A single-sided formwork reinforcement system for walls and a pouring construction method
By combining the template panel, supporting frame, embedded connectors and inclined support components, and using the poured concrete slab as the reaction point, the problem of template tilting in single-sided formwork is solved, and the continuity of the waterproof layer and the ease of construction are achieved.
Patent Information
- Application Number
- CN202611555137.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-10-09
- Publication Date
- 2026-11-17
AI Technical Summary
In deep foundation pit engineering, when formwork is supported on one side, the reaction point of the formwork support frame is concentrated on one side of the wall foot, which makes the top formwork of the wall prone to tilting away from the wall. In addition, setting restraint components on the waterproof layer will destroy the continuity of the waterproof layer.
The structure adopts a combination of template panels, supporting frame, pre-embedded connectors, pre-embedded anchors and diagonal supports. The cast-in-place concrete slab is used as the reaction point on the upper part of the supporting frame. It is connected to the supporting frame through pre-embedded connectors. The diagonal supports and the bottom plate anchors form a triangular support to avoid perforation in the waterproof layer.
This method effectively constrains the upper part of the support frame without disrupting the continuity of the waterproof layer, preventing the formwork from tilting away from the wall, ensuring the wall elevation and verticality, simplifying the construction process, and reducing damage to the waterproof layer.
Smart Images

Figure CN123109393A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of building construction technology, and in particular to a single-sided formwork reinforcement system for walls and a pouring construction method. Background Technology
[0002] In deep foundation pit engineering, when the distance between the basement exterior wall to be poured and the foundation pit retaining structure is insufficient and there is no double-sided formwork and working space, it is usually only possible to erect a single formwork from the inside of the exterior wall, and the formwork support frame set on that side bears the lateral pressure during concrete pouring.
[0003] In existing single-sided formwork construction methods, the available reaction points for the formwork support frame are mostly concentrated on one side of the wall base. During the pouring process, the formwork at the top of the wall tends to tilt outwards away from the wall, making it difficult to control the elevation and verticality of the top of the wall.
[0004] To provide additional constraints on the upper part of the formwork, current practices involve installing tie rods or top bracing points on the outer side of the wall. However, the outer side of basement walls is usually covered with a waterproof layer, and the above practices require drilling holes in the waterproof layer and having the components pass through, thus affecting the continuity of the waterproof layer. Summary of the Invention
[0005] The present invention aims to provide a single-sided formwork reinforcement system for walls and a pouring construction method to solve the above-mentioned technical problems.
[0006] The objective of this invention can be achieved by adopting the following technical solution: In a first aspect, the present invention provides a single-sided formwork reinforcement system for a wall, used for single-sided formwork of a wall to be poured, including a template panel, a support frame, pre-embedded connectors, pre-embedded anchors and inclined support members; The lower end of the wall to be poured is located on the already poured base plate, and the upper end is connected to the already poured concrete slab. A construction joint is provided at the joint between the concrete slab and the wall to be poured. The template panel is set against the construction side of the wall to be poured, and the supporting frame is located on the side of the template panel away from the wall to be poured and abuts against the template panel; The pre-embedded connector includes an anchoring section embedded in the concrete slab and an extension section extending out from the construction joint. The extension section passes through the template panel and is fastened to the upper part of the support frame. The pre-embedded anchor is embedded in the base plate and extends from the top surface of the base plate. The lower end of the inclined support is connected to the pre-embedded anchor and the upper end is connected to the support frame. The inclined support extends upward from the pre-embedded anchor toward the wall to be poured to the support frame.
[0007] In some embodiments, a waterproof layer is also included, which covers the bottom surface of the base plate and extends upward along the side of the wall to be poured away from the template panel to the concrete slab, wherein the embedded connectors and the embedded anchors do not penetrate the waterproof layer.
[0008] In some embodiments, the support frame includes uprights extending along the height direction of the wall to be poured, and horizontal ribs arranged on the side of the uprights facing the wall to be poured; the uprights include a plurality of them spaced apart along the length direction of the wall to be poured, and the horizontal ribs include a plurality of them spaced apart along the height direction of the wall to be poured, each of the horizontal ribs extending along the length direction of the wall to be poured, and at least a portion of the horizontal ribs being connected to the corresponding uprights; the template panel is abutted against and fixed to the side of each of the horizontal ribs facing the wall to be poured.
[0009] In some embodiments, the transverse rib is composed of two transverse steel pipes arranged side by side in a vertical direction; the extended section passes through the template panel and is fastened to the uppermost transverse rib.
[0010] In some embodiments, the inclined support extends obliquely upward from its lower end and is connected to the corresponding upright at no less than three connection points via fasteners.
[0011] In some embodiments, two fasteners are provided at each of the three connection locations located below.
[0012] In some embodiments, the pre-embedded anchors are a plurality of those arranged at intervals along the length of the wall to be poured, and the spacing between two adjacent pre-embedded anchors is the same as the spacing between two adjacent uprights along the length of the wall to be poured.
[0013] In some embodiments, the support frame further includes a connecting rod and an adjustable top support, the connecting rod being fixedly connected to the upright; the adjustable top support includes a bracket and an adjusting screw, the bracket supporting the horizontal rib, one end of the adjusting screw being connected to the bracket and the other end being inserted into the end of the connecting rod facing the template panel, and the length of the adjusting screw extending from the connecting rod is adjustable.
[0014] Secondly, the present invention also provides a method for constructing a wall with single-sided formwork, wherein the lower end of the wall to be poured is located on a base plate and the upper end is connected to a concrete slab; the method includes: During the pouring of the base slab, pre-embedded anchors are embedded in the base slab and extend from the top surface of the base slab, with the pre-embedded anchors maintaining a non-penetrating distance from the waterproof layer covering the base slab. During the pouring of the concrete slab, a construction joint is reserved at the junction of the concrete slab and the wall to be poured, and a pre-embedded connector is embedded in the concrete slab. The pre-embedded connector includes an anchoring section and an extension section connected together, so that the anchoring section is anchored in the concrete slab and the extension section extends out from the construction joint. Install a template panel on the construction side of the wall to be poured, so that the protruding section passes through the template panel, and erect a support frame on the side of the template panel away from the wall to be poured, so that the template panel abuts against the support frame; An inclined support is fixedly installed between the support frame and the pre-embedded anchor, so that the inclined support extends obliquely upward from the pre-embedded anchor toward the wall to be poured to the support frame. The protruding section extending from the template panel is fastened to the upper part of the support frame; and After the extended section is fastened to the upper part of the support frame, the concrete of the wall to be poured is poured into the cavity between the template panel and the existing foundation pit sidewall.
[0015] In some embodiments, when pouring concrete for the wall to be poured, concrete is poured simultaneously and symmetrically in layers at two oppositely arranged walls to be poured, and the difference in concrete liquid level between the two walls at each pouring stage is not greater than 500mm.
