Mooring test system for waste heat turbine generator
By setting up steam generation units at the dock and steam storage devices on board, the problems of load testing and grid compatibility of the waste heat turbine generator system during the mooring phase of the ship were solved. Stable and controllable testing during the mooring phase was achieved, reducing sea trial risks and costs, and improving equipment reliability and delivery schedule.
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- GUANGZHOU SHIPYARD INTERNATIONAL LTD
- Filing Date
- 2026-02-28
- Publication Date
- 2026-05-12
AI Technical Summary
During the ship mooring phase, load testing and grid compatibility verification of the waste heat turbine generator system are difficult to complete at the dock, resulting in high risks, high costs, and uncertain delivery schedules during the sea trial phase.
A steam generation unit is installed at the dock and a steam storage device is installed on board to provide a stable and controllable source of superheated steam for load testing and grid connection testing of the waste heat turbine generator during the mooring phase, and the cleanliness of the pipeline is ensured by purging the passage.
The load test and grid connection coordination test of the turbine generator were completed during the mooring phase, which reduced the risk of sea trials, reduced the number of test items and time, reduced equipment costs, and improved equipment reliability and delivery schedule.
Smart Images

Figure CN122016360A_ABST
Abstract
Description
Technical Field
[0001] This application relates to the field of marine power system testing technology, and in particular to a waste heat turbine generator mooring test system. Background Technology
[0002] With increasingly stringent environmental requirements for ships, waste heat turbine generator systems are being gradually installed. These systems generate steam by heating exhaust gases from the main engine to drive electricity generation. They work in conjunction with diesel generators and shaft-driven generators to supply power to the ship's main electrical grid, becoming a crucial component of the ship's propulsion system. To ensure the reliability of these systems, according to classification society rules, after installation, the turbine generators must undergo load tests: 4 hours of operation at 100% rated load and 0.5 hours of operation at 110% rated load. Simultaneously, the high cleanliness of the steam piping must be maintained to prevent damage to the turbine impeller.
[0003] However, due to limited mooring capacity at the docks during the mooring phase, the main engines often cannot reach the load required for testing. Therefore, turbine generator testing is currently mainly conducted during the sea trial phase. However, conducting turbine generator testing during the sea trial phase still presents several challenges. First, the grid compatibility of three generator sets with different characteristics was not verified beforehand, significantly increasing the risk of sea trials. Second, the additional load cylinders required during sea trials not only increase the testing period but also incur high costs. Finally, the scheduling of procedures during the sea trial phase is complex, the success rate is uncertain, and this seriously affects the ship delivery schedule. Summary of the Invention
[0004] The purpose of this invention is to provide a waste heat turbine generator mooring test system that can solve the above-mentioned problems existing in the prior art.
[0005] To achieve the above objectives, this application adopts the following technical solution:
[0006] On the one hand, a waste heat turbine generator mooring test system is provided for conducting full-load and grid-connected tests on waste heat turbine generators during the ship's mooring phase, including: A steam generating unit, located on the dock, is configured to generate superheated steam; A steam storage device is installed on the ship and is configured to store and stabilize the superheated steam generated by the steam generating unit, providing superheated steam for the load test of the waste heat turbine generator, the grid connection and coordination test of the waste heat turbine generator with other generator sets on the ship, and the steam pipeline purging test; the first gas port of the steam storage device is connected to the gas outlet of the steam generating unit through a first pipeline. The waste heat turbine generator is connected to the second gas port of the steam storage device. The waste heat turbine generator is configured to receive superheated steam output from the steam storage device and conduct load tests and grid connection and coordination tests between the waste heat turbine generator and other generator sets on the ship during the mooring phase based on the superheated steam.
[0007] Preferably, the steam storage device is provided with a third air port and a fourth air port. The third air port is connected to the steam drum outlet of the forward cofferdam through a first purging passage, and the fourth air port is connected to the steam drum outlet of the aft cofferdam through a second purging passage. The second air port of the steam storage device is connected to the ship's outer hull discharge pipeline via the waste heat turbine generator through the third purging passage.
[0008] Preferably, a purge detector is provided at the outlet of the first purge passage, the second purge passage, and the third purge passage. The purge detector is configured to detect the amount of impurities remaining after the pipeline is purged in order to verify the cleanliness of the pipeline.
