A construction method for the steel-concrete composite section of the main tower
By using a prestressed support box system, gradient zoning of stiffening ribs, segmented pouring of micro-expansion concrete, and staged tensioning technology, the stress concentration and stiffness difference problems in the steel-concrete composite section of the main tower were solved, achieving efficient force transfer and long-term durability of the structure.
Patent Information
- Application Number
- CN202611383210.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-09-08
- Publication Date
- 2026-11-17
AI Technical Summary
The existing steel-concrete composite section of the main tower has problems with stress concentration, stiffness differences, and structural durability caused by early shrinkage deformation in terms of structural stress mechanism and construction control.
The prestressed support box system with gradient zoning of stiffening ribs, symmetrical pouring of micro-expansion concrete in sections, and step-gradient tensioning process are adopted. Combined with three-dimensional positioning steel skeleton network and high-strength grouting and anchoring technology, the end face bearing pressure transmission and structural stiffness are smoothly transitioned, and early shrinkage deformation is compensated.
It significantly improves the splitting and fatigue resistance of the steel-concrete composite section of the main tower, ensures the long-term tight pressing and load-bearing reliability of the steel-concrete interface, and improves the service durability of the structure.
Smart Images

Figure CN123109065A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of bridge engineering and civil engineering construction technology, specifically to a construction method for a steel-concrete composite section of a main tower. Background Technology
[0002] In the field of bridge engineering, the main towers of long-span cable-stayed or suspension bridges typically employ a hybrid load-bearing system consisting of a substructure of concrete and an upper structure of steel. The steel-concrete composite section of the main tower, as a crucial link connecting two materials with different elastic moduli, must withstand and transmit enormous axial forces, bending moments, and shear forces. However, existing steel-concrete composite sections of main towers still face the following core technical challenges in terms of structural stress mechanisms and construction control: Firstly, the anchoring of traditional steel-concrete composite sections mainly relies on a dense array of conventional cylindrical shear studs on the inner side of the steel plate for interface force transfer. Under this point-shear force transfer mode, the stress generated by the load is highly concentrated in the root region of the shear studs. Under complex dynamic loads from large vehicles and wind loads, the local shear stress can easily exceed the tensile strength limit of the concrete, thus inducing cluster-stud splitting failure, resulting in low stress redundancy in the overall structure.
[0003] Secondly, existing designs for the steel-concrete composite sections of main towers typically employ a design with evenly spaced longitudinal stiffening ribs. This homogenized stiffening support structure results in significant differences in cross-sectional stiffness at the steel-concrete interface. Under long-term alternating loads, the stress transfer from the pure concrete section to the pure steel structure section cannot achieve a smooth transition. The abrupt change in stiffness at the interface generates a large local additional bending moment, making the main load-bearing wall panels highly susceptible to local buckling and fatigue cracking.
[0004] Finally, in the conventional construction procedures for the joint section, a one-time large-volume pouring combined with a one-time full-load tensioning process after the concrete reaches its design strength is often adopted. Conventional pouring and tensioning procedures fail to effectively compensate for the shrinkage deformation of the large-volume concrete during the early hydration heat physical cooling stage. This results in microscopic shrinkage separation gaps between the concrete and the internal steel plate before the interface prestress is established. Simultaneously, the conventional asymmetric large-volume single-sided pouring operation forces the thin-walled steel shell to exhibit significant horizontal eccentric deflection deformation, further weakening the physical compression and compactness between the steel structure and the core concrete, severely affecting the long-term durability of the joint section's stress transfer. Summary of the Invention
[0005] To achieve the above objectives, the present invention provides the following technical solution: This invention provides a construction method for a steel-concrete composite section of a main tower, comprising the following steps: S100, steel structure fabrication and installation: a prestressed support box system is welded on the inner side of the main load-bearing wall panel of the steel-concrete composite section of the main tower, and stiffening ribs are arranged in gradient zones along the elevation direction on the main load-bearing wall panel; the prestressed support box system is composed of anchor plates, anchor pipes, compressive stiffening ribs and bearing plates connected together, the anchor pipes penetrate the internal cavity of the main load-bearing wall panel and are connected to the bearing plates, and the bearing plates are set perpendicular to the main load direction; S200, Reinforcing steel and prestressed duct installation: A three-dimensional positioning reinforcing steel skeleton mesh is tied in the internal cavity of the steel-concrete composite section of the main tower, and the prestressed duct is inserted into the three-dimensional positioning reinforcing steel skeleton mesh for positioning and fixing, so that the tail end of the prestressed duct is connected to the anchor pipe. S300, Compartmentalized Concrete Casting: A compartmentalized symmetrical casting process is adopted, in which micro-expansion concrete is cast in layers into the internal cavity of the main tower steel-concrete composite section and then cured by watering. S400, Staged Gradient Tensioning and Grouting Anchoring: Prestressed steel strands are inserted into the prestressed duct, and the prestressed steel strands are tensioned symmetrically in stages based on the strength development state of the micro-expansion concrete; when the micro-expansion concrete reaches the first preset strength, the first stage tensioning of the first batch of prestressed steel strands is carried out to establish the initial interface stress; after the micro-expansion concrete reaches the second preset strength and meets the preset age, the second stage tensioning of the remaining prestressed steel strands is carried out, and the duct is grouted and anchored after tensioning is completed.
