Construction control methods for pile driving process

By installing sensors and inclinometers on the pile hammer and combining them with a computer control system to optimize the pile driving process, the problem of coordinating inclination detection and penetration stop judgment was solved, realizing automated and refined control of the pile driving process and improving the accuracy and efficiency of construction.

CN123109153APending Publication Date: 2026-11-17CHINA HARBOUR ENGINEERING
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202611486548.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-09-22
Publication Date
2026-11-17

AI Technical Summary

Technical Problem

In the existing technology, the tilt detection, verticality correction and penetration stopping judgment lack coordinated control during the hammer driving process, which leads to misjudgment of penetration data and construction interruption under tilt conditions, affecting the level of construction automation and precision.

Method used

A hammer blow count sensor, an inclinometer, and a laser rangefinder are installed on the pile hammer and connected to a computer control system. The inclinometer monitors the tilt in real time and issues correction commands to keep the pile hammer continuously hammering. After the tilt is restored, the penetration data is recounted. The decision to stop hammering is optimized by combining energy conversion efficiency and sensor data.

Benefits of technology

It improves the accuracy of hammer stopping judgment, avoids soil stress redistribution and construction efficiency loss caused by interruption of hammering due to deviation correction, ensures the continuity and comparability of penetration data, and realizes the coordinated control of tilt detection, verticality correction and penetration hammer stopping.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123109153A_ABST
    Figure CN123109153A_ABST
Patent Text Reader

Abstract

This invention discloses a construction control method for the pile driving process, belonging to the field of pile foundation engineering construction technology. Addressing the problem in existing technologies where the penetration measurement stop-hammer judgment still operates independently when the pile inclination exceeds the limit, leading to misjudgments, this method monitors the pile inclination during pile driving. When the inclination exceeds the limit and a correction command is issued, the penetration measurement stop-hammer judgment is paused while continuous hammering continues. Once the inclination recovers, the stop-hammer judgment is resumed and the penetration data is recounted. This achieves coordinated control of inclination detection, verticality correction, and penetration measurement stop-hammer judgment, improving the accuracy of the stop-hammer judgment and the continuity of construction. It can be used for the automatic control of the pile driving process.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of pile foundation construction technology, and specifically to a construction control method for the pile driving process. Background Technology

[0002] Hammer driving is a commonly used method in the construction of precast pile foundations. Its basic principle is to use the impact force of a pile hammer to drive the precast pile section by section into the soil until the pile tip reaches the design elevation or meets the specified stopping criteria. During hammer driving, the verticality of the pile is one of the key indicators affecting the bearing capacity and structural safety of the pile foundation. When the verticality deviation exceeds the allowable range, the pile will generate an additional bending moment, reducing the vertical bearing capacity of the pile foundation, and in severe cases, even leading to cracking or breakage. Therefore, the verticality of the pile must be continuously monitored during the driving process, and any deviation exceeding the limit should be corrected promptly. At the same time, controlling the stopping of hammer driving is also a core aspect of construction. Stopping the hammer too early may result in the pile tip failing to penetrate the design bearing layer, while stopping too late may cause damage to the pile or waste of materials. Currently, penetration depth is commonly used as the main criterion for stopping hammer driving in engineering projects; that is, when the average penetration depth per blow of several consecutive hammer blows is less than or equal to a preset value, the stopping condition is considered met.

[0003] Patent CN104563171B discloses a device and method for detecting the penetration depth of steel pipe piles driven by hammer. The technical solution of this patent is as follows: a hammer blow count sensor and three laser rangefinders are installed on the pile hammer. Each laser rangefinder consists of a laser rangefinder and a G-sensor on top of the rangefinder. The G-sensor and the laser rangefinder are arranged symmetrically about the horizontal plane. By performing a double integration on the change in the vertical direction, the relative displacement of the laser rangefinder in the vertical direction is corrected. The three laser rangefinders transmit the detected data to a computer. The computer control system calculates the angles between the three sides of the triangle and its projection, thereby detecting the inclination of the steel pipe pile during the hammer driving process. When the inclination is too large, the computer control system automatically issues an alarm. Simultaneously, the laser rangefinders send distance data to the computer control system, and the hammer blow count sensor sends the number of hammer blows to the computer control system. The computer control system calculates the average penetration depth together with the received distance data and the number of hammer blows, compares it with a preset value, and issues a stop hammer instruction when the requirements are met. The laser rangefinder in this patent uses a wireless connection with the computer.

[0004] While the existing technology described above achieves the detection and alarm functions for pile inclination, it still has significant shortcomings. The patent's handling of inclination exceeding limits relies solely on automatically issuing an alarm, with operators deciding whether to stop hammering and how to perform corrective measures based on the alarm information. Under this approach, there is a lack of coordinated control among inclination detection, penetration stopping judgment, and verticality correction. After the inclination exceeding limit alarm is issued, the penetration stopping judgment continues to operate independently. If the penetration value happens to meet the stopping conditions at this time, the computer control system will directly issue a stopping instruction. However, the penetration data measured when the engineering pile is tilted is already affected by the pile inclination and cannot accurately reflect the actual degree to which the pile tip has entered the bearing layer. Making a stopping decision based on this interfered penetration data may lead to misjudgment. Furthermore, after receiving an alarm, operators usually need to stop hammering to perform corrective operations, but this stopping-and-correction method interrupts the continuity of pile driving, causing stress redistribution in the surrounding soil, and potentially distorting the initial penetration data when hammering resumes.

[0005] Therefore, it is evident that the existing technology lacks an effective coordinated control mechanism among tilt detection, verticality correction, and penetration depth stopping judgment. When the tilt exceeds the limit, the penetration depth stopping judgment still operates independently, which may lead to stopping the hammer decision based on disturbed penetration depth data. This deficiency limits the automation and precision of the hammer driving pile construction process control. Summary of the Invention

[0006] This invention provides a construction control method for the pile driving process. When a correction command is issued, the judgment logic that uses penetration as the basis for stopping the hammer is paused, and the pile hammer is continuously hammered. After the verticality is restored, the hammer stopping judgment logic is restored and the penetration data is recounted. This avoids the penetration data in the inclined state being incorrectly used for hammer stopping judgment.

[0007] To achieve these objectives and other advantages according to the present invention, a construction control method for the pile driving process is provided, comprising the following steps:

[0008] Step 1: Install a hammer blow count sensor on the pile hammer, and install an inclinometer and a laser rangefinder on the pile driving equipment. Connect the hammer blow count sensor, inclinometer, and laser rangefinder to the computer control system respectively.

[0009] Step 2: Hoist the engineering pile into the pile stabilization and positioning platform, and adjust the verticality of the engineering pile by using the jacks on the pile stabilization and positioning platform so that the inclination of the engineering pile is less than or equal to the first preset value.

[0010] Step 3: Start the pile hammer to drive the engineering pile. During the pile driving process, the real-time pile inclination data of the engineering pile is continuously collected by the inclinometer and sent to the computer control system. The computer control system compares the real-time pile inclination data with the second preset value. When the real-time pile inclination data is greater than the second preset value, the computer control system issues a correction command and adjusts the verticality of the engineering pile by jacking until the real-time pile inclination data is less than or equal to the second preset value.

[0011] Step 4: While the pile driving is in progress, real-time penetration data is collected by a laser rangefinder and the real-time number of hammer blows is collected by a hammer blow count sensor. The computer control system calculates the average penetration per blow and compares it with the third preset value. When the average penetration per blow of a consecutive preset number of hammer blows is less than or equal to the third preset value, a stop hammer command is issued. Here, a preset number of consecutive hammer blows is a set.

[0012] Step 5: When the correction command is issued in Step 3, the computer control system pauses the comparison and hammer stop command in Step 4, while maintaining continuous hammering. After the real-time pile inclination data recovers to less than or equal to the second preset value, the system restarts counting the average penetration per blow for a preset number of consecutive hammerings.

[0013] Preferably, in the construction control method for the pile driving process, in step four, stress sensors and acceleration sensors are installed on the pile body. The stress sensors are used to collect the time history of the impact force exerted by the pile hammer on the pile during each hammer blow, and the acceleration sensors are used to collect the time history of the acceleration of the pile during each hammer blow. The computer control system obtains the impact impulse of each hammer blow by integrating the impact force time history over time, and obtains the displacement time history of the pile during each hammer blow by integrating the acceleration time history twice over time. The computer control system calculates the input energy of each hammer blow based on the impact force time history and the displacement time history, and calculates the input energy based on the pile mass and displacement. The time-history calculation measures the increase in pile potential energy for each hammer blow; the computer control system divides the increase in pile potential energy for each hammer blow by the input energy to obtain the energy conversion efficiency for each hammer blow; the computer control system judges the trend of the change in energy conversion efficiency for each hammer blow, and when the energy conversion efficiency for P consecutive hammer blows is less than or equal to the energy conversion efficiency of the previous hammer blow, the computer control system uses the current average penetration per blow as a dynamic reference value, and multiplies the dynamic reference value by a preset proportional coefficient to obtain an adjusted third preset value, which replaces the original third preset value for subsequent hammer stop judgment; P is a positive integer greater than or equal to 5.

[0014] Preferably, in the construction control method for the pile driving process, in step three, pressure sensors are installed at each jack of the pile stabilization and positioning platform, a first positioning device is installed at the center of the pile stabilization and positioning platform, and a second positioning device is installed at the centerline of the pile body. The pressure sensors are used to collect the real-time output pressure of the corresponding jacks, and the first and second positioning devices are used to provide the computer control system with the relative spatial position between the center point of the pile stabilization and positioning platform and the centerline of the pile body. When the computer control system issues a correction command, the computer control system calculates the projection position of the resultant force point of each jack's output thrust on the horizontal plane based on the real-time output pressure of each jack and the spatial distribution position of each jack, thus obtaining the real-time thrust center coordinates of the jack array. The computer control system then calculates the relative spatial position of the resultant force point of each jack's output thrust on the horizontal plane based on the real-time output pressure of each jack and the spatial distribution position of each jack. The second positioning device provides the relative spatial position, calculates the projection position of the pile centerline on the horizontal plane, and obtains the real-time pile center coordinates. The computer control system calculates the horizontal distance between the real-time thrust center coordinates and the real-time pile center coordinates, and obtains the thrust-pile center offset. The computer control system compares the thrust-pile center offset with the fourth preset value. When the thrust-pile center offset is greater than the fourth preset value, the computer control system adjusts the output pressure distribution of each jack, so that the real-time thrust center coordinates move towards the real-time pile center coordinates, until the thrust-pile center offset is less than or equal to the fourth preset value. The computer control system uses the pile inclination less than or equal to the second preset value and the thrust-pile center offset less than or equal to the fourth preset value as the judgment condition for the correction to be completed.

