Method and system for dynamically regulating and controlling pre-camber in pouring process of U-shaped simply-supported aqueduct

By using multi-source sensing modules and dynamic control algorithms, the pre-camber of the U-shaped simply supported aqueduct is monitored and adjusted in real time, solving the problems of insufficient construction accuracy and safety in traditional methods and achieving efficient and safe aqueduct construction.

CN121596727AActive Publication Date: 2026-03-03SINOHYDRO BUREAU 14 CO LTD +2
View PDF 7 Cites 0 Cited by

Patent Information

Application Number
CN202610107823.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-01-27
Publication Date
2026-03-03
Estimated Expiration
2046-01-27

Smart Images

  • Figure CN121596727A_ABST
    Figure CN121596727A_ABST
Patent Text Reader

Abstract

The invention discloses a pre-camber dynamic regulation and control method and system in the pouring process of a U-shaped simply-supported aqueduct, and relates to the technical field of hydraulic engineering construction.The method comprises the steps that longitudinal settlement, transverse unbalance loading, structural stress and temperature and humidity data are collected in real time through a multi-source sensing module; based on the transverse unbalance loading and structural stress data, a wet weight-settlement coupling model is constructed, and the concrete wet weight is calculated in real time; the load eccentric distance is calculated through the transverse unbalance load data so as to correct the influence of the torsional deformation of the bracket on the settlement; utilizing extended Kalman filtering to fuse the longitudinal settlement data to generate a pre-camber dynamic compensation amount; when the compensation amount exceeds a preset threshold value, a fuzzy PID controller is triggered to adjust the hydraulic jacking amount of a hydraulic servo jacking mechanism, and meanwhile the initial setting state of concrete is monitored; and after concrete pouring is completed, the electromagnetic valve is switched to release the hydraulic oil way, and the piston rod is pushed to reset to the initial position through the self-reset execution unit. And the construction precision and safety of the U-shaped aqueduct are ensured.
Need to check novelty before this filing date? Find Prior Art

Citation Information

Patent Citations

  • Self-adaptive load control method for aqueduct structure

    CN116988417A

  • Large-span bridge construction monitoring method

    CN117034400A

  • Intelligent monitoring and balancing method for cantilever casting unbalance loading of hanging basket

    CN117367672A

  • Continuous rigid frame bridge construction monitoring method

    CN120562172A

  • Large-span arch bridge reasonable arch axis design method based on hybrid algorithm and dynamic load