A tracked mobile tower crane with autonomous boom lifting and its usage method
By designing a crawler-type mobile tower crane with autonomous boom lifting, the problems of cumbersome relocation and safety hazards of tower cranes have been solved. It enables rapid separation of the crawler walking mechanism and autonomous adjustment of the boom, improving the equipment's maneuverability and safety.
Patent Information
- Application Number
- CN202611592204.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-10-14
- Publication Date
- 2026-11-17
AI Technical Summary
Existing tower cranes are cumbersome and costly to disassemble and assemble during relocation. The overall height of the machine cannot be reduced during travel, limiting its wind resistance. Furthermore, the crawler traveling mechanism cannot be quickly separated from the tower crane body, resulting in poor jacking and positioning accuracy and posing safety hazards.
A tracked mobile tower crane with autonomous boom lifting was designed. It adopts a detachable track walking mechanism, a double lifting frame structure, an automatic insertion and removal pin device, and guide wheels to realize autonomous adjustment and rapid connection and separation of the boom. With the help of lifting cylinders and shear pins, the lifting alignment accuracy and safety are improved.
It enables rapid separation of the tracked walking mechanism from the tower crane body, allowing the boom to rise and fall autonomously, lowering the overall center of gravity, improving equipment maneuverability and wind resistance, reducing the number of equipment required, and enhancing construction efficiency and safety.
Smart Images

Figure CN123105484A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of tower crane technology in engineering machinery, and in particular to a crawler-type mobile tower crane with autonomous boom lifting and lowering and its usage method. Background Technology
[0002] Traditional tower cranes are mostly installed on fixed foundations. The disassembly and relocation of the entire machine is a complicated process that requires large hoisting equipment to complete the disassembly and relocation work. The relocation cycle is long and the cost is high.
[0003] Existing technologies include solutions for automatic tower crane systems. These systems utilize drive units and sensors in the traveling mechanism, slewing mechanism, luffing mechanism, and hoisting mechanism, working in conjunction with a tower controller and a ground control station to achieve automatic operation of the tower crane along a fixed route. However, the traveling mechanism in these solutions is mostly a rail-type traveling support device, where the tower crane moves along a preset track. This does not involve a separable design between the tracked chassis and the tower crane body, nor does it solve the problem of autonomous boom height adjustment. Furthermore, the overall height cannot be lowered during traveling operations, limiting its maneuverability and wind resistance.
[0004] There are also solutions for self-climbing tower cranes, which involve adding tower sections one by one from below the tower body by configuring movable lifting units and climbing frames to increase the tower height. The counterweight boom can pivot between horizontal and vertical positions to adapt to climbing operations. However, this climbing method relies on adding standard sections from below, and the tower body itself continuously increases in height as it climbs. This is a tower height extension technology and cannot achieve autonomous lifting and adjustment of the boom along a fixed tower body. Furthermore, this type of solution does not have crawler-mounted relocation capability, and disassembly and assembly operations are still required for relocation.
[0005] Some tower cranes on the market use tracked bases, which move by being driven by a motor to rotate the track wheels and track chains. Once in place, the base is fixed in the soil using a drive cylinder. However, this type of tracked base is fixedly installed on the tower crane and cannot be quickly separated from the crane body. Each tower crane requires a separate tracked walking mechanism, resulting in high equipment purchase costs. Furthermore, the base itself only has the functions of moving and fixing, and does not have the ability to adjust the boom lifting.
[0006] Currently, there are only a few tower cranes capable of being lifted, with the crawler chassis and tower crane base being an integrated structure. Each tower crane requires a crawler walking mechanism, resulting in high equipment purchase costs. During lifting operations, the alignment process relies heavily on manual insertion and removal of pins, leading to low work efficiency and safety hazards associated with manual high-altitude operations. Furthermore, the lifting guide and positioning structure is simple, making it prone to deviation during the lifting process, resulting in poor alignment accuracy and affecting the safety and reliability of the lifting operation.