[0006] Furthermore, the gradient zoning of stiffening ribs along the elevation direction on the main load-bearing wall panel specifically includes: The main tower steel-concrete composite section is divided into a strong constraint zone, a stiffness transition zone, and a weak constraint zone along the elevation direction from bottom to top. Within the strongly constrained zone, the stiffening ribs are densely arranged at a first preset interval, and a transverse connecting partition perpendicular to the main load-bearing wall panel is added. Within the stiffness transition zone, the spacing of the stiffening ribs gradually and smoothly transitions from the first preset spacing to the second preset spacing, and the second preset spacing is greater than the first preset spacing. Within the weakly constrained area, the stiffening ribs are arranged at a third preset spacing, which is greater than the second preset spacing.
[0007] Furthermore, the prestressed support box system adopts the following connection relationship during assembly welding: The anchor plate is fixed to one end of the anchor pipe by full penetration welding; The compressive stiffening ribs are fully welded to the side wall of the anchor plate, the outer wall of the anchor pipe, and the inner wall of the main load-bearing wall plate, respectively. The pressure plate is installed at the other end of the anchor pipe away from the anchor plate, and the surface of the pressure plate is perpendicular to the transmission direction of the prestressing tension reaction force.
[0008] Furthermore, step S100 also includes: Several high-strength studs are welded to the surface of the bearing plate on the side opposite to the anchor pipe, so that during the tensioning process in step S400, the prestress reaction force of the bearing plate is dispersed and transferred to the micro-expansion concrete through the high-strength studs, forming end face bearing anchorage. In step S100, after the steel structure fabrication and installation are completed and welded, an anti-corrosion treatment process is also included: After the prestressed support box system and the stiffening ribs are welded together and pass the ultrasonic non-destructive testing of the welds, epoxy zinc-rich primer and fluorocarbon topcoat are sprayed sequentially on the surface of the steel structure, and the total dry film thickness is controlled to be greater than or equal to the preset thickness threshold.
[0009] Furthermore, the spatial binding process of the three-dimensional positioning steel reinforcement mesh includes: Several longitudinal steel bars are arranged in multiple layers along the longitudinal direction of the main load-bearing wall panel, and several closed stirrups with transverse spacing are tied to the outside of the multiple layers of longitudinal steel bars. The intersections of the longitudinal reinforcing bars and the closed stirrups are fixed by binding or spot welding to form a three-dimensional mesh skeleton that is enclosed in the internal cavity and used to accommodate the prestressed duct.
[0010] Furthermore, in step S200, the process of inserting the prestressed duct into the three-dimensional positioning steel reinforcement mesh for positioning and fixing is subject to the following high-precision limitations: The prestressed pipe is made of plastic corrugated pipe or metal corrugated pipe; The prestressed duct is inserted into the grid of the three-dimensional positioning steel reinforcement mesh, and the prestressed duct is locked and positioned to the three-dimensional positioning steel reinforcement mesh using additional positioning steel bars. After positioning and fixing, the grid control spacing between adjacent prestressed pipes meets the preset spacing threshold, and the overall straightness error of the prestressed pipes is less than or equal to the preset error threshold. When the tail end of the prestressed duct is connected to the anchor pipe, a grout leakage prevention and sealing process is also included: The end of the prestressed duct is coaxially inserted into the inner hole of the anchor pipe, and sealing tape or sealant is wrapped around the overlapping joint of the prestressed duct and the anchor pipe to prevent cement slurry leakage during the pouring process in step S300, which could lead to blockage of the prestressed duct.
[0011] Furthermore, in step S300, the use of a compartmentalized symmetrical casting process, in which micro-expansion concrete is cast in layers into the internal cavity of the main tower's steel-concrete composite section, is defined by the following spatial compartmentalization and casting sequence: Along the horizontal cross-sectional direction, the internal cavity is divided into a core compartment located in the middle and two side compartments symmetrically distributed on both sides of the core compartment; Within a single layer height construction cycle, the micro-expansion concrete is first poured into the core compartment, and then the micro-expansion concrete is simultaneously poured evenly and symmetrically into the two side compartments to avoid structural deformation caused by unilateral eccentric loading.
[0012] Furthermore, in step S300, the layered pouring process has the following dynamic operation and anti-interference restrictions: The thickness of the micro-expansion concrete in a single layered pour is controlled to be less than or equal to a preset layer thickness threshold. During the pouring operation, the vibrating equipment is inserted into the internal cavity through the vibration hole reserved on the outer wall of the main tower steel-concrete composite section, and the micro-expansion concrete is vibrated in a high-frequency low-amplitude mode to prevent aggregate segregation and avoid disturbing the spatial positioning accuracy of the prestressed duct in the internal cavity. The physicochemical properties and curing control of the micro-expansion concrete specifically include: The micro-expansion concrete mix proportion includes a concrete expansion agent, which is used to generate micro-expansion in volume during the hydration and crystallization process to offset the shrinkage deformation caused by early hydration heat. After the micro-expansion concrete reaches its final set state, geotextile is covered on its exposed interface and water is continuously sprayed for moisturizing and curing. The curing period is greater than or equal to the preset minimum number of days, thereby ensuring tight bonding between the steel structure and the concrete interface and eliminating micro-delamination at the interface.
[0013] Furthermore, the staged symmetrical tensioning of the prestressed steel strands based on the strength development state of the micro-expansion concrete includes the following specific order and condition triggering control: The first preset strength is set as a preset first percentage of the design strength standard value of the micro-expansion concrete; when the first preset strength is reached, a first proportion of the prestressed steel strands in the preset total number of strands are selected symmetrically along the cross section to perform the first-order tensioning; The second preset strength is set as a preset second percentage of the design strength standard value of the micro-expansion concrete, and the preset second percentage is greater than the preset first percentage; after the second preset strength is met and the on-site curing time of the micro-expansion concrete reaches the preset age threshold, the second-stage tensioning is performed on the remaining prestressed steel strands.