[0016] The beneficial technical effects of this invention are as follows: Compared with the method of installing tie rods or setting top support fixing points on the outside of the wall, this invention takes the reaction force of the upper part of the support frame from the already poured concrete slab connected to the top of the wall to be poured. The anchoring section of the pre-embedded connector is embedded in the concrete slab during the pouring process, and its protruding section extends out from the construction joint reserved at the junction of the concrete slab and the wall to be poured and enters the construction side. Therefore, the constraint of the upper part of the support frame can be established under the condition that there is no working space between the wall to be poured and the existing foundation pit sidewall. Moreover, the entire process of formwork and reinforcement does not require drilling holes or setting through members in the waterproof layer on the outside of the wall, and the waterproof layer remains continuous.
[0017] Furthermore, the present invention arranges the fastening connection between the extended section and the upper part of the support frame after the support frame has been erected and the inclined support has been installed. The pouring of the concrete to be poured is arranged after this fastening connection, so that the verticality of the template panel and the assembly gap inside the support frame can be corrected and eliminated before fastening, reducing the additional effect on the fastening connection caused by forcibly correcting the position of the template. Attached Figure Description
[0018] To more clearly illustrate the technical solutions of the embodiments of the present invention, the accompanying drawings used in the description of the embodiments will be briefly introduced below. Obviously, the accompanying drawings described below show some embodiments of the present invention. For those skilled in the art, other drawings can be obtained based on these drawings without creative effort.
[0019] Figure 1 This is a structural schematic diagram of the single-sided formwork reinforcement system for walls provided in an embodiment of the present invention; Figure 2 for Figure 1 A partially enlarged schematic diagram of the junction between the upper part of the wall to be poured and the concrete slab; Figure 3 This is a schematic diagram of the structure of the support frame connected to the template panel via an adjustable top support, as provided in an embodiment of the present invention. Figure 4 A schematic diagram of the connection structure between the inclined support member, the upright, and the pre-embedded anchor provided in an embodiment of the present invention; Figure 5 This is a schematic diagram of the overall structure of the single-sided formwork reinforcement system for walls provided in this embodiment of the invention when used for two oppositely arranged walls to be poured. Figure 6 This is a schematic flowchart of a wall single-sided formwork casting construction method provided in an embodiment of the present invention.
[0020] Explanation of reference numerals in the attached figures: In the diagram: 10-Wall to be poured, 20-Formwork panel, 30-Support frame, 31-Upright pole, 32-Horizontal rib, 321-First horizontal steel pipe, 322-Second horizontal steel pipe, 33-Adjustable top support, 331-Support base, 332-Adjusting screw, 34-Connecting rod, 40-Embedded connector, 41-Anchoring section, 42-Extended section, 43-Fastener, 50-Embedded anchor, 60-Inclined support, 70-Base plate, 80-Concrete slab, 90-Construction joint, 100-Waterproof layer, 110-Existing foundation pit sidewall. Detailed Implementation
[0021] The technical solutions of the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some, not all, of the embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of the present invention.
[0022] It should be understood that, when used in this specification and the appended claims, the terms "comprising" and "including" indicate the presence of the described features, integrals, steps, operations, elements and / or components, but do not exclude the presence or addition of one or more other features, integrals, steps, operations, elements, components and / or collections thereof.
[0023] It should also be understood that the terminology used in this specification is for the purpose of describing particular embodiments only and is not intended to limit the invention. As used in this specification and the appended claims, the singular forms “a,” “an,” and “the” are intended to include the plural forms unless the context clearly indicates otherwise.
[0024] It should also be further understood that the term "and / or" as used in this specification and the appended claims refers to any combination of one or more of the associated listed items and all possible combinations, and includes such combinations.
[0025] When there is no space for formwork erection and operation between the wall to be poured and the existing foundation pit sidewall located on its outer side, the wall to be poured can only be erected on one side of the inner side. In this case, the formwork support frame cannot be balanced by tie members that penetrate the wall to be poured, and its available reaction points are concentrated on one side of the wall foot. The upper section of the support frame along the height of the wall to be poured lacks restraint, and the formwork is prone to tilting outward away from the wall to be poured under the lateral pressure of the concrete. At the same time, the side of the wall to be poured away from the construction side is usually covered with a waterproof layer, and it is not allowed to install tie members or top support fixing points on this side by drilling, piercing or other penetrating methods, further compressing the available force-taking positions.
[0026] In this embodiment of the invention, the pre-cast concrete slab connected to the upper end of the wall to be poured serves as the source of reaction force for the upper part of the supporting frame. During the pouring of this concrete slab, connectors are pre-embedded, and a construction joint is reserved at the junction of the concrete slab and the wall to be poured. One end of the connector is anchored within the concrete slab, and the other end extends from the construction joint and is securely connected to the upper part of the supporting frame. The lower part of the supporting frame is connected via inclined supports to anchors pre-embedded during the pouring of the base slab and extending from the top surface of the base slab. Thus, without requiring any drilling work on the side of the wall to be poured facing the existing foundation pit sidewall, the upper part of the supporting frame is constrained by the pre-cast concrete slab, and the outward tilt of the top of the formwork panel away from the wall to be poured is limited.
[0027] See Figure 1 This invention provides a single-sided formwork reinforcement system for a wall, used for single-sided formwork support of a wall 10 to be poured. The reinforcement system includes a formwork panel 20, a support frame 30, embedded connectors 40, embedded anchors 50, and inclined support members 60.
[0028] The lower end of the wall 10 to be poured is located on the already poured base slab 70, and the upper end connects with the already poured concrete slab 80. That is, the concrete slab 80 is located at the elevation of the top of the wall 10 to be poured and is poured before the wall 10. When the base slab 70 is poured, a vertical wall root section can be poured upwards at its edge facing the existing foundation pit sidewall 110. The top surface of this wall root section is where the lower end of the wall 10 to be poured is located, and it is also the horizontal interface formed by the staged pouring of the base slab 70 and the wall 10 to be poured. A construction joint 90 is provided at the junction of the concrete slab 80 and the wall 10 to be poured. The construction joint 90 is the interface formed by the staged pouring of the concrete slab 80 and the wall 10 to be poured, and it is reserved when the concrete slab 80 is poured; this interface runs vertically from the top surface of the concrete slab 80 to its bottom surface. Accordingly, the wall to be poured 10 includes a wall body extending along the height direction and a top horizontal section extending from the top of the wall body away from the construction side along the thickness direction to the top of the interface, with an inverted L-shaped cross section; the concrete of the wall to be poured 10 is poured to the interface and connected with the concrete slab 80.
[0029] The wall 10 to be poured has two opposing sides along its thickness. The side facing away from the existing pit sidewall 110, providing formwork and working space, is the construction side; the side facing the existing pit sidewall 110 lacks working space, therefore the wall 10 to be poured can only be formed from the construction side alone. The existing pit sidewall 110 refers to the surface of the pit retaining structure facing the wall 10 to be poured, such as slope protection piles, diaphragm walls, pile banks with shotcrete and anchor layers, or the surface of a pre-formed soil nailing wall slope facing the wall 10 to be poured. Figure 1 In the illustrated embodiment, the existing foundation pit sidewall 110 is formed by the surface of the slope protection pile facing the wall 10 to be poured. The top of the slope protection pile abuts the bottom surface of the concrete slab 80, and its shaft passes downward through the elevation of the bottom slab 70 and is embedded in the soil layer below the bottom surface of the bottom slab 70. The side of the wall 10 to be poured facing the existing foundation pit sidewall 110 is attached to the existing foundation pit sidewall 110 through a waterproof layer 100, and there is no space between the two for formwork erection and operation. The space between the formwork panel 20 and the existing foundation pit sidewall 110 constitutes the cavity to be filled by the concrete of the wall 10 to be poured.