[0007] Therefore, there is an urgent need to develop a tracked mobile tower crane with a tracked walking mechanism that can be quickly separated, a boom that can be autonomously and continuously raised and lowered, high jacking and positioning accuracy, and the ability to transfer multiple tower cranes with one set of walking mechanism. This would solve the technical problems of existing technologies, such as cumbersome relocation, high cost, excessive overall height during walking operations, and high safety risks in high wind conditions. Summary of the Invention
[0008] The purpose of this invention is to overcome the shortcomings of the prior art and provide a tracked mobile tower crane with autonomous boom lifting and lowering and a method of use, enabling the entire machine to move independently via the tracked system, and the boom to autonomously adjust its height; after the machine is in position, the tracked walking mechanism can quickly detach from the tower crane body, and one tracked walking mechanism can transport multiple tower cranes; during travel and transport, and in windy conditions, the boom can be lowered to its lowest height, reducing the overall center of gravity and improving the equipment's passability and wind resistance safety; the lifting operation uses an automatic insertion and removal pin device in conjunction with shear pins, along with multiple sets of guide wheel structures, to improve the lifting alignment accuracy and operational safety.
[0009] To achieve the above objectives, the present invention adopts the following technical solution: A tracked mobile tower crane with autonomous boom lifting includes a tracked traveling mechanism, a support base, a tower body, a lower lifting frame, an upper lifting frame, a slewing bearing, a boom mounting base, a lifting boom, and a counterweight boom. The tracked traveling mechanism is quickly and detachably connected to the support base via an automatic pin-plugging device. The bottom of the tower body is connected to the tower body mounting base on the support base via pins. The tower body is composed of multiple standard sections, each with several shear pin holes spaced vertically. The lower lifting frame is fitted onto the outside of the tower body, as is the upper lifting frame. A lifting cylinder is installed between the lower and upper lifting frames. The lower lifting frame is equipped with an automatic pin-plugging device and shear pins, with the shear pins threadedly connected to the automatic pin-plugging device. The lower lifting frame also includes... There are multiple sets of guide wheel boxes, and guide wheels are installed inside the guide wheel boxes. The guide wheels fit against the outer wall of the tower body to achieve lifting and lowering guidance. The internal structure of the upper lifting frame is the same as that of the lower lifting frame, and it is also equipped with an automatic insertion and removal pin device, shear pin, guide wheel box and guide wheels. The lower end of the slewing bearing is bolted to the upper lifting frame, and the upper flange of the slewing bearing is connected to the boom mounting seat. The boom mounting seat is equipped with a lifting boom mounting seat and a counterweight boom mounting seat. The lifting boom is connected to the lifting boom mounting seat, and the counterweight boom is connected to the counterweight boom mounting seat. A counterweight block is installed at the tail of the counterweight boom.
[0010] The tracked walking mechanism includes a walking track and an intermediate load-bearing platform. A support base is set on the intermediate load-bearing platform. Each support base is equipped with an automatic pin insertion and removal device. The automatic pin insertion and removal device is adapted to the support at the bottom of the support base to realize the quick connection and separation of the tracked walking mechanism and the support base.
[0011] The support base includes a load-bearing platform, a tower mounting base, multiple sets of support cylinders, and supports. The multiple sets of support cylinders are vertically arranged on the load-bearing platform. When the support cylinders extend, they can lift the entire machine, causing the track walking mechanism to lift off the ground. The supports are arranged under the load-bearing platform and are used to connect with the automatic insertion and removal pin device of the track walking mechanism.
[0012] The lower jacking frame includes a jacking frame, which is equipped with guide wheel boxes. Each guide wheel box contains guide wheels. Hydraulic cylinder mounting seats are located at the crossbeam positions of the jacking frame. The lower end of the jacking cylinder is hinged to the cylinder mounting seat of the lower jacking frame, and the upper end of the jacking cylinder is hinged to the cylinder mounting seat of the upper jacking frame. The jacking frame has pre-drilled assembly holes, in which automatic insertion and removal pin devices are installed. The front end of the automatic insertion and removal pin device is threadedly connected to a shear pin. The shear pin can be inserted into the shear pin hole of the standard tower section to achieve load-bearing positioning.
[0013] The upper lifting frame includes an inner frame and an outer frame, which are welded and fixed together. The lower end of the outer frame is used to connect to the slewing bearing. The inner frame is equipped with the same guide wheel box, guide wheels, cylinder mounting base, automatic insertion and removal pin device, and shear pin as the lower lifting frame.
[0014] The boom mounting base includes a frame, a lower flange, a boom mounting base, and a counterweight boom mounting base. The lower flange is connected to the upper flange of the slewing bearing. The boom mounting base is located at the front end of the frame for assembling the boom, and the counterweight boom mounting base is located at the rear end of the frame for assembling the counterweight boom.