[0015] Preferably, in the construction control method for the pile driving process, in step four, the computer control system continuously calculates the rate of change of the average penetration depth per blow between each two adjacent hammer blows during the pile driving process. The calculation method for the rate of change of the average penetration depth per blow is as follows: the difference between the average penetration depth per blow of the current hammer blow and the average penetration depth per blow of the previous hammer blow is divided by the larger value between the average penetration depth per blow of the current hammer blow and the average penetration depth per blow of the previous hammer blow; when both the average penetration depth per blow of the current hammer blow and the average penetration depth per blow of the previous hammer blow are zero, the rate of change of the average penetration depth per blow is set to zero. The machine control system compares the calculated average penetration rate per blow with the fifth preset value. When the average penetration rate per blow for N consecutive blows is less than or equal to the fifth preset value, and when the third preset value adjustment condition based on energy conversion efficiency is not triggered, the computer control system uses the current average penetration per blow as a dynamic reference value, and multiplies the dynamic reference value by a preset proportional coefficient to obtain the adjusted third preset value. The adjusted third preset value replaces the original third preset value for subsequent hammer stop judgment. N is a positive integer greater than or equal to 3, and the proportional coefficient ranges from 0.3 to 0.7.

[0016] Preferably, in the construction control method for the pile driving process, in step four, after each hammer blow, the peak time of the impact force time history curve and the rise time from zero to the peak value are determined based on the impact force time history collected by the stress sensor. The round-trip time difference required for the stress wave to travel back and forth once within the entire length of the pile is calculated based on the known pile length and pile wave velocity. The ratio of the rise time to the round-trip time difference is calculated to obtain the relative duration coefficient of the impact force. The relative duration coefficient of the impact force is compared with a sixth preset value. When the relative duration coefficient of the impact force is greater than the sixth preset value, the hammer blow is marked as an eccentric hammer blow, and the impact force time history and acceleration time history of the hammer blow are excluded from the calculation of input energy and pile potential energy increment. The hammer blow marked as an eccentric hammer blow is not counted in the count of consecutive P hammer blows, and the P count is carried over to subsequent hammer blows that are not marked as eccentric hammer blows.

[0017] Preferably, in the construction control method for the pile driving process, in step three, when the computer control system issues a correction command and drives each jack to extend simultaneously, each pressure sensor continuously collects real-time output pressure during the jack extension process and sends it to the computer control system; taking any two adjacent pressure sensors as a group, the difference in real-time output pressure between the two pressure sensors in the same group is calculated to obtain the pressure difference time history of the group; the peak value of the pressure difference time history of each group is calculated respectively, and the peak values ​​of each group are compared with each other. When the difference between the peak value of any group and the average value of the peak values ​​of other groups is greater than a seventh preset value, it is determined that at least one pressure sensor in the group has failed, and a sensor failure alarm is issued.

[0018] Preferably, in the construction control method for the pile driving process, in step four, the computer control system continuously records the average penetration per blow and the corresponding hammer energy for each blow during the pile driving process; the computer control system calculates the ratio of the hammer energy for each blow to the corresponding average penetration per blow to obtain the energy consumption per unit penetration; wherein, when the average penetration per blow of a certain blow is zero, the energy consumption per unit penetration for that blow is not calculated, the blow is marked as an abnormal blow, and the average penetration per blow of that blow is excluded from the average penetration per blow calculation. In addition to calculating the penetration change rate, the computer control system continuously records the energy consumption per unit penetration, forming a time series of energy consumption per unit penetration. The computer control system calculates the moving average of the energy consumption per unit penetration time series, compares the energy consumption per unit penetration of the current hammer blow with the moving average, and when the difference between the energy consumption per unit penetration of the current hammer blow and the moving average is greater than an eighth preset value, the computer control system marks the current hammer blow as an abnormal hammer blow and excludes the average penetration per blow of the current hammer blow from the calculation of the average penetration change rate per blow.

[0019] Preferably, in the construction control method for the pile driving process, in step four, after each hammer blow, the computer control system determines the peak time of the impact force time history curve based on the impact force time history collected by the stress sensor, and uses this peak time as the starting point to sequentially search for each local extreme point on the impact force time history curve, recording the time of occurrence of each local extreme point to obtain an extreme point time sequence; the computer control system calculates the time difference between two adjacent extreme point times in the extreme point time sequence to obtain an extreme point interval sequence; the computer control system statistically analyzes the frequency of occurrence of each value in the extreme point interval sequence. The system uses the most frequent value as the round-trip time difference required for the stress wave to travel one round trip within the current length of the engineering pile, replacing the round-trip time difference calculated from the known pile length and pile wave velocity. When multiple values ​​have the highest frequency, the smaller value is used. When the frequency of each value in the extreme point interval sequence is lower than the ninth preset value, the computer control system determines that the signal quality of the current hammer blow does not meet the self-calibration requirements, and still uses the round-trip time difference calculated from the known pile length and pile wave velocity as the round-trip time difference. The ninth preset value is a positive integer between 3 and 5.

[0020] Preferably, in the construction control method for the pile driving process, in step three, before issuing the correction command, the computer control system first collects the real-time output pressure of each pressure sensor under the current tilt state of the engineering pile, and calculates the difference between the real-time output pressure of two pressure sensors in the same group, taking any two adjacent pressure sensors as a group, to obtain the pressure difference before correction for each group; after issuing the correction command and driving each jack to extend, the computer control system collects the real-time output pressure of each pressure sensor again, and calculates the difference between the real-time output pressure of two pressure sensors in the same group, to obtain the pressure difference time history after correction for each group; the computer control system calculates the ratio of the peak value of the pressure difference time history after correction to the pressure difference before correction for each group, to obtain the pressure difference change rate for each group; the computer control system compares the pressure difference change rates of each group with each other, and when the difference between the pressure difference change rate of any group and the average value of the pressure difference change rate of other groups is greater than a tenth preset value, the computer control system determines that at least one pressure sensor in that group has failed and issues a sensor failure alarm.

[0021] Preferably, in the construction control method for the pile driving process, in step four, the computer control system continuously records the hammer energy and the corresponding average penetration per blow during the hammer driving process, and plots the data points of each hammer blow on the phase plane with hammer energy as the abscissa and average penetration per blow as the ordinate; the computer control system selects the data points of V hammer blows prior to the current hammer blow as the center to form a reference point set, wherein when the number of hammer blows is less than V, the current hammer blow is marked as a normal hammer blow; the centroid coordinates and covariance matrix of the reference point set in the phase plane are calculated, and the distribution elliptical region of the reference point set is determined according to the covariance matrix; the major and minor axis directions of the distribution elliptical region are determined by the eigenvectors of the covariance matrix, and the lengths of the major and minor axes of the distribution elliptical region are determined by multiplying the eigenvalues ​​of the covariance matrix by a preset multiple, the preset multiple being 2 to 10 ... Values ​​between 3 and 5; The computer control system determines whether the data point of the current hammer blow is located inside the distribution ellipse area. If it is, the hammer blow is marked as a normal hammer blow. If it is located outside the distribution ellipse area, the system further determines whether the data point of the previous hammer blow is also located outside the distribution ellipse area. If the data point of the previous hammer blow is located inside the distribution ellipse area, the computer control system marks the current hammer blow as an abnormal hammer blow and excludes the average penetration per blow of the current hammer blow from the calculation of the average penetration per blow change rate. If the data point of the previous hammer blow is also located outside the distribution ellipse area, the computer control system determines that the engineering pile is currently in the soil layer transition stage. The soil layer transition stage refers to the transition process of the engineering pile tip from the current soil layer to the adjacent soil layer. The average penetration per blow of the current hammer blow is included in the calculation of the average penetration per blow change rate. V is a positive integer greater than or equal to 5.

[0022] The present invention has at least the following beneficial effects:

[0023] I. This invention suspends the judgment logic that uses penetration as the basis for stopping hammering when a correction command is issued, thus avoiding the incorrect use of penetration data measured when the engineering pile is in an inclined state for stopping hammering. This makes the decision to stop hammering based on the penetration data measured when the engineering pile is in a vertical state, thereby improving the accuracy of the decision to stop hammering.

[0024] Second, this invention maintains continuous hammering during the correction period, avoiding the problems of stress redistribution in the soil around the pile and distortion of penetration data when hammering is restarted due to stopping hammering for correction. This ensures that the penetration data used to determine when to stop hammering can be obtained during the continuous pile driving process, guaranteeing the continuity and comparability of the data.

[0025] Third, this invention restarts counting penetration data after the verticality of the engineering pile is restored, ensuring that all penetration data of the continuous preset number of hammer blows used for stopping the hammer are collected within the time period when the engineering pile is in a vertical state, thus eliminating the interference of the correction process on the penetration data statistical interval.

[0026] Fourth, this invention automatically executes tilt comparison, correction command issuance, hammer stop judgment pause and resumption, and penetration data recount through a computer control system, reducing manual intervention in the construction process and enabling the three links of tilt detection, verticality correction and penetration hammer stop judgment to form a coordinated relationship in time sequence.

[0027] Fifth, this invention maintains continuous hammering during the correction period, avoiding the loss of construction efficiency caused by frequent hammer stops and restarts, while also reducing the impact of possible creep settlement of the pile body during hammer stops on the subsequent pile driving quality.

[0028] Other advantages, objectives and features of the present invention will become apparent in part from the following description, and in part from those skilled in the art through study and practice of the invention. Attached Figure Description

[0029] Figure 1 This is a flowchart of the construction control method for the pile driving process of the present invention. Detailed Implementation

[0030] The present invention will now be described in further detail so that those skilled in the art can implement it based on the description.

[0031] It should be understood that terms such as “having,” “comprising,” and “including” as used herein do not exclude the presence or addition of one or more other elements or combinations thereof.

[0032] According to one embodiment of the present invention, a construction control method for pile driving is provided. Before the pile driving operation, a hammer blow count sensor is installed on the pile hammer, and an inclinometer and a laser rangefinder are installed on the pile driving equipment. The hammer blow count sensor can be installed on the side of the pile hammer to record the number of hammer blows for each strike. The inclinometer can be installed on the support of the pile driving equipment or the pile hammer guide frame to continuously monitor the tilt angle of the engineering pile during construction. The inclinometer can be a dual-axis inclinometer with a range of ±90° and an accuracy of 0.1°. The laser rangefinder can be installed on the support at the upper end of the pile hammer, and a reflective film can be set at a corresponding position below the laser rangefinder. The reflective film is installed on the top of the pile hammer or the upper surface of the pile cap. The range of the laser rangefinder can be selected from 10 m to 50 m, and its resolution can reach 0.1 mm. The hammer blow count sensor, inclinometer, and laser rangefinder are connected to a computer control system via wired or wireless communication. The computer control system can be an industrial control computer or an embedded controller, with data acquisition, signal processing, and logic judgment functions.

