Rapid erection device and construction method for bridge flood damage beam and slab

The rapid erection device for bridge beams damaged by water utilizes a combination of beam erection trusses and related devices to achieve rapid and low-cost erection of bridge beams damaged by water, solving the problem of erecting bridge beams damaged by water in remote mountainous areas and other geologically constrained environments.

CN121519441APending Publication Date: 2026-02-13ROAD & BRIDGE INT CO LTD +1
View PDF 8 Cites 0 Cited by

Patent Information

Application Number
CN202512024936.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2025-12-30
Publication Date
2026-02-13

AI Technical Summary

Technical Problem

In existing bridge construction, especially in remote mountainous areas with poor transportation and limited geological conditions, it is difficult to quickly erect water-damaged beams and slabs, and the use of large lifting equipment is costly.

Method used

A rapid erection device for bridge beams damaged by water is adopted, which includes a beam erection truss, a pilot truss, a deflection adjustment device, a truss jacking device, a truss lifting device, a rolling support device, and an anchoring device. Through the combined use of these devices, the rapid movement and precise positioning of the beam erection truss are achieved, avoiding reliance on large lifting equipment.

Benefits of technology

It enables the rapid and low-cost erection of beams and slabs for flood-damaged bridges without the use of large lifting equipment, and is suitable for construction scenarios with limited geological conditions, such as remote mountainous areas with poor transportation.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN121519441A_ABST
    Figure CN121519441A_ABST
Patent Text Reader

Abstract

The invention discloses a rapid erection device and construction method for a bridge flood damage beam slab, and the device comprises a beam slab erection truss, a pilot truss, a deflection adjusting device, a truss pushing device, a truss jacking device, a rolling supporting device, a counter-force device and an anchoring device, and the pilot truss is installed at the front end of the beam slab erection truss; the deflection adjusting device is installed at the front end of the pilot truss, the truss jacking devices are installed at the front end and the rear end of the beam plate erecting truss respectively, the rolling supporting device is arranged below the beam plate erecting truss, and the truss jacking devices are connected with the counter-force device. A transverse moving device is installed on a jacking cross beam of the truss jacking device, a beam plate erecting truss is connected with the transverse moving device, a supporting walking device is installed at the lower end of a jacking telescopic supporting column, a longitudinal sliding device is installed on a truss lower chord, and the lower end of the longitudinal sliding device is connected with a hoisting device. According to the method, beam and slab erecting construction of the flood-destroyed bridge can be completed on the basis that large hoisting equipment is not used, construction is rapid, and cost is low.
Need to check novelty before this filing date? Find Prior Art

Description

TECHNICAL FIELD

[0001] The present application relates to the technical field of bridge construction, in particular to a bridge water-damaged beam plate rapid erection device and construction method. BACKGROUND

[0002] With the development of the construction industry, the bridge construction technology is also developing steadily, and the number and scale of bridge engineering are expanding. When the bridge is under construction and the upper structure is damaged and replaced, the commonly used methods include bridge erection method, gantry crane installation, large lifting equipment (crawler crane) installation and other processes. These processes are greatly affected by the site and environment, and in the case of poor traffic environment and limited surrounding geological environment, a lot of manpower and material resources are often needed to handle. In remote mountainous areas, large lifting equipment usually cannot arrive in time, and cannot achieve the timely and rapid erection of water-damaged beam plates. Moreover, the use of large lifting equipment for construction has high cost of manpower and material resources. SUMMARY

[0003] The purpose of the present application is to provide a bridge water-damaged beam plate rapid erection device and construction method to solve the problems existing in the prior art, which can complete the erection of the beam plate of the water-damaged bridge without using large lifting equipment, and has the advantages of rapid construction and low cost.

