An amphibious piling operation platform and its usage method

By designing a separate structure for the driving vehicle and the piling vehicle, along with multi-degree-of-freedom connecting components, the problem of low operating efficiency of existing piling equipment in complex terrains where land and water meet is solved, enabling efficient and safe amphibious operations and adapting to the construction needs of various terrains.

CN123064147APending Publication Date: 2026-11-10CCCC WUHAN HARBOR ENG DESIGN & RES
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202611254076.6
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-08-18
Publication Date
2026-11-10

AI Technical Summary

Technical Problem

Existing piling equipment cannot operate efficiently and safely in complex terrains where land and water meet, and it is especially difficult to respond quickly to emergency needs in extreme weather and complex environments, resulting in low operational efficiency.

Method used

It adopts a separate structure for the driver vehicle and the piling vehicle, combined with multi-degree-of-freedom connectors and an all-terrain tracked chassis to achieve amphibious operations; the piling vehicle is equipped with a robotic arm and positioning piles, and with the help of drones for high-altitude surveying, it can improve construction accuracy and safety.

Benefits of technology

It enables efficient and safe operation in complex terrain, improves construction efficiency and safety, adapts to amphibious passage and obstacle crossing capabilities in various terrains, and reduces construction waiting time.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123064147A_ABST
    Figure CN123064147A_ABST
Patent Text Reader

Abstract

This invention provides an amphibious piling platform and its usage method. The amphibious piling platform includes a driver vehicle and a piling vehicle, connected by a connecting component. The driver vehicle has an amphibious all-terrain chassis and drive wheels at its bottom. The piling vehicle also has an amphibious all-terrain chassis and wheels at its bottom. The piling vehicle contains several placement racks for holding piles. A robotic arm is also located inside the piling vehicle for gripping piles and performing piling operations. Several positioning piles are mounted on the piling vehicle. The platform employs a separate structure for the driver and piling vehicle, combined with a multi-degree-of-freedom connecting component. This allows for both combined operation to improve amphibious mobility and separate operation, with the piling vehicle performing fixed-point piling and the driver vehicle retracing its route to replenish piles, enabling uninterrupted operation and significantly improving construction efficiency. The all-terrain tracked chassis adapts to various terrains, including land, mudflats, and shallow water, meeting the needs of amphibious operations.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of piling equipment technology, specifically to an amphibious piling platform and its usage method. Background Technology

[0002] In scenarios such as water conservancy projects, tidal flat development, wetland construction, and construction of floating photovoltaic pile foundations, a large number of operational needs are concentrated in complex terrains such as soft soil foundations and shallow water areas at the junction of land and water.

[0003] Existing piling equipment is mostly land-based fixed or ordinary tracked piling machines, which have core defects such as poor passability, easy getting stuck, and inability to operate amphibiously in swamps, tidal flats, and shallow water areas. Some specialized amphibious piling equipment adopts an integrated body, which is long and has limited turning and obstacle-crossing capabilities in narrow terrain, steep slopes, and complex obstacle scenarios.

[0004] Furthermore, in recent years, global climate change has intensified and extreme weather events have become more frequent. my country's complex geographical environment has led to frequent natural disasters such as floods and mudslides. In traditional emergency rescue operations, piling equipment is often constrained by complex terrain and environments such as deep water, silt, and swamps, making it difficult to efficiently and safely approach and carry out operations. This often results in missing the "golden time" for disaster relief, leading to the escalation of the danger and causing huge losses of life and property. Summary of the Invention

[0005] The main objective of this invention is to provide an amphibious piling operation platform and its usage method, thereby solving the problems that existing piling equipment cannot be applied to complex amphibious terrain and has low efficiency in emergency piling.

[0006] To solve the above-mentioned technical problems, the technical solution adopted by the present invention is as follows: An amphibious piling operation platform includes a driver vehicle and a piling vehicle, with a connecting component between the driver vehicle and the piling vehicle; The vehicle is equipped with an amphibious all-terrain chassis and drive wheels at the bottom. The pile driver is equipped with an amphibious all-terrain chassis and wheels at the bottom; The piling vehicle is equipped with several placement racks for placing the piles. The piling vehicle is equipped with a robotic arm, which is used to grip the pile and perform the piling operation. The piling vehicle is equipped with several positioning stakes.

[0007] In a preferred embodiment, the end of the robotic arm is equipped with a vibrating hammer; The piling vehicle is equipped with a control structure and an operating room. The robotic arm is equipped with a rotating base, which is located inside the operating room. There are two placement racks, located on either side of the robotic arm; The vehicle includes a driver's cab, control equipment, drone equipment, and wireless transmission equipment; the control equipment is used for overall control and is connected to the control structure via signals; the drone equipment is used for high-altitude detection of the piling environment and piling conditions; and the wireless transmission equipment is used for signal transmission.