[0014] Furthermore, in step S400, both the first-stage tensioning and the second-stage tensioning employ a dual-control tensioning process for closed-loop verification of construction quality. Tension load is applied to the prestressed steel strands using tension force as the main control index, and elongation is used as the verification index. During the tensioning process, the actual elongation value of the prestressed steel strand is acquired in real time, and the elongation error between the actual elongation value and the theoretical elongation value is calculated to ensure that the absolute value of the elongation error is controlled within the preset error tolerance range, so as to prevent over-tensioning from causing structural damage or under-tensioning from causing loss of interface prestress. After tensioning is completed, grouting and anchor sealing of the ducts are performed, meeting the following aging and physical-chemical boundary requirements: Within a preset time period after the completion of the second-stage tensioning, the inside of the prestressed duct is grouted under full load using high-strength grout, and the compressive strength of the cured high-strength grout is required to be greater than or equal to the preset lower limit of strength. After the grouting is fully saturated and the grout has initially set, the anchor sealing concrete is poured to completely seal the anchor plate and tensioning end, thereby cutting off the path for external corrosive media to invade the prestressed duct and ensuring the long-term durability of the steel-concrete composite section of the main tower. Beneficial effects
[0015] This invention transforms traditional point-based shear force transmission into end-face bearing force transmission by constructing a prestressed support box system and a coordinated spatial topology structure with gradient partitioning of stiffening ribs on the inner side of the main load-bearing wall panel. This eliminates stress concentration peaks and achieves a smooth transition of cross-sectional stiffness in the joint section, significantly improving the structure's resistance to splitting and fatigue buckling. Simultaneously, combined with three-dimensional high-precision skeleton network positioning, compartmentalized symmetrical micro-expansion concrete pouring, and a stepped gradient dual-control tensioning process based on concrete age and strength, it effectively compensates for early hydration thermal shrinkage deformation of concrete, limits the eccentric displacement deflection of the thin-walled steel shell during pouring, and ensures long-term tight compression of the steel-concrete interface and high-density anti-corrosion sealing of the ducts. From the dual dimensions of three-dimensional mechanical structure and construction physicochemical control, it improves the load-bearing reliability and service durability of the steel-concrete joint section of the large-span main tower. Attached Figure Description
[0016] Figure 1 This is a flowchart illustrating the overall construction method of the present invention. Figure 2 This is a schematic diagram of the stiffening rib gradient zoning layout and structure of the present invention; Figure 3 This is a spatial flow diagram of the symmetrical concrete pouring process of the present invention. Figure 4 This is a flowchart of the hierarchical gradient tensioning logic of the present invention. Detailed Implementation
[0017] To enable those skilled in the art to better understand the present invention, the technical solutions of the present invention will be clearly and completely described below with reference to the accompanying drawings of the embodiments of the present invention. Obviously, the described embodiments are only some embodiments of the present invention, and not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative effort should fall within the scope of protection of the present invention.
[0018] It should be noted that the terms "first," "second," etc., in the specification, claims, and accompanying drawings of this invention are used to distinguish similar objects and are not necessarily used to describe a specific order or sequence. It should be understood that such data can be interchanged where appropriate so that the embodiments of the invention described herein can be implemented in orders other than those illustrated or described herein. Furthermore, the terms "comprising" and "having," and any variations thereof, are intended to cover a non-exclusive inclusion; for example, a process, method, system, product, or apparatus that comprises a series of steps or units is not necessarily limited to those steps or units explicitly listed, but includes other steps or units not explicitly listed or inherent to such processes, methods, products, or apparatus.
[0019] The present invention will now be described in further detail with reference to the accompanying drawings: Example
[0020] like Figures 1 to 4 As shown, a construction method for a steel-concrete composite section of a main tower includes the following steps: S100. Steel Structure Fabrication and Installation: A prestressed support box system is welded to the inner side of the main load-bearing wall panel of the steel-concrete composite section of the main tower, and stiffening ribs are arranged in gradient zones along the elevation direction on the main load-bearing wall panel; the prestressed support box system is composed of anchor plates, anchor pipes, compressive stiffening ribs and bearing plates connected together, the anchor pipes penetrate the internal cavity of the main load-bearing wall panel and are connected to the bearing plates, and the bearing plates are set perpendicular to the main load direction; S200, Reinforcing steel and prestressed duct installation: A three-dimensional positioning reinforcing steel skeleton mesh is tied in the internal cavity of the steel-concrete composite section of the main tower, and the prestressed duct is inserted into the three-dimensional positioning reinforcing steel skeleton mesh for positioning and fixing, so that the tail end of the prestressed duct is connected to the anchor pipe. S300, Compartmentalized Concrete Casting: A compartmentalized symmetrical casting process is adopted, in which micro-expansion concrete is cast in layers into the internal cavity of the main tower steel-concrete composite section and then cured by watering. S400, Staged Gradient Tensioning and Grouting Anchoring: Prestressed steel strands are inserted into the prestressed duct, and the prestressed steel strands are tensioned symmetrically in stages based on the strength development state of the micro-expansion concrete; when the micro-expansion concrete reaches the first preset strength, the first stage tensioning of the first batch of prestressed steel strands is carried out to establish the initial interface stress; after the micro-expansion concrete reaches the second preset strength and meets the preset age, the second stage tensioning of the remaining prestressed steel strands is carried out, and the duct is grouted and anchored after tensioning is completed.
