Construction process of sponge city permeable pavement rainwater garden

By integrating construction and seepage control structure, the problem of poor seepage control at the junction of permeable pavement and rain garden was solved, achieving effective control of seepage and graded interception of sewage, improving construction quality and permeability, avoiding waterlogging, and extending the service life of the facilities.

CN123064296APending Publication Date: 2026-11-10CHINA RAILWAY NO 5 ENG GRP NO 6 ENG CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202611459381.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-09-20
Publication Date
2026-11-10

AI Technical Summary

Technical Problem

The existing permeable pavement and rain garden facilities are constructed separately, resulting in poor seepage control at the junction, unrestricted seepage paths, low sewage interception efficiency, and difficulty in simultaneously addressing the infiltration capacity and waterlogging issues both inside and outside the design recurrence period.

Method used

The integrated construction process utilizes a seepage control structure consisting of a water-resistant support section, a variable permeability coefficient transition section, and a flow-limiting overflow section at the junction. This structure effectively controls seepage and intercepts sewage in stages. Combined with the design of different permeability coefficient sections, it ensures that rainwater infiltrates or overflows within the design return period and automatically switches between operating modes.

Benefits of technology

It improved construction quality and efficiency, enhanced seepage control and sewage interception capabilities, ensured that the permeability did not decrease within the design recurrence period, avoided water accumulation and flooding, and extended the service life of the facilities.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123064296A_ABST
    Figure CN123064296A_ABST
Patent Text Reader

Abstract

The application relates to a construction process of a sponge city water-permeable pavement rainwater garden, and relates to the technical field of sponge cities. The construction process comprises the following steps: S1, construction preparation; S2-1, integrated foundation pit excavation; S2-2, junction seepage regulation structure construction: a seepage regulation structure is constructed at the junction of a water-permeable pavement area and a rainwater garden area, the seepage regulation structure comprises a water-resisting supporting section, a variable-permeability transition section and a flow-limiting overflow section; S2-3, water-permeable pavement layer construction; S2-4, rainwater garden structure layer construction; and S3, integrated acceptance. The variable-permeability transition section is used to realize graded sewage interception along the way; the flow-limiting overflow section is used to realize that, when the rainfall is within the design return period, all the rainwater is infiltrated, and when the rainfall exceeds the design return period, the rainwater is overflowed, so that waterlogging is avoided, the seepage at the junction of the water-permeable pavement area and the rainwater garden area can be effectively controlled, the rainwater can be automatically switched between infiltration and overflow transmission, and the rainwater can be graded intercepted.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This application relates to the technical field of sponge cities, and in particular to a construction process for permeable paving rain gardens in sponge cities. Background Technology

[0002] With the promotion of the concept of sponge city construction, permeable pavement and rain gardens, as two important low-impact development (LID) facilities, are widely used in urban roads, squares, parking lots, and other areas. Permeable pavement allows rainwater to infiltrate through permeable concrete layers and permeable base layers, thereby reducing runoff and replenishing groundwater; rain gardens, on the other hand, store, purify, and infiltrate rainwater through sunken planting soil layers and gravel drainage layers.

[0003] However, in existing technologies, permeable pavement and rain gardens are usually designed and constructed as independent facilities, lacking effective seepage control and connection structures at their interface, resulting in the following shortcomings: Firstly, the construction processes for the two are separate, making it difficult to guarantee the quality of the connection at the junction, which reduces the construction quality and efficiency. Moreover, the permeable pavement area and the rain garden area are usually only simply connected, and the seepage path of rainwater at the junction is not constrained, which can easily lead to bypassing, short-circuiting or concentrated scouring, making it difficult to control the seepage at the junction.

[0004] Secondly, existing permeable paving and rain gardens are mostly structures with a single particle size or a single permeability coefficient, which have limited ability to intercept pollutants of different particle sizes in rainwater. Large pollutants are easy to clog the surface quickly, while small pollutants are difficult to be effectively intercepted, resulting in low overall pollution interception efficiency and short service life.

[0005] Third, existing facilities usually only consider infiltration within the design return period, or only set up overflow outlets. This means that within the design return period, rainwater may overflow prematurely due to insufficient infiltration capacity; and beyond the design return period, waterlogging may occur due to poor drainage. It is difficult to address both issues simultaneously.

[0006] Therefore, there is an urgent need for a construction process that can integrate the construction of permeable pavement areas and rain garden areas, and achieve effective control of seepage at the interface between the two, graded interception of sewage, and automatic switching between infiltration filtration and overflow transmission. Summary of the Invention

[0007] In order to achieve effective control of seepage at the boundary between the permeable pavement area and the rain garden area, as well as the automatic switching between graded interception of sewage and infiltration filtration and overflow transmission, this application provides a construction process for permeable pavement rain gardens in sponge cities.

[0008] This application provides a construction process for permeable paving and rain gardens in sponge cities, which adopts the following technical solution: A construction process for permeable paving rain gardens in sponge cities includes the following steps: S1, Construction Preparation: Conduct on-site surveys and layout to determine the boundaries and elevations of the permeable paving area and the rain garden area; S2-1, Integrated foundation pit excavation: The permeable pavement area and the rain garden area are excavated in an integrated manner according to the design elevation to form a continuous foundation pit; S2-2, Construction of seepage control structure at the junction of the permeable pavement area and the rain garden area: a seepage control structure is constructed at the junction of the permeable pavement area and the rain garden area. The seepage control structure includes a water-resistant support section, a variable permeability coefficient transition section and a flow-limiting overflow section that are connected and coordinated in sequence along the seepage direction. The waterproof support section supports the variable permeability coefficient transition section from below; the permeability coefficient of the variable permeability coefficient transition section decreases monotonically from the permeable pavement area side to the rain garden area side along the seepage direction, thereby achieving graded interception of sewage along the process within the variable permeability coefficient transition section; the flow-limiting overflow section is set at the downstream end of the variable permeability coefficient transition section along the seepage direction, with its top surface higher than the top surface of the variable permeability coefficient transition section, for the purpose of intercepting and blocking water. The water-resistant support section, the variable permeability coefficient transition section, and the flow-limiting overflow section work together to intercept rainwater entering the variable permeability coefficient transition section within the design return period of rainfall. This allows all rainwater to infiltrate into the rain garden area after being intercepted and treated in stages by the variable permeability coefficient transition section. When rainfall exceeds the design return period, the water level in the variable permeability coefficient transition section rises and overflows over the top surface of the flow-limiting overflow section into the rain garden area, achieving automatic switching between the two working modes of infiltration filtration and overflow transmission. S2-4, Construction of permeable pavement layer: In the permeable pavement area, a permeable base layer, a leveling layer and a permeable surface layer are laid in sequence; S2-5, Construction of rain garden structural layer: In the rain garden area, an impermeable layer, a gravel drainage layer and a planting soil layer are laid in sequence. The top surface elevation of the planting soil layer is lower than the top surface elevation of the permeable surface layer, forming a sunken rain garden. The gravel drainage layer is located on the downstream side of the variable permeability coefficient transition section along the seepage direction and is connected to the downstream end of the variable permeability coefficient transition section. S3, Integrated Acceptance.