[0033] After completing the installation and connection of the aforementioned sensors, the engineering pile is hoisted into the pile stabilization and positioning platform. The pile stabilization and positioning platform is a pile positioning device installed at the pile driving construction site. It has a double-layered annular steel frame structure, with the two layers fixedly connected by vertical support columns. Several hydraulic jacks are arranged at equal angles along the circumference of the engineering pile on the inner edge of each layer of the steel frame. The piston rod of each jack extends towards the outer wall of the engineering pile, used to apply radial thrust to adjust the verticality of the pile. Four hydraulic jacks can be arranged along the circumference of the engineering pile on the upper and lower layers of the pile stabilization and positioning platform, respectively. The maximum thrust of each jack can be selected as 100 t. The verticality of the engineering pile is adjusted using the jacks on the pile stabilization and positioning platform. During adjustment, a long strip level can be used for rough calibration first, followed by testing with two theodolites or two plumb bobs in two directions at 90° to each other. Under the control of the computer control system, the jacks extend and retract sequentially, pushing the engineering pile so that its inclination is less than or equal to a first preset value. The first preset value can be determined according to project requirements and geological conditions. Generally, the verticality deviation of the pile body can be taken as no more than 0.5%. For steel pipe pile driving, the verticality deviation can be controlled within 1% of the pile length.

[0034] After adjustment, the pile hammer is activated to drive the engineering pile. During the driving process, the inclinometer continuously collects real-time pile inclination data and sends this data to the computer control system. The computer control system compares the received real-time pile inclination data with a pre-set second preset value. The second preset value can be set to a pile verticality deviation of no more than 0.8%. When the real-time pile inclination data detected by the inclinometer exceeds the second preset value, the computer control system issues a correction command. At this time, jacks on the pile stabilization platform apply a correction thrust to the engineering pile to adjust its verticality. The direction of the correction thrust of the jacks can be determined based on the inclination direction detected by the inclinometer, i.e., applying thrust towards the opposite side of the inclination direction. During the correction process, the computer control system continuously receives real-time inclination data returned by the inclinometer until the data returns to less than or equal to the second preset value.

[0035] While pile driving continues, a laser rangefinder continuously collects real-time penetration data of the engineering pile. The laser rangefinder calculates the change in pile depth under each hammer blow by measuring the change in distance between itself and the reflective film. A hammer count sensor simultaneously collects the real-time number of hammer blows. Both the real-time penetration data collected by the laser rangefinder and the real-time number of hammer blows collected by the hammer count sensor are sent to the computer control system. The computer control system calculates the average penetration per blow based on the received real-time penetration data and the real-time number of hammer blows. The average penetration per blow is calculated as follows: Taking 10 consecutive blows as a group, the total penetration of the 10 blows in that group is divided by 10 to obtain the average penetration per blow. ,in, S represents the average penetration per blow. 10 The total penetration of 10 consecutive shots.

[0036] The computer control system compares the calculated average penetration per blow with a pre-set third preset value. This third preset value can be determined based on test pile results or design requirements; generally, the final penetration should not be less than 20 mm / 10 blows. When the average penetration per blow of three consecutive sets of hammer blows is less than or equal to the third preset value, the computer control system issues a stop hammer command. The preferred number of sets is three, and the preferred number of blows is 10, meaning three consecutive sets of hammer blows, each consisting of 10 blows.

[0037] During pile driving, when the inclinometer detects that the real-time pile inclination data exceeds a second preset value and the computer control system issues a correction command, the computer control system pauses the comparison of the average penetration per blow with a third preset value and the issuance of a stop command. Simultaneously, the pile hammer continues to continuously strike the pile, without interrupting the pile driving operation due to the correction command. Once the real-time pile inclination data detected by the inclinometer returns to less than or equal to the second preset value, the computer control system resumes comparing the average penetration per blow with the third preset value and issuing stop commands, and restarts counting the penetration data used for stop-driving judgment, i.e., restarting the counting of the average penetration per blow for three consecutive blows starting from the first set.

[0038] like Figure 1 As shown, this embodiment completes the entire process of sensor installation and connection, pile hoisting and verticality adjustment, pile driving, tilt monitoring and correction, and penetration depth acquisition and hammer stop determination according to the above steps. When the inclinometer detects that the tilt is less than or equal to the second preset value, the computer control system continuously collects real-time penetration data and real-time hammer blow count and calculates the average penetration per blow. When the average penetration per blow of three consecutive hammer blows is less than or equal to the third preset value, the computer control system issues a hammer stop command.

[0039] Compared to existing technologies that stop hammering and then correct the deviation when the pile verticality deviation exceeds the allowable value, this implementation method maintains continuous hammering during the correction period while pausing the hammering stop judgment logic. This avoids stress redistribution in the soil around the pile and creep settlement of the pile caused by hammering stoppage. Pile foundation construction specifications require that the centerlines of the pile hammer, pile cap, and pile body be kept on the same centerline, and that the verticality of the pile body be checked continuously during pile driving. Existing technologies typically stop hammering when dealing with verticality deviations, while this implementation method, through software logic control, achieves parallel operation of correction and continuous pile driving while ensuring construction safety. This reduces the construction efficiency loss caused by frequent hammering stops and restarts, and avoids the adverse effects of soil stress changes during hammering stoppages on the subsequent pile driving quality.

[0040] According to another embodiment of the present invention, in the construction control method for the pile driving process, a stress sensor and an acceleration sensor are installed on the pile body before the hammer driving operation. The stress sensor is used to collect time history data of the impact force exerted by the pile hammer on the pile during each hammer blow, and the measured strain is converted into impact force based on the elastic modulus and cross-sectional area of ​​the pile body. The stress sensor can be a resistance strain gauge force sensor or a piezoelectric force sensor, and its range can be selected according to the magnitude of the impact force of the pile hammer, generally 500 t to 2000 t, and the sampling frequency can be selected from 10 kHz to 20 kHz. The acceleration sensor is used to collect the acceleration time history data of the pile during each hammer blow. A piezoelectric acceleration sensor can be used, and its range can be selected from ±500 g to ±2000 g, with the sampling frequency consistent with that of the stress sensor. The stress sensor and the acceleration sensor can be installed in pairs on both sides of the pile body. The vertical distance between the sensor and the pile top should not be less than twice the pile diameter, and the centers of the strain sensor and the acceleration sensor should be located on the same horizontal plane. The sensors can be bolted to the pile body. For steel pipe piles, holes can be drilled and threaded before installation, while for concrete piles, expansion bolts can be used. The stress sensor and acceleration sensor are connected to the computer control system via signal cables.

[0041] During pile driving, stress sensors continuously collect time-history data F(t) of the impact force exerted by the pile hammer on the engineering pile at each hammer blow and send this data to the computer control system. After receiving the impact force time-history data, the computer control system integrates the data over time to obtain the impact impulse data for each hammer blow. Where I is the impact impulse and F(t) is the impact force time history data.

[0042] Simultaneously, the accelerometer continuously collects the acceleration time history data a(t) of the pile during each hammer blow and sends this data to the computer control system. Upon receiving the acceleration time history data, the computer control system integrates the data to obtain the velocity time history data. Then, the velocity time history data is integrated twice to obtain the displacement time history data of the engineering pile during each hammer blow. It should be noted that obtaining displacement time history data through double integration of the acceleration signal is feasible in engineering practice.

[0043] After obtaining the impact force time history data F(t) and displacement time history data s(t), the computer control system calculates the input energy data for each hammer blow. The calculation method for the input energy data is as follows: the impact force time history data and displacement time history data are multiplied point-by-point along the same time axis, and then integrated over time to obtain the input energy transmitted to the pile body for each hammer blow. E inThe input energy is F(t), the impact force time history data is v(t), the velocity time history data is v(t), and the displacement derivative is ds.

[0044] Simultaneously, the computer control system calculates the increase in pile potential energy after each hammer blow based on the pile mass data *m* and displacement time history data. The calculation method for the pile potential energy increase is as follows: multiply the pile mass data by the gravitational acceleration *g*, and then multiply by the final displacement *s* generated by that hammer blow. end With initial displacement s start The difference yields the increase in the pile's potential energy: E p Let m be the increase in potential energy of the pile, g be the mass of the pile, and s be the acceleration due to gravity. end Let s be the final displacement value. start This represents the initial displacement value.

[0045] The computer control system divides the incremental potential energy of the pile calculated for each hammer blow by the input energy data to obtain the energy conversion efficiency data for each hammer blow. Where η is the energy conversion efficiency, E p E represents the increase in the potential energy of the pile. in The input energy is used for calculation. It should be noted that the energy conversion efficiency in this embodiment refers to the proportion of the increase in the pile's potential energy to the input energy. This efficiency value is usually much less than 1 because most of the input energy is consumed during the hammering process by the elastic deformation of the pile body, the vibration of the soil around the pile, the frictional resistance of the pile side, and heat dissipation. This is different from the energy transfer efficiency from the pile hammer to the pile body in the conventional sense.

[0046] During the pile driving process, the computer control system continuously calculates the energy conversion efficiency data η for each hammer blow and judges the trend of the energy conversion efficiency data. When the energy conversion efficiency data of P consecutive hammer blows is less than or equal to the energy conversion efficiency data of the previous hammer blow, and when the condition that the average penetration rate per blow of N consecutive hammer blows is less than or equal to the fifth preset value is not triggered, the computer control system determines that the engineering pile has entered the bearing layer. It then uses the current average penetration per blow as a dynamic benchmark value, multiplies the dynamic benchmark value by a preset proportional coefficient to obtain an adjusted third preset value, and replaces the original third preset value with the adjusted third preset value for subsequent hammer stopping judgment; P is a positive integer greater than or equal to 5.

[0047] Compared to existing technologies that rely on manual observation of penetration changes and geological data to determine the bearing stratum, or on using fixed preset values ​​for stopping hammering, this implementation method achieves quantitative identification of the bearing stratum by calculating energy conversion efficiency in real time and automatically adjusts the hammering stop threshold accordingly. While existing pile driving analyzers and other equipment can monitor parameters such as hammering energy and penetration, they are primarily used for post-mortem analysis or bearing capacity assessment, and do not use energy conversion efficiency as a real-time control indicator for bearing stratum identification. This implementation method uses the ratio of the pile's potential energy increment to the input energy as the basis for bearing stratum identification. When the pile tip enters the bearing stratum, the soil resistance increases sharply, and the proportion of the hammering input energy converted into downward pile displacement decreases significantly. By automatically tightening the hammering stop standard after P consecutive cycles of achieving the energy conversion efficiency target, over-driving can be avoided while ensuring the pile tip enters the bearing stratum, reducing pile driving quality problems and construction efficiency losses caused by improper hammering stop standards.

[0048] According to another embodiment of the present invention, in the construction control method for the pile driving process, pressure sensors are installed at each jack of the pile stabilization and positioning platform before the start of the hammer driving operation. The pile stabilization and positioning platform can be configured as a double-layer structure, with four hydraulic jacks evenly distributed along the circumference of the engineering pile in each layer. The maximum jacking force of each jack can be selected from 100 t to 200 t. The pressure sensors can be installed between the piston rod end of each jack and the contact surface of the engineering pile, or installed in the hydraulic oil circuit of the jack to detect oil pressure and convert it into thrust. The pressure sensors can be resistance strain gauge pressure sensors or piezoelectric pressure sensors, and their range can be selected according to the maximum jacking force, generally from 100 t to 300 t, and the accuracy can be selected from 0.5 grade or higher. At the same time, a first positioning device is installed at the center position of the pile stabilization and positioning platform. This first positioning device is used to determine the projected position of the center point of the pile stabilization and positioning platform on the horizontal plane. The first positioning device can be a GPS rover, which is used to lay out and mark the cross axis of the center of the engineering pile on the pile stabilization and positioning platform. The first positioning device can also employ a total station or laser rangefinder in conjunction with a fixed prism. By setting multiple reference points with known coordinates on the pile positioning platform, the planar coordinates of the platform's center point are determined using intersection surveying or re-intersection methods. A second positioning device is installed at the centerline of the pile. This second positioning device is used to determine the projected position of the pile's centerline on the horizontal plane. The second positioning device can be a reflecting prism or laser target installed at the pile's centerline, used in conjunction with a total station or theodolite for measurement. Alternatively, the second positioning device can use a centering rod or laser plumb line installed at the center of the pile top. The planar position of the pile's centerline is determined by measuring the projected coordinates of the bottom of the centering rod on the horizontal plane. The first and second positioning devices can be connected to a computer control system via wired or wireless communication. The computer control system can be an industrial control computer or embedded controller, equipped with a data acquisition module and a coordinate calculation module, possessing real-time data acquisition, coordinate calculation, and logical judgment functions.