[0021] Furthermore, the specific implementation process of step S100 is as follows: Step S100 involves the forming process of the outer steel shell and internal prestressed support system of the main tower steel-concrete composite section. Q345qD bridge structural steel is selected as the main foundation material. CNC plasma cutting equipment is used to cut the main load-bearing wall panels (specifications set as 30mm thickness, 1000mm or 721mm width), top and bottom plates, longitudinal stiffening ribs (specifications set as 30mm thickness, 250mm width), anchor plates (specifications set as 20mm thickness), anchor pipes (specifications set as 97mm outer diameter, 16mm wall thickness), compressive stiffening ribs (specifications set as 16mm thickness), and bearing plates. The welded edges of the plates are all machined with bevels using a mechanical milling process, with the bevel angle constantly set at 30°, and a 2mm blunt edge dimension retained at the root of the bevel.
[0022] Gradient zoning of stiffening ribs is carried out on the surface of the main load-bearing wall panel. Taking the bottom elevation of the main tower steel-concrete composite section as the zero point, the area is divided into a strong constraint zone (elevation 0 to 1.5m), a stiffness transition zone (elevation 1.5m to 3.0m), and a weak constraint zone (elevation above 3.0m) along the elevation direction.
[0023] In the strongly constrained zone, multiple longitudinal stiffeners are positioned parallel to each other on the inner wall of the main load-bearing panel at a center-to-center spacing of 150mm. Adjacent longitudinal stiffeners are fully welded with orthogonally arranged transverse connecting plates, each 20mm thick, forming a mutually perpendicular grid-like support framework. In the stiffness transition zone, the center-to-center spacing of the longitudinal stiffeners gradually increases upwards from 150mm to 250mm following a linear increasing distribution. In the weakly constrained zone, the center-to-center spacing of the longitudinal stiffeners remains constant at 300mm. The connection between the longitudinal stiffeners and the main load-bearing panel uses partial penetration fillet welds, while full penetration welds are used in the stress-concentrated areas at the top and bottom. After the first root pass weld is completed, the back side is cleaned using carbon arc gouging to thoroughly remove weld root defects before the final root pass weld.
[0024] The main load-bearing wall panel, with the stiffening ribs positioned, is placed on the assembly jig, and the prestressed support box system is welded onto its inner side. The first end face of the anchor pipe is placed at the pre-drilled hole in the center of the anchor plate, and full-penetration circumferential welding is performed along the outer circumference of the anchor pipe. The welded anchor pipe and anchor plate assembly are then attached to the predetermined coordinate position on the inner wall of the main load-bearing wall panel. Four compression stiffening ribs are taken and attached to the four orthogonal positions (top, bottom, left, and right) of the anchor pipe cross-section. The first side of the compression stiffening rib is fully welded to the side wall of the anchor plate, the second side is fully welded to the outer wall of the anchor pipe, and the third side is fully welded to the inner wall of the main load-bearing wall panel. The pressure plate is flush with the second end face of the anchor pipe, and a closed circumferential fillet weld is performed. The overall three-dimensional spatial positioning tolerance of the prestressed support box system is controlled within 2mm.
[0025] On the exposed surface of the bearing plate facing away from the anchor pipe, the coordinates of the studs are marked according to the staggered array rule. High-strength studs with a specification of φ13×150mm are selected, and through welding is performed at each coordinate point using a drawn arc welding machine to make the high-strength studs perpendicular to the surface of the bearing plate.
[0026] After all components are welded, an ultrasonic flaw detector is used to scan the full penetration welds for internal defects. Components that pass the non-destructive testing are transferred to the painting workshop. Quartz sand is used as an abrasive to sandblast and remove rust from the component surface, achieving a roughness of Sa2.5. Subsequently, two coats of epoxy zinc-rich primer and two coats of fluorocarbon topcoat are applied sequentially using high-pressure airless spraying equipment. A coating thickness gauge is used to measure the surface of the steel component at points on a 1-square-meter grid, and the total dry film thickness must meet the technical specification of greater than or equal to 200μm. Finally, a crawler crane is used to lift the component to the main tower construction work surface for three-dimensional assembly and alignment.
[0027] Experimental scenario and data validation table: To verify the spatial positioning accuracy and pressure-bearing node connection strength of the prestressed support box system during assembly and welding, three system specimens (Specimen A, Specimen B, and Specimen C) produced according to the standard process of step S100 were extracted for physical parameter determination in a laboratory setting.
[0028] The spatial three-dimensional eccentricity between the anchor pipe's central axis and the design axis was calibrated and measured using a Leica TS60 total station; the perpendicularity of the bearing plate end face normal to the force axis was determined using an inclination sensor. Simultaneously, three high-strength studs were randomly selected from the bearing plate surface, and a destructive pull-out test was performed in the vertical direction using a universal testing machine to record the peak load at pull-out fracture. Specific measured data are shown in Table 1 below. Table 1: Assembly Accuracy and Joint Strength Test Data of Prestressed Support Box System
[0029] The data in Table 1 shows that the prestressed support box system manufactured according to the set process and spatial topology relationship has all key assembly tolerances controlled within the allowable boundaries of 2mm and ±0.2°, and the pull-out resistance of the studs exceeds the preset benchmark threshold of the project. From the data perspective, this objectively supports the reliability of the implementation of step S100 in the actual project.
[0030] Furthermore, the specific implementation process of step S200 is as follows: Step S200 involves the three-dimensional reinforcement skeleton weaving of the internal cavity of the steel-concrete composite section of the main tower, the spatial positioning of the prestressed ducts, and the treatment of the grout leakage prevention interface.
[0031] HRB400 grade threaded steel bars were selected as the basic reinforcement material. Along the longitudinal direction of the main load-bearing wall panel, longitudinal steel bars with a diameter of 25mm were arranged in four parallel layers, with the cutting length of a single longitudinal steel bar set between 1161mm and 1427mm. Closed stirrups with a diameter of 12mm were arranged around the outside of the multiple layers of longitudinal steel bars, with the center-to-center spacing between adjacent closed stirrups constantly controlled at 200mm. The perpendicular intersections of the longitudinal steel bars and the closed stirrups were fully tied with binding wire, and some main load-bearing nodes were spot-welded using argon arc welding for positioning, forming a three-dimensional positioning steel reinforcement mesh with deformation resistance within the internal cavity.