[0004] To achieve the above-mentioned purpose, the present application provides the following solutions: The present application provides a bridge water-damaged beam plate rapid erection device, which comprises a beam plate erection truss, a pilot truss, a deflection adjusting device, a truss jacking device, a truss jacking device, a rolling support device, a counterforce device and an anchoring device. The pilot truss is installed at the front end of the beam plate erection truss, the deflection adjusting device is installed at the front side bottom of the pilot truss, and the deflection adjusting device is used to adjust the deflection of the whole pilot truss and beam plate erection truss after reaching the previous bridge deck, the truss jacking device is installed at the front and rear ends of the beam plate erection truss, the rolling support device is arranged below the beam plate erection truss, the rolling support device and the beam plate erection truss are in rolling contact, and the rolling support device is used to support the beam plate erection truss, the counterforce device is anchored to the roadbed and / or bridge deck through the anchoring device, the truss jacking device is connected with the counterforce device, and the truss jacking device is used to push the beam plate erection truss forward on the rolling support device under the support of the counterforce device. The truss jacking device comprises a jacking frame, the jacking frame comprises a jacking beam and jacking telescopic struts fixed at both ends of the jacking beam, a transverse moving device is installed on the jacking beam, the beam slab erection truss is connected with the transverse moving device, and the beam slab erection truss can be driven to move transversely along the jacking beam through the transverse moving device; a support walking device is installed at the lower end of the jacking telescopic strut, the support walking device can be extended downward out of the jacking telescopic strut or retracted into the jacking telescopic strut, and the jacking frame can be driven to move transversely through the support walking device. A longitudinal sliding device is installed on the truss lower chord of the beam slab erection truss, a hoisting device is connected at the lower end of the longitudinal sliding device, the hoisting device is used for hoisting a prefabricated beam slab, and the hoisted prefabricated beam slab can be moved longitudinally along the truss lower chord through the longitudinal sliding device.

[0005] Preferably, the deflection adjusting device comprises a support beam and a telescopic jacking device, one end of the support beam is rotationally connected to the front side bottom of the leading truss, the other end is a free end, a support roller is fixedly installed on the bottom surface of the support beam, the telescopic jacking device is arranged above the support beam, both ends of the telescopic jacking device are rotationally connected with the leading truss and the free end of the support beam respectively, and after reaching the previous bridge deck, the deflection adjusting device is supported on the previous bridge deck by the support roller at the bottom of the support beam, and the angle between the support beam and the leading truss is adjusted through the telescopic jacking device to realize the adjustment of the deflection.

[0006] Preferably, the truss pushing device comprises a jacking oil cylinder, a pushing oil cylinder and a slide rail assembly, the slide rail assembly comprises a slide rail and a sliding block, the slide rail is used for anchoring on the roadbed and / or the bridge deck, the sliding block is slidingly arranged on the slide rail, the cylinder barrel of the pushing oil cylinder is rotationally connected on the counterforce device, the piston rod of the pushing oil cylinder is rotationally connected on one side of the piston rod of the jacking oil cylinder, the cylinder barrel of the jacking oil cylinder is fixed on the sliding block, and the piston rod of the jacking oil cylinder can be telescopically extended to tightly press or loosen the beam slab erection truss.

[0007] Preferably, the support walking device is vertically slidingly connected at the lower end of the jacking telescopic strut, and a driving oil cylinder is connected between the support walking device and the jacking telescopic strut, the support walking device is driven to extend downward out of the jacking telescopic strut or retract into the jacking telescopic strut through the driving oil cylinder.

[0008] Preferably, the longitudinal sliding device is rollingly connected on the truss lower chord through a roller.

[0009] Preferably, the rolling support device includes a base and a plurality of rollers rotatably connected to the base, the base being anchored to the roadbed and / or bridge deck by the anchoring device.

[0010] Preferably, the telescopic lifting device is a hydraulic cylinder.

[0011] Preferably, the lifting telescopic support includes a fixed column, a movable column, and a telescopic cylinder. The upper end of the fixed column is fixed to the lifting beam, the movable column is slidably connected to the lower end of the fixed column, and the telescopic cylinder connects the fixed column and the movable column, driving the movable column to move up and down.

