By outputting a zero-voltage vector before the rectifier is put into operation and using the filter inductor to generate a current response, combined with sorting or angle matching methods to automatically identify the correspondence of rectifier terminals, the problem of incorrect wiring in the field of the rectifier is solved, and the equipment startup efficiency and operational stability are improved.
Patent Information
- Application Number
- CN202611347422.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2026-09-02
- Publication Date
- 2026-11-10
- Estimated Expiration
- 2046-09-02
AI Technical Summary
In the field wiring process of existing rectifiers, the actual correspondence between the input voltage detection terminals and the three-phase output terminals is prone to errors, requiring manual shutdown for troubleshooting and correction, resulting in unstable equipment operation and low debugging efficiency.
Before the rectifier is put into operation, the output zero voltage vector is used to generate a current response proportional to the grid phase voltage by the filter inductor. The terminal correspondence is automatically identified by combining the size sorting or vector angle matching method, and the phase sequence matching relationship is saved to adjust the control algorithm, avoiding manual inspection.
It enables automatic identification of terminal correspondence without relying on manual inspection, simplifies the debugging process, reduces professional skill requirements, improves startup efficiency, reduces overcurrent risk, adapts to different wiring methods, and does not require additional hardware detection circuits.
Smart Images

Figure CN122869963B_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of power electronic control technology, and specifically to a method for adaptive matching of the phase sequence of rectifier output and input voltages. Background Technology
[0002] A pulse width modulation rectifier, also known as an active front-end rectifier, is a power electronic device that uses fully controlled power devices and pulse width modulation technology to convert AC to DC. It features high power factor, low harmonic pollution, and bidirectional energy flow, and is widely used in industrial frequency converters, new energy power generation devices, and elevator energy feedback devices.
[0003] In the rectifier control process, to achieve precise synchronization between the rectifier output voltage and the grid voltage, the control algorithm needs to acquire the three-phase grid voltage information in real time through the input voltage detection terminals. Based on this voltage information, it generates a pulse-width modulation drive signal synchronized with the grid, which drives the power devices to complete the rectification function via the three-phase output terminals of the rectifier. Under normal circumstances, there is a pre-set one-to-one correspondence between the input voltage detection terminals and the three-phase output terminals. The grid voltage corresponding to a certain phase drive signal generated by the control algorithm should be obtained from the corresponding input voltage detection terminal. This correspondence is a prerequisite for the normal operation of the control algorithm.
[0004] However, rectifier products typically do not come with filters at the factory; the filter must be configured and installed by the user on-site according to actual needs. During on-site installation, the three-phase power supply from the grid needs to be connected to the filter before being connected to the three-phase output terminals of the rectifier. Simultaneously, the rectifier's input voltage detection terminals are connected to the grid to obtain a voltage synchronization signal. Due to complex on-site construction conditions and varying skill levels among construction personnel, wiring errors frequently occur, resulting in discrepancies between the actual wiring correspondence between the input voltage detection terminals and the three-phase output terminals and the pre-set correspondence. In this situation, the control algorithm generates pulse-width modulation drive signals based on incorrect voltage phase information, causing the rectifier output voltage to lose synchronization with the grid voltage. This can easily lead to overcurrent and overvoltage faults after the rectifier starts operating, and in severe cases, damage to power devices.
[0005] Currently, the common solution to the aforementioned wiring errors is for professionals to inspect the phase wiring relationships of the input voltage detection terminals one by one after the rectifier is shut down and powered off. Only after identifying, confirming, and correcting incorrect wiring can the rectifier be put back into operation. This method has the following drawbacks: First, it requires shutting down the equipment and disconnecting the power, affecting production efficiency; second, it requires skilled personnel to conduct on-site inspections, resulting in low debugging efficiency; and third, for large-scale equipment or complex installation environments, the time required for wiring inspection and rectification is long, increasing the overall on-site debugging cycle. Summary of the Invention
[0006] The technical problem to be solved by this invention is that, in the existing rectifier wiring process, the actual correspondence between the input voltage detection terminals and the three-phase output terminals is prone to errors and requires manual shutdown for inspection and correction. This invention provides a rectifier output input voltage phase sequence adaptive matching method, which can automatically identify the actual correspondence between the input voltage detection terminals and the three-phase output terminals before the rectifier is put into normal operation, and complete the phase sequence matching without relying on manual wiring inspection.