[0032] Select a plastic or metal corrugated pipe with an inner diameter of C-50 as the prestressed duct. Insert the prestressed duct into the three-dimensional positioning steel reinforcement mesh according to the design coordinates. Cut additional positioning steel bars with a diameter of 12mm and weld them to the three-dimensional positioning steel reinforcement mesh to form a grid-shaped limiting node enveloping the outer wall of the prestressed duct. In three-dimensional space, adjust the spacing between the central axes of adjacent prestressed ducts and lock them in place using the additional positioning steel bars, ensuring that the grid spacing of the prestressed duct on the cross-section is precisely locked at 400mm × 400mm. After completing the welding of all limiting nodes, stretch a reference steel wire along the longitudinal axis of the prestressed duct. Use calipers to measure the vertical distance from the outer edge of the pipe wall to the reference steel wire span by span, forcibly checking and adjusting the pipe body alignment to ensure that the absolute value of the overall straightness error of the prestressed duct along its entire length is less than or equal to 5mm.
[0033] Perform an interface sealing process at both ends of the prestressed duct. The tail end of the prestressed duct is coaxially pushed into the inner hole of the anchor pipe of the prestressed support box system, ensuring an insertion overlap depth of not less than 50 mm. Polyurethane sealant is extruded into the annular overlap gap between the outer wall of the prestressed duct and the inner wall of the anchor pipe. Subsequently, at least three layers of butyl waterproof sealant tape are tightly wrapped around the circumferential surface of the anchor pipe and the prestressed duct using a half-overlap method. External pressure is applied to expel residual air bubbles between the tapes, forming a physical sealing barrier between the anchor pipe opening and the prestressed duct.
[0034] Experimental scenario and data validation table: To verify the spatial positioning tolerance of prestressed ducts in the three-dimensional positioning steel reinforcement mesh and the anti-leakage performance of the interface sealing process, three duct installation test sections (test section D, test section E, and test section F) were fabricated at the construction site according to the S200 process standard for physical parameter collection.
[0035] Actual point cloud data of the prestressed duct was acquired using a 3D laser scanner. The central axis of the duct was extracted by fitting the data, and the average actual grid spacing between adjacent ducts and the maximum straightness deviation of a single duct were calculated. After the joint was sealed and cured for 24 hours, dyed water was injected into the prestressed duct, both ends were sealed, and the water pressure inside the pipe was increased to 0.5 MPa using a miniature pressure testing pump. The pressure holding time was set to 30 minutes. After the pressure holding period, the volume of dyed water leakage at the anchor pipe joint was collected and recorded using a measuring cylinder. The specific measured data are shown in Table 2 below. Table 2: Test Data on Spatial Positioning Accuracy and Interface Sealing Performance of Prestressed Pipes
[0036] Table 2 shows that, according to the set additional positioning rebar locking logic, the grid spacing of the prestressed duct can be stably maintained near the nominal size of 400mm, and the straightness deviation is completely suppressed within the tolerance limit of 5mm. Under the action of internal water pressure of 0.5MPa, the leakage at the anchor pipe interface wrapped with a composite of polyurethane sealant and butyl tape remains at 0mL, objectively verifying the accuracy of the assembly parameters of this process and the absolute sealing capability of the anti-leakage grout interface under extreme hydration pressure environment.
[0037] Furthermore, the specific implementation process of step S300 is as follows: Step S300 involves the concrete pouring process, anti-interference vibration, and physical and chemical curing of the internal cavity of the steel-concrete composite section of the main tower.
[0038] C50 grade micro-expansion concrete was prepared. A concrete expansion agent was added to the micro-expansion concrete mix proportion to control the slump of the freshly mixed micro-expansion concrete within a range of 160±20mm. Along the horizontal cross-sectional direction, the internal cavity of the main tower's steel-concrete composite section was divided into three casting chambers. Based on spatial geometric topology, these were divided into a core chamber located on the central axis and two side chambers distributed on either side of the core chamber as its center of symmetry.
[0039] Within a single layer height construction cycle, the pouring thickness of the micro-expansion concrete layer is controlled to be less than or equal to 3m. The concrete pump truck is started, and the micro-expansion concrete is first pumped and poured into the core compartment. After the core compartment's single-layer pouring is completed, a dual-pump truck or a three-way distribution valve is used to simultaneously pour micro-expansion concrete into the two side compartments at the same rate, ensuring the liquid level in both side compartments rises at the same level.
[0040] During the simultaneous pouring operation, the attached vibrator is inserted into the fluidized micro-expansion concrete within the internal cavity through a pre-drilled 160mm diameter hole on the outer wall of the main tower's steel-concrete composite section. The attached vibrator is set to high-frequency, low-amplitude operation. The attached vibrator is moved along a spatial coordinate path that avoids the three-dimensional positioning steel reinforcement mesh and prestressed ducts, ensuring a minimum 50mm spatial safety gap between the physical boundary of the attached vibrator and the outer wall of the prestressed ducts.
[0041] After the micro-expansion concrete has completed its initial and final setting, geotextile is applied to the exposed micro-expansion concrete interface and the interfaces of the pre-reserved circular holes. Spray pipes are installed to continuously spray fresh water onto the geotextile, maintaining it at saturation. A curing timer is initiated, controlling the water curing cycle to be greater than or equal to 14 days. Experimental scenario and data validation table: To verify the control accuracy of the symmetrical casting process on the eccentric displacement of the steel plate, and the physical volume evolution of the micro-expansion concrete during the constant humidity curing period, three steel-concrete test sections (test section G, test section H, and test section I) containing confined cavities were constructed for in-situ parameter measurement.