[0009] Preferably, the first pipeline includes: The first pipe section, the first end of the first pipe section is connected to the gas outlet of the steam generating unit; The second pipe section, the first end of the second pipe section is connected to the second end of the first pipe section; The third pipe section, the first end of which is connected to the second end of the second pipe section, and the second end of the third pipe section is connected to the first gas port of the steam storage device; The first pipe segment and the third pipe segment are configured as flexible pipe segments, and the second pipe segment is configured as a rigid pipe segment.
[0010] Preferably, the second pipe section is provided with multiple Ω-shaped expansion joints; when the second pipe section is conveying a high-temperature medium, the Ω-shaped expansion joints are configured to extend when the temperature of the medium conveyed in the second pipe section is higher than a preset temperature, and to contract when the temperature of the medium conveyed in the second pipe section is lower than the preset temperature.
[0011] Preferably, the second section of the first pipeline is made of seamless steel pipe, and the second section located on the boarding tower is arranged at a height higher than the normal water level by a preset height; the connection between the first section of the first pipeline and the outlet of the steam generating unit is fixed by a fixing bracket; the connection between the third section of the first pipeline and the first outlet of the steam storage device is fixed by a fixing bracket.
[0012] Preferably, the steam generating unit includes: A boiler is located on a dock; the boiler's outlet is connected to a first outlet of the steam storage device; the boiler is configured to generate superheated steam. An oil tank is located on the dock; the oil tank is connected to the oil supply pump of the boiler; the oil tank is configured to provide fuel for the operation of the boiler. A water tank is located on the dock; the water tank is connected to the water supply pump of the boiler; the water tank is configured to provide an initial water source for the boiler and to recover condensate after testing.
[0013] Preferably, a steam outlet valve is provided at the steam outlet of the boiler; the boiler is also provided with a safety valve.
[0014] Preferably, an inlet shut-off valve is provided at the first air port of the steam storage device, and an outlet shut-off check valve is provided at the second air port, the third air port and the fourth air port of the steam storage device.
[0015] Preferably, the steam generating unit is configured with a design pressure of 4 bar to 12 bar, a design temperature of 125°C to 375°C, and a steam output of 4.5 T / h to 12.5 T / h; the steam storage device is configured with a design pressure of 4 bar to 12 bar, a design temperature of 125°C to 375°C, and a volume ≥ 3.5 m³.
[0016] The beneficial effects of this application are as follows: This application provides a stable and controllable superheated steam source for turbine generator testing by coordinating an independently set steam generation unit on the dock with a steam storage device on board. This allows the load test and grid connection test of the waste heat turbine generator to be completed in advance during the ship's mooring phase, without relying on the main engine to generate waste heat steam. This overcomes the limitation of insufficient main engine load during the dock mooring phase, and can also reduce the number of test items and time occupied during the sea trial phase, reduce equipment operating costs, and shorten the construction cycle.
[0017] This application allows for grid compatibility verification of the waste heat turbine generator with other generator sets on board during the mooring phase, identifying and eliminating grid connection risks in advance, significantly reducing uncertainties and safety risks during the sea trial phase, and improving the success rate of the sea trial.
[0018] This application enables the simultaneous completion of the ship's steam pipeline purging test during the mooring phase, ensuring the cleanliness of the pipeline interior, preventing impurities from entering the turbine generator and damaging the impeller, and improving the reliability of equipment operation. Attached Figure Description
[0019] The present application will now be described in further detail with reference to the accompanying drawings and embodiments.
[0020] Figure 1 This is a front view structural schematic diagram of a waste heat turbine generator mooring test system provided in an embodiment of this application; Figure 2This is a top view of a waste heat turbine generator mooring test system provided in one embodiment of this application.
[0021] In the picture: 100. Steam generating unit; 110. Boiler; 120. Oil tank; 130. Water tank; 200. Dock; 300. Steam storage device; 400. Ship; 500. First pipeline; 600. Boarding tower; 700. Forward cofferdam steam drum. Detailed Implementation
[0022] To make the technical problems solved by this application, the technical solutions adopted, and the technical effects achieved clearer, the technical solutions of the embodiments of this application are further described in detail below. Obviously, the described embodiments are only some embodiments of this application, and not all embodiments. Based on the embodiments in this application, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of this application.
