcing hanger. The bottom of the precast groove bottom body is connected and limited to the vertical section of the bottom steel mold through the positioning steel plate. The weight of the precast groove bottom body is transferred to the bottom steel mold, so that the bottom of the precast groove bottom body does not need to be supported by multiple square timbers. This solves the problem that the bottom mold of the groove area is supported by multiple square timbers, which leads to the further occupation of the descent space. Attached Figure Description

[0014] Figure 1 This is a schematic diagram of the structure of the present invention; In the figure: 1-Precast groove bottom; 11-Positioning steel plate; 12-Connecting rib; 2-Cast-in-place body; 3-Inner steel mold; 31-Telescopic rod; 4-Bottom steel mold; 41-Support rod; 5-Reinforcing hanger; 6-Through bolt assembly; 61-Opening sleeve. Detailed Implementation

[0015] The technical solution of the present invention is further described below, but the scope of protection is not limited to what is described.

[0016] See Figure 1 As shown.

[0017] This application discloses a construction structure for opening holes at floor settlement points, comprising: The prefabricated groove bottom 1 is constructed by prefabrication, and positioning steel plates 11 are pre-embedded at both ends of the prefabricated groove bottom 1.

[0018] The precast groove bottom 1 with positioning steel plate 11 has L-shaped cast-in-place bodies 2 at both ends. The vertical section of the cast-in-place body 2 and the precast groove bottom 1 form a floor settlement groove. The precast groove bottom 1 has pre-embedded connecting bars 12 that extend into the cast-in-place body 2. The precast groove bottom 1 and the cast-in-place body 2 are connected by the connecting bars 12.

[0019] The positioning steel plates 11 at both ends of the precast groove bottom 1 are welded and fixedly connected to the inner steel mold 3 and the bottom steel mold 4. The inner steel molds 3 are supported by telescopic rods 31.

[0020] The bottom of the horizontal section of the bottom steel mold 4 has a support rod 41 for support; the top of the inner steel mold 3 is fixedly connected to a reinforcing rod 5 by bolts, and the two ends of the reinforcing rod 5 are connected to the horizontal section of the bottom steel mold 4 by through bolt assemblies 6; the cast-in-place body 2 corresponding to the through bolt assembly 6 has a pre-embedded opening sleeve 61, which forms an opening for the screw body of the through bolt assembly 6 to pass through.

[0021] During the casting of the cast-in-place body 2, the vertical section of the cast-in-place body 2 is cast through the casting space formed by the inner steel mold 3, the vertical section of the bottom steel mold 4, and the precast groove bottom body 1. The top of the precast groove bottom body 1 is connected and limited to the horizontal section of the bottom steel mold 4 through the inner steel mold 3 and the reinforcing hanger 5. The bottom of the precast groove bottom body 1 is connected and limited to the vertical section of the bottom steel mold 4 through the positioning steel plate 11. The weight of the precast groove bottom body 1 is transferred to the bottom steel mold 4, so that the bottom of the precast groove bottom body 1 does not need to be supported by multiple square timbers. This solves the problem that the bottom mold of the groove area is supported by multiple square timbers, which leads to the further occupation of the descending space.

[0022] This application discloses a construction process for treating floor settlement in prefabricated buildings, particularly a construction process for creating openings at floor settlement points, comprising the following steps: The bottom steel mold 4 is supported by the support rod 41. The reinforcing hanger 5 is connected to the horizontal section of the bottom steel mold 4 by the through bolt assembly 6. The inner steel mold 3 is connected to the reinforcing hanger 5. The two ends of the positioning steel plate 11 of the precast groove bottom 1 are welded and fixed to the bottom steel mold 4 and the inner steel mold 3, so that the precast groove bottom 1 is fixedly connected to the bottom steel mold 4 and the inner steel mold 3 and bears the force. The bottom of the precast groove bottom 1 does not need to be supported. Concrete is poured into the pouring space formed by the inner steel mold 3, the vertical section of the bottom steel mold 4 and the precast groove bottom 1 to form the cast-in-place body 2. At this time, the cast-in-place body 2 and the precast groove bottom 1 are connected and assembled by the connecting bar 12. The vertical section of the cast-in-place body 2 and the precast groove bottom 1 form a floor settlement groove.