[0009] By adopting the above technical solutions, this process achieves effective control of seepage at the interface between the two through "integrated excavation + boundary seepage control structure + permeable paving and rain garden collaboration", graded interception of rainwater, and automatic switching between infiltration filtration and overflow transmission.

[0010] On-site surveying and layout were conducted to determine the boundaries and elevations of the permeable pavement area and the rain garden area, providing a benchmark for integrated excavation. Based on the elevations, the two areas were excavated in an integrated manner to form a continuous foundation pit. The excavation depth of the rain garden area was greater than that of the permeable pavement area to provide space for subsequent structural layers. At the junction, a seepage control structure consisting of a waterproof support section, a variable permeability coefficient transition section, and a flow-limiting overflow section was set up.

[0011] Waterproof support section: Supports the variable permeability transition section from below, used to constrain the seepage in the transition section into a horizontal one-dimensional seepage flow along its surface. According to Darcy's law, horizontal one-dimensional seepage facilitates precise control of the seepage path and residence time; Variable permeability transition section: The permeability coefficient decreases monotonically along the seepage direction (from the permeable pavement area to the rain garden area).

[0012] According to Darcy's Law (i=q / K, where i is the hydraulic gradient, q is the infiltration flow rate, and K is the permeability coefficient), a decrease in K leads to an increase in i, resulting in an increasing head loss along the flow path. Simultaneously, different permeability coefficient ranges have varying capacities for retaining pollutants, achieving graded pollution interception along the flow path—larger particle size ranges retain larger particles, while smaller particle size ranges retain finer particles.

[0013] Flow-limiting overflow section: Located at the downstream end of the transition section, its top surface is higher than the top surface of the transition section. Its function is to impound and retain water, compensating for the head loss caused by the decreasing permeability coefficient within the transition section. When the rainfall is within the design return period, all rainwater entering the transition section can infiltrate into the rain garden area after being intercepted in stages. When the rainfall exceeds the design return period, the water level in the transition section rises and overflows the top surface of the flow-limiting overflow section, overflowing into the rain garden area, realizing the automatic switching between the two modes of "infiltration filtration" and "overflow transmission".

[0014] Construction of the permeable pavement layer: In the permeable pavement area, a permeable base layer, a leveling layer, and a permeable surface layer are laid sequentially. Construction of the rain garden structural layer: In the rain garden area, an impermeable layer, a gravel drainage layer, and a planting soil layer are laid sequentially. The top surface of the planting soil layer is lower than the permeable surface layer, forming a sunken rain garden. The gravel drainage layer connects to the downstream end of the variable permeability transition section to receive infiltrated rainwater. A joint permeability test is conducted on both areas, and construction is completed after passing the test.

[0015] Integrated construction reduces repeated excavation and allows for more accurate excavation locations, improving construction efficiency and quality while ensuring precise alignment between the two areas. A variable permeability coefficient transition section enables graded interception of pollutants along the route, enhancing overall interception efficiency and service life. A flow-limiting overflow section ensures that rainwater infiltrates within the design return period and overflows when rainfall exceeds this period, preventing waterlogging. The decreasing permeability coefficient creates a gradual gradient, accelerating infiltration without additional power and guaranteeing flow capacity within the design return period. Overflow control effectively manages seepage at the boundary between permeable pavement and rain garden areas, enabling graded interception and automatic switching between infiltration filtration and overflow transmission.

[0016] Optionally, the construction of the waterproof support section is as follows: A geotextile is laid, extending continuously from below the permeable base layer of the permeable pavement area to the impermeable layer of the rain garden area and overlapping it to form a continuous and impermeable base plate. The width of the geotextile extending to the permeable pavement area is not less than 1.2 times the horizontal projection width of the transition section with varying permeability coefficient. The overlap width between the geotextile extending to the rain garden area and the impermeable layer is not less than 300mm, and the overlap is sealed by hot-melt welding or adhesive bonding. The geotextile and the bottom surface of the permeable base layer are compacted and tightly adhered, leaving no gaps between them.

[0017] By adopting the above technical solution, the impermeable support section is achieved by laying impermeable geotextile at the junction. The impermeable geotextile extends continuously from below the permeable base layer in the permeable pavement area to the impermeable layer in the rain garden area and overlaps with it in a sealed manner, forming a continuous and impermeable base plate. The width of the impermeable geotextile extending to the permeable pavement area is not less than 1.2 times the horizontal projection width of the transition section with varying permeability coefficient, ensuring sufficient support and restraint. The overlap width between the impermeable geotextile and the impermeable layer on the side extending to the rain garden area is not less than 300mm, and is sealed by hot-melt welding or adhesive bonding to ensure airtightness. The impermeable geotextile and the bottom surface of the permeable base layer are compacted tightly without gaps, ensuring that the seepage is restrained to a horizontal one-dimensional flow.

[0018] Vertical leakage is prevented by the waterproof base plate, which forces rainwater to flow horizontally and improves the interception efficiency of the transition section. Hot-melt welding or adhesive sealing ensures that there is no leakage at the overlap. Geotextile supports the transition layer and prevents the transition layer material from sinking or mixing. The 1.2 times projection width ensures that there is no seepage around the edge of the transition section, further improving the interception efficiency and service life.

[0019] Optionally, the construction of the variable permeability transition section is as follows: A transition layer is laid on the upper surface of the waterproof support section. The permeability coefficient of the transition layer decreases monotonically from the permeable pavement area to the rain garden area along the seepage direction, and the downstream end of the transition layer connects with the gravel drainage layer of the rain garden area. The transition layer is laid in layers of graded crushed stone, with the particle size decreasing segment by segment along the seepage direction. The ratio of the maximum particle size to the minimum particle size of the transition layer is not less than 2:1. The transition layer is divided into n segments along the seepage direction, where n is 3 to 5. The permeability coefficients of each segment are K1, K2, ..., Kn, satisfying K1>K2>...>Kn, and the ratio of the permeability coefficients of two adjacent segments, Ki / Ki+1, is 1.5 to 3.0.

[0020] By adopting the above technical solution, a transition layer is laid on the upper surface of the waterproof support section. This transition layer uses graded crushed stone laid in layers, with the particle size decreasing progressively along the seepage direction, and the ratio of the maximum to the minimum particle size not less than 2:1. The transition layer is divided into n segments (n=3~5) along the seepage direction, with permeability coefficients of K1, K2, ..., Kn, respectively, satisfying K1>K2>...>Kn, and the ratio of permeability coefficients between adjacent segments, Ki / Ki+1, is 1.5~3.0. The decreasing permeability coefficient causes the hydraulic gradient (i(x)=q / K(x)) to increase along the flow path, forming an accelerated seepage section. Different particle sizes of the crushed stone layers have different pollutant retention capacities; larger particle size segments retain larger particles, while smaller particle size segments retain smaller particles, achieving graded pollution interception. The downstream end of the transition layer connects to the gravel drainage layer, allowing infiltrated rainwater to enter the rain garden.