[0012] This invention also provides a method for rapid erection of bridge beams damaged by floods, using the aforementioned rapid erection device for bridge beams damaged by floods, and includes the following steps: (1) According to the needs of the construction site, the reaction device is anchored to the roadbed and / or bridge surface through the anchoring device, the truss jacking device is connected to the reaction device, and the rolling support device is anchored to the roadbed and / or bridge surface through the anchoring device. (2) The truss is transported to the location where the bridge needs to be erected and assembled to obtain the beam-plate erection truss; the pilot truss is installed at the front end of the beam-plate erection truss, the deflection adjustment device is installed at the front end of the pilot truss, the front and rear ends of the beam-plate erection truss are respectively connected to the lifting frame through the lateral moving device, the support walking device is installed at the lower end of the lifting telescopic column, and the longitudinal sliding device is installed on the lower chord of the truss; at this time, the beam-plate erection truss is placed on the rolling support device, and the truss jacking device is located below the beam-plate erection truss; (3) The beam-plate erection truss is pushed forward by the truss jacking device. After the deflection adjustment device reaches the previous span of the bridge, the deflection adjustment device is activated. The deflection adjustment device uses the previous span of the bridge as support to adjust the overall deflection of the pilot truss and the beam-plate erection truss. The beam-plate erection truss is pushed forward until the beam-plate erection truss reaches the predetermined position through the hole. (4) Start the truss lifting device at both ends to extend the lifting telescopic column and support it on the previous span of the bridge. Then remove the pilot truss and the deflection adjustment device. Continue lifting to make the beam erection truss reach the predetermined height for beam hoisting. (5) Extend the support walking device downwards, move the lifting frame laterally to the designated installation position through the support walking device, and then retract the support walking device into the lifting telescopic column, which supports it on the bridge surface. (6) The precast beam is hoisted onto the longitudinal sliding device by the hoisting device, and the hoisted precast beam is transported to the designated position by the longitudinal sliding device. Then the precast beam is lowered and the lateral position of the precast beam is further adjusted by the lateral moving device to accurately lower the precast beam onto the cap beam. (7) Repeat steps (5) and (6) to complete the installation of all precast beams and slabs.

[0013] The present invention achieves the following technical effects compared to the prior art: The bridge beam erection device and construction method provided by this invention utilize a rolling support device to support the beam erection truss, with rolling contact between the two. A truss jacking device, supported by a reaction device and an anchoring device, can push the beam erection truss forward on the rolling support device. Furthermore, a pilot truss and a deflection adjustment device ensure the beam erection truss can smoothly pass through the opening and reach its designated position. After the beam erection truss has passed through the opening, a truss lifting device provides temporary support, facilitating the removal of the pilot truss and deflection adjustment device. The pilot truss and deflection adjustment device are then removed. After the scaffolding and deflection adjustment device are installed, the jacking telescopic support column can be used to lift the beam slab to the predetermined hoisting height. The jacking frame is then moved laterally to the designated installation position via a support traveling device. A longitudinal sliding device transports the hoisted precast beam slab to the designated location. During the lowering process of the precast beam slab via the hoisting device, the lateral position of the precast beam slab is further adjusted by the lateral moving device, accurately placing the precast beam slab onto the cap beam, thus completing the erection of the precast beam slab. Then, the support traveling device moves laterally to the next installation position, and the installation of each precast beam slab is completed sequentially. Using this device, the erection of beam slabs for flood-damaged bridges can be completed without the use of large lifting equipment. Construction is fast and cost-effective, making it particularly suitable for remote mountainous areas with poor transportation and limited surrounding geological conditions. Attached Figure Description

[0014] To more clearly illustrate the technical solutions in the embodiments of the present invention or the prior art, the drawings used in the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For those skilled in the art, other drawings can be obtained based on these drawings without creative effort.

[0015] Figure 1 This is a schematic diagram of the rapid erection device for bridge beams damaged by water in an embodiment of the present invention before passing through the hole; Figure 2 This is a schematic diagram of the rapid erection device for bridge beams damaged by water in an embodiment of the present invention in a through-hole; Figure 3This is a schematic diagram of the bridge water-damaged beam erection device in an embodiment of the present invention, in which the deflection is adjusted in the passage through a deflection adjustment device. Figure 4 This is a side view of the bridge flood-damaged beam erection device in an embodiment of the present invention when the beam erection truss is in place. Figure 5 This is a schematic diagram of the connection structure between the pilot truss and the deflection adjustment device in this invention; Figure 6 This is a structural schematic diagram of the truss jacking device in the invention. Figure 7 This is a schematic diagram of the rolling support device in the invention.