[0007] To solve the above-mentioned technical problems, the technical solution adopted by the present invention is: a rectifier output input voltage phase sequence adaptive matching method, wherein the three-phase output terminals of the rectifier are connected to the power grid through a filter inductor, and the method includes the following:
[0008] Before the rectifier is put into normal operation, the rectifier is controlled to output a zero voltage vector. The duration of the zero voltage vector is a preset duration. Under the action of the zero voltage vector, the grid voltage is applied to the three-phase output terminals of the rectifier through the filter inductor, generating three-phase output currents that are proportional to the grid voltage of the corresponding phase.
[0009] Within the preset time period, the three-phase output current is collected synchronously, and the three-phase grid voltage fed back from the three-phase input voltage detection terminal is obtained synchronously.
[0010] Based on the correspondence between the three-phase output current and the three-phase grid voltage, the actual correspondence between the three-phase output terminals of the rectifier and the three-phase input voltage detection terminals is determined, thus obtaining the phase sequence matching relationship. The methods for determining the actual correspondence include: sorting the three-phase output current and the three-phase grid voltage by numerical value, and determining the actual correspondence according to the correspondence of the sorted positions; alternatively, the three-phase output current can be transformed according to various possible arrangements between the three-phase output terminals and the three-phase input voltage detection terminals to obtain multiple current vector angles, and these multiple current vector angles are compared with the voltage vector angles corresponding to the three-phase grid voltages. The arrangement with the smallest angle difference is determined as the actual correspondence.
[0011] Based on the phase sequence matching relationship, the calling relationship between the three-phase grid voltage and the three-phase output terminal drive signal in the rectifier control algorithm is adjusted so that the rectifier generates pulse width modulation drive signal according to the adjusted calling relationship during subsequent operation.
[0012] Furthermore, the preset duration is determined based on the rectifier's filter inductance value, the rectifier's rated current, and the peak value of the grid phase voltage, so that the peak value of the three-phase output current generated under the zero voltage vector reaches a preset proportion of the rectifier's rated current. Within the preset duration, the three-phase output current can also be monitored in real time. When the current value of any phase reaches a preset current threshold, the output of the zero voltage vector is stopped in advance to reduce the risk of overcurrent.
[0013] Furthermore, the phase sequence matching relationship can be saved to a non-volatile storage device, and the saved phase sequence matching relationship can be directly read and called when the rectifier is restarted, without having to repeat the phase sequence matching learning process.
[0014] The beneficial effects that this invention can achieve are as follows: 1. By automatically identifying the actual correspondence between the input voltage detection terminals and the three-phase output terminals before the rectifier is put into normal operation, the process of having professionals check the wiring relationship one by one after shutdown, which is required in the existing technology, is avoided. This simplifies the on-site commissioning process and reduces the requirements for the professional skills of the commissioning personnel.
[0015] 2. The phase sequence matching learning process can be completed at the moment of each rectifier start-up. The preset duration determined by the filter inductance value and rated current is usually on the order of several milliseconds, which has little impact on the time required for the rectifier to start normally.
[0016] 3. Regardless of the actual wiring arrangement between the three-phase input voltage detection terminals and the power grid, the method described in this invention can determine the actual correspondence based on the collected correspondence between the three-phase output current and the three-phase power grid voltage, so that the rectifier can obtain the correct phase sequence matching relationship under different wiring arrangements.
[0017] 4. Once the phase sequence matching relationship is determined, it can be saved to a non-volatile storage device. When the rectifier is restarted in the future, the saved phase sequence matching relationship can be directly called, avoiding repeated matching learning process and further improving startup efficiency.
[0018] 5. By determining the preset duration of the zero-voltage vector based on the filter inductance value, the rectifier rated current, and the peak value of the grid phase voltage, and combining it with the real-time monitoring and early stop mechanism of the three-phase output current, the three-phase output current generated during the zero-voltage vector operation period is controlled within the preset proportion of the rectifier rated current, thereby reducing the risk of overcurrent damage to the rectifier power devices during the phase sequence matching learning process.
[0019] 6. The method described in this invention is based on the existing current detection unit and input voltage detection terminal of the rectifier, without the need to add additional hardware detection circuits or sensors, and has no special requirements on the existing hardware architecture of the rectifier. Attached Figure Description
[0020] The invention will now be further described with reference to the accompanying drawings.