[0030] For ease of description, the horizontal direction extending along the wall surface of the wall to be poured 10 is called the length direction, the direction from the bottom plate 70 to the concrete slab 80 is called the height direction, and the direction connecting the construction side and the existing foundation pit sidewall 110 is called the thickness direction.
[0031] The formwork panel 20 is installed against the construction side of the wall 10 to be poured, to form the cavity and to bear the lateral pressure applied by the concrete of the wall 10 before pouring and initial setting. The support frame 30 is located on the side of the formwork panel 20 away from the wall 10 to be poured and abuts against the formwork panel 20.
[0032] The term "abutting" here refers to the abutting of the supporting frame 30 towards the formwork panel 20 and the back of the formwork panel 20 against each other. This allows the lateral pressure on the formwork panel 20 to be transmitted to the supporting frame 30 via this abutting part, whereby the supporting frame 30 assumes the supporting function behind the panel. Abutting does not preclude the possibility of a separate fixed connection between the two: in some implementations, in addition to abutting against the supporting frame 30, the formwork panel 20 can also be fixed to the supporting frame 30 towards the wall 10 to be poured via nails, bolts, or clamps to prevent the formwork panel 20 from warping at the joints. Therefore, abutting describes the force transmission relationship between the two, while a fixed connection is one specific implementation.
[0033] The supporting frame 30 can take various forms, such as a frame composed of vertical members extending along the height direction and horizontal members extending along the length direction, or a truss-type back rib, steel vertical ribs combined with timber horizontal ribs, etc.
[0034] The embedded connector 40 includes an anchoring section 41 and an extended section 42 connected together. The anchoring section 41 is embedded in the concrete slab 80, and the extended section 42 extends out from the construction joint 90. The embedded connector 40 can be a straight rod extending horizontally along the thickness direction of the wall 10 to be poured, with its anchoring section 41 located on the side of the construction joint 90 away from the wall 10 to be poured and embedded in the concrete slab 80, and its extended section 42 extending horizontally from the interface of the construction joint 90 and entering the construction side of the wall 10 to be poured.
[0035] The term "embedding" here refers to the anchoring section 41 being inserted into the reinforcement of the concrete slab 80 before the concrete slab 80 is poured, and being formed in one step along with the pouring of the concrete slab 80. The outer surface of the anchoring section 41 is bonded to the concrete slab 80 along its entire embedded length. This method differs from the post-installation method, which involves drilling holes in the already formed component and then inserting the anchor: the anchoring force of the post-installation method depends on the quality of the hole and the grouting material, and the drilling position is constrained by the reinforcement of the already formed component; while the anchoring section 41 is formed in one step along with the concrete slab 80, and its position can be precisely positioned according to the predetermined arrangement of the support frame 30 during the reinforcement stage of the concrete slab 80.
[0036] The extended section 42 extends from the construction joint 90, passes through the formwork panel 20, and is securely connected to the upper part of the support frame 30. The upper part of the support frame 30 refers to the upper section of the support frame 30 along the height direction of the wall 10 to be poured, that is, the section close to the concrete slab 80 in the height direction, and is not limited to the upper end of any single member of the support frame 30; as long as the secure connection falls within this upper section, it can restrain the outward tilt of the top of the formwork panel 20. It should be noted that the support frame 30 refers to the entire member system located on the side of the formwork panel 20 away from the wall 10 to be poured, bearing and transmitting the lateral pressure of the concrete transmitted from the formwork panel 20; members falling within the aforementioned upper section and directly supporting the formwork panel 20, regardless of whether they are directly connected to or connected via the formwork panel 20, are all part of the support frame 30. A through hole is provided on the template panel 20 at a position corresponding to the extension section 42 for the extension section 42 to pass through. The position of the through hole can be determined according to the actual position of the extension section 42.
[0037] The extended section 42 can be fastened to the upper part of the support frame 30 via fasteners 43. Fasteners 43 can be, for example, nuts that thread with the extended section 42, or connecting plates or wedge pins that snap onto the end of the extended section 42. In the implementation using nuts, a washer can be added between the nut and the support frame 30 to increase the bearing area.
[0038] The pre-embedded anchor 50 is embedded in the base plate 70 and extends from the top surface of the base plate 70. Similar to the anchoring section 41, the pre-embedded anchor 50 is also placed during the casting of the base plate 70 and is formed in one piece with the base plate 70, so there is no need to drill holes in the already formed base plate 70.
[0039] The lower end of the inclined support member 60 is connected to the pre-embedded anchor 50, and the upper end is connected to the support frame 30. The inclined support member 60 extends obliquely upward from the pre-embedded anchor 50 toward the wall 10 to be poured to the support frame 30. That is, the pre-embedded anchor 50 is spaced a distance from the formwork panel 20 in the thickness direction, and the inclined support member 60 extends obliquely upward from this point and overlaps with the support frame 30. The axis of the inclined support member 60 forms an angle with the top surface of the base plate 70. This angle can be selected according to the height of the support frame 30 and the available working width on the base plate 70, and is determined according to the design.
[0040] When concrete for the wall 10 to be poured is poured into the cavity between the formwork panel 20 and the existing foundation pit sidewall 110, the concrete exerts a lateral pressure on the formwork panel 20 in the thickness direction away from the wall 10 to be poured. This lateral pressure is transmitted to the support frame 30 through the part where the formwork panel 20 abuts against the support frame 30, and forms a tendency on the support frame 30 to flip over, causing it to move away from the wall 10 to be poured.
[0041] At the lower part of the support frame 30, the inclined support member 60 is compressed along its axial direction and transmits the force to the base plate 70 through the pre-embedded anchor 50. The support frame 30, the base plate 70 and the inclined support member 60 form a triangular support relationship to limit the displacement of the lower part of the support frame 30 along the thickness direction.
[0042] At the upper part of the support frame 30, this tendency is constrained by the fastening connection between the extension section 42 and the support frame 30: the extension section 42 thus bears a force away from the direction of the wall to be poured 10, which is transmitted to the concrete slab 80 through the bond between the anchor section 41 and the concrete slab 80. The construction joint 90 is a vertical interface from which the extension section 42 extends horizontally and passes through the template panel 20, its axial direction being consistent with the direction of the aforementioned force it bears. After the extension section 42 is fastened to the upper part of the support frame 30, the fastener 43 presses the upper part of the support frame 30 along the axial direction of the extension section 42, restricting its outward movement away from the wall to be poured 10 in the thickness direction; the rod body of the extension section 42 passes through the through hole of the template panel 20 and is connected to the upper part of the support frame 30 at the fastening point, using its cross-section to restrict the displacement of the template panel 20 and the upper part of the support frame 30 in the height direction, such as floating during the pouring process. Therefore, this constraint has components in both the thickness and height directions. The protruding section 42 can also extend obliquely at a certain angle to the horizontal direction, as long as it can pass through the template panel 20 and be securely connected to the upper part of the support frame 30.