[0023] In the description of this application, unless otherwise expressly specified and limited, the terms "connected," "linked," and "fixed" should be interpreted broadly. For example, they can refer to a fixed connection, a detachable connection, or an integral part; they can refer to a mechanical connection or an electrical connection; they can refer to a direct connection or an indirect connection through an intermediate medium; they can refer to the internal communication of two components or the interaction between two components. Those skilled in the art can understand the specific meaning of the above terms in this invention based on the specific circumstances.
[0024] In this application, unless otherwise expressly specified and limited, "above" or "below" the second feature can include direct contact between the first and second features, or contact between the first and second features through another feature between them. Furthermore, "above," "over," and "on top" of the second feature includes the first feature being directly above or diagonally above the second feature, or simply indicates that the first feature is at a higher horizontal level than the second feature. "Below," "below," and "under" the second feature includes the first feature being directly below or diagonally below the second feature, or simply indicates that the first feature is at a lower horizontal level than the second feature.
[0025] Figure 1 This is a front view structural schematic diagram of a waste heat turbine generator mooring test system provided in an embodiment of this application; Figure 2 This is a top view of a waste heat turbine generator mooring test system provided in one embodiment of this application. Figures 1 to 2As shown, this embodiment provides a waste heat turbine generator mooring test system for conducting full-load and grid-connected tests on the waste heat turbine generator during the ship mooring phase. The system includes: a steam generation unit 100, a steam storage device 300, and a waste heat turbine generator. The steam generating unit 100 is installed on the dock 200 and configured to generate superheated steam. The steam storage device 300 is installed on the ship 400 and configured to store and stabilize the superheated steam generated by the steam generating unit 100, providing superheated steam for the waste heat turbine generator load test, the grid connection and coordination test of the waste heat turbine generator with other generator sets on the ship, and the steam pipeline purging test. The first air port of the steam storage device 300 is connected to the air outlet of the steam generating unit 100 through the first pipeline 500. The waste heat turbine generator is connected to the second air port of the steam storage device 300. The waste heat turbine generator is configured to receive the superheated steam output by the steam storage device 300 and conduct the waste heat turbine generator load test and the grid connection and coordination test of the waste heat turbine generator with other generator sets on the ship during the mooring phase based on the superheated steam.
[0026] This application provides a stable and controllable superheated steam source for turbine generator testing by coordinating an independently set steam generation unit on the dock with a steam storage device on board. This allows the load test and grid connection test of the waste heat turbine generator to be completed in advance during the ship's mooring phase, without relying on the main engine to generate waste heat steam. This overcomes the limitation of insufficient main engine load during the dock mooring phase, and can also reduce the number of test items and time occupied during the sea trial phase, reduce equipment operating costs, and shorten the construction cycle.
[0027] The vessel involved in this embodiment can be a passenger ro-ro ship. Accordingly, other generator sets on the vessel mentioned in this text generally refer to the main diesel generator set and the shaft-driven generator set of the passenger ro-ro ship. Furthermore, the main diesel generator set can serve as the core power supply unit during the ship's navigation and berthing operations, while the shaft-driven generator set generates electricity using the main engine shaft power. Here, the waste heat turbine generator, as an energy-saving power generation unit, needs to undergo grid-connected coordination tests with the main diesel generator set and the shaft-driven generator set to verify the compatibility of the three in terms of voltage, frequency, phase, and load distribution.
[0028] In this embodiment, passenger roll-on / roll-off ships generally have high requirements for the reliability of the power system and the stability of the power grid. The waste heat turbine generator mooring test system provided in this embodiment allows for the completion of load tests and grid-connected coordination tests of the waste heat turbine generator during the dock mooring phase. Furthermore, the grid-connected coordination test requires attention to the paralleling, disconnection, and load transfer capabilities between the waste heat turbine generator and the main diesel generator set, as well as the coordinated stability of the waste heat turbine generator and the shaft-driven generator set at different main engine speeds.