[0016] In the diagram: 1-Beam and slab erection truss, 110-Truss lower chord, 2-Pilot truss, 3-Deflection adjustment device, 31-Support beam, 32-Telescopic lifting device, 33-Support roller, 4-Truss jacking device, 41-Lifting cylinder, 42-Pushing cylinder, 43-Slide rail, 44-Slider, 5-Truss lifting device, 51-Lifting crossbeam, 52-Lifting telescopic support column, 521-Fixed column, 522-Moving column, 523-Telescopic cylinder, 53-Lateral movement device, 54-Support walking device, 6-Rolling support device, 61-Base, 62-Roller, 7-Reaction device, 8-Anchoring device, 9-Roadbed, 10-Bridge deck, 11-Cap beam, 12-Longitudinal sliding device, 13-Lifting device, 14-Precast beam and slab. Detailed Implementation

[0017] The technical solutions of the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of the present invention, and not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of the present invention.

[0018] The purpose of this invention is to provide a rapid erection device and construction method for bridge beams damaged by floods, so as to solve the problems existing in the prior art. It can complete the erection of beams of flood-damaged bridges without the use of large lifting equipment, and the construction is fast and low-cost.

[0019] To make the above-mentioned objects, features and advantages of the present invention more apparent and understandable, the present invention will be further described in detail below with reference to the accompanying drawings and specific embodiments.

[0020] Example 1 like Figures 1-7As shown, this embodiment provides a rapid erection device for bridge beams damaged by water, including a beam erection truss 1, a pilot truss 2, a deflection adjustment device 3, a truss jacking device 4, a truss lifting device 5, a rolling support device 6, a reaction device 7, and an anchoring device 8. The pilot truss 2 is installed at the front end of the beam erection truss 1, and the deflection adjustment device 3 is installed at the bottom front side of the pilot truss 2. It is used to adjust the deflection of the pilot truss 2 and the beam erection truss 1 as a whole after reaching the previous span of the bridge deck, using the previous span as support. The beam-slab erection truss 1 is equipped with a truss lifting device 5 at each of its front and rear ends. A rolling support device 6 is located below the beam-slab erection truss 1 and makes rolling contact with the beam-slab erection truss 1 to provide rolling support for the beam-slab erection truss 1. A reaction device 7 is anchored to the roadbed 9 and / or bridge deck 10 through an anchoring device 8. A truss jacking device 4 is connected to the reaction device 7 and, supported by the reaction device 7, is used to jack the beam-slab erection truss 1 forward on the rolling support device 6. The truss lifting device 5 includes a lifting frame, which includes a lifting beam 51 and lifting telescopic supports 52 fixed to both ends of the lifting beam 51. A lateral moving device 53 is installed on the lifting beam 51. The beam-plate erecting truss 1 is connected to the lateral moving device 53. The lateral moving device 53 can drive the beam-plate erecting truss 1 to move laterally along the lifting beam 51. The lateral moving device 53 can be a mechanism with powered rollers. The powered rollers are driven by a drive motor, thereby driving the lateral moving device 53 to move laterally along the lifting beam 51. After the device 53 is connected to the beam-slab erection truss 1, it can drive the beam-slab erection truss 1 to move laterally under the action of the drive motor; the lower end of the lifting telescopic column 52 is equipped with a support walking device 54. The support walking device 54 can extend downwards into the lifting telescopic column 52 or retract into the lifting telescopic column 52. The support walking device 54 can drive the lifting frame to move laterally. The support walking device 54 can be a support roller. The support roller can extend downwards to roll and support on the bridge deck 10. Then, pushing the lifting frame can realize the lateral movement of the lifting frame. A longitudinal sliding device 12 is installed on the lower chord 110 of the beam-slab erection truss 1. The lower end of the longitudinal sliding device 12 is connected to a hoisting device 13. The hoisting device 13 is used to hoist the precast beam slab 14. The hoisted precast beam slab 14 can be moved longitudinally along the lower chord 110 of the truss through the longitudinal sliding device 12. The longitudinal sliding device 12 can be a mechanism with a roller assembly. This mechanism is rolled on the lower chord 110 of the truss through the roller assembly and can move longitudinally along the lower chord 110 of the truss. The precast beam slab 14 can be moved longitudinally along the lower chord 110 of the truss by pushing it.