[0043] In existing single-sided formwork structures, the available reaction points of the supporting frame are concentrated on one side of the wall base, and the upper section lacks constraints. The conventional approach to set additional constraint points for the upper section is to insert tie rods or set top support fixing points on the outside of the wall, but this is difficult to implement when the outside of the wall is covered with a waterproof layer and there is no working space. The main effect of this reinforcement system lies in the force-taking method of the upper constraint: the anchoring section 41 of the pre-embedded connector 40 is embedded in the concrete slab 80 connected to the top of the wall 10 to be poured, and its protruding section 42 extends out from the construction joint 90 interface between the concrete slab 80 and the wall 10 to be poured and enters the construction side. Therefore, the reaction force required by the upper part of the support frame 30 is directly transmitted to the poured concrete slab 80 through the anchoring section 41 and is borne by the slab body of the concrete slab 80. It is not necessary to set up beams, corbels or other special anchoring components on the top of the wall 10 to be poured, nor is it necessary to arrange any components between the wall 10 to be poured and the existing foundation pit sidewall 110, and there is no need to carry out drilling or installation work on this side. Therefore, the reinforcement system can still be implemented when there is no working space between the wall to be poured 10 and the existing foundation pit sidewall 110; after the concrete of the wall to be poured 10 reaches the design strength and the formwork is removed, the protruding section 42 can be cut off from the wall surface of the wall to be poured 10, leaving no exposed components on the wall surface.
[0044] Furthermore, the working conditions upon which this power-taking method depends are also relevant. When the top of the wall 10 to be poured is connected to the already poured concrete slab 80, the constraint on the upper part of the supporting frame 30 can be provided by anchoring, i.e., by the pre-embedded connectors 40 embedded in the concrete slab 80 bearing tensile force. Conversely, when there is no already poured component at the top of the wall to be poured, the constraint on its upper part must be provided by support from other parts, with struts bearing compressive force, and additional support objects and corresponding space are required. The objects of force taking and the nature of the forces are different in these two cases.
[0045] The concrete slab 80 can be a raft slab, or a structural base slab, basement slab, water tank top slab, or top panel of a foundation, etc., which are cast in advance of the wall 10 to be poured and whose upper end is connected to it.
[0046] The embedded connector 40 can be a threaded rod with an external thread at the end of its extended section 42, which is then fastened with a nut; it can also be a hooked steel bar with a connecting plate welded to the end of its extended section 42 and connected to the support frame 30; or it can be an anchor bolt with an anchor plate at one end, connected to the support frame 30 by a high-strength bolt. Regarding the relationship between the anchoring section 41 and the extended section 42, the embedded connector 40 can be an integral type consisting of two sections of the same rod body, or it can be a separate type where the anchoring section 41 and the extended section 42 are two independent rods connected by a sleeve. When using a split design, the anchoring section 41 can be embedded first when the concrete slab 80 is poured. After the side formwork is removed and the extended end of the anchoring section 41 is exposed, the extended section 42 is then connected. Then, according to the actual position of the extended section 42, the template panel 20 is laid out and the template panel 20 is positioned. The length of the extended section 42 can be selected according to the actual measured distance from the extended end of the anchoring section 41 to the designed position of the template panel 20, so as to match the installation position of the template panel 20.
[0047] The pre-embedded anchor 50 can be a steel bar head, a U-shaped anchor ring, an anchor plate, or an anchor bolt with an anchoring end; all of the above forms are placed before the bottom plate 70 is poured and formed in one go with the bottom plate 70, and the form of drilling holes in the already formed bottom plate 70 and then placing it is not adopted.
[0048] The diagonal support 60 can be a single steel pipe diagonal brace, or a double-splitting steel pipe diagonal brace composed of two parallel steel pipes, a steel profile diagonal brace, or an adjustable support with an adjusting screw.
[0049] The wall 10 to be poured can be a single wall or two walls arranged opposite each other within the same foundation pit. In this case, the construction sides of the two walls 10 to be poured face each other, and each is equipped with the aforementioned reinforcement system, such as... Figure 5 As shown.
[0050] Based on the above specific implementation, in some optional implementations, the support frame 30 is composed of rods extending in different directions, so as to provide connection points for the pre-embedded connector 40 and the inclined support 60 while bearing the lateral pressure transmitted by the template panel 20.
[0051] See Figure 3 The supporting frame 30 includes uprights 31 extending along the height of the wall 10 to be poured, and horizontal ribs 32 arranged on the side of the uprights 31 facing the wall 10 to be poured. The uprights 31 include a plurality of ribs spaced apart along their length, and the horizontal ribs 32 include a plurality of ribs spaced apart along their height, each horizontal rib 32 extending along its length. At least a portion of each horizontal rib 32 is connected to the corresponding upright 31. This connection can be direct or indirect, as described below, via an adjustable top support 33 and a connecting rod 34. The uppermost horizontal rib 32 can also be connected to the upright 31, or it can be located above the top of the upright 31 without direct connection to it. In this case, the horizontal rib 32 is connected to the horizontal ribs 32 below it and the uprights 31 via the template panel 20 to form a whole. The template panel 20 is abutted against and fixed to the side of each horizontal rib 32 facing the wall 10 to be poured.
[0052] Therefore, the lateral pressure borne by the formwork panel 20 is first distributed along the height direction to each horizontal rib 32, then distributed along the length direction by the horizontal rib 32 to each vertical pole 31, and finally transmitted from the vertical pole 31 to the inclined support 60, and from the upper horizontal rib 32 through the extension section 42 to the concrete slab 80. The horizontal rib 32 is located between the vertical pole 31 and the formwork panel 20, and is the force transmission link between the formwork panel 20 and the vertical pole 31; the vertical pole 31 does not directly contact the formwork panel 20, and a distance equivalent to the outer contour dimension of the horizontal rib 32 and the distance required for its connection structure is maintained between them along the thickness direction.
[0053] The spacing between two adjacent uprights 31 along the length direction is, for example, 900 mm. The spacing between two adjacent horizontal ribs 32 along the height direction is, for example, 458 mm. The template panel 20 and the horizontal ribs 32 can be fixed together, for example, by self-tapping screws, butterfly clips, or pressure strips.
[0054] The main body of the support frame 30 can be, for example, a disc-lock scaffold. The uprights 31 are the uprights of this scaffold, and each upright 31 is connected by a horizontal bar extending along its length (not separately labeled in the attached drawings) to form a whole. This horizontal bar is used to maintain the relative position between the uprights 31 and is not the same component as the transverse ribs 32 supporting the formwork panel 20. The support frame 30 can consist of only one row of uprights 31 arranged along its length, or it can include multiple rows of uprights 31 spaced apart along its thickness. Adjacent rows of uprights 31 are connected by horizontal bars extending along their thickness, and the spacing between each row of uprights 31 along its length is the same. In the implementation with multiple rows of uprights 31, the row of uprights 31 closest to the formwork panel 20 is connected to the transverse ribs 32. The transverse ribs 32 are attached to the side of the scaffold facing the formwork panel 20 and are also part of the support frame 30.