[0049] During pile driving, when the inclinometer detects that the real-time pile inclination exceeds a second preset value, the computer control system issues a correction command. Simultaneously, each pressure sensor continuously collects the real-time output pressure data of its corresponding jack and sends this data to the computer control system. Upon receiving the real-time output pressure data from each jack, the computer control system calculates the projection position of the resultant force of each jack's output thrust onto the horizontal plane based on the spatial distribution of the jacks, thus obtaining the real-time thrust center coordinates of the jack array. The installation position coordinates of each jack on the pile stabilization platform can be obtained by measurement after platform installation and pre-input into the computer control system. Let there be n jacks in total, and the thrust of the i-th jack be F.i Its spatial distribution location coordinates are (x i ,y i If the x-coordinate of the thrust center is x, then... c and the vertical coordinate y c They are respectively: , Where n is the total number of jacks, F i Let x be the thrust of the i-th jack. i ,y i Let (x) be the spatial coordinates of the i-th jack. c ,y c () represents the coordinates of the thrust center.

[0050] At the same time, the computer control system calculates the projection position of the center line of the engineering pile on the horizontal plane based on the relative spatial position data provided by the first and second positioning devices, and obtains the real-time center coordinates (x, y) of the engineering pile. p ,y p) The first positioning device provides the fixed coordinates of the center point of the pile stabilization positioning platform, and the second positioning device provides the real-time projection coordinates of the center line of the pile body on the horizontal plane. Combining these two methods determines the position of the pile body center relative to the center of the pile stabilization positioning platform. When the pile is vertical, the projection of the pile body center line onto the horizontal plane is a point, and the coordinates of this point are the real-time coordinates of the pile body center.

[0051] The computer control system obtains the real-time thrust center coordinates (x c ,y c ) and real-time pile center coordinates (x p ,y p Then, the horizontal distance between the two is calculated to obtain the thrust-pile center offset data d: The thrust-pile center offset reflects the degree of deviation between the point of application of the resultant force applied to the engineering pile by the jack array and the centerline of the engineering pile itself. A deviation of the thrust center from the pile center will cause the engineering pile to bear eccentric loads, potentially generating additional bending moments, affecting the correction effect, and even causing damage to the pile. The computer control system compares the calculated thrust-pile center offset data with a pre-set fourth preset value d0. The fourth preset value can be determined based on the diameter of the engineering pile, the strength of the pile material, and the required correction accuracy. Generally, it can be taken as 5% to 10% of the engineering pile diameter. For example, for an engineering pile with a diameter of 1000 mm, the fourth preset value can be 50 mm to 100 mm.

[0052] When the thrust-pile center offset data d is greater than the fourth preset value d0, the computer control system adjusts the output pressure distribution of each jack to make the real-time thrust center coordinate (x) equal to the pile center offset data d. c ,yc ) to the real-time pile center coordinates (x p ,y p The adjustment can be performed as follows: when the thrust center is located on one side of the pile center, the computer control system reduces the thrust of the jacks on that side while increasing the thrust of the jacks on the opposite side, causing the thrust center to gradually move towards the pile center. The thrust adjustment of the jacks can be achieved by adjusting the electro-hydraulic proportional pressure reducing valve in the hydraulic circuit of each jack. During continuous hammering, the computer control system uses the interval between two adjacent hammering strikes as the output pressure adjustment window to adjust the output pressure of each jack, thus avoiding control disturbances caused by pressure adjustment at the instant of impact load application. During the adjustment process, the computer control system continuously receives real-time feedback data from each pressure sensor and continuously calculates the updated thrust center coordinates until the thrust-pile center offset data is less than or equal to the fourth preset value.

[0053] The computer control system uses the pile inclination data being less than or equal to the second preset value and the thrust-pile center offset data being less than or equal to the fourth preset value as the conditions for completing the correction. That is, the correction is completed when both the pile inclination and the thrust center offset are within the allowable range.

[0054] Compared to existing technologies that directly drive jacks to correct tilt after detecting tilt using tilt sensors, and only use the achievement of a tilt standard as the condition for completion of correction, this implementation introduces control over the offset between the thrust center and the pile center. In existing technologies, jack correction typically employs open-loop or semi-closed-loop control. That is, after detecting tilt, the jack is driven to push, and then the tilt standard is checked again; if not, pushing continues. While this method eventually achieves the required tilt, it cannot guarantee the rationality of the pile's stress state during the correction process. The thrust center and the pile center may remain misaligned for a long time, causing the pile to bear continuous eccentric loads. This implementation calculates the offset between the thrust center and the pile center in real time and incorporates this offset into the judgment condition for completion of correction. This ensures that the correction process not only straightens the pile but also straightens it evenly, avoiding additional stress and potential damage to the pile caused by eccentric loads. Meanwhile, by monitoring the position of the thrust center in real time and dynamically adjusting the output distribution of each jack, the continuous balance of the force on the pile body during the correction process can be achieved, thereby improving the safety of the correction operation and the quality of the pile body.

[0055] According to another embodiment of the present invention, in the construction control method for the pile driving process, during the pile driving process, a laser rangefinder continuously collects penetration data for each hammer blow, and a hammer blow count sensor synchronously collects the number of hammer blows. The computer control system calculates the average penetration per blow based on the received real-time penetration data and the real-time number of hammer blows. The average penetration per blow can be calculated in groups of 10 consecutive blows, i.e., the total penetration of the 10 blows in that group is divided by 10 to obtain the average penetration per blow for that group. The computer control system continuously calculates the rate of change of the average penetration per blow between each adjacent group or between each adjacent two hammer blows during the pile driving process. The method for calculating the rate of change of average penetration per blow is as follows: Divide the difference between the average penetration per blow of the current blow and the average penetration per blow of the previous blow by the larger of the two values. When both the average penetration per blow of the current blow and the average penetration per blow of the previous blow are zero, set the rate of change of average penetration per blow to zero. Let the average penetration per blow of the previous blow be... The average penetration per blow in the current hammer strike is Then the rate of change r k for: , where r k Let be the rate of change of the average penetration per blow of the k-th blow relative to the (k-1)-th blow. The average penetration per blow in the current hammer strike. The average penetration per blow of the previous hammer strike. The larger of the two values ​​is taken as the rate of change. This rate of change is a dimensionless ratio, ranging from -1 to 1, reflecting the increase or decrease in penetration depth between two consecutive hammer blows.

[0056] The computer control system calculates the average penetration rate r per blow for each time. k The value is compared with a pre-set fifth preset value r0. The fifth preset value can be a value between 0.05 and 0.15, preferably 0.10. When the average penetration rate per blow after N consecutive hammer blows is less than or equal to the fifth preset value, that is: This indicates that the penetration depth has stabilized, and the computer control system determines that the pile has entered the bearing stratum and sets the current average penetration depth per blow. This serves as a dynamic reference value. N is a positive integer greater than or equal to 3, preferably an integer between 3 and 5. The computer control system uses this dynamic reference value as a basis, multiplying it by a preset proportional coefficient β to obtain an adjusted third preset value: ,

[0057] The adjusted third preset value replaces the original third preset value for subsequent hammer stop determination. The proportional coefficient β ranges from 0.3 to 0.7. Preferably, this proportional coefficient can be determined according to the hardness of the bearing layer. When the bearing layer is a hard bearing layer, β can be 0.3 to 0.5, and when the bearing layer is a soft bearing layer, β can be 0.5 to 0.7. The third preset value is the aforementioned penetration threshold used for hammer stop determination. According to industry standards, the final penetration should not be less than 20 mm / 10 blows. To avoid excessive pile driving, damage to the pile body or pile hammer due to an excessively low adjusted third preset value, the adjusted third preset value should not be lower than the preset lower limit. This lower limit is determined according to the minimum final penetration depth specified in current standards, generally not less than 20 mm / 10 blows, and not less than 15 mm / 10 blows when the pile tip bearing layer is strongly weathered rock. When the adjusted third preset value calculated by the proportional coefficient is less than this lower limit, the computer control system uses this lower limit as the adjusted third preset value. When using the adjusted third preset value for hammer stopping judgment, if the average penetration depth per blow of three consecutive hammer blows is less than or equal to the adjusted third preset value, the computer control system issues a hammer stopping command. The adjustment of the third preset value based on the penetration change rate is only executed when the adjustment condition based on energy conversion efficiency is not triggered; if the adjustment condition based on energy conversion efficiency has been triggered and the third preset value adjustment has been completed, the adjustment of the third preset value based on the penetration change rate will not be repeated to avoid repeated modification of the same third preset value.

[0058] Compared to existing technologies that use fixed preset values ​​to determine when to stop hammering, and the empirical method in construction specifications that relies on manually observing the gradual decrease in penetration depth to determine when to stop hammering, this implementation method achieves quantitative monitoring of the penetration depth change trend by calculating the penetration depth change rate between each two adjacent hammer blows in real time. When the penetration depth change rate remains small, it indicates that the penetration depth per blow has stabilized and the pile tip has entered the bearing layer with uniform resistance. At this point, the hammering stop standard is automatically tightened based on the current penetration depth, which avoids the problems of premature hammering due to an excessively large fixed preset value or excessive pile driving due to an excessively small fixed preset value, making the hammering stop judgment more consistent with actual working conditions.

[0059] According to another embodiment of the present invention, in the construction control method for the pile driving process, a stress sensor is installed on the pile body before the hammer driving operation. The stress sensor is used to collect time-history data of the impact force exerted by the pile hammer on the pile during each hammer blow, and the measured strain is converted into impact force based on the pile's elastic modulus and cross-sectional area. The selection and installation method of the stress sensor are the same as those described above for installing stress sensors and acceleration sensors. The stress sensor is connected to a computer control system via a signal cable.

[0060] After each impact, the stress sensor sends the collected impact force time history data to the computer control system. The computer control system then determines the peak time t of the impact force time history curve based on the received impact force time history data. peak This refers to the moment when the impact force reaches its maximum value. Simultaneously, the computer control system determines the rise time data t, which is the time it takes for the impact force time history curve to rise from zero to the peak impact force. rise The computer control system also calculates the round-trip time t required for the stress wave to travel one round trip along the entire length of the engineering pile, based on the known pile length data L and pile wave velocity data c. round : The propagation speed of stress waves in the pile body is related to the elastic modulus and density of the pile material. For concrete piles, the wave velocity can generally be taken as 3500 m / s to 4500 m / s; for steel pipe piles, the wave velocity can generally be taken as 5100 m / s.