[0021] Different permeability coefficient ranges correspond to different interception particle sizes, improving overall interception efficiency; decreasing permeability coefficients increase the slope, accelerate water flow, and prevent clogging; a ratio of 1.5 to 3.0 balances interception effect and flow capacity; and it connects with the gravel drainage layer to ensure that infiltrated rainwater can smoothly enter the rain garden.

[0022] Optionally, the construction of the flow-limiting overflow section is as follows: A water-retaining reverse edge is installed at the downstream end of the variable permeability coefficient transition section along the seepage direction. The top surface of the water-retaining reverse edge is higher than the top surface of the variable permeability coefficient transition section, and the superelevation of the top surface of the water-retaining reverse edge is determined according to the backwater height in the variable permeability coefficient transition section under the design return period rainfall. The superelevation Δh of the top surface of the water-retaining reverse edge is determined by Δh=h1+h2, where h1 is the backwater height controlled by the seepage capacity of the variable permeability coefficient transition section under the design return period rainfall, and h2 is the safety superelevation, which is 50mm~100mm. The backwater height h1 is obtained by integrating the hydraulic gradient i(x)=q / K(x) along the seepage direction of each section of the variable permeability coefficient transition section, where q is the design infiltration flow rate, and K(x) is the permeability coefficient of the variable permeability coefficient transition section along the seepage direction.

[0023] By adopting the above technical solution, a water-retaining inverted edge is set at the downstream end of the variable permeability coefficient transition section, with its top surface higher than the top surface of the transition section. The freeboard Δh of the top surface of the water-retaining inverted edge is determined according to the backwater height in the transition section under the design return period rainfall: Δh = h1 + h2, where h1 is the backwater height controlled by the permeability capacity of the transition section under the design return period rainfall, and h2 is the safety freeboard (50mm~100mm). The backwater height h1 is obtained by integrating the hydraulic gradient i(x) = q / K(x) along the seepage direction of each section of the transition section: h1 = dx. The water-blocking and backwater system retains and impounds water to compensate for the head loss caused by the decrease in permeability coefficient within the transition section, ensuring that all rainwater infiltrates within the design return period of rainfall.

[0024] Backwater compensation: The water head retained by the back of the water barrier compensates for the head loss along the flow path, ensuring the flow capacity within the design return period; when the design return period is exceeded, the water level overflows beyond the back of the water barrier, achieving automatic switching; h2 ensures that wave and rainfall fluctuations do not cause premature overflow; the backwater height is calculated based on integrals, making the design scientific and reasonable.

[0025] Optionally, the permeability coefficient of the variable permeability coefficient transition section decreases along the seepage direction, causing the head loss of the variable permeability coefficient transition section to increase along the seepage direction. This head loss is compensated by the backwater head formed by the flow-limiting overflow section, ensuring that the flow capacity of the variable permeability coefficient transition section during the design return period rainfall is not lower than that of the homogeneous transition layer of the same particle size.

[0026] By adopting the above technical solution, the permeability coefficient of the variable permeability transition section decreases along the seepage direction, causing the head loss to increase along the seepage direction. This head loss is compensated by the backwater head formed by the overflow section, ensuring that the flow capacity of the transition section during the design return period rainfall is not lower than that of the homogeneous transition layer of the same particle size. In other words, the compensation of the backwater head offsets the additional resistance caused by the decrease in permeability coefficient, ensuring that the flow capacity is not reduced.

[0027] After compensating for head loss, the flow capacity is no less than that of a homogeneous transition layer of the same particle size; it achieves graded interception of sewage without sacrificing drainage capacity; and the flow capacity is precisely controlled through the design of the backwater height.

[0028] Optionally, 3 to 5 levels of rain garden units are set sequentially from top to bottom along the contour lines of the slope in the rain garden area, with adjacent units separated by energy-dissipating waterfalls.

[0029] By adopting the above technical solution, 3 to 5 levels of rain garden units are sequentially set up from top to bottom along the contour lines of the slope in the rain garden area, with adjacent levels separated by energy-dissipating waterfalls. Rainwater is stored, infiltrated, and purified sequentially within each level unit, with excess rainwater overflowing to the next level through the waterfalls. The waterfalls dissipate energy and prevent water erosion.

[0030] Multi-stage unit series connection improves overall purification effect; cascades consume water flow energy and prevent erosion; suitable for sloping terrain, making full use of gravity flow.

[0031] Optionally, in step S2-3, the permeable base layer is paved with graded crushed stone or permeable concrete with a thickness of 150mm~300mm; the leveling layer is paved with medium sand with a thickness of 20mm~50mm; the permeable surface layer is paved with permeable bricks or permeable concrete; in step S2-4, the gravel drainage layer has a thickness of 200mm~400mm and the gravel particle size is 20mm~40mm; the planting soil layer has a thickness of 300mm~500mm and the planting soil layer contains an improved medium.

[0032] By adopting the above technical solution, the material and thickness range of each structural layer are given, so that the seepage control structure matches the permeability of the upper and lower structural layers, and avoids the formation of stagnant water due to abrupt changes in permeability between adjacent layers.

[0033] Optionally, in step S3, a joint permeability test is performed on the two areas. The method for the joint permeability test is as follows: Several test points are selected on the permeable surface layer, and the permeability coefficient of each test point is measured using a permeability meter. At the same time, water is injected into the water storage layer of the rain garden area to the design water level, and the water level drop rate is measured. When the permeability coefficient of the permeable pavement area is ≥0.5mm / s and the water level drop rate of the rain garden area meets the design requirements, the joint permeability test is deemed qualified.

[0034] By adopting the above technical solution, test points are selected on the permeable surface layer, and the permeability coefficient is measured using a permeability meter; simultaneously, water is injected into the rain garden's water storage layer to the design water level, and the water level drop rate is measured. When the permeability coefficient of the permeable pavement area is ≥0.5mm / s and the water level drop rate of the rain garden meets the design requirements, the combined permeability test is deemed qualified.

[0035] Joint acceptance: Simultaneously test the permeability of two areas to ensure overall coordination; Quantitative standard: Permeability coefficient ≥ 0.5mm / s, with clear standards; Guaranteed function: Ensure that both the permeable pavement and the rain garden can function normally.

[0036] Optionally, the following further exists between S2-4 and S3: Step S2-5: Installation of the intelligent monitoring and automatic backwashing system: A permeability rate sensor and a water quality sensor are embedded in the gravel drainage layer, and the signals from each sensor are connected to a central controller. A backwashing pipe is laid in the gravel drainage layer, and the backwashing pipe is at least partially laid in the variable permeability coefficient transition section, for in-situ backwashing of the permeability coefficient decreasing section of the variable permeability coefficient transition section. The backwashing pipe is connected to a high-pressure water source through a solenoid valve group, and the backwashing is triggered by the central controller according to the signal from the permeability rate sensor.