[0021] This device supports the beam-slab erection truss 1 via a rolling support device 6. The two components roll in contact, resulting in low friction and facilitating the forward movement of the beam-slab erection truss 1. The truss jacking device 4, supported by the reaction device 7 and anchoring device 8, pushes the beam-slab erection truss 1 forward on the rolling support device 6. Furthermore, the pilot truss 2 and deflection adjustment device 3 ensure the beam-slab erection truss 1 smoothly passes through the hole and reaches its designated position. After the beam-slab erection truss 1 passes through the hole, the truss lifting device 5 provides temporary support for it, allowing for the removal of the pilot truss 2 and deflection adjustment device 3. After removing the pilot truss 2 and deflection adjustment device... After placement 3, the jacking telescopic support column 52 can be used to lift the beam truss 1 to the predetermined height for beam hoisting. The jacking frame is then moved laterally to the designated installation position via the support traveling device 54. The longitudinal sliding device 12 transports the hoisted precast beam 14 to the designated position. During the lowering process of the precast beam 14 via the hoisting device 13, the lateral position of the precast beam 14 is further adjusted by the lateral moving device 53 to accurately lower it onto the cap beam 11, thus completing the erection of the precast beam 14. Then, the support traveling device 54 moves it laterally to the next installation position, and the installation of each precast beam 14 is completed sequentially. Using this device, the erection of beams for flood-damaged bridges can be completed without the use of large lifting equipment. Construction is fast and cost-effective, making it particularly suitable for remote mountainous areas with poor transportation and limited surrounding geological conditions.

[0022] In this embodiment, the deflection adjustment device 3 includes a support beam 31 and a telescopic lifting device 32. The telescopic lifting device 32 can be a hydraulic cylinder. One end of the support beam 31 is rotatably connected to the bottom front side of the pilot truss 2, and the other end is a free end. Support rollers 33 are fixedly installed on the bottom surface of the support beam 31. The telescopic lifting device 32 is located above the support beam 31. Both ends of the telescopic lifting device 32 are rotatably connected to the pilot truss 2 and the free end of the support beam 31, respectively. After reaching the previous span 10, the deflection adjustment device 3 is supported on the previous span 10 by the support rollers 33 at the bottom of the support beam 31. The angle between the support beam 31 and the pilot truss 2 is adjusted by the extension and retraction of the telescopic lifting device 32 to achieve the deflection adjustment, so that the pilot truss 2 and the beam-plate erection truss 1 can remain horizontal and smoothly pass through the hole to reach the predetermined position.

[0023] In this embodiment, the truss jacking device 4 includes a lifting cylinder 41, a pushing cylinder 42, and a slide rail assembly. The slide rail assembly includes a slide rail 43 and a slider 44. The slide rail 43 is used to anchor to the roadbed 9 and / or the bridge deck 10. The slider 44 is slidably disposed on the slide rail 43. The cylinder of the pushing cylinder 42 is rotatably connected to the reaction device 7. The piston rod of the pushing cylinder 42 is rotatably connected to one side of the piston rod of the lifting cylinder 41. The cylinder of the lifting cylinder 41 is fixed to the slider 44. The piston rod of the lifting cylinder 41 can extend and retract to tighten or loosen the beam plate to erect the truss 1. During the jacking process, the piston rod of the lifting cylinder 41 extends and presses against the beam-plate erecting truss 1. Then, the piston rod of the pushing cylinder 42 extends, pushing the lifting cylinder 41 to move along the slide rail 43. Rubber pads to increase friction can be placed on the contact surface between the piston rod of the lifting cylinder 41 and the beam-plate erecting truss 1, so that the beam-plate erecting truss 1 can be moved forward through friction. After one jacking operation, the piston rod of the lifting cylinder 41 retracts to its original position, and the piston rod of the pushing cylinder 42 retracts to its original position. This process is repeated to achieve continuous jacking of the beam-plate erecting truss 1.