[0008] In a preferred embodiment, the connector includes a connector seat, and one end of the connector frame is hinged to the side of the connector seat closest to the driver's vehicle; the connector frame is connected to the driver's vehicle. A second telescopic cylinder is hinged to the top of the connecting seat, and the output end of the second telescopic cylinder is hinged to the other end of the connecting frame; The front and rear sides of the connecting seat are hinged with the first telescopic cylinders, and the front and rear sides of the first telescopic cylinders are hinged together with the hinge seat, which is close to the pile driver. The hinged seat is hinged to the connecting seat on the side away from the piling vehicle; The hinged seat is equipped with a mounting base, which is connected to the piling vehicle.

[0009] In the preferred embodiment, the drive wheel is a tracked wheel, which contains a drive wheel and an idler wheel; The traveling wheels are the same as the drive wheels.

[0010] In the preferred embodiment, both ends of the piling vehicle are equipped with plug-in blocks, and the plug-in blocks are vertically equipped with connection holes; The mounting base is equipped with a plug-in sleeve, and the plug-in sleeve has a plug-in hole that is compatible with the plug-in block; The top of the plug-in sleeve is equipped with a third telescopic cylinder, and the output end of the third telescopic cylinder is equipped with a connecting post. The connecting post is located inside the plug sleeve and is adapted to the connecting hole.

[0011] In the preferred embodiment, the drive wheel is a tracked wheel, which contains a drive wheel and an idler wheel; The running wheels are the same as the drive wheels; or The walking wheels are a passive walking structure, consisting of off-road tires and rims.

[0012] In a preferred embodiment, the placement rack includes a support column, on which an inclined placement plate is provided; The edge of the placement board is equipped with a baffle; The bottom of the placement plate is provided with a stop block, and a positioning block is provided on the side of the stop block near the placement plate; The piles are stacked on the placement plate, with one end abutting against the positioning block and the other end extending out of the placement plate to the outside of the pile driver; The protruding length of the upper pile is greater than that of the lower pile.

[0013] In the preferred embodiment, the placement plate is provided with several positioning mechanisms located on both sides of the pile body, which are used to support the pile body one by one, making it convenient to remove the pile and avoid the pile body getting stuck together; The positioning mechanism includes a support plate, and a rotating seat is rotatably connected inside the support plate; The rotating base is equipped with a support block; the two ends of the rotating base are equipped with rotating shafts, and a motor is provided on the side of the support plate, with the output shaft of the motor connected to the rotating shaft; The support plate has several movable grooves on the side near the pile body, and the movable grooves are adapted to the support block; After the support block moves out of the movable slot, it is used to support the pile body; after the support block moves into the movable slot, it does not affect the placement and removal of the pile body below.

[0014] A method for using an amphibious piling operation platform includes the following steps: S1. According to the construction requirements, drive the vehicle and the piling truck to the construction area; S2. The pile driver is in place, and the positioning pile is lowered and fixed. S3. The robotic arm picks up the pile and moves it to the pile driving position; S4. Piling is completed with the assistance of a vibratory hammer at the end of the robotic arm; S5. Repeat S3-S4 until all the piles on the pile driver are used up. S6. The driver and pile driver return to the pile replacement location to add piles; S7. Repeat S1-S6 until all piling tasks are completed.

[0015] In the preferred embodiment, S1 includes: S11. During driving, the road conditions of the route are monitored in real time, and extreme road conditions are transmitted to the central control computer in the driver's cab via wireless signal. S12. When driving to extreme road conditions, the connecting parts rotate, connect and disconnect, and the driving vehicle and the pile driver move relative to each other to complete climbing, obstacle crossing, turning and position switching. S13. Move to the construction area so that the end of the piling vehicle closest to the mechanical arm is close to the construction position; When the piling truck is working at the construction site, the connector is disconnected. The driver then moves to the piling location, connects another piling truck fully loaded with piles through the connector, and then transports the connected piling truck to the construction site. During construction, the working signal of the piling truck is transmitted by the staff to the control structure via wireless signal. The control structure then controls the piling truck to complete the piling construction. Both ends of the piling machine can be connected to the driver's vehicle via connectors.