[0037] By adopting the above technical solution, infiltration rate sensors and water quality sensors are buried in the gravel drainage layer of the rain garden area, and the signals are connected to the central controller. Backwash pipes are laid in the gravel drainage layer, at least partially in the transition section with varying permeability coefficient, for in-situ backwashing of the decreasing permeability coefficient section of the transition section. The backwash pipes are connected to a high-pressure water source through a solenoid valve assembly, and the central controller triggers backwashing based on the signal from the infiltration rate sensor.

[0038] Real-time monitoring: Multiple sensors monitor infiltration rate and water quality; In-situ backwashing: Backwashing pipes are laid in the transition section to directly clean the section with decreasing permeability coefficient and restore permeability; Automatic triggering: Automatically triggered based on infiltration rate signal, without manual intervention; Extended lifespan: Timely backwashing prevents blockage and extends the system's lifespan; Simultaneously, it intercepts contaminants in stages, and backwashing can achieve backwashing of substances step by step, further improving the system's lifespan.

[0039] Optionally, the central controller uses the initial design infiltration rate of the rain garden area as a benchmark and collects the current infiltration rate of the infiltration rate sensor in real time. When the current infiltration rate of a rain garden area decreases by ≥30% relative to the initial design infiltration rate, the backwashing program is automatically triggered. A high-pressure water source is provided through a variable frequency speed control pump and switched to the backwashing pipeline through the solenoid valve group. The backwashing pressure is 0.2MPa~0.5MPa, and the backwashing time is 10min~20min. During the backwashing process, the turbidity of the effluent is monitored in real time by a water quality sensor. When the turbidity of the effluent is lower than the set threshold for 5 consecutive minutes, the backwashing is automatically stopped.

[0040] By adopting the above technical solution, the central controller uses the initial design infiltration rate of the rain garden area as a benchmark and collects the current infiltration rate in real time. When the infiltration rate decreases by ≥30% compared to the initial design, the backwashing program of that unit is automatically triggered. A high-pressure water source (0.2~0.5MPa) is provided by a variable frequency speed-regulating pump, which is switched to the backwashing pipeline via a solenoid valve group. The backwashing lasts for 10~20 minutes. During the backwashing process, the turbidity of the effluent is monitored in real time by a water quality sensor. When the effluent turbidity is lower than the set threshold for 5 consecutive minutes, the backwashing is automatically stopped.

[0041] Precise triggering: Triggers when water level drops by ≥30%, avoiding backwashing too early or too late; Controllable pressure: 0.2~0.5MPa pressure effectively cleans without damaging the structure; Turbidity closed-loop: Automatically stops when effluent turbidity is below the threshold for 5 consecutive minutes, ensuring cleaning effect while saving water; Automated operation: Fully automatic control reduces maintenance costs.

[0042] In summary, this application includes at least one of the following beneficial technical effects: 1. Integrated construction reduces repeated excavation and allows for more accurate excavation locations, improving construction efficiency and quality while ensuring precise elevation connections between the two areas. A variable permeability coefficient transition section enables graded interception of pollutants along the route, improving overall interception efficiency and service life. A flow-limiting overflow section ensures that rainwater infiltrates within the design return period and overflows when rainfall exceeds the design return period, preventing waterlogging. The decreasing permeability coefficient creates an increasing gradient, accelerating infiltration without additional power and guaranteeing flow capacity within the design return period. Overflow control effectively manages seepage at the boundary between permeable pavement and rain garden areas, enabling automatic switching between graded interception, infiltration filtration, and overflow transmission.

[0043] 2. Vertical leakage is prevented by the waterproof base plate, which forces rainwater to flow horizontally and improves the interception efficiency of the transition section; hot-melt welding or adhesive sealing ensures that there is no leakage at the overlap; geotextile supports the transition layer to prevent the transition layer material from sinking or mixing; 1.2 times the projected width ensures that there is no seepage around the edge of the transition section, further improving the interception efficiency and service life.

[0044] 3. By using different permeability coefficient ranges corresponding to different interception particle sizes, the overall interception efficiency is improved; the decreasing permeability coefficient increases the slope and accelerates the water flow, avoiding siltation; the ratio of 1.5 to 3.0 balances interception effect and flow capacity; and it connects with the gravel drainage layer to ensure that infiltrated rainwater can smoothly enter the rain garden.

[0045] 4. The head loss along the flow path is compensated by the water head impounded by the water-blocking inverted side, ensuring the flow capacity within the design return period; when the design return period is exceeded, the water level overflows beyond the water-blocking inverted side, and h2 ensures that wave and rainfall fluctuations do not cause premature overflow; the design is scientific and reasonable based on integral calculation of the backfill height. Attached Figure Description

[0046] Figure 1 This is a flowchart of the construction process for permeable paving and rain gardens in sponge cities; Figure 2 This is a two-dimensional cross-sectional schematic diagram of the construction process of permeable paving and rain gardens in sponge cities.

[0047] Attached reference numerals: 1. Permeable pavement area; 2. Rain garden area; 3. Seepage control structure; 31. Waterproof support section; 32. Variable permeability coefficient transition section; 33. Flow-limiting overflow section; 34. Waterproof base plate; 35. Transition layer; 36. Water-retaining reverse edge; 4. Permeable pavement layer; 41. Permeable base layer; 42. Leveling layer; 43. Permeable surface layer; 5. Rain garden structural layer; 51. Impermeable layer; 52. Gravel drainage layer; 53. Planting soil layer; 61. Infiltration rate sensor; 62. Water quality sensor; 63. Central controller; 64. Backwash pipe. Detailed Implementation

[0048] The following provides a further detailed description of this application.

[0049] This application discloses a construction process for permeable paving rain gardens in sponge cities.

[0050] Reference Figure 1 and Figure 2 The construction process of permeable paving and rain gardens for sponge cities includes the following steps: S1, Construction Preparation: Conduct on-site surveys and layout to determine the boundaries and elevations of permeable pavement area 1 and rain garden area 2. According to the design drawings, the elevation of permeable pavement area 1 is higher than that of rain garden area 2. A seepage control structure 3 is set at the junction of the two. The survey content includes the original foundation bearing capacity, groundwater level, and slope contour lines.

[0051] S2-1, Integrated Excavation: The permeable pavement area 1 and the rain garden area 2 are excavated in an integrated manner according to the design elevation to form a continuous excavation pit; the excavation depth of the rain garden area 2 is greater than the excavation depth of the permeable pavement area 1, or it can be achieved by utilizing the terrain difference, as long as the two form the required elevation difference; integrated excavation avoids the problems of soil disturbance and uneven connection at the interface caused by traditional separate excavation, and also has higher positional accuracy between the two.

[0052] The excavation depth for permeable pavement area 1 is 500~800mm (from the designed ground elevation to the bottom of the pit), and the excavation depth for rain garden area 2 is 800~1500mm. The pit slope is set at 1:0.5~1:1, and the slope surface is temporarily protected by plastic film or geotextile. 100~200mm is reserved at the bottom of the pit for manual cleaning to avoid mechanical over-excavation and disturbance of the original soil.