[0055] See Figure 2 In a further implementation, the horizontal rib 32 is composed of two transverse steel pipes arranged adjacent to each other in the vertical direction, namely the first transverse steel pipe 321 and the second transverse steel pipe 322. "Adjacent to each other" means that the two transverse steel pipes are arranged close to each other in the vertical direction, either abutting against each other or with a gap smaller than the outer diameter of the transverse steel pipes to allow the extended section 42 to pass through. The axes of the two transverse steel pipes extend along their length and are parallel to each other. When arranged adjacent to each other, they jointly support the formwork panel 20, so that the load transmitted from the formwork panel 20 is borne by both transverse steel pipes. The bending bearing capacity and bending stiffness of the horizontal rib 32 are correspondingly greater than those of a single transverse steel pipe. Simultaneously, in an implementation without the adjustable top support 33, the clamping position formed between the two transverse steel pipes in the vertical direction allows fasteners to be inserted from the outside and connected to the upright 31.
[0056] The extended section 42 passes through the formwork panel 20 and is securely connected to the uppermost horizontal rib 32. The uppermost horizontal rib 32 is closest to the concrete slab 80 in the height direction, and its distance from the top of the formwork panel 20 is minimal. Therefore, securing the extended section 42 to this horizontal rib 32 ensures that the restraint point is as close as possible to the top of the formwork panel 20 where it experiences the greatest outward tilting tendency. Simultaneously, after extending from the back of the formwork panel 20, the extended section 42 only needs to pass over the outer contour of the horizontal rib 32 to engage with the fastener 43; its required extension length is less than the length required when fastening to the upright 31. The length of the extended section 42 extending beyond the back of the formwork panel 20 should meet the assembly requirements of the horizontal rib 32 and the fastener 43. The uppermost horizontal rib 32 can be located above the top of the upright 31 and connected to the upright 31 without the adjustable top support 33. At this time, the position of the horizontal rib 32 along the thickness direction is determined by the template panel 20 and the extended section 42. After the extended section 42 is tightened, the horizontal rib 32, together with the top of the template panel 20, is locked to the concrete slab 80. In addition, the elevation of the extended section 42 is determined when the concrete slab 80 is poured, and each horizontal rib 32 is installed from bottom to top, and its elevation accumulates along the height direction. Therefore, the uppermost horizontal rib 32 is positioned according to the actual measured elevation of each extended section 42, and the distance between the horizontal rib 32 and the adjacent horizontal rib 32 below it is determined according to the actual measurement result, without being constrained by the distance between the other horizontal ribs 32, so that each extended section 42 falls on the tightened position of the horizontal rib 32.
[0057] In the implementation method using double transverse steel pipes, the extended section 42 can pass through the gap between the first transverse steel pipe 321 and the second transverse steel pipe 322, and clamp the two transverse steel pipes simultaneously with the nut and the washer, so that the clamping force applied by the fastener 43 is borne by the two transverse steel pipes together.
[0058] Based on the above specific implementation method, the specific implementation method of the anchoring section 41 of the pre-embedded connector 40 in the concrete slab 80 is further explained as follows.
[0059] See Figure 2 In addition to bonding with the concrete slab 80, the anchoring section 41 is also connected to the reinforcing steel bars within the concrete slab 80. This connection can be achieved by welding or binding.
[0060] The embedment length and anchoring structure of the anchoring section 41 within the concrete slab 80 are determined according to the design. The position of the anchoring section 41 within the concrete slab 80 falls within the slab thickness range, and a distance of not less than the thickness of the concrete cover is maintained between it and the upper and lower surfaces of the concrete slab 80.
[0061] The extended section 42 extends from the construction joint 90. The construction joint 90 is a vertical interface extending from the top surface of the concrete slab 80 to its bottom surface along the height direction. The distance between this interface and the side of the wall away from the construction side along the thickness direction is, for example, 200 mm. The top horizontal section of the wall 10 to be poured extends from the top of the wall away from the construction side along the thickness direction to this interface. The lower part of the section extending beyond the wall is supported by the top surface of the retaining structure constituting the existing foundation pit sidewall 110 through the waterproof layer 100. Thus, the wall and the top horizontal section form an inverted L-shaped cross-section cast in one go, while the concrete slab 80 is cast first in this pour. The anchoring section 41 is embedded in the concrete slab 80, and the extended section 42 extends horizontally from the aforementioned vertical interface and passes through the top of the top horizontal section and the top of the wall in sequence to reach the formwork panel 20. In addition to the construction joint 90 at the junction of the wall 10 and the concrete slab 80, the lower end of the wall 10 to be poured also has a horizontal interface at the junction of the wall 10 and the base slab 70. This interface is located, for example, 915mm above the top surface of the base slab 70, that is, the top surface of the wall root section that is poured together with the base slab 70 during the pouring.
[0062] The pre-embedded connectors 40 can be multiple ones arranged at intervals along the length direction. The spacing between two adjacent pre-embedded connectors 40 is, for example, the same as the spacing between two adjacent uprights 31 along the length direction, so that the upper part of the support frame 30 is provided with constraint points in the vertical plane where each upright 31 arranged along the length direction is located.
[0063] In the implementation method using a split-type pre-embedded connector 40, the extended end of the anchoring section 41 is provided with an internally threaded sleeve or an externally threaded joint, and the corresponding end of the extended section 42 is screwed into it. The length of the extended section 42 can be selected according to the actual measured distance from the extended end of the anchoring section 41 to the designed position of the template panel 20, so as to adapt to the installation position of the template panel 20.
[0064] Based on the above specific implementation, in some optional implementations, the support frame 30 also includes a connecting rod 34 and an adjustable top support 33, which are used to adjust the position of the template panel 20 relative to the upright 31 after the crossbeam 32 is in place.
[0065] See Figure 3 The adjustable top support 33 includes a support 331, an adjusting screw 332, and an adjusting nut (not individually labeled in the drawings). The support 331 supports the horizontal rib 32. One end of the adjusting screw 332 is connected to the support 331, and the other end is inserted into the end of the connecting rod 34 facing the template panel 20. The adjusting nut is screwed onto the adjusting screw 332 and is located between the support 331 and that end of the connecting rod 34. The connecting rod 34 extends along the thickness direction and is fixedly connected to the uprights 31 by fasteners or other fasteners. It is not the same component as the aforementioned horizontal rod that connects the uprights 31 into a whole.
[0066] The support 331 is, for example, a groove-shaped support. Its base plate is connected to the end of the adjusting screw 332 and is perpendicular to the axis of the adjusting screw 332. The upper and lower wing plates extend from the base plate along the thickness direction toward the wall 10 to be poured, forming a groove between the two wing plates with an opening toward the wall 10 to be poured. The transverse rib 32 is accommodated in the groove. When the transverse rib 32 is composed of two transverse steel pipes, both transverse steel pipes are accommodated together in the groove. The two wing plates prevent the transverse rib 32 from dislodging from the support 331 along the height direction. Rotating the adjusting nut to move it along the adjusting screw 332 changes the length of the adjusting screw 332 extending from the connecting rod 34. The support 331 moves accordingly along the thickness direction, and the distance between the transverse rib 32 and the upright rod 31 along the thickness direction changes accordingly. After adjustment, the threaded engagement between the adjusting nut and the adjusting screw 332 maintains the distance automatically. During pouring, the adjusting nut abuts against the end face of the connecting rod 34. The lateral pressure from the template panel 20 is transmitted sequentially through the support 331, the adjusting screw 332 and the adjusting nut to the connecting rod 34, and then from the connecting rod 34 to the upright 31.