[0016] This invention provides an amphibious piling operation platform and its usage method. By adopting the above solution, the following beneficial effects are achieved: The vehicle adopts a separate structure for the driver and the pile driver, and is equipped with multi-degree-of-freedom connecting parts. It can be used in combination to improve amphibious mobility, or it can be used separately for operation. The pile driver can carry out fixed-point construction, while the driver can go back and forth to replenish piles, achieving uninterrupted operation and greatly improving construction efficiency. The all-terrain tracked chassis can adapt to various terrains such as land, mudflats, and shallow water areas, meeting the needs of amphibious operations.

[0017] The connector has multiple degrees of freedom for pitch and yaw adjustment, which can adapt to complex terrain with undulations and tilts, avoid structural interference and stress concentration when the two vehicles are driving, and improve the ability to overcome obstacles and climb hills in extreme road conditions; the quick-plug connection structure enables the two vehicles to be quickly separated and docked, and is compatible with both push and pull traction methods to deal with sudden scenarios such as slippage and getting stuck.

[0018] The inclined placement frame, combined with the stepped pile layout and the positioning mechanism on both sides, enables the orderly release of piles one by one, avoiding jamming between stacked piles, resulting in higher pile retrieval efficiency and reducing the difficulty of alignment for the robotic arm. The positioning mechanism uses a rotating support block, which is compact, precise, and can stably support multiple layers of piles.

[0019] During pile driving operations, the positioning pile extends to touch the ground, which can lift and level the entire vehicle, counteracting the vibration and reaction force of the robotic arm during pile driving and improving operational stability. Combined with drone aerial surveying, the construction environment and pile driving accuracy can be monitored in real time, improving construction safety and work quality.

[0020] The dual-wheel pile replacement mode allows a single driver to dispatch multiple pile drivers to work alternately, reducing construction waiting time. The pile drivers can use passive walking wheels to reduce equipment costs and are suitable for multi-vehicle network operation scenarios. Attached Figure Description

[0021] The present invention will be further described below with reference to the accompanying drawings and embodiments: Figure 1 This is a schematic diagram of the structure of the present invention; Figure 2 This is a schematic diagram of the structure during the construction of this invention; Figure 3 This is a structural schematic diagram of the climbing process of the present invention; Figure 4 This is a structural schematic diagram of the present invention during the turning process; Figure 5 This is a schematic diagram of the structure of the piling vehicle of the present invention; Figure 6 This is a schematic diagram of the structure of the placement rack of the present invention; Figure 7 This is a top view of the piling vehicle of the present invention; Figure 8 This is a cross-sectional view of the piling vehicle of the present invention; Figure 9 This is a cross-sectional view of the positioning mechanism of the present invention; Figure 10 This is a side sectional view of the positioning mechanism of the present invention; Figure 11 This is a schematic diagram of the structure of the connector of the present invention; Figure 12 This is a cross-sectional view of the insertion sleeve of the present invention.

[0022] In the picture: 1. Driving vehicle, 101. Control device, 102. Drive wheel, 2. Piling vehicle, 201. Operating room, 202. Walking wheel, 3. Connector, 301. Insertion block, 302. Connecting hole, 303. Connecting seat, 304. Hinge seat, 305. First telescopic cylinder, 306. Second telescopic cylinder, 307. Mounting seat, 308. Insertion sleeve, 309. Insertion hole, 310. Third telescopic cylinder, 311. Connecting column, 312. Positioning pile, 4. Mechanical arm, 5. Placement frame, 6. Support column, 601. Placement plate, 602. Baffle, 603. Stop block, 604. Positioning block, 605. Positioning mechanism, 7. Support plate, 701. Rotating seat, 702. Rotating shaft, 703. Motor, 704. Support block, 705. Movable groove, 706. Piling body, 8. Detailed Implementation

[0023] Example 1: like Figure 1 , 2 As shown in 3, 4, 5, 6, 7, 8 and 11, an amphibious piling operation platform includes a driving vehicle 1, a piling vehicle 2, a connecting piece 3, a positioning pile 4, a robotic arm 5 and a placement frame 6.

[0024] Specifically, the driver vehicle 1 is the power and control center of the entire vehicle. The front of the vehicle is equipped with a closed waterproof cab, and the middle is equipped with control equipment 101, a drone storage compartment and wireless transmission equipment. The bottom is equipped with an amphibious all-terrain chassis. The drive wheels 102 of the chassis are tracked wheels, with built-in drive wheels, idler wheels and multiple sets of load-bearing wheels. The drive wheels are preferably driven by a high-torque low-speed hydraulic motor, and the idler wheels are equipped with a screw-type track tensioning mechanism. The track width is preferably 650mm, and the ground pressure is ≤35kPa. It can travel stably in soft mudflats, swamps and shallow water areas with a depth of less than 1.2m, and has all-terrain amphibious travel capability.