[0015] This invention also provides a method for using the aforementioned tracked mobile tower crane, including the following boom lifting steps: the tracked walking mechanism carries the entire machine to the construction position; during the transport and carrying operation, the boom is in its lowest position to ensure the stability of the entire machine during travel; the support cylinder of the support base extends, presses against the ground, and lifts the support base together with the upper tower crane as a whole; the pin of the automatic insertion and removal pin device of the upper lifting frame retracts, and the shear pin of the upper lifting frame disengages from the shear pin hole in the tower body; at this time, the shear pin of the lower lifting frame remains inserted into the pin hole in the tower body, and the lower lifting frame bears all the load of the upper part; the lifting mechanism is then activated. The lifting cylinder extends, driving the upper lifting frame, slewing bearing, boom mounting base, boom, and counterweight boom to rise as a whole, completing one lifting stroke. After a single lifting stroke, the pin of the automatic insertion and removal device of the lower lifting frame retracts, the shear pin of the lower lifting frame exits the pin hole in the tower body, and the pin of the automatic insertion and removal device of the upper lifting frame extends, inserting the shear pin of the upper lifting frame into the corresponding pin hole in the tower body, switching the load to the upper lifting frame. The lifting cylinder retracts, pulling the lower lifting frame upward, completing one full lifting cycle. The above steps are repeated until the boom is raised to the target working height. When it is necessary to lower the boom, the above cycle is executed in reverse to lower the boom to the lowest position.
[0016] Once the entire machine is in place and the support cylinders have completed their ground support, the automatic pin insertion and removal device of the crawler walking mechanism can be controlled to pull out the pin shaft, thereby separating the crawler walking mechanism from the support base. The crawler walking mechanism can then leave the work station to transport other tower crane equipment of the same model. The tower crane slewing operation is driven by the slewing bearing.
[0017] Compared with the prior art, the present invention has the following beneficial effects: 1. The present invention features a detachable tracked walking mechanism. The tracked walking mechanism is quickly and detachably connected to the support base via an automatic plug-in pin device. After being in place, the tracked walking mechanism can be detached from the tower crane body. One tracked walking mechanism can transport multiple tower cranes, which helps to reduce equipment procurement costs.
[0018] 2. This invention features a double-lifting frame structure with a lower lifting frame and an upper lifting frame. Combined with lifting cylinders, an automatic insertion and removal pin device, and shear pins, it can autonomously and continuously complete the raising and lowering of the boom without the need for external hoisting equipment. In travel and transportation conditions or in windy weather, the boom can be lowered to its lowest point, reducing the overall center of gravity of the machine and improving the equipment's passability and wind resistance safety performance.
[0019] 3. The lifting frame of this invention is equipped with multiple sets of guide wheels, which are in close contact with the outer wall of the tower body throughout the lifting process, and guide and limit the lifting movement, which helps to improve the positioning accuracy of the lifting and avoid the risk of the lifting frame deviating and jamming; the shear pin is driven by an automatic pin insertion and removal device, which replaces manual pin insertion and removal, which helps to reduce the risk of high-altitude operation and improve the automation level and safety of the lifting operation.
[0020] 4. The present invention enables the entire machine to move to the site autonomously using its tracks, without the need for a large truck crane for disassembly and assembly, which helps to shorten the time for equipment to enter and move to the site and improve the construction efficiency of the construction site. Attached Figure Description
[0021] Figure 1 This is a front view of a tracked mobile tower crane with autonomous boom lifting capability according to the present invention; Figure 2 This is a diagonal view of the tracked walking mechanism of the present invention; Figure 3 This is a two-view oblique projection of the support base of the present invention; Figure 4 This is a two-view oblique projection of the lower lifting frame of the present invention; Figure 5 This is a two-view oblique projection of the lifting frame of the present invention; Figure 6 This is a two-view oblique projection of the boom mounting base of the present invention.