[0067] The adjusting nut may be equipped with a handle for easy turning. Turning the handle will cause the adjusting nut to be screwed in or out along the adjusting screw 332.
[0068] The function of the adjustable top support 33 is as follows: before the extended section 42 is fastened to the upper part of the support frame 30, the adjustable top support 33 can be adjusted one by one, so that each horizontal rib 32 and the template panel 20 it supports can move along the thickness direction to a position that matches the designed wall position, ensuring that the verticality of the template panel 20 meets the requirements and eliminating the original assembly gap between the horizontal rib 32 and the upright 31. Afterwards, the extended section 42 is fastened to the upper part of the support frame 30. During the fastening process, it is not necessary to forcibly pull the support frame 30 with the fastener 43 to correct the positional deviation of the template panel 20; thus, the additional effect on the fastening connection caused by forcibly correcting the template position is reduced.
[0069] Based on the above specific embodiments, in some optional implementations, the support frame 30 includes multiple rows of uprights 31 arranged at intervals along the thickness direction, and the inclined support member 60 is not connected to the support frame 30 at only one place.
[0070] See Figure 4The inclined support member 60 extends obliquely upward from its lower end and is connected to the corresponding upright 31 at no less than three connection points via fasteners (not separately labeled in the attached drawings). Since the inclined support member 60 extends obliquely upward from the pre-embedded anchor 50 toward the wall 10 to be poured, it passes sequentially through rows of uprights 31 arranged at intervals along the thickness direction during its extension, and a connection point can be set at each of these points. Fasteners are installed at no less than three such connection points, connecting the inclined support member 60 to the corresponding upright 31 at each location. Therefore, the inclined support member 60 spans no less than three rows of uprights 31. The fasteners are, for example, swivel fasteners, with one end clamping the inclined support member 60 and the other end clamping the upright 31.
[0071] The spacing between adjacent rows of uprights 31 along the thickness direction is, for example, 900mm, and the spacing for some rows can be adjusted to 1200mm according to the site dimensions. Two inclined supports 60 can be installed, with lengths, for example, 3.0m and 3.5m respectively. The distances along the thickness direction between the lower ends of the two inclined supports 60 and the wall 10 to be poured are, for example, 2500mm and 2600mm respectively. The inclined supports 60 can, for example, be composed of two parallel steel pipes.
[0072] In a further implementation, two fasteners are provided at each of the three connection points located below to improve the reliability of the connection and limit the slippage of the inclined support 60 relative to the upright 31.
[0073] Based on the above specific implementation, in some optional implementations, the pre-embedded anchors 50 are multiple ones arranged at intervals along the length direction of the wall 10 to be poured, and the spacing between two adjacent pre-embedded anchors 50 is the same as the spacing between two adjacent uprights 31 along the length direction, for example, both are 900mm.
[0074] With each pre-embedded anchor 50 and its corresponding upright 31 aligned in the same vertical plane, the pre-embedded anchors 50 on the base plate 70 located in this vertical plane correspond one-to-one with each inclined support 60. Each inclined support 60 is thus positioned within this vertical plane, with its lower pre-embedded anchor 50, the uprights 31 connected along its path, and its upper connecting portion all falling within the same vertical plane. The force transmitted by the inclined support 60 is therefore transmitted along this vertical plane, preventing eccentricity along the length of the support frame 30.
[0075] Based on the above specific implementation methods, in some optional implementation methods, the reinforcement system also includes a waterproof layer 100.
[0076] See Figure 1The waterproof layer 100 covers the bottom surface of the base slab 70 and extends upward along the side of the wall 10 to be poured away from the formwork panel 20 to the concrete slab 80. That is, the waterproof layer 100 extends horizontally from the bottom surface of the base slab 70 to the edge of the base slab 70, wraps around the side of the base slab 70 at the edge, and then turns upward. It extends vertically upward continuously along the side of the wall 10 to be poured facing the existing pit sidewall 110 to the elevation of the bottom surface of the concrete slab 80, and then turns away from the wall 10 to be poured. It extends horizontally along the top horizontal section of the wall 10 to be poured and the bottom surface of the concrete slab 80 and covers the top surface of the retaining structure that constitutes the existing pit sidewall 110. The horizontal and vertical sections of the waterproof layer 100 are connected sequentially and there is a continuous transition between adjacent sections, thereby forming a continuous waterproof interface between the wall to be poured 10 and the existing foundation pit sidewall 110, as well as between the top horizontal section of the wall to be poured 10, the concrete slab 80 and the retaining structure below it.
[0077] Neither the embedded connector 40 nor the embedded anchor 50 penetrates the waterproof layer 100. Regarding the embedded connector 40, the anchoring section 41 is embedded within the concrete slab 80, and the extended section 42 extends out from the construction joint 90 and enters the construction side of the wall 10 to be poured. The entire length of the embedded connector 40 is located above a section of the waterproof layer 100 extending horizontally along the bottom surface of the concrete slab 80, spaced apart from and approximately parallel to this section in the height direction, and does not intersect with the waterproof layer 100. Regarding the embedded anchor 50, it is embedded within the base slab 70 and extends from the top surface of the base slab 70. A gap is maintained in the height direction between its embedded end and the waterproof layer 100 on the bottom surface of the base slab 70.
[0078] Since the lower end of the inclined support 60 is connected to the pre-embedded anchor 50 pre-embedded during the pouring of the base plate 70, rather than the anchor installed by drilling holes in the already formed base plate 70, and the upper part of the support frame 30 is constrained by the extended section 42 extending from the construction joint 90, it is not necessary to drill holes, puncture or install penetrating components in the waterproof layer 100 during the entire process of formwork installation, frame erection, and inclined brace installation and fastening. The waterproof layer 100 remains continuous and intact and will not form a leakage channel due to penetration.
[0079] The following section uses a single-sided formwork support for the side wall of a pit within a pit as an example to further illustrate the above specific implementation method.
[0080] In a deep pit project for stage machinery in a theater, a sunken pit-within-a-pit is constructed within the existing pit. The top surface of the bottom slab 70 of the pit-within-a-pit is at an elevation of -20.02m. The basement exterior wall surrounding the pit-within-a-pit, i.e., the wall 10 to be poured, terminates upwards at an elevation of -14.24m on a pre-cast raft slab, which is the concrete slab 80. The single-sided formwork height is approximately 5.78m. The side of the wall 10 to be poured, facing the existing pit sidewall 110, is adjacent to the retaining piles, and there is no space for formwork erection or operation between them. Therefore, the wall 10 to be poured can only be erected from the inside of the pit-within-a-pit on one side.