[0025] Furthermore, the control equipment 101 adopts a PLC integrated control cabinet, equipped with an on-board industrial control computer, to realize centralized control of the vehicle's driving, connecting parts' actions, and work commands; the drone equipment adopts a hexacopter survey drone, equipped with a high-definition gimbal camera and ultrasonic depth sounding module, which can take off and land autonomously from the take-off and landing platform on the top of the driver's vehicle, and is used for terrain mapping before construction, monitoring of pile driving verticality during construction, and environmental inspection; the wireless transmission equipment adopts industrial-grade 5G + data transmission radio dual-link communication to realize signal interaction and remote data transmission between the driver's vehicle and the pile driving vehicle.

[0026] The pile driver 2 is the main operating unit, and its bottom is also equipped with an amphibious all-terrain chassis. The walking wheels 202 and the drive wheels 102 have the same structure, and have the same amphibious driving and obstacle crossing capabilities. The pile driver 2 is equipped with an operating room 201 on the upper part. The operating room 201 is equipped with the rotary base of the robotic arm 5 and the pile driving-specific control structure. The robotic arm 5 is preferably a four-section folding hydraulic robotic arm with a maximum operating radius of 8.5m. A vibratory hammer is installed at the end. The vibratory hammer is preferably a DZ-30 type vibratory pile hammer with a continuously adjustable excitation force of 0-300kN and a vibration frequency of 0-25Hz. It is suitable for various pile types such as steel pipe piles and precast concrete piles. It can hold the pile body 8 through a hydraulic clamping mechanism and use high-frequency vibration to sink the pile body into the stratum. Four sets of positioning piles 4 are vertically installed at the four corners of the frame of the piling vehicle 2. The positioning piles 4 are preferably multi-stage hydraulic outriggers with a rated support force of ≥100kN per outrigger and an extension stroke of 1.5m. The bottom is equipped with a conical pile head. During operation, the positioning piles 4 extend and insert into the ground, lifting the piling vehicle 2 as a whole and automatically leveling it to counteract the vibration reaction force of piling and ensure operational stability.

[0027] Inside the carriage of the pile driver 2, on both the left and right sides of the robotic arm 5, are two sets of placement racks 6 for storing piles 8. Each set of placement racks 6 includes a support column 601, an inclined placement plate 602, a baffle 603, a stop block 604, and a positioning block 605. The support column 601 is vertically fixed to the bottom plate of the carriage, and the placement plate 602 is inclined and fixed to the support column 601 at an angle of 15-45°. The piles 8 are stacked along the inclined surface of the placement plate 602. The two sides of the placement plate 602 are provided with protruding baffles 603 to prevent the piles 8 from sliding sideways. The lower end of the placement plate 602 is provided with a stop block 604, and the inner side of the stop block 604 is provided with a positioning block 605. The bottom end of the pile 8 abuts against the positioning block 605 to achieve axial positioning. Due to the influence of the positioning block 605, after stacking, the outward extension length of the upper pile 8 is greater than that of the lower pile 8, forming a stepped arrangement, which facilitates the robotic arm 5 to pick up the piles layer by layer from the end.

[0028] Connector 3 is positioned between the driver vehicle 1 and the piling vehicle 2 to enable articulated traction and multi-degree-of-freedom relative motion between the two vehicles. Connector 3 includes a connecting seat 303, a connecting frame 304, a hinge seat 305, a first telescopic cylinder 306, and a second telescopic cylinder 307. One end of the connecting frame 304 is hinged to the left side of the connecting seat 303, and the other end is fixedly connected to the rear traction seat of the driver vehicle 1. The middle of the cylinder body of the second telescopic cylinder 307 is hinged to the top of the connecting seat 303, and the end of the piston rod is hinged to the upper part of the connecting frame 304. The second telescopic cylinder 307 is preferably an HSG80 series engineering hydraulic cylinder, which, through extension and retraction, drives the connecting seat 303 to pitch and swing around the hinge point, adjusting the pitch angle of the two vehicles to adapt to climbing slopes and vertical obstacle crossing. The right side of the connecting seat 303 is hinged to the middle of the hinge seat 305. A set of first telescopic cylinders 306 are hinged to each of the front and rear sides of the connecting seat 303. The piston rod ends of the two sets of first telescopic cylinders 306 are respectively hinged to the front and rear sides of the hinge seat 305. The first telescopic cylinders 306 are preferably HSG series hydraulic cylinders. Through the differential extension and retraction of the two cylinders, the hinge seat 305 can be driven to rotate horizontally around the hinge point, achieving horizontal steering angle compensation for the two vehicles and adapting to curves and lateral undulations. A mounting seat 308 is fixedly installed on the right side of the hinge seat 305. The mounting seat 308 is fixedly connected to the end of the frame of the piling vehicle 2 to achieve the transmission of traction force.