[0024] In this embodiment, the supporting walking device 54 is vertically slidably connected to the lower end of the lifting telescopic column 52. A driving cylinder is connected between the supporting walking device 54 and the lifting telescopic column 52. The driving cylinder drives the supporting walking device 54 to extend downwards into the lifting telescopic column 52 or retract into the lifting telescopic column 52. When lateral movement is required, the supporting walking device 54 is extended downwards to move laterally via its rollers. After moving into position, the supporting walking device 54 is retracted, and the lifting telescopic column 52 continues to provide support, improving the stability of the support.

[0025] In this embodiment, the longitudinal sliding device 12 is connected to the lower chord 110 of the truss by rollers to reduce the moving friction and facilitate the longitudinal movement of the precast beam slab 14.

[0026] In this embodiment, the rolling support device 6 includes a base 61 and a plurality of rollers 62 rotatably connected to the base 61. The base 61 is anchored to the roadbed 9 and / or bridge deck 10 by an anchoring device 8. The rolling support device 6 can also be an existing heavy-duty displacement device, which is placed upside down on the roadbed 9 and / or bridge deck 10 and then anchored.

[0027] In this embodiment, the lifting telescopic support column 52 includes a fixed column 521, a movable column 522, and a telescopic cylinder 523. The upper end of the fixed column 521 is fixed to the lifting beam 51, and the movable column 522 is slidably connected to the lower end of the fixed column 521. The telescopic cylinder 523 connects the fixed column 521 and the movable column 522, and drives the movable column 522 to move up and down. The structure is simple and the control is convenient.

[0028] Example 2 This embodiment provides a method for rapid erection of bridge beams damaged by floods, using the rapid erection device for bridge beams damaged by floods described in Embodiment 1, including the following steps: (1) According to the needs of the construction site, the reaction device 7 is anchored to the appropriate position of the roadbed 9 and / or bridge deck 10 through the anchoring device 8, the truss jacking device 4 is connected to the reaction device 7, and the rolling support device 6 is anchored to the appropriate position of the roadbed 9 and / or bridge deck 10 through the anchoring device 8; the anchoring method of the anchoring device 8 can be the same as the method of chemical anchoring with rebar. (2) Transport the truss to the location where the bridge needs to be erected and assemble it to obtain the beam-slab erection truss 1; install the pilot truss 2 at the front end of the beam-slab erection truss 1, install the deflection adjustment device 3 at the front end of the pilot truss 2, connect the front and rear ends of the beam-slab erection truss 1 to the lifting frame through the lateral moving device 53, install the support walking device 54 at the lower end of the lifting telescopic support 52, and install the longitudinal sliding device 12 on the lower chord 110 of the truss; at this time, the beam-slab erection truss 1 is placed on the rolling support device 6, and the truss jacking device 4 is located below the beam-slab erection truss 1. (3) Push the beam-plate erection truss 1 forward by truss jacking device 4. After the support beam 31 of the deflection adjustment device 3 reaches and contacts the previous span bridge deck 10, start the deflection adjustment device 3. The deflection adjustment device 3 uses the previous span bridge deck 10 as support and adjusts the overall deflection of the pilot truss 2 and the beam-plate erection truss 1 by telescopic jacking device 32 so that the overall pilot truss 2 and the beam-plate erection truss 1 remain horizontal. Continue to push the beam-plate erection truss 1 forward until the beam-plate erection truss 1 passes through the hole smoothly and reaches the predetermined position. (4) Start the truss lifting device 5 at both ends, so that the lifting telescopic column 52 extends and supports the bridge deck 10 of the previous span, and temporarily supports the beam erection truss 1. Then remove the pilot truss 2 and the deflection adjustment device 3; continue to lift so that the beam erection truss 1 reaches the predetermined height for beam hoisting. (5) Extend the support walking device 54 downwards, move the lifting frame laterally to the designated installation position through the support walking device 54, and then retract the support walking device 54 into the lifting telescopic column 52, which supports the bridge deck 10. (6) The precast beam 14 is hoisted onto the longitudinal sliding device 12 by the hoisting device 13, and the hoisted precast beam 14 is transported to the designated position by the longitudinal sliding device 12. Then the precast beam 14 is lowered, and the lateral position of the precast beam 14 is further adjusted by the lateral moving device 53, so that the precast beam 14 is accurately lowered onto the cap beam 11. (7) Repeat steps (5) and (6) to complete the installation of all precast beams and slabs 14.