[0061] Computer control system calculates rise time data t rise Round-trip time difference data t round The ratio of the impact force to the relative duration coefficient γ is obtained. This coefficient is a dimensionless ratio reflecting the proportion of the impact force rise time to the time required for the stress wave to travel one round trip within the pile. The computer control system compares the impact force relative duration coefficient data γ with a pre-set sixth preset value γ0. The sixth preset value can be determined based on test pile results or engineering experience, and is generally a value between 0.5 and 1.0. When γ > γ0, it indicates that the impact force rise time is too long relative to the stress wave round trip time, and the computer control system marks this hammer blow as an eccentric hammer blow. During an eccentric hammer blow, the pile body generates a bending vibration component, causing the impact force rise process to slow down, and the proportion of the rise time to the stress wave round trip time to shift. The computer control system excludes the impact force time history data and acceleration time history data of the hammer blow marked as an eccentric hammer blow from the calculation of input energy data and pile potential energy increment data, to avoid abnormal data generated by eccentric hammer blows affecting subsequent energy conversion efficiency calculations and bearing layer judgments. Hammerings marked as eccentric hammerings are not included in the count of the aforementioned consecutive P hammerings; the count of P hammerings is carried over to subsequent hammerings that are not marked as eccentric hammerings.

[0062] Compared to existing technologies that determine hammer impact eccentricity by comparing the amplitude differences of force signals from both sides, this implementation only requires a single-sided stress sensor to identify eccentric hammer impacts. Existing standard methods for determining hammer impact eccentricity require at least two stress sensors symmetrically installed, comparing the amplitude differences of force signals from both sides to determine eccentricity. Eccentricity is determined when the absolute value of the difference between one of the force signals and the average force exceeds 33% of the average. This implementation uses the ratio of the impact force rise time to the stress wave round-trip time difference as the criterion, without relying on amplitude comparisons from both sensors. This results in a simpler hardware configuration and provides a feasible solution for eccentricity identification in single-sensor scenarios.

[0063] According to another embodiment of the present invention, in the construction control method for the pile driving process, pressure sensors are installed at each jack of the pile stabilization and positioning platform before the start of the hammer driving operation. The setup of the pile stabilization and positioning platform and the selection of pressure sensors are the same as in the aforementioned embodiment of installing pressure sensors at each jack. Each pressure sensor is connected to a computer control system via a signal cable.

[0064] When the computer control system issues a correction command and drives all jacks to extend simultaneously, each pressure sensor continuously collects real-time pressure data during the jack extension process and sends this data to the computer control system. The computer control system groups any two adjacent pressure sensors together and calculates the difference between the real-time output pressure data of the two sensors within the same group, obtaining the pressure difference time history data for that group. Let the real-time output pressure data of the two pressure sensors within the same group be p1(t) and p2(t), then the pressure difference time history data Δp(t) for that group is: In a jack array, adjacent jacks are positioned close together and their load variation trends are similar. Therefore, the pressure difference time histories of adjacent pressure sensors should have similar characteristics. The computer control system calculates the peak data Δp of the pressure difference time histories for each group. max This refers to the maximum absolute value of the time history data of each group of pressure differences during the correction process.

[0065] The computer control system compares the peak data of each group and calculates the average value of the peak data of the other groups. Then calculate the peak data for any group. The difference between this average value and the predetermined seventh preset value Δp0. The computer control system determines that at least one pressure sensor in the group has malfunctioned and issues a sensor fault alarm. The seventh preset value can be determined based on the accuracy of the pressure sensor and the normal operating pressure range of the jack. Generally, it can be taken as 5% to 10% of the jack's rated thrust. For example, for a jack with a rated thrust of 100 t, the seventh preset value can be the pressure value corresponding to 5 t to 10 t. When the peak value of the pressure difference time history of a certain group deviates significantly from the average level of other groups, it indicates that at least one pressure sensor in that group is outputting abnormally, such as zero-point drift, decreased sensitivity, or response lag. After issuing a sensor fault alarm, the computer control system can suspend the execution of correction commands until the fault is cleared, thus preventing erroneous correction actions caused by sensor malfunctions.

[0066] Compared to existing fault diagnosis methods that primarily rely on the absolute value of a single sensor's output signal for threshold judgment, this implementation utilizes the spatial arrangement of adjacent sensors within the jack array for cross-validation. Existing sensor fault diagnosis typically relies on monitoring the output signal of a single sensor, identifying a fault when the signal exceeds a preset normal range. This method requires setting individual thresholds for each sensor and struggles to distinguish between sensor faults and normal signal fluctuations caused by changes in operating conditions. This implementation does not rely on the absolute accuracy of a single sensor but identifies anomalies by comparing the relative relationships between adjacent sensors. When the peak pressure difference time history of a certain group significantly deviates from the average level of other groups, it indicates an anomaly within that group. This array-consistency-based diagnostic method does not rely on any external reference standards; fault judgment is entirely driven by the data consistency within the sensor array, resulting in better robustness and reliability in jack correction systems.

[0067] According to another embodiment of the present invention, in the construction control method for the pile driving process, during the hammer driving process, the computer control system continuously records the average penetration depth data per hammer blow for each hammer blow. And the hammer energy data E corresponding to each hammer blow k Hammering energy data can be obtained through a pile driving analyzer or calculated from impact force time history data collected by a stress sensor. Average penetration per blow data can be calculated from real-time penetration data collected by a laser rangefinder. When the average penetration per blow data for a given blow is zero, the energy consumption per unit penetration for that blow is not calculated, the blow is marked as an abnormal blow, and the average penetration per blow data for that blow is excluded from the calculation of the rate of change of average penetration per blow. The computer control system calculates the ratio of the hammering energy data for each blow to the corresponding average penetration per blow data to obtain the energy consumption per unit penetration data e. k : , where e kLet E be the energy consumption per unit penetration of the k-th hammer strike. k Let be the hammer energy of the k-th hammer strike. Let be the average penetration depth per blow of the k-th hammer strike.

[0068] The computer control system continuously records energy consumption data per unit penetration depth, forming time series data of energy consumption per unit penetration depth {e1,e2,…,e k The computer control system calculates the moving average of the time series data on energy consumption per unit penetration. The calculation window width for the moving average can be 5 to 10 hammer blows. The computer control system will use the energy consumption data per unit penetration of the current hammer blow. k With moving average The comparison is performed, and when the difference between the two is greater than the eighth preset value Δe0, that is: The computer control system marks the current hammer blow as an abnormal blow and excludes the average penetration per blow data of the current blow from the calculation of the average penetration per blow change rate. The eighth preset value can be determined based on engineering experience, and is generally taken as 20% to 40% of the moving average.

[0069] In the same soil layer, the energy consumption per unit penetration should be relatively stable. When the energy consumption per unit penetration of a certain hammer blow deviates significantly from the moving average, it indicates that there is an anomaly in the data of that hammer blow. Excluding its penetration data from the calculation of the rate of change can avoid the interference of abnormal data on the judgment of the bearing layer and the decision to stop hammering.

[0070] Compared to existing technologies that rely on manual observation of penetration data or simple threshold removal to handle outliers, this implementation introduces energy consumption per unit penetration as a physical constraint indicator, incorporating the physical relationship between hammering energy and penetration into the anomaly identification criteria. When the energy consumption of a hammering operation significantly deviates from its normal level, it can be identified as an abnormal hammering operation, regardless of whether the penetration value itself is abnormal. This method is more reliable than statistical methods that solely rely on penetration values ​​because the physical relationship between hammering energy and penetration exhibits good stability under different operating conditions.

[0071] According to another embodiment of the present invention, in the construction control method for the pile driving process, after each hammer blow, a stress sensor sends the collected impact force time history data to a computer control system. The computer control system determines the peak time t of the impact force time history curve based on the received impact force time history data. peakThis refers to the moment when the impact force reaches its maximum value. Starting from this peak moment, the computer control system searches for local extreme points sequentially along the impact force time history curve. Local extreme points are the local maximum and minimum points on the impact force time history curve, which can be determined by comparing the values ​​of adjacent sampling points. The computer control system records the time {t1, t2, ..., t...} when each local extreme point occurs. m}, thus obtaining the time sequence data of the extreme points.

[0072] The computer control system calculates the time difference between two adjacent extreme point times in the extreme point time sequence, obtaining the extreme point interval sequence data {Δt1, Δt2, ..., Δt}. m-1}, where: Δt j =t j+1 -t j (j=1,2,…,m-1), the computer control system counts the frequency of occurrence of each value in the extreme point interval sequence data, and takes the value with the highest frequency as the round-trip time difference t required for the stress wave to travel one round trip within the current length range of the engineering pile. round,mode : ,in, The frequency of the extreme point interval Δt in the extreme point interval sequence.

[0073] The stress wave propagates back and forth in the pile body and forms local extreme points with basically equal intervals on the impact force time history curve. The time interval is the time required for the stress wave to make one round trip. The periodic feature can be extracted by statistically analyzing the interval of the extreme point with the highest frequency, which is the mode statistical method. When multiple interval values ​​have the highest frequency, the smaller value is taken as the round trip time difference.

[0074] The computer control system uses this round-trip time difference data t round,mode The round-trip time difference (t) calculated from the known pile length and pile wave velocity data of the engineering pile is replaced. round =2L / c, used for subsequent calculation of the relative duration coefficient of impact force and judgment of eccentric hammering. When the frequency of occurrence of each value in the extreme point interval sequence data is lower than the ninth preset value f0, that is: This indicates that the fluctuation characteristics on the impact force time history curve are not obvious enough, which may be due to insufficient hammering energy, large pile damping, or poor sensor signal quality. In this case, the computer control system determines that the signal quality of the current hammering does not meet the self-calibration requirements, and still uses the round-trip time difference data calculated from the known pile length data and pile wave velocity data as the round-trip time difference data. The ninth preset value can be determined according to the data length, and is generally an integer between 3 and 5.

[0075] Compared to existing post-hoc detection methods that use stress wave reflection travel time to infer pile length or wave velocity, and traditional peak-to-peak methods that measure the time interval between the first two peaks of the reflected wave to extract the reflection period, this embodiment applies the mode statistics of extreme point intervals to real-time round-trip time difference self-calibration during pile driving. The existing peak-to-peak method only utilizes the time interval between the first two reflected wave peaks, making it susceptible to noise interference and waveform distortion, and primarily used for post-hoc pile quality detection. This embodiment extracts the round-trip time difference by statistically analyzing the mode of a large number of extreme point intervals, utilizing all fluctuation information on the time history curve, resulting in stronger noise resistance and robustness. Furthermore, this self-calibration method does not rely on pre-inputted pile length and wave velocity data, automatically adapting to the constantly changing free length of the pile during pile driving, fundamentally eliminating round-trip time difference calculation errors caused by pile length variations and wave velocity uncertainties.