[0029] In this embodiment, during operation: The driver vehicle 1 pulls the pile driver 2 synchronously via the connector 3, and the tracked amphibious chassis adapts to complex land and water terrain. When encountering extreme road conditions such as climbing slopes or overcoming obstacles, the second telescopic cylinder 307 extends and retracts to adjust the pitch angle, while the two sets of first telescopic cylinders 306 differentially adjust the horizontal deflection angle, releasing the freedom between the two vehicles, avoiding structural interference and stress concentration, and improving passability. Upon reaching the construction area, the positioning pile 4 extends to touch the ground and level the pile driver 2. The robotic arm 5 picks up the pile 8 from the placement frame 6 and moves it to the pile driving point. The end vibratory hammer is activated, vibrating the pile 8 into the ground. During the operation, a drone is launched to survey the area and transmits real-time data on pile position deviation and the surrounding environment, ensuring construction accuracy.

[0030] Example 2: like Figure 1 , 2 As shown in 3, 4, 5, 6, 7, 8, 11 and 12, the core difference from Embodiment 1 is that in this embodiment, the piling vehicle 2 and the connecting piece 3 adopt a quick-separation plug-in structure, and the walking wheel 202 can adopt a passive walking structure. The other unmentioned structures, connection relationships and working principles are the same as in Embodiment 1.

[0031] Both ends of the piling vehicle 2 are fixedly equipped with plug-in blocks 301. The plug-in blocks 301 are rectangular steel structures with 1-2 vertically extending connecting holes 302. The mounting base 308 of the connector 3 is fixed to the right side of the plug-in sleeve 309. The plug-in sleeve 309 has a plug-in hole 310 inside. The opening direction of the plug-in hole 310 is away from the connecting base 301. The size of the plug-in hole 310 is adapted to the shape of the plug-in block 301, which can realize the lateral insertion and docking of the plug-in block 301. 1-2 third telescopic cylinders 311 are vertically installed on the top of the plug-in sleeve 309. The third telescopic cylinder 311 is preferably a short-stroke high-precision hydraulic cylinder. The lower end of the piston rod is fixed with a connecting column 312. The connecting column 312 extends coaxially into the connecting hole 310 and is clearance-fitted with the connecting hole 302.

[0032] During docking, the driver vehicle 1 moves the connector 3 closer to the piling vehicle 2, aligning the plug sleeve 309 with the plug block 301. Continuing to move, the plug block 301 is inserted into the plug hole 310. The third telescopic cylinder 311 extends, and the connecting column 312 is inserted into the connecting hole 302, completing axial locking and achieving rapid connection between the two vehicles. During separation, the third telescopic cylinder 311 retracts, the connecting column 312 exits the connecting hole 302, and the driver vehicle 1 moves the connector 3 away to complete the separation.

[0033] Meanwhile, the walking wheel 202 in this embodiment can be replaced with a passive walking structure, using large-size wide-base off-road tires in conjunction with a wheel hub structure. The tires are wide tires specifically for desert off-road use. There is no need to equip an independent drive system. The vehicle 1 is towed or pushed by the connecting piece 3. This solution can eliminate the track drive system of the piling vehicle, greatly reducing the manufacturing cost of a single piling vehicle, and is suitable for scenarios where multiple piling vehicles are rotated.

[0034] This embodiment is illustrated with a typical application scenario: When the driver vehicle 1 tows the pile driver 2 to a muddy and slippery section of road, the third telescopic cylinder 311 can be controlled to retract, disconnecting from the pile driver 2. After the driver vehicle 1 reduces its load, it passes through the slippery area on its own, and then goes around to the other end of the pile driver 2. The connecting piece 3 is then connected and locked with the plug block 301 at the other end of the pile driver 2. The pile driver 2 is then pushed through the slippery section by pushing. Alternatively, the driver vehicle 2 can be towed in the opposite direction to change the route and adapt to different terrain conditions.

[0035] In operation, once the piling vehicle 2 is in place and secured by the positioning pile 4, the connection is disconnected. The driver vehicle 1 can then detach from the current piling vehicle 2 and drive to the piling replacement area to connect with another piling vehicle 2 fully loaded with piles 8. The vehicles are then transported to the construction site for rotation, ensuring uninterrupted piling operations. When the piling vehicle 2 is in operation, workers can remotely send control commands via wireless transmission from inside the driver vehicle to operate the piling vehicle 2 and complete the piling operation. This eliminates the need for personnel to remain on the piling vehicle, thus improving personnel safety.