[0021] Figure 1 This is a schematic diagram of the pulse width modulation rectifier system structure and input voltage detection wiring in an embodiment of the present invention; Figure 2 This is a block diagram illustrating the zero-voltage vector pulse detection principle in an embodiment of the present invention. Figure 3 This is a flowchart of the phase sequence matching learning method based on size sorting in an embodiment of the present invention; Figure 4 This is a flowchart of the phase sequence matching learning method based on vector angle matching in an embodiment of the present invention; Figure 5 This is a schematic diagram showing the location of the phase sequence matching learning function in the rectifier control system in an embodiment of the present invention. Detailed Implementation
[0022] The technical solutions of the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of the present invention, and not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of the present invention.
[0023] like Figure 1 As shown, the rectifier system in this embodiment includes a rectifier main circuit, a filter inductor, a current detection unit, a voltage detection unit, and a controller. The rectifier main circuit consists of three bridge arms, each including an upper switching transistor and a lower switching transistor. Each switching transistor is a fully controlled power device, such as an insulated-gate bipolar transistor (IGBT). The rectifier main circuit has three-phase output terminals, labeled U, V, and W, which are connected to the three phase lines of the power grid via the filter inductor. The inductance value of the filter inductor is denoted as L. In this embodiment, the filter inductor can be a standalone inductor or an input-side or output-side inductor in an LCL filter, configured and installed by the user on-site according to actual needs.
[0024] The rectifier also has three input voltage detection terminals, labeled R, S, and T, for acquiring the three-phase voltage information of the power grid. This information is used by the control algorithm to generate pulse-width modulation drive signals synchronized with the power grid. Theoretically, the R detection terminal corresponds to the U-phase output terminal, the S detection terminal to the V-phase output terminal, and the T detection terminal to the W-phase output terminal, meaning there is a pre-defined one-to-one correspondence between them. However, since the wiring between the three-phase output terminals and the filter inductor, as well as the wiring between the three-phase input voltage detection terminals and the power grid, are all completed by on-site construction personnel, the actual wiring relationships may differ from the pre-defined correspondences. There are six possible actual wiring arrangements, including one arrangement consistent with the pre-defined relationship and the other five arrangements. The method described in this invention is used to automatically identify the currently existing wiring arrangement before the rectifier is put into normal operation and adjust the calling relationships in the control algorithm accordingly.
[0025] The current detection units are respectively set on the current paths of the U, V, and W three-phase output terminals to detect the corresponding output currents of the three-phase output terminals. The detected output currents are denoted as Iu, Iv, and Iw, respectively. The current detection units can be implemented using Hall current sensors or by combining sampling resistors with signal amplification circuits. The voltage detection units are connected to the R, S, and T three-phase input voltage detection terminals to obtain the grid voltage fed back from the three-phase input voltage detection terminals. The detected voltages are denoted as UR, US, and UT, respectively. The controller is connected to both the current and voltage detection units to receive the detection data fed back from the current and voltage detection units and to determine the actual correspondence between the three-phase output terminals and the three-phase input voltage detection terminals of the rectifier according to the method described in this invention. The controller also controls the on / off states of the switching transistors in the rectifier main circuit, and generates pulse width modulation drive signals and zero-voltage vectors.
[0026] like Figure 2 As shown, the controller can be functionally divided into a zero-voltage vector output module, a sampling module, and a phase sequence matching learning module. The zero-voltage vector output module controls the rectifier main circuit to output a zero-voltage vector at a preset time. The sampling module synchronously acquires the detection data from the current detection unit and the voltage detection unit during the zero-voltage vector output period. The phase sequence matching learning module determines the actual correspondence between the three-phase output terminals and the three-phase input voltage detection terminals of the rectifier based on the data acquired by the sampling module, and generates a phase sequence matching relationship. These functional modules can be implemented using digital signal processors, microcontrollers, or field-programmable gate arrays (FPGAs) combined with corresponding control programs, or they can be implemented using dedicated integrated circuits (ASICs). This invention does not limit the specific implementation device.