[0029] In one embodiment, the steam storage device 300 is provided with a third air port and a fourth air port. The third air port is connected to the outlet of the forward cofferdam steam drum 700 through a first purging passage, and the fourth air port is connected to the outlet of the aft cofferdam steam drum through a second purging passage. The second air port of the steam storage device 300 is connected to the waste heat turbine generator and the ship's outer hull discharge pipeline through a third purging passage. Here, the second air port is mainly connected to the inlet pipe of the disassembled waste heat turbine generator through the third purging passage. During operation, the steam storage device 300 outputs stable superheated steam, which is used to purge and clean the steam pipeline belonging to the forward cofferdam steam drum 700 through the first purging passage and the steam pipeline belonging to the aft cofferdam steam drum through the second purging passage. At the same time, the superheated steam can also purge the inlet pipe of the waste heat turbine generator through the third purging passage, discharging impurities in the pipeline through the outer hull discharge pipeline. In this embodiment, the first, second, and third purging passages are purged independently, which can more comprehensively maintain the cleanliness of the ship's steam pipeline, prevent impurities from entering the waste heat turbine generator and damaging the impeller, improve test safety and equipment operation reliability, and provide stable and reliable preconditions for the load test and grid-connected collaborative test of the waste heat turbine generator.
[0030] In one embodiment, purge detectors are installed at the outlet ends of the first, second, and third purge passages. These detectors are configured to detect the amount of residual impurities after pipeline purging, thereby verifying pipeline cleanliness. This embodiment, by installing purge detectors at the ends of the three purge passages, allows for early verification of the cleanliness of the entire steam pipeline during the mooring phase. This effectively prevents impurities such as welding slag and rust from entering the waste heat turbine generator and causing impeller damage, improving test safety and equipment operational reliability. Simultaneously, it reduces the risk of rework due to substandard pipeline cleanliness during sea trials, ensuring a smooth test process and successful delivery within the ship delivery cycle.
[0031] Furthermore, when the amount of residual impurities detected by the purge detector is below the preset threshold and there are no obvious hard particles, the cleanliness of the pipeline meets the safety operation requirements of the waste heat turbine generator. When the amount of residual impurities detected by the purge detector is above the preset threshold and there are obvious hard particles, the cleanliness of the pipeline does not meet the safety operation requirements of the waste heat turbine generator, and purging needs to continue until the amount of residual impurities detected by the purge detector is below the preset threshold and there are no obvious hard particles.
[0032] In one embodiment, the first pipeline 500 includes a first pipe segment, a second pipe segment, and a third pipe segment.
[0033] The first end of the first pipe section is connected to the outlet of the steam generating unit 100; the first end of the second pipe section is connected to the second end of the first pipe section; the first end of the third pipe section is connected to the second end of the second pipe section, and the second end of the third pipe section is connected to the first outlet of the steam storage device 300; the first pipe section and the third pipe section are configured as flexible pipe sections, and the second pipe section is configured as a rigid pipe section.
[0034] In this embodiment, the first and third pipe sections located at the equipment inlet and outlet are configured as flexible pipe sections. This can compensate for the relative displacement between the dock and the ship caused by tides, waves, or mooring conditions, preventing damage to the pipe interfaces due to shearing or pulling, and improving the sealing and reliability of the pipe connections. Furthermore, this embodiment configures the second pipe section located between the first and third pipe sections as a rigid pipe section to ensure stable and reliable support for the steam transport path, reduce pipe deformation and vibration, and improve the safety and stability during high-temperature and high-pressure steam transport.
[0035] The diameter of the first, second, and third pipe sections can be between 180mm and 220mm, which satisfies the steam flow requirements while also optimizing the pipeline layout space and facilitating installation.
[0036] In a preferred embodiment, the diameter of the first pipe section, the second pipe section and the third pipe section can be 200mm, which can be matched with standard interfaces to ensure sufficient steam flow area, which can meet the large flow and stable pressure steam supply required for high load test of waste heat turbine generator, and ensure stable and reliable test conditions.
[0037] In one embodiment, multiple Ω-shaped expansion joints are provided on the second pipe section. When the second pipe section is transporting a high-temperature medium, the Ω-shaped expansion joints are configured to extend when the temperature of the medium transported in the second pipe section is higher than a preset temperature, and to contract when the temperature of the medium transported in the second pipe section is lower than the preset temperature. This embodiment effectively absorbs the thermal expansion and contraction deformation caused by temperature changes during the transport of high-temperature steam in the second pipe section, reducing problems such as deformation, cracking, and loosening of joints due to thermal stress concentration in the pipeline. This ensures the structural strength and sealing reliability of the pipeline under high-temperature and variable-temperature conditions, making steam transport more stable and safe.