[0022] Marking Explanation: 100, Tracked Traveling Mechanism; 101, Traveling Track; 102, Intermediate Load-Bearing Platform; 103, Support Base; 104, Automatic Insertion and Removal Pin Device for Tracked Traveling Mechanism; 200, Support Base; 201, Load-Bearing Platform; 202, Tower Body Mounting Base; 203, Support Cylinder; 204, Support; 300, Tower Body; 400, Lower Lifting Frame; 401, Lifting Frame; 402, Lower Lifting Frame Guide Wheel Box; 403, Lower Lifting Frame Guide Wheel; 404, Lower Lifting Frame Cylinder Mounting Base; 405, Lifting Cylinder; 406, Lower Lifting Frame Automatic pin insertion / removal device; 407; Lower lifting frame shear pin; 500; Upper lifting frame; 501; Internal frame; 502; External frame; 503; Upper lifting frame guide wheel box; 504; Upper lifting frame guide wheel; 505; Upper lifting frame cylinder mounting seat; 506; Upper lifting frame automatic pin insertion / removal device; 507; Upper lifting frame shear pin; 600; Slewing bearing; 700; Boom mounting seat; 701; Frame; 702; Lower flange; 703; Lifting boom mounting seat; 704; Counterweight boom mounting seat; 800; Lifting boom; 900; Counterweight boom. Detailed Implementation
[0023] The technical solutions of the present invention will be further described below with reference to the accompanying drawings and embodiments.
[0024] like Figure 1 As shown, a tracked mobile tower crane with autonomous boom lifting capability includes a tracked walking mechanism 100, a support base 200, a tower body 300, a lower lifting frame 400, an upper lifting frame 500, a slewing bearing 600, a boom mounting base 700, a lifting boom 800, and a counterweight boom 900. The entire machine uses the tracked walking mechanism 100 to carry the support base 200 and the upper tower crane structure to achieve self-moving relocation. The lower lifting frame 400 and the upper lifting frame 500 cooperate with the lifting cylinder 405 to achieve autonomous lifting and adjustment of the boom along the tower body 300.
[0025] like Figure 2 As shown, the tracked traveling mechanism 100 includes a traveling track 101 and an intermediate load-bearing platform 102. A support base 103 is arranged on the intermediate load-bearing platform 102, and an automatic pin insertion / retraction device 104 is installed on the support base 103. The automatic pin insertion / retraction device 104 and the support base 204 of the support base 200 are docked and locked, enabling the tracked traveling mechanism 100 to move the entire machine while carrying it. The automatic pin insertion / retraction device 104 can be an electric push rod driven or hydraulically driven pin insertion / retraction mechanism to achieve automatic extension and retraction of the pin shaft. The specific model is selected according to the actual load requirements. The traveling track 101 can be a steel track plate or a rubber track plate commonly used in construction machinery, adapting to different construction site conditions.
[0026] like Figure 3As shown, the support base 200 consists of a load-bearing platform 201, a tower body mounting base 202, multiple sets of support cylinders 203, and supports 204. The bottom pin of the tower body 300 is connected to the tower body mounting base 202. After the equipment is in place, the multiple sets of support cylinders 203 extend downwards to support the ground, lifting the entire machine, and the crawler walking mechanism 100 can be unloaded and separated. The support cylinders 203 can be hydraulic outrigger cylinders commonly used in engineering machinery, which have sufficient support rigidity and stroke. The mating surface between the supports 204 and the automatic insertion and removal pin device 104 of the crawler walking mechanism is equipped with a positioning guide structure to facilitate quick alignment and connection.
[0027] The tower body 300 is assembled from several standard sections. Shear pin holes are equidistantly spaced vertically in each standard section for the insertion of shear pins 407 from the lower jacking frame and shear pins 507 from the upper jacking frame to transfer the load from the upper structure. The standard sections can be constructed using welded steel truss structures, with the shear pin holes located at the nodes of the main chord or web members to ensure load-bearing strength.
[0028] like Figure 4 As shown, the lower lifting frame 400 includes a lifting frame 401, which is connected to a lower lifting frame guide wheel box 402 via a flange. The lower lifting frame guide wheel box 402 houses the lower lifting frame guide wheel 403. A lower lifting frame cylinder mounting seat 404 is installed on the crossbeam of the lifting frame 401. The lower end of the lifting cylinder 405 is hinged to the lower lifting frame cylinder mounting seat 404. An automatic insertion / removal pin device 406 for the lower lifting frame is installed on the lifting frame 401, and its front end is threadedly connected to a lower lifting frame shear pin 407. Each lower lifting frame guide wheel box 402 is equipped with a lower lifting frame guide wheel 403. During lifting operations, the lower lifting frame guide wheel 403 is pressed against the outer surface of the standard tower section for guidance and limitation. The lifting cylinder 405 can be a double-acting hydraulic cylinder, whose extension and retraction are controlled by a hydraulic system to provide the thrust and pull required for lifting. The guide wheel 403 of the lower lifting frame can be an eccentric shaft type adjustable guide wheel, which is convenient to adjust the gap with the outer wall of the tower during installation and ensures the guiding accuracy.