[0053] S2-2, Construction of seepage control structure 3 at the junction of permeable pavement area 1 and rain garden area 2: The seepage control structure 3 is constructed at the junction of permeable pavement area 1 and rain garden area 2. The seepage control structure 3 includes a waterproof support section 31, a variable permeability coefficient transition section 32 and a flow-limiting overflow section 33 that are connected and coordinated in sequence along the seepage direction.

[0054] The impermeable support section 31 supports the variable permeability coefficient transition section 32 from below, and constrains the seepage within the variable permeability coefficient transition section 32 into a horizontal one-dimensional seepage flow along the upper surface of the impermeable support section 31. The permeability coefficient of the variable permeability coefficient transition section 32 decreases monotonically from the permeable pavement area 1 side to the rain garden area 2 side along the seepage direction, so that the decrease in permeability coefficient is converted into the increase in hydraulic gradient along the flow path, thereby forming an accelerated seepage section with graded interception of sewage along the flow path within the variable permeability coefficient transition section 32. The flow-limiting overflow section 33 is set at the downstream end of the variable permeability coefficient transition section 32 along the seepage direction, and its top surface is higher than the top surface of the variable permeability coefficient transition section 32, which is used to impound and retain water.

[0055] The water-resistant support section 31, the variable permeability coefficient transition section 32, and the flow-limiting overflow section 33 work together to ensure that rainwater entering the variable permeability coefficient transition section 32 within the design return period is intercepted by the flow-limiting overflow section 33, allowing all the rainwater to infiltrate into the rain garden area 2 after being intercepted in stages by the variable permeability coefficient transition section 32. When the rainfall exceeds the design return period, the water level in the variable permeability coefficient transition section 32 rises and overflows over the top surface of the flow-limiting overflow section 33 into the rain garden area 2, realizing the automatic switching between the two working modes of infiltration filtration and overflow transmission.

[0056] S2-3, Construction of Permeable Pavement Layer 4: In permeable paving area 1, a permeable base layer 41, a leveling layer 42, and a permeable surface layer 43 are laid sequentially. The permeable base layer 41 is paved with graded crushed stone or permeable concrete, with a thickness of 150~300mm. The leveling layer 42 is paved with medium sand, with a thickness of 20~50mm. The permeable surface layer 43 is paved with permeable bricks or permeable concrete, with a drainage slope of 1%~2%, and the drainage slope faces towards the rain garden area 2.

[0057] As a preferred option: the permeable base layer 41 uses graded crushed stone (particle size 5~20mm), with a compaction degree ≥95% and a permeability coefficient ≥1×10⁻²cm / s. The leveling layer 42 has a medium sand fineness modulus of 2.3~3.0. The permeable surface layer 43 uses permeable bricks (compressive strength ≥Cc40, permeability coefficient ≥1×10⁻²cm / s) or permeable concrete (porosity 15%~25%, thickness 80~150mm). The permeable surface layer 43 has a drainage slope of 1.5%, sloping towards the rain garden area 2.

[0058] S2-4, Construction of Rain Garden Structure Layer 5: In rain garden area 2, a seepage-proof layer 51, a gravel drainage layer 52, and a planting soil layer 53 are laid sequentially. The seepage-proof layer 51 is made of modified asphalt or high-density polyethylene (HDPE) geomembrane, etc. The top surface elevation of the planting soil layer 53 is lower than the top surface elevation of the permeable surface layer 43, forming a sunken rain garden. The gravel drainage layer 52 is located downstream of the variable permeability coefficient transition section 32 along the seepage direction and connects to the downstream end of the variable permeability coefficient transition section 32. The thickness of the gravel drainage layer 52 is 200~400mm, and the gravel particle size is 20~40mm. The thickness of the planting soil layer 53 is 300~500mm, and the planting soil layer 53 contains a modified medium. The top surface elevation of the planting soil layer 53 is 200~400mm lower than the lowest point elevation of the permeable surface layer 43.

[0059] In Rain Garden Area 2, 3-5 levels of rain garden units are sequentially arranged along the contour lines of the slope from top to bottom, with adjacent units separated by energy-dissipating cascades. Rainwater is stored, infiltrated, and purified within each unit, with excess rainwater overflowing to the next level via the cascades. Each rain garden unit is 5-15m long, 3-8m wide, and has a water depth of 200-400mm. The energy-dissipating cascades are 200-500mm high and constructed using C20 concrete or natural stone. Overflow outlets with a width of 100-300mm are provided on the top surface of the cascades.

[0060] The construction of the waterproof support section 31 is as follows: First, the impermeable layer 51 is constructed. Then, an impermeable geotextile is laid at the junction of the permeable pavement area 1 and the rain garden area 2. The impermeable geotextile extends continuously from below the permeable base layer 41 of the permeable pavement area 1 to the impermeable layer 51 of the rain garden area 2 and overlaps with it in a sealed manner to form a continuous and impermeable waterproof base plate 34. After the impermeable geotextile is laid, the construction of the permeable pavement layer 4 and other layers in the rain garden structural layer 5 is carried out.

[0061] The width of the geotextile extending to the permeable pavement area 1 shall not be less than 1.2 times the horizontal projected width of the transition section 32 with varying permeability coefficient. The overlap width between the geotextile extending to the rain garden area 2 and the impermeable layer 51 shall not be less than 300mm, and the overlap shall be sealed by hot-melt welding or adhesive bonding. The geotextile and the bottom surface of the permeable base layer 41 shall be compacted tightly together, leaving no gaps between them.

[0062] As a preferred option: the impermeable geotextile uses HDPE geomembrane with a thickness of 1.0~2.0mm and a permeability coefficient ≤1×10⁻¹²cm / s. The overlap width of the hot-melt welding is ≥100mm, and the tensile strength of the weld is ≥80% of the strength of the parent material. The adhesive sealing uses a special geomembrane adhesive with a bonding strength ≥0.5MPa. The HDPE geomembrane (1.5mm thick) remains leak-free for 24 hours under 0.3MPa water pressure; the average tensile strength of the hot-melt weld is 85% of the parent material; with an overlap width of 300mm, the leakage at the overlap is 0; after compaction and close bonding, the porosity between the impermeable geotextile and the bottom surface of the permeable base layer 41 is <2%.

[0063] The construction of the variable permeability transition section 32 is as follows: multiple transition layers 35 are laid on the upper surface of the waterproof support section 31, forming the variable permeability transition section 32. The permeability coefficient of the transition layer 35 decreases monotonically from the permeable pavement area 1 to the rain garden area 2 along the seepage direction, and the downstream end of the transition layer 35 connects with the gravel drainage layer 52 of the rain garden area 2. The transition layer 35 is laid in layers of graded crushed stone, with the particle size decreasing segment by segment along the seepage direction, and the ratio of the maximum particle size to the minimum particle size is not less than 2:1. The transition layer 35 is divided into n segments (n=3~5) along the seepage direction, and the permeability coefficients of each segment are K1, K2, ..., Kn, satisfying K1>K2>...>Kn, and the ratio of the permeability coefficients of two adjacent segments Ki / Ki+1 is 1.5~3.0.