[0029] After all the beams and slabs are installed, the lifting telescopic support 52 is retracted, the beam and slab erection truss 1 is lowered, and the hoisting device 13, longitudinal sliding device 12, etc. are removed in sequence.

[0030] Specific examples have been used to illustrate the principles and implementation methods of this invention. The descriptions of the above embodiments are only for the purpose of helping to understand the method and core ideas of this invention. Furthermore, those skilled in the art will recognize that, based on the ideas of this invention, there will be changes in the specific implementation methods and application scope. Therefore, the content of this specification should not be construed as a limitation of this invention.

Claims

1. A rapid erection device for bridge beams damaged by water, characterized in that: The system includes a beam-slab erection truss, a pilot truss, a deflection adjustment device, a truss jacking device, a truss lifting device, a rolling support device, a reaction device, and an anchoring device. The pilot truss is installed at the front end of the beam-slab erection truss. The deflection adjustment device is installed at the bottom front side of the pilot truss and is used to adjust the overall deflection of the pilot truss and the beam-slab erection truss after reaching the previous span of the bridge deck, using the previous span as support. One truss lifting device is installed at each of the front and rear ends of the beam-slab erection truss. The rolling support device is located below the beam-slab erection truss and rolls in contact with the beam-slab erection truss to provide rolling support. The reaction device is anchored to the roadbed and / or bridge deck through the anchoring device. The truss jacking device is connected to the reaction device and, supported by the reaction device, pushes the beam-slab erection truss forward on the rolling support device. The truss lifting device includes a lifting frame, which includes a lifting beam and lifting telescopic supports fixed to both ends of the lifting beam. A lateral moving device is installed on the lifting beam. The beam-plate erecting truss is connected to the lateral moving device, which can drive the beam-plate erecting truss to move laterally along the lifting beam. A support traveling device is installed at the lower end of the lifting telescopic support. The support traveling device can extend downwards from the lifting telescopic support or retract into the lifting telescopic support. The support traveling device can drive the lifting frame to move laterally. A longitudinal sliding device is installed on the lower chord of the truss supporting the beam and slab. The lower end of the longitudinal sliding device is connected to a hoisting device, which is used to hoist the precast beam and slab. The hoisted precast beam and slab can be moved longitudinally along the lower chord of the truss through the longitudinal sliding device.

2. The rapid erection device for bridge beams damaged by water as described in claim 1, characterized in that: The deflection adjustment device includes a support beam and a telescopic lifting device. One end of the support beam is rotatably connected to the front bottom of the pilot truss, and the other end is a free end. Support rollers are fixedly installed on the bottom surface of the support beam. The telescopic lifting device is located above the support beam, and its two ends are rotatably connected to the pilot truss and the free end of the support beam, respectively. After reaching the previous span, the deflection adjustment device is supported on the previous span by the support rollers at the bottom of the support beam, and the angle between the support beam and the pilot truss is adjusted by the extension and retraction of the telescopic lifting device to achieve deflection adjustment.

3. The rapid erection device for bridge beams damaged by water as described in claim 1, characterized in that: The truss jacking device includes a lifting cylinder, a pushing cylinder, and a slide rail assembly. The slide rail assembly includes a slide rail and a slider. The slide rail is used to anchor to the roadbed and / or bridge deck. The slider is slidably mounted on the slide rail. The cylinder of the pushing cylinder is rotatably connected to the reaction device. The piston rod of the pushing cylinder is rotatably connected to one side of the piston rod of the lifting cylinder. The cylinder of the lifting cylinder is fixed to the slider. The piston rod of the lifting cylinder can extend and retract to tighten or loosen the beam plate to erect the truss.