[0029] like Figure 5As shown, the upper lifting frame 500 includes an inner frame 501 and an outer frame 502, which are welded together. The outer frame 502 is bolted to the slewing bearing 600. The inner frame 501 is connected to the upper lifting frame guide wheel box 503 via a flange. The upper lifting frame guide wheel 504 is installed inside the upper lifting frame guide wheel box 503. The upper lifting frame guide wheel 504 is close to the outer surface of the standard tower section for guidance and positioning. The crossbeam is equipped with an upper lifting frame cylinder mounting seat 505, and the upper end of the lifting cylinder 405 is hinged to the upper lifting frame cylinder mounting seat 505. The internal frame 501 is equipped with an automatic upper lifting frame insertion and removal pin device 506, and the front end of the automatic upper lifting frame insertion and removal pin device 506 is threadedly connected to the upper lifting frame shear pin 507. The upper lifting frame shear pin 507 can be inserted into the shear pin hole of the standard section of the tower body to achieve load-bearing positioning. The structural configuration of the internal frame 501 is consistent with that of the lower lifting frame 400. The outer frame 502 of the upper lifting frame 500 serves as the mounting base of the slewing bearing 600 and must have sufficient structural rigidity to withstand the overturning moment during slewing operations.
[0030] The lower part of the slewing bearing 600 is bolted to the upper lifting frame 500, and the upper flange is connected to the boom mounting base 700. The slewing bearing 600 can be a single-row four-point contact ball slewing bearing or a three-row roller slewing bearing, selected according to the rated lifting torque of the tower crane. It is driven by the slewing drive mechanism to realize the slewing operation of the upper structure of the tower crane.
[0031] like Figure 6 As shown, the boom mounting base 700 includes a frame 701, a lower flange 702, a boom mounting base 703, and a counterweight boom mounting base 704. The boom 800 is mounted on the boom mounting base 703; the counterweight boom 900 is mounted on the counterweight boom mounting base 704, and a counterweight block is mounted at the tail of the counterweight boom. The lower flange 702 is connected to the upper flange of the slewing bearing 600 by high-strength bolts to ensure reliable connection. The boom 800 can be a truss-type boom, and the counterweight boom 900 can be a truss-type counterweight boom. The tail counterweight block is configured according to the boom length and rated lifting capacity.
[0032] During transport, the boom remains at its lowest position, and the tracked walking mechanism 100 carries the entire machine to the construction site; the support cylinder 203 of the support base 200 extends to the ground for leveling. At this time, the center of gravity of the entire machine is low, which is beneficial to the stability and passability during the movement, and can also maintain a low windward height in windy conditions.
[0033] During the lifting operation, the automatic pin insertion and removal device 506 of the upper lifting frame 500 retracts, and the shear pin 507 of the upper lifting frame disengages from the pin hole in the tower body. At this time, the shear pin 407 of the lower lifting frame 400 inserts into the pin hole to bear the upper load. The lifting cylinder 405 extends, lifting the upper lifting frame and the upper boom together upwards by one stroke. After reaching the target height, the automatic pin insertion and removal device 406 of the lower lifting frame 400 retracts, and the shear pin 407 of the lower lifting frame exits from the pin hole. The automatic pin insertion and removal device 506 of the upper lifting frame 500 extends, and the shear pin 507 of the upper lifting frame inserts into the pin hole in the tower body, transferring the load to the upper lifting frame. The lifting cylinder 405 retracts, driving the lower lifting frame 400 to move upwards, completing one lifting cycle. The cycle is repeated until the target height is reached. Throughout the lifting process, the lower lifting frame guide wheel 403 of the lower lifting frame 400 and the upper lifting frame guide wheel 504 of the upper lifting frame 500 always roll in contact with the outer wall of the tower body, guiding and limiting the lifting movement of the lifting frame to prevent the lifting frame from deviating or getting stuck.