[0064] Experimental data: Taking n=4 as an example, the transition layer 35 is divided into 4 segments: The decreasing permeability coefficient causes the hydraulic gradient i(x) = q / K(x) to increase along the seepage direction. When the design infiltration flow rate q is 0.0002 m³ / (s·m), the hydraulic gradients for each section are as follows: Section 1: i1 = q / K1 = 0.0002 / (1.2 × 10⁻³) = 0.17; Section 2: i² = q / K² = 0.0002 / (6.0 × 10⁻ 4 =0.33; Section 3: i3 = q / K3 = 0.0002 / (3.0 × 10⁻ 4 =0.67; Section 4: i4 = q / K4 = 0.0002 / (1.5 × 10⁻ 4 =1.33.

[0065] The hydraulic gradient increases gradually along the flow path, forming an accelerated seepage section; the retention capacity of pollutants varies in the same particle size section—the first section retains large particles (>40μm), the second section retains medium particles (10~40μm), the third section retains small particles (5~10μm), and the fourth section retains fine particles (2~5μm), thus achieving graded pollution interception along the flow path.

[0066] As a preferred option: the thickness of each transition layer is 150~300mm, and the total thickness is 600~1200mm. A permeable geotextile isolation layer (200~300g / m²) is set between each section to prevent the mixing of crushed stones of different particle sizes, and the compaction degree of the transition layer is ≥93%.

[0067] Experimental data verification: The total retention rate of suspended solids in the 4-section transition layer 35 is ≥85%. The first section retains approximately 45% of large particles, the second section retains approximately 25% of medium particles, the third section retains approximately 18% of small particles, and the fourth section retains approximately 12% of fine particles. The head loss along the accelerated seepage section is distributed as follows: 0.08m in the first section, 0.17m in the second section, 0.33m in the third section, and 0.67m in the fourth section, with a total head loss of 1.25m. The total head loss of the homogeneous transition layer 35 (single particle size 20~40mm) is 0.42m, and the head loss of the accelerated seepage section is approximately 0.83m higher than that of the homogeneous transition layer 35 with the same particle size.

[0068] The construction of the flow-limiting overflow section 33 is as follows: A water-retaining inverted edge 36 is installed on the upper surface of the downstream end of the variable permeability coefficient transition section 32 along the seepage direction. The construction of the water-retaining inverted edge 36 forms the flow-limiting overflow section 33. The top surface of the water-retaining inverted edge 36 is higher than the top surface of the variable permeability coefficient transition section 32. The top surface freeboard is determined according to the backwater height within the variable permeability coefficient transition section 32 under the design return period rainfall. The top surface freeboard Δh of the water-retaining inverted edge 36 is determined by Δh = h1 + h2, where h1 is the backwater height controlled by the seepage capacity of the variable permeability coefficient transition section 32 under the design return period rainfall, and h2 is the safety freeboard, with h2 ranging from 50mm to 100mm. The backwater height h1 is obtained by integrating the hydraulic gradient i(x) = q / K(x) along the seepage direction of each section of the variable permeability coefficient transition section 32: h1 = h1 = dx , Taking the above four transition layers 35 as an example, the length of each layer is L / 4 (L is the total length of the transition layer, taken as 2.0m). Taking the actual design infiltration flow rate q = 0.001m³ / (s·m), then: h1 = q × (L1 / K1 + L2 / K2 + L3 / K3 + L4 / K4) = 0.001 × (0.5 / 1.2 × 10⁻³ + 0.5 / 6.0 × 10⁻³) 4 +0.5 / 3.0×10⁻ 4 +0.5 / 1.5×10⁻ 4=0.0002×6250=1.25m, the top surface superelevation of the water-blocking reverse side 36 is Δh=h1+h2=1.25+0.075=1.325m (h2 is taken as 75mm).

[0069] As a preferred option: the water-retaining reverse edge 36 is made of C25 concrete with a thickness of 100~200mm and a top surface width of 100~150mm; the top surface superelevation Δh of the water-retaining reverse edge 36 is 0.3~1.5m (depending on the design return period and the parameters of the variable permeability coefficient transition section 32).

[0070] Experimental data verification: Under the design return period (3-year return period) rainfall, the measured water retention height of the water-retaining reverse side 36 is 1.22m, which deviates from the calculated value of 1.25m by less than 3%; within the design return period, all rainwater in the variable permeability coefficient transition section 32 infiltrates without overflow; when the rainfall exceeds the design return period (5-year return period), the water level rises to 1.35m, overflowing over the top surface (1.325m) of the water-retaining reverse side 36, with the overflow volume accounting for about 15% of the total rainfall; the flow-limiting overflow section 33 ensures that the flow capacity within the design return period is not lower than that of the homogeneous transition layer 35 of the same particle size (measured flow capacity deviation <5%).

[0071] S2-5. Installation of Intelligent Monitoring and Automatic Backwashing System: A permeability sensor 61 and a water quality sensor 62 are embedded in the gravel drainage layer 52 of the rain garden area 2. The permeability sensor 61 and water quality sensor 62 are connected to the central controller 63. Simultaneously, a backwashing pipe 64 is laid within the gravel drainage layer 52, with at least a portion of the backwashing pipe 64 located within the variable permeability coefficient transition section 32. This backwashing pipe 64 is used for in-situ backwashing of the decreasing permeability section of the variable permeability coefficient transition section 32. The backwashing pipe 64 is connected to a high-pressure water source via a solenoid valve assembly, and the central controller 63 triggers backwashing based on the signal from the permeability sensor 61.

[0072] When laying the filter layer 35, a portion of the backwash pipe 64 is buried in the filter layer 35. Then, when laying the gravel drainage layer 52, another portion of the backwash pipe 64 is buried in the gravel drainage layer 52. At the same time, a permeation rate sensor 61 and a water quality sensor 62 are buried in the gravel drainage layer 52. The permeation rate sensor 61 and the water quality sensor 62 are then connected to the central processing unit 63. The backwash pipe 64 is also connected to the variable frequency speed control pump and the solenoid valve group, which are also connected to the central processing unit 63.

[0073] The central controller 63 uses the initial design infiltration rate of the rain garden area as a benchmark and collects the current infiltration rate from the infiltration rate sensor 61 in real time. When the infiltration rate decreases by ≥30% relative to the initial design infiltration rate, the backwashing program is automatically triggered. High-pressure water is provided through a variable frequency speed-regulating pump and switched to the backwashing pipeline 64 via a solenoid valve group. The backwashing pressure is 0.2MPa~0.5MPa, and the backwashing duration is 10min~20min. During the backwashing process, the turbidity of the effluent is monitored in real time. When the water quality sensor 62 detects that the effluent turbidity is below the set threshold for 5 consecutive minutes, the backwashing is automatically stopped.