[0042] Total station reflecting prisms and displacement gauges were spot-welded onto the sidewall steel plates of each test section to collect the maximum horizontal eccentric load deflection limit of the steel plates throughout the entire pouring cycle of a single-layer 3m micro-expansion concrete. High-precision vibrating wire strain gauges were embedded in the geometric center of the micro-expansion concrete to read the volumetric micro-strain values after a continuous 14-day constant humidity curing period (positive values represent volume expansion, negative values represent volume shrinkage). After the curing process was completed, a phased array ultrasonic flaw detector was used to perform a matrix scan on the steel-concrete joint interface to calculate the percentage of void area. Specific measured data are shown in Table 3 below. Table 3: Displacement parameters and micro-expansion volume stability test data for symmetrical casting in sections:
[0043] Table 3 data shows that, under the spatial operation sequence constraint of simultaneous lifting of the core compartment followed by the side compartments, the maximum horizontal eccentric load deflection of the thin-walled steel plate was forcibly limited to a physical tolerance range of 1.2 mm. Relying on continuous hydration of the geotextile in a saturated state for 14 days, the micro-expansion concrete generated a constant positive micro-volume expansion (+17.5 to +21.2 με) within the closed cavity, and the scanning void rate returned to zero. Objective indicators demonstrate the engineering feasibility of symmetrical segmented casting combined with specific physical and chemical curing conditions in maintaining structural geometric stability and achieving dense compression bonding of the steel-concrete interface.
[0044] Furthermore, the specific implementation process of step S400 is as follows: Step S400 involves the application of prestress, verification of elongation tolerance, and anti-corrosion sealing of internal ducts in the steel-concrete composite section of the main tower after reaching a specific age.
[0045] The working length parameter (8.887m), the anchor ring compensation parameter at the tensioning end, and the physical length parameter of the jack were obtained. These three values were added together to calculate the absolute value of the prestressed steel strand cutting length: 9.687m. Steel strands of specification 5ε15.2 were cut and bundled to form 12 prestressed steel strands. These 12 prestressed steel strands were then inserted into the prestressing ducts. JM15-12 anchorages were installed at both ends of the prestressed steel strands, ensuring the strands passed through the holes in the anchorages and were locked inside the jack's clamp assembly.
[0046] The first preset strength is set at 75% of the design strength standard value of the micro-expansion concrete. The real-time compressive strength of the micro-expansion concrete is determined using test blocks cured under the same conditions. When the real-time compressive strength of the micro-expansion concrete reaches 75% of the design value, the first tensioning process is initiated. 50% of the total number of prestressed steel strands are symmetrically selected along the left and right sides of the main tower cross-section for first-stage tensioning. The hydraulic pump stations at both ends synchronously and uniformly supply oil to the jacks, and the tension force is smoothly applied to the first-stage stress level according to the set initial oil pressure calibration value, with the tension applied symmetrically and uniformly to the left and right steel strands.
[0047] The second preset strength was set at 95% of the design strength standard value of the micro-expansion concrete. After the real-time compressive strength of the micro-expansion concrete reached 95% of the design value and the cumulative curing time with water spraying reached the 14-day age threshold, the second batch of tensioning was initiated. Second-stage tensioning was performed on the remaining 50% of the prestressed steel strands. The hydraulic pump station was continuously operated to supply oil and increase pressure, so that the final tension control stress σcon reached 0.72fptk, that is, the absolute value of the tension control stress was equal to 1339.2 MPa.
[0048] During the first and second stage of tensioning, a dual-control tensioning process of "tension force + elongation value" is executed simultaneously. The tension force reading fed back by the hydraulic pressure gauge is used as the main control index, while the elongation displacement of the steel strand is used as the verification index. The displacement parameters of the piston rod are read during the extension stroke of the hydraulic cylinder to obtain the actual elongation value of the prestressed steel strand. The mathematical difference between the actual elongation value and the theoretical elongation value is calculated, and the mathematical difference is divided by the theoretical elongation value to obtain the elongation error value. Throughout the entire oil supply and pressure regulation stage, the absolute value of the elongation error is forcibly controlled to be less than or equal to 6%. If the calculated elongation error exceeds the 6% tolerance boundary, the hydraulic pump station's pressure relief and shutdown logic is immediately triggered for troubleshooting.
[0049] Grouting is performed within 48 hours after the completion of symmetrical tensioning in two batches. A vacuum pump is used to create a negative pressure environment at the first end of the prestressed duct, and an ultrafine cement-based high-strength grout is injected at the second end using a grouting pump. The injection continues until the consistency of the grout discharged from the first end's vent valve is completely consistent with the consistency of the grout inlet hole. Then, the vent valve is closed, and a stable pressure load of 0.5 MPa to 0.7 MPa is applied and maintained for 3 minutes. Under normal temperature curing conditions, the compressive strength of the high-strength grout is controlled to be greater than or equal to 50 MPa. After the grout has initially set, a partially enclosed formwork is erected in the external space of the anchor plate and tensioning end, and C50 grade sealing concrete is poured to completely cover the exposed anchor components and prestressed steel strand ends. Experimental scenario and data validation table: To verify the following accuracy of the dual control indicators in the stepped gradient tensioning process, as well as the filling degree and curing mechanical properties of the high-strength grout inside the closed long-distance pipe, three proportionally scaled physical test sections (test section J, test section K, and test section L) containing corrugated pipes, anchors, and prestressed steel strands were made according to the process specifications of step S400 for physical verification.