[0038] In one embodiment, the second section of the first pipeline 500 is made of seamless steel pipe, and the second section located on the boarding tower 600 is arranged at a height higher than the normal water level by a preset height. The connection between the first section of the first pipeline 500 and the outlet of the steam generating unit 100 is fixed by a fixing clip. The connection between the third section of the first pipeline 500 and the first outlet of the steam storage device 300 is also fixed by a fixing clip. In this embodiment, the second section is made of seamless steel pipe, which can withstand the long-term transportation of high-temperature and high-pressure superheated steam. Seamless steel pipe has high strength, good sealing performance, and is not easily deformed or leaked, which can ensure a stable and reliable steam supply. In addition, in this embodiment, the second section in the boarding tower 600 area is arranged higher than the normal water level, which can avoid the pipeline being soaked, corroded, or even damaged by tides and water accumulation, thereby improving the safety and service life of the waste heat turbine generator mooring test system in the dock mooring environment. At the same time, the fixing clips at the equipment inlet and outlet connections can limit the displacement of the pipeline ends, reduce the impact of vibration and tension on the interface, prevent flange loosening and steam leakage, and improve the reliability of the steam transmission pipeline connection.
[0039] In one embodiment, the steam generating unit 100 includes a boiler 110, an oil tank 120, and a water tank 130. The boiler 110 is mounted on a dock 200; the steam outlet of the boiler 110 is connected to a first steam outlet of the steam storage device 300; the boiler 110 is configured to generate superheated steam; the oil tank 120 is mounted on the dock 200; the oil tank 120 is connected to an oil supply pump of the boiler 110; the oil tank 120 is configured to provide fuel for the operation of the boiler 110; the water tank 130 is mounted on the dock 200; the water tank 130 is connected to a water supply pump of the boiler 110; the water tank 130 is configured to provide an initial water source for the boiler 110 and to recover condensate after testing.
[0040] In this embodiment, the boiler 110 is arranged on the dock 200, and an oil tank 120 and a water tank 130 are arranged next to the boiler 110 to facilitate the normal operation of the boiler 110. The oil tank 120 is mainly used to provide fuel for the boiler 110. The water tank 130 is mainly used to provide water for the boiler 110 and to recover condensate.
[0041] Furthermore, a steam outlet valve is provided at the steam outlet of the boiler 110 to control the opening and closing of the steam output path of the boiler 110 and to regulate the flow rate. By adjusting the steam outlet valve, it is easier to switch test conditions and adjust parameters.
[0042] Furthermore, the boiler 110 is also equipped with a safety valve. When the internal pressure of the boiler 110 exceeds a preset safety value, the safety valve can automatically open to release pressure, preventing the boiler 110 from operating under overpressure and ensuring safe use.
[0043] In one embodiment, an inlet shut-off valve is provided at the first air port of the steam storage device 300, and outlet shut-off check valves are provided at the second air port, the third air port and the fourth air port of the steam storage device 300.
[0044] Before starting the test, close all inlet shut-off valves and outlet shut-off check valves to ensure the waste heat turbine generator mooring test system is in standby mode. Start the steam generation unit 100. After the boiler 110 generates stable superheated steam, open the inlet shut-off valve. The superheated steam enters the steam storage device 300 through the first pipeline, where it is stored and pressure stabilized. At this time, the inlet shut-off valve can flexibly adjust the inlet flow rate according to the pressure inside the steam storage device 300 to ensure that the pressure inside the steam storage device 300 is maintained within the range required for the test. When the pressure inside the steam storage device 300 reaches the preset value, the outlet shut-off check valve at the corresponding outlet can be opened according to the test requirements. During pipeline purging tests, the outlet check valves at the third and fourth gas ports are opened. Steam flows through the first purging passage to the 700 outlet pipeline of the front cofferdam steam drum and through the second purging passage to the outlet pipeline of the rear cofferdam steam drum. Simultaneously, the outlet check valve at the second gas port is opened, and steam flows through the third purging passage to the inlet pipeline of the disassembled waste heat turbine generator, completing the synchronous or stepwise purging of the three pipelines. During load tests and grid-connected coordinated tests, the outlet check valves at the third and fourth gas ports are closed, and only the outlet check valve at the second gas port is opened to ensure a stable supply of steam to the waste heat turbine generator, providing continuous power for the tests. Finally, after the tests are completed, the inlet shut-off valve is closed first to cut off the steam supply, and then each outlet check valve is gradually closed. The system is shut down after cooling and depressurization.