[0081] When the base slab 70 is poured, 14mm diameter steel bars are pre-embedded in the base slab 70 at 900mm intervals along the length direction as pre-embedded anchors 50. Two anchors are pre-embedded at each length position, extending from the top surface of the base slab 70. The distances along the thickness direction between the protruding positions and the wall surface of the wall 10 to be poured on the construction side are 2500mm and 2600mm, respectively, corresponding to the lower ends of the two diagonal support members 60. When the concrete slab 80 is poured, a vertical construction joint 90 is reserved 200mm away from the side of the wall away from the construction side; at the same time, 14mm diameter threaded rods are pre-embedded in the concrete slab 80 as pre-embedded connectors 40. The anchoring section 41 of the threaded rod is lapped and welded to the steel bars arranged along the length direction in the steel mesh of the concrete slab 80, and the protruding section 42 extends horizontally from the construction joint 90.
[0082] During formwork erection, the formwork panel 20 is positioned against the construction side of the wall 10 to be poured, and the extended section 42 protrudes through the pre-laid through hole on the formwork panel 20. Horizontal ribs 32 are arranged from bottom to top on the back side of the formwork panel 20, each rib 32 consisting of two adjacent steel pipes with an outer diameter of 48mm. The main body of the supporting frame 30 is a disc-lock scaffold, fully distributed between the two walls 10 to be poured, arranged opposite each other in the same direction. The uprights 31 are spaced 900mm along the length direction and arranged in 900mm×6 spans, 1200mm×1 span, and 900mm×6 spans along the thickness direction. The supporting frame 30 of the two walls 10 to be poured is connected into a whole by this scaffold. Except for the topmost horizontal rib 32, all other horizontal ribs 32 are connected to the uprights 31 via adjustable top supports 33 and connecting rods 34. The topmost horizontal rib 32 is located above the top of the upright 31, and its position along the thickness direction is determined by the template panel 20 and the extended section 42. Two diagonal supports 60 are provided in each vertical plane along the length of the wall 10 to be poured, with lengths of 3.0m and 3.5m respectively. Each vertical plane corresponds one-to-one with the vertical plane where each upright 31 is located and is arranged repeatedly along the length direction. The lower end of each diagonal support 60 is fully welded to the pre-embedded anchor 50. It extends diagonally upward from the lower end and is connected to the corresponding upright 31 via fasteners at no less than three connection positions. Two fasteners are provided at each of the three connection positions at the bottom. The waterproof layer 100 extends from the bottom surface of the base plate 70 and upward along the side of the wall 10 to be poured toward the existing foundation pit sidewall 110 to the bottom surface of the concrete slab 80, and then extends horizontally along the bottom surface to cover the top surface of the slope protection pile.
[0083] After the supporting frame 30 is erected and the inclined support 60 is installed, the adjustable top support 33 is rotated one by one to change its extension length, thereby adjusting the distance between the horizontal rib 32 and the upright 31 along the thickness direction, correcting the verticality of the template panel 20 and eliminating assembly gaps. Then, the extended section 42 is fastened to the uppermost horizontal rib 32 with a nut. Only then can the concrete of the wall 10 to be poured be poured into the cavity between the template panel 20 and the existing pit sidewall 110. Each of the walls 10 to be poured around the pit is equipped with the above-mentioned reinforcement system; among them, two walls 10 to be poured are arranged opposite each other in the same direction and are poured synchronously and symmetrically in layers, controlling the difference in concrete liquid level between the two walls 10 at each pouring stage to be no more than 500mm. This pouring method helps to reduce the uneven effect of pouring on both sides on the above-mentioned disc-lock scaffolding; the uppermost horizontal rib 32 is above the top of the upright 31 and is supported on the scaffolding without the adjustable top support 33 and connecting rod 34. The top of the horizontal rib 32, together with the top of the template panel 20, is constrained to the concrete slab 80 by the extension section 42.
[0084] The following describes the pouring construction method corresponding to the above-mentioned single-sided formwork reinforcement system for walls.
[0085] See Figure 6 Corresponding to the aforementioned single-sided formwork reinforcement system for walls, this embodiment of the invention also provides a method for single-sided formwork casting of walls. The method targets a wall 10 to be cast, the lower end of which is located on a base slab 70, and the upper end which is connected to a concrete slab 80. The retaining structure constituting the existing foundation pit sidewall 110 has been completed, and the waterproof layer 100 and its protective layer at the relevant locations are constructed according to design requirements before the corresponding concrete components are poured. The method includes: Step S601: During the pouring of the base plate, the pre-embedded anchors are embedded in the base plate and extend from the top surface of the base plate, and the pre-embedded anchors maintain a non-penetrating distance from the waterproof layer covering the base plate.
[0086] Before pouring the base slab 70, pre-embedded anchors 50 are installed and fixed according to the predetermined arrangement of the supporting frame 30, with their upper ends extending beyond the designed top surface of the base slab 70 for subsequent connection with the inclined support 60. The embedment depth and exposed length of the pre-embedded anchors 50 are determined according to the design, and a gap is maintained between their embedded ends and the waterproof layer 100 on the bottom surface of the base slab 70. After the base slab 70 is poured, the position and exposed length of the pre-embedded anchors 50 are checked.
[0087] Step S602: During the pouring of the concrete slab, a construction joint is reserved at the junction of the concrete slab and the wall to be poured, and a pre-embedded connector is embedded in the concrete slab. The pre-embedded connector includes an anchoring section and an extension section connected together, so that the anchoring section is anchored in the concrete slab and the extension section extends out from the construction joint.
[0088] Before pouring the concrete slab 80, the location of the construction joint 90 is determined at its junction with the wall 10 to be poured, and a pre-embedded connector 40 is installed to fix the anchoring section 41 in the reinforcement of the concrete slab 80, with the protruding section 42 extending out from the predetermined interface of the construction joint 90. After the concrete slab 80 is poured and formed, the protruding section 42 remains outside this interface. The specific structure of the anchoring section 41 is the same as described in the aforementioned reinforcement system; before pouring the wall 10, the interface of the construction joint 90 is roughened and cleaned.
[0089] Step S603: Install a template panel on the construction side of the wall to be poured, so that the extended section passes through the template panel, and erect a support frame on the side of the template panel away from the wall to be poured, so that the template panel abuts against the support frame.
[0090] After the reinforcement of the poured wall 10 is tied, the formwork panel 20 is positioned on the construction side, so that the protruding section 42 extends through the corresponding through hole to the back side of the formwork panel 20. The position of the through hole can be determined according to the actual position of the protruding section 42.
[0091] After the template panel 20 is in place and temporarily supported, a support frame 30 is erected on its back side so that the support frame 30 and the template panel 20 form a force transmission contact that is against each other, and the extended section 42 is in a position that can be fastened to the upper part of the support frame 30.
[0092] Step S604: Fix an inclined support member between the support frame and the pre-embedded anchor, so that the inclined support member extends obliquely upward from the pre-embedded anchor toward the wall to be poured to the support frame.
[0093] The inclined support 60 is positioned and fixedly connected to the pre-embedded anchor 50 and the support frame 30 respectively. In the implementation method using steel pipe diagonal bracing and pre-embedded steel bar ends, the lower end of the inclined support 60 is welded and fixed to the pre-embedded anchor 50, and fasteners are installed at the corresponding connection positions between it and the upright 31.
[0094] Step S605: Securely connect the protruding section that extends out of the template panel to the upper part of the support frame.