[0074] As a preferred embodiment: the permeation rate sensor 61 is a pressure permeameter with a range of 0~100 mm / h and an accuracy of ±5%. The water quality sensor 62 is a turbidity sensor with a range of 0~1000 NTU and an accuracy of ±5%. The central controller 63 is a PLC or industrial computer with data storage and remote communication functions. The backwash pipe 64 is made of DN50~DN80 stainless steel pipe and has multiple spray holes for water spraying.

[0075] S3, integrated acceptance, involves joint permeability testing of two areas, and construction is completed after passing the test.

[0076] The method for combined permeability testing is as follows: Several test points are selected on the permeable surface layer 43, and the permeability coefficient of each test point is measured using a permeameter. At the same time, water is injected into the rain garden area 2 to the design water level, and the water level drop rate is measured. When the permeability coefficient of the permeable pavement area 1 is ≥0.5mm / s, and the water level drop rate of the rain garden area 2 meets the design requirements, the combined permeability test is deemed qualified.

[0077] As a preferred option: the permeable surface layer 43 has no fewer than 3 testing points per 100m², and a standard permeameter is used. Rain garden area 2 is filled with water to the design water level (300mm), and the time required for the water level to drop from 300mm to 100mm is measured, which must be ≤24 hours.

[0078] The working principle of this application embodiment is as follows: On-site surveying and layout were conducted to determine the boundaries and elevations of the permeable pavement area 1 and the rain garden area 2. According to the design elevation, the permeable pavement area 1 and the rain garden area 2 were excavated as a single unit, forming a continuous foundation pit. An impermeable layer 51 was laid in the rain garden area 2, followed by an impermeable geotextile extending from the permeable pavement area 1 to the rain garden area 2 and connecting with the impermeable layer 51 to form a waterproof base slab 34. In the permeable pavement area 1, a permeable base layer 41, a leveling layer 42, and a permeable surface layer 43 were laid sequentially. Multiple transition layers 35 are laid between area 1 and rain garden area 2. Backwash pipes 64 are buried in the transition layers 35. Water-retaining reverse edges 36 are constructed on the transition layers 35. In rain garden area 2, gravel drainage layer 52 and planting soil layer 53 are laid in sequence. When laying gravel drainage layer 52, backwash pipes 64, infiltration rate sensor 61 and water quality sensor 62 are buried in gravel drainage layer 52. The gravel drainage layer 52 is connected to the downstream end of transition layer 35. Finally, the permeability of the two areas is tested together. After passing the test, the construction is completed.

[0079] During rainfall, rainwater infiltrates into the permeable base layer 41 in the permeable paved area 1 and is blocked by the impermeable base plate 34, preventing it from flowing freely downwards. Instead, it flows horizontally in one dimension along the upper surface of the impermeable base plate within the transition layer 35 into the rain garden area 2. Since the permeability coefficient of the transition layer 35 decreases monotonically along the seepage direction, under a certain infiltration flow rate, rainwater infiltrates more rapidly within the transition layer 35. The coarse-particle section first intercepts coarse-particle sediment, and the fine-particle section intercepts fine-particle sediment, achieving graded interception of pollutants along the process. The head loss of the transition layer 35 increases along the process, and this loss is compensated by the backwater head formed by the water-blocking reverse side 36. Therefore, the flow capacity is no less than that of the homogeneous transition layer 35 of the same particle size, and the backwater raises the water level within the transition layer 35 and prolongs the residence time, further improving the pollutant interception rate.

[0080] When the rainfall intensity does not exceed the design return period, the rainwater entering the transition layer 35 is intercepted by the water-retaining inverted edge 36 and completely filtered before infiltrating into the gravel drainage layer 52. When the rainfall intensity exceeds the design return period, the water level in the transition layer 35 rises and overflows over the top surface of the water-retaining inverted edge 36 into the rain garden area 2 for regulation. This achieves automatic switching between the two working modes of infiltration filtration and overflow transfer, thereby effectively controlling the seepage at the junction of the permeable pavement area 1 and the rain garden area 2, grading the interception of sewage, and automatically switching between infiltration filtration and overflow transfer, thus improving the sewage interception efficiency and service life.

[0081] The central controller 63 uses the initial design infiltration rate of the rain garden area 2 as a benchmark and collects the current infiltration rate from the infiltration rate sensor 61 in real time. When the current infiltration rate decreases by ≥30% relative to the initial design infiltration rate, an automatic backwashing procedure is initiated. High-pressure water is supplied via a variable frequency speed-regulating pump and switched to the backwashing pipeline 64 via a solenoid valve group. The backwashing pressure is 0.2MPa~0.5MPa, and the backwashing duration is 10min~20min. During the backwashing process, the turbidity of the effluent is monitored in real time. When the effluent turbidity is below the set threshold for 5 consecutive minutes, the backwashing is automatically stopped, further improving the interception efficiency and service life.

[0082] The above are all preferred embodiments of this application, and are not intended to limit the scope of protection of this application. Therefore, all equivalent changes made in accordance with the structure, shape and principle of this application should be covered within the scope of protection of this application.

Claims

1. A construction process for permeable paving and rain gardens in sponge cities, characterized in that, Includes the following steps: S1, Construction preparation: Conduct on-site survey and layout to determine the boundaries and elevations of the permeable paving area (1) and the rain garden area (2); S2-1, Integrated foundation pit excavation: The permeable pavement area (1) and the rain garden area (2) are excavated in an integrated manner according to the design elevation to form a continuous foundation pit; S2-2, Construction of the seepage control structure (3): A seepage control structure (3) is constructed at the junction of the permeable pavement area (1) and the rain garden area (2). The seepage control structure (3) includes a water-resistant support section (31), a variable permeability coefficient transition section (32), and a flow-limiting overflow section (33) that are connected and coordinated in sequence along the seepage direction. The waterproof support section (31) supports the variable permeability coefficient transition section (32) from below; the permeability coefficient of the variable permeability coefficient transition section (32) decreases monotonically from the side of the permeable pavement area (1) to the side of the rain garden area (2) along the seepage direction, thereby achieving graded interception of sewage along the process in the variable permeability coefficient transition section (32); the flow-limiting overflow section (33) is set at the downstream end of the variable permeability coefficient transition section (32) along the seepage direction, and its top surface is higher than the top surface of the variable permeability coefficient transition section (32) for the purpose of blocking and impounding water; The three components of the waterproof support section (31), the variable permeability coefficient transition section (32), and the flow-limiting overflow section (33) work together to intercept rainwater entering the variable permeability coefficient transition section (32) within the design return period of rainfall. This allows all the rainwater to infiltrate into the rain garden area (2) after being intercepted by the variable permeability coefficient transition section (32) in stages. When the rainfall exceeds the design return period, the water level in the variable permeability coefficient transition section (32) rises and overflows into the rain garden area (2) over the top surface of the flow-limiting overflow section (33), thus achieving automatic switching between the two working modes of infiltration filtration and overflow transmission. S2-3, Construction of permeable pavement layer (4): In the permeable pavement area (1), permeable base layer (41), leveling layer (42) and permeable surface layer (43) are laid in sequence. S2-4, Construction of the rain garden structure layer (5): In the rain garden area (2), the impermeable layer (51), the gravel drainage layer (52) and the planting soil layer (53) are laid in sequence. The top surface elevation of the planting soil layer (53) is lower than the top surface elevation of the permeable surface layer (43) to form a sunken rain garden. The gravel drainage layer (52) is located on the downstream side of the variable permeability coefficient transition section (32) along the seepage direction and is connected to the downstream end of the variable permeability coefficient transition section (32). S3, Integrated Acceptance.