[0045] In this embodiment, by setting an inlet shut-off valve, the opening and closing of the steam inlet passage and the regulation of the flow rate are realized, which can ensure the stable charging and pressure stabilization of the steam storage device 300 and avoid problems such as steam waste or pressure runaway. In addition, the outlet shut-off check valves set at each outlet can independently control the opening and closing of each gas path, realize flexible switching of different test conditions, and effectively prevent steam backflow, condensate backflow and other situations, avoid pressure fluctuations caused by cross-flow of gas between different gas paths, and prevent backflow steam from damaging the steam storage device 300 and pipelines.
[0046] In one embodiment, the steam generating unit 100 is configured with a design pressure of 4 bar to 12 bar, a design temperature of 125°C to 375°C, and a steam output of 4.5 T / h to 12.5 T / h; the steam storage device 300 is configured with a design pressure of 4 bar to 12 bar, a design temperature of 125°C to 375°C, and a volume ≥ 3.5 m³. Preferably, the steam generating unit 100 is configured with a design pressure of 8 bar, a design temperature of 250°C, and a steam output of 8.5 T / h; the steam storage device 300 is configured with a design pressure of 8 bar, a design temperature of 250°C, and a volume ≥ 3.5 m³.
[0047] This embodiment can stably output high-temperature, high-pressure superheated steam that meets the requirements of classification societies. It can guarantee the steam supply and pressure requirements of the waste heat turbine generator for 4 hours of operation at 100% rated load and 0.5 hours of operation at 110% rated load, and can also adapt to the flow rate and velocity required for pipeline purging. Furthermore, in this embodiment, the volume of the steam storage device 300 is set to be no less than 3.5 m³, which can effectively buffer steam pressure fluctuations and stabilize the output pressure, thereby ensuring the safe and reliable conduct of load tests, grid connection tests, and pipeline purging tests.
[0048] In the description herein, it should be understood that the terms "upper," "lower," "left," "right," and other orientations or positional relationships are used only for ease of description and simplification of operation, and do not indicate or imply that the device or element referred to must have a specific orientation, or be constructed and operated in a specific orientation, and therefore should not be construed as a limitation of this application. Furthermore, the terms "first" and "second" are used merely for descriptive distinction and have no special meaning.
[0049] In the description of this specification, references to terms such as "an embodiment," "example," etc., indicate that a specific feature, structure, material, or characteristic described in connection with that embodiment or example is included in at least one embodiment or example of the present invention. In this specification, illustrative expressions of the above terms do not necessarily refer to the same embodiment or example.
[0050] Furthermore, it should be understood that although this specification describes embodiments, not every embodiment contains only one independent technical solution. This narrative style of the specification is merely for clarity. Those skilled in the art should consider the specification as a whole, and the technical solutions in each embodiment can also be appropriately combined to form other embodiments that can be understood by those skilled in the art.
[0051] The technical principles of this application have been described above with reference to specific embodiments. These descriptions are merely for explaining the principles of this application and should not be construed as limiting the scope of protection of this application in any way. Based on this explanation, those skilled in the art can readily conceive of other specific embodiments of this application without inventive effort, and these embodiments will all fall within the scope of protection of this application.