[0027] The principle behind generating a zero-voltage vector is as follows: before the rectifier is put into normal operation, the controller controls the main circuit of the rectifier to output a zero-voltage vector with a preset duration. In this embodiment, the zero-voltage vector is achieved by controlling the upper switching transistors of the three-phase bridge arms of the rectifier to be turned on simultaneously, while simultaneously controlling the lower switching transistors of the three-phase bridge arms to be turned off simultaneously. In this conducting state, the three-phase output terminals of the rectifier's main circuit are interconnected inside the rectifier via the conducting upper switching transistors, forming a common connection point, making the line voltage between the three-phase output terminals zero, hence the name zero-voltage vector. In other embodiments, the lower switching transistors of the three-phase bridge arms can also be controlled to be turned on simultaneously, while the upper switching transistors are turned off simultaneously, achieving the same effect of zero line voltage between the three-phase output terminals, with the same operating principle.
[0028] During the zero-voltage vector effect, the three-phase output terminals of the rectifier are short-circuited into a common coupling point inside the rectifier, while the other end of each phase output terminal is connected to the corresponding phase line of the power grid via a filter inductor. At this time, the voltage difference across the filter inductor is equal to the difference between the grid phase voltage and the potential of the common coupling point. Since the three-phase grid voltage is symmetrically distributed under normal conditions, the potential of the common coupling point is approximately the average value of the three-phase grid voltage. Under the condition of symmetrical three-phase voltage, this average value is approximately zero. Therefore, the voltage difference across the filter inductor is approximately equal to the grid voltage of the corresponding phase. Under the action of this voltage difference, the current in the filter inductor gradually increases according to the voltage-current relationship of the inductor. Since the zero-voltage vector effect is short and the initial current value is zero, the current increase process can be approximated as a linear process, thus making the current value at the end of the zero-voltage vector effect approximately proportional to the voltage difference across the filter inductor.
[0029] The current response model and the determination of the preset duration are defined by assuming the duration of the zero voltage vector is the preset duration. The voltage differences across the filter inductors corresponding to the U, V, and W phase output terminals of the rectifier are respectively denoted as... , , The inductance value of the filter inductor is denoted as Then, at the moment when the zero-voltage vector action ends, the relationship between the three-phase output current of the rectifier and the voltage difference can be approximately expressed as the following equation:
[0030]
[0031]
[0032] in, , , These are the output currents at the U, V, and W phase output terminals of the rectifier at the moment when the zero voltage vector action ends. In this embodiment, the direction of current flow from the main circuit of the rectifier to the filter inductor is defined as the positive direction. , , These are the instantaneous values of the grid phase voltages actually detected by the three-phase input voltage detection terminals, corresponding to the U, V, and W phase output terminals of the rectifier. The actual correspondence between the three-phase output terminals and the three-phase input voltage detection terminals needs to be determined. , , The values correspond to one of the three voltages UR, US, and UT, but their specific correspondence cannot be determined before the zero voltage vector output. The preset duration of action for the zero voltage vector; This is the inductance value of the filter inductor.
[0033] As can be seen from the above relationship, within the preset duration With inductance value Under the same conditions, the magnitude of the output current of a certain phase is directly proportional to the instantaneous value of the corresponding grid phase voltage. That is, the larger the instantaneous value of the corresponding grid phase voltage, the larger the output current of that phase. This proportional relationship is the fundamental basis for determining the actual correspondence between the three-phase output terminals and the three-phase input voltage detection terminals of the rectifier in this invention.
[0034] Preset duration The preset duration needs to be reasonably determined: if the preset duration is too short, the output current generated during the zero-voltage vector action period will be too small, making it susceptible to detection noise and reducing the reliability of phase sequence matching learning; if the preset duration is too long, the output current generated during the zero-voltage vector action period will be too large, easily exceeding the safe tolerance range of the rectifier's power devices, posing a risk of overcurrent damage. Therefore, in this embodiment, the preset duration is determined based on the rectifier's filter inductance value, the rectifier's rated current, and the peak value of the grid phase voltage. An estimate is made to ensure that the peak output current generated during the zero-voltage vector action reaches a preset proportion of the rectifier's rated current.
[0035] Assume the rated current of the rectifier is The peak value of the grid phase voltage is If it is desired that the peak output current generated during the zero-voltage vector action period reaches 50% of the rated current, then the preset duration is... The following relationship can be used to estimate:
[0036] in, This is the inductance value of the filter inductor; This is the rated current of the rectifier; The peak value of the phase voltage of the power grid; coefficient The preset ratio represents the desired peak current generated during the zero-voltage vector action to reach 50% of the rated current. The specific value of this coefficient can be adjusted according to the actual overcurrent capacity of the rectifier. In other embodiments, the preset ratio can also be other values less than one.