[0034] After the support cylinder 203 lands and supports the tower crane body, the pin of the automatic insertion and removal pin device 104 of the crawler traveling mechanism is pulled out, the crawler traveling mechanism 100 separates from the support base 200, and the crawler traveling mechanism leaves the site to transport other tower crane equipment. Such a crawler traveling mechanism can serve multiple tower cranes, which helps to reduce the number of equipment configurations and procurement costs.
[0035] When it is necessary to lower the boom height or avoid danger in strong winds, the lifting cycle is executed in reverse to lower the boom and counterweight boom to their lowest positions, thereby lowering the overall center of gravity and improving equipment safety. During the descent, the upper lifting frame 500 first bears the load, and the lifting cylinder 405 retracts, causing the upper lifting frame to descend one stroke. Then, the automatic insertion and removal pin device 406 of the lower lifting frame 400 extends, inserting the lower lifting frame shear pin 407 into the pin hole to bear the load. After the upper lifting frame 500 disengages, the lifting cylinder 405 extends and pulls the upper lifting frame down. This cycle is repeated until the boom is lowered to its lowest position.
[0036] The slewing motion of the tower crane is driven by the slewing bearing 600. The boom 800 and counterweight boom 900 rotate together with the boom mounting base 700 around the tower axis to achieve lifting operations in different directions.
[0037] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention and are not intended to limit it. Although the present invention has been described in detail with reference to preferred embodiments, those skilled in the art should understand that modifications or equivalent substitutions can be made to the technical solutions of the present invention without departing from the spirit and scope of the technical solutions of the present invention, and all such modifications or substitutions should be covered within the scope of the claims of the present invention.
Claims
1. A tracked mobile tower crane with autonomous boom lifting capability, characterized in that, It includes a tracked walking mechanism (100), a support base (200), a tower body (300), a lower lifting frame (400), an upper lifting frame (500), a slewing bearing (600), a boom mounting base (700), a lifting boom (800), and a counterweight boom (900); The tracked walking mechanism (100) is detachably connected to the support base (200) via an automatic insertion and removal pin device; The bottom of the tower body (300) is connected to the support base (200). The tower body (300) is composed of multiple standard sections. The standard sections are provided with a number of shear pin holes at intervals along the vertical direction. The lower lifting frame (400) and the upper lifting frame (500) are both fitted onto the outside of the tower body (300), and a lifting cylinder (405) is provided between the lower lifting frame (400) and the upper lifting frame (500); Both the lower lifting frame (400) and the upper lifting frame (500) are equipped with an automatic insertion and removal pin device and a shear pin connected to the automatic insertion and removal pin device. The shear pin can be inserted into the shear pin hole of the tower body (300) to achieve load-bearing positioning. The lower end of the slewing bearing (600) is fixedly connected to the upper lifting frame (500), the upper end of the slewing bearing (600) is connected to the boom mounting base (700), and the lifting boom (800) and the counterweight boom (900) are respectively connected to the boom mounting base (700).
2. A tracked mobile tower crane with autonomous boom lifting capability according to claim 1, characterized in that, The tracked walking mechanism (100) includes a walking track (101) and an intermediate load-bearing platform (102). At least one set of support seats (103) is provided on the intermediate load-bearing platform (102). Each support seat (103) is equipped with an automatic insertion and removal pin device (104) for the tracked walking mechanism. The automatic insertion and removal pin device (104) for the tracked walking mechanism is adapted to the support (204) at the lower part of the support base (200) to realize the quick connection and separation of the tracked walking mechanism (100) and the support base (200).
3. A tracked mobile tower crane with autonomous boom lifting capability according to claim 2, characterized in that, The support base (200) includes a load-bearing platform (201), a tower mounting base (202), multiple sets of support cylinders (203), and a support (204); the multiple sets of support cylinders (203) are vertically arranged on the load-bearing platform (201), and the support cylinders (203) can extend to lift the whole machine, so that the track walking mechanism (100) is off the ground; the support (204) is arranged on the lower side of the load-bearing platform (201) and is used to dock with the automatic insertion and removal pin device (104) of the track walking mechanism.
4. A tracked mobile tower crane with autonomous boom lifting capability according to claim 1, characterized in that, The lower lifting frame (400) includes a lifting frame (401), the lifting frame (401) is provided with at least one set of lower lifting frame guide wheel boxes (402), the lower lifting frame guide wheel boxes (402) are equipped with lower lifting frame guide wheels (403), the lower lifting frame guide wheels (403) are set in contact with the outer wall of the tower body (300) for lifting and guiding.