[0050] High-precision displacement sensors were installed at the tensioning end to read real-time elongation values. The maximum elongation error was calculated and recorded when the tensioning control stress reached 1339.2 MPa. After grouting was completed and allowed to cure for 28 days, cylindrical core samples of the cured grout were taken from inside the pipe and subjected to static uniaxial compression testing on a universal testing machine to obtain the actual compressive strength after 28 days. Industrial CT equipment was used to perform non-destructive tomographic scanning of the test section to calculate the grout filling rate of the cross-section. Specific measured data are shown in Table 4 below. Table 4: Test data on the error of tensile elongation under dual control and the physical and chemical properties of grouting ducts.
[0051] Table 4 shows that after introducing the trigger percentage and dual-control tensioning logic, the absolute value of the maximum elongation error in the three test sections was controlled below 3.5%, far below the 6% tolerance upper limit required by the specification. The measured compressive strength of the high-strength grout ranged from 55.9 MPa to 58.1 MPa, consistently exceeding the design lower limit requirement of 50 MPa. Industrial CT scans showed that the grouting filling rate of the ducts was close to 100%, with no cross-sectional pore aggregation defects. The measured data objectively confirmed the absolute reliability of the S400 process boundary in terms of tensioning accuracy and sealing density from both mechanical and materials science perspectives.
[0052] The above embodiments are only used to illustrate the technical solutions of the present invention, and are not intended to limit it. Although the present invention has been described in detail with reference to the foregoing embodiments, those skilled in the art should understand that modifications can still be made to the technical solutions described in the foregoing embodiments, or equivalent substitutions can be made to some of the technical features. Such modifications or substitutions will not cause the essence of the corresponding technical solutions to deviate from the spirit and scope of the technical solutions of the embodiments of the present invention.
Claims
1. A construction method for a steel-concrete composite section of a main tower, characterized in that, Includes the following steps: S100. Steel Structure Fabrication and Installation: A prestressed support box system is welded to the inner side of the main load-bearing wall panel of the steel-concrete composite section of the main tower, and stiffening ribs are arranged in gradient zones along the elevation direction on the main load-bearing wall panel; the prestressed support box system is composed of anchor plates, anchor pipes, compressive stiffening ribs and bearing plates connected together, the anchor pipes penetrate the internal cavity of the main load-bearing wall panel and are connected to the bearing plates, and the bearing plates are set perpendicular to the main load direction; S200, Reinforcing steel and prestressed duct installation: A three-dimensional positioning reinforcing steel skeleton mesh is tied in the internal cavity of the steel-concrete composite section of the main tower, and the prestressed duct is inserted into the three-dimensional positioning reinforcing steel skeleton mesh for positioning and fixing, so that the tail end of the prestressed duct is connected to the anchor pipe. S300, Compartmentalized Concrete Casting: A compartmentalized symmetrical casting process is adopted, in which micro-expansion concrete is cast in layers into the internal cavity of the main tower steel-concrete composite section and then cured by watering. S400, Staged Gradient Tensioning and Grouting Anchoring: Prestressed steel strands are inserted into the prestressed duct, and the prestressed steel strands are tensioned symmetrically in stages based on the strength development state of the micro-expansion concrete; when the micro-expansion concrete reaches the first preset strength, the first stage tensioning of the first batch of prestressed steel strands is carried out to establish the initial interface stress; after the micro-expansion concrete reaches the second preset strength and meets the preset age, the second stage tensioning of the remaining prestressed steel strands is carried out, and the duct is grouted and anchored after tensioning is completed.
2. The construction method for the steel-concrete composite section of the main tower according to claim 1, characterized in that, The gradient zoning arrangement of stiffening ribs along the elevation direction on the main load-bearing wall panel specifically includes: The main tower steel-concrete composite section is divided into a strong constraint zone, a stiffness transition zone, and a weak constraint zone along the elevation direction from bottom to top. Within the strongly constrained zone, the stiffening ribs are densely arranged at a first preset interval, and a transverse connecting partition perpendicular to the main load-bearing wall panel is added. Within the stiffness transition zone, the spacing of the stiffening ribs gradually and smoothly transitions from the first preset spacing to the second preset spacing, and the second preset spacing is greater than the first preset spacing. Within the weakly constrained area, the stiffening ribs are arranged at a third preset spacing, which is greater than the second preset spacing.
3. The construction method for the steel-concrete composite section of the main tower according to claim 2, characterized in that, The prestressed support box system is assembled and welded using the following connection relationships: The anchor plate is fixed to one end of the anchor pipe by full penetration welding; The compressive stiffening ribs are fully welded to the side wall of the anchor plate, the outer wall of the anchor pipe, and the inner wall of the main load-bearing wall plate, respectively. The pressure plate is installed at the other end of the anchor pipe away from the anchor plate, and the surface of the pressure plate is perpendicular to the transmission direction of the prestressing tension reaction force.
4. The construction method for the steel-concrete composite section of the main tower according to claim 3, characterized in that, Step S100 further includes: Several high-strength studs are welded to the surface of the bearing plate on the side opposite to the anchor pipe, so that during the tensioning process in step S400, the prestress reaction force of the bearing plate is dispersed and transferred to the micro-expansion concrete through the high-strength studs, forming end face bearing anchorage. In step S100, after the steel structure fabrication and installation are completed and welded, an anti-corrosion treatment process is also included: After the prestressed support box system and the stiffening ribs are welded together and pass the ultrasonic non-destructive testing of the welds, epoxy zinc-rich primer and fluorocarbon topcoat are sprayed sequentially on the surface of the steel structure, and the total dry film thickness is controlled to be greater than or equal to the preset thickness threshold.