[0036] Example 3: likeFigure 5 , 6 As shown in 7, 8, 9 and 10, this embodiment can be applied to the platform structure of embodiment 1 or embodiment 2. The other structures and principles that are the same as those in embodiment 1 and embodiment 2 will not be described again. Only the placement frame 6 and the positioning mechanism 7 will be described in detail.

[0037] Specifically, multiple sets of positioning mechanisms 7 are symmetrically arranged on the placement plate 602 of the placement frame 6 and on the left and right sides of the pile body 8, which are used to support the pile body 8 one by one, to avoid the stacked pile bodies 8 squeezing and jamming each other, and to achieve orderly pile removal.

[0038] Specifically, each positioning mechanism 7 includes a support plate 701, a rotating seat 702, a rotating shaft 703, a motor 704, and a support block 705.

[0039] The support plate 701 is vertically fixed to the side of the placement plate 602. Multiple installation cavities are opened inside the support plate 701. The rotating seat 702 is rotatably installed in the installation cavity through the rotating shafts 703 at both ends. The installation cavities are arranged in layers along the stacking direction of the piles 8, with one installation cavity corresponding to each layer of piles. One end of the rotating shaft 703 extends out of the support plate 701 and is connected to the output shaft of the motor 704. The motor 704 is preferably a 42BYG250 stepper motor with a planetary reducer, which can precisely control the rotation angle to realize the screwing in and out of the support block 705. Several movable slots 706 are opened on the side wall of the support plate 701 facing the pile body 8. The movable slots 706 correspond one-to-one with the support blocks 705 and are adapted in shape. The support block 705 is an arc-shaped block structure, fixed on the outer periphery of the rotating seat 702. When the motor 704 drives the rotating seat 702 to rotate, the support block 705 can rotate out from the movable slot 706 and protrude from the surface of the support plate 701, and then support the pile body 8 of the corresponding layer. After the pile body 8 is removed, the corresponding support block 705 is rotated into the movable slot 706 and flush with the surface of the support plate 701, and then the pile body 8 of the lower layer can be removed.

[0040] The working process of this embodiment is as follows: In the initial state, all support blocks 705 of the positioning mechanism 7 are in the rotated-out state, and each layer of pile 8 is supported by support blocks 705 of corresponding height, without the piles 8 pressing against each other. When picking up a pile, the robotic arm 5 picks up the topmost pile 8, and then the motor 704 of the top layer drives the rotating seat 702 to rotate, and the support block 705 rotates into the movable slot 706. The piles 8 of the second layer above can then wait to be picked up, and so on, to achieve orderly picking up of piles one by one. Conversely, the loading of piles 8 can be completed.

[0041] This structure effectively avoids jamming caused by the stacking and squeezing of multiple piles, while ensuring that only one pile is picked up and placed at a time, making the pile picking action stable and controllable. The stepped outward extension of the pile end also further reduces the difficulty of clamping and aligning the robotic arm, improving work efficiency.

[0042] Example 4: A method for using an amphibious piling platform, applying the above embodiments 1-3, includes the following specific steps: Preliminary survey and planning: Before the operation, release the drone equipment to conduct aerial surveying of the construction area and the route, generate a 3D topographic map and a water depth distribution map, plan the optimal route and pile driving points, and pre-set a traffic plan for extreme road conditions; import the pile coordinates, pile parameters, construction elevation and other data into the control equipment 101 to complete the system calibration before the operation.

[0043] S1. The driver vehicle 1 is connected to the pile driver 2, which is fully loaded with piles 8, via the connector 3, and drives towards the construction area according to the planned route. S11. During driving, the vehicle-mounted tilt sensor, water depth sensor and drone monitor the road conditions in real time and transmit data such as road bearing capacity, water depth and obstacle size back to the central control computer in the driver's cab through wireless transmission equipment to assist the driver in decision-making. S12. When encountering extreme road conditions such as uphill, side slope, and ditch, the first telescopic cylinder 306 and the second telescopic cylinder 307 of the control connector 3 work together to adjust the pitch angle and horizontal yaw angle of the two vehicles, release the relative degrees of freedom, and smoothly complete obstacle crossing, uphill climbing and turning. If there is a risk of slipping and getting stuck, disconnect the connection in the manner of Example 2, adjust the traction method and continue to pass. S13. After arriving at the construction area, adjust the vehicle's posture so that the end of the pile driver 2 with the mechanical arm 5 is facing the construction point, which will facilitate the operation.