4. The rapid erection device for bridge beams damaged by water as described in claim 1, characterized in that: The supporting walking device is vertically slidably connected to the lower end of the lifting telescopic column. A driving cylinder is connected between the supporting walking device and the lifting telescopic column. The driving cylinder drives the supporting walking device to extend downwards into the lifting telescopic column or retract into the lifting telescopic column.

5. The rapid erection device for bridge beams damaged by water as described in claim 1, characterized in that: The longitudinal sliding device is connected to the lower chord of the truss by rollers.

6. The rapid erection device for bridge beams damaged by water as described in claim 1, characterized in that: The rolling support device includes a base and a plurality of rollers rotatably connected to the base, the base being anchored to the roadbed and / or bridge deck by the anchoring device.

7. The rapid erection device for bridge beams damaged by water as described in claim 2, characterized in that: The telescopic lifting device is a hydraulic cylinder.

8. The rapid erection device for bridge beams damaged by water as described in claim 1, characterized in that: The lifting telescopic support includes a fixed column, a movable column, and a telescopic cylinder. The upper end of the fixed column is fixed to the lifting beam, the movable column is slidably connected to the lower end of the fixed column, and the telescopic cylinder connects the fixed column and the movable column, driving the movable column to move up and down.

9. A method for rapid erection of bridge beams damaged by water, characterized in that, Construction using the rapid erection device for bridge beams damaged by water, as described in any one of claims 1 to 8, includes the following steps: (1) According to the needs of the construction site, the reaction device is anchored to the roadbed and / or bridge surface through the anchoring device, the truss jacking device is connected to the reaction device, and the rolling support device is anchored to the roadbed and / or bridge surface through the anchoring device. (2) The truss is transported to the location where the bridge needs to be erected and assembled to obtain the beam-plate erection truss; the pilot truss is installed at the front end of the beam-plate erection truss, the deflection adjustment device is installed at the front end of the pilot truss, the front and rear ends of the beam-plate erection truss are respectively connected to the lifting frame through the lateral moving device, the support walking device is installed at the lower end of the lifting telescopic column, and the longitudinal sliding device is installed on the lower chord of the truss; at this time, the beam-plate erection truss is placed on the rolling support device, and the truss jacking device is located below the beam-plate erection truss; (3) The beam-plate erection truss is pushed forward by the truss jacking device. After the deflection adjustment device reaches the previous span of the bridge, the deflection adjustment device is activated. The deflection adjustment device uses the previous span of the bridge as support to adjust the overall deflection of the pilot truss and the beam-plate erection truss. The beam-plate erection truss is pushed forward until the beam-plate erection truss reaches the predetermined position through the hole. (4) Start the truss lifting device at both ends to extend the lifting telescopic column and support it on the previous span of the bridge. Then remove the pilot truss and the deflection adjustment device. Continue lifting to make the beam erection truss reach the predetermined height for beam hoisting. (5) Extend the supporting walking device downwards, move the lifting frame laterally to the designated installation position through the supporting walking device, and then retract the supporting walking device into the lifting telescopic column, which supports it on the bridge surface. (6) The precast beam is hoisted onto the longitudinal sliding device by the hoisting device, and the hoisted precast beam is transported to the designated position by the longitudinal sliding device. Then the precast beam is lowered and the lateral position of the precast beam is further adjusted by the lateral moving device to accurately lower the precast beam onto the cap beam. (7) Repeat steps (5) and (6) to complete the installation of all precast beams and slabs.

Citation Information

Patent Citations

  • Bridge erecting machine for fast construction of prefabricated bridges

    CN109183618A

  • Bridge erecting machine for curved hole-passing girder erection and application method thereof

    CN109763430A

  • Four-front supporting leg system for bridge erecting machine and erecting method of four-front supporting leg system for bridge erecting machine

    CN110184945A

  • Expandable guide beam structure used in pushing and pier loading process

    CN118326840A

  • Rapid erection device and construction method for bridge flood damage beam and slab

    CN121023960A