Claims

1. A construction process for treating settlement at the floor level of a prefabricated building, characterized in that, include: Construction process for creating openings in the structure to address floor settlement.

2. The construction process for treating settlement at the floor level of a prefabricated building as described in claim 1, characterized in that: The construction process includes supporting the bottom steel mold (4) with a support rod (41), connecting the reinforcing rod (5) to the horizontal section of the bottom steel mold (4) with a through bolt assembly (6), connecting the inner steel mold (3) to the reinforcing rod (5), fixing the two ends of the positioning steel plate (11) of the precast groove bottom body (1) to the bottom steel mold (4) and the inner steel mold (3) respectively, so that the precast groove bottom body (1) can be fixed and connected to the bottom steel mold (4) and the inner steel mold (3) and the bottom of the precast groove bottom body (1) does not need to be supported; using concrete to pour into the pouring space formed by the inner steel mold (3), the vertical section of the bottom steel mold (4) and the precast groove bottom body (1) to form the cast-in-place body (2), at this time the cast-in-place body (2) and the precast groove bottom body (1) are connected and assembled by the connecting bar (12), and the vertical section of the cast-in-place body (2) and the precast groove bottom body (1) form a floor settlement groove.

3. The construction process for treating settlement at the floor level of a prefabricated building as described in claim 1 or 2, characterized in that, The construction structure for opening holes at the floor settlement location includes: A prefabricated groove bottom body (1) with positioning steel plates (11) embedded at both ends; The positioning steel plates (11) at both ends of the prefabricated groove bottom body (1) are fixed in correspondence with the bottom steel mold (4) and the inner steel mold (3).

4. The construction process for treating settlement at the floor level of a prefabricated building as described in claim 3, characterized in that: The precast groove bottom (1) with positioning steel plate (11) has L-shaped cast-in-place bodies (2) at both ends. The vertical section of the cast-in-place body (2) and the precast groove bottom (1) form a floor settlement groove.

5. The construction process for treating settlement at the floor level of a prefabricated building as described in claim 3, characterized in that: The precast groove bottom body (1) is pre-embedded with connecting ribs (12) extending into the cast-in-place body (2), and the precast groove bottom body (1) and the cast-in-place body (2) are connected by the connecting ribs (12).

6. The construction process for treating settlement at the floor level of a prefabricated building as described in claim 3, characterized in that: The bottom of the horizontal section of the bottom steel mold (4) has a support rod (41) that provides support; the top of the inner steel mold (3) is fixedly connected with a reinforcing rod (5), the bottom surfaces of both ends of the reinforcing rod (5) can contact the cast-in-place body (2), and the two ends of the reinforcing rod (5) are fixedly connected to the horizontal section of the bottom steel mold (4) by through bolt assemblies (6).

7. The construction process for treating settlement at the floor level of a prefabricated building as described in claim 6, characterized in that: An opening sleeve (61) is pre-embedded in the cast-in-place body (2) corresponding to the through bolt assembly (6), and the opening sleeve (61) forms an opening for the through bolt assembly (6) screw body to pass through.

Citation Information

Patent Citations

  • Circulating type rail top air duct hanging formwork assembly without drooping retaining wall

    CN217811195U

  • Prefabricating construction method for concrete flashing sill

    CN108487630A

  • Sinking type toilet suspension template structure and construction method thereof

    CN110821156A

  • Returnable descending board accurate positioning formwork lifting system and construction method thereof

    CN111997359A

  • Suspended cast-in-place caisson bin partition top plate structure

    CN214116704U