2. The construction process for a permeable pavement rain garden in a sponge city according to claim 1, characterized in that, The construction of the water-resistant support section (31) is as follows: A geotextile is laid, which extends continuously from the permeable base layer (41) of the permeable paving area (1) to the impermeable layer (51) of the rain garden area (2) and overlaps with it to form a continuous and impermeable waterproof base plate (34); the width of the geotextile extending to one side of the permeable paving area (1) is not less than 1.2 times the horizontal projection width of the transition section (32) with variable permeability coefficient; the overlap width of the geotextile extending to one side of the rain garden area (2) and the impermeable layer (51) is not less than 300mm, and the overlap is sealed by hot-melt welding or adhesive; the geotextile and the bottom surface of the permeable base layer (41) are compacted and closely attached, leaving no gaps between them.

3. The construction process for a permeable pavement rain garden in a sponge city according to claim 1, characterized in that, The construction of the variable permeability transition section (32) is as follows: A transition layer (35) is laid on the upper surface of the waterproof support section (31). The permeability coefficient of the transition layer (35) decreases monotonically from the side of the permeable paving area (1) to the side of the rain garden area (2) along the seepage direction. The downstream end of the transition layer (35) is connected to the gravel drainage layer (52) of the rain garden area (2). The transition layer (35) is laid in layers of graded crushed stone. Its particle size decreases segment by segment along the seepage direction. The ratio of the maximum particle size to the minimum particle size of the transition layer (35) is not less than 2:

1. The transition layer (35) is divided into n segments along the seepage direction, where n is 3 to 5. The permeability coefficients of each segment are K1, K2, ..., Kn, satisfying K1>K2>...>Kn. The ratio of the permeability coefficients of two adjacent segments, Ki / Ki+1, is 1.5 to 3.

0.

4. The construction process for a permeable pavement rain garden in a sponge city according to claim 1, characterized in that, The construction of the flow-limiting overflow section (33) is as follows: A water-blocking reverse edge (36) is provided at the downstream end of the variable permeability coefficient transition section (32) along the seepage direction. The top surface of the water-blocking reverse edge (36) is higher than the top surface of the variable permeability coefficient transition section (32), and the top surface superelevation of the water-blocking reverse edge (36) is determined according to the backwater height in the variable permeability coefficient transition section (32) under the design return period rainfall. The top surface superelevation Δh of the water-blocking reverse edge (36) is determined according to Δh=h1+h2, where h1 is the backwater height controlled by the seepage capacity of the variable permeability coefficient transition section (32) under the design return period rainfall, and h2 is the safety superelevation and h2 is taken as 50mm~100mm. The backwater height h1 is obtained by integrating the hydraulic gradient i(x)=q / K(x) along each section of the variable permeability coefficient transition section (32) along the seepage direction, where q is the design infiltration flow rate and K(x) is the permeability coefficient of the variable permeability coefficient transition section (32) along the seepage direction.

5. The construction process for a permeable pavement rain garden in a sponge city according to claim 1, characterized in that, The permeability coefficient of the variable permeability coefficient transition section (32) decreases along the seepage direction, causing the head loss of the variable permeability coefficient transition section (32) to increase along the seepage direction. This head loss is compensated by the backwater head formed by the flow-limiting overflow section (33), so that the flow capacity of the variable permeability coefficient transition section (32) during the design return period rainfall is not lower than that of the homogeneous transition layer (35) of the same particle size.

6. The construction process for a permeable pavement rain garden in a sponge city according to claim 1, characterized in that, In the rain garden area (2), 3 to 5 levels of rain garden units are set up sequentially from top to bottom along the contour lines of the slope, and adjacent units are separated by energy-dissipating waterfalls.

7. The construction process for a permeable pavement rain garden in a sponge city according to claim 1, characterized in that, In step S2-3, the permeable base layer (41) is laid with graded crushed stone or permeable concrete, with a thickness of 150mm~300mm; the leveling layer (42) is laid with medium sand, with a thickness of 20mm~50mm; the permeable surface layer (43) is laid with permeable bricks or permeable concrete; in step S2-4, the gravel drainage layer (52) has a thickness of 200mm~400mm and a gravel particle size of 20mm~40mm; the planting soil layer (53) has a thickness of 300mm~500mm and contains an improved medium.

8. The construction process for a permeable pavement rain garden in a sponge city according to claim 1, characterized in that, In step S3, a joint permeability test is performed on the two areas. The method for the joint permeability test is as follows: Several test points were selected on the permeable surface layer (43), and the permeability coefficient of each test point was measured using a permeability meter. At the same time, water was injected into the water storage layer of the rain garden area (2) to the design water level, and the water level drop rate was measured. When the permeability coefficient of the permeable paving area (1) is ≥0.5mm / s and the water level drop rate of the rain garden area (2) meets the design requirements, the joint permeability test is deemed qualified.

9. The construction process for a permeable pavement rain garden in a sponge city according to claim 1, characterized in that, Between S2-4 and S3, there is also: Step S2-5: Installation of the intelligent monitoring and automatic backwashing system: A permeability rate sensor (61) and a water quality sensor (62) are embedded in the gravel drainage layer (52), and the signals of each sensor are connected to the central controller (63). A backwash pipe (64) is laid in the gravel drainage layer (52), and the backwash pipe (64) is at least partially laid in the variable permeability coefficient transition section (32) for in-situ backwashing of the permeability coefficient decreasing section of the variable permeability coefficient transition section (32). The backwash pipe (64) is connected to a high-pressure water source through a solenoid valve group, and the central controller (63) triggers backwashing according to the signal of the permeability rate sensor (61).

10. The construction process for a permeable pavement rain garden in a sponge city according to claim 9, characterized in that, The central controller (63) uses the initial design infiltration rate of the rain garden area (2) as a benchmark and collects the current infiltration rate of the infiltration rate sensor (61) in real time. When the current infiltration rate of a rain garden area (2) decreases by ≥30% relative to the initial design infiltration rate, the backwashing program is automatically triggered. A high-pressure water source is provided by a variable frequency speed pump and switched to the backwashing pipeline (64) through the solenoid valve group. The backwashing pressure is 0.2MPa~0.5MPa and the backwashing time is 10min~20min. During the backwashing process, the turbidity of the effluent is monitored in real time by the water quality sensor (62). When the turbidity of the effluent is lower than the set threshold for 5 consecutive minutes, the backwashing is automatically stopped.