Claims
1. A waste heat turbine generator mooring test system, used for conducting full-load and grid-connected tests of waste heat turbine generators during the ship's mooring phase, characterized in that, include: A steam generating unit (100) is installed on the dock (200) and configured to generate superheated steam; A steam storage device (300) is installed on the ship (400) and configured to store and stabilize the superheated steam generated by the steam generating unit (100) to provide superheated steam for the load test of the waste heat turbine generator, the grid connection and coordination test of the waste heat turbine generator and other generator sets on the ship, and the steam pipeline purging test; the first air port of the steam storage device (300) is connected to the air outlet of the steam generating unit (100) through the first pipeline (500); Waste heat turbine generator, which is connected to the second air port of the steam storage device (300), is configured to receive superheated steam output by the steam storage device (300) and conduct load tests on the waste heat turbine generator and grid connection and coordination tests between the waste heat turbine generator and other generator sets on the ship during the mooring phase based on the superheated steam.
2. The waste heat turbine generator mooring test system according to claim 1, characterized in that, The steam storage device (300) is provided with a third air port and a fourth air port. The third air port is connected to the outlet of the front cofferdam steam drum (700) through a first purging passage, and the fourth air port is connected to the outlet of the rear cofferdam steam drum through a second purging passage. The second air port of the steam storage device (300) is connected to the ship's outer side discharge pipeline through the waste heat turbine generator through the third purging passage.
3. The waste heat turbine generator mooring test system according to claim 2, characterized in that, The first, second, and third purging passages are all equipped with purging detectors at their outlet ends. The purging detectors are configured to detect the amount of impurities remaining after the pipeline is purged, in order to verify the cleanliness of the pipeline.
4. The waste heat turbine generator mooring test system according to claim 1, characterized in that, The first conduit (500) includes: The first pipe section, the first end of the first pipe section is connected to the outlet of the steam generating unit (100); The second pipe section, the first end of the second pipe section is connected to the second end of the first pipe section; The third pipe section, the first end of which is connected to the second end of the second pipe section, and the second end of the third pipe section is connected to the first gas port of the steam storage device (300); The first pipe segment and the third pipe segment are configured as flexible pipe segments, and the second pipe segment is configured as a rigid pipe segment.
5. The waste heat turbine generator mooring test system according to claim 4, characterized in that, Multiple Ω-shaped expansion joints are provided on the second pipe section; when the second pipe section is transporting a high-temperature medium, the Ω-shaped expansion joints are configured to extend when the temperature of the medium transported in the second pipe section is higher than a preset temperature, and to contract when the temperature of the medium transported in the second pipe section is lower than the preset temperature.
6. The waste heat turbine generator mooring test system according to claim 4, characterized in that, The second section of the first pipeline (500) is made of seamless steel pipe, and the second section located on the boarding tower (600) is arranged at a height higher than the normal water level by a preset height; the connection between the first section of the first pipeline (500) and the outlet of the steam generating unit (100) is fixed by a fixing bracket; the connection between the third section of the first pipeline (500) and the first outlet of the steam storage device (300) is fixed by a fixing bracket.
7. The waste heat turbine generator mooring test system according to claim 1, characterized in that, The steam generating unit (100) includes: A boiler (110) is installed on the dock (200); the steam outlet of the boiler (110) is connected to the first steam outlet of the steam storage device (300); the boiler (110) is configured to generate superheated steam. An oil tank (120) is provided on the dock (200); the oil tank (120) is connected to the oil supply pump of the boiler (110); the oil tank (120) is configured to provide fuel for the operation of the boiler (110); A water tank (130) is provided on the dock (200); the water tank (130) is connected to the water supply pump of the boiler (110); the water tank (130) is configured to provide an initial water source for the boiler (110) and to recover condensate after testing.
8. The waste heat turbine generator mooring test system according to claim 7, characterized in that, The boiler (110) is equipped with a steam outlet valve at the steam outlet; the boiler (110) is also equipped with a safety valve.
9. The waste heat turbine generator mooring test system according to claim 1, characterized in that, An inlet shut-off valve is provided at the first air port of the steam storage device (300), and an outlet shut-off check valve is provided at the second air port, the third air port and the fourth air port of the steam storage device (300).
10. The waste heat turbine generator mooring test system according to claim 1, characterized in that, The steam generating unit (100) is configured with a design pressure of 4 bar to 12 bar, a design temperature of 125°C to 375°C, and a steam output of 4.5 T / h to 12.5 T / h; the steam storage device (300) is configured with a design pressure of 4 bar to 12 bar, a design temperature of 125°C to 375°C, and a volume ≥ 3.5 m³.