[0076] According to another embodiment of the present invention, in the construction control method for the pile driving process, pressure sensors are installed at each jack of the pile stabilization and positioning platform before the start of the hammer driving operation. The setup of the pile stabilization and positioning platform and the selection of pressure sensors are the same as in the aforementioned embodiment of installing pressure sensors at each jack. Each pressure sensor is connected to a computer control system via a signal cable.

[0077] Before issuing a correction command, the computer control system first collects real-time pressure data from each pressure sensor under the current tilt state of the engineering pile. The pressure distribution under the current tilt state naturally reflects the uneven load distribution caused by the tilt; the jacks on one side of the tilt bear a larger load, while those on the opposite side bear a smaller load. The computer control system groups any two adjacent pressure sensors together and calculates the difference between the real-time output pressure data of the two pressure sensors within the same group, obtaining the pressure difference data Δp before correction for each group. before,j Δp before,j =|p j,1 -p j,2 |, where Δp before,j Let p be the pressure difference of group j before correction. j,1 and p j,2 This represents the real-time output pressure data of the two pressure sensors in group j.

[0078] After issuing a correction command and driving each jack to extend, the computer control system again collects the real-time output pressure data of each pressure sensor. Following the same grouping method, it calculates the difference between the real-time output pressure data of two pressure sensors within the same group, obtaining the time-history data Δp of the pressure difference after correction for each group. after,j (t): Δp after,j (t)=|p j,1 (t)-p j,2(t)|, where Δp after,j (t) represents the time history data of the pressure difference in the j-th group after correction.

[0079] The computer control system calculates the peak value (Δp) of the time history data of the pressure difference after each group of corrections. after,j (t) and the pressure difference data before correction Δp before,j The ratio of the pressure difference change rate λ for each group is obtained. j : The pressure difference change rate reflects the degree of change in pressure difference between adjacent jacks before and after the correction.

[0080] The computer control system compares the pressure difference change rate data of each group and calculates the average value of the pressure difference change rate data of the other groups. Then calculate the rate of change of pressure difference λ for any set of data. j The difference between this average value and the mean value. When this difference is greater than the tenth preset value λ0, that is: The computer control system determines that at least one pressure sensor in the group has malfunctioned and issues a sensor fault alarm. The tenth preset value can be determined based on the accuracy of the pressure sensor and engineering experience, and is generally a value between 0.2 and 0.4. When the rate of change of pressure difference in a group deviates significantly from the average level of other groups, it indicates that at least one pressure sensor in that group is outputting abnormally during the correction process, such as zero-point drift, sensitivity changes, or response lag. After issuing a sensor fault alarm, the computer control system can suspend the execution of correction commands until the fault is resolved and the execution of correction commands resumes.

[0081] Compared to existing fault diagnosis methods that primarily rely on the absolute value of a single sensor's output signal for threshold judgment, and methods that use multi-sensor consistency verification for fault detection, this implementation uses the pressure distribution of the engineering pile itself under its tilted state before correction as a reference benchmark. Existing multi-sensor consistency verification typically assumes that each sensor should output the same or similar signals under normal operating conditions. However, this assumption does not hold true when the engineering pile is tilted, as the load borne by the jacks on one side of the tilt direction is inevitably greater than that on the other side. This implementation, by introducing a self-reference benchmark before correction, fundamentally eliminates the interference of uneven systemic pressure distribution caused by tilt on fault diagnosis, making fault judgment more accurate and reliable. This self-comparison approach does not rely on any external standards or preset thresholds; it is entirely based on real-time data during the current correction process, making it simple to implement and highly applicable.

[0082] According to another embodiment of the present invention, in the construction control method for the pile driving process, during the pile driving process, the computer control system continuously records the hammer energy data E of each hammer blow. kand the corresponding average penetration per hit data The method for obtaining hammer impact energy and average penetration per blow data is the same as the aforementioned method for calculating energy consumption per unit penetration. The computer control system uses hammer impact energy data as the x-axis and average penetration per blow data as the y-axis, and plots the data points for each hammer impact. The data is plotted on the phase plane. The phase plane is a two-dimensional coordinate plane with the hammer energy as the horizontal axis and the penetration as the vertical axis. In the same soil layer, there is a stable positive correlation between hammer energy and penetration. The data points are distributed in a band-shaped region in the phase plane.

[0083] The computer control system uses the data points of the current hammer strike. Centered on the data points of the V hammer blows preceding the current blow, select the relevant data points. A reference point set is constructed. When the number of hammer blows already occurred is less than V, the current hammer blow is marked as a normal hammer blow. V is a positive integer greater than or equal to 5, preferably an integer between 5 and 10. The computer control system calculates the centroid coordinates of the reference point set in the phase plane. And covariance matrix C: , , .

[0084] The computer control system determines the elliptical region of the reference point set based on the covariance matrix. The center of the elliptical region is the centroid coordinate. The directions of the major and minor axes of the ellipse are determined by the eigenvectors of the covariance matrix. The lengths of the major and minor axes of the ellipse can be determined by multiplying the eigenvalues ​​of the covariance matrix by a preset multiple, which can be a value between 2 and 3, corresponding to a confidence interval of approximately 95% to 99%.

[0085] The computer control system determines the data point of the current hammer strike. Whether the data point of the current hammer blow is located inside the distribution elliptical region. If the data point of the current hammer blow is located inside the distribution elliptical region, then the hammer blow is marked as a normal hammer blow. If the data point of the current hammer blow is located outside the distribution elliptical region, then the data point of the previous hammer blow is further analyzed. Is it also located outside the distribution elliptical region? If the data point from the previous hammer blow was located inside the distribution elliptical region, it indicates that the current hammer blow is an isolated single-point deviation. The computer control system marks the current hammer blow as an abnormal blow and excludes the average penetration per blow data from the calculation of the average penetration per blow change rate. If the data point from the previous hammer blow was also located outside the distribution elliptical region, it indicates that the data point has been located outside the distribution elliptical region for two consecutive times, showing a continuous migration trend. The computer control system determines that the engineering pile is currently in the soil layer transition stage. The soil layer transition stage refers to the transition process of the engineering pile tip from the current soil layer to the adjacent soil layer. The average penetration per blow data of the current hammer blow is included in the calculation of the average penetration per blow change rate.

[0086] Compared to existing technologies that identify abnormal hammer blows using one-dimensional time series moving averages or filtering methods, and those that only monitor single parameters such as hammer energy and penetration depth separately, this implementation combines hammer energy and penetration depth into a single physical quantity for trajectory analysis in the phase plane. While existing pile driving analysis techniques can monitor the hammer energy and penetration depth of each blow, they are limited to monitoring each parameter separately and do not perform joint analysis as binary data. This implementation distinguishes between two different events by observing the trajectory shape of data points in the phase plane: isolated single-point deviation corresponds to abnormal hammer blows, while continuous multi-point migration corresponds to soil layer transitions. This method of distinguishing event types based on trajectory shape rather than numerical magnitude enables real-time judgment with zero lag, effectively avoiding the problem of misjudging normal soil layer transitions as abnormal hammer blows and resulting in erroneous data rejection.

[0087] Application examples

[0088] This application example uses a precast pile foundation project in a coastal area as an example to provide a detailed description of the construction control method for the pile driving process provided by this invention.

[0089] This project employs hammer-driven prestressed concrete pipe pile foundations, using commercially available prestressed concrete pipe piles with a diameter of 500 mm and a concrete strength grade of C80. The designed pile length is 35 m, using a tapered steel pile tip. The geological survey report indicates that the site, from top to bottom, consists of fill, silty clay, silty clay, medium-dense sand, and a strongly weathered rock bearing layer. The characteristic value of the vertical bearing capacity of a single pile is 2000 kN. Commercially available cylindrical diesel hammers are used for pile driving, with an impact weight of 5 tons and a drop height controlled between 1.5 m and 2.0 m. During construction, pile length control is the primary focus, supplemented by penetration control; the average penetration of the last three drives is controlled to be no greater than 20 mm / 10 blows.

[0090] Before construction, a blow count sensor is installed on the side of the pile hammer to record the number of blows for each strike. A biaxial inclinometer with a range of ±90° and an accuracy of 0.1° is installed on the pile hammer guide frame to continuously monitor the tilt angle of the engineering pile during construction. A laser rangefinder with a range of 50 m and a resolution of 0.1 mm is installed on the support at the top of the pile hammer. A reflective film is also installed on the upper surface of the pile cap. The laser rangefinder calculates the change in the pile's penetration depth under each blow by measuring the change in distance between itself and the reflective film. Resistance strain gauge force sensors and piezoelectric accelerometers are also installed on the pile body. The stress sensor has a range of 1000 t, and the accelerometer has a range of ±1000 g, both with a sampling frequency of 20 kHz. The sensors are symmetrically installed on both sides of the pile body, with the centers of the strain gauge and accelerometer located on the same horizontal plane. The hammer impact sensor, inclinometer, laser rangefinder, stress sensor, and accelerometer are connected to the computer control system via signal cables. The computer control system is an industrial control computer equipped with a multi-channel data acquisition card, which has real-time data acquisition, signal processing, and logic judgment functions.

[0091] Four hydraulic jacks are evenly distributed along the circumference of the engineering pile on both the upper and lower levels of the pile stabilization and positioning platform. Each jack has a maximum jacking force of 100 t. A resistance strain gauge pressure sensor with a range of 150 t is installed at the end of the piston rod of each jack. A GPS rover station is installed at the center of the pile stabilization and positioning platform as the first positioning device to determine the planar coordinates of the platform's center point. A reflecting prism is installed at the center of the pile top as the second positioning device, which, in conjunction with a total station, determines the projection position of the pile's centerline on the horizontal plane. Each pressure sensor, the first positioning device, and the second positioning device are connected to the computer control system via wired or wireless communication.

[0092] After the engineering pile is hoisted into the pile stabilization and positioning platform, a long strip leveling rod is first used for rough calibration, and then two theodolites are used to check in two directions at 90° to each other. Under the control of the computer control system, the jacks extend and retract sequentially to push the engineering pile so that the verticality deviation of the pile body does not exceed 0.5%, that is, the first preset value is 0.5%.

[0093] The pile hammer is activated to drive the engineering pile. During the driving process, an inclinometer continuously collects real-time pile inclination data at a sampling frequency of 10 Hz and sends this data to the computer control system. The computer control system compares the received real-time pile inclination data with a second preset value, which is set to a verticality deviation of no more than 0.8%. When the real-time pile inclination data detected by the inclinometer exceeds 0.8%, the computer control system issues a correction command. At this time, jacks on the pile stabilization platform apply a correction thrust to the engineering pile to adjust its verticality. The direction of the correction thrust is determined based on the inclination direction detected by the inclinometer, i.e., the thrust is applied towards the opposite side of the inclination direction. During the correction process, the computer control system continuously receives real-time inclination data returned by the inclinometer until the data returns to less than or equal to 0.8%.