[0037] Obtain the preset duration After estimating the value, the controller sets the rectifier's current carrier period to that value and then outputs a zero-voltage vector. After a preset time... Then, the controller will receive the current from the current detection unit. , , The voltages UR, US, and UT fed back by the voltage detection unit are recorded respectively, and the output of the zero voltage vector is turned off to restore the normal control state of each switching transistor in the rectifier main circuit.
[0038] In addition to pre-determining the preset duration based on the estimation method described above, this embodiment also includes an overcurrent protection mechanism to further reduce the risk of overcurrent during phase sequence matching learning. Specifically, during zero-voltage vector output, the controller monitors the three-phase output current values in real time through the current detection unit. When the current value of any one phase of the three-phase output current reaches a preset current threshold, the controller immediately stops outputting the zero-voltage vector, restores the normal control state of each switch in the rectifier main circuit, and records the current and voltage detection values at this time for subsequent phase sequence matching learning. The preset current threshold can be set according to the safe current range of the rectifier power devices, and is usually set slightly lower than the maximum instantaneous current value that the power devices can pass. Through the above overcurrent protection mechanism, even if there is a deviation between the estimated value of the preset duration and the actual operating conditions, it is possible to avoid the output current exceeding the safe tolerance range of the rectifier power devices during the zero-voltage vector operation, thereby improving the reliability of the phase sequence matching learning process.
[0039] A phase sequence matching method based on size sorting is used to obtain the current detection value at the end of the zero voltage vector action. , , After obtaining the voltage detection values UR, US, and UT, this embodiment provides two specific phase sequence matching learning methods. The first is a phase sequence matching method based on size sorting, such as... Figure 3 As shown.
[0040] As can be seen from the aforementioned current response formula, , , Proportional to the corresponding instantaneous value of the grid phase voltage , , ,and , , In reality, each corresponds to one of the three voltages: UR, US, and UT. This is due to the proportionality coefficient. The current is the same constant for all three phases, therefore the current , , The numerical order between them, and their corresponding instantaneous phase voltage values in the power grid. , , The numerical values must be in the same order.
[0041] Based on the above principles, in this embodiment, the current , , The current values are sorted in descending order to obtain the current sorting results. The current with the largest value in the sorting results is recorded as the first output current, the current with the middle value is recorded as the second output current, and the current with the smallest value is recorded as the third output current. At the same time, the voltage values UR, US, and UT are sorted in descending order to obtain the voltage sorting results. The voltage with the largest value in the sorting results is recorded as the first detection voltage, the voltage with the middle value is recorded as the second detection voltage, and the voltage with the smallest value is recorded as the third detection voltage.
[0042] Since the instantaneous value of the grid phase voltage corresponding to the first output current is the largest among the three, and the first detected voltage is precisely the largest feedback voltage among the three-phase input voltage detection terminals, both correspond to the largest phase voltage in the grid at the same moment. Therefore, it can be determined that there is a correspondence between the output terminal corresponding to the first output current and the input voltage detection terminal corresponding to the first detected voltage. Similarly, it can be determined that there is a correspondence between the output terminal corresponding to the second output current and the input voltage detection terminal corresponding to the second detected voltage, and a correspondence between the output terminal corresponding to the third output current and the input voltage detection terminal corresponding to the third detected voltage. Through the above three sets of correspondences, the actual correspondence between the three-phase output terminals and the three-phase input voltage detection terminals of the rectifier can be completely determined.
[0043] For example, if the current detection value meets the following conditions: Maximum value Centered values If the voltage detection values satisfy the following conditions: UT is the largest, US is in the middle, and UR is the smallest, then according to the above ordering correspondence principle, it can be determined that the U-phase output terminal corresponds to the T detection terminal, the V-phase output terminal corresponds to the S detection terminal, and the W-phase output terminal corresponds to the R detection terminal. That is, in the current actual wiring relationship, the T detection terminal actually detects the grid phase voltage corresponding to the U-phase output terminal, the S detection terminal actually detects the grid phase voltage corresponding to the V-phase output terminal, and the R detection terminal actually detects the grid phase voltage corresponding to the W-phase output terminal.
[0044] The phase sequence matching method based on size sorting has a simple calculation process and low requirements for the controller's computing resources, making it suitable for applications where high phase sequence matching learning speed is required. However, in rare cases where the instantaneous values of the three-phase voltages in the power grid are very close between two phases, the sorting results may be misjudged. Therefore, this embodiment provides a second phase sequence matching learning method as a supplement or alternative.