5. A tracked mobile tower crane with autonomous boom lifting capability according to claim 4, characterized in that, The lifting frame (401) is provided with a lower lifting frame cylinder mounting seat (404), and the lower end of the lifting cylinder (405) is hinged to the lower lifting frame cylinder mounting seat (404); the lifting frame (401) is provided with a lower lifting frame automatic insertion and removal pin device (406), and the front end of the lower lifting frame automatic insertion and removal pin device (406) is threadedly connected to the lower lifting frame shear pin (407).
6. A tracked mobile tower crane with autonomous boom lifting capability according to claim 1, characterized in that, The upper lifting frame (500) includes an inner frame (501) and an outer frame (502), the inner frame (501) and the outer frame (502) being fixedly connected; the lower end of the outer frame (502) is connected to the slewing bearing (600); the inner frame (501) is provided with an upper lifting frame guide wheel box (503), and an upper lifting frame guide wheel (504) is installed inside the upper lifting frame guide wheel box (503), the upper lifting frame guide wheel (504) fitting against the tower body (3). 00) Outer wall setting; the inner frame (501) is provided with an upper lifting frame cylinder mounting seat (505), the upper end of the lifting cylinder (405) is hinged to the upper lifting frame cylinder mounting seat (505); the inner frame (501) is provided with an upper lifting frame automatic insertion and removal pin device (506), the front end of the upper lifting frame automatic insertion and removal pin device (506) is threadedly connected to the upper lifting frame shear pin (507); the structural configuration of the inner frame (501) is consistent with that of the lower lifting frame (400).
7. A tracked mobile tower crane with autonomous boom lifting capability according to claim 1, characterized in that, The boom mounting base (700) includes a frame (701), a lower flange (702), a boom mounting base (703), and a counterweight boom mounting base (704); the lower flange (702) is connected to the upper flange of the slewing bearing (600); the boom mounting base (703) is located at one end of the frame (701) for mounting the boom (800); and the counterweight boom mounting base (704) is located at the other end of the frame (701) for mounting the counterweight boom (900).
8. A tracked mobile tower crane with autonomous boom lifting capability according to claim 1, characterized in that, The tail of the balance arm (900) is equipped with a counterweight.
9. A method of using a tracked mobile tower crane with autonomous boom lifting as described in any one of claims 1 to 8, characterized in that, Includes the following steps: S1. The tracked walking mechanism (100) carries the whole machine to the construction position, and the boom is at the lowest position during the transfer operation. S2. The support cylinder (203) of the support base (200) extends to lift the support base (200) together with the upper tower crane as a whole; S3. The automatic insertion and removal pin device of the upper lifting frame (500) retracts, the shear pin of the upper lifting frame (500) disengages from the shear pin hole of the tower body (300), and the shear pin of the lower lifting frame (400) remains inserted into the shear pin hole of the tower body (300), and the upper load is borne by the lower lifting frame (400). S4. The lifting cylinder (405) extends and drives the upper lifting frame (500), the slewing bearing (600), the boom mounting base (700), the lifting boom (800) and the counterweight boom (900) to lift upward as a whole, completing one lifting stroke; S5. After a single lifting stroke is completed, the automatic insertion and removal pin device of the lower lifting frame (400) retracts, the shear pin of the lower lifting frame (400) exits the shear pin hole of the tower body (300), the automatic insertion and removal pin device of the upper lifting frame (500) extends, the shear pin of the upper lifting frame (500) inserts into the corresponding shear pin hole of the tower body (300), and the load is switched to be borne by the upper lifting frame (500). S6. The lifting cylinder (405) retracts, pulling the lower lifting frame (400) upward to complete one lifting cycle; repeat steps S3 to S6 until the boom is lifted to the target working height. When it is necessary to lower the boom, reverse the above lifting cycle process to lower the boom back to the lowest position.
10. The method of use according to claim 9, characterized in that, It also includes a track walking mechanism separation step: after the whole machine is in place and the support cylinder (203) is supported on the ground, the pin of the automatic insertion and removal pin device of the track walking mechanism (100) is pulled out, so that the track walking mechanism (100) is separated from the support base (200), and the track walking mechanism (100) drives away from the work position for the transfer of other tower crane equipment of the same model.