[0094] While pile driving continues, a laser rangefinder continuously collects real-time penetration data of the engineering pile, and a hammer count sensor simultaneously collects the real-time number of hammer blows. Based on the received real-time penetration data and the real-time number of hammer blows, the computer control system calculates the average penetration per blow by dividing the total penetration of 10 consecutive blows in a group by 10. The computer control system compares the calculated average penetration per blow with a pre-set third preset value, which is 20 mm / 10 blows. When the average penetration per blow of three consecutive sets of blows is less than or equal to 20 mm / 10 blows, the computer control system issues a stop command. Three sets refer to three consecutive groups of blows, each group consisting of 10 blows.

[0095] Meanwhile, during the pile driving process, the computer control system continuously calculates the rate of change of the average penetration per blow between each adjacent two blows. The rate of change is calculated by dividing the difference between the average penetration per blow of the current blow and the average penetration per blow of the previous blow by the larger of the two values. For example, if the average penetration per blow of the previous blow was 25 mm / 10 blows and the current blow is 22 mm / 10 blows, then the rate of change is: r = (22 - 25) / 25 = -0.12.

[0096] The computer control system compares the calculated rate of change with a fifth preset value, which is 0.10. When the rate of change of the average penetration per blow for three consecutive hammer blows is less than or equal to 0.10, and the aforementioned adjustment condition for the third preset value based on energy conversion efficiency is not triggered, the computer control system uses the current average penetration per blow as a dynamic reference value, multiplies it by a proportional coefficient of 0.5, and obtains the adjusted third preset value, replacing the original third preset value for subsequent hammer stop judgment.

[0097] Regarding data acquisition from stress and acceleration sensors, the stress sensor continuously acquires the time-history data F(t) of the impact force exerted by the pile hammer on the engineering pile during each hammer blow, while the acceleration sensor continuously acquires the time-history data a(t) of the acceleration of the engineering pile during each hammer blow. The computer control system integrates the impact force time-history data over time to obtain the impact impulse data for each hammer blow. The velocity time history data is obtained by integrating the acceleration time history data once. Then, the velocity time history data is integrated twice to obtain the displacement time history data of the engineering pile during each hammer blow. The computer control system, based on the impact force time history data and displacement time history data, multiplies the impact force time history data and displacement time history data point by point on the same time axis and then integrates over time to obtain the input energy transmitted to the pile body for each hammer blow. Simultaneously, the computer control system multiplies the pile mass of approximately 13 tons by the gravitational acceleration of 9.8 m / s², and then by the difference between the final and initial displacement values ​​generated by the hammer blow, to obtain the pile's potential energy increment E. p =m×g×(s end -s start The computer control system divides the increase in the pile's potential energy by the input energy to obtain the energy conversion efficiency η=E for each hammer blow. p / E in When the energy conversion efficiency of five consecutive hammer blows is less than or equal to the energy conversion efficiency of the previous hammer blow, the computer control system determines that the engineering pile has entered the bearing layer, and uses the current average penetration per blow as the dynamic benchmark value, multiplies it by a proportional coefficient of 0.5 to obtain the adjusted third preset value, which replaces the original third preset value for subsequent hammer stop judgment.

[0098] During the correction process, the computer control system also controls the offset between the thrust center of the jack array and the pile center. Each pressure sensor continuously collects real-time output pressure data from its corresponding jack. Based on the real-time output pressure data of each jack and their spatial distribution on the pile stabilization platform, the computer control system uses the torque balance principle to calculate the projection position of the resultant force application point of each jack's output thrust on the horizontal plane, thus obtaining the real-time thrust center coordinates (x, y) of the jack array. c ,y c The x-coordinate and y-coordinate of the thrust center are respectively: Simultaneously, the computer control system calculates the projection position of the centerline of the engineering pile on the horizontal plane based on the relative spatial position data provided by the first and second positioning devices, thus obtaining the real-time center coordinates (x, y) of the engineering pile. p ,y pThe computer control system calculates the horizontal distance between the real-time thrust center coordinates and the real-time pile center coordinates to obtain the thrust-pile center offset data. When the offset exceeds a fourth preset value (50 mm), the computer control system adjusts the output pressure distribution of each jack. By adjusting the electro-hydraulic proportional pressure reducing valve in the hydraulic circuit of each jack, the output pressure of each jack is independently adjusted, causing the real-time thrust center coordinate to move towards the real-time pile center coordinate until the thrust-pile center offset is less than or equal to 50 mm. The computer control system uses a pile inclination less than or equal to 0.8% and a thrust-pile center offset less than or equal to 50 mm as the criteria for successful correction.

[0099] Furthermore, after each hammer blow, the computer control system determines the peak moment of the impact force time history curve and the rise time t taken for the impact force time history curve to rise from zero to the peak impact force based on the impact force time history data collected by the stress sensor. rise Simultaneously, the computer control system calculates the round-trip time t required for the stress wave to complete one round trip in the current free section of the engineering pile, based on the current free section length L of the engineering pile and the pile wave velocity of 4000 m / s. round =2L / c. The computer control system calculates the ratio of rise time to round-trip time difference to obtain the relative duration coefficient of impact force γ=t. rise / t round The data is then compared with a sixth preset value, which is 0.8. When γ > 0.8, the computer control system marks the impact as an eccentric impact and excludes the impact force time history data and acceleration time history data from the calculation of input energy and pile potential energy increment. To further improve the accuracy of the round-trip time difference, the computer control system also searches for local extreme points sequentially from the peak time of the impact force time history curve, recording the time of occurrence of each local extreme point {t1, t2, ..., t...}. m} Calculate the time difference Δt between adjacent extreme points. j =t j+1 -t j The most frequently occurring value was used as the stress wave round-trip time t. round,mode =argmax Δt freq(Δt) replaces the round-trip time difference calculated from the pile length and wave velocity.

[0100] In the fault diagnosis of jack pressure sensors, the computer control system takes any two adjacent pressure sensors as a group, calculates the difference Δp(t) = |p1(t) - p2(t)| between the real-time output pressure data of the two pressure sensors in the same group, obtains the pressure difference time history data of the group, and calculates the peak value Δp of the pressure difference time history data of each group.max When the difference between the peak value of any group and the average of the peak values ​​of other groups exceeds the pressure value corresponding to the seventh preset value of 10 t, the computer control system determines that at least one pressure sensor in that group has malfunctioned and issues an alarm. To eliminate interference from the uneven systemic pressure distribution caused by the tilt of the engineering pile on fault diagnosis, the computer control system first collects the real-time output pressure data of each pressure sensor under the current tilt state of the engineering pile before issuing the correction command, and calculates the pressure difference data Δp of each group before correction. before,j After issuing the correction command and driving each jack to extend, data is collected again to calculate the peak value (Δp) of the time history data of the pressure difference after correction for each group. after,j (t)); Calculate the ratio of the peak value after correction to the pressure difference data before correction for each group, and obtain the pressure difference change rate λ. j =max(Δp after,j (t)) / Δp before,j When the difference between the pressure difference change rate of any group and the average change rate of other groups is greater than 0.3, it is determined that there is a sensor fault in that group.

[0101] In terms of abnormal hammer impact identification, the computer control system continuously records the hammer impact energy E of each hammer impact. k and the corresponding average penetration per shot The energy consumption per unit penetration is obtained by calculating the ratio of hammering energy to penetration depth. This generates time series data of energy consumption per unit penetration depth and calculates its moving average. When the difference between the energy consumption per unit penetration of the previous hammer blow and the moving average value is greater than 30% of the eighth preset value (the moving average value), that is... The computer control system marks the current hammer blow as an abnormal blow and excludes its penetration data from the rate of change calculation. To distinguish between soil transition and abnormal blows, the computer control system also establishes a phase plane with hammer energy as the x-axis and penetration as the y-axis, and sets the data points for each hammer blow accordingly. Plot the data points on the phase plane, selecting the data points from the previous 5 hammer blows as the center, to form a reference point set. Calculate the centroid coordinates of the reference point set. The covariance matrix C is used to determine the distribution ellipse region. If the current data point is outside the ellipse while the previous data point was inside the ellipse, it is marked as an abnormal hammer blow; if both the current and previous data points are outside the ellipse, it is determined to be a soil transition, and the penetration data is included in the calculation normally.

[0102] During pile driving, when the inclinometer detects a real-time pile inclination greater than 0.8% and the computer control system issues a correction command, the computer control system pauses comparing the average penetration per blow with the third preset value and issuing stop commands. The pile hammer continues to strike continuously, without interrupting the pile driving operation due to the correction command. Once the real-time pile inclination detected by the inclinometer returns to less than or equal to 0.8%, the computer control system resumes comparing the average penetration per blow with the third preset value and issuing stop commands, and restarts counting the average penetration per blow for three consecutive rounds of hammering, beginning from the first round.

[0103] When the average penetration depth of each of the three consecutive hammer blows is less than or equal to the adjusted third preset value, the computer control system issues a stop hammer command. Ultimately, all 551 engineering piles in the project were driven, and the pass rate of the pile verticality deviation and the single pile vertical bearing capacity sampling inspection both met the design requirements. Compared to the existing technology that stops hammering and manually corrects deviations when the pile inclination exceeds the limit, in this application example, the computer control system pauses the penetration depth judgment during the correction period while maintaining continuous hammering. This significantly shortens the average driving time for a single engineering pile and greatly improves construction efficiency. During the correction process, the stress in the soil around the pile is no longer redistributed due to the stop hammering. After the correction is completed, the penetration depth data does not need to be re-stabilized before it can be used to continue judging the stop hammering, reducing the number of misjudgments from approximately 8 per 100 piles to approximately 1. Furthermore, due to the continuous hammering during the correction period, the number of corrections per pile decreased from an average of 4.5 to an average of 2.8, and the correction time was shortened from an average of 25 minutes to approximately 15 minutes.

[0104] The number of devices and processing scale described herein are for the purpose of simplifying the description of the invention. Applications, modifications, and variations of the invention will be readily apparent to those skilled in the art.

[0105] Although embodiments of the present invention have been disclosed above, they are not limited to the applications listed in the specification and embodiments. They can be applied to various fields suitable for the present invention. For those skilled in the art, other modifications can be easily made. Therefore, without departing from the general concept defined by the claims and their equivalents, the present invention is not limited to the specific details and embodiments shown and described herein.

Claims

1. A construction control method for the pile driving process, characterized in that, Includes the following steps: Step 1: Install a hammer blow count sensor on the pile hammer, and install an inclinometer and a laser rangefinder on the pile driving equipment. Connect the hammer blow count sensor, inclinometer, and laser rangefinder to the computer control system respectively. Step 2: Hoist the engineering pile into the pile stabilization and positioning platform, and adjust the verticality of the engineering pile by using the jacks on the pile stabilization and positioning platform so that the inclination of the engineering pile is less than or equal to the first preset value. Step 3: Start the pile hammer to drive the engineering pile. During the pile driving process, the real-time pile inclination data of the engineering pile is continuously collected by the inclinometer and sent to the computer control system. The computer control system compares the real-time pile inclination data with the second preset value. When the real-time pile inclination data is greater than the second preset value, the computer control system issues a correction command and adjusts the verticality of the engineering pile by jacking until the real-time pile inclination data is less than or equal to the second preset value. Step 4: While the pile driving is in progress, real-time penetration data is collected by a laser rangefinder and the real-time number of hammer blows is collected by a hammer blow count sensor. The computer control system calculates the average penetration per blow and compares it with the third preset value. When the average penetration per blow of a consecutive preset number of hammer blows is less than or equal to the third preset value, a stop hammer command is issued. Here, a preset number of consecutive hammer blows is a set. Step 5: When the correction command is issued in Step 3, the computer control system pauses the comparison and hammer stop command in Step 4, while maintaining continuous hammering. After the real-time pile inclination data recovers to less than or equal to the second preset value, the system restarts counting the average penetration per blow for a preset number of consecutive hammerings.