[0045] The second phase sequence matching learning method is based on vector angle matching, such as... Figure 4 As shown, this method uses the vector angles obtained after coordinate transformation of three-phase current or three-phase voltage for matching and judgment, which can reduce the risk of misjudgment caused by the three-phase values being close at certain times.
[0046] First, the voltages UR, US, and UT fed back from the three-phase input voltage detection terminals are transformed to obtain the components of the voltage vector in the rectangular coordinate system. The transformation relationship is as follows:
[0047]
[0048] in, , These are the components of the voltage vector along two orthogonal axes in a rectangular coordinate system; , , These are the three-phase voltage detection values fed back from the three-phase input voltage detection terminals.
[0049] in accordance with , The angle of the voltage vector is calculated using the following formula:
[0050] in, This represents the angle corresponding to the voltage vector.
[0051] Secondly, considering the various possible arrangements between the three-phase output terminals U, V, W of the rectifier and the three-phase input voltage detection terminals R, S, T, this embodiment has six arrangements: the U-phase output terminal corresponding to the first phase current, the V-phase output terminal corresponding to the second phase current, the W-phase output terminal corresponding to the third phase current, and the remaining five arrangements. Each arrangement corresponds to the current... , , A combination of substitutions into the coordinate transformation formula in different orders. For each arrangement, the current values in the corresponding order are substituted into the formula of the same form as the aforementioned voltage coordinate transformation to obtain the current vector angle corresponding to that arrangement. Six arrangements yield six current vector angles respectively.
[0052] Compare the above six current vector angles with the voltage vector angles respectively. By comparing and calculating the angle differences between each current vector angle and voltage vector angle, six angle differences are obtained. Since the current vector direction and voltage vector direction should be approximately the same for the correct arrangement, the arrangement corresponding to the angle difference with the value closest to zero is the actual correspondence between the three-phase output terminals and the three-phase input voltage detection terminals of the rectifier.
[0053] In this embodiment, for ease of explanation, the relationship between the six arrangements, the corresponding current vector angles, and the determined actual correspondences is summarized as follows: The currents are arranged sequentially according to... , , The actual correspondence between the angles obtained by sequentially substituting them is as follows: U-phase output terminal corresponds to R detection terminal, V-phase output terminal corresponds to S detection terminal, and W-phase output terminal corresponds to T detection terminal; the current is then sequentially... , , The actual correspondence between the angles obtained by sequentially substituting them is as follows: U-phase output terminal corresponds to R detection terminal, V-phase output terminal corresponds to T detection terminal, and W-phase output terminal corresponds to S detection terminal; the current is then sequentially... , , The actual correspondence between the angles obtained by sequentially substituting them is as follows: U-phase output terminal corresponds to S-detection terminal, V-phase output terminal corresponds to R-detection terminal, and W-phase output terminal corresponds to T-detection terminal; the current is then sequentially... , , The actual correspondence between the angles obtained by sequentially substituting them is as follows: U-phase output terminal corresponds to T-detection terminal, V-phase output terminal corresponds to R-detection terminal, and W-phase output terminal corresponds to S-detection terminal; the current is then sequentially... , , The actual correspondence between the angles obtained by sequentially substituting them is as follows: U-phase output terminal corresponds to T-detection terminal, V-phase output terminal corresponds to S-detection terminal, and W-phase output terminal corresponds to R-detection terminal; the current is then sequentially... , , The actual correspondences of the angles obtained by sequential substitution are: U-phase output terminal corresponds to S-detection terminal, V-phase output terminal corresponds to T-detection terminal, and W-phase output terminal corresponds to R-detection terminal. The controller determines the current actual correspondence based on the one of the six angle differences calculated that is closest to zero from the above six correspondences.
[0054] The phase sequence matching method based on vector angle matching utilizes the overall directional characteristics of three-phase electrical quantities after coordinate transformation for judgment. Compared to methods based on magnitude sorting, it has stronger resistance to misjudgments caused by noise interference or close numerical values at individual detection moments, making it suitable for applications with high requirements for the reliability of phase sequence matching learning. In practical applications, the controller can choose to use either a magnitude sorting-based method or a vector angle matching-based method to determine the actual correspondence between the three-phase output terminals and the three-phase input voltage detection terminals of the rectifier, depending on the specific application of the rectifier and the different requirements for computing resources and reliability.