[0044] S2. Control the four sets of positioning piles 4 to extend synchronously, and insert the conical pile head into the stratum. The high-precision level sensor feeds back to automatically level the pile driver 2, so that the frame is in a horizontal state and the hydraulic pressure of the outriggers is locked to ensure the stability of the vehicle body during operation.

[0045] S3, the robotic arm 5 moves to the end of the placement frame 6 and clamps the outermost pile 8; When using the positioning mechanism 7, the corresponding pile body is picked up and placed according to the logic of Example 3; After the robotic arm 5 picks up the pile 8, it lifts it to the preset pile driving point and adjusts the verticality of the pile to a deviation of ≤0.5° using an inclination sensor.

[0046] S4. The hydraulic clamping mechanism of the vibratory hammer grips the top of the pile body 8, starts the vibratory hammer, and adjusts the excitation force and vibration frequency according to the pile type and the hardness of the stratum. In the initial stage, low-frequency slow pressing is used. After the pile body is stable in the soil, the frequency is increased to the rated frequency and vibrated continuously. During the process, the verticality of the pile is monitored in real time using drones and pile top tilt sensors. Any deviations are corrected in a timely manner until the pile reaches the design elevation.

[0047] S5. After completing the construction of a single pile, the robotic arm is reset and steps S3-S4 are repeated to complete the pile driving operation of all piles 8 of this vehicle in sequence.

[0048] S6. After the pile body 8 of the current piling vehicle 2 is used up, a two-wheel replacement scheme is adopted. The positioning pile 4 is put away, and the driver vehicle 1 and the piling vehicle 2 drive to the pile replacement point. The driver vehicle 1 disconnects from the empty piling vehicle 2, connects to the fully loaded spare piling vehicle 2, and tows it to the construction point to continue the operation. The empty pile driver 2 completes the pile filling at the pile replenishment point and waits for the next round of rotation, achieving uninterrupted construction.

[0049] S7. After all operations are completed, retrieve the positioning pile 4 and the robotic arm 5, and the driver vehicle 1 connects with the pile driver 2 to form a convoy and leave the site, completing all pile driving tasks.

[0050] The above embodiments are merely preferred technical solutions of the present invention and should not be considered as limitations on the present invention. The scope of protection of the present invention should be limited to the technical solutions described in the claims, including equivalent substitutions of the technical features described in the claims. That is, equivalent substitutions and improvements within this scope are also within the scope of protection of the present invention.

Claims

1. An amphibious piling operation platform, characterized in that: It includes a driver vehicle (1) and a pile driver (2), and a connecting piece (3) is provided between the driver vehicle (1) and the pile driver (2); The driving vehicle (1) is equipped with an amphibious all-terrain chassis and drive wheels (102) at the bottom. The bottom of the pile driver (2) is equipped with an amphibious all-terrain chassis and wheels (202). The pile driver (2) is equipped with several placement racks (6), which are used to place piles (8). The pile driver (2) is equipped with a mechanical arm (5), which is used to grip the pile body (8) and perform pile driving operation; The pile driver (2) is equipped with several positioning piles (4).

2. The amphibious piling operation platform according to claim 1, characterized in that: The end of the robotic arm (5) is equipped with a vibrating hammer; The piling vehicle (2) is equipped with a control structure and an operating room (201). The robotic arm (5) is equipped with a rotating base, which is located inside the operating room (201). There are two placement racks (6), located on both sides of the robotic arm (5); The driving vehicle (1) includes a driver's cab, control equipment (101), unmanned aerial vehicle (UAV) equipment and wireless transmission equipment; the control equipment (101) is used for overall control and is connected to the control structure signal; the UAV equipment is used for high-altitude detection of the piling environment and piling conditions; the wireless transmission equipment is used for transmitting signals.

3. The amphibious piling operation platform according to claim 1, characterized in that: The connector (3) includes a connector (303), and one end of a connector (304) is hinged to the side of the connector (303) near the driver vehicle (1); the connector (304) is connected to the driver vehicle (1); A second telescopic cylinder (307) is hinged to the top of the connecting seat (303), and the output end of the second telescopic cylinder (307) is hinged to the other end of the connecting frame (304); The front and rear sides of the connecting seat (303) are hinged with the first telescopic cylinder (306), and the front and rear sides of the first telescopic cylinder (306) are hinged together with the hinge seat (305), which is close to the pile driver (2). The hinged seat (305) is hinged to the connecting seat (303) on the side away from the pile driver (2); The hinged seat (305) is provided with a mounting seat (308), which is connected to the pile driver (2).