5. The construction method for the steel-concrete composite section of the main tower according to claim 4, characterized in that, The spatial binding process of the three-dimensional positioning steel reinforcement mesh includes: Several longitudinal steel bars are arranged in multiple layers along the longitudinal direction of the main load-bearing wall panel, and several closed stirrups with transverse spacing are tied to the outside of the multiple layers of longitudinal steel bars. The intersections of the longitudinal reinforcing bars and the closed stirrups are fixed by binding or spot welding to form a three-dimensional mesh skeleton that is enclosed in the internal cavity and used to accommodate the prestressed duct.
6. The construction method for the steel-concrete composite section of the main tower according to claim 5, characterized in that, In step S200, the prestressed duct is inserted into the three-dimensional positioning steel reinforcement mesh for positioning and fixing, subject to the following high-precision requirements: The prestressed pipe is made of plastic corrugated pipe or metal corrugated pipe; The prestressed duct is inserted into the grid of the three-dimensional positioning steel reinforcement mesh, and the prestressed duct is locked and positioned to the three-dimensional positioning steel reinforcement mesh using additional positioning steel bars. After positioning and fixing, the grid control spacing between adjacent prestressed pipes meets the preset spacing threshold, and the overall straightness error of the prestressed pipes is less than or equal to the preset error threshold. When the tail end of the prestressed duct is connected to the anchor pipe, a grout leakage prevention and sealing process is also included: The end of the prestressed duct is coaxially inserted into the inner hole of the anchor pipe, and sealing tape or sealant is wrapped around the overlapping joint of the prestressed duct and the anchor pipe to prevent cement slurry leakage during the pouring process in step S300, which could lead to blockage of the prestressed duct.
7. The construction method for the steel-concrete composite section of the main tower according to claim 6, characterized in that, In step S300, the symmetrical casting process with compartmentalized sections is adopted, in which micro-expansion concrete is cast in layers into the internal cavity of the steel-concrete composite section of the main tower. The spatial compartmentalization and casting sequence are defined as follows: Along the horizontal cross-sectional direction, the internal cavity is divided into a core compartment located in the middle and two side compartments symmetrically distributed on both sides of the core compartment; Within a single layer height construction cycle, the micro-expansion concrete is first poured into the core compartment, and then the micro-expansion concrete is simultaneously poured evenly and symmetrically into the two side compartments to avoid structural deformation caused by unilateral eccentric loading.
8. The construction method for the steel-concrete composite section of the main tower according to claim 7, characterized in that, In step S300, the layered pouring process has the following dynamic operation and anti-interference restrictions: The thickness of the micro-expansion concrete in a single layered pour is controlled to be less than or equal to a preset layer thickness threshold. During the pouring operation, the vibrating equipment is inserted into the internal cavity through the vibration hole reserved on the outer wall of the main tower steel-concrete composite section, and the micro-expansion concrete is vibrated in a high-frequency low-amplitude mode to prevent aggregate segregation and avoid disturbing the spatial positioning accuracy of the prestressed duct in the internal cavity. The physicochemical properties and curing control of the micro-expansion concrete specifically include: The micro-expansion concrete mix proportion includes a concrete expansion agent, which is used to generate micro-expansion in volume during the hydration and crystallization process to offset the shrinkage deformation caused by early hydration heat. After the micro-expansion concrete reaches its final set state, geotextile is covered on its exposed interface and water is continuously sprayed for moisturizing and curing. The curing period is greater than or equal to the preset minimum number of days, thereby ensuring tight bonding between the steel structure and the concrete interface and eliminating micro-delamination at the interface.
9. The construction method for a steel-concrete composite section of a main tower according to claim 8, characterized in that, In step S400, the prestressed steel strands are tensioned in stages symmetrically based on the strength development state of the micro-expansion concrete. The specific order and triggering control include: The first preset strength is set as a preset first percentage of the design strength standard value of the micro-expansion concrete; when the first preset strength is reached, a first proportion of the prestressed steel strands in the preset total number of strands are selected symmetrically along the cross section to perform the first-order tensioning; The second preset strength is set as a preset second percentage of the design strength standard value of the micro-expansion concrete, and the preset second percentage is greater than the preset first percentage; after the second preset strength is met and the on-site curing time of the micro-expansion concrete reaches the preset age threshold, the second-stage tensioning is performed on the remaining prestressed steel strands.
10. A construction method for a steel-concrete composite section of a main tower according to claim 9, characterized in that, In step S400, both the first-stage tensioning and the second-stage tensioning employ a dual-control tensioning process for closed-loop verification of construction quality. Tension load is applied to the prestressed steel strands using tension force as the main control index, and elongation is used as the verification index. During the tensioning process, the actual elongation value of the prestressed steel strand is acquired in real time, and the elongation error between the actual elongation value and the theoretical elongation value is calculated to ensure that the absolute value of the elongation error is controlled within the preset error tolerance range, so as to prevent over-tensioning from causing structural damage or under-tensioning from causing loss of interface prestress. After tensioning is completed, grouting and anchor sealing of the ducts are performed, meeting the following aging and physical-chemical boundary requirements: Within a preset time period after the completion of the second-stage tensioning, the inside of the prestressed duct is grouted under full load using high-strength grout, and the compressive strength of the cured high-strength grout is required to be greater than or equal to the preset lower limit of strength. After the grouting is fully saturated and the grout has initially set, the anchor sealing concrete is poured to completely seal the anchor plate and tensioning end, thereby cutting off the path for external corrosive media to invade the prestressed duct and ensuring the long-term durability of the steel-concrete composite section of the main tower.