[0055] Application and storage reuse of phase sequence matching results, such as Figure 5 As shown, the controller includes a main control module and non-volatile storage devices. After the phase sequence matching learning module determines the actual correspondence between the three-phase output terminals and the three-phase input voltage detection terminals of the rectifier, it transmits this correspondence to the main control module. The main control module adjusts the calling relationship between the three-phase grid voltage and the three-phase output terminal drive signals in the rectifier control algorithm according to this correspondence. This changes the drive signal, which should have been generated by a certain phase grid voltage, to one that uses the voltage information fed back from the input voltage detection terminal that actually corresponds to that phase output terminal. This ensures that when the rectifier is running normally, the control algorithm can generate pulse width modulation drive signals based on the correct voltage phase information, thus achieving synchronization between the rectifier output voltage and the grid voltage.
[0056] Furthermore, considering that the field wiring relationships typically do not change after the rectifier is put into use, this embodiment also includes a function for storing and reusing phase sequence matching relationships. The actual correspondence determined by the phase sequence matching learning module can be saved to a non-volatile storage device. This non-volatile storage device can be implemented using an electrically erasable programmable read-only memory (EEPROM) or other non-volatile storage media such as flash memory. When the rectifier restarts, the controller can choose to directly read the phase sequence matching relationship already saved in the non-volatile storage device and hand it over to the main control module for use, instead of repeatedly executing the zero-voltage vector output and phase sequence matching learning process, thereby further shortening the rectifier's startup time. When the field wiring relationships change, the phase sequence matching learning process can be restarted manually, and the newly determined phase sequence matching relationship can be overwritten and stored in the non-volatile storage device.
[0057] Regarding the triggering method and overall process, this embodiment employs two methods for the zero-voltage vector triggering timing. In the first method, the triggering moment is the instant the rectifier starts up each time. That is, during each power-on startup, the rectifier automatically performs a phase sequence matching learning process to determine the current actual correspondence before entering normal operation. The advantage of this method is its adaptability to changes in wiring relationships and its high reliability. In the second method, the triggering moment is when the controller receives a manual trigger command. This is achieved when the user or commissioning personnel issue a trigger command to the controller via the operation panel, communication interface, or other human-machine interaction methods. Upon receiving the command, the controller executes the phase sequence matching learning process. After learning, the results are saved to non-volatile storage for direct retrieval during subsequent startups. The advantage of this method is that it avoids repetitive calculations caused by performing the learning process every time, further improving daily startup efficiency. These two triggering methods can be used individually or in combination, depending on the specific application of the rectifier. For example, a manual triggering method can be used during initial installation and commissioning, while during subsequent normal use, the saved phase sequence matching relationship is used by default, and manual triggering is only used again when necessary to relearn the sequence.
[0058] In summary, the rectifier output and input voltage phase sequence adaptive matching method described in this embodiment outputs a zero voltage vector before the rectifier is put into normal operation. It utilizes the current response characteristics of the filter inductor under the action of the zero voltage vector, which is proportional to the grid phase voltage, and combines size sorting or vector angle matching to determine the actual correspondence between the three-phase output terminals and the three-phase input voltage detection terminals of the rectifier. This correspondence is then applied to the rectifier control algorithm. Simultaneously, reasonable estimation of the preset time and an overcurrent protection mechanism reduce the overcurrent risk during the phase sequence matching learning process. Furthermore, the storage and reuse mechanism of the phase sequence matching relationship improves the rectifier's startup efficiency, achieving the technical effect of automatically completing the rectifier output and input voltage phase sequence matching without relying on manual wiring checks.
[0059] The foregoing has provided a detailed description of one embodiment of the present invention, but this description is merely a preferred embodiment and should not be construed as limiting the scope of the invention. All equivalent variations and modifications made within the scope of the claims of this invention should still fall within the patent coverage of this invention.