2. The construction control method for the pile driving process as described in claim 1, characterized in that, In step four, stress sensors and acceleration sensors are installed on the pile body. The stress sensors are used to collect the time history of the impact force exerted by the pile hammer on the pile during each hammer blow, and the acceleration sensors are used to collect the time history of the acceleration of the pile during each hammer blow. The computer control system obtains the impact impulse of each hammer blow by integrating the impact force time history over time, and obtains the displacement time history of the pile during each hammer blow by integrating the acceleration time history twice over time. The computer control system calculates the input energy of each hammer blow based on the impact force time history and the displacement time history, and calculates the increase in pile potential energy of each hammer blow based on the pile mass and the displacement time history. The computer control system divides the increase in pile potential energy by the input energy for each hammer blow to obtain the energy conversion efficiency for each blow. The computer control system judges the trend of the energy conversion efficiency for each blow. When the energy conversion efficiency of P consecutive hammer blows is less than or equal to the energy conversion efficiency of the previous hammer blow, the computer control system uses the current average penetration per blow as a dynamic reference value, and multiplies the dynamic reference value by a preset proportional coefficient to obtain an adjusted third preset value. The adjusted third preset value replaces the original third preset value for subsequent hammer stop judgment. P is a positive integer greater than or equal to 5.

3. The construction control method for the pile driving process as described in claim 1, characterized in that, In step three, pressure sensors are installed at each jack of the pile stabilization and positioning platform, a first positioning device is installed at the center of the platform, and a second positioning device is installed at the centerline of the pile body. The pressure sensors collect the real-time output pressure of the corresponding jacks, and the first and second positioning devices provide the computer control system with the relative spatial position between the center point of the pile stabilization and positioning platform and the centerline of the pile body. When the computer control system issues a correction command, it calculates the projection position of the resultant force point of each jack's output thrust on the horizontal plane based on the real-time output pressure and spatial distribution of each jack, thus obtaining the real-time thrust center coordinates of the jack array. The computer control system then uses the relative spatial position provided by the first and second positioning devices to... In terms of spatial location, the system calculates the projection position of the pile's centerline onto the horizontal plane to obtain the real-time center coordinates of the pile. The computer control system calculates the horizontal distance between the real-time thrust center coordinates and the real-time pile center coordinates to obtain the thrust-pile center offset. The computer control system compares the thrust-pile center offset with a fourth preset value. When the thrust-pile center offset is greater than the fourth preset value, the computer control system adjusts the output pressure distribution of each jack to move the real-time thrust center coordinates toward the real-time pile center coordinates until the thrust-pile center offset is less than or equal to the fourth preset value. The computer control system uses the pile inclination being less than or equal to a second preset value and the thrust-pile center offset being less than or equal to a fourth preset value as the criteria for completing the correction.

4. The construction control method for the pile driving process as described in claim 2, characterized in that, In step four, the computer control system continuously calculates the rate of change of the average penetration depth per blow between each two adjacent blows during the pile driving process. The method for calculating the rate of change of the average penetration depth per blow is as follows: the difference between the average penetration depth per blow of the current blow and the average penetration depth per blow of the previous blow is divided by the larger value between the average penetration depth per blow of the current blow and the average penetration depth per blow of the previous blow. When both the average penetration depth per blow of the current blow and the average penetration depth per blow of the previous blow are zero, the rate of change of the average penetration depth per blow is set to zero. The computer control system compares the average penetration rate per blow calculated each time with the fifth preset value. When the average penetration rate per blow for N consecutive blows is less than or equal to the fifth preset value, and when the third preset value adjustment condition based on energy conversion efficiency is not triggered, the computer control system uses the current average penetration per blow as a dynamic reference value, and multiplies the dynamic reference value by a preset proportional coefficient to obtain the adjusted third preset value. The adjusted third preset value replaces the original third preset value for subsequent hammer stop judgment. N is a positive integer greater than or equal to 3, and the proportional coefficient ranges from 0.3 to 0.

7.

5. The construction control method for the pile driving process as described in claim 2, characterized in that, In step four, after each hammer blow, the peak moment of the impact force time history curve and the rise time from zero to the peak are determined based on the impact force time history collected by the stress sensor. The round-trip time difference required for the stress wave to travel one round trip along the entire length of the engineering pile is calculated based on the known pile length and pile wave velocity. The ratio of the rise time to the round-trip time difference is calculated to obtain the relative duration coefficient of the impact force. The relative duration coefficient of the impact force is compared with the sixth preset value. When the relative duration coefficient of the impact force is greater than the sixth preset value, the hammer blow is marked as an eccentric hammer blow, and the impact force time history and acceleration time history of the hammer blow are excluded from the calculation of input energy and pile potential energy increment. Hammerings marked as eccentric hammerings are not counted in the count of consecutive P hammerings; the count of P hammerings is carried over to subsequent hammerings that are not marked as eccentric hammerings.

6. The construction control method for the pile driving process as described in claim 3, characterized in that, In step three, when the computer control system issues a correction command and drives all jacks to extend simultaneously, each pressure sensor continuously collects real-time output pressure during the jack extension process and sends it to the computer control system. Taking any two adjacent pressure sensors as a group, the difference in real-time output pressure between the two pressure sensors in the same group is calculated to obtain the pressure difference time history of the group. The peak value of the pressure difference time history of each group is calculated separately, and the peak values ​​of each group are compared with each other. When the difference between the peak value of any group and the average value of the peak values ​​of other groups is greater than the seventh preset value, it is determined that at least one pressure sensor in the group has failed, and a sensor failure alarm is issued.

7. The construction control method for the pile driving process as described in claim 4, characterized in that, In step four, the computer control system continuously records the average penetration per blow and the corresponding hammer energy for each blow during the pile driving process. The computer control system calculates the ratio of the hammer energy to the corresponding average penetration per blow to obtain the energy consumption per unit penetration. When the average penetration per blow is zero, the energy consumption per unit penetration for that blow is not calculated, and the blow is marked as an abnormal blow, and its average penetration per blow is excluded from the calculation of the rate of change of average penetration per blow. The computer control system continuously records the energy consumption per unit penetration, forming a time series of energy consumption per unit penetration. The computer control system calculates the moving average of the energy consumption per unit penetration time series, compares the energy consumption per unit penetration for the current blow with the moving average, and when the difference between the energy consumption per unit penetration for the current blow and the moving average is greater than an eighth preset value, the computer control system marks the current blow as an abnormal blow and excludes its average penetration per blow from the calculation of the rate of change of average penetration per blow.

8. The construction control method for the pile driving process as described in claim 5, characterized in that, In step four, after each hammer blow, the computer control system determines the peak time of the impact force time history curve based on the impact force time history collected by the stress sensor. Starting from this peak time, it sequentially searches for local extreme points on the impact force time history curve, recording the time of occurrence of each local extreme point to obtain an extreme point time sequence. The computer control system calculates the time difference between two adjacent extreme point times in the extreme point time sequence to obtain an extreme point interval sequence. The computer control system then counts the frequency of occurrence of each value in the extreme point interval sequence and records the value with the highest frequency. The value is used as the round-trip time difference required for the stress wave to travel one round trip within the current length range of the engineering pile, replacing the round-trip time difference calculated from the known pile length and pile wave velocity. Among them, when the frequency of occurrence of multiple values ​​is the highest, the smaller value is taken. When the frequency of occurrence of each value in the extreme point interval sequence is lower than the ninth preset value, the computer control system determines that the signal quality of the current hammer blow does not meet the self-calibration requirements, and still uses the round-trip time difference calculated from the known pile length and pile wave velocity as the round-trip time difference. The ninth preset value is a positive integer between 3 and 5.

9. The construction control method for the pile driving process as described in claim 6, characterized in that, In step three, before issuing the correction command, the computer control system first collects the real-time output pressure of each pressure sensor under the current tilt state of the engineering pile, and calculates the difference between the real-time output pressure of two pressure sensors in the same group by taking any two adjacent pressure sensors as a group, so as to obtain the pressure difference of each group before correction. After issuing a correction command and driving each jack to extend, the computer control system again collects the real-time output pressure of each pressure sensor and calculates the difference between the real-time output pressures of two pressure sensors in the same group to obtain the pressure difference time history after correction for each group. The computer control system calculates the ratio of the peak value of the pressure difference time history after correction to the pressure difference before correction for each group to obtain the pressure difference change rate for each group. The computer control system compares the pressure difference change rates of each group with each other. When the difference between the pressure difference change rate of any group and the average value of the pressure difference change rate of other groups is greater than the tenth preset value, the computer control system determines that at least one pressure sensor in that group has failed and issues a sensor failure alarm.

10. The construction control method for the pile driving process as described in claim 7, characterized in that, In step four, the computer control system continuously records the hammering energy and the corresponding average penetration per blow during the pile driving process, and plots the data points of each hammering on the phase plane with hammering energy as the horizontal axis and average penetration per blow as the vertical axis. The computer control system uses the data point of the current hammer blow as the center and selects data points from V previous hammer blows to form a reference point set. If the number of hammer blows is less than V, the current hammer blow is marked as a normal hammer blow. The system calculates the centroid coordinates and covariance matrix of the reference point set in the phase plane and determines the elliptical distribution region of the reference point set based on the covariance matrix. The major and minor axes of the elliptical distribution region are determined by the eigenvectors of the covariance matrix, and the lengths of the major and minor axes are determined by multiplying the eigenvalues ​​of the covariance matrix by a preset multiple, which is between 2 and 3. The computer control system determines whether the data point of the current hammer blow is located inside the elliptical distribution region. If it is, the hammer blow is marked as normal. If the current hammer blow is marked as a normal hammer blow, and the data point of the previous hammer blow is located outside the distribution ellipse area, the system further determines whether the data point of the previous hammer blow is also located outside the distribution ellipse area. If the data point of the previous hammer blow is located inside the distribution ellipse area, the computer control system marks the current hammer blow as an abnormal hammer blow and excludes the average penetration per blow of the current hammer blow from the calculation of the average penetration per blow rate of change. If the data point of the previous hammer blow is also located outside the distribution ellipse area, the computer control system determines that the engineering pile is currently in the soil layer transition stage. The soil layer transition stage refers to the transition process of the pile tip from the current soil layer to the adjacent soil layer. The average penetration per blow of the current hammer blow is included in the calculation of the average penetration per blow rate of change. V is a positive integer greater than or equal to 5.