[0095] After the supporting frame 30 is erected and the inclined support 60 is installed, the position and verticality of the template panel 20 are corrected, and then each protruding section 42 is fastened to the upper part of the supporting frame 30. In the implementation with an adjustable top support 33, the position of the template panel 20 can be corrected and assembly gaps eliminated by adjusting the adjustable top support 33 before fastening; the protruding section 42 is clamped and fixed to the uppermost horizontal rib 32, for example, by nuts and washers. After fastening, the verticality of the template panel 20, the firmness of the connection between the inclined support 60 and the supporting frame 30, and the reliability of the fastening connection of the protruding section 42 are checked. Concrete pouring can only proceed after the checks are passed.
[0096] Step S606: After the extended section is fastened to the upper part of the support frame, the concrete of the wall to be poured is poured into the cavity between the template panel and the existing foundation pit sidewall.
[0097] Concrete is poured and vibrated in layers from the top of the formwork panel 20 into the cavity between the formwork panel 20 and the existing foundation pit sidewall 110 until the poured surface reaches the top elevation of the concrete slab 80 and connects with the interface of the construction joint 90. The lateral pressure of the concrete acting on the formwork panel 20 is transmitted through the support frame 30 and borne by the upper constraint provided by the pre-embedded connector 40 and the support provided by the inclined support 60.
[0098] Through the above steps, an upper constraint provided by the concrete slab 80 and a support provided by the pre-embedded anchors 50 in the inclined support member 60 and the base plate 70 are established before the concrete of the wall 10 to be poured, so as to limit the outward movement of the formwork panel 20 under the pressure of the pouring side. Neither type of pre-embedded part penetrates the waterproof layer 100, so the formwork and reinforcement work does not require drilling holes or setting through members in the waterproof layer 100.
[0099] In the implementation method where two walls 10 to be poured are arranged opposite each other and the supporting frames 30 on both sides are connected as a whole by a disc-lock scaffold, the two walls 10 to be poured are poured with concrete in layers simultaneously and symmetrically, and the difference in concrete liquid level between the two walls 10 at each pouring stage is controlled to be no more than 500mm, so as to reduce the uneven effect caused by pouring on both sides.
[0100] After the concrete is poured, it should be cured according to the design and corresponding construction requirements. Once the concrete reaches the strength required for demolding, the formwork and support system should be removed.
[0101] The above description is merely a specific embodiment of the present invention, but the scope of protection of the present invention is not limited thereto. Any person skilled in the art can easily conceive of various equivalent modifications or substitutions within the technical scope disclosed in the present invention, and these modifications or substitutions should all be covered within the scope of protection of the present invention. Therefore, the scope of protection of the present invention should be determined by the scope of the claims.
Claims
1. A single-sided formwork reinforcement system for walls, used for single-sided formwork support of walls to be poured, characterized in that, This includes template panels, support frames, embedded connectors, embedded anchors, and inclined support components; The lower end of the wall to be poured is located on the already poured base plate, and the upper end is connected to the already poured concrete slab. A construction joint is provided at the joint between the concrete slab and the wall to be poured. The template panel is set against the construction side of the wall to be poured, and the supporting frame is located on the side of the template panel away from the wall to be poured and abuts against the template panel; The pre-embedded connector includes an anchoring section embedded in the concrete slab and an extension section extending out from the construction joint. The extension section passes through the template panel and is fastened to the upper part of the support frame. The pre-embedded anchor is embedded in the base plate and extends from the top surface of the base plate. The lower end of the inclined support is connected to the pre-embedded anchor and the upper end is connected to the support frame. The inclined support extends upward from the pre-embedded anchor toward the wall to be poured to the support frame.
2. The wall unilateral formwork reinforcement system according to claim 1, characterized in that, It also includes a waterproof layer that covers the bottom surface of the base plate and extends upward along the side of the wall to be poured away from the template panel to the concrete slab. Neither the embedded connector nor the embedded anchor penetrates the waterproof layer.
3. The wall unilateral formwork reinforcement system according to claim 1, characterized in that, The supporting frame includes uprights extending along the height direction of the wall to be poured, and horizontal ribs arranged on the side of the uprights facing the wall to be poured; the uprights include a plurality of them spaced apart along the length direction of the wall to be poured, and the horizontal ribs include a plurality of them spaced apart along the height direction of the wall to be poured, each of the horizontal ribs extending along the length direction of the wall to be poured, and at least a portion of the horizontal ribs being connected to the corresponding uprights; the template panel is abutted against and fixed to the side of each of the horizontal ribs facing the wall to be poured.
4. The wall single-sided formwork reinforcement system according to claim 3, characterized in that, The horizontal rib is composed of two horizontal steel pipes arranged side by side in a vertical direction; the extended section passes through the template panel and is fastened to the uppermost horizontal rib.
5. The wall unilateral formwork reinforcement system according to claim 3, characterized in that, The inclined support extends obliquely upward from its lower end and is connected to the corresponding upright at no less than three connection points via fasteners.
6. The wall unilateral formwork reinforcement system according to claim 5, characterized in that, Two fasteners are provided at each of the three connection positions located below.
7. The wall unilateral formwork reinforcement system according to claim 3, characterized in that, The pre-embedded anchors are a plurality of those arranged at intervals along the length of the wall to be poured, and the spacing between two adjacent pre-embedded anchors is the same as the spacing between two adjacent uprights along the length of the wall to be poured.
8. The wall unilateral formwork reinforcement system according to claim 3, characterized in that, The supporting frame also includes a connecting rod and an adjustable top support. The connecting rod is fixedly connected to the upright. The adjustable top support includes a bracket and an adjusting screw. The bracket supports the horizontal rib. One end of the adjusting screw is connected to the bracket, and the other end is inserted into the end of the connecting rod facing the template panel. The length of the adjusting screw extending from the connecting rod is adjustable.
9. A method for single-sided formwork casting construction of a wall, characterized in that, The lower end of the wall to be poured is located on the base slab, and the upper end is connected to the concrete slab; the method includes: During the pouring of the base slab, pre-embedded anchors are embedded in the base slab and extend from the top surface of the base slab, with the pre-embedded anchors maintaining a non-penetrating distance from the waterproof layer covering the base slab. During the pouring of the concrete slab, a construction joint is reserved at the junction of the concrete slab and the wall to be poured, and a pre-embedded connector is embedded in the concrete slab. The pre-embedded connector includes an anchoring section and an extension section connected together, so that the anchoring section is anchored in the concrete slab and the extension section extends out from the construction joint. Install a template panel on the construction side of the wall to be poured, so that the protruding section passes through the template panel, and erect a support frame on the side of the template panel away from the wall to be poured, so that the template panel abuts against the support frame; An inclined support is fixedly installed between the support frame and the pre-embedded anchor, so that the inclined support extends obliquely upward from the pre-embedded anchor toward the wall to be poured to the support frame. The protruding section extending from the template panel is fastened to the upper part of the support frame; and After the extended section is fastened to the upper part of the support frame, the concrete of the wall to be poured is poured into the cavity between the template panel and the existing foundation pit sidewall.
10. The method for single-sided formwork casting construction of a wall according to claim 9, characterized in that, When pouring concrete for the wall to be poured, concrete is poured simultaneously and symmetrically in layers at two oppositely arranged walls to be poured, and the difference in concrete liquid level between the two walls at each pouring stage is no more than 500mm.