Claims
1. A method for adaptive phase sequence matching of rectifier output and input voltages. The three-phase output terminals of the rectifier are connected to the power grid via a filter inductor, characterized in that... include: Before the rectifier is put into normal operation, the rectifier is controlled to output a zero voltage vector. The duration of the zero voltage vector is a preset duration. Under the action of the zero voltage vector, the grid voltage is applied to the three-phase output terminals of the rectifier through the filter inductor, generating three-phase output currents that are proportional to the grid voltage of the corresponding phase. Within the preset time period, the three-phase output current is collected synchronously, and the three-phase grid voltage fed back from the three-phase input voltage detection terminal is obtained synchronously. Based on the correspondence between the three-phase output current and the three-phase grid voltage, the actual correspondence between the three-phase output terminals of the rectifier and the three-phase input voltage detection terminals is determined, and the phase sequence matching relationship is obtained; Based on the phase sequence matching relationship, the calling relationship between the three-phase grid voltage and the three-phase output terminal drive signal in the rectifier control algorithm is adjusted so that the rectifier generates pulse width modulation drive signal according to the adjusted calling relationship during subsequent operation. Determining the actual correspondence between the three-phase output terminals of the rectifier and the three-phase input voltage detection terminals based on the correspondence between the three-phase output current and the three-phase grid voltage includes: The three-phase output currents are sorted from largest to smallest to obtain the first output current, the second output current and the third output current, wherein the first output current is greater than the second output current and the second output current is greater than the third output current. The three-phase grid voltages are sorted from largest to smallest to obtain a first detection voltage, a second detection voltage, and a third detection voltage, wherein the first detection voltage is greater than the second detection voltage, and the second detection voltage is greater than the third detection voltage. The output terminal corresponding to the first output current is determined to correspond to the input voltage detection terminal corresponding to the first detection voltage, the output terminal corresponding to the second output current is determined to correspond to the input voltage detection terminal corresponding to the second detection voltage, and the output terminal corresponding to the third output current is determined to correspond to the input voltage detection terminal corresponding to the third detection voltage.
2. The rectifier output-input voltage phase sequence adaptive matching method according to claim 1, characterized in that, Determining the actual correspondence between the three-phase output terminals of the rectifier and the three-phase input voltage detection terminals based on the correspondence between the three-phase output current and the three-phase grid voltage includes: The coordinate transformation of the three-phase grid voltage is performed to obtain the voltage vector angle corresponding to the three-phase grid voltage; Based on the various arrangements between the three-phase output terminals and the three-phase input voltage detection terminals, the coordinate transformation of the three-phase output current is performed to obtain multiple current vector angles corresponding to each arrangement. The angles of the multiple current vectors are compared with the angles of the voltage vectors to obtain multiple angle differences. The arrangement of the angle differences that are closest to zero is determined as the actual correspondence between the three-phase output terminals of the rectifier and the three-phase input voltage detection terminals.
3. The rectifier output-input voltage phase sequence adaptive matching method according to claim 1, characterized in that, Controlling the rectifier output zero voltage vector includes: controlling the upper switching transistors of the three-phase bridge arms of the rectifier to be turned on simultaneously and the lower switching transistors to be turned off simultaneously, so that the line voltage between the three-phase output terminals of the rectifier is zero.
4. The rectifier output-input voltage phase sequence adaptive matching method according to claim 1, characterized in that, Also includes: Within the preset time period, the three-phase output current is monitored in real time. When the current value of any one of the three-phase output currents reaches the preset current threshold, the zero voltage vector is stopped from being output.
5. The rectifier output-input voltage phase sequence adaptive matching method according to claim 1, characterized in that, The preset duration is determined based on the rectifier's filter inductance value, the rectifier's rated current, and the peak value of the grid phase voltage, so that the peak value of the three-phase output current generated under the zero voltage vector reaches a preset proportion of the rectifier's rated current.
6. The rectifier output-input voltage phase sequence adaptive matching method according to claim 1, characterized in that, The trigger moment for controlling the zero-voltage vector output of the rectifier is the instant the rectifier starts up.
7. The rectifier output-input voltage phase sequence adaptive matching method according to claim 1, characterized in that, The trigger time for controlling the zero-voltage vector output of the rectifier is the moment when the controller receives the manual trigger command.
8. The rectifier output-input voltage phase sequence adaptive matching method according to claim 1, characterized in that, Also includes: The phase sequence matching relationship is saved to a non-volatile storage device. When the rectifier is restarted, the phase sequence matching relationship saved in the non-volatile storage device is read, and the calling relationship between the three-phase grid voltage and the three-phase output terminal drive signal in the rectifier control algorithm is adjusted according to the read phase sequence matching relationship.
Citation Information
Patent Citations
Domestic high-power IGBT (Insulated Gate Bipolar Translator) rectification system and method
CN121124582A
Adaptive Electrical Power Distribution Panel
US20230155482A1