4. An amphibious piling operation platform according to any one of claims 1-3, characterized in that: The drive wheel (102) is a tracked wheel, with an internal drive wheel and an idler wheel; The traveling wheel (202) is the same as the drive wheel (102).

5. The amphibious piling operation platform according to claim 3, characterized in that: Both ends of the piling vehicle (2) are provided with plug-in blocks (301), and the plug-in blocks (301) are provided with vertical connecting holes (302); The mounting base (308) is provided with a plug sleeve (309), and the plug sleeve (309) is provided with a plug hole (310), which is compatible with the plug block (301); The top of the plug sleeve (309) is provided with a third telescopic cylinder (311), and the output end of the third telescopic cylinder (311) is provided with a connecting post (312). The connecting post (312) is located inside the plug sleeve (309) and is adapted to the connecting hole (302).

6. An amphibious piling platform according to any one of claims 1, 2, 3 and 5, characterized in that: The drive wheel (102) is a tracked wheel, with an internal drive wheel and an idler wheel; The traveling wheels (202) are the same as the drive wheels (102); or The walking wheel (202) is a passive walking structure, which includes an off-road tire and a wheel hub.

7. The amphibious piling operation platform according to claim 1, characterized in that: The placement rack (6) includes a support column (601) and an inclined placement plate (602) is provided on the support column (601). The edge of the placement plate (602) is provided with a baffle (603); The bottom of the placement plate (602) is provided with a stop block (604), and the side of the stop block (604) near the placement plate (602) is provided with a positioning block (605). The pile body (8) is stacked on the placement plate (602), with one end abutting against the positioning block (605) and the other end extending out of the placement plate (602) to the outside of the pile driver (2); The extension length of the upper pile (8) is greater than the extension length of the lower pile (8).

8. The amphibious piling operation platform and its method of use according to claim 7, characterized in that: The placement plate (602) is provided with several positioning mechanisms (7) located on both sides of the pile body (8) to support the pile body (8) one by one, so as to facilitate the removal of the pile and avoid the pile body (8) getting stuck together; The positioning mechanism (7) includes a support plate (701), and a rotating seat (702) is rotatably connected inside the support plate (701). The rotating seat (702) is provided with a support block (705); the two ends of the rotating seat (702) are provided with rotating shafts (703), and the side of the support plate (701) is provided with a motor (704), and the output shaft of the motor (704) is connected to the rotating shaft (703); The support plate (701) is provided with several movable grooves (706) on the side near the pile body (8), and the movable grooves (706) are adapted to the support block (705); After the support block (705) moves away from the movable slot (706), it is used to support the pile body (8); after the support block (705) moves into the movable slot (706), it does not affect the placement and removal of the pile body (8) below.

9. A method of using an amphibious piling platform as described in any one of claims 1-8, characterized in that: Includes the following steps: S1. According to the construction requirements, drive vehicle (1) and pile driver (2) to the construction area; S2, the pile driver (2) is in place, and the positioning pile (4) is lowered to complete the fixing; S3. The robotic arm (5) picks up the pile (8) and moves the pile (8) to the pile driving position; S4. Piling is completed with the assistance of a vibratory hammer at the end of the robotic arm (5); S5. Repeat S3-S4 until all the piles (8) on the pile driver (2) are used up; S6. The driver (1) and the pile driver (2) return to the pile replacement position to replace the pile body (8). S7. Repeat S1-S6 until all piling tasks are completed.

10. The method of using an amphibious piling platform according to claim 9, characterized in that: S1 includes: S11. During driving, the road conditions of the route are monitored in real time, and extreme road conditions are transmitted to the central control computer in the driver's cab via wireless signal. S12. When driving to the extreme road conditions, the connecting piece (3) rotates, connects and disconnects, and the driving vehicle (1) moves relative to the pile driver (2) to complete climbing, obstacle crossing, turning and position switching. S13. Move to the construction area and bring the end of the pile driver (2) close to the mechanical arm (5) to the construction position; When the piling vehicle (2) is working at the construction site, the connector (3) is disconnected, the driver (1) travels to the piling site, and another piling vehicle (2) fully loaded with piles (8) is connected through the connector (3). Then the connected piling vehicle (2) is transported to the construction site. During construction, the working signal of the piling vehicle (2) is transmitted by the staff to the control structure via wireless signal, and the piling vehicle (2) is controlled by the control structure to complete the piling construction. Both ends of the piling vehicle (2) can be connected to the driving vehicle (